Rethinking how Saudi projects are delivered

25 January 2024

 

In early January, Italian contractor WeBuild secured a $4.7bn contract to construct the three dams that will create a lake at the centre of Saudi Arabia’s Trojena mountain resort in Neom. 

Like most in the kingdom, the project is large in scale and technically challenging. It also has an aggressive delivery schedule as the lake – and the surrounding resort and ski slopes – must be ready for the Asian Winter Games in 2029. 

The project will also have to be completed at the same time as the rest of the growing volume of construction work in the kingdom. According to regional projects tracker MEED Projects, there were close to $95bn of contract awards across all sectors in the kingdom in 2023 – an all-time record and significantly higher than the $59bn recorded the previous year.

For construction specifically, there were $23bn-worth of awards made in 2023, which is marginally less than the total for 2022. With this level of awards expected to be maintained or exceeded in 2024, the challenges facing the kingdom’s construction sector will be amplified this year.

New approach

The development firms that have been tasked with delivering Riyadh’s five official gigaprojects – and the raft of other large masterplanned projects – are rethinking how projects in the kingdom are delivered.

The first area of concern is procurement, and securing sufficient resources to complete projects. 

In the case of the Trojena dams, this was done by engaging with a group of construction firms on an early contractor involvement (ECI) basis. Contractors took part in a two-stage tender, with bidders submitting preliminary prices and then working with the client to arrive at a final price for the project. 

By working on the project at an early stage, contractors have a better understanding of the work involved and are more likely to bid. 

Neom is not the only giga- project developer using this approach. Last year, Qiddiya Investment Company appointed UAE-based Alec to build the motorsports Speed Park at its entertainment city project on the outskirts of Riyadh. 

Qiddiya is also engaging with contractors on an ECI basis for its Prince Mohammed bin Salman Stadium, which features a complex design that will be built on top of a 200-metre cliff.

Other steps that have been taken to make projects in Saudi Arabia more attractive include better payment terms and an overhaul of the use of performance guarantees. 

Red Sea Global (RSG), which is developing the Red Sea Project and Amaala gigaprojects, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention.

By working on the project at an early stage, contractors have a better understanding of the work involved

Packaging projects

Projects are also being packaged differently. For the Trojena dams, the work was packaged as a large infrastructure project. This route also appears to be the favoured solution for other developers undertaking large-scale infrastructure projects. 

For building work, there are several approaches. RSG created much noise in the market when it decided to adopt a construction management approach for its projects. This meant breaking the project down into a series of smaller packages, which are then managed by an in-house construction management team. 

The aim of this approach is to give the developer more control over the project. It also helps to overcome some of the deficiencies of the market that have existed for main contractors in the kingdom for the past decade. 

Other clients are taking a different approach. In recent months, clients such as Diriyah Company and Rua al-Madinah have tendered contracts for constructing superblocks, which include the construction of a district within a development that comprises several buildings. This approach aims to offer contracts to major local, regional and international construction firms with enough scale for them to invest in the project. 

The superblock approach was used in previous eras of Saudi construction when major firms – led by Saudi Binladin Group and Saudi Oger – would regularly take on large work packages. 

Phasing is another way that the pressure in the market can be alleviated. Last year, executives of Saudi development companies spoke privately about the need for project priorities to be set so that they can focus on specific objectives. 

At the end of last year, that notion was given more weight when Finance Minister Mohammed al-Jadaan told reporters at the launch of the state budget that Saudi Arabia needs more time to deliver its projects. 

“A longer period is needed to build factories, build even sufficient human resources. The delay or rather the extension of some projects will serve the economy,” he said, adding: “There are strategies that have been postponed and there are strategies that will be financed after 2030.” 

As the minister did not give specifics, it is not clear which projects will be delayed and which will remain on their original schedule. That said, projects with event-driven deadlines – such as the 2027 Asian Cup, the 2029 Asian Winter Games, Expo 2030 and the 2034 World Cup – will have to be delivered on time.


This package also includes:

> LEADERSHIP: DHB Holding CEO Omar Delawar on constructing a sustainable future
> INTERVIEW: Gensler co-CEO Andy Cohen on how the buildings and cities of the future can achieve net zero


https://image.digitalinsightresearch.in/uploads/NewsArticle/11463808/main.gif
Colin Foreman
Related Articles
  • Libya and Tunisia reschedule joint oil and gas licensing round

    19 August 2026

    The Libyan-Tunisian Joint Oil Exploration, Exploitation and Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.

    The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.

    Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.

    The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.

    Significant data are available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.

    The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.

    Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).

    LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.

    Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.

    The key dates from the new schedule for the licensing round are:

    • 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
    • 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
    • 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
    • 31 December 2026: Bid round closes
    • 8 January 2027: Bid submissions due
    • 26 February 2027: Winning bidders notified
    • 30 April 2027: Formal awards expected

    Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.

    Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.

    A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.

    Despite this, the field has remained undeveloped for over three decades.

    One of the key challenges to developing the reserve is its high carbon dioxide content.

    Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main.jpg
    Wil Crisp
  • UAE cuts trade and financial links with Iran

    19 August 2026

    Register for MEED’s 14-day trial access 

    The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.

    The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.

    The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.

    It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.

    The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.

    The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg
    Colin Foreman
  • Abu Dhabi begins Dar Al-Funoon Saadiyat construction

    19 August 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based piling contractor APCC Piling & Marine Contracting has started the enabling works on Dar Al-Funoon, a cultural development near the Saadiyat Cultural District.

