Riyadh reins in spending
24 May 2024

Register for MEED's guest programme
On the surface, it feels like business as usual in Saudi Arabia as new projects continue to be launched.
On 8 May, designs for another futuristic project at Neom’s Gulf of Aqaba were released with slick computer-generated imagery. Known as Jaumur (pictured), it includes the development of a mixed-use community featuring 1,200 residential units and two hotels offering 350 rooms. The most eye-catching part of the project is at the marina, which will have a 1.5-kilometre aerofoil that will rise above the yacht berths.
Beneath the surface, a consensus is emerging that the kingdom’s projects market is in the midst of a recalibration as spending is reined in.
The challenge for Riyadh over the next few years will be balancing the delivery of its ambitions with the reality of its financial capabilities.
The first public sign that things were changing came in December 2023, when Finance Minister Mohammed Al Jadaan told reporters at the launch of the 2024 budget that the delivery of some of the projects included in the Saudi Vision 2030 plan may be delayed to avoid pressure on the economy.
Tightening the purse strings
The ministry-level decision is trickling down as individual development companies are not getting their full budgets approved. “Our firm is working on almost all of the major projects in Saudi Arabia in some capacity,” says an international consultant. “The feedback we are getting is that budget spending for 2024 has been reduced by about 30% on average.”
Many of these delivery companies are subsidiaries of sovereign wealth vehicle the Public Investment Fund (PIF), which has taken a leading role in transforming the kingdom’s economy over the past eight years with development schemes including its five official gigaprojects, Neom, Roshn, Red Sea Global (RSG), Qiddiya and Diriyah.
The reports of budget cuts have coincided with a drop in contract awards. According to MEED’s Gigaprojects Tracker, there has been a sharp decline in the value of contracts awarded by the five official gigaprojects this year.
In April, they awarded $166m of work, down from $271m in March and $509m in February. The total in January was $5.56bn, largely due to the $4.7bn contract awarded to the local Webuild for the construction of dams at the Trojena mountain resort in Neom.
The reports of budget cuts have coincided with a drop in contract awards
Funding options
The budget cuts are just part of the message, says the consultant. The delivery companies are being told to find external investment to deliver their projects, and there are already signs of this happening. The clearest came in late April, when Neom announced a $2.7bn revolving credit facility from nine local banks to cater to the project’s short-term financing requirements.
In a statement, Neom CEO Nadhmi Nasser highlighted the project’s drive to find new sources of funding. “As Neom continues to gather pace, this new credit facility, backed by Saudi Arabia’s leading financial institutions, is a natural fit within our wider strategy for funding. We continue to explore a variety of funding sources as we deliver transformational infrastructure assets while supporting the wider Vision 2030 programme,” he said.
In a research note following the deal, London-based Capital Economics said: “While this does take some of the onus away from the government and Public Investment Fund, it is increasingly using resources that could be used more productively in the private non-oil sector.”
Capital Economics also noted that the facility adds to the growing share of commercial banks’ lending to the public sector. Since 2015, this share has increased from 7% to 22% in March 2024.
Another solution for development companies is deploying public-private partnerships (PPPs) to deliver infrastructure and utilities. This is attractive because PPPs reduce the initial capital expenditure required for a project.
RSG has already pursued this route for The Red Sea Project and Amaala; other development companies are exploring the PPP avenue for their projects.
Real estate investment is another option. There is an expectation that Riyadh will introduce a foreign ownership law that could turbocharge the market as a similar law did for Dubai in the early 2000s.
There are already examples of real estate investment deals being done, including the National Housing Company with Spain’s Urbas Group for housing in Riyadh, RSG with Kingdom Holding Company for hotels, and King Salman with a real estate development fund.
PPP offers budget and efficiency routes
Prioritising projects
As projects in the kingdom are developed differently, the challenge for the construction industry will be identifying which of the many schemes that aim to transform the Saudi economy are a top priority.
Much will depend on the success of the investment drive. The most likely projects to go ahead are those linked to global events with immovable deadlines. Experience across the region over the past decade has shown that even if construction elsewhere slowed down, construction for Expo 2020 in Dubai and the 2022 Fifa World Cup in Qatar continued regardless.
