Regional rail construction surges ahead

21 November 2025

 

> This package also includesMiddle East becomes a hub as rail networks mature


The GCC is at the centre of global rail construction activity after a decade of stop-start activity. Progress is being made on several large-scale rail schemes, providing renewed opportunities for international contractors to re-enter the market.

From the Qiddiya high-speed rail in Saudi Arabia to the planned expansion of Dubai’s metro network and the long-awaited revival of the GCC railway, a new wave of projects is shaping the region’s economic future.

Well-timed resurgence

According to data from regional projects tracker MEED Projects, the region boasts a pipeline of over $140bn-worth of railway schemes. Several factors are driving the renewed focus on major infrastructure.

Firstly, the region’s post-pandemic recovery has been underpinned by robust fiscal performance. Higher oil prices since 2022 have strengthened government balance sheets, enabling public investment in capital projects. Unlike in previous cycles, however, the current wave of spending is guided by a clearer vision rooted in diversification and long-term national development strategies.

Saudi Arabia’s Vision 2030, the UAE’s Centennial Plan 2071 and Oman’s Vision 2040 all emphasise connectivity, mobility and urban liveability as essential components of sustainable growth. Governments are therefore prioritising infrastructure that forms the backbone for tourism, logistics and housing development.

Secondly, project delivery capabilities have matured across the GCC. Local developers, contractors and authorities have gained experience delivering large and complex schemes such as the Dubai and Riyadh metros and Doha’s Fifa World Cup infrastructure. This has built confidence and the capacity to handle more ambitious undertakings.

Thirdly, global construction markets are shifting. With slowing growth in some developed economies, the GCC offers a stable, well-capitalised and politically supportive environment for investment. 

In addition, international contractors, consultants and suppliers are facing shrinking margins elsewhere and are therefore refocusing on the Gulf region’s more promising project pipelines.

Strong prospects

Saudi Arabia has a pipeline of about $60bn-worth of rail projects. The long-discussed Saudi Land Bridge, connecting the Red Sea to the Gulf through Riyadh, is being prepared for procurement. Once complete, it will be a 1,300-kilometre (km) corridor from Jeddah to Dammam, transforming freight logistics and positioning Saudi Arabia as a regional trade hub.

The kingdom’s planned Qiddiya high-speed rail, meanwhile, will link King Salman International airport with Qiddiya entertainment city. It is part of Riyadh’s broader mobility masterplan and reflects the government’s intention to integrate developments with efficient public transport.

Riyadh also continues to expand its metro system, with Line 7 currently under tendering. This addition will extend the network’s reach to growing urban districts, further embedding mass transit into the daily life of the city.


Dubai is moving forward with the proposed Metro Gold Line


In the UAE, the momentum is just as strong. The ongoing Etihad Rail project is entering a new phase with the anticipated rollout of passenger services, connecting Abu Dhabi, Dubai and eventually the northern emirates. Freight operations are already under way, providing a backbone for industrial connectivity and cross-border trade. Plans for an Abu Dhabi–Dubai high-speed link are also progressing as bid evaluation continues for the main construction works.

Dubai is also going ahead with the proposed Metro Gold Line, which is designed to serve new growth corridors and improve connectivity to emerging districts. 

Meanwhile, regional integration is back on the agenda with the GCC Railway, a long-delayed project that is finally gaining traction. Once realised, the network will connect Kuwait to Oman via Saudi Arabia, Bahrain, Qatar and the UAE, and governments are now actively coordinating to align standards, timelines and funding mechanisms.

The GCC offers a stable, well-capitalised and politically supportive environment for investment

Evolving delivery models

While public funding remains central to these initiatives, the GCC’s infrastructure landscape is also seeing a gradual shift towards new delivery and financing models.

Public-private partnerships (PPPs) are gaining traction, especially in Saudi Arabia. The proposed Qiddiya high-speed rail project is planned as a PPP, while several components of Hafeet Rail are being delivered through joint ventures providing financing arrangements.

This evolution comes with challenges, however. These frameworks must balance investor confidence with
public value, creating a need for clear risk allocation and transparent governance.

The scale and ambition of the ongoing projects have not gone unnoticed internationally. Leading construction, engineering, and technology firms are either expanding or returning to the region after years of reduced activity. 

Global rail specialists are competing for lucrative contracts in the region, while international consultancies are increasingly embedded in master planning and programme management roles.

The resurgence in project activity within the regional rail sector means firms will have many prospects to explore. 

“The regional market has not been this exciting in a long, long time,” a senior executive from a major international rail firm told MEED. 

“The market is shaping up for a golden era in rail and we will make sure that we give it our full attention.”

Another executive added: “This is primarily because of the resources available to governments now compared to in previous years, but more importantly [it is due to] the intent and will to make the projects happen.”

The GCC’s clear project pipeline and decisive execution are also a draw. Several rail projects in the region, such as Dubai Metro and Etihad Rail, have progressed from concept to implementation in relatively short timeframes.

Moreover, sustainability and innovation are becoming central to the GCC’s value proposition. Digital engineering, modular construction and low-carbon materials are being adopted more widely. 

Developers are under pressure to meet environmental standards and align with global best practices. Commitment to these concerns, particularly through the UAE and Saudi Arabia’s net-zero goals, further enhances the region’s attractiveness to global investors.

Bringing together transport, tourism, logistics and sustainability is creating a practical approach to modern urban development

Challenges ahead

Despite the optimism, challenges remain. Cost pressures, supply chain disruptions and competition for skilled labour could slow progress or inflate project budgets. 

The rapid pace of project launches also risks overstretching local capacity. Maintaining quality, timelines and financial discipline will require strong governance and careful coordination between various government agencies.

Long-term success depends on integrating infrastructure investment with broader social and economic goals. Transport systems must connect to affordable housing, job clusters and educational hubs, otherwise benefits remain limited. 

That said, the GCC has shown remarkable adaptability. The lessons learned from previous cycles, especially the importance of phasing, master planning and stakeholder alignment, are helping to shape current strategies. Authorities are more selective, prioritising projects that yield clear economic multipliers and align with national visions.

The current wave of infrastructure expansion looks set to position the GCC region as a global rail construction hotspot. The projects will also define the physical and economic landscape of the region for decades to come.

By connecting cities, ports, and industries, these projects are reshaping the region’s economy. Bringing together transport, tourism, logistics and sustainability is creating a practical approach to modern urban development.

If the previous era of regional construction was defined by skyscrapers and luxury resorts, the coming decade will be defined by connectivity and integration. The GCC’s major projects today are not about scale alone, but also about building more connected economies that can sustain growth.

The renewed momentum also presents an opportunity for regional governments to amplify their national ambitions by building more diversified economies, reducing carbon emissions and enhancing liveability.


Main image: Haramain high-speed train in Jeddah, Saudi Arabia


Middle East becomes a hub as rail networks mature: MEED interviews Martin Vaujour, Alstom’s Africa, Middle East and Central Asia region president

https://image.digitalinsightresearch.in/uploads/NewsArticle/15132273/main.gif
Yasir Iqbal
Related Articles
  • SLB passes evaluation for Kuwait upstream project

    12 December 2025

    The US-based oilfield services company SLB, formerly Schlumberger, has passed the technical bid evaluation for a major project to develop Kuwait’s Mutriba oil field.

    The Houston-headquartered company was the only bidder to pass the technical evaluation for the Mutriba integrated project management (IPM) contract.

    The minimum passing technical evaluation score was 75%.

    The full list of bidders was:

    • SLB (US): 97%
    • Halliburton (US): 72%
    • Weatherford (US): 61.5%

    The decision was finalised at a meeting of the Higher Purchase Committee (HPC) of state-owned Kuwait Petroleum Corporation (KPC) on 20 November 2025.

    According to a document published earlier this year by KOC, the IPM tender for the Mutriba field aims to “accelerate production through a comprehensive study that includes economic feasibility evaluation, well planning and long-term sustainability strategies”.

    The field was originally discovered in 2009.

    Commercial production from the Mutriba field started earlier this year, on 15 June, after several wells were connected to production facilities.

