Riyadh rides power projects surge

7 September 2023

This package on Saudi Arabia's power sector also includes: 

> Israeli talks decisive for Saudi nuclear programme
> Jinko outprices other bidders for Tubarjal solar contract
> Synergy wins 7.2GW Saudi advisory role
> Team submits lowest Hinakiyah solar bid
> Saudi offtaker holds Taiba and Qassim bidder meetings
> Saudi Arabia confirms Shuaibah financial close


 

Recent months have been busier than usual for the Saudi power generation sector. Riyadh’s plan to build its first large-scale nuclear power plant has gathered momentum, with the tendering process under way for the project’s main contract.

In May, the Public Investment Fund (PIF) awarded three solar photovoltaic (PV) power plant contracts with a total combined capacity of 4,550MW.

In August, utility developer Acwa Power reached financial close for the Shuaibah 1 and Shuaibah 2 solar PV independent power producer (IPP) projects, which have a total combined capacity of over 2,600MW.

French energy heavyweight TotalEnergies has also reached financial close for the 120MW Wadi al-Dawasir solar scheme, tendered under round three of the kingdom’s National Renewable Energy Programme (NREP).

During the past few months, the state-backed power offtaker, Saudi Power Procurement Company (SPPC), has received proposals and shortlisted two bidders each for the two solar PV contracts under NREP’s round four.

Riyadh has also accelerated the procurement of gas-fired capacity over the past year.

SPPC is simultaneously evaluating bids for four combined-cycle gas turbine (CCGT) plants, the Taiba 1 and 2 and Al-Qassim 1 and 2 IPPs, which have a total combined capacity of 7,200MW.

In addition to the potential award of these four contracts over the next few months, the state offtaker is expected to tender two more gas-fired projects – the PP15 IPP in Riyadh and another power generation plant in Al-Khafji – next year. Each will have a design capacity of 3,600MW.

Overall, close to $30bn-worth of power generation projects are in execution or about to start construction in Saudi Arabia, according to the latest data from MEED Projects. 

At least $44bn are in the pre-execution phase, excluding the kingdom’s $35bn nuclear power plant programme.

Liquid fuel displacement

Given the kingdom’s ambitious plan to boost its renewable energy installed capacity to 58,700MW by 2030, up from about 1,100MW today, the pace of renewable energy contract awards is no surprise.

CCGT projects support the kingdom’s plan to cut down on burning liquid fuels. The Energy Ministry’s liquid fuel displacement programme, launched as part of Saudi Vision 2030, aims to displace 1 million barrels a day of liquid fuels across the utilities, industry and agriculture sectors by 2030.

The latest data from the King Abdullah Petroleum Studies & Research Centre (Kapsarc) shows that liquid fuels, comprising crude oil, heavy fuel oil and diesel, accounted for up to 43 per cent of Saudi Arabia’s fuel mix for power generation and water desalination processes as of 2018.

This translates to about 1,670 trillion BTUs, roughly equivalent to 760,000 barrels a day, of liquid fuels.

Meanwhile, natural gas consumption across the kingdom’s power generation and water desalination sectors is estimated at 2,226 trillion BTUs, or 6 billion cubic feet a day.

Kapsarc research fellow Rami Shabaneh noted in a 2020 report: “Overall fuel consumption saw a significant decline of almost 8 per cent year-on-year in 2018. This was due to increased energy-efficiency regulations and energy price reforms.”

This trend – along with other energy-efficiency measures in the power generation, water desalination, and transmission and distribution network – suggests there has been a decrease in fuel consumption in the intervening years too.

However, much still needs to be done to reach the kingdom’s 2030 liquid fuel displacement target, as well as its energy diversification objectives.

While the massive expansion of gas-fired capacity seems inconsistent with cutting emissions, the significant number of fleets that still burn liquid fuel appears to justify the dual approach to expanding both renewable and gas-fired capacity to meet rising demand and security of supply.

“Plants running on highly efficient CCTG technologies is the way to go,” says an expert who works for an international utility developer.

This approach also dovetails with the kingdom’s goal for 50 per cent natural gas and 50 per cent clean or renewable energy in its energy mix by 2030.

Saudi’s ambition to achieve carbon neutrality by 2060 – 10 years later than typical targets – could also be advantageous in terms of procuring more efficient CCGT plants in the interim.

With the kingdom’s power-purchase agreements (PPAs) generally lasting 25 years, gas-fired IPPs procured this year and next will reach commercial operations by 2027 or 2028. This takes the validity of upcoming PPAs into the early 2050s, still well within the country’s energy transition period.