“For Saudi Arabia, there are three major events: the Asian Winter Games in 2029, Expo 2030 and World Cup 2034. They will be the obvious priorities,” says the international consultant.
Exclusive from Meed
-
Iranian missiles hit Qatari and Kuwaiti fuel tankers1 April 2026
-
-
-
Drone strikes Kuwait International airport1 April 2026
-
Saudi Arabia’s Sadara halts chemical production1 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iranian missiles hit Qatari and Kuwaiti fuel tankers1 April 2026
Iranian missiles have struck fuel tankers in Gulf waters belonging to Qatar and Kuwait, as Tehran continues to target energy, industrial and logistical assets in GCC countries.
A fuel oil tanker chartered by QatarEnergy, named Aqua 1, was struck by missiles in Qatar’s northern territorial waters in the early hours of 1 April, the company said in a statement.
“None of the crew members on board were injured, and there is no impact on the environment as a result of this incident,” QatarEnergy said.
Earlier, on 31 March, said one of its very large crude carriers, Al-Salmi, caught fire after being hit by an Iranian missile while anchored in UAE waters just outside Dubai.
The vessel’s crew, with support from UAE authorities, extinguished the fire by 04:26 Kuwait time on 31 March, KPC said. It added that all 24 crew members were safe and that no oil spill or environmental damage occurred.
“KPC is continuing to assess the damage in coordination with relevant authorities,” the Kuwaiti state energy conglomerate said.
ALSO READ: Iran strikes Gulf aluminium assets after hits on its steel sector
https://image.digitalinsightresearch.in/uploads/NewsArticle/16217670/main4010.jpg -
One killed and one injured in drone attacks on the UAE1 April 2026
Debris falling from Iranian drones intercepted by the UAE’s air defence systems has killed one person in the emirate of Fujairah and injured another in Umm Al-Quwain in two separate incidents on 1 April.
A successful interception of a drone by UAE air defence forces resulted in debris falling on a farm in Fujairah, leading to the death of a Bangladeshi national.
The latest fatality brings the total death toll in the UAE since the start of the US-Israel-Iran war to 12. Most of the deaths have been caused by falling debris following interceptions. Among the deceased are two members of the UAE armed forces who died while performing their duties, as well as a Moroccan civilian contracted by the armed forces.
The remaining victims were of Bangladeshi, Indian, Nepali, Pakistani and Palestinian nationalities.
Hours after the Fujairah incident, authorities in Umm Al-Quwain confirmed that an Indian national was injured when debris from an intercepted drone fell in the emirate.
In a statement posted on its official social media channels, the Umm Al-Quwain government media office said the incident occurred near an industrial facility in the Umm Al-Thuoob area, after air defence systems successfully intercepted an unmanned aerial vehicle (UAV).
Meanwhile, the latest data from the UAE Ministry of Defence, released on 31 March, showed that air defence systems had engaged 36 UAVs, four cruise missiles and eight ballistic missiles in the previous 24 hours. Cumulatively, authorities said 1,977 drones, 19 cruise missiles and 433 ballistic missiles have been intercepted since the onset of the war on 28 February.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16218126/main.jpg -
Contractors submit Al-Maktoum airport superstructure bids1 April 2026

Dubai Aviation Engineering Projects (DAEP) received proposals on 31 March from contractors for three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.
MEED understands that the selected contractor will undertake superstructure works on three packages:
- West Terminal and concourse one
- Concourse two
- Concourse three
Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.
According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.
It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.
In August last year, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport.
The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
Construction progress
Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.
Construction on the project’s first phase is expected to be completed by 2032.
The government approved the updated designs and timelines for its largest construction project in April 2024.
In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
The statement added that the project will create housing demand for 1 million people around the airport.
In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.
Project history
The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.
An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.
Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16215664/main.jpg -
Drone strikes Kuwait International airport1 April 2026
Register for MEED’s 14-day trial access
Kuwait International airport was hit by further drone attacks on Wednesday, with strikes on fuel tanks sparking a major fire.
