Riyadh reins in spending
24 May 2024

Register for MEED's guest programme
On the surface, it feels like business as usual in Saudi Arabia as new projects continue to be launched.
On 8 May, designs for another futuristic project at Neom’s Gulf of Aqaba were released with slick computer-generated imagery. Known as Jaumur (pictured), it includes the development of a mixed-use community featuring 1,200 residential units and two hotels offering 350 rooms. The most eye-catching part of the project is at the marina, which will have a 1.5-kilometre aerofoil that will rise above the yacht berths.
Beneath the surface, a consensus is emerging that the kingdom’s projects market is in the midst of a recalibration as spending is reined in.
The challenge for Riyadh over the next few years will be balancing the delivery of its ambitions with the reality of its financial capabilities.
The first public sign that things were changing came in December 2023, when Finance Minister Mohammed Al Jadaan told reporters at the launch of the 2024 budget that the delivery of some of the projects included in the Saudi Vision 2030 plan may be delayed to avoid pressure on the economy.
Tightening the purse strings
The ministry-level decision is trickling down as individual development companies are not getting their full budgets approved. “Our firm is working on almost all of the major projects in Saudi Arabia in some capacity,” says an international consultant. “The feedback we are getting is that budget spending for 2024 has been reduced by about 30% on average.”
Many of these delivery companies are subsidiaries of sovereign wealth vehicle the Public Investment Fund (PIF), which has taken a leading role in transforming the kingdom’s economy over the past eight years with development schemes including its five official gigaprojects, Neom, Roshn, Red Sea Global (RSG), Qiddiya and Diriyah.
The reports of budget cuts have coincided with a drop in contract awards. According to MEED’s Gigaprojects Tracker, there has been a sharp decline in the value of contracts awarded by the five official gigaprojects this year.
In April, they awarded $166m of work, down from $271m in March and $509m in February. The total in January was $5.56bn, largely due to the $4.7bn contract awarded to the local Webuild for the construction of dams at the Trojena mountain resort in Neom.
The reports of budget cuts have coincided with a drop in contract awards
Funding options
The budget cuts are just part of the message, says the consultant. The delivery companies are being told to find external investment to deliver their projects, and there are already signs of this happening. The clearest came in late April, when Neom announced a $2.7bn revolving credit facility from nine local banks to cater to the project’s short-term financing requirements.
In a statement, Neom CEO Nadhmi Nasser highlighted the project’s drive to find new sources of funding. “As Neom continues to gather pace, this new credit facility, backed by Saudi Arabia’s leading financial institutions, is a natural fit within our wider strategy for funding. We continue to explore a variety of funding sources as we deliver transformational infrastructure assets while supporting the wider Vision 2030 programme,” he said.
In a research note following the deal, London-based Capital Economics said: “While this does take some of the onus away from the government and Public Investment Fund, it is increasingly using resources that could be used more productively in the private non-oil sector.”
Capital Economics also noted that the facility adds to the growing share of commercial banks’ lending to the public sector. Since 2015, this share has increased from 7% to 22% in March 2024.
Another solution for development companies is deploying public-private partnerships (PPPs) to deliver infrastructure and utilities. This is attractive because PPPs reduce the initial capital expenditure required for a project.
RSG has already pursued this route for The Red Sea Project and Amaala; other development companies are exploring the PPP avenue for their projects.
Real estate investment is another option. There is an expectation that Riyadh will introduce a foreign ownership law that could turbocharge the market as a similar law did for Dubai in the early 2000s.
There are already examples of real estate investment deals being done, including the National Housing Company with Spain’s Urbas Group for housing in Riyadh, RSG with Kingdom Holding Company for hotels, and King Salman with a real estate development fund.
PPP offers budget and efficiency routes
Prioritising projects
As projects in the kingdom are developed differently, the challenge for the construction industry will be identifying which of the many schemes that aim to transform the Saudi economy are a top priority.
Much will depend on the success of the investment drive. The most likely projects to go ahead are those linked to global events with immovable deadlines. Experience across the region over the past decade has shown that even if construction elsewhere slowed down, construction for Expo 2020 in Dubai and the 2022 Fifa World Cup in Qatar continued regardless.
“For Saudi Arabia, there are three major events: the Asian Winter Games in 2029, Expo 2030 and World Cup 2034. They will be the obvious priorities,” says the international consultant.
Exclusive from Meed
-
EtihadWE tenders $150m Ajman substation project21 July 2026
-
-
-
-
Dubai Municipality awards Tasreef drainage contract21 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
EtihadWE tenders $150m Ajman substation project21 July 2026
The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.
Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.
The bid submission deadline is 10 August.
According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.
The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.
Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.
This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.
EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.
In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg -
Seven seeks contractors for Dammam water park and hotel21 July 2026

Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.
The waterfront development sits on a 324,300-square-metre (sq m) plot.
A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.
Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.
The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.
The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.
Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.
Detailed design and issued-for-construction packages are complete.
Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.
The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.
The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.
Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.
Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.
The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.
The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg -
Al-Ula appoints equestrian village early works contractor21 July 2026

Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.
The contract was awarded to Al-Khobar-based Al-Shalawi International Company.
Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.
Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.
RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.
The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.
These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg -
Contractors await decision on Riyadh airport sewage plant21 July 2026

Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.
It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.
The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.
The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).
The bidders (all local) are:
- Al-Rawaf Trading & Contracting
- Almajal Alarabi
- Nesma Water & Energy
- Safari Company
- Saudi Services for Electro-Mechanic Works
- Washnah Contracting
- Water & Environment Technologies (Wetico)
The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.
US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.
The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.
Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.
The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.
These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg -
Dubai Municipality awards Tasreef drainage contract21 July 2026

Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.
It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.
The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.
The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.
Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.
In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.
The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg