Riyadh reins in spending

24 May 2024

 

Register for MEED's guest programme 

On the surface, it feels like business as usual in Saudi Arabia as new projects continue to be launched.

On 8 May, designs for another futuristic project at Neom’s Gulf of Aqaba were released with slick computer-generated imagery. Known as Jaumur (pictured), it includes the development of a mixed-use community featuring 1,200 residential units and two hotels offering 350 rooms. The most eye-catching part of the project is at the marina, which will have a 1.5-kilometre aerofoil that will rise above the yacht berths.

Beneath the surface, a consensus is emerging that the kingdom’s projects market is in the midst of a recalibration as spending is reined in.

The challenge for Riyadh over the next few years will be balancing the delivery of its ambitions with the reality of its financial capabilities.

The first public sign that things were changing came in December 2023, when Finance Minister Mohammed Al Jadaan told reporters at the launch of the 2024 budget that the delivery of some of the projects included in the Saudi Vision 2030 plan may be delayed to avoid pressure on the economy.

Tightening the purse strings

The ministry-level decision is trickling down as individual development companies are not getting their full budgets approved. “Our firm is working on almost all of the major projects in Saudi Arabia in some capacity,” says an international consultant. “The feedback we are getting is that budget spending for 2024 has been reduced by about 30% on average.”

Many of these delivery companies are subsidiaries of sovereign wealth vehicle the Public Investment Fund (PIF), which has taken a leading role in transforming the kingdom’s economy over the past eight years with development schemes including its five official gigaprojects, Neom, Roshn, Red Sea Global (RSG), Qiddiya and Diriyah.

The reports of budget cuts have coincided with a drop in contract awards. According to MEED’s Gigaprojects Tracker, there has been a sharp decline in the value of contracts awarded by the five official gigaprojects this year. 

In April, they awarded $166m of work, down from $271m in March and $509m in February. The total in January was $5.56bn, largely due to the $4.7bn contract awarded to the local Webuild for the construction of dams at the Trojena mountain resort in Neom.

The reports of budget cuts have coincided with a drop in contract awards

Funding options

The budget cuts are just part of the message, says the consultant. The delivery companies are being told to find external investment to deliver their projects, and there are already signs of this happening. The clearest came in late April, when Neom announced a $2.7bn revolving credit facility from nine local banks to cater to the project’s short-term financing requirements.

In a statement, Neom CEO Nadhmi Nasser highlighted the project’s drive to find new sources of funding. “As Neom continues to gather pace, this new credit facility, backed by Saudi Arabia’s leading financial institutions, is a natural fit within our wider strategy for funding. We continue to explore a variety of funding sources as we deliver transformational infrastructure assets while supporting the wider Vision 2030 programme,” he said. 

In a research note following the deal, London-based Capital Economics said: “While this does take some of the onus away from the government and Public Investment Fund, it is increasingly using resources that could be used more productively in the private non-oil sector.”

Capital Economics also noted that the facility adds to the growing share of commercial banks’ lending to the public sector. Since 2015, this share has increased from 7% to 22% in March 2024.

Another solution for development companies is deploying public-private partnerships (PPPs) to deliver infrastructure and utilities. This is attractive because PPPs reduce the initial capital expenditure required for a project. 

RSG has already pursued this route for The Red Sea Project and Amaala; other development companies are exploring the PPP avenue for their projects.

Real estate investment is another option. There is an expectation that Riyadh will introduce a foreign ownership law that could turbocharge the market as a similar law did for Dubai in the early 2000s. 

There are already examples of real estate investment deals being done, including the National Housing Company with Spain’s Urbas Group for housing in Riyadh, RSG with Kingdom Holding Company for hotels, and King Salman with a real estate development fund.

PPP offers budget and efficiency routes

Prioritising projects

As projects in the kingdom are developed differently, the challenge for the construction industry will be identifying which of the many schemes that aim to transform the Saudi economy are a top priority.

Much will depend on the success of the investment drive. The most likely projects to go ahead are those linked to global events with immovable deadlines. Experience across the region over the past decade has shown that even if construction elsewhere slowed down, construction for Expo 2020 in Dubai and the 2022 Fifa World Cup in Qatar continued regardless. 