Kuwait’s state news agency Kuna said the attack caused significant damage to fuel tanks belonging to Kuwait Aviation Fuelling Company. No casualties were reported.
This was the second reported incident at the airport in recent days. Local media reported that the airport was attacked on 28 March by multiple drones, causing significant damage to its radar system.
The airport is currently undergoing expansion works that are expected to be completed by 2027, as MEED reported previously.
Project execution of the second terminal began in 2017, with the completion date pushed back from the original 2022 target.
The second terminal project consists of three packages.
These are:
- Package 1: Main works – $4,329m
- Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
- Package 3: Aircraft parking, runways and service buildings – $950m
Turkiye’s Limak Holding is executing the main works.
The terminal building was designed by Foster+Partners and Gulf Consult.
Spanish firm Ineco is providing the project management services for the new terminal building and the airfield.
The scope of the main package includes the new terminal building, a building for cooling and electricity supply facilities, and a building for the water supply and the future Automatic People Mover (APM) connection to the satellite building.
The terminal building will be three times the size of the original building and will have 36 boarding gates.
The building will cover more than 700,000 square metres and have five floors, one of which will be underground.
It will have the capacity, at maximum service level, for 25 million passengers a year once the first phase has been completed and up to 50 million passengers after further phases are completed.
The second package of works includes a new car park with approximately 5,000 parking spaces, connected to the new passenger terminal.
It also includes all new access roads to the airport and landscaping.
The scope of the third package comprises the main platform, new taxiways and several tunnels, including one under the platform between the terminal building and the future cargo area of the airport.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16216797/main.png -
Saudi Arabia’s Sadara halts chemical production1 April 2026
Register for MEED’s 14-day trial access
Sadara Chemical Company (Sadara), the Saudi Aramco-Dow Chemical joint venture producing petrochemicals and specialty chemicals, has announced a temporary shutdown of production, citing ongoing supply chain disruptions.
Sadara operates a sprawling chemical production complex in Jubail in Saudi Arabia’s Eastern Province, with a total output capacity of more than 3 million metric tonnes a year. Aramco and Dow established the Sadara petrochemicals complex – estimated to have cost $13bn – in 2016.
The suspension was announced in a filing on the Saudi Exchange (Tadawul) by Sadara Basic Services, which issues sukuk, or Islamic bonds, for its parent. “The shutdown was successfully completed in accordance with Sadara’s high safety standards and in a manner that safeguards operations and reduces risk,” the entity said in its filing on 31 March.
“Sadara cannot provide, at the present time, an estimate for the return to production, as this is contingent on domestic and international factors,” it said, adding the shutdown is expected to impact this year’s financial results.
The month-long war between Israel, the US and Iran has spread across the Middle East, disrupting energy supplies and threatening the global economy, as Tehran has responded to US and Israeli attacks by targeting regional energy and industrial infrastructure, as well as shipping.
ALSO READ: Sultan Al-Jaber calls Strait of Hormuz blockade “economic terrorism”
Separately, Sadara, in another Tadawul filing on 31 March, announced a net loss of SR5,793bn ($1.54bn) for the full year 2025, a further decline of about 40% compared to 2024. The company’s revenue in 2025 fell by about 15% year-on-year to $2.63bn.
The chemicals producer attributed the deepening of its losses in 2025 to a reduction in sales volumes, “which resulted from unplanned operational events and extended maintenance activities that temporarily impacted production availability”.
Sadara also pinned its augmented losses to “margin compression, and higher fixed costs associated with unplanned operational events and extended maintenance activities.
“In addition, the company experienced lower average selling prices across certain portfolio lines, which further contributed to the overall decrease in revenue,” Sadara said in the disclosure.
In addition, “the net loss for 2025 increased compared to 2024, mainly due to an accounting adjustment related to a debt modification that had a favourable impact on the prior year’s results,” the company added.
ALSO READ: Sabic registers $6.87bn net loss in 2025
https://image.digitalinsightresearch.in/uploads/NewsArticle/16215635/main2446.jpg