Regional downstream sector prepares for consolidation

30 December 2024

 

The Middle East and North Africa (Mena) region’s midstream and downstream oil, gas and petrochemicals sectors together had one of their best years on record in 2024, with state-owned companies and private players collectively spending close to $38bn on projects.

Saudi Arabia emerged as the biggest regional spender on midstream and downstream projects. To address incremental volumes of gas entering the grid as Saudi Aramco increases its conventional and unconventional gas production, the state enterprise has spent more than $17bn on gas processing and transportation projects this year.

In April 2024, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

On 30 June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn. 

Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028 with the installation of about 4,000 kilometres
of pipelines and 17 new gas compression trains.

Abu Dhabi capex

The UAE has been the second-largest spender on midstream, downstream and chemicals projects in 2024, led by investments from Abu Dhabi National Oil Company (Adnoc) and Taziz – its 60:40 joint venture with industrial holding entity ADQ.

Adnoc’s biggest capital expenditure (capex) was in the form of a $5.5bn EPC contract that it awarded to a consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy to develop a greenfield liquefied natural gas (LNG) terminal complex in Ruwais. 

The upcoming Ruwais LNG export terminal will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each of which has a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.

Adnoc Group subsidiary Adnoc Gas has also advanced a project to expand its sales gas pipeline network across the UAE, which is known as Estidama. The Abu Dhabi-listed company has awarded two EPC packages of the project this year, which together were worth more than $500m. 

Adnoc Gas is expected to award the contract for another Estidama package before the end of 2024 that covers the construction of a pipeline that will provide feedstock from its Habshan gas processing plant to the upcoming Ruwais LNG complex.

Taziz, meanwhile, awarded three EPC contracts totalling $2bn for infrastructure works at the industrial chemicals zone that it is developing in Ruwais Industrial City.

Spending to plateau

Having reached a peak in spending, and with EPC contracts awarded for strategic midstream, downstream and chemicals projects in 2024, the Mena region is set to enter a period of more pragmatic project spending in 2025. However, this does not imply that a slump in project capex is likely, and the region could once again equal the level of contract awards made in 2024.

One of the largest projects that may be awarded in 2025 is the main contract for the North Field West LNG project – the third phase of QatarEnergy’s LNG expansion programme. 

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. 

The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore
gas reserve.

Taziz is also on course to make progress with the second expansion phase of its derivatives complex, which will more than double the number of chemicals produced at the industrial hub. The expansion’s centrepiece will be a large-scale steam cracker that will supply feedstocks to the several new chemical plants earmarked for third-party investments.

In Saudi Arabia, there has been speculation that Aramco may be revisiting its investment strategy and execution approach for its strategic liquids-to-chemicals programme. 

The aim of the programme is to derive greater economic value from every barrel of crude produced in the kingdom by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.

Aramco has divided its liquids-to-chemicals programme into four main projects. It took a major step forward
in September 2023 by selecting US firm KBR, France’s Technip Energies, UK-based Wood Group and Australia- headquartered Worley to provide project management consultancy services for the four different segments of the scheme.

Progress on a programme as big as the liquids-to-chemicals scheme is expected to be measured and laboured. 

While day-to-day the advancement might appear sluggish, Amin Nasser, Aramco’s president and CEO, said earlier in 2024 that the Saudi energy giant is on track to achieve its crude oil-to-chemicals conversion goal by 2030.

“We are on track to achieve our target of 4 million b/d liquids-to-chemicals [conversion capacity] by 2030,” he said.

Meanwhile, Kuwait is in a similar situation with its planned Al-Zour integrated complex upgrade programme (Zicup), which has suffered significant delays in recent years. However, state-owned Kuwait Integrated Petroleum Industries Company (Kipic), the project’s operator, recently appointed a team to look into the logistics of developing a benzine pipeline as part of the estimated $10bn Zicup scheme.

Although this may be a small step, it does indicate that Kuwait remains determined to achieve its ambition of developing a large-scale petrochemicals facility, which, when integrated with its $16bn Al-Zour refinery, could become one of the biggest integrated refining and petrochemicals complexes in the Mena region.

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13145202/main.gif
Indrajit Sen
Related Articles
  • Jordan sets market briefing for Amman water PPP

    10 April 2026

    Jordan’s Ministry of Investment, through its Public-Private Partnership Unit (PPPU), has announced a public information session for the South Amman non-revenue water (NRW) reduction PPP project.

    The session will be held on 15 April and is being organised in collaboration with the Ministry of Water & Irrigation and Miyahuna, according to a notice published by the PPPU. 

    The project covers the southern and southeastern areas of Amman and aims to reduce water losses and improve the efficiency of the capital’s distribution network.

