Rethinking how Saudi projects are delivered

25 January 2024

 

In early January, Italian contractor WeBuild secured a $4.7bn contract to construct the three dams that will create a lake at the centre of Saudi Arabia’s Trojena mountain resort in Neom. 

Like most in the kingdom, the project is large in scale and technically challenging. It also has an aggressive delivery schedule as the lake – and the surrounding resort and ski slopes – must be ready for the Asian Winter Games in 2029. 

The project will also have to be completed at the same time as the rest of the growing volume of construction work in the kingdom. According to regional projects tracker MEED Projects, there were close to $95bn of contract awards across all sectors in the kingdom in 2023 – an all-time record and significantly higher than the $59bn recorded the previous year.

For construction specifically, there were $23bn-worth of awards made in 2023, which is marginally less than the total for 2022. With this level of awards expected to be maintained or exceeded in 2024, the challenges facing the kingdom’s construction sector will be amplified this year.

New approach

The development firms that have been tasked with delivering Riyadh’s five official gigaprojects – and the raft of other large masterplanned projects – are rethinking how projects in the kingdom are delivered.

The first area of concern is procurement, and securing sufficient resources to complete projects. 

In the case of the Trojena dams, this was done by engaging with a group of construction firms on an early contractor involvement (ECI) basis. Contractors took part in a two-stage tender, with bidders submitting preliminary prices and then working with the client to arrive at a final price for the project. 

By working on the project at an early stage, contractors have a better understanding of the work involved and are more likely to bid. 

Neom is not the only giga- project developer using this approach. Last year, Qiddiya Investment Company appointed UAE-based Alec to build the motorsports Speed Park at its entertainment city project on the outskirts of Riyadh. 

Qiddiya is also engaging with contractors on an ECI basis for its Prince Mohammed bin Salman Stadium, which features a complex design that will be built on top of a 200-metre cliff.

Other steps that have been taken to make projects in Saudi Arabia more attractive include better payment terms and an overhaul of the use of performance guarantees. 

Red Sea Global (RSG), which is developing the Red Sea Project and Amaala gigaprojects, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention.

By working on the project at an early stage, contractors have a better understanding of the work involved

Packaging projects

Projects are also being packaged differently. For the Trojena dams, the work was packaged as a large infrastructure project. This route also appears to be the favoured solution for other developers undertaking large-scale infrastructure projects. 

For building work, there are several approaches. RSG created much noise in the market when it decided to adopt a construction management approach for its projects. This meant breaking the project down into a series of smaller packages, which are then managed by an in-house construction management team. 

The aim of this approach is to give the developer more control over the project. It also helps to overcome some of the deficiencies of the market that have existed for main contractors in the kingdom for the past decade. 

Other clients are taking a different approach. In recent months, clients such as Diriyah Company and Rua al-Madinah have tendered contracts for constructing superblocks, which include the construction of a district within a development that comprises several buildings. This approach aims to offer contracts to major local, regional and international construction firms with enough scale for them to invest in the project. 

The superblock approach was used in previous eras of Saudi construction when major firms – led by Saudi Binladin Group and Saudi Oger – would regularly take on large work packages. 

Phasing is another way that the pressure in the market can be alleviated. Last year, executives of Saudi development companies spoke privately about the need for project priorities to be set so that they can focus on specific objectives. 

At the end of last year, that notion was given more weight when Finance Minister Mohammed al-Jadaan told reporters at the launch of the state budget that Saudi Arabia needs more time to deliver its projects. 

“A longer period is needed to build factories, build even sufficient human resources. The delay or rather the extension of some projects will serve the economy,” he said, adding: “There are strategies that have been postponed and there are strategies that will be financed after 2030.” 

As the minister did not give specifics, it is not clear which projects will be delayed and which will remain on their original schedule. That said, projects with event-driven deadlines – such as the 2027 Asian Cup, the 2029 Asian Winter Games, Expo 2030 and the 2034 World Cup – will have to be delivered on time.


This package also includes:

> LEADERSHIP: DHB Holding CEO Omar Delawar on constructing a sustainable future
> INTERVIEW: Gensler co-CEO Andy Cohen on how the buildings and cities of the future can achieve net zero


https://image.digitalinsightresearch.in/uploads/NewsArticle/11463808/main.gif
Colin Foreman
Related Articles
  • Sumitomo team submits Facility E bid

    25 July 2024

    A team led by Japan's Sumitomo Corporation submitted a bid for the contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    Qatar state utility General Electricity & Water Corporation (Kahramaa) previously extended the tender closing date for the contract in response to developers’ requests, as MEED reported.