    The project, commissioned by the Department of Culture & Tourism – Abu Dhabi, was designed by the late Canadian-American architect Frank Gehry.

    The venue is scheduled to open in 2030.

    MEED understands that the main contract bids are under evaluation and the project is slated for award soon.

    The complex will feature a multipurpose hall with more than 2,000 seats, a 3,500-seat open-air amphitheatre, a 400-seat studio theatre and a 250-seat jazz venue, bringing total capacity to more than 6,000 across its performance spaces.

    The venue will host leading international productions, delivering high-quality cultural experiences for audiences locally, regionally and globally.

    Upon completion, it will become one of the region’s largest performing arts venues.

    The project was announced by Sheikh Khaled Bin Mohamed Bin Zayed Al-Nahyan, Crown Prince of Abu Dhabi and Chairman of the Abu Dhabi Executive Council in June, as MEED reported.

    During a review of the plans, he was briefed on the architectural concept and the development and construction phases, as well as the venue’s advanced technical capabilities, which are being designed to meet the highest international standards for staging major global productions.

    The announcement is part of the ongoing development of Saadiyat Island, which already includes Louvre Abu Dhabi, Zayed National Museum, Natural History Museum Abu Dhabi, teamLab Phenomena Abu Dhabi and the upcoming Guggenheim Abu Dhabi.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18852155/main4145.jpg
    Yasir Iqbal
  • Contractor wins Dubai Canal drainage deal

    19 August 2026

     

    Register for MEED’s 14-day trial access 

    Local firm Detech Contracting has won an engineering, procurement and construction (EPC) contract to upgrade and rehabilitate the East Dubai Canal stormwater system.

    The project, known as TF-16-C1, is part of Dubai’s Tasreef strategic plan to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
     
    According to a source, Lebanon's Khatib & Alami has also been appointed as a consultant on the project.

    The works will focus on upgrading existing stormwater infrastructure to increase capacity and improve reliability during heavy rainfall.

    The scope includes upgrading the stormwater drainage system, laying pipelines and constructing manholes and gullies. It also includes the construction of pumping stations and diversion works, site clearance and other associated facilities.

    In February, MEED reported that the municipality had invited consultants to qualify for a contract to supervise three stormwater drainage projects (TF-16-C1, TF-15-C2 and TF-13-C1)

    China State Construction Engineering Corporation announced in July that it had won the EPC contract for the TF-15-C2 stormwater drainage network project located on Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    MEED understands contractor bids are still being evaluated for the TF-13-C1 project, which focuses on developing a drainage system for the Al-Marmum area.

    Detech has been awarded several packages under the Tasreef programme in the past 18 months.

    These include:

    • TF-16-C1: upgrading and rehabilitation of East Dubai Canal stormwater system
    • TF-15-C1: stormwater drainage system at Al-Wasl Road for communities west of Dubai Canal
    • TF-05-C1: stormwater drainage system in Jebel Ali 
    • TF-04: stormwater drainage system on Sheikh Mohammed Bin Zayed Road and Al-Yalayis Road
    • DS-419: Tasreef rainwater drainage network: West Deira stormwater system upgrade and rehabilitation 

    As MEED exclusively reported, the municipality recently issued a letter of award for the TF-15-C1 project, covering the construction of a stormwater drainage system on Al-Wasl Road and communities west of Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    This week, Dubai Municipality also issued three tenders for stormwater and sewerage infrastructure projects serving Hind City, Dubailand and surrounding areas.

    The projects cover drainage networks for Hind 4, connections to the stormwater network in Dubailand and a stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman.

    All three have bid submission deadlines of 10 September.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18850438/main.jpg
    Mark Dowdall
  • Maaden and Aramco sign deal to create joint venture

    18 August 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabian Mining Company (Maaden) and Saudi Aramco have signed a shareholders’ agreement to form a joint venture (JV). Maaden will hold a 51% stake in the JV, while Aramco will own the remaining 49%.

    Before signing the shareholders’ agreement, the two Saudi state-owned companies signed a non-binding heads of agreement in January 2025 aimed at establishing the JV.

    “Combining the strengths of two leaders in their respective fields, the JV will focus on copper and other minerals critical to the energy transition,” the two parties said in a joint statement.

    The JV will focus on exploration across Zone 4, also known as the Transition Zone, within the Arabian Platform in Saudi Arabia. Spanning approximately 182,000 square kilometres – nearly 10% of the kingdom’s total land area – the expected exploration area stretches along a 100-kilometre-wide corridor running parallel to the Arabian Shield.

    “It represents a major new opportunity for mineral discovery in the kingdom,” Maaden and Aramco said.

    Copper, which is increasingly significant for electric vehicles, power networks, energy storage and renewable energy systems, will be a main focus of the JV.

    Copper accounts for more than 20% of the $1.2tn mined-metals market. The copper market is currently valued at about $250bn and is projected to grow to more than $400bn by 2035.

    The JV will also explore for other energy transition minerals, including zinc, lead and rare earth elements, “that are expected to be crucial to industries of the future”.

    “Leveraging advanced computational algorithms, [artificial intelligence] AI, and high-performance computing, the JV intends to target areas most likely to contain copper and valuable minerals, accelerating the path from regional screening to target definition and discovery. This is expected to support long-term sector development, reinforce the kingdom’s role in the global minerals value chain, and help meet rising demand for transition minerals,” the partners said.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18833329/main.jpg
    Indrajit Sen