    According to the ministry, the scheme will serve about 1.4 million people across 17 zones and forms part of Jordan’s wider National Water Strategy. 

    The planned market briefing is intended to provide early detail on the project’s PPP structure, procurement pathway and performance-based contracting model.

    It is also expected to outline the project’s risk allocation and bankability framework to prospective investors, operators and infrastructure companies.

    The Ministry of Investment opened prequalification for the scheme in March.

    Qualified companies and consortiums have been invited to participate in a two-stage procurement process for the performance-based contract. 

    The project aims to reduce NRW levels to 25% by 2040, while modernising and expanding the existing network using smart technologies and advanced leak detection systems. 

    The original deadline was 23 April. That has since been extended to 12 May.

    Jordan is among the most water-scarce countries in the world, and losses from distribution networks are estimated to account for about 45% of water supplied.

    The country is also advancing its $6bn Aqaba-Amman water desalination and conveyance project that aims to meet about 40% of Jordan’s municipal water demand by 2040.

    As MEED recently reported, the project is nearing financial close. Once complete, it will supply about 300 million cubic metres of potable water a year from the Red Sea to Amman and other regions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340931/main.jpg
    Mark Dowdall
  • OQ allows more time for natural gas liquids project proposals

    10 April 2026

     

    Omani state energy conglomerate OQ Group has allowed contractors more time to prepare proposals for a major project to build a natural gas liquids (NGL) facility in the sultanate.

    The planned NGL facility will extract condensates in Saih Nihayda in central Oman and transport those volumes to Duqm, located along the sultanate’s Arabian Sea coastline, for fractionation and export, OQ Group has said.

    OQ Group intends to deliver the project using a front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) competition model.

    The state enterprise issued the main tender for the feed-to-EPC competition “earlier in March”, setting an initial deadline of 8 April for contractors to submit proposals, MEED previously reported. The deadline has now been extended to 6 May, according to sources.

    MEED previously reported that OQ had started the prequalification process for the feed-to-EPC contest for the planned NGL project in November last year, with contractors submitting responses by 15 December.

    The following contractors, among others, are understood to have been invited to participate in the feed-to-EPC contest for OQ’s planned NGL project, sources told MEED:

    • Chiyoda (Japan) / CTCI (Taiwan)
    • G S Engineering & Construction (South Korea)
    • Hyundai Engineering & Construction (South Korea) / KBR (US)
    • JGC Corporation (Japan)
    • Kent (UAE)
    • Petrofac (UK)
    • Saipem (Italy)
    • Samsung E&A (South Korea) / Larsen & Toubro Energy Hydrocarbon (India) / Wood (UAE)
    • Technip Energies (France)
    • Tecnicas Reunidas (Spain)
    • Tecnimont (Italy)

    The scope of work on the project covers the development, verification and integration of feed deliverables for the following facilities and systems:

    • NGL extraction facility – Saih Nihayda:
      • Verification and updating of the existing feed to enable dual-mode operation (ethane recovery and ethane rejection).
      • Identification and implementation of required process, equipment, utilities, and control system modifications.
         
    • NGL Pipeline – Saih Nihayda to Duqm:
      Feed for a new approximately 230km NGL transmission pipeline, including routing, hydraulics, stations, pigging facilities, metering, corrosion protection, leak detection, and safety systems.
       
    • Fractionation unit at Duqm:
      • Feed for a new fractionation facility to process ethane and propane + NGL and recover propane, butane, condensate, and provision for future ethane recovery.
      • Design accommodating licensed or open-art technology and future tie-in to a planned petrochemical project in Duqm.
         
    • Product pipelines, storage and export facilities at Duqm jetty:
      • Feed for product pipelines, cryogenic and atmospheric storage tanks, vapour recovery systems, marine loading arms, and export facilities.
      • Integration with existing port and refinery infrastructure, where feasible.
         
    • Supporting systems and studies:
      Utilities, offsites, flare systems, safety and environmental studies, cost estimates (class 2+10%), project schedules, constructability assessments, and EPC tender documentation.
    Natural gas liquids projects

    Gulf national oil companies have been allocating significant capital expenditure to building or expanding NGL production facilities.

    QatarEnergy, in September last year, awarded the main EPC contract for its project to add a fifth NGL train at its fractionation complex in Qatar’s Mesaieed Industrial City. The aim of the project, which is estimated to be worth $2.5bn, is to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.

    The main EPC contract for the QatarEnergy NGL-5 project was won by a consortium of India’s Larsen & Toubro Energy Hydrocarbons Onshore and Greece-headquartered Consolidated Contractors Group.

    Separately, the gas processing business of Abu Dhabi National Oil Company (Adnoc Gas) has also selected the main contractor for a project to install a fifth NGL fractionation train at its Ruwais gas processing facility in Abu Dhabi.

