Renewables to drive Saudi switchgear expansion

16 July 2024

The high-voltage (HV) switchgear market in Saudi Arabia is one of the fastest-growing globally, with a market value of $901.65m in 2023, according to a recent report by GlobalData.

Gas-insulated substations (GIS) account for about 90% of the total value, driven by the extreme environmental conditions prevailing in the kingdom.

According to the report, Saudi Arabia had 1,248 transmission substations in the 72-172 kilovolt (kV) segment and 246 substations in the over 172kV segment in 2023. The total length of transmission lines in the kingdom stood at 95,564 circuit kilometres (Ckm).

GlobalData expects the total number of transmission substations in the 72-172kV segment to rise to 1,327 and the number in the over 172kV segment to increase to 269 by 2028.

The transmission line length in the kingdom by 2028 is expected to reach 100,360Ckm.

The findings for Saudi Arabia are part of a broader report looking at global switchgear market trends.

"Increasing electricity demand is propelling the HV switchgear market in growing economies in Asia Pacific and the Middle East," the report said.

Future transmission investments in Saudi Arabia will be directed towards developing grid infrastructure to evacuate power from the upcoming renewable energy plants, in addition to grid refurbishment and modernisation.

The report said: "Saudi Electricity Company (SEC) has awarded transmission contracts worth SR6.8bn ($1.8bn) for the construction of new infrastructure and expansion or extension of existing substations [between January 2020 and July 2021].

"In March 2023, the Gulf Cooperation Council Interconnection Authority awarded a contract to SEC for upgrading the Al-Fadhili high-voltage, direct-current (HVDC) converter station to exchange up to 1.8GW among GCC countries.

"To this end, 3,600Ckm of transmission lines will be added by SEC [between 2023 and 2025] to the nation’s grid, with an investment of about SR5.4bn."

In June 2023, Hitachi Energy signed agreements with SEC and Enowa, the utility subsidiary of Saudi gigaproject developer Neom, under the supervision and direction of the Energy Ministry.

The agreements comprise the supply of three HVDC transmission systems to Enowa in northwest Saudi Arabia. The combined power capacity of the three HVDC lines will be up to 9GW.

Adverse environmental conditions 

The geographical and climatic conditions in Saudi Arabia affect the electrical equipment installed in the substations. The extreme temperature, sandstorms and salt-laden atmosphere affect the performance and service life of the switchgear equipment.

In addition, outdoor air-insulated switchgear (AIS) substations are difficult to operate and maintain in such conditions. This has made GIS the most viable option for substation projects in Saudi Arabia. Most of the substations are indoors, protecting the switchgear from the harmful environment and increasing reliability. This will be a major factor that propels the GIS market in Saudi Arabia, which is more predominant than AIS in the region.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12126744/main.gif
Jennifer Aguinaldo
Related Articles
  • Dewa raises Empower stake in $1.41bn deal

    12 February 2026

    Dubai Electricity & Water Authority (Dewa) has announced it has increased its stake in Emirates Central Cooling Systems Corporation (Empower) from 56% to 80%.

    The transaction was completed through the purchase of 2.4 billion shares and the transfer of the entire ownership of Emirates Power Investment (EPI), which is wholly owned by Dubai Holding.

    The total value of the deal is AED5.184bn ($1.41bn).

    Empower currently holds over 80% of Dubai’s district cooling market and operates 88 district cooling plants across the emirate.

    According to MEED Projects, the UAE’s district cooling sector currently has nine projects worth $1.29bn in the pre-execution phase.

    Empower has ownership in four of these projects, which have a combined value of $472m.

    This includes a $200 million district cooling plant at Dubai Science Park, with a total capacity of 47,000 refrigeration tonnes serving 80 buildings.

    Empower signed a contract to design the plant last August, with construction scheduled to begin by the end of the first quarter of 2026.

    The utility is also building a district cooling plant at Dubai Internet City.

    UAE-based TMF Euro Foundations was recently appointed as the enabling and piling subcontractor for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15635949/main.jpg
    Mark Dowdall
  • Saudi cabinet approves Qatar high-speed rail link

    12 February 2026

    Saudi Arabia has approved the establishment of a proposed high-speed rail line connecting Riyadh and Doha.

    The approval was granted during a cabinet session chaired by King Salman Bin Abdulaziz Al-Saud in Riyadh on 10 February.

    The high-speed railway line will cover 785 kilometres (km) and will pass through Hofuf and Dammam, while also linking King Salman International airport and Hamad International airport.

    Saudi Arabia and Qatar signed an agreement in December last year to build a high-speed rail line.

    The agreement was inked by Saudi Arabia’s Transport & Logistics Services Minister, Saleh Al-Jasser, and Qatar’s Transport Minister, Sheikh Mohammed Bin Abdulla Bin Mohammed Al-Thani.

    Trains will reach speeds exceeding 300 kilometres an hour, reducing the travel time between the two capitals to about two hours.

    The project is slated for completion in six years. It is expected to serve over 10 million passengers annually and create more than 30,000 direct and indirect jobs.

    Riyadh and Doha relaunched the proposed rail link between the two countries in 2022, after agreeing to set a date to begin studying the connection. 

    In July of that year, France’s Systra was selected to conduct a feasibility study on the proposed scheme, as MEED reported.

    A rail link connecting Saudi Arabia and Qatar was planned before the diplomatic dispute that froze relations between Riyadh and Doha from 2017 until the Al-Ula Declaration was signed in January 2021.

