Regional downstream sector prepares for consolidation

30 December 2024

 

The Middle East and North Africa (Mena) region’s midstream and downstream oil, gas and petrochemicals sectors together had one of their best years on record in 2024, with state-owned companies and private players collectively spending close to $38bn on projects.

Saudi Arabia emerged as the biggest regional spender on midstream and downstream projects. To address incremental volumes of gas entering the grid as Saudi Aramco increases its conventional and unconventional gas production, the state enterprise has spent more than $17bn on gas processing and transportation projects this year.

In April 2024, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

On 30 June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn. 

Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028 with the installation of about 4,000 kilometres
of pipelines and 17 new gas compression trains.

Abu Dhabi capex

The UAE has been the second-largest spender on midstream, downstream and chemicals projects in 2024, led by investments from Abu Dhabi National Oil Company (Adnoc) and Taziz – its 60:40 joint venture with industrial holding entity ADQ.

Adnoc’s biggest capital expenditure (capex) was in the form of a $5.5bn EPC contract that it awarded to a consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy to develop a greenfield liquefied natural gas (LNG) terminal complex in Ruwais. 

The upcoming Ruwais LNG export terminal will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each of which has a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.

Adnoc Group subsidiary Adnoc Gas has also advanced a project to expand its sales gas pipeline network across the UAE, which is known as Estidama. The Abu Dhabi-listed company has awarded two EPC packages of the project this year, which together were worth more than $500m. 

Adnoc Gas is expected to award the contract for another Estidama package before the end of 2024 that covers the construction of a pipeline that will provide feedstock from its Habshan gas processing plant to the upcoming Ruwais LNG complex.

Taziz, meanwhile, awarded three EPC contracts totalling $2bn for infrastructure works at the industrial chemicals zone that it is developing in Ruwais Industrial City.

Spending to plateau

Having reached a peak in spending, and with EPC contracts awarded for strategic midstream, downstream and chemicals projects in 2024, the Mena region is set to enter a period of more pragmatic project spending in 2025. However, this does not imply that a slump in project capex is likely, and the region could once again equal the level of contract awards made in 2024.

One of the largest projects that may be awarded in 2025 is the main contract for the North Field West LNG project – the third phase of QatarEnergy’s LNG expansion programme. 

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. 

The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore
gas reserve.

Taziz is also on course to make progress with the second expansion phase of its derivatives complex, which will more than double the number of chemicals produced at the industrial hub. The expansion’s centrepiece will be a large-scale steam cracker that will supply feedstocks to the several new chemical plants earmarked for third-party investments.

In Saudi Arabia, there has been speculation that Aramco may be revisiting its investment strategy and execution approach for its strategic liquids-to-chemicals programme. 

The aim of the programme is to derive greater economic value from every barrel of crude produced in the kingdom by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.

Aramco has divided its liquids-to-chemicals programme into four main projects. It took a major step forward
in September 2023 by selecting US firm KBR, France’s Technip Energies, UK-based Wood Group and Australia- headquartered Worley to provide project management consultancy services for the four different segments of the scheme.

Progress on a programme as big as the liquids-to-chemicals scheme is expected to be measured and laboured. 

While day-to-day the advancement might appear sluggish, Amin Nasser, Aramco’s president and CEO, said earlier in 2024 that the Saudi energy giant is on track to achieve its crude oil-to-chemicals conversion goal by 2030.

“We are on track to achieve our target of 4 million b/d liquids-to-chemicals [conversion capacity] by 2030,” he said.

Meanwhile, Kuwait is in a similar situation with its planned Al-Zour integrated complex upgrade programme (Zicup), which has suffered significant delays in recent years. However, state-owned Kuwait Integrated Petroleum Industries Company (Kipic), the project’s operator, recently appointed a team to look into the logistics of developing a benzine pipeline as part of the estimated $10bn Zicup scheme.

Although this may be a small step, it does indicate that Kuwait remains determined to achieve its ambition of developing a large-scale petrochemicals facility, which, when integrated with its $16bn Al-Zour refinery, could become one of the biggest integrated refining and petrochemicals complexes in the Mena region.

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13145202/main.gif
Indrajit Sen
Related Articles
  • Contractors prepare bids for Oxagon wastewater plant

    14 September 2026

     

    Contractors are preparing to submit bids to build a wastewater treatment plant for Oxagon, Neom’s industrial cluster.

    The industrial wastewater treatment package will have an initial capacity of 35,000 cubic metres a day (cm/d), supplied in modular trains of 5,000 cm/d each. A separate sanitary wastewater treatment package will have a capacity of 1,000 cm/d.

    The contract is structured as a design-build-operate project and covers the supply, installation and commissioning of industrial and sanitary wastewater treatment packages, as well as three years of operation and maintenance.

    Bids are due on 2 October, a source close to the project told MEED.