    The field is located in a relatively undeveloped area in northwest Kuwait and spans more than 230 square kilometres.

    The oil at the Mutriba field has unusually high hydrogen sulfide content, which can be as much as 40%.

    This presents operational challenges requiring specialised technologies and safety measures.

    In order to start producing oil at the field, KOC deployed multiphase pumps to increase hydrocarbon pressure and enable transportation to the nearest Jurassic production facilities in north Kuwait.

    The company also built long-distance pipelines stretching 50 to 70 kilometres, using high-grade corrosion-resistant materials engineered to withstand the high hydrogen sulfide levels and ensure long-term reliability.

    KOC also commissioned the Mutriba long-term testing facility in northwest Kuwait, with a nameplate capacity of around 5,000 barrels of oil a day (b/d) and 5 million standard cubic feet of gas a day (mmscf/d).

    Once this facility was commissioned, production stabilised at 5,000 b/d and 7 mmscf/d.

    In documents published earlier this year, KOC said that starting production from the field had “laid a solid foundation” for the IPM contract by generating essential reservoir and surface data that will guide future development.

    Future output from the field is expected to range between 80,000 and 120,000 b/d, in addition to approximately 150 mmscf/d of gas.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15235579/main.png
    Wil Crisp
  • Dana Gas makes onshore discovery in Egypt

    12 December 2025

    Register for MEED’s 14-day trial access 

    UAE-based Dana Gas has made an onshore gas discovery in Egypt’s Nile Delta area, according to a statement from the company.

    The discovery was made by the drilling of the North El-Basant 1 exploratory well, and initial well results indicate estimated reserves of 15-25 billion cubic feet of gas.

    Production from the reserve is expected to exceed 8 million cubic feet a day (cf/d) once the well is connected to the national network.

    The North El-Basant 1 exploratory well was the fourth well in a campaign of 11 development and exploration wells.

    The campaign is being executed as part of the company’s $100m investment programme to support domestic gas production, increase reserves and meet growing energy demand.

    Earlier this year, Dana Gas completed the drilling of three wells, adding 10 million cf/d.

    The programme is expected to increase long-term production and add approximately 80 billion cubic feet of recoverable gas reserves, according to Dana Gas.

    Dana Gas expects to start drilling the fifth well in the programme, the Daffodil exploration well, in the first week of January 2026.

    Richard Hall, the chief executive of Dana Gas, said: “The latest drilling success reinforces the value of our investment programme in Egypt and highlights the significant remaining potential within the Nile Delta.”

    He added: “By increasing local gas production, the programme will help reduce Egypt’s reliance on imported liquefied natural gas (LNG) and fuel oil and is expected to generate more than $1bn in savings for the national economy over time.”

    Previously, Dana Gas signed an agreement with state-owned Egyptian Natural Gas Holding Company (EGas) to secure additional acreage under improved fiscal terms, and to accelerate drilling activity.

    Hall said: “We appreciate the strong cooperation from EGas and the ministry, and we remain committed to delivering the majority of our planned programme next year.

    “Regular and timely payments from our partners are crucial to sustaining our investment programme in Egypt."

    In November, a new gas discovery was made in Egypt’s Western Desert region by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation and US-headquartered Apache Corporation.

    Egypt also started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.

    The country is currently pushing to increase gas production in order to meet domestic demand and reduce its import bill.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15235552/main.png
    Wil Crisp
  • SAR to tender new phosphate rail track section in January

    12 December 2025

     

    Register for MEED’s 14-day trial access 

    Saudi Arabian Railways (SAR) is expected to float another multibillion-riyal tender to double the tracks on the existing phosphate railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the Eastern Province.

    MEED understands that the new tender – covering the second section of the track-doubling works, spanning more than 150 kilometres (km) – will be issued in January.

    The new tender follows SAR’s issuance of the tender for the project's first phase in November, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.

    The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track.

    The scope also covers support for signalling and telecommunications systems.

    The tender notice was issued in late November, with a bid submission deadline of 20 January 2026.

    Switzerland-based engineering firm ARX is the project consultant.

    MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line.

    The other packages expected to be tendered shortly include the depot and the systems package.

