Oil and gas contractors feel interest rate pinch

24 February 2023

Commentary

Wil Crisp

Oil & gas reporter

Rising interest rates are eating into the profits of some contractors developing oil and gas projects in the Middle East and North Africa (Mena) region and are likely to force them to put up prices for clients.

Although contingent upon the agreed financing arrangements, higher interest rates will likely leave many contractors paying more to borrow the money they spend on project execution.

This month, the central banks of the UAE, Saudi Arabia and Bahrain raised their benchmark borrowing rates after the US Federal Reserve raised its key interest rate in its first policy decision of the year on 1 February.

GCC currencies, except for that of Kuwait, are pegged to the US dollar and therefore follow US monetary policy.

The Fed increased its policy rate by 25 basis points as it continued to push to bring inflation down towards its target range of 2 per cent and restore price stability.

This was the eighth rate increase since the US central bank started raising rates in March last year and pushed rates in the US to their highest since the 2008 financial crisis.

Rising interest rates have raised costs significantly for some contractors executing projects in the Mena region, dramatically reducing profit margins.

Contractors that have taken out loans to execute projects using a build-operate-transfer (BOT) contract model are among those hardest hit.

Under a BOT contract, a public entity grants a concession to a company to finance, build and operate a project.

The company usually deploys debt and equity upfront to build the project and then operates it over the long term to recoup its investment. It then transfers control of the project back to the public entity.

Because the company only usually starts paying off its loan gradually once the project is completed and the facility is operational, it can take many years to pay back. The higher interest rates are likely to significantly impact the contractor’s profits.

Contractors that have taken a loan to execute a project using the engineering, procurement and construction (EPC) contract model are also likely to be negatively impacted by higher interest rates, but to a lesser extent.

This is because EPC contractors are usually fully paid for their work when the project is completed, allowing them to pay off their loan far more quickly than if a BOT contract model has been used.

The additional costs associated with higher rates are likely to be especially problematic for contractors wrestling with supply chain issues and higher material costs due to inflation.

For clients looking to tender major oil and gas projects, the higher interest rates could mean a project may see less enthusiasm from contractors if it tenders a contract using the BOT model.

If they use this model, they can also expect to see higher prices quoted as contractors try to pass on the cost of higher interest rates.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10621486/main.jpg
Wil Crisp
Related Articles
  • Fuel storage facility attacked in Bahrain

    13 March 2026

    Register for MEED’s 14-day trial access 

    Fuel storage tanks at a facility on Bahrain’s Muharraq Island were targeted in an attack attributed to Iran, according to a statement from Bahrain’s Interior Ministry.

    The ministry put out an alert for people in surrounding neighbourhoods “to remain in their homes, close windows and ventilation openings, as a precautionary measure against possible exposure to smoke”.

    Videos of the incident, which took place on 12 March, showed a large fire emitting black smoke. The fire was later extinguished by teams of firefighters.

    Bahrain’s international airport is also located on Muharraq Island.

    Iran has been firing missiles at a range of targets in nearby countries since it was attacked by the US and Israel on 28 February.

    On 11 March, a similar attack on fuel storage tanks in Oman led to the closure of some terminals at the port of Salalah.

    Footage recorded by vessel crews at the port, which is the largest in the country, showed explosions and a large fire.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15963333/main.png
    Wil Crisp
  • Bahrain contacts engineering companies over Sitra refinery damage

    13 March 2026

    Register for MEED’s 14-day trial access 

    Bahrain’s national oil and gas company Bapco Energies is in touch with international engineering companies about damage done to the Sitra refinery by Iranian strikes, according to industry sources.

    In a statement on 9 March, Bapco Energies said its decision to issue the force majeure notice followed “the recent attack on its refinery complex”, without providing details.

    Bapco Energies is yet to share full details about the extent of the damage caused to the refinery, sources said.

    One source said: “Bapco has been corresponding with several companies with regard to the damage. It is being careful not to share confidential information, but it has reached out.”

    Prior to Bapco’s 9 March statement, the Sitra refinery was hit by a strike earlier in the day.

    That strike on the Sitra refinery was the second strike on the complex in days.

    Iranian missiles hit the facility on 5 March, resulting in parts of the refinery being engulfed in flames.

    Iran has been firing missiles at a range of targets in nearby countries since it was attacked by the US and Israel on 28 February.

    In November last year, MEED reported that Bapco Energies was in the final stages of ramping up volumes processed by new units that were installed as part of the Bapco Modernisation Programme (BMP).

    The project at the Sitra refinery in Bahrain is estimated to have been worth $7bn and was inaugurated by Bahrain’s King Hamad Bin Isa Al-Khalifa in December 2024.

    At the time, the companies involved in the engineering, procurement and construction (EPC) contract for the project were still working on the site to assist with efforts to increase volumes.

    Bapco Energies awarded the main $4.2bn contract to perform EPC works on the BMP to a consortium led by France’s Technip Energies in February 2018.

    The consortium also included Spain’s Tecnicas Reunidas and South Korea’s Samsung E&A.

    Technip Energies also performed the project’s front-end engineering and design work. US oil and gas producer Chevron acted as a consultant on the BMP, while Australia-based Worley was the project management consultant.

    In March 2024, after a series of setbacks and delays, France’s Total Energies was brought in to support Bapco in “optimising” the project.

    The BMP is central to Bahrain’s Vision 2030 economic development strategy, and Bapco has said that it is crucial to boosting the country’s long-term downstream potential.

    The BMP was originally expected to reach mechanical completion in 2023, with operations set to begin in 2024.