    The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day, or about 8 million tonnes a year.

    The Ruwais NGL Train 5 project represents the second phase of Adnoc Gas’ ambitious Rich Gas Development (RGD) programme, and its budget value is estimated to be around $4bn, Peter Van Driel, Adnoc Gas’ chief financial officer, confirmed in February. The company expects to achieve final investment decision on the project within the first quarter of 2026, Van Driel said at the time.

    ALSO READ: PDO awards Oman gas plant expansion project
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340039/main5958.jpg
    Indrajit Sen
  • Masdar’s move abroad will not be the last

    10 April 2026

    Commentary
    Mark Dowdall
    Power & water editor

    Masdar’s new joint-venture agreement with France’s TotalEnergies will not be the last time we see regional energy investors use strong balance sheets and domestic growth to build larger positions overseas.

    For Masdar in particular, the deal broadens its international exposure at a time when investors are asking questions about the Middle East’s geopolitical risk.

    By combining portfolios, the two companies start with 3GW of operational capacity and another 6GW in advanced development.

    The deal covers nine Asian countries, reflecting a prudent strategy that spreads capital across markets with different risk profiles and growth trajectories.

    In Kazakhstan, which already includes 2.6GW of assets under development, there is clear logic behind this move.

    The country is expected to see a significant increase in renewable generation over the next decade, supported by strong wind resources and the availability of large land areas for utility-scale developments.

    There is also a practical advantage in partnering with TotalEnergies, which already has project delivery experience and an established presence in several of these markets.

    The US-Iran ceasefire announced on 8 April has brought some respite to energy infrastructure stakeholders in the region.

    For investors and developers, however, the long-term uncertainty remains. Until there is clear evidence of regime change, the removal of sanctions or lasting peace in the region, the outlook will be less clear.

    With uncertainty one of the biggest killers of investor confidence, many will now be looking at this agreement and thinking whether they should also follow suit.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340038/main.jpg
    Mark Dowdall
  • Turkish firm launches Mecca villas project

    10 April 2026

    Register for MEED’s 14-day trial access 

    Turkish real estate investment firm Emlak Konut has announced the launch of Hayat Makkah, its first development in Saudi Arabia.

    The project is part of the National Housing Company’s (NHC) wider Mecca Gate masterplan.

    According to the company, Hayat Makkah will feature 1,014 villas, with home sizes ranging from 150 to 5,000 square metres.

    NHC and Emlak Konut signed an investment agreement worth over SR1bn ($266m) in November last year to develop the project.

    The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.

    Ertan Keles, chairman of Emlak Konut, said the firm is in talks with stakeholders about launching a second project, while a third development is also being lined up in Jeddah.

    GlobalData expects the Saudi Arabian construction industry to grow by 3.6% in real terms in 2026, supported by an increase in foreign direct investment (FDI) and investments in the housing and manufacturing sectors.

    The residential construction sector is expected to grow by 3.8% in real terms in 2026 and register an average annual growth rate of 4.7% between 2027 and 2030, supported by the country’s aim – under Saudi Vision 2030 – to increase homeownership from 65.4% in 2024 to 70% by 2030, including by building 600,000 homes by 2030.

    According to the General Authority for Statistics, Saudi Arabia attracted a net FDI inflow of SR72.3bn ($19.3bn) in the first nine months of 2025, an increase of 32.7% year-on-year (YoY) compared to the same period in 2024.

    Similarly, the total value of real estate loans from banks grew by 11.5% YoY in 2025, preceded by an annual growth of 13.3% in 2024, according to the Saudi Central Bank (Sama).


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340004/main.png
    Yasir Iqbal
  • Kuwait gives bidders more time for Al-Khairan IWPP

    10 April 2026

     

    Kuwait has extended bidding for the first phase of the Al-Khairan independent water and power producer (IWPP) project.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant.

    The new deadline is 30 April. The original deadline was 31 March.

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate.

    These include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) / Jera (Japan)
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
    • China Power / Malakoff International (Malaysia) / Abdul Aziz Al-Ajlan Sons (Saudi Arabia)
    • Nebras Power (Qatar)                                                                                                                                        
    • Sumitomo Corporation (Japan)

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Kapp extended another deadline recently for a contract to develop zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic independent power project (IPP) in partnership with the ministry.

    The bid submission deadline was moved to the end of April, a source close to the project told MEED.

    According to the MEWRE, the total generation capacity currently offered under partnership projects has reached 6,100MW, equivalent to about 30% of Kuwait’s existing power capacity.

    The ministry and Kapp are also preparing to tender the main contract for the 3,600MW Nuwaiseeb power and water desalination plant after plans were approved by Kuwait’s Council of Ministers last November.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16339960/main.jpg
    Mark Dowdall