Regional downstream sector prepares for consolidation

30 December 2024

 

The Middle East and North Africa (Mena) region’s midstream and downstream oil, gas and petrochemicals sectors together had one of their best years on record in 2024, with state-owned companies and private players collectively spending close to $38bn on projects.

Saudi Arabia emerged as the biggest regional spender on midstream and downstream projects. To address incremental volumes of gas entering the grid as Saudi Aramco increases its conventional and unconventional gas production, the state enterprise has spent more than $17bn on gas processing and transportation projects this year.

In April 2024, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

On 30 June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn. 

Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028 with the installation of about 4,000 kilometres
of pipelines and 17 new gas compression trains.

Abu Dhabi capex

The UAE has been the second-largest spender on midstream, downstream and chemicals projects in 2024, led by investments from Abu Dhabi National Oil Company (Adnoc) and Taziz – its 60:40 joint venture with industrial holding entity ADQ.

Adnoc’s biggest capital expenditure (capex) was in the form of a $5.5bn EPC contract that it awarded to a consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy to develop a greenfield liquefied natural gas (LNG) terminal complex in Ruwais. 

The upcoming Ruwais LNG export terminal will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each of which has a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.

Adnoc Group subsidiary Adnoc Gas has also advanced a project to expand its sales gas pipeline network across the UAE, which is known as Estidama. The Abu Dhabi-listed company has awarded two EPC packages of the project this year, which together were worth more than $500m. 

Adnoc Gas is expected to award the contract for another Estidama package before the end of 2024 that covers the construction of a pipeline that will provide feedstock from its Habshan gas processing plant to the upcoming Ruwais LNG complex.

Taziz, meanwhile, awarded three EPC contracts totalling $2bn for infrastructure works at the industrial chemicals zone that it is developing in Ruwais Industrial City.

Spending to plateau

Having reached a peak in spending, and with EPC contracts awarded for strategic midstream, downstream and chemicals projects in 2024, the Mena region is set to enter a period of more pragmatic project spending in 2025. However, this does not imply that a slump in project capex is likely, and the region could once again equal the level of contract awards made in 2024.

One of the largest projects that may be awarded in 2025 is the main contract for the North Field West LNG project – the third phase of QatarEnergy’s LNG expansion programme. 

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. 

The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore
gas reserve.

Taziz is also on course to make progress with the second expansion phase of its derivatives complex, which will more than double the number of chemicals produced at the industrial hub. The expansion’s centrepiece will be a large-scale steam cracker that will supply feedstocks to the several new chemical plants earmarked for third-party investments.

In Saudi Arabia, there has been speculation that Aramco may be revisiting its investment strategy and execution approach for its strategic liquids-to-chemicals programme. 

The aim of the programme is to derive greater economic value from every barrel of crude produced in the kingdom by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.

Aramco has divided its liquids-to-chemicals programme into four main projects. It took a major step forward
in September 2023 by selecting US firm KBR, France’s Technip Energies, UK-based Wood Group and Australia- headquartered Worley to provide project management consultancy services for the four different segments of the scheme.

Progress on a programme as big as the liquids-to-chemicals scheme is expected to be measured and laboured. 

While day-to-day the advancement might appear sluggish, Amin Nasser, Aramco’s president and CEO, said earlier in 2024 that the Saudi energy giant is on track to achieve its crude oil-to-chemicals conversion goal by 2030.

“We are on track to achieve our target of 4 million b/d liquids-to-chemicals [conversion capacity] by 2030,” he said.

Meanwhile, Kuwait is in a similar situation with its planned Al-Zour integrated complex upgrade programme (Zicup), which has suffered significant delays in recent years. However, state-owned Kuwait Integrated Petroleum Industries Company (Kipic), the project’s operator, recently appointed a team to look into the logistics of developing a benzine pipeline as part of the estimated $10bn Zicup scheme.

Although this may be a small step, it does indicate that Kuwait remains determined to achieve its ambition of developing a large-scale petrochemicals facility, which, when integrated with its $16bn Al-Zour refinery, could become one of the biggest integrated refining and petrochemicals complexes in the Mena region.

