Rethinking how Saudi projects are delivered
25 January 2024

In early January, Italian contractor WeBuild secured a $4.7bn contract to construct the three dams that will create a lake at the centre of Saudi Arabia’s Trojena mountain resort in Neom.
Like most in the kingdom, the project is large in scale and technically challenging. It also has an aggressive delivery schedule as the lake – and the surrounding resort and ski slopes – must be ready for the Asian Winter Games in 2029.
The project will also have to be completed at the same time as the rest of the growing volume of construction work in the kingdom. According to regional projects tracker MEED Projects, there were close to $95bn of contract awards across all sectors in the kingdom in 2023 – an all-time record and significantly higher than the $59bn recorded the previous year.
For construction specifically, there were $23bn-worth of awards made in 2023, which is marginally less than the total for 2022. With this level of awards expected to be maintained or exceeded in 2024, the challenges facing the kingdom’s construction sector will be amplified this year.
New approach
The development firms that have been tasked with delivering Riyadh’s five official gigaprojects – and the raft of other large masterplanned projects – are rethinking how projects in the kingdom are delivered.
The first area of concern is procurement, and securing sufficient resources to complete projects.
In the case of the Trojena dams, this was done by engaging with a group of construction firms on an early contractor involvement (ECI) basis. Contractors took part in a two-stage tender, with bidders submitting preliminary prices and then working with the client to arrive at a final price for the project.
By working on the project at an early stage, contractors have a better understanding of the work involved and are more likely to bid.
Neom is not the only giga- project developer using this approach. Last year, Qiddiya Investment Company appointed UAE-based Alec to build the motorsports Speed Park at its entertainment city project on the outskirts of Riyadh.
Qiddiya is also engaging with contractors on an ECI basis for its Prince Mohammed bin Salman Stadium, which features a complex design that will be built on top of a 200-metre cliff.
Other steps that have been taken to make projects in Saudi Arabia more attractive include better payment terms and an overhaul of the use of performance guarantees.
Red Sea Global (RSG), which is developing the Red Sea Project and Amaala gigaprojects, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention.
By working on the project at an early stage, contractors have a better understanding of the work involved
Packaging projects
Projects are also being packaged differently. For the Trojena dams, the work was packaged as a large infrastructure project. This route also appears to be the favoured solution for other developers undertaking large-scale infrastructure projects.
For building work, there are several approaches. RSG created much noise in the market when it decided to adopt a construction management approach for its projects. This meant breaking the project down into a series of smaller packages, which are then managed by an in-house construction management team.
The aim of this approach is to give the developer more control over the project. It also helps to overcome some of the deficiencies of the market that have existed for main contractors in the kingdom for the past decade.
Other clients are taking a different approach. In recent months, clients such as Diriyah Company and Rua al-Madinah have tendered contracts for constructing superblocks, which include the construction of a district within a development that comprises several buildings. This approach aims to offer contracts to major local, regional and international construction firms with enough scale for them to invest in the project.
The superblock approach was used in previous eras of Saudi construction when major firms – led by Saudi Binladin Group and Saudi Oger – would regularly take on large work packages.
Phasing is another way that the pressure in the market can be alleviated. Last year, executives of Saudi development companies spoke privately about the need for project priorities to be set so that they can focus on specific objectives.
At the end of last year, that notion was given more weight when Finance Minister Mohammed al-Jadaan told reporters at the launch of the state budget that Saudi Arabia needs more time to deliver its projects.
“A longer period is needed to build factories, build even sufficient human resources. The delay or rather the extension of some projects will serve the economy,” he said, adding: “There are strategies that have been postponed and there are strategies that will be financed after 2030.”
As the minister did not give specifics, it is not clear which projects will be delayed and which will remain on their original schedule. That said, projects with event-driven deadlines – such as the 2027 Asian Cup, the 2029 Asian Winter Games, Expo 2030 and the 2034 World Cup – will have to be delivered on time.
This package also includes:
> LEADERSHIP: DHB Holding CEO Omar Delawar on constructing a sustainable future
> INTERVIEW: Gensler co-CEO Andy Cohen on how the buildings and cities of the future can achieve net zero
Exclusive from Meed
-
-
Bahrain opens bids for 1.2GW Sitra IWPP19 June 2026
-
-
Chinese firms win $506m Saudi housing project deals18 June 2026
-
Diriyah awards $727m Waldorf Astoria superblock deal17 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Aramco issues tender for gas pipeline at Ras Tanura refinery19 June 2026

Register for MEED’s 14-day trial access
Contractors are preparing bids for a Saudi Aramco tender involving the replacement of a pipeline that is part of the Gas Line Abqaiq – Ras Tanura (GART) transmission network.
The GART grid transports associated gas and natural gas liquids (NGL) from the Abqaiq oil processing complex as feedstock, northwards to the Ras Tanura refinery in Saudi Arabia’s Eastern Province.
The aim of the project is to replace the GART-22 pipeline that connects the Juaymah export terminal on the Gulf coast in the Eastern Province to the Ras Tanura refinery, to ensure reliable fuel gas supply and meet ongoing demand.
