Rethinking how Saudi projects are delivered

25 January 2024

 

In early January, Italian contractor WeBuild secured a $4.7bn contract to construct the three dams that will create a lake at the centre of Saudi Arabia’s Trojena mountain resort in Neom. 

Like most in the kingdom, the project is large in scale and technically challenging. It also has an aggressive delivery schedule as the lake – and the surrounding resort and ski slopes – must be ready for the Asian Winter Games in 2029. 

The project will also have to be completed at the same time as the rest of the growing volume of construction work in the kingdom. According to regional projects tracker MEED Projects, there were close to $95bn of contract awards across all sectors in the kingdom in 2023 – an all-time record and significantly higher than the $59bn recorded the previous year.

For construction specifically, there were $23bn-worth of awards made in 2023, which is marginally less than the total for 2022. With this level of awards expected to be maintained or exceeded in 2024, the challenges facing the kingdom’s construction sector will be amplified this year.

New approach

The development firms that have been tasked with delivering Riyadh’s five official gigaprojects – and the raft of other large masterplanned projects – are rethinking how projects in the kingdom are delivered.

The first area of concern is procurement, and securing sufficient resources to complete projects. 

In the case of the Trojena dams, this was done by engaging with a group of construction firms on an early contractor involvement (ECI) basis. Contractors took part in a two-stage tender, with bidders submitting preliminary prices and then working with the client to arrive at a final price for the project. 

By working on the project at an early stage, contractors have a better understanding of the work involved and are more likely to bid. 

Neom is not the only giga- project developer using this approach. Last year, Qiddiya Investment Company appointed UAE-based Alec to build the motorsports Speed Park at its entertainment city project on the outskirts of Riyadh. 

Qiddiya is also engaging with contractors on an ECI basis for its Prince Mohammed bin Salman Stadium, which features a complex design that will be built on top of a 200-metre cliff.

Other steps that have been taken to make projects in Saudi Arabia more attractive include better payment terms and an overhaul of the use of performance guarantees. 

Red Sea Global (RSG), which is developing the Red Sea Project and Amaala gigaprojects, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention.

By working on the project at an early stage, contractors have a better understanding of the work involved

Packaging projects

Projects are also being packaged differently. For the Trojena dams, the work was packaged as a large infrastructure project. This route also appears to be the favoured solution for other developers undertaking large-scale infrastructure projects. 

For building work, there are several approaches. RSG created much noise in the market when it decided to adopt a construction management approach for its projects. This meant breaking the project down into a series of smaller packages, which are then managed by an in-house construction management team. 

The aim of this approach is to give the developer more control over the project. It also helps to overcome some of the deficiencies of the market that have existed for main contractors in the kingdom for the past decade. 

Other clients are taking a different approach. In recent months, clients such as Diriyah Company and Rua al-Madinah have tendered contracts for constructing superblocks, which include the construction of a district within a development that comprises several buildings. This approach aims to offer contracts to major local, regional and international construction firms with enough scale for them to invest in the project. 

The superblock approach was used in previous eras of Saudi construction when major firms – led by Saudi Binladin Group and Saudi Oger – would regularly take on large work packages. 

Phasing is another way that the pressure in the market can be alleviated. Last year, executives of Saudi development companies spoke privately about the need for project priorities to be set so that they can focus on specific objectives. 

At the end of last year, that notion was given more weight when Finance Minister Mohammed al-Jadaan told reporters at the launch of the state budget that Saudi Arabia needs more time to deliver its projects. 

“A longer period is needed to build factories, build even sufficient human resources. The delay or rather the extension of some projects will serve the economy,” he said, adding: “There are strategies that have been postponed and there are strategies that will be financed after 2030.” 

As the minister did not give specifics, it is not clear which projects will be delayed and which will remain on their original schedule. That said, projects with event-driven deadlines – such as the 2027 Asian Cup, the 2029 Asian Winter Games, Expo 2030 and the 2034 World Cup – will have to be delivered on time.


This package also includes:

> LEADERSHIP: DHB Holding CEO Omar Delawar on constructing a sustainable future
> INTERVIEW: Gensler co-CEO Andy Cohen on how the buildings and cities of the future can achieve net zero


https://image.digitalinsightresearch.in/uploads/NewsArticle/11463808/main.gif
Colin Foreman
Related Articles
  • Aldar launches Yas Island community park project

    30 June 2026

    Abu Dhabi-based real estate developer Aldar, in partnership with the Abu Dhabi Department of Community Development (DCD), has announced the launch of Yas Community Park on Yas Island.

    A key feature of the park is Nabdh Yas, a community hub developed in collaboration with DCD.

    Once open, Nabdh Yas will serve as a central gathering space and host a range of community-led programmes.

    In a statement, Aldar said: “Nabdh Yas will be delivered on a public-private partnership (PPP) basis, marking the first time private sector investment has been directed towards this type of community infrastructure.

    “With DCD overseeing the hub’s development and long-term management, the initiative reflects Abu Dhabi’s focus on innovative approaches that generate lasting social value and enhance community wellbeing,” the statement added.

    A memorandum of understanding was signed between Aldar and DCD.

    The agreement establishes a framework to expand the Nabdh Community Hub model across Aldar developments in Abu Dhabi, Al-Ain and Al-Dhafra.

    Last month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).

    Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.

    UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.