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13145202/main.gif
Indrajit Sen
Related Articles
  • Iraq enters era of resilience, reform and rising risks

    11 May 2026

     

    Iraq’s projects market is at an inflection point. The country has built a sizeable and increasingly diverse projects pipeline, backed by ambitious national plans and an improving reform narrative. But according to MEED’s newly updated Iraq Projects Market report, the near-term outlook is now being tested by renewed regional volatility and persistent structural constraints at home.

    Iraq is the Middle East and North Africa’s fifth-largest economy by nominal GDP, yet it remains heavily exposed to the hydrocarbons cycle. Oil and gas generate about 90% of government revenues and more than 40% of GDP, a dependency that shapes annual capital spending and the bankability of public-private partnership (PPP) deals. Earlier this year, the IMF forecast GDP growth of 3%-4%. In light of the latest regional conflict dynamics involving the US and Israel with Iran, that growth outlook is expected to soften as investor risk perceptions rise and supply chains face renewed stress.

    Even so, Iraq’s projects market is not starting from a blank slate. By the end of March 2026, almost $120bn of contracts were in execution, with a further $300.4bn in the broader pipeline. The scale of that opportunity is underpinned by enduring reconstruction requirements, urgent energy-sector needs and a policy push to translate oil wealth into long-lived productive assets.

    Reconstruction needs

    Nearly a decade after the official end of the Islamic State conflict, Iraq’s reconstruction gap remains substantial. Estimates put the shortfall at about $88bn, reflecting the long tail of damage to housing, utilities, public buildings and transport links. Southern and central regions dominate the live pipeline, largely because they sit close to Iraq’s oil heartlands. Basra, in particular, is pivotal, anchoring major upstream activity and vital export infrastructure.

    At the policy level, Iraq Vision 2030 signals a long-term ambition to diversify into tourism, agriculture, industry and digital transformation. The government’s immediate delivery vehicle is the National Development Plan (NDP) 2024-28, which commits more than $17bn a year in capital expenditure and prioritises energy, transport, housing and water infrastructure. This shift is reinforced by Iraq’s Green Growth Framework (2026), indicating that future procurement may place greater weight on efficiency, emissions reduction and climate resilience.

    Macro risk

    Despite policy ambition, the most immediate determinant of Iraq’s fiscal room is the oil price. A $10-a-barrel drop can reduce government revenue by an estimated $7bn-$9bn annually. Such sensitivity matters because infrastructure spending is still largely funded by the public purse. Oil price swings affect project awards, payment cycles and the government’s willingness to assume up-front capex obligations.

    Iraq’s execution environment continues to be defined by bureaucratic delays, unclear land titles and opaque procurement processes. These factors can add 12-24 months to average delivery timelines. Nevertheless, there are signs of adaptation. PPP legislation is advancing, and developer-led models are gaining traction in large housing programmes. Furthermore, there is a growing reliance on international project management consultancy (PMC) firms—such as Hill International, Worley, and AtkinsRealis—to bridge capacity gaps and improve governance, cost control and scheduling.

    Hydrocarbon driver

    Oil and gas upstream remains the single largest driver of capital expenditure. Major developments, including the Gas Growth Integrated Project (GGIP) and Mansouriya, sit alongside a push to reduce gas flaring and expand downstream processing. The objective is to sustain export revenues while improving domestic fuel availability.

    The power sector is even more urgent. Iraq faces an estimated 8-10GW generation shortfall, which keeps electricity supply at the centre of political risk. This gap is driving rapid procurement of generation capacity and grid upgrade contracts. Beyond traditional infrastructure, Iraq is also moving on digital adoption. Smart city pilots and fibre rollouts are attracting regional technology investors, while AI-enabled data centre projects are beginning to emerge.

    Investment targets

    Foreign direct investment (FDI) remains below $3bn a year, a low figure relative to market size. The most active investors outside the oil sector include the UAE, Saudi Arabia and Kuwait. To convert interest into deals, the National Investment Commission (NIC) is pursuing streamlined licensing and investor-protection reforms. A “one-stop shop” approach has reportedly reduced registration timelines for foreign investors from months to weeks in key sectors.