The basic scope of work on the project is to install a new, 24-inch pipeline system that will replace the GART-22 line and the abandoned GART-24 line. It will cover a distance of 18 kilometres between Juaymah and the Ras Tanura terminal.
The scope also includes the installation of associated scraper trap facilities (launcher and receiver), pressure control valves, motor-operated valves and gas detection and sampling systems.
Aramco issued the tender for the project in May and has set a deadline of 30 June for contractors to submit proposals.
The following contractors, among others, are understood to be bidding for the project:
- ACE Pipeline Arabia
- Combined Group Contracting Company
- Gas Arabian Services Company
- Max Streicher Saudi Arabia
- National Basics Company
- Saad Ali Alessa Group
- Sicim
- Sinopec Engineering Group Saudi
- Tecton Engineering & Construction
Ras Tanura refinery complex
The Ras Tanura refinery is the oldest, and one of the largest, crude oil refineries in Saudi Arabia. The complex has a refining capacity of 550,000 barrels a day (b/d).
The facility also has a 305,000 b/d NGL processing facility, a 960,000 b/d crude stabilisation facility, combined steam and gas turbine electrical power generation plants with a summer capacity of 145MW and a winter capacity of 158MW, and a combined 150-pound and 600-pound steam capacity of 6,217 million pounds an hour.
It has 75 crude oil and products storage tanks with a combined capacity of 5.8 million barrels.
The Ras Tanura refinery’s major facilities include a 325,000 b/d crude distillation unit, a 225,000 b/d gas condensate distillation unit, a 50,000 b/d hydrocracker and 107,000 b/d of catalytic reforming capacity.
The facility is Aramco’s only refinery to contain a Visbreaker processing unit, which has a 60,000 b/d capacity.
The Visbreaker reduces the quantity of residual oil produced in the distillation of crude oil and increases the yield of more valuable middle distillates, heating oil and diesel.
The refinery complex also produces 17,000 b/d of asphalt, more than any other refinery in Saudi Arabia.
Ras Tanura receives crude feedstock from the Abqaiq, Safaniya and Manifa oil field developments.
Crude is typically transferred to Ras Tanura through a pipeline and can also be supplied by ship.
Most of Ras Tanura’s production is transferred to the Dhahran bulk plant for domestic use, while some products are exported from the nearby Ras Tanura shipping terminal.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17332850/main.JPG -
Bahrain opens bids for 1.2GW Sitra IWPP19 June 2026
Register for MEED’s 14-day trial access
Two developers have submitted bids for the 1.2GW Sitra independent water and power plant (IWPP), according to details published by Bahrain’s Tender Board.
The offers were made by Abu Dhabi National Energy Company (Taqa) and Saudi Arabia's Acwa. The technical element of the bid was opened on 18 June.
The Sitra IWPP is a combined-cycle gas turbine plant and is expected to have a generation capacity of about 1,200MW of electricity. The project’s seawater reverse osmosis desalination facility will have a production capacity of 30 million imperial gallons a day.
The build, own and operate project is being procured by Bahrain’s Electricity & Water Authority (EWA) under a public-private partnership framework for 20-25 years.
According to a source, "evaluation will be done on technical bids and put up to a tender board for approval".
Financials will be opened only after the technical element has been approved.
Other major IWPP projects in the region have also recorded relatively low bidder particpation in recent weeks, reflecting the level of investment required for such projects.
Earlier this month, MEED reported that just two bids had been received for the first phase of Kuwait’s Al-Khairan IWPP project.
Three consortiums and two individual companies had previously prequalified to participate in the tender.
In 2024, Bahrian's EWA received statements of qualifications from nine firms interested in bidding for the Sitra IWPP. Seven international companies and consortiums were then prequalified to bid last year.
Sitra grid works
Meanwhile, firms are still awaiting awards for two separate contracts related to the establishment of new Sitra 400kV grid substations.
The first contract involves transformer and reactor works for the establishment of the substations.
Switzerland-headquartered Hitachi Energy submitted the lowest bid of BD17.8m ($47.1m). Germany’s Siemens Energy submitted an offer of BD23.9m ($63.2m).
The second contract involves 400kV and 220kV feeder cable works for the same Sitra 400kV grid substations. Three South Korean companies previously bid for the contract.
Bids for both contracts were opened in March.
In September, Siemens Energy won a contract worth BD48.1m ($127m) to build a 400kV transmission substation in Sitra to provide the transmission link for the planned Sitra IWPP.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17329853/main.jpg -
Jordan starts international stadium construction works18 June 2026
Register for MEED’s 14-day trial access
Jordan has started preliminary excavation and site preparation work at its Al-Hussein Bin Abdullah II International Stadium, located east of the capital city of Amman.
The project is part of the first phase of the Amra City development master plan.
The development is being implemented by Jordan Cities & Facilities Development Company, a Jordan Investment Fund-owned company.
The main works are expected to begin early next year, with the stadium slated for completion in 2029.
The project will cover an area of about 1 million square metres and the stadium will have a capacity of 50,000 spectators.