“For Saudi Arabia, there are three major events: the Asian Winter Games in 2029, Expo 2030 and World Cup 2034. They will be the obvious priorities,” says the international consultant.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11816519/main.gif
Colin Foreman
Related Articles
  • Gulf needs $40bn of pipelines to bypass Hormuz

    20 November 2026

    Register for MEED’s 14-day trial access 

    Gulf producers would need to spend about $40bn on new pipelines to route most of their oil exports around the Strait of Hormuz, according to the International Energy Agency (IEA).

    The estimate, published in the agency's World Energy Outlook 2026, covers 6.8 million barrels a day (b/d) of export capacity that is either under construction or proposed in Saudi Arabia, the UAE and Iraq. The IEA calculates that the investment would add about $2 to the cost of each barrel exported from the Middle East.

    The figure gives the clearest indication yet of the scale of the pipeline programme that could follow the 2026 crisis, which the IEA describes as the largest energy supply shock the world has faced. Oil volumes transiting the strait collapsed from 20 million b/d to an average of about 3 million b/d in March, April and May.

    Project pipeline

    The only scheme under construction in the IEA’s list is Abu Dhabi National Oil Company’s (Adnoc) West-East pipeline, which will add 1.8 million b/d of capacity. MEED has reported that the 520-kilometre line from Jebel Dhanna to Fujairah is being built in three sections. It is expected to double Adnoc’s crude export capacity through Fujairah when it is commissioned in 2027.

    Separately, Adnoc expects to tender the main engineering, procurement and construction (EPC) contract for a new offshore line linking its Gulf processing islands to Jebel Dhanna, which will eventually connect to the West-East pipeline, by the end of the year.

    The largest proposed project is a 3 million b/d expansion of Saudi Aramco’s East-West pipeline from Abqaiq to Yanbu on the Red Sea. Aramco president and CEO Amin Nasser has said engineering work began in the early days of the conflict. Saudi Energy Minister Prince Abdulaziz bin Salman said in October that the kingdom is looking to expand its crude export capacity by pipeline to as much as 10 million b/d.

    In Iraq, the IEA counts two 1 million b/d lines from Haditha. One would run to Baniyas in Syria. The other would run to Fishkhabur, where it would link to the Iraq-Turkiye pipeline to Ceyhan. MEED has reported that a consortium led by Qatar’s UCC, including Chevron and TotalEnergies, is discussing terms for four interconnected pipeline packages worth about $5bn, with a contract expected to be signed before year-end. Iraq and Saudi Arabia are also considering reviving the 1,568km pipeline from Zubair to Yanbu, which was halted in 1990.

    The agency says the new routes would not help all Gulf producers. Bahrain, Kuwait and Qatar would still depend on the strait for their exports.

    Bypass flows

    About 8 million b/d of bypass pipeline capacity is already available, according to the report. These lines carried about 2 million b/d in 2025 and ramped up to a peak of 6.8 million b/d during the crisis.

    In the IEA’s Stated Policies Scenario (STEPS), only the Adnoc project is completed and bypass flows return to about 3 million b/d by 2035. If every existing, under-construction and proposed route were built and used to capacity, bypass flows could reach about 14.5 million b/d. Most Saudi and UAE exports, along with more than 60% of Iraq’s, would then avoid the strait.

    The IEA’s new Low Hormuz Case adds higher output from producers outside the Gulf and demand cuts by importers. In that case, oil transit through the strait falls below 2 million b/d by 2035. Raising supply outside the strait would require about $200bn of additional upstream investment between 2025 and 2035.

    Security caveats

    The agency cautions that the pipelines would not remove the risk. Drone attacks temporarily shut the East-West pipeline in September, and any exports to the Red Sea must pass through the Bab Al-Mandab Strait. MEED has reported that Houthi attacks on Aramco’s Red Sea assets since July, including the Jizan refinery, have cost Riyadh that alternative route. Even in the Low Hormuz Case, the Middle East still exports nearly 15 million b/d in 2035, about 20% of global oil trade.

    The IEA also notes that if the strait is at least partially open, Gulf producers would have few reasons not to use it. That could weaken the commercial case for the most expensive bypass schemes.

    Execution risks are emerging in Iraq. MEED has reported that the Common Seawater Supply Project is behind schedule, largely because pipeline segments cannot easily be imported through the strait. The same problem could force contractors on new export lines to use more costly routes.

    The IEA says there is no feasible bypass for liquefied natural gas (LNG). About 110 billion cubic metres of gas passed through the strait in 2025, most of it from Qatar. Adnoc is pursuing a 4 million tonne-a-year LNG export facility at Fujairah, fed by pipeline from Abu Dhabi. MEED has reported that it has selected three teams for front-end engineering and design work.

    Cost pressures

    The wider upstream picture is less encouraging for contractors. The IEA expects global upstream oil and gas investment to rise by about 1% to $550bn in 2026, with increases elsewhere largely offset by reductions in the Middle East. Its Upstream Capital Cost Index is forecast to rise by about 8% this year, which the agency says will raise the risk of overruns and delays.

    The agency also warns that a resolution of the crisis could create a buyers’ market for oil and gas. Lower prices would test whether the security case for bypass pipelines survives once the strait reopens.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21612651/main.jpg
    Colin Foreman
  • Riyadh gives bidders more time for aviation complex

    20 November 2026

     

    Contractors have been given an extension until 31 January to submit proposals for an estimated SR3bn ($817m) contract to build an aviation complex within the King Salman International airport master development in Riyadh.

    Government-owned aviation organisation Saudi Royal Aviation (SRA) tendered the contract in August, with an initial bid submission deadline of 8 October, which was later extended to 19 November.

    Phase one of the programme comprised the concept design stage, which the design consultant has completed.

    SRA is now seeking to deliver the second phase, covering design development, detailed design, procurement, construction, testing, commissioning and close-out of the works.

    The scope covers 30 landside buildings, including 16 screening areas and gates, plus 15 airside buildings, including four gates.

    The assets include maintenance hangars, workshops, office and administrative buildings (including interior fit-out), warehouses, storage, security and catering facilities, aprons and access roads, and site utilities and civil works.

    King Salman International airport will provide primary utilities to designated tie-in points, with the contractor taking responsibility from there.

    Although the site is within King Salman International airport’s boundaries, it is classified as landside and is a greenfield development. The contractor must therefore meet airport security, safety and access requirements, in addition to SRA’s own clearance processes.

    Project scale

    The King Salman International airport project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.

    The airport aims to accommodate up to 100 million passengers by 2030. The goal for cargo is to process 2 million tonnes a year by 2030.

    Saudi Arabia plans to invest significantly in its aviation sector. The Saudi Aviation Strategy, announced by the General Authority of Civil Aviation, aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.

    It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21611358/main.png
    Yasir Iqbal
  • Dar Global launches Trump project in Qatar

    20 November 2026

    London-listed developer Dar Global and The Trump Organisation have launched the QR2.5bn ($686m) Trump International Simaisma development in Qatar.

    The project combines beachfront residences, a golf course and lifestyle amenities, according to senior company officials speaking at a launch ceremony in Palm Beach, Florida.

    The residential element, Trump Residences, will comprise a gated community of three-, four- and five-bedroom branded villas. Each villa will have beach access and views of the sea and golf course.

    The development will also include the Trump International Golf Club, Simaisma, Qatar, anchored by an 18-hole championship golf course, a members-only clubhouse and a beach club.

    A private community centre will provide sports, recreation and wellness facilities for residents.

    The project forms part of Qatar’s wider Simaisma tourism development, launched by Qatar’s Ministry of Municipality in June 2024.

    The Simaisma project covers eight square kilometres and extends along seven kilometres of beachfront on Qatar’s eastern coast, north of Doha. It includes 16 tourism zones available for private sector development, with planned resorts, a theme park, an 18-hole golf course, residential villas, a yacht marina, restaurants and retail facilities.

    Qatari Diar Real Estate Investment Company is managing the wider development.

    The integrated tourism project supports the objectives of Qatar’s Third National Development Strategy 2024-30, which aims to increase the contribution of non-oil sectors to the economy.

    The launch extends the partnership between Dar Global and The Trump Organisation into Qatar.

    Dar Global develops luxury residential and hospitality projects across Europe and the Middle East.

    As of 30 June 2026, Dar Global’s portfolio had a total gross development value of $23bn, the company said.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21609076/main.jpeg
    Yasir Iqbal
  • Saipem wins Egypt offshore drilling contract

    20 November 2026

    Italy’s Saipem has been awarded an offshore drilling contract for three oil and gas wells in Egypt, according to a company statement.