    In 2016, Qatar Railways Company (Qatar Rail) planned to tender a design-and-build contract for the construction of regional railways in Qatar, including a link to the Saudi border.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15635582/main.jpg
    Yasir Iqbal
  • Bidders line up for Saudi sewage treatment contract

    12 February 2026

     

    Six bidders are competing in the next phase of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, as National Water Company (NWC) moves closer to awarding a contract.

    The contract covers the North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11) and has an estimated value of about $211m.

    The project involves the construction and upgrade of two sewage treatment plants with a combined capacity of about 440,000 cubic metres a day (cm/d).

    As MEED understands, the companies that have submitted proposals include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • United Water (China)
    • Kuzu Group (Turkey)
    • VA Tech Wabag (India)
    • Aguas de Valencia (Spain)

    LTOM11, also known as the North Western A Cluster, forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    The scheme is being procured on an engineering, procurement and construction (EPC) basis with a long-term operations component.

    The scope also includes a pumping station, surplus discharge lines, SCADA installation and associated infrastructure.

    The main contract was tendered last year, with an award initially expected by the end of 2025.

    It is now understood that NWC is preparing to offer the main contract in this quarter.

    LTOM programme

    LTOM11 follows a series of earlier awards under the programme.

    In January, a consortium of United Water (China), Prosus Energy (UAE) and Armada Holding (Saudi Arabia) won the main contract for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).

    This has an estimated value of about SR203m ($54.1m).

    NWC previously awarded $2.7bn-worth of contracts for the first phase of its LTOM programme. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years.

    As MEED reported, local contracting firm Alkhorayef Water & Power Technologies won three contracts with a combined capacity of 2.04 million cm/d, nearly half of the awarded total. These three contracts are worth more than SR5.53bn ($1.47bn).

    A consortium of France’s Suez and the local Al-Awael Modern Contracting Group, with its affiliate Civil Works Company (CWC), won two packages worth a combined SR1.84bn.

    A consortium comprising France’s Veolia and Awael-CWC won a single package worth SR1.26bn, and local utility developer Miahona won one package worth SR392m.

    In 2024, a joint venture of CWC and Al-Awael Modern Contracting was awarded a $211m contract for LTOM9.

    As part of the second phase, the main contract bids for LTOM12 (North Western B Cluster) have also been submitted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15635292/main.jpg
    Mark Dowdall
  • Indian firm wins Dubai Latifa Bint Hamdan road project

    12 February 2026

    Indian contractor Larsen & Toubro (L&T) has won a contract to construct the first phase of the Latifa Bint Hamdan Street development project in Dubai.

    The contract value is between $110m and $275m, according to L&T’s contract classification.

    This project covers 12.2 kilometres of road network from its intersection with Al-Khail Road to Emirates Road.

    The project also includes 8.1km of bridges and will add capacity for about 16,000 vehicles an hour in both directions.

    The scope also involves widening the two-lane dual carriageway to four lanes in each direction.

    The project is scheduled for completion within 36 months.

    The contract was awarded by Dubai’s Roads & Transport Authority (RTA).

    The project is part of the RTA’s estimated AED16bn ($4.3bn) 2024-27 Main Roads Development Plan, which includes 22 projects across Dubai’s road network, as announced in November 2024.

    The development plan includes the construction of new roads and bridges to alleviate traffic congestion at several key locations across Dubai.

    Planning for growth

    The Dubai 2040 Urban Master Plan was launched in March 2021. Its launch referenced studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension also forms part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims to ensure that residents can meet 80% of their daily needs within a 20-minute walk or bike ride. This goal will be achieved by developing integrated service centres with the necessary facilities and by increasing population density around mass transit stations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15635237/main.gif
    Yasir Iqbal
  • SAR tenders Riyadh section of Saudi Landbridge

    12 February 2026

     

    Saudi Arabia Railways (SAR) has tendered a design-and-build contract for the construction of a new railway line, the Riyadh Rail Link, which will run from north to south Riyadh.

    The tender was issued on 29 January, with a bid submission deadline of 29 March.

    The scope of work includes constructing a 35-kilometre-long double-track railway line connecting SAR’s North-South Railway to the Eastern Railway network.

    The contract also covers the procurement, construction and installation of associated infrastructure such as viaducts, civil works, utility installations, signalling systems and other related works.

    The project is expected to form a key component of the Saudi Landbridge railway.

    Last month, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium for the construction of the project, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements and that the project will now be delivered in several phases under a different procurement model.

    The project has been under negotiation between Saudi Arabia and China-backed investors keen to develop it through a public-private partnership.

    Al-Malik said that the project cost is about SR100bn ($26.6bn).

    It comprises more than 1,500 kilometres (km) of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.

    In April last year, MEED exclusively reported that SAR had issued a tender for the lead design consultancy services contract on the Saudi Landbridge railway network.

    MEED understands that the scope covered the concept design and options for the preliminary and issued-for-construction design stages on the network.

    MEED reported that the launch of a design tender directly by SAR suggested that Riyadh was looking at other options to develop it alongside the Chinese proposal.

    In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.

    If it proceeds, the Saudi Landbridge will be one of the largest railway projects ever undertaken in the Middle East and one of the biggest globally. Based on typical design timeframes, tenders for construction are likely to be ready by mid-2026, although the question of how it will be financed will need to be answered before it can proceed to the next step.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15635220/main.jpg
    Yasir Iqbal