The stadium is being built within the Amra City development, which is located about 40 kilometres (km) from downtown Amman and 35km from Zarqa City and Queen Alia International airport.
The project forms part of Jordan's Economic Modernisation Vision (EMV) 2023-25.
The EMV – Amman’s flagship reform programme – aims to increase real income per capita by an average of 3% annually, create 1 million jobs, and more than double the country’s GDP over the next decade.
The strategy envisages a leading role for the private sector, which is expected to account for 73% of the estimated $58.8bn investment required.
To achieve these targets, a substantial pipeline of public-private partnership (PPP) projects is planned in sectors including water desalination, school construction, clean energy, green hydrogen, transport and road infrastructure.
Last year, the PPP unit at the Investment Ministry said it was targeting seven key PPP projects in 2025.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17325757/main.png -
Chinese firms win $506m Saudi housing project deals18 June 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s Municipalities & Housing Ministry has awarded contracts worth over SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.
The first contract has been awarded to China Architectural Construction Corporation for the construction of 2,010 housing units at the Al-Ruba residential project in Riyadh. The contract value is SR875m ($233m).
The other contract has been awarded to China State Construction Engineering Corporation for the Al-Rasha Al-Faisaliah residential project in Dammam. The project comprises 2,426 housing units, and the contract value is over SR1bn ($266m).
The contracts were announced during the official visit of Majed Al-Hogail, Saudi Municipalities & Housing Minister, to China, where he also signed six memorandums of understanding (MoUs) between Saudi and Chinese firms. The MoUs aim to accelerate housing development, localise advanced construction technologies and enhance public-private sector collaboration.
MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.
By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and to become one of the 10 wealthiest cities in the world.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17322994/main.png -
Diriyah awards $727m Waldorf Astoria superblock deal17 June 2026

Saudi gigaproject developer Diriyah Company has awarded a SR2.7bn ($727m) contract for the main construction works on the development’s Waldorf Astoria superblock.
The contract was awarded to the joint venture of Hassan Allam Construction Saudi and UCC Saudi, the local branch of Qatar’s Urbacon Holding.
The Waldorf Astoria superblock is a mixed-use development comprising a Waldorf Astoria hotel, Waldorf Astoria-branded residences, commercial and residential facilities, and office space.
The Waldorf Astoria hotel will feature 200 keys, while the residential component will comprise 47 branded residences.
The project is located on the Grand Boulevard South and Northern Arterial Road in the Boulevard Northwestern district at Diriyah Gate 2.
Diriyah Company tendered the contract in November last year, with submissions due in January, as MEED reported.
Diriyah Company Group CEO Jerry Inzerillo said: “We are delighted to announce this latest major construction contract for the Waldorf Astoria superblock as we continue to progress at pace across the Diriyah development area. The Waldorf Astoria will be a world-class addition to our growing portfolio of globally renowned hospitality brands, further strengthening Diriyah’s appeal as a globally significant destination that offers world-class hospitality and lifestyle experiences.
“Together with our partners, we look forward to delivering another landmark development that supports the kingdom’s Vision 2030 ambitions and contributes to the continued growth and success of Diriyah.”
Hassan Allam, chairman and CEO of Hassan Allam Holding, said: “We are proud to support the development of one of the kingdom’s most ambitious and transformative destinations and to continue our partnership with Diriyah Company in bringing its vision to life.
“Drawing on more than 90 years of experience across the Mena region, we remain committed to delivering the highest standards of quality and excellence on landmark projects that are helping shape the kingdom’s future.”
Ramez Al-Khayyat, UCC Holding president and group CEO, said: “Being awarded this contract by Diriyah Company marks another important milestone in our growing partnership and reinforces our shared commitment to delivering world-class developments across the kingdom. This project builds on our ongoing collaboration in Diriyah, including the delivery of four luxury hotels and the Royal Diriyah Equestrian and Polo Club in Wadi Safar.
“We value the opportunity to contribute once again to one of Saudi Arabia’s most ambitious and prestigious urban development destinations, supporting the vision of creating a world-class cultural, hospitality and lifestyle hub.”
The latest award follows Diriyah Company’s award of an estimated SR730m ($195m) construction contract for civic quarter buildings within the Diriyah development to local contractor Al-Rashid Trading & Contracting Company (RTCC).
In April, Diriyah announced a SR1.84bn ($490m) construction contract to build the Saudi Arabia Museum of Contemporary Art (SAMoCA) within the Diriyah development. The contract was awarded to a consortium of Egyptian contractor Hassan Allam Construction Saudi and Saudi Arabia’s Albawani.
In March, Diriyah Company awarded an estimated SR2.5bn ($666m) contract to build the Pendry superblock in the DG2 area.
The Pendry superblock includes the construction of the Pendry Hotel alongside residential and commercial assets. The package will cover 75,365 square metres and is located in the northwestern district of the DG2 area.
The previous month, Diriyah Company also awarded a SR717m ($192m) contract for the construction of the One Hotel, located in the Diriyah Two area of the masterplan, with a gross floor area of more than 31,000 sq m.
The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh’s city centre, it will cover 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17287718/main.jpg