    Kahramaa received the single bid on 25 July.

    Sumitomo is understood to have submitted a proposal for the contract along with fellow Japanese utility developer Shikoku Electric, and Seoul-headquartered Korea Overseas Infrastructure & Urban Development Corporation and Korea Southern Power Company.

    The developer consortium's engineering, procurement and consortium (EPC) partner is South Korea's Samsung C&T, according to sources close to the project.   

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day (MIGD).

    The contract to develop the Facility E IWPP was first tendered in 2019. The three teams that submitted bids for the contract in August 2020 were:   

    • Engie (France) / Mitsui (Japan) / Yonden (Shikoku Electric, Japan)
    • Sumitomo / Kansai Electric (Japan)
    • Marubeni / Kyushu Electric (Japan)

    The original plan was for Facility E IWPP to have a power generation capacity of about 2,300MW and a desalination component of 100MIGD once fully operational.

    However, Kahramaa revised the power plant’s design capacity to 2,600MW and sought alternative prices from bidders. 

    Kahramaa eventually cancelled and reissued the tender in September 2023. The current tender entails a power generation plant with the same capacity as initially tendered in 2019.

    MEED understands that the new target commercial operation date for the Facility E IWPP project has been moved to 2027. 

    The state utility’s transaction advisory team includes UK-headquartered PwC and Clyde & Co as financial and legal advisers, respectively, led by Belgrade-headquartered Energoprojekt as technical adviser.

    Facility E is Qatar’s fifth IWPP scheme. Completed and operational IWPPs include three projects in Ras Laffan – known as Facilities A, B and C – and Facility D in Umm Al-Houl.

    Awarded in 2015 and completed in 2018, Facility D was developed by a Japanese consortium of Mitsubishi Corporation and Tokyo Electric Power Company (Tepco). South Korea's Samsung C&T was the engineering, procurement and construction contractor.  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12220438/main.gif
    Jennifer Aguinaldo
  • Iraq drives Gulf projects market growth

    25 July 2024

     

    The Gulf Projects Index rose by 0.7% from 7 June to 12 July, spurred by value gain in the Iraq projects market and, to a lesser extent, the UAE projects market, while the Saudi projects market experienced a slight contraction.

    The rise in the index represents the 16th consecutive month of upward trending value in the regional projects market, dating back to March 2023.

    Iraq rail plans

    The Iraqi projects market gained $26.3bn in value, or 7%, due to the reactivation of plans for a national network of high-speed rail connections across the country, from north to south as well as east to west. The costs of these Iraq rail schemes, which have been under study in various forms for several decades, are relatively indeterminate, but run into the tens of billions of dollars. The rail network is now in the design phase.

    In another major development for the country, the $27bn Gas Growth Integrated Project (GGIP) being undertaken by the National Oil Company and Basra Oil Company, in partnership with TotalEnergies and QatarEnergy, has also passed from study into front-end engineering and design.

    Elsewhere in the region, the UAE projects markets increased in value by $10.6bn, or 1.3%, while Saudi Arabia’s projects market shrank by a comparable $13.9bn, though lesser 0.7%, reducing its value to around about the value it held
    in mid-May.

    The other countries in the GCC and wider Gulf saw comparatively minor changes, with Qatar’s projects market adding $3.9bn or 1.7%, Bahrain’s projects market adding $2bn or 2.9%, Iran’s projects market adding $1.4bn or 0.5%, and Oman’s projects market adding a marginal $0.2bn or 0.1%. Kuwait’s project market value slipped by $0.7bn or 0.4%.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219885/main.gif
    John Bambridge
  • Abu Dhabi tenders 400MW battery storage contract

    25 July 2024

    State offtaker Emirates Water & Electricity Company (Ewec) has invited prequalified companies to submit their proposals for a contract to develop and operate an independent 400MW battery energy storage system (bess) power project in Abu Dhabi.

    Ewec expects to receive bids by the fourth quarter of 2024.

    The planned facility is expected to provide up to 800 megawatt-hours (MWh) of storage capacity.

