Oil and gas contractors feel interest rate pinch

24 February 2023

Commentary

Wil Crisp

Oil & gas reporter

Rising interest rates are eating into the profits of some contractors developing oil and gas projects in the Middle East and North Africa (Mena) region and are likely to force them to put up prices for clients.

Although contingent upon the agreed financing arrangements, higher interest rates will likely leave many contractors paying more to borrow the money they spend on project execution.

This month, the central banks of the UAE, Saudi Arabia and Bahrain raised their benchmark borrowing rates after the US Federal Reserve raised its key interest rate in its first policy decision of the year on 1 February.

GCC currencies, except for that of Kuwait, are pegged to the US dollar and therefore follow US monetary policy.

The Fed increased its policy rate by 25 basis points as it continued to push to bring inflation down towards its target range of 2 per cent and restore price stability.

This was the eighth rate increase since the US central bank started raising rates in March last year and pushed rates in the US to their highest since the 2008 financial crisis.

Rising interest rates have raised costs significantly for some contractors executing projects in the Mena region, dramatically reducing profit margins.

Contractors that have taken out loans to execute projects using a build-operate-transfer (BOT) contract model are among those hardest hit.

Under a BOT contract, a public entity grants a concession to a company to finance, build and operate a project.

The company usually deploys debt and equity upfront to build the project and then operates it over the long term to recoup its investment. It then transfers control of the project back to the public entity.

Because the company only usually starts paying off its loan gradually once the project is completed and the facility is operational, it can take many years to pay back. The higher interest rates are likely to significantly impact the contractor’s profits.

Contractors that have taken a loan to execute a project using the engineering, procurement and construction (EPC) contract model are also likely to be negatively impacted by higher interest rates, but to a lesser extent.

This is because EPC contractors are usually fully paid for their work when the project is completed, allowing them to pay off their loan far more quickly than if a BOT contract model has been used.

The additional costs associated with higher rates are likely to be especially problematic for contractors wrestling with supply chain issues and higher material costs due to inflation.

For clients looking to tender major oil and gas projects, the higher interest rates could mean a project may see less enthusiasm from contractors if it tenders a contract using the BOT model.

If they use this model, they can also expect to see higher prices quoted as contractors try to pass on the cost of higher interest rates.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10621486/main.jpg
Wil Crisp
Related Articles
  • Consultants submit bids for Saudi Arabia’s GCC rail link

    20 July 2026

     

    Consultants submitted proposals on 14 July for a contract to provide design consultancy services for the Saudi Arabian section of the GCC railway network, which is intended to link all six member states.

    Saudi Arabia Railways (SAR) issued the tender on 7 May, MEED previously reported.

    The tender covers the concept, preliminary and issued for construction design stages. SAR requires the selected consultant to review, update and complete the existing preliminary design.

    The consultants who submitted bids include: 

    • Atkins with Khatib & Alami
    • DeutscheBahn with ARX
    • Egis with Sener
    • Idom with Dal al-Handasah
    • Systra

    Saudi Arabia’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, on Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).

    The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Turkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.

    The KNRR forms part of the wider GCC rail network. GCC railway projects have gained renewed momentum since the six member states signed the Al-Ula Declaration in January 2021.

    In October last year, Qatar’s cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to span about 2,186km in total.

    The route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220km/h and freight trains operating at 80-120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705320/main.gif
    Yasir Iqbal
  • Chinese firm wins Dubai drainage contract

    20 July 2026

    China State Construction Engineering Corporation (CSCEC) has announced it has won a contract to deliver a stormwater drainage pipeline package under Dubai Municipality’s Tasreef programme.

    The contract is for the TF-15-C2 stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai. 

    MEED exclusively revealed in May that the contractor had been selected for the engineering, procurement and construction (EPC) contract. The project is estimated to cost $162m.

    The scope of work includes the construction of about 20 kilometres of new stormwater pipelines, together with associated inspection and intake manholes. The project is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    It is being delivered as part of Dubai’s Tasreef strategic plan, which supports the Dubai 2040 Urban Master Plan. Once completed, the new drainage infrastructure is expected to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.

    In February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.

    These include a separate contract awarded to CSCEC for the TF-11-C1 stormwater drainage project in the Dubailand area.

    Also in February, Dubai Municipality invited consultants to qualify for a contract to supervise construction on the TF-15-C2 stormwater drainage projects along with two other projects (TF-13-C1 and TF-16-C1) under the Tasreef programme.

    According to a source, a consultant has yet to be appointed.

    TF-16-C1 involves upgrading and rehabilitating the stormwater system east of the Dubai Canal, while TF-13-C1 involves building a water pipeline stormwater drainage system at Al-Marmoum, Al-Qudra and Al-Yalayis 2 & 3.

    Bids are currently under evaluation for the EPC contracts for both projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705058/main.jpg
    Mark Dowdall
  • Dubai receives eight bids for Hassyan SWRO pipeline contract

    20 July 2026

    Register for MEED’s 14-day trial access 

    Eight contractors have made offers for a contract to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the Hassyan seawater reverse osmosis (SWRO) phase two network in Dubai.

    The contract relates to project one of the Hassyan pipeline network expansion being undertaken by state utility Dubai Electricity & Water Authority (Dewa).

    Local firm Binladin Contracting Group submitted the lowest offer of AED335.92m ($91.5m), according to results published by the utility.

    The other bids were:

    • Green Oasis General Contracting (UAE) – AED345.00m ($93.9m)
    • Al-Nasr Contracting (UAE) – AED391.54m ($106.6m)
    • Wade Adams Contracting (UAE) – AED393.80m ($107.2m)
    • RMB Contracting (UAE) – AED437.96m ($119.3m) 
    • Tristar Engineering & Construction (UAE) – AED441.55m ($120.2m)
    • Shapoorji Pallonji Mideast (UAE/India) – AED451.47m ($122.9m)
    • Gulf Petrochemical Services Trading (UAE) – AED495.20m ($134.8m)

    RMB also submitted a conditional discounted offer of AED427.02m ($116.3m). Three companies submitted regret notices, while one offer was rejected after no valid commercial offer was received. 

    In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.

    Dewa has two other contracts out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.

    Project two was tendered on 22 January and has a bid submission deadline of 21 July. Project three was tendered on 26 January and has a bid submission deadline of 29 July.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704940/main.jpg
    Mark Dowdall
  • Abu Dhabi launches E20 highway expansion project

    20 July 2026

    Abu Dhabi’s Department of Municipalities and Transport (DMT) has announced the E20 highway expansion project.

    The scheme covers widening the main carriageway from three to five lanes, constructing more than 10 kilometres (km) of new ramps and loops, and building four bridges.

    Works also include 1.5km of internal roads and the addition of eight signalised junctions across Khalifa City and the Zayed International airport precinct.

    The project includes utility works, comprising 62km of stormwater drainage, 37km of irrigation networks and the installation of 485 streetlights.

    The E20 expansion is one of the major infrastructure schemes being overseen by DMT in Abu Dhabi.

    Separately, DMT is evaluating bids for a design-and-build contract to construct two bridges serving Hudayriyat Island in Abu Dhabi.

    The scope includes a two-lane bridge connecting 32nd Street to Shakhbout Bin Sultan Street, and a single-lane bridge on 8th Street. It also includes upgrades to signalised intersections.

    Shakhbout Bin Sultan Street is a two-way road with three lanes in each direction, providing access to and from Hudayriyat Island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704696/main.jpg
    Yasir Iqbal
  • Firms given more time for Mid Island Parkway prequalifications

    20 July 2026

     

    Abu Dhabi’s Modon Infrastructure has extended the deadline to 31 July for firms to submit expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership (PPP).

    The previous deadline was 15 July. MEED understands the prequalification notice was issued in June, following Modon Infrastructure’s invitation in May for firms to register their interest.

    Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.

    Phase two of the MIPP involves the construction of about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.

    The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.

    Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704765/main.jpg
    Yasir Iqbal