    In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.

    Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15229624/main.jpg
    Yasir Iqbal
  • Dar Global to develop $4.2bn Oman mixed-use project

    10 December 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia-headquartered real estate developer Dar Global has announced that it will develop a mixed-use project in Muscat at an estimated investment of RO1.6bn ($4.2bn).

    Dar Global will co-develop the Muscat Marine, Art & Digital District project with Oman's Art District Real Estate Development Company.

    The project will cover an area of over 1.5 million square metres (sq m) and will be developed in several phases over 12 years.

    The development will comprise a mix of residential communities, cultural venues, marinas, retail spaces, finance and business parks and hotels.

    Dar Global, a subsidiary of Dar Al-Arkan, was one of the first Saudi brands to list on the London Stock Exchange.

    Dar Al-Arkan established Dar Global in 2017 to focus on developing projects in the Middle East and Europe, including in Dubai, Qatar, Oman, London and the Costa del Sol in southern Spain.

    Dar Global has $12bn-worth of projects under development in six countries: the UAE, Oman, Qatar, Saudi Arabia, the UK and Spain.

    It completed three developments – the Urban Oasis and Da Vinci towers in Dubai and the Sidra gated community in Bosnia – in 2023.

    The company collaborates with global brands including Missoni, W Hotels, Versace, Elie Saab, Automobili Pagani and Automobili Lamborghini.

    In Oman, Dar Global is also developing the Aida project. In May, it awarded a contract to develop the villas and apartments as part of the project.

    According to an official statement, the construction works are expected to start immediately and the project is slated for completion in 2026.

    The main contract was awarded to local firm Al-Adrak Trading & Contracting.

    The latest announcement follows the awarding of contracts in June last year for the development of the first phase of the Aida project.

    The Aida project is being developed as a joint venture with Omran Group and the first phase is expected to be completed in 2027.

    UK analytics firm GlobalData forecasts that the Omani construction industry will expand at an annual average growth rate of 4.2% in 2025-28. Growth in the country will be supported by rising government investments in renewable energy, the transport infrastructure and the housing sector, all as part of Oman's Vision 2040 strategy.

    Growth during the forecast period will also be supported by increasing hospitality sector investments, with the government planning to invest RO11.9bn ($31bn) in tourism development projects by 2040 and supporting the construction of several hospitality projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15222694/main.jpg
    Yasir Iqbal
  • Contract award nears for Saudi Defence Ministry headquarters

    10 December 2025

     

    Saudi Arabia’s Defence Ministry (MoD) is preparing to award the contract to build a new headquarters building, as part of its P-563 programme in Riyadh.

    MEED understands that bid evaluation has reached advanced stages and the contract award is imminent.

    The MoD issued the tender in April. The commercial bids were submitted in September, as MEED reported.

    Located to the northwest of Riyadh, the P-563 programme includes the development of facilities and infrastructure to support the MoD’s broader initiatives under the kingdom’s Vision 2030 strategy.

    It covers the construction of:

    • A new military city featuring the MoD headquarters, support and logistics facilities, a residential and commercial community and space for future command centres
    • A National Defence University with a library, conference centre and academic buildings
    • A self-sustaining Joint Forces Command compound located approximately 50 kilometres from the military city

    The budget for the entire programme is expected to be $10bn-$12bn.

    In September 2023, MEED reported that Spain-headquartered Typsa had won two contracts for the project.

    The first contract, worth $11.4m, included data management, geographic information systems management, geotechnical reporting and the preparation of the phase one final traffic report. The contract duration was 270 days from the notice to proceed.

    The second contract, valued at $10.8m, involved preparing four conceptual masterplans for the P-563 site. It was set to last 255 days from the notice to proceed.

    These followed a $290m consultancy contract awarded to Typsa in March of the same year. The single-award task order covered a three-year base period, with an optional two-year extension.

    Typsa’s scope of work included programme management planning, communications, change and quality management and cost and schedule tracking.

    It also included design requirements, codes, standards and submission requirements, programme guidance, study integration, risk analysis and management, design reviews and a programme-of-work breakdown plan.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here