Region’s hotel projects pipeline balloons
4 April 2025

This package also includes: Beaches and luxury drive regional tourism
Despite a somewhat lackluster 2024 performance in the region for hospitality-linked project award activity, Middle East and North Africa (Mena) contractors are eyeing more than $60bn in projects in design and bid that are set to proceed to market in the near future.
Last year, project awards in the Mena region’s hospitality-linked construction segment declined slightly to $6.2bn, falling below the contract award values in both 2022 and 2023, while remaining above that of the three preceding years and the average for the past five years.
Also positively, the awards value for 2024 was commensurate with the value of projects in the bidding phase this time last year, when $1.3bn-worth of projects had been awarded and $5.2bn-worth of projects were in the bidding phase. This indicates that projects in the segment are delivering and not stalling.
Top projects
Saudi Arabia dominated the overall project activity in the segment with a total contract award value of $4.4bn. This was followed by the UAE at $1bn and a handful of other countries with a combined $700m in value – making for a significantly skewed project activity landscape.
The largest single project to be awarded was the $762m Keturah Creekside Resort, a Ritz-Carlton Residences scheme in Dubai that is being developed by the local Mag Property Development. The main contract was awarded to Cecep Techand Middle East, a Dubai-based contracting subsidiary of a Chinese state-owned enterprise that is generally better known for its involvement in utility projects.
The next largest award was for the $508m Six Senses Falcon’s Nest Hotel in the Wadi Safar area of Saudi Arabia’s Diriyah gigaproject. This contract was awarded by Diriyah Company to a joint venture (JV) of Qatar’s UCC Holding and local construction group Al-Bawani.
Diriyah Company also let the contracts for four other hotels at Wadi Safar – Aman, Chedi, Faena and Oberoi-branded properties worth a combined $826m – to the same JV.
Three further Diriyah projects worth a combined $519m were awarded for the building of a Capella hotel, a Raffles hotel and a Ritz-Carlton Residences to a variety of other contractors.
Significant gigaproject-linked contract awards were also made on the Amaala development within Red Sea Global’s project portfolio, and for a hotel complex at Qiddiya, the Riyadh-adjacent entertainment city.
The largest contract awarded in a third country was a $125m Avani-Tivoli hotel and residences project in Bahrain let to local contractor Cebarco by Bahrain Real Estate Investment Company (Edamah) as part of the Bilaj Al-Jazayer development.
Project pipeline
Looking ahead in 2025, there are $8.6bn-worth of projects in the bidding phase, with $3.9bn at the prequalification stage, $2.2bn in bid submission and $2.5bn in bid evaluation. If all of this value is awarded as expected, alongside the $410m in awards so far this year, then 2025 could turn out to be the best year for hotel project activity since 2015.
There is also a much larger groundswell of projects in the design phase. This time last year, the value of projects in design was $15bn, but that value has swollen by 270% to $56bn in the past 12 months, led by Egypt’s launch of South Med, a 2,300-hectare tourism masterplan valued at $21bn.
Launched by Talaat Moustafa Group, the South Med project is situated 165 kilometres (km) to the west of Alexandria on Egypt’s northern Mediterranean coastline and 60km east of Ras El-Hekma, an area earmarked for development by Abu Dhabi following a $24bn deal for the land rights.
Between the two masterplans, Egypt’s northern coast promises to generate a significant amount of construction work in the years to come, and developments in the area are also accelerating as the stretch of coastline grows in significance as a source of interest for investors. Local developer Sodic, which in 2021 become a subsidiary of UAE developer Aldar, launched its own plans in September to deliver a $500m Nobu hotel and residences complex just east of the Ras El-Hekma area.
In Saudi Arabia, which accounts for $41.6bn or 50% of the hospitality project pipeline in the Mena region – including $24.4bn-worth of projects in design – the pending work is led in value terms by the $7bn in-design second phase of the Red Sea Project. There are also four packages of work worth a combined $3bn in design for the towers and podiums of the Mukaab project – the cubic centrepiece of the New Murabba development in Riyadh. Meanwhile, a further $3.8bn of projects are in design or bid – split $1.8bn and $2bn, respectively – at the Rua Al-Madinah development.
The next-largest areas of pending hospitality projects in the region are in the UAE and Oman. The UAE’s pipeline is led by Emaar’s $1.5bn Dubai Creek Harbour Tower and a $1.3bn JW Marriott Resort & Residences planned by private developer Wow Resorts for Al-Marjan Island in Ras Al-Khaimah. In Oman, the projects are led by the $500m third phase of the tourism ministry’s Yenkit Hills development and a $500m Trump resort being developed by Omran, the UAE’s Dar Al-Arkan and the US’ Trump Organisation.
If even a small fraction of the $56bn of hospitality-linked projects in the design phase in the region proceeds to execution in 2025, it could swell the awards total to record levels. After a somewhat sluggish performance in Q1, awards activity could pick up markedly from Q2 onwards, given the $2.5bn in projects that are already in bid evaluation and are set for imminent award.
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
Beaches and luxury drive regional tourism