Riyadh rides power projects surge

7 September 2023

This package on Saudi Arabia's power sector also includes: 

> Israeli talks decisive for Saudi nuclear programme
> Jinko outprices other bidders for Tubarjal solar contract
> Synergy wins 7.2GW Saudi advisory role
> Team submits lowest Hinakiyah solar bid
> Saudi offtaker holds Taiba and Qassim bidder meetings
> Saudi Arabia confirms Shuaibah financial close


 

Recent months have been busier than usual for the Saudi power generation sector. Riyadh’s plan to build its first large-scale nuclear power plant has gathered momentum, with the tendering process under way for the project’s main contract.

In May, the Public Investment Fund (PIF) awarded three solar photovoltaic (PV) power plant contracts with a total combined capacity of 4,550MW.

In August, utility developer Acwa Power reached financial close for the Shuaibah 1 and Shuaibah 2 solar PV independent power producer (IPP) projects, which have a total combined capacity of over 2,600MW.

French energy heavyweight TotalEnergies has also reached financial close for the 120MW Wadi al-Dawasir solar scheme, tendered under round three of the kingdom’s National Renewable Energy Programme (NREP).

During the past few months, the state-backed power offtaker, Saudi Power Procurement Company (SPPC), has received proposals and shortlisted two bidders each for the two solar PV contracts under NREP’s round four.

Riyadh has also accelerated the procurement of gas-fired capacity over the past year.

SPPC is simultaneously evaluating bids for four combined-cycle gas turbine (CCGT) plants, the Taiba 1 and 2 and Al-Qassim 1 and 2 IPPs, which have a total combined capacity of 7,200MW.

In addition to the potential award of these four contracts over the next few months, the state offtaker is expected to tender two more gas-fired projects – the PP15 IPP in Riyadh and another power generation plant in Al-Khafji – next year. Each will have a design capacity of 3,600MW.

Overall, close to $30bn-worth of power generation projects are in execution or about to start construction in Saudi Arabia, according to the latest data from MEED Projects. 

At least $44bn are in the pre-execution phase, excluding the kingdom’s $35bn nuclear power plant programme.

Liquid fuel displacement

Given the kingdom’s ambitious plan to boost its renewable energy installed capacity to 58,700MW by 2030, up from about 1,100MW today, the pace of renewable energy contract awards is no surprise.

CCGT projects support the kingdom’s plan to cut down on burning liquid fuels. The Energy Ministry’s liquid fuel displacement programme, launched as part of Saudi Vision 2030, aims to displace 1 million barrels a day of liquid fuels across the utilities, industry and agriculture sectors by 2030.

The latest data from the King Abdullah Petroleum Studies & Research Centre (Kapsarc) shows that liquid fuels, comprising crude oil, heavy fuel oil and diesel, accounted for up to 43 per cent of Saudi Arabia’s fuel mix for power generation and water desalination processes as of 2018.

This translates to about 1,670 trillion BTUs, roughly equivalent to 760,000 barrels a day, of liquid fuels.

Meanwhile, natural gas consumption across the kingdom’s power generation and water desalination sectors is estimated at 2,226 trillion BTUs, or 6 billion cubic feet a day.

Kapsarc research fellow Rami Shabaneh noted in a 2020 report: “Overall fuel consumption saw a significant decline of almost 8 per cent year-on-year in 2018. This was due to increased energy-efficiency regulations and energy price reforms.”

This trend – along with other energy-efficiency measures in the power generation, water desalination, and transmission and distribution network – suggests there has been a decrease in fuel consumption in the intervening years too.

However, much still needs to be done to reach the kingdom’s 2030 liquid fuel displacement target, as well as its energy diversification objectives.

While the massive expansion of gas-fired capacity seems inconsistent with cutting emissions, the significant number of fleets that still burn liquid fuel appears to justify the dual approach to expanding both renewable and gas-fired capacity to meet rising demand and security of supply.

“Plants running on highly efficient CCTG technologies is the way to go,” says an expert who works for an international utility developer.

This approach also dovetails with the kingdom’s goal for 50 per cent natural gas and 50 per cent clean or renewable energy in its energy mix by 2030.

Saudi’s ambition to achieve carbon neutrality by 2060 – 10 years later than typical targets – could also be advantageous in terms of procuring more efficient CCGT plants in the interim.

With the kingdom’s power-purchase agreements (PPAs) generally lasting 25 years, gas-fired IPPs procured this year and next will reach commercial operations by 2027 or 2028. This takes the validity of upcoming PPAs into the early 2050s, still well within the country’s energy transition period.

Different tunes

As things stand, not everyone is convinced of the need for the scale of the new natural gas fleet planned in the kingdom.

“I think they should focus more on renewables,” says a Dubai-based industry expert, who notes the large gap between Saudi Arabia’s current renewable energy installed capacity and 2030 target.

Given that renewable energy accounts for, roughly, just 1 per cent of known power generation installed capacity, 70-fold growth is needed to hit the end-of-the-decade target.

Some international utility developers, with internal carbon-neutrality deadlines of 2050 or before, may not be able to participate in the ongoing CCGT tenders, unless they integrate decarbonisation measures. This could affect the competitiveness of bid prices.

However, Paddy Padmanathan, former CEO of Saudi utility Acwa Power, says the kingdom has room for both technologies.

“I see no reason why a fast or even faster pace of renewable energy procurement cannot run in parallel with CCGT procurement,” he tells MEED.

“[The] Saudi procurement process, PPA risk allocation and certainty of projects moving forward to the timetable set out in the requests for proposals are well recognised and appreciated,” the executive, who is a member of Acwa Power’s board following his retirement as CEO earlier this year, explains.

Padmanathan says there is no shortage of equity and debt funding for these projects. He also cites the kingdom’s “very high” credit rating.

These factors, along with abating supply chain challenges for solar PV modules and the keenness of CCGT original equipment manufacturers for new contracts, mean the kingdom will continue to be an exciting market for power projects well into the next decade, Padmanathan asserts.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11115963/main.gif
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia raises electricity tariffs

    26 October 2026

    Saudi Energy, formerly Saudi Electricity Company, has announced revised electricity tariffs, which will take effect on 1 January 2027. 

    The revised tariff schedule, published on the company’s official website, covers residential, commercial, industrial, agricultural, charitable and government customers.

    The largest percentage increase in consumption rates is 16.7%, for residential customers using up to 6,000 kilowatt-hours (kWh) a month. Residential customers will pay 21 halalas/kWh for monthly consumption of up to 6,000kWh, up from 18 halalas. For consumption above 6,000kWh, the rate will rise from 30 to 33 halalas/kWh, a 10% increase.

    The industrial tariff will increase by 15%, from 20 to 23 halalas/kWh. Commercial customers, private healthcare facilities and private educational facilities will pay 25 halalas/kWh, up from 22 halalas, for consumption up to 6,000kWh a month, and 35 halalas/kWh above that level, up from 32 halalas.

    Tariffs for charities and government customers will also increase. In addition to consumption-based charges, customers will pay a fixed monthly fee based on the capacity of their electricity meter. This replaces the previous separate charge for meter reading, maintenance and billing, with VAT applied to the revised tariffs. 

    Electricity investment

    The new tariffs coincide with changes to water consumption tariffs announced by the National Water Company, also effective from 1 January 2027.

    King Salman Bin Abdulaziz Al-Saud directed support measures following a proposal presented by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.

    This includes raising the minimum wage required for Saudi nationals to count as full employees towards private sector localisation quotas under the Nitaqat programme. 

    The tariff changes come as Saudi Arabia plans substantial investment in its electricity infrastructure. In September 2025, Saudi Energy announced plans to invest SR220bn ($58.7bn) in power infrastructure projects between 2025 and 2030.

    A June 2025 report by Fitch Ratings forecast negative free cash flow of about SR16bn a year over the period and rising leverage, reflecting the financial demands of the programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20924301/main.jpg
    Mark Dowdall
  • Dubai Municipality confirms AED3bn Tasreef drainage awards

    26 October 2026

    Dubai Municipality has confirmed it has awarded four contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.

    The projects will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. The works include constructing and extending main stormwater drainage lines with diameters of up to three metres.

    The four packages are part of Dubai’s AED30bn Tasreef programme, which aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.

    The contracts have been awarded to China State Construction Engineering Corporation (CSCEC) and three local firms: Arifco Group, Nael Construction & Contracting (NCC) and Detech Contracting. Dubai Municipality did not state which projects the awards relate to.

    According to sources, the contract awards include packages TF-15-C1, TF-15-C2 and TF-13-C1.

    The first package, TF-15-C1, involves the construction of 21 kilometres of main and secondary drainage lines along Al-Wasl Road and in surrounding areas. It will cover Za’abeel 2, Al-Wasl, Jumeirah 1 and 2, Al-Bada’a, Al-Satwa and Dubai World Trade Centre. The estimated $100m contract was awarded to Detech in July, as exclusively reported by MEED.

    The second package, TF-15-C2, covers the corridor between Sheikh Zayed Road and Al-Khail Road. It includes about 14km of main drainage lines serving Al-Quoz Industrial Areas 1, 3 and 4, and Al-Barsha 1. In July, MEED reported that CSCEC had won the engineering, procurement and construction contract for this project.

    The third package, TF-13-C1, covers Al-Marmoom, where 23km of drainage infrastructure will be developed. According to a source, Arifco has been awarded this contract.

    The final package covers Jumeirah and Umm Suqeim, where about 42km of main drainage lines will serve Umm Suqeim 1, 2 and 3; Umm Al-Sheif; Jumeirah 3; Al-Safa 1 and 2; and Al-Manara.

    In May, MEED reported that NCC had been awarded a contract to build a sewage and stormwater drainage system, DS-204. However, it is unconfirmed whether this relates to the same project.

    Earlier, in February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.

    These included two contracts awarded to Detech and one to CSCEC for stormwater drainage infrastructure. In addition, two consultancy contracts were awarded for the study and design of drainage systems in selected areas across the emirate.

    Cumulatively valued at AED2.5bn, the new projects will serve 30 vital areas, spanning approximately 430 million square metres and supporting an estimated population of three million residents by 2040.

    Previously, in April 2025, an earlier package of awards was announced under phase one of the Tasreef programme. The overall masterplan aims to expand Dubai’s rainwater drainage capacity by 700% by 2033.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20923924/main4827.jpg
    Mark Dowdall
  • Nakheel awards $259m Dubai Islands buildings contract

    26 October 2026

    Dubai-based master developer Nakheel, part of Dubai Holding Real Estate, has awarded local firm Parkway International Contracting a construction contract valued at about AED950m ($259m) for phases two and four of Bay Grove Residences on Dubai Islands.

    The package covers 617 residential units across eight buildings, ranging from one to four bedrooms, together with basement structures, infrastructure and community amenities including swimming pools, sports courts and fitness centres.

    Phase two comprises 360 homes across four buildings, with main construction scheduled for completion in late 2028.

    Phase four includes 257 homes across four buildings, with completion targeted for the second quarter of 2029.

    The award follows an earlier contract valued at about AED800m ($218m) awarded to local contractor Metac General Contracting Company for phases one and three, covering 537 homes across seven buildings.

    Together, the two contracts total more than AED1.75bn ($476m) and account for all 1,154 planned homes across the 15 buildings of Bay Grove Residences.

    Project activity on Dubai Islands has gathered pace in recent months. Earlier this month, Nakheel awarded local firm Mar Marine & Building Contracting a contract for marine and coastal works on Island B. The scope includes constructing breakwaters, removing existing rock revetments and creating a new 320-metre beach near the Bay Villas development, as well as remedial and refurbishment works along approximately 3 kilometres of the island’s western shoreline.