    Investor protection mechanisms, such as access to international arbitration, are being strengthened, though enforcement remains a concern. Iraq’s three free zones—Basra, Karbala and Nineveh—offer additional incentives including tax holidays and customs exemptions, provided they can be paired with reliable utilities and bankable arrangements.

    Conflict premium

    The latest escalation involving the US and Israel with Iran has increased Iraq’s security risk premium. This is inflating materials costs and disrupting supply chains near eastern border zones. Even where projects are far from conflict areas, contractors are pricing in higher contingency for logistics and insurance. Iraq must also balance deep economic ties with Iran—particularly in energy—with Western investor expectations and sanctions-related compliance.

    With more than 60% of its population under 25, Iraq has a potential demographic dividend, but it also faces immediate employment pressure and a shortage of skilled technical labour. Iraq’s projects market outlook for 2026 is best described as cautiously constructive. The pipeline is deep and the need is undeniable, but delivery will hinge on whether Iraq can translate plans into predictable execution. If progress on procurement and contract enforcement continues, Iraq can sustain a broad-based market that extends beyond hydrocarbons.

    Click here to learn more about MEED’s newly updated Iraq Projects Market report

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16782507/main.gif
    Colin Foreman
  • Retal to develop project in Oman’s Sultan Haitham City

    11 May 2026

    Saudi Arabia’s Retal Urban Development Company has entered Oman with its first development agreement, signing a deal to build more than 2,000 residential units in Sultan Haitham City in Muscat.

    In a statement to the Saudi Stock Exchange (Tadawul) on 11 May, the company said it had signed an agreement with Oman’s Ministry of Housing & Urban Planning to develop an integrated residential community at an estimated cost of SR3bn ($823m).

    The community will be developed across zones 3, 15 and 17 within Sultan Haitham City, covering a total area of 1.3 million square metres.

    The project will include villas and apartments, alongside commercial and mixed-use elements and community facilities.

    Retal said the development will be delivered through an off-plan sales model and is expected to take nearly nine years to complete.

    The first phase of the Sultan Haitham City project includes the development of a 5 square-kilometre city centre and six of the development’s 19 planned neighbourhoods. The first phase is set for completion by 2030.

    US-based architectural firm SOM unveiled masterplan proposals for Sultan Haitham City in August 2024.

    The final phase of the project is expected to be completed by 2045.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16781867/main.jpg
    Yasir Iqbal
  • Qiddiya seeks firms for light rail transit system

    11 May 2026

     

    Saudi gigaproject developer Qiddiya Investment Company (QIC) has requested contractors to express interest in a contract to design and build the first phase of the light rail transit system at Qiddiya Entertainment City.

    The notice was issued on 5 May, with firms given until 20 June to submit expressions of interest.

    The project, also known as the Primary Urban Axis, comprises a 22-kilometre automated, driverless rail line as part of its first phase.

    The contract scope includes about 16 stations – 11 elevated and five underground – along with 8km of tunnels, viaducts and other associated structures. It covers all civil, architectural, and mechanical, electrical and plumbing works.

    Stations will be located at Resort Core East Village, Grand Central Station, Anime Hub Integrated Station and Primary Urban Axis 1 & 2 Hub Station.

    A subsequent phase will extend the railway network by a further 11km.

    QIC is accelerating plans to develop additional assets at Qiddiya City.

    Separately, QIC, the Royal Commission for Riyadh City and the National Centre for Privatisation & PPP received prequalification statements from firms on 30 April for the public-private partnership (PPP) package of the Qiddiya high-speed rail project in Riyadh. This follows submission of prequalification statements for the engineering, procurement, construction and financing package on 16 April, as previously reported by MEED.

    The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at up to 250 kilometres per hour, reaching Qiddiya in 30 minutes.