    The core objective of the BMP was to upgrade the Sitra refinery – Bahrain’s only oil refining asset, which is 90 years old.

    One of the key units to be built as part of the BMP was a residual hydrocracking unit (RHCU) powered by technology licensed from US-based Chevron Lummus Global. The BMP team has built a two-train RHCU with a capacity of 65,000 barrels a day.

    The Sitra refinery includes seven crude distillation units (CDUs) and vacuum distillation units (VDUs) as part of the BMP.

    The new 225,000 b/d integrated crude and vacuum unit replaced CDUs 1, 2 and 3 and VDUs 1 and 3, which had served Bapco Energies for over 80 years.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15963329/main.jpg
    Wil Crisp
  • Italian consultant wins Egypt battery storage contract

    13 March 2026

    Italy-headquartered consultancy Rina has announced its appointment as owner’s engineer for the 1 gigawatt-hour Nefertiti battery energy storage system (bess) project in Egypt.

    The project is being developed by Dubai-based firm Amea Power and is located in the Benban Photovoltaic Industrial Park in Aswan.

    The scheme will deploy a 500MW/1,000 megawatt-hour (MWh) utility-scale bess, making it the largest independent energy storage project in Africa.

    In March, a group comprising China Energy Engineering International Group, Zhejiang Thermal Power Construction and Southwest Electric Power Design & Research Institute was appointed as the main engineering, procurement and construction contractor.

    The $250m project also includes the construction of a 220kV substation, upgrades to an adjacent substation and development of grid network connection infrastructure.

    Under the owner’s engineer scope, Rina will deliver engineering design review, construction monitoring and commissioning support. The company will also undertake performance verification.

    Egypt’s utilities sector had its strongest year in over a decade in 2025, hitting $5bn in contract awards for the first time since 2015. 

    Last July, Amea Power commissioned Egypt’s first-ever utility-scale bess.

    The 300MWh project had previously reached financial close in June.

    The bess project is an extension of Amea Power’s operational 500MW solar photovoltaic plant in Aswan Governorate, which was commissioned in December 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15954234/main.jpg
    Mark Dowdall
  • Oil tankers attacked in Iraqi waters

    12 March 2026

    Register for MEED’s 14-day trial access 

    Two tankers carrying Iraqi oil products were set on fire after being attacked in Iraq’s territorial waters near the country’s southern export terminals, increasing concerns about global energy supplies.

    After the attack, the country’s Oil Ministry said that it saw the attacks as “a worrying indicator of escalating tensions in a vital area of the global economy and energy supply”.

    It added that “the safety and safety of navigation in international sea corridors and energy supply routes should be kept away from regional conflicts”.

    The Oil Ministry said the attacks had a direct impact on the stability of the global economy and energy markets, as well as putting the lives of civilians and workers in the maritime transport sector at risk.

    Farhan Al-Fartousi, from Iraq’s General Company for Ports, told state television that one crew member had been killed in the attack and that 38 crew members had been rescued.

    Iraq’s state-owned oil marketing company Somo said that the Maltese-flagged oil tanker Zefyros was attacked as it was preparing to enter the port of Khor Al-Zoubair, where it would have taken on board an additional 30,000 tonnes of liquid naphtha.

    The second targeted vessel, Safesea Vishnu, was sailing under the Marshall Islands flag and was chartered by an Iraqi company, according to Somo.

    Iraq’s oil production has fallen steeply since the conflict began, from 3.3 million barrels a day (b/d) to less than 1 million b/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15951323/main.png
    Wil Crisp
  • Chevron yet to agree terms for Iraq oil field takeover

    12 March 2026

     

    US-based oil company Chevron is yet to agree terms with Iraqi state-owned Basra Oil Company (BOC) for its potential takeover of Iraq’s West Qurna-2 oil field, according to industry sources.

    Last month, Chevron signed a preliminary agreement with BOC to explore taking control of the West Qurna-2 oil field.

    Until recently, West Qurna-2 was operated by Russia’s Lukoil, which faces a 28 February deadline to divest its assets in Iraq under sanctions.

    One industry source said: “Chevron is yet to agree terms, and it has made it clear that it wants different terms to the contract that Lukoil had.”

    In January, Iraq’s cabinet approved temporarily nationalising petroleum operations at the West Qurna-2 oil field until a new operator was found.

    Lukoil declared force majeure at the West Qurna-2 oil field in November, after sanctions by the UK, EU and US were announced in October.

    The Russian company had a 75% stake in the asset.      

    Prior to Russia’s Lukoil declaring force majeure, Iraq’s state oil authorities froze all cash and crude payments to Lukoil in compliance with the sanctions.

    In a statement released on 1 December 2025, Iraq’s Oil Ministry said that it had extended “direct and exclusive invitations to a number of major American oil companies”.

    Awarded to Lukoil in 2009, West Qurna-2 lies about 65 kilometres northwest of Basra in southern Iraq and produces about 480,000 barrels a day (b/d) of oil, accounting for roughly 10% of the country’s total oil output.

    At the same meeting on 23 February, Chevron also signed a deal relating to the development of the Nasiriyah field, four exploration sites in the province of Dhi Qar and a field in the province of Salahaddin.

    Chevron signed an agreement in principle with Iraq in August 2025 to develop the Nasiriyah oil project in the province of Dhi Qar.

    At the time, Iraq said it expected the Nasiriyah project to reach a production capacity of 600,000 b/d within seven years.


    READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

    Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

    Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15944830/main.png
    Wil Crisp