    Called Bess 1, the project will closely follow the model of Ewec's independent power project (IPP) programme, in which developers enter into a long-term energy storage agreement (ESA) with Ewec as the sole procurer.

    The first plant will be in Al-Bihouth, approximately 45 kilometres (km) southwest of Abu Dhabi, and the second plant will be in Madinat Zayed, about 160km southwest of the city.  

    According to Ewec, the request for proposals is being issued to 27 prequalified companies and consortiums, out of the 93 companies that submitted an expression of interest to bid for the contract in April this year.

    It did not specify the prequalified companies.

     MEED previously reported that the companies that submitted SOQs to bid for the contract include:

    • Acwa Power (Saudi Arabia)
    • EDF (France)
    • GE (US)
    • Jera (Japan)
    • Korea Electric Power Corporation (Kepco, South Korea)
    • Marubeni Corporation (Japan)
    • Samsung C&T (South Korea)

    Sources also cited that "several Chinese Bess manufacturers and suppliers" have applied to prequalify as investors in the project.

    The ESA will be for 15 years, commencing on the project's commercial operation date, which falls in the third quarter of 2026. 

    According to Ewec, the Bess project will provide additional flexibility to the system and ancillary services such as frequency response and voltage regulation.

    "Ewec is deploying BESS to enhance the flexibility and stability of Abu Dhabi’s energy network, allowing for the effective management of peak demand and integration of increasing amounts of renewable energy," the utility said in a media statement on 25 July.

    It added: "BESS technology will also provide crucial ancillary services such as frequency response and voltage regulation, further reinforcing the security of supply and supporting Ewec to increase its solar photovoltaic (PV) capacity to 7.5 gigawatts (GW) by 2030.

    "This accelerated growth in renewables will significantly reduce the carbon dioxide intensity of Ewec's power supply, from 330 kilograms per megawatt hour (kg/MWh) in 2019 to an estimated 190 kg/MWh by 2030."

    Global BESS market

    The overall capacity of deployed Bess globally is expected to reach 127GW by 2027, up from an estimated cumulative deployment of 36.7GW at the end of 2023, according to a recent GlobalData report.

    The report cited Chinese companies BYD and CATL and South Korean companies LG Energy Solutions and Samsung SDI among the top battery technology providers globally.

    Related read: Abu Dhabi tenders 2.5GW Taweelah C contract

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219884/main.gif
    Jennifer Aguinaldo
  • Transforming Riyadh into a world-class city

    25 July 2024

     

    Riyadh is changing fast. As the Saudi capital, it is not only located in the country’s geographical centre, but also at the heart of Vision 2030 and the kingdom’s economic transformation, with a wide range of ambitious development projects.

    The city wants to be one of the best in the world. “The strategic vision for Riyadh focuses on transforming it into a world-class city that is sustainable, innovative and culturally rich,” says Fahad AlSolaie, deputy mayor for digital transformation and smart cities at Riyadh Region Municipality. 

    “The vision includes improving quality of life for residents, diversifying the economy away from oil dependence, and promoting green and smart urban development.”

    Riyadh’s ambitions are driven by population growth and people visiting the city for major global events. “Riyadh is expected to experience significant population growth in the coming years, driven by its economic expansion and global events hosted by the kingdom, such as Expo 2030 and major sports events,” says AlSolaie.

    “Additionally, the presence of large-scale unique projects like the King Abdullah Global Gardens, the development of Wadi Al-Sulay, King Salman Park and others contribute to the city’s attractiveness and livability, further boosting population growth. It is targeted for the population of Riyadh to reach 10 million residents, reflecting its rising prominence as a business and cultural hub. This growth will enhance Riyadh’s status as a dynamic urban centre, equipped to meet the evolving needs of its expanding population.”

    The vision includes improving quality of life, diversifying the economy, and promoting green and smart urban development
    Fahad AlSolaie, Riyadh Region Municipality

    Infrastructure projects

    Riyadh Region Municipality is playing a key role in the city’s development. “Riyadh municipality is responsible for a wide array of infrastructure projects that are crucial for the city’s development and sustainability. These include paving, asphalting and road stabilisation projects, which are essential for maintaining and improving the city’s road networks,” says AlSolaie.

    “The municipality develops public parks, ensuring that the necessary infrastructure is in place to provide recreational spaces. Bridge and tunnel construction and ongoing enhancements are also a significant focus, aimed at improving traffic flow and connectivity across the city. Furthermore, Riyadh is committed to extensive lighting projects and the maintenance of these systems, with the city one of the largest globally in terms of the number of streetlight poles.” 