Different tunes

As things stand, not everyone is convinced of the need for the scale of the new natural gas fleet planned in the kingdom.

“I think they should focus more on renewables,” says a Dubai-based industry expert, who notes the large gap between Saudi Arabia’s current renewable energy installed capacity and 2030 target.

Given that renewable energy accounts for, roughly, just 1 per cent of known power generation installed capacity, 70-fold growth is needed to hit the end-of-the-decade target.

Some international utility developers, with internal carbon-neutrality deadlines of 2050 or before, may not be able to participate in the ongoing CCGT tenders, unless they integrate decarbonisation measures. This could affect the competitiveness of bid prices.

However, Paddy Padmanathan, former CEO of Saudi utility Acwa Power, says the kingdom has room for both technologies.

“I see no reason why a fast or even faster pace of renewable energy procurement cannot run in parallel with CCGT procurement,” he tells MEED.

“[The] Saudi procurement process, PPA risk allocation and certainty of projects moving forward to the timetable set out in the requests for proposals are well recognised and appreciated,” the executive, who is a member of Acwa Power’s board following his retirement as CEO earlier this year, explains.

Padmanathan says there is no shortage of equity and debt funding for these projects. He also cites the kingdom’s “very high” credit rating.

These factors, along with abating supply chain challenges for solar PV modules and the keenness of CCGT original equipment manufacturers for new contracts, mean the kingdom will continue to be an exciting market for power projects well into the next decade, Padmanathan asserts.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11115963/main.gif
Jennifer Aguinaldo
Related Articles
  • Adnoc Onshore selects contractors for well tie-ins project

    27 October 2026

     

    Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.

    Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields. 

    The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.

    Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.

    Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.

    The project budget is estimated at $1.2bn.

    Bidders for the contract are understood to have included:

    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Jereh (China)
    • Kalpataru Projects International (India)
    • Matrix Construction (UAE)
    • Robt Stone Middle East (UAE)
    • Target Engineering Construction Company (UAE)

    The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg
    Indrajit Sen
  • Ashghal tenders Al-Udeid air base access road works

    27 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.

    The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road. 

    The tender was issued on 22 October, with a submission deadline of 22 November.

    The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.

    Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.

    The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.

    The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.

    The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.

    Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.

    The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.

    Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.

    Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.

    For joint-venture bids, the lead partner must hold the required classification grade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg
    Yasir Iqbal
  • Saudi Arabia gauges interest for Al-Ula wastewater expansion

    27 October 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) is conducting market sounding for the first phase of the Mughayra wastewater treatment plant (WWTP) expansion before formally starting its tendering process, according to industry sources.

    The project is valued at SR400m ($107m) and is intended to increase the Mughayra plant’s wastewater treatment capacity to 62,000 cubic metres a day.

    RCU is gauging interest from potential contractors and has not yet issued a prequalification questionnaire, a source said.

    The scheme forms part of Saudi Arabia’s broader investment drive to develop its cultural and tourism offering across Al-Ula.

    The commission launched its Journey Through Time Masterplan in April 2021, with implementation scheduled in three phases through 2035. The masterplan covers infrastructure development, water management and irrigation, alongside the regeneration of a 9-kilometre cultural oasis.

    French engineering firm Artelia previously noted in its 2025 annual corporate report that it is involved in the design phase of the Mughayra WWTP.

    RCU is also developing strategic potable-water storage infrastructure in Al-Ula, including a design-and-build project covering a 50,000-cubic-metre reservoir at Hub 06 and a 15,000-cubic-metre reservoir at Hub 08.

    Local contractor Bin Omairah previously confirmed that it is serving as the engineering, procurement and construction contractor for the storage facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950333/main.jpg
    Mark Dowdall
  • Qatari firm wins $147m Syria road deal

    27 October 2026

    Qatari contractor Al-Mohannadi for Roads, Trading & Contracting has signed a $147m contract with Syria’s General Directorate of Roads to rehabilitate and expand a 215-kilometre (km) highway corridor connecting to the Iraqi border.

    The project covers the rehabilitation and dualisation of a 170km section linking the Al-Busairi junction to the Al-Tanf border crossing, alongside the construction of a 45km link between the Al-Sabaa Biyar junction and Al-Busairi. Work is scheduled for completion within 900 days.