    The group attributed its performance to revenue from its development backlog and steady income from its investment properties.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17489270/main.jpeg
    Yasir Iqbal
  • Dubai sets August deadline for Airport Express metro bids

    30 June 2026

     

    Dubai’s Roads & Transport Authority (RTA) has given consultants until 10 August to submit proposals for a contract to study and design the Airport Express Line, which will extend from Dubai International airport (DXB) in the Al-Garhoud area to Al-Maktoum International Airport (DWC) in the Jebel Ali area.

    The previous deadline was 8 July.

    The proposed line will stretch about 55 kilometres and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    The RTA issued the tender in April, with an initial deadline of June, as MEED reported.

    The new line will run from the Red Line metro station at DXB through Al Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing to DWC.

    There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch towards Business Bay, where another station will be built.

    The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is under construction and due to be completed by 2030.

    The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Earlier this month, MEED exclusively reported that the RTA had issued the request for qualification notice for a contract to build the new Gold Line, as part of its expansion of the Dubai Metro network.

    Tendering activity is also ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.

    MEED exclusively reported in April that consultants had submitted bids for the project.

    The extension to the line will run for about 3km and will feature two stations.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17489266/main.jpg
    Yasir Iqbal
  • Eni increases gas production in Libya

    30 June 2026

    The Italian oil and gas company Eni has announced the startup of offshore gas production enabled by the Sabratha compression project in Libya.

    The client on the project was Mellitah Oil & Gas (MOG), a joint venture of Eni and Libya’s state-owned National Oil Corporation (NOC).

    The Sabratha compression project was designed to increase gas output from the Bahr Essalam gas field, located approximately 100 kilometres off Libya’s coast.

    The scope of the project included the installation of a new 1,600-tonne compression module on the Sabratha platform, equipped with new compression trains, providing an overall compression capacity of about 440 million cubic feet a day.

    In a statement, Eni said: “The new module enables production under low-pressure conditions, offsetting the natural decline of the Bahr Essalam field and maximising gas recovery, ensuring increased volumes of gas of about 800 million cubic metres per year and associated condensate.

    “This additional production will play a critical role in sustaining national power generation, reinforcing Libya’s energy security, and supporting export to Italy via the Greenstream pipeline.”

    The company also said that the project strengthened the resilience of Libya’s gas infrastructure and represented “a tangible contribution to the stability and growth of the country’s energy sector”.

    MOG also has two other projects in Libya that are currently under execution.

    The first is the Bouri gas utilisation project, whose tie-in and commissioning activities are under way following the recent installation of the Bouri gas recovery module.

    The other project, known as ‘Structures A&E’, will develop two offshore gas fields.

    Eni has been present in Libya since 1959 and last year had average equity production in the country of approximately 162,000 barrels of oil equivalent a day.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17489032/main3444.jpg
    Wil Crisp
  • Jordan faces fresh round of challenges

    29 June 2026

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17479483/main.gif
    MEED Editorial
  • Levant recovers in three speeds

    29 June 2026

    Commentary
    Colin Foreman
    Editor

    The Levant enters the second half of 2026 in a state of uneven recovery. Jordan, Lebanon and Syria are each navigating distinct pressures, but share a common condition: the pace of improvement is being set less by domestic policy than by the willingness of external actors to commit capital and the capacity of local systems to absorb it.

    Syria presents the most dramatic transformation. The fall of the Assad government in December 2024 unlocked a wave of Gulf and international engagement that would have been unimaginable a year earlier. The World Bank estimates the cost of reconstruction at $216bn, and commitments are accumulating. Qatar’s UCC Holding anchors two of the largest, a $7bn power programme and a $4bn rebuild of Damascus International airport. Dubai’s DP World is operational at Tartous under a 30-year concession. Abu Dhabi’s Eagle Hills has presented plans for urban developments in Damascus and Latakia with a reported budget of $50bn.

    Yet the gap between commitment and delivery is wide, and the binding constraint is financial infrastructure rather than investor appetite. Syria’s central bank sent its first Swift message in 14 years in November 2025. Visa and Mastercard processing resumed only in May. Correspondent banks remain cautious on compliance grounds. The IMF has declined to extend a lending programme, citing the need for banking reform and central-bank independence. Until the financial plumbing works at scale, the pledged billions will remain signed announcements rather than funded projects.

    Jordan’s position is more stable but equally constrained. Prime Minister Jafar Hassan has held the fiscal line since his appointment in September 2024, narrowing the deficit from 7.3% of GDP to a projected 5.4% in 2026 under the IMF programme. The $2.3bn Aqaba Port Railway, backed by the UAE, and the $5.8bn National Water Carrier project together represent the largest foreign investment in the kingdom’s history, according to Hassan. 

    But growth is projected at just 2.7% through 2026, well short of what the Economic Modernisation Vision requires, and structural reforms to the labour market have stalled.

    Lebanon, meanwhile, continues to mark time. Political leadership is in place and Block 8 offshore has attracted TotalEnergies, Eni and QatarEnergy, but the country produces virtually no hydrocarbons and its broader economic recovery remains fragile as the threat of conflict persists.

     


    MEED’s July 2026 report on the Levant includes:

    > GOVERNMENT: Jordan consolidates as deeper reforms lag
    > BANKING: Caution governs Jordanian bank lending
    > POWER & WATER: Record investment drives Jordan’s utilities market
    > ECONOMY: Gulf liquidity outpaces Syria’s financial revival
    > PROJECTS: 
    Momentum builds for Syrian projects
    > OIL & GAS: Activity ramps up in Syria’s oil and gas sector
    > CONSTRUCTION: Prospects improve for Levant construction
    > OIL & GAS: Lebanon taps foreign players to assess resources

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17479313/main.gif
    Colin Foreman