    Contractors are also preparing bids for a 13 May deadline for a contract covering new infrastructure works at Qiddiya Entertainment City. The scope includes two infrastructure development packages for District 0, including the construction of four event park-and-ride facilities.

    QIC’s other major projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    QIC officially opened the Six Flags theme park to the public in December last year.

    The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16779176/main.jpg
    Yasir Iqbal
  • RCRC awards $1bn Sheikh Jaber Al-Sabah Road contract

    11 May 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Royal Commission for Riyadh City (RCRC) has awarded an estimated SR5bn ($1.3bn) contract for the construction of the Sheikh Jaber Al-Sabah Road project in Riyadh.

    The contract was awarded to the joint venture of Riyadh-based Al-Rashid Trading & Contracting Company (RTCC) and Turkiye’s IC Ictas.

    The project stretches 12 kilometres (km) from Khurais Road to Al-Thumama Road in Riyadh.

    The Sheikh Jaber Al-Sabah Road project is a key component of the Second Eastern Ring Road scheme. 

    The project includes the construction of five interchanges: Prince Bandar interchange, King Abdullah interchange, Imam Abdullah interchange, Dammam Road interchange and Al-Thumama interchange.

    The latest contract marks another significant project award to the RTCC-IC Ictas joint venture by RCRC. 

    In June 2024, RCRC awarded an estimated SR4bn ($1bn) design-and-build contract to upgrade the Wadi Laban cable bridge in Riyadh to the joint venture of RTCC and IC Ictas.

    The project aims to ease traffic congestion around the Western Ring Road in the area extending from Ibn-Hazm Road to Jeddah Road. The contract also covers the construction of an intersection at Jeddah Road.

    The construction of the bridge originally began in August 1993 and was completed in 1997.

    The existing bridge is 763 metres long and 35 metres wide, with two 14-metre-wide carriageways. 

    In 2021, Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud said the population of Riyadh would double to 15-20 million people by 2030. 

    He directed government entities to work closely with the RCRC to prepare the city’s development strategy.

    The RCRC’s major projects include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park, Green Riyadh and several road development projects in the capital.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16775717/main.jpg
    Yasir Iqbal
  • Aecom to supervise Dubai Loop construction

    11 May 2026

     

    Register for MEED’s 14-day trial access 

    US-based Aecom has been selected for a contract to undertake design review and construction supervision services for the Dubai Loop transportation system.

    The contract was tendered by Dubai’s Roads & Transport Authority (RTA), which signed a construction agreement with Elon Musk-backed firm The Boring Company.

    The first phase comprises a 6.4-kilometre route with four stations, linking the Dubai International Financial Centre (DIFC) and Dubai Mall.

    Stations will be located at DIFC 2, ICD Brookfield Place, Dubai Mall Zabeel Parking and Burj Khalifa.

    The first phase is expected to cost about AED565m ($154m) and be delivered within one year of design work and other preparations being completed. Tunnelling is expected to begin in the second half of this year.

    The latest update follows the appointment of Parsons Corporation to deliver programme management services for the Dubai Loop transportation system.

    Next phase

    The second phase will connect the Dubai World Trade Centre and DIFC with Business Bay.

    The tunnels will extend up to 22km and include 19 stations.

    The total cost across both phases is expected to be around AED2bn ($545m), with completion scheduled within three years.

    The pilot route is expected to serve around 13,000 passengers a day, while the full route is projected to have a capacity of about 30,000 passengers a day.

    The RTA and The Boring Company signed a memorandum of understanding on the sidelines of the World Governments Summit in Dubai in February last year to explore the development of the Dubai Loop transportation system.

    The Dubai Loop is expected to be similar to The Boring Company’s Las Vegas Convention Centre (LVCC) Loop project. The LVCC Loop is a 2.7km underground tunnel system that connects different convention centre halls, reducing walking time across the site to about two minutes.

    The LVCC Loop has been in operation since 2021. It uses Tesla Model 3 cars to carry passengers between five stations. The Boring Company began construction in November 2019 at an estimated cost of $49m.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16775632/main.jpg
    Yasir Iqbal