    Burullus Gas Company, a joint venture of UK-based Shell, Malaysia’s Petronas and the state-owned Egyptian General Petroleum Corporation (EGPC), awarded the contract.

    The operations are scheduled to begin in the first quarter of 2027 and will use the semi-submersible unit Scarabeo 9.

    In the same statement, Saipem also said it had been awarded a separate contract by France’s TotalEnergies to drill in Suriname with the same semi-submersible unit, once the campaign in Egypt was completed.

    Saipem said the two contracts were worth approximately $181m in total.

    In its statement, the Italian company said: “These new awards bolster the backlog for Saipem’s offshore drilling fleet, ensuring operational continuity and greater visibility regarding the utilisation of the Scarabeo 9 throughout 2027 and 2028, while strengthening the long-standing partnerships with Burullus Gas Company and TotalEnergies.”

    Since the US and Israel attacked Iran on 28 February, sparking a regional conflict, there has been increased interest in oil and gas assets in North African countries such as Egypt.

    The ongoing conflict has made exporting oil and gas through the Strait of Hormuz and the Bab Al-Mandab Strait more difficult due to attacks on shipping.

    Unlike many Middle East nations, Egypt, Algeria and Libya do not need to use these export routes and can continue to ship oil and gas without disruption.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21597235/main.jpg
    Wil Crisp
  • Kuwait’s $7.7bn oil contract shift may reduce interest from bidders

    20 November 2026

    Analysis
    Wil Crisp
    Oil & gas reporter

    If the state-owned upstream operator Kuwait Oil Company (KOC) proceeds with its plan to retender four upstream project tenders worth an estimated $7.7bn under a different contract model, it could reduce interest from international bidders.

    On 19 November, MEED revealed that KOC is discussing relaunching the project tenders using the build-own-operate (BOO) contract model, where the contractor provides upfront funding for the project and then recoups its investment by operating the facility over the long term.

    Previously, the contracts were tendered using the engineering, procurement and construction (EPC) contract model, where the client funds the project and then takes ownership after it is brought online.

    This dramatic change in strategy would greatly reduce the upfront expenditure KOC would need to pay out, but it would also mean that many of the EPC specialists that submitted bids in the previous bidding round would no longer be interested in participating in the tender process.

    The four contracts that KOC is considering relaunching with the BOO model are:

    • Separation Gathering Centre 1 (SGC-I) and Water Injection Plant (WIP-1)
      Previous low bidder: Tecnicas Reunidas (Spain) – $2.47bn
    • Separation Gathering Centre 3 (SGC-3) and Water Injection Plant (WIP-3)
      Previous low bidder: Larsen & Toubro (India) – $2.48bn
    • Installation of Water Injection Plant (WIP-4)
      Previous low bidder: Petrofac (UK) – $1.48bn
    • Effluent Water Disposal Plants 1 & 2 expansion project (EWDP 1&2)
      Previous low bidder: Larsen & Toubro (India) – $1.30bn

    Many industry insiders believe India’s Larsen & Toubro, the low bidder for two contracts in the previous tender process, would no longer be interested in bidding if the contracts are tendered under the BOO model.

    One source said: “Investing in upstream facilities in Kuwait and then operating them over the long term is not part of Larsen & Toubro’s strategy, so I don’t think they would participate in a tender where the contract uses the BOO model.”

    Sources believe that Italy’s Saipem, as well as the South Korean contractors Samsung E&A and Hyundai E&C, would also not be interested in bidding for the project if it was tendered as a BOO.

    One source said: “If KOC goes ahead with this plan to tender these projects using the BOO model, there is a risk that there will be far fewer companies that want to submit bids.”

    While many previous bidders may not compete for the contracts if KOC goes ahead with its BOO plans, some other companies may see the new model as a profitable opportunity.

    Companies that could potentially be interested in participating in the tenders include Kuwait’s Spetco, China’s Jereh Oil & Gas Engineering and India’s Megha Engineering & Infrastructures (Meil).

    Before proceeding with the possible relaunch of the four contracts, KOC is likely to hold informal talks with potential bidders to gauge interest in the BOO model.

    If industry interest proves insufficient, the shift risks triggering further project delays while KOC reassesses its procurement strategy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21597044/main.jpg
    Wil Crisp