    A key responsibility of the municipality is to maintain the city’s cleanliness and environmental health, adds AlSolaie. “This involves regular street cleaning, waste management and pollution control measures to keep the city clean and environmentally sustainable. These efforts are integral to quality of life, contributing to the vision of making Riyadh a more livable and accessible urban environment.”

    Signature schemes

    The municipality is also involved in the delivery of a series of signature projects in and around Riyadh. “The King Abdullah Global Gardens project aims to create a vast green space that combines natural landscapes with high-tech interactive exhibits, promoting environmental education and sustainability,” says AlSolaie. 

    The Wadi Al-Sulay development, meanwhile, is focused on transforming Wadi Al-Sulay into a recreational and cultural destination, featuring amenities that encourage outdoor activities and community gatherings.

    The municipality collaborates extensively with other government agencies and private sector partners to ensure cohesive and integrated development. This includes coordinating efforts on large-scale projects, urban planning and infrastructure improvements to support the city’s growth.

    “The municipality ensures alignment with master developers and major projects through regulatory frameworks, strategic planning sessions and collaborative platforms that facilitate integration of infrastructure projects and urban development efforts across the city,” says AlSolaie.

    With aspirations to become one of the world’s most advanced cities, digital transformation is helping Riyadh achieve its goals. “Digital transformation is vital for Riyadh Municipality for several compelling reasons. Firstly, it enhances service efficiency by adopting digital technologies, streamlining operations, reducing manual processes, minimising errors and speeding up response times. This not only improves service delivery, but also cuts operational costs, allowing for better resource allocation. 

    “Secondly, it improves citizen engagement through digital platforms that enable interactive and responsive communication. Citizens can easily access information, request services and provide feedback, enhancing transparency and building trust.

    “Thirdly, digital transformation fosters innovation in urban management using technologies such as the Internet of Things , artificial intelligence and big data analytics to optimise urban functionalities like smart waste monitor manholes and public safety. 

    “Additionally, it supports economic diversification by modernising infrastructure and services, thus attracting new businesses, especially in the technology sector, aligning with Saudi Arabia’s Vision 2030,” says AlSolaie.

    Online services

    Riyadh Region Municipality is moving its services online as part of the digital transformation. “Riyadh municipality is progressively digitising its services by offering e-services platforms where residents can access various municipal services such as mobile applications, geoportal web application and service requests online, thus increasing accessibility and convenience,” says AlSolaie. 

    The drive to digitise will enable Riyadh to become a smart city. “By implementing advanced technologies such as the Internet of Things, artificial intelligence and geographic information systems, Riyadh Municipality is optimising key city functions such as reducing and monitoring visual pollution, enhancing public safety and conducting environmental monitoring,” he says. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219710/main.gif
    Colin Foreman
  • WTTCO tenders water pipeline and reservoir packages

    25 July 2024

    State-owned Saudi water transmission and storage operator Water Transmission & Technologies Company (WTTCO) has issued two tenders involving a contract to build a water transmission pipeline in Dammam City and an engineering design services contract for water reservoir stations.

    The first contract is for the supply and installation of a water transmission system for the Second Industrial City in Dammam.

    WTTCO expects to receive proposals for this contract by 1 August.

    The second request for proposals involves a contract to provide engineering and design services for phases 2 and 3 of WTTCO’s strategic water reservoir station projects.

    The two phases cover reservoir stations in 150 locations and about 750 kilometres of water transmission pipeline.

    WTTCO expects to receive proposals from engineering consultancy firms for this contract by 4 August.

    The company has embarked on one of the world’s largest water conveyance and storage programmes as it seeks to increase potable water supply capacity across the kingdom.

    The expenditure programme, which WTTCO estimates is worth up to SR140bn ($38bn) by 2030, covers 396 individual projects, MEED reported in May.

    WTTCO’s objectives by 2027 are to have a total network size of 15,000km, 9.5 million cubic-metres-a-day transmission capacity, 118 pumping stations and more than 900 storage tanks.

    The capital expenditure programme was outlined in a WTTCO presentation at the Future Projects Forum in Riyadh on 20 May.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12219515/main.jpg
    Jennifer Aguinaldo