Riyadh rides power projects surge
7 September 2023
This package on Saudi Arabia's power sector also includes:
> Israeli talks decisive for Saudi nuclear programme
> Jinko outprices other bidders for Tubarjal solar contract
> Synergy wins 7.2GW Saudi advisory role
> Team submits lowest Hinakiyah solar bid
> Saudi offtaker holds Taiba and Qassim bidder meetings
> Saudi Arabia confirms Shuaibah financial close

Recent months have been busier than usual for the Saudi power generation sector. Riyadh’s plan to build its first large-scale nuclear power plant has gathered momentum, with the tendering process under way for the project’s main contract.
In May, the Public Investment Fund (PIF) awarded three solar photovoltaic (PV) power plant contracts with a total combined capacity of 4,550MW.
In August, utility developer Acwa Power reached financial close for the Shuaibah 1 and Shuaibah 2 solar PV independent power producer (IPP) projects, which have a total combined capacity of over 2,600MW.
French energy heavyweight TotalEnergies has also reached financial close for the 120MW Wadi al-Dawasir solar scheme, tendered under round three of the kingdom’s National Renewable Energy Programme (NREP).
During the past few months, the state-backed power offtaker, Saudi Power Procurement Company (SPPC), has received proposals and shortlisted two bidders each for the two solar PV contracts under NREP’s round four.
Riyadh has also accelerated the procurement of gas-fired capacity over the past year.
SPPC is simultaneously evaluating bids for four combined-cycle gas turbine (CCGT) plants, the Taiba 1 and 2 and Al-Qassim 1 and 2 IPPs, which have a total combined capacity of 7,200MW.
In addition to the potential award of these four contracts over the next few months, the state offtaker is expected to tender two more gas-fired projects – the PP15 IPP in Riyadh and another power generation plant in Al-Khafji – next year. Each will have a design capacity of 3,600MW.
Overall, close to $30bn-worth of power generation projects are in execution or about to start construction in Saudi Arabia, according to the latest data from MEED Projects.
At least $44bn are in the pre-execution phase, excluding the kingdom’s $35bn nuclear power plant programme.
Liquid fuel displacement
Given the kingdom’s ambitious plan to boost its renewable energy installed capacity to 58,700MW by 2030, up from about 1,100MW today, the pace of renewable energy contract awards is no surprise.
CCGT projects support the kingdom’s plan to cut down on burning liquid fuels. The Energy Ministry’s liquid fuel displacement programme, launched as part of Saudi Vision 2030, aims to displace 1 million barrels a day of liquid fuels across the utilities, industry and agriculture sectors by 2030.
The latest data from the King Abdullah Petroleum Studies & Research Centre (Kapsarc) shows that liquid fuels, comprising crude oil, heavy fuel oil and diesel, accounted for up to 43 per cent of Saudi Arabia’s fuel mix for power generation and water desalination processes as of 2018.
This translates to about 1,670 trillion BTUs, roughly equivalent to 760,000 barrels a day, of liquid fuels.
Meanwhile, natural gas consumption across the kingdom’s power generation and water desalination sectors is estimated at 2,226 trillion BTUs, or 6 billion cubic feet a day.
Kapsarc research fellow Rami Shabaneh noted in a 2020 report: “Overall fuel consumption saw a significant decline of almost 8 per cent year-on-year in 2018. This was due to increased energy-efficiency regulations and energy price reforms.”
This trend – along with other energy-efficiency measures in the power generation, water desalination, and transmission and distribution network – suggests there has been a decrease in fuel consumption in the intervening years too.
However, much still needs to be done to reach the kingdom’s 2030 liquid fuel displacement target, as well as its energy diversification objectives.
While the massive expansion of gas-fired capacity seems inconsistent with cutting emissions, the significant number of fleets that still burn liquid fuel appears to justify the dual approach to expanding both renewable and gas-fired capacity to meet rising demand and security of supply.
“Plants running on highly efficient CCTG technologies is the way to go,” says an expert who works for an international utility developer.
This approach also dovetails with the kingdom’s goal for 50 per cent natural gas and 50 per cent clean or renewable energy in its energy mix by 2030.
Saudi’s ambition to achieve carbon neutrality by 2060 – 10 years later than typical targets – could also be advantageous in terms of procuring more efficient CCGT plants in the interim.
With the kingdom’s power-purchase agreements (PPAs) generally lasting 25 years, gas-fired IPPs procured this year and next will reach commercial operations by 2027 or 2028. This takes the validity of upcoming PPAs into the early 2050s, still well within the country’s energy transition period.
Different tunes
As things stand, not everyone is convinced of the need for the scale of the new natural gas fleet planned in the kingdom.
“I think they should focus more on renewables,” says a Dubai-based industry expert, who notes the large gap between Saudi Arabia’s current renewable energy installed capacity and 2030 target.
Given that renewable energy accounts for, roughly, just 1 per cent of known power generation installed capacity, 70-fold growth is needed to hit the end-of-the-decade target.
Some international utility developers, with internal carbon-neutrality deadlines of 2050 or before, may not be able to participate in the ongoing CCGT tenders, unless they integrate decarbonisation measures. This could affect the competitiveness of bid prices.
However, Paddy Padmanathan, former CEO of Saudi utility Acwa Power, says the kingdom has room for both technologies.
“I see no reason why a fast or even faster pace of renewable energy procurement cannot run in parallel with CCGT procurement,” he tells MEED.
“[The] Saudi procurement process, PPA risk allocation and certainty of projects moving forward to the timetable set out in the requests for proposals are well recognised and appreciated,” the executive, who is a member of Acwa Power’s board following his retirement as CEO earlier this year, explains.
Padmanathan says there is no shortage of equity and debt funding for these projects. He also cites the kingdom’s “very high” credit rating.
These factors, along with abating supply chain challenges for solar PV modules and the keenness of CCGT original equipment manufacturers for new contracts, mean the kingdom will continue to be an exciting market for power projects well into the next decade, Padmanathan asserts.
Exclusive from Meed
-
EtihadWE tenders $150m Ajman substation project21 July 2026
-
-
-
-
Dubai Municipality awards Tasreef drainage contract21 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
EtihadWE tenders $150m Ajman substation project21 July 2026
The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.
Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.
The bid submission deadline is 10 August.
According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.
The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.
Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.
This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.
EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.
In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg -
Seven seeks contractors for Dammam water park and hotel21 July 2026

Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.
The waterfront development sits on a 324,300-square-metre (sq m) plot.
A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.
Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.
The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.
The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.
Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.
Detailed design and issued-for-construction packages are complete.
Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.
The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.
The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.
Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.
Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.
The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.
The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg -
Al-Ula appoints equestrian village early works contractor21 July 2026

Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.
The contract was awarded to Al-Khobar-based Al-Shalawi International Company.
Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.
Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.
RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.
The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.
These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg -
Contractors await decision on Riyadh airport sewage plant21 July 2026

Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.
It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.
The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.
The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).
The bidders (all local) are:
- Al-Rawaf Trading & Contracting
- Almajal Alarabi
- Nesma Water & Energy
- Safari Company
- Saudi Services for Electro-Mechanic Works
- Washnah Contracting
- Water & Environment Technologies (Wetico)
The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.
US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.
The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.
Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.
The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.
These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg -
Dubai Municipality awards Tasreef drainage contract21 July 2026

Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.
It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.
The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.
The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.
Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.
In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.
The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg