Riyadh reins in spending

24 May 2024

 

Register for MEED's guest programme 

On the surface, it feels like business as usual in Saudi Arabia as new projects continue to be launched.

On 8 May, designs for another futuristic project at Neom’s Gulf of Aqaba were released with slick computer-generated imagery. Known as Jaumur (pictured), it includes the development of a mixed-use community featuring 1,200 residential units and two hotels offering 350 rooms. The most eye-catching part of the project is at the marina, which will have a 1.5-kilometre aerofoil that will rise above the yacht berths.

Beneath the surface, a consensus is emerging that the kingdom’s projects market is in the midst of a recalibration as spending is reined in.

The challenge for Riyadh over the next few years will be balancing the delivery of its ambitions with the reality of its financial capabilities.

The first public sign that things were changing came in December 2023, when Finance Minister Mohammed Al Jadaan told reporters at the launch of the 2024 budget that the delivery of some of the projects included in the Saudi Vision 2030 plan may be delayed to avoid pressure on the economy.

Tightening the purse strings

The ministry-level decision is trickling down as individual development companies are not getting their full budgets approved. “Our firm is working on almost all of the major projects in Saudi Arabia in some capacity,” says an international consultant. “The feedback we are getting is that budget spending for 2024 has been reduced by about 30% on average.”

Many of these delivery companies are subsidiaries of sovereign wealth vehicle the Public Investment Fund (PIF), which has taken a leading role in transforming the kingdom’s economy over the past eight years with development schemes including its five official gigaprojects, Neom, Roshn, Red Sea Global (RSG), Qiddiya and Diriyah.

The reports of budget cuts have coincided with a drop in contract awards. According to MEED’s Gigaprojects Tracker, there has been a sharp decline in the value of contracts awarded by the five official gigaprojects this year. 

In April, they awarded $166m of work, down from $271m in March and $509m in February. The total in January was $5.56bn, largely due to the $4.7bn contract awarded to the local Webuild for the construction of dams at the Trojena mountain resort in Neom.

The reports of budget cuts have coincided with a drop in contract awards

Funding options

The budget cuts are just part of the message, says the consultant. The delivery companies are being told to find external investment to deliver their projects, and there are already signs of this happening. The clearest came in late April, when Neom announced a $2.7bn revolving credit facility from nine local banks to cater to the project’s short-term financing requirements.

In a statement, Neom CEO Nadhmi Nasser highlighted the project’s drive to find new sources of funding. “As Neom continues to gather pace, this new credit facility, backed by Saudi Arabia’s leading financial institutions, is a natural fit within our wider strategy for funding. We continue to explore a variety of funding sources as we deliver transformational infrastructure assets while supporting the wider Vision 2030 programme,” he said. 

In a research note following the deal, London-based Capital Economics said: “While this does take some of the onus away from the government and Public Investment Fund, it is increasingly using resources that could be used more productively in the private non-oil sector.”

Capital Economics also noted that the facility adds to the growing share of commercial banks’ lending to the public sector. Since 2015, this share has increased from 7% to 22% in March 2024.

Another solution for development companies is deploying public-private partnerships (PPPs) to deliver infrastructure and utilities. This is attractive because PPPs reduce the initial capital expenditure required for a project. 

RSG has already pursued this route for The Red Sea Project and Amaala; other development companies are exploring the PPP avenue for their projects.

Real estate investment is another option. There is an expectation that Riyadh will introduce a foreign ownership law that could turbocharge the market as a similar law did for Dubai in the early 2000s. 

There are already examples of real estate investment deals being done, including the National Housing Company with Spain’s Urbas Group for housing in Riyadh, RSG with Kingdom Holding Company for hotels, and King Salman with a real estate development fund.

PPP offers budget and efficiency routes

Prioritising projects

As projects in the kingdom are developed differently, the challenge for the construction industry will be identifying which of the many schemes that aim to transform the Saudi economy are a top priority.

Much will depend on the success of the investment drive. The most likely projects to go ahead are those linked to global events with immovable deadlines. Experience across the region over the past decade has shown that even if construction elsewhere slowed down, construction for Expo 2020 in Dubai and the 2022 Fifa World Cup in Qatar continued regardless. 

“For Saudi Arabia, there are three major events: the Asian Winter Games in 2029, Expo 2030 and World Cup 2034. They will be the obvious priorities,” says the international consultant.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11816519/main.gif
Colin Foreman
Related Articles
  • Firms submit Mid Island Parkway prequalifications

    18 August 2026

     

    Abu Dhabi’s Modon Infrastructure has received expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership.

    Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.

    Phase two of the MIPP involves constructing about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.

    The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.

    Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18830452/main.png
    Yasir Iqbal
  • Adnoc selects contractors for new LNG project in the UAE

    18 August 2026

     

    Abu Dhabi National Oil Company (Adnoc) has selected contractors for a design competition it is overseeing for a major project to build a new liquefied natural gas (LNG) export facility along the UAE’s eastern coast.

    The proposed onshore LNG liquefaction facility – whose precise location Adnoc has yet to reveal – will have a nameplate output capacity of 4 million tonnes a year (t/y) and will mainly serve export purposes, MEED reported in June. The facility will receive sales-gas-quality feedstock via pipelines from Adnoc’s gas processing facilities in Abu Dhabi and will export LNG via a loading jetty.

    MEED previously reported on Adnoc’s intention to execute work on the project through a design competition or front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) contest.

    Under this model, the project operator selects contractors to carry out feed work. The operator then awards the EPC contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.

    The Abu Dhabi energy giant has selected the following three entities to undertake feed work on the planned onshore LNG liquefaction facility, according to sources:

    • Saipem (Italy) / Larsen & Toubro Energy Hydrocarbon (India)
    • Technip Energies (France) / JGC Corporation (Japan)
    • Tecnimont (Italy)

    Adnoc issued draft letters of award to the selected contractors between 11 and 12 August, the sources added.

    In addition to the contractors picked by Adnoc, MEED previously reported that the following contractors were shortlisted for the feed-to-EPC contest:

    • McDermott (US)
    • Samsung E&A (South Korea)
    • Wison (China)

    MEED reported that Adnoc issued the expression of interest (EoI) document for the planned LNG facility project on 2 June, with contractors submitting responses by 5 June.

    Given the strategic importance of the project, Adnoc is understood to be fast-tracking the tendering exercise, issuing the main tender for the feed-to-EPC contest within days of the EoI submission. The company sought proposals from participating contractors by 1 July, sources said.

    In its EoI document, Adnoc said it intends to award the main EPC contract in the third quarter of this year.

    Adnoc has yet to specify where it plans to build the LNG complex, stating only in the EoI document that it will be located at a coastal site in the UAE.

    MEED understands Adnoc may be considering a site near one of the UAE’s eastern port facilities in the emirate of Fujairah. The blockade of the Strait of Hormuz in recent months has increased interest in prioritising exports and maritime trade through ports on the Gulf of Oman.

    The scope of work on the planned LNG facility covers the following units:

    LNG facilities:

    • An onshore LNG liquefaction facility in a coastal location, with a nominal output capacity of 4 million t/y;
    • Process units necessary to bring sales feed to a liquefaction-quality feed gas (i.e. carbon dioxide removal, dehydration, mercury removal and total sulphur reduction);
    • Common facilities including inlet receiving facilities, refrigerant storage and flares;
    • Utilities to support the facility, allowing it to be self-sufficient, including but not limited to local power generation and any necessary tie-ins;
    • LNG export facilities, including a jetty and berth;
    • Structures including control buildings, amenities, a laboratory, a warehouse, workshops and administration buildings, to fully support the plant operation.

    LNG storage facilities:

    • LNG storage tanks, handling of boil-off gases (BOG) and potentially a BOG reliquefaction unit to facilitate major shutdown operations for bidders opting to compete with a single liquefaction train option.

    Feed gas supply:

    • Supplying and installing an additional identical gas compressor to be located at an existing compression station near Adnoc Gas’ Habshan complex in Abu Dhabi, to provide additional capacity in an existing gas pipeline system;
    • A new feed gas pipeline, approximately 160 kilometres long, to route sales gas quality feed gas from an existing pipeline network to the LNG facility.

    Modifications to upstream facilities (alternative scope):

    • Installation of sulphur removal beds in Habshan to bring feed gas to required LNG quality at the upstream gas conditioning facility, rather than at the LNG facility. This may be selected by bidders to avoid additional investment for processing the regeneration gas.

    Construction facilities:

    • Temporary construction facilities, laydown area and material offloading facility, to support EPC execution requirements;
    • Construction labour accommodation camp.
    Adnoc LNG output capacity

    Adnoc has an LNG liquefaction capacity of 6 million t/y, which is set to more than double to 15 million t/y when its under-construction LNG terminal complex in Abu Dhabi’s Ruwais enters operations in 2028.

    The upcoming LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.

    Adnoc awarded the full EPC contract and reached the final investment decision for the Ruwais LNG terminal project in June 2024. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy – a subsidiary of NMDC Group – was awarded the $5.5bn EPC contract. In March of that year, Adnoc issued a limited notice to proceed to the consortium of contractors led by Technip Energies for early EPC works on the Ruwais LNG terminal project.

    The complex will feature process units, storage tanks and an export jetty for loading cargoes and LNG bunkering, as well as utilities, flare handling systems and associated buildings.

    The planned LNG facility will run on electric-powered rotary equipment and compressors instead of gas-fired units. Adnoc awarded a $400m contract in October 2023 to US-based Baker Hughes for the supply of all-electric compression systems for the project. The LNG trains will run on energy-efficient Baker Hughes technology, including compressors driven by 75MW electric motors.

    Adnoc has also signed agreements with international energy companies to divest a total stake of 40% in the Ruwais LNG project. UK energy producer BP, Mitsui & Co, Shell and French energy producer TotalEnergies will each hold 10% stakes in the Ruwais LNG terminal project, with Adnoc retaining the majority 60% stake in the facility.

    Adnoc Group subsidiary Adnoc Gas will acquire its parent company’s 60% stake in the Ruwais LNG facility at cost in the second half of 2028, when first production from the complex is due.

    To date, Adnoc has secured offtake agreements totalling 8 million t/y, representing approximately 90% of the Ruwais LNG project’s output capacity.

    Photo for illustration only

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18829520/main.jpg
    Indrajit Sen
  • Saudi Arabia extends bid deadline for Round 7 solar projects

    18 August 2026

     

    Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), has extended the deadline for developers bidding for four solar projects under the seventh round of the National Renewable Energy Programme (NREP).

    Round seven of the NREP comprises solar photovoltaic (PV) and wind independent power producer (IPP) projects with a combined capacity of 5,300MW. The renewables programme is being led and supervised by the Ministry of Energy.

    The four solar PV projects comprise:

    • 1,400MW Tabjal 2 solar PV IPP (Tabrijal, Al-Jouf province)
    • 600MW Mawqqaq solar PV IPP (Mawqqaq, Hail province)
    • 600MW Tathleeth solar PV IPP (Tathleeth, Aseer province)
    • 500MW South Al-Ula solar PV IPP (Al-Ula, Medina province)

    The projects were tendered in January, with submissions previously expected by 30 August. The new deadline is 13 September.

    The programme also includes the 1,300MW Bilgah and 900MW Shagra wind IPPs. The bid submission deadline for these projects is 14 September.

    As previously reported by MEED, procurement for the seventh round of the NREP opened in August 2025 when SPPC issued a request for qualification. 

    In January, MEED reported that 16 developers qualified to bid as both managing and technical members for the four solar PV projects. A further six companies qualified to bid as a managing member only.

    For the wind IPPs, SPPC qualified 13 developers in the managing and technical members category, and a further six companies in the managing member category only. The request for proposals for both wind and solar IPPs was issued that same month. 

    The renewable energy programme aims to supply 50% of the kingdom’s electricity from renewable energy by 2030.

    Earlier rounds under the NREP have already put in place large capacities. Last October, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP.

    These comprise four solar PV IPP projects and one wind IPP project with a total combined capacity of 4,500MW.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18828963/main.jpg
    Mark Dowdall
  • Construction begins on phase two of Cairo Metro Line 4

    18 August 2026

    Egypt’s National Authority for Tunnels (NAT) has begun implementing the second phase of Cairo Metro’s Line 4, spanning about 27 kilometres.

    The main construction works contract was awarded to a joint venture of local firms, including Arab Contractors, Hassan Allam, Petrojet and Concord Engineering & Contracting.

    Cairo Metro Line 4 will stretch from Fustat station to Zahraa Nasr City station in New Cairo. The line will comprise 21 stations, 15 underground and six elevated.

    According to data from regional projects tracker MEED Projects, the scope also covers:

    • Construction of a tunnel route starting from Al-Fustat station, following Salah Salem Road, and intersecting with the sixth metro line at Sayeda Aisha station
    • An extension along Hafez Ibrahim Street, intersecting the Shinzo Abe Axis and linking Ahmed Al-Zomor and Al-Mithaq streets
    • A section running via Nasr Road and Nasr City to Anwar Al-Mufti Street, with an interchange with the East Nile Monorail at Aviation station
    • Construction of a depot at the Omra El-Gasima site
    • Integration of interchange stations with existing lines, including Line 1 and Line 2
    • Construction of structures over and under major roadways, including the Ring Road and Cairo-Suez Road
    • Earthworks and site preparation, including elevated foundations and underground excavations
    • Construction of all other associated infrastructure

    Local media reports said construction work on the first phase of Line 4 is expected to be completed in 2028.

    The joint venture of Arab Contractors, Hassan Allam, Petrojet and Concord Engineering & Contracting is also undertaking the main works on the first phase.

    The Japan International Cooperation Agency (Jica) provided half of the $4bn funding required for Line 4’s first phase.

    The media reports added that NAT is currently studying the third and fourth phases of Line 4.

    The third phase aims to connect the Ashgar Gardens and Al-Hosary areas via a rail line spanning more than 16km.

    The fourth phase will be more than 38km long and will connect the Al-Rehab area with the capital’s international airport east of Cairo.

    Once completed across all phases, Line 4 will link 6th of October City with southern and eastern Cairo, the New Administrative Capital and Capital International airport, making it one of the longest transport networks in the country.

    In April last year, MEED reported on Egypt’s future rail project plans, which include eight key projects spanning metro, high-speed rail and light rail transit.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18825481/main.jpg
    Yasir Iqbal
  • RTA opens bridge connecting DWTC to Al-Mustaqbal Street

    18 August 2026

    Dubai’s Roads & Transport Authority (RTA) has opened a new 500-metre, two-lane bridge connecting traffic from Dubai World Trade Centre (DWTC) and One Central to Al-Mustaqbal Street.

    The bridge will reduce travel time from DWTC to Al-Mustaqbal Street from around 10 minutes to about two minutes during major events.

    The bridge is part of the $172m Al-Mustaqbal Street Development Project. The wider scheme includes around 2,000 metres of bridges and tunnels, along with a pedestrian bridge on Al-Sukook Street, and runs from Zaabeel Palace Street to Financial Centre Street.

    As part of the project, Al-Mustaqbal Street will be widened from three to four lanes in each direction, increasing overall capacity by 33% to 8,800 vehicles per hour in both directions.

    The RTA added that this is expected to cut end-to-end travel time along the corridor from 13 minutes to six minutes.

    Three tunnels, totalling 1,500 metres, at the intersection of Al-Mustaqbal Street and Trade Centre Street are scheduled to open in February 2027.

    These include a three-lane tunnel towards Deira with a capacity of 4,500 vehicles per hour, a two-lane tunnel for left-turn movements between the two streets, and a one-lane tunnel serving One Central.

    The RTA said that the overall project completion rate has reached 85%.

    In February last year, MEED exclusively reported that the RTA had selected local firm Wade Adams to undertake improvement works on Al-Mustaqbal Street.

    Planning for growth

    The Dubai 2040 Urban Master Plan was launched in March 2021. Its launch referenced studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18822891/main.jpg
    Yasir Iqbal