    In August 2025, Nakheel awarded Fibrex Contracting a AED2.6bn ($708m) construction contract for the Bay Villas residential project. That followed a AED527m ($143m) contract awarded to Al-Nasr Contracting Company in April 2026 for primary infrastructure and utilities on Island B.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20923389/main.jpg
    Yasir Iqbal
  • Morocco plans second high-speed rail phase to Agadir

    26 October 2026

    Morocco has outlined a second rail investment cycle for 2030-35, which includes beginning construction of a high-speed rail extension from Marrakech to Agadir and connecting Essaouira to the national rail network.

    The pipeline forms part of the government’s 2026-31 programme, presented to parliament last week.

    The Marrakech-Agadir link is estimated to cost close to MD55bn ($5.5bn) and will cover a 240-kilometre (km) route through the High Atlas Mountains via Chichaoua. Civil engineering structures, including tunnels and viaducts, are expected to account for nearly 70% of the alignment.

    In September, the government issued a decree declaring the Marrakech-Agadir and Chichaoua-Essaouira rail corridors to be of public utility, paving the way for land acquisition and expropriation procedures.

    Under the long-term masterplan Plan Rail Maroc 2040, Essaouira is expected to connect to the network via a separate line branching off at Chichaoua, designed for operating speeds of up to 200km an hour. The mainline to Agadir is designed for speeds of up to 320km/h.

    The 2030-35 cycle also includes rehabilitating the Casablanca-Khouribga-Oued Zem line; constructing a new line between Oued Zem and Beni Mellal via Bejaad, with a branch to Fquih Ben Salah; doubling and upgrading the 140km Benguerir-Safi line; expanding capacity on the Fez-Oujda corridor; and building new-generation passenger stations.

    The plans follow Morocco’s ongoing MD134bn ($13.4bn) 2024-30 rail investment programme, which focuses on completing the Kenitra-Marrakech high-speed line ahead of the 2030 Fifa World Cup.

    The programme also includes developing regional express network services across five regions, electrifying the Fez-Oujda line and completing a freight rail link to the Nador West Med port.

    Work on the Kenitra-Marrakech line had reached about 30% by May 2026, with commercial services targeted to begin in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20920349/main.jpg
    Yasir Iqbal
  • Riyadh tenders King Salman Stadium works

    26 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Sports Ministry has tendered a contract covering early works at King Salman International Stadium in Riyadh.

    The scope includes enabling works, site preparation and initial construction activities.

    The tender was issued on 11 October, with a submission deadline of 19 November.

    The stadium will cover about 660,000 square metres (sq m) and seat 92,000. Facilities will include a 150-seat royal suite, 120 hospitality suites, 300 VIP seats and 2,200 dignitary seats.

    The wider development will include sports facilities covering more than 360,000 sq m, including two training fields and fan zones; a closed sports hall; an Olympic-sized swimming pool; an athletics track; and outdoor courts for volleyball, basketball and padel.

    The stadium is set to host the final of the 2034 Fifa World Cup and will serve as the Saudi national football team’s main base.

    US-based architectural firm Populous is the lead architect for the stadium.

    Construction of the stadium is expected to be completed by 2029.

    The stadium will be located next to King Abdulaziz Park.

    Firms submitted prequalification statements for the main design-and-build contract in February.

    Saudi stadium plans

    In August 2024, MEED reported that Saudi Arabia planned to build 11 new stadiums and refurbish four facilities for the 2034 Fifa World Cup. 

    Eight stadiums will be located in Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom.

    A further 10 cities will host training bases: Al-Baha, Jazan, Taif, Medina, Alula, Umluj, Tabuk, Hail, Al-Ahsa and Buraidah.

    There are expected to be 134 training sites in the kingdom, including 61 existing facilities and 73 new venues.

    Saudi Arabia was officially selected to host the 2034 Fifa World Cup during an online convention of Fifa member associations at the Fifa Congress on 11 December 2024.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20919233/main.jpg
    Yasir Iqbal