    The agreement was signed in Damascus by Moaz Najjar, director-general of the General Directorate of Roads, and Abdullah Adnan Al-Zattam, chief executive of Al-Mohannadi, in the presence of Syrian Transport Minister Yarob Badr and Finance Minister Mohammad Yusr Barnieh.

    The upgrade is intended to restore and expand one of Syria’s primary overland arteries to Iraq, which has suffered significant deterioration and capacity bottlenecks following years of conflict. The Al-Tanf corridor represents the most direct overland link between Damascus, central Syrian industrial centres and Baghdad.

    The project is designed to accommodate heavier commercial freight vehicles and reduce transit times between the two countries.

    The investment also forms part of broader efforts to re-establish Syria’s role as a regional transit corridor connecting Mediterranean ports with landlocked trade routes into Iraq and the wider region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950332/main.gif
    Yasir Iqbal
  • Adnoc showcases $16.3bn local manufacturing potential

    27 October 2026

    Abu Dhabi National Oil Company (Adnoc Group) has identified more than AED60bn ($16.3bn) in local manufacturing opportunities through 2030.

    The Abu Dhabi energy company also announced changes to its procurement, supplier registration and In-Country Value (ICV) localisation frameworks.

    The measures were announced at the second Make it with Adnoc Forum, held in Abu Dhabi on October 25. They are intended to give manufacturers, suppliers and investors greater visibility of future demand and a faster, clearer route to compete for Adnoc contracts, the company said.

    The more than 200 manufacturing opportunities cover products required for Adnoc’s projects and operations, including:

    • Rotating equipment and power
    • Electrical, control and automation systems
    • Drilling and completion equipment
    • Chemicals and catalysts
    • Piping, fabrication and heavy equipment
    • Spare parts and advanced manufacturing

    Many of the identified products are currently imported, Adnoc said. “Manufacturing them in the UAE shortens lead times, reduces exposure to global supply disruptions and strengthens the resilience of Adnoc’s operations,” it said in its statement.

    Adnoc, the UAE Ministry of Industry & Advanced Technology and the Abu Dhabi Investment Office (Adio) will work together to connect manufacturers with these opportunities. The collaboration will combine visibility of Adnoc’s demand, access to the national industrial database and financing through the National Industrial Resilience Fund, the company said.

    Adnoc also signed two memorandums of understanding on the sidelines of the forum with Adio and Kezad Group.

    ICV scheme expansion

    Adnoc announced the expansion of its Local+ programme, part of its ICV framework, to more than 100 UAE manufacturers, compared with 70 at its launch in May. The programme gives UAE-made products priority in Adnoc projects by requiring engineering, procurement and construction (EPC) contractors bidding for new tenders to source relevant products from manufacturers approved under the programme.

    Separately, Adnoc announced a redesign of its supplier registration and prequalification process. The company is targeting a reduction of up to 80% in the time required for suppliers to complete the process and become eligible to compete for Adnoc opportunities.

    The new model halves the number of required documents and removes prequalification requirements for 60% of service categories.

    A single window brings together registration, qualification and compliance, with requirements tailored to the nature of the work and its level of risk. Artificial intelligence will support document verification and the reuse of existing data, reducing repetitive submissions and administrative processing.

    ALSO READ:
    Adnoc steps up crude oil capacity expansion
    Adnoc funnels billions into boosting gas processing

    “Adnoc’s enhanced ICV model will more closely connect procurement decisions with commercial value and suppliers’ contribution to the UAE economy. Under the new model, commercial and ICV offers will be integrated into a single evaluation model,” the company said.

    “The previous bid-matching approach will be retired, encouraging suppliers to submit their most competitive commercial and ICV offers from the outset. Requirements will be proportionate to contract size and scope.

    “The model also enhances the administration of ICV-related retention payments. Where retention applies, automated calculation and release processes through the Adnoc Supplier Hub will improve transparency, reduce manual follow-up and support suppliers’ cash flow as obligations are met.”

    Alongside the ICV and registration enhancements, Adnoc outlined a new commercial approach built around four strategic shifts: agile, competitive, strategic and forward-looking.

    “The approach will advance simpler procurement and faster decision-making, contracting models aligned with project and market dynamics, targeted commercial negotiations and earlier visibility of Adnoc’s future demand.”

    Since its launch in 2018, Adnoc’s ICV programme has directed more than AED307bn ($83.6bn) into the UAE economy, the company said. By the end of 2025, it had also supported the localisation of more than 130 products, the development of 95 UAE factories, and employment opportunities for more than 27,500 Emiratis at participating private sector companies.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20948385/main5518.jpg
    Indrajit Sen