    It is understood that Neom’s water utility Enowa issued the request for proposals earlier this year. The plant is designed to provide “interim wastewater treatment” capacity for Neom’s Oxagon Industrial Quarter as industrial development in the area progresses.

    Enowa has described the treatment systems as interim and de-mountable, allowing them to be installed and subsequently removed or relocated as requirements at Oxagon develop. The plant can be expanded to a maximum of 45,000 cm/d.

    The tender documents also state that Neom may consider export credit agency (ECA) financing for the project, with the strength of bidders’ ECA financing proposals forming part of the commercial evaluation.

    The project follows an earlier tender for the Oxagon Village Water Recycling Plant, which was cancelled despite contractors submitting bids in 2024.

    MEED reported at the time that Beijing-based PowerChina, the local Alfanar Company and Cairo-headquartered Orascom had submitted bids for the project. It is understood that these firms are also likely to participate in the latest tender.

    The earlier scheme included truck receiving facilities, pretreatment, biological treatment using food chain reactor technology, tertiary treatment, sludge handling and recycled-water storage.

    The latest procurement appears to represent a reworked approach to wastewater treatment at Oxagon Industrial Quarter, with the previous engineering, procurement and construction scheme replaced by an interim, modular and de-mountable facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19640903/main.jpg
    Mark Dowdall
  • Saudi Arabia shuts East-West oil pipeline after drone strikes

    14 September 2026

    Saudi Arabia has temporarily closed its 1,200-kilometre East-West pipeline after it was targeted by multiple drones launched from Iraq, disrupting one of the kingdom’s most critical energy export routes and threatening global oil supplies already strained by conflict across the region.

    The Ministry of Energy said the pipeline, which connects the Abqaiq oil field in the east to the Red Sea port of Yanbu, was hit in the Riyadh and Medina regions on 12 September. Specialised teams have begun securing the facility and assessing damage. A Foreign Ministry statement said the attack resulted in injuries and “some damage that is currently being addressed”.

    The closure removes about 4 million barrels a day from the global market, representing 4% of world oil supply. The pipeline’s role has become increasingly critical since the US-Iran conflict forced a near-complete shutdown of flows through the Strait of Hormuz in March.

    Saudi Arabia has been using the East-West route to bypass the chokepoint, but the assault has left the kingdom dependent on substantially reduced Hormuz exports and Red Sea shipping routes now threatened by Iran-backed Houthi forces in Yemen.

    Iraqi Prime Minister Ali Al-Zaidi’s office confirmed the drone strike on the East-West Pipeline originated in the Maysan province, which borders Iran. The government formally condemned the attack, announced an investigation into the Maysan operations command and dismissed its commander. No armed group has claimed responsibility, but security analysts attribute the strike to Iran-backed militias operating from Iraqi territory.

    Riyadh said it was not retaliating “at this stage”, choosing instead to support Iraqi efforts to prevent further strikes from its territory. 

    The attack comes amid wider regional upheaval. Houthi forces have rapidly advanced along Yemen’s coast, seizing the strategic Mokha port and the Zuqar Island in the southern Red Sea, moving closer to the Bab El-Mandab strait. Saudi authorities said the group simultaneously launched dozens of drones and missiles at the southern kingdom on 11 September, striking civilian and economic targets and injuring 73 people.

    Oil analysts and traders reported that Yanbu’s storage capacity, estimated at around 35 million barrels, now holds supplies sufficient for only five to seven days of exports without pipeline operations. Storage facilities at Egypt’s Ain Sokhna and Sidi Kerir ports have similar constraints. Repair timelines remain uncertain, with sources citing estimates ranging from days to five or six weeks.

    The dual disruption of both the pipeline and Red Sea shipping has compressed global energy supplies. Energy analysts warned that without pipeline repairs, oil prices could return to the $120-a-barrel peak reached earlier in the regional conflict.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19641513/main.gif
    Colin Foreman
  • WSP wins Dammam airport expansion design works

    14 September 2026

    WSP Middle East, the regional arm of Canadian engineering firm WSP, has won a design contract to expand King Fahd International airport in Dammam, Saudi Arabia.

    Dammam Airports Company (DACO) awarded the contract.

    The scope includes designing passenger terminal expansions, facility upgrades, and improvements to airport entrances and access roads.

    It also covers the development of baggage-handling systems, digital services and other associated infrastructure.

    The expansion works will be carried out in line with the airport’s approved masterplan, which targets serving more than 19 million passengers a year by 2030.

    The plan also aims to increase air cargo capacity to more than 600,000 tonnes a year and raise aircraft operational capacity to 77 movements per hour, supported by comprehensive expansions to infrastructure, runways and general aviation facilities.

    This contract forms part of DACO’s ongoing efforts to strengthen the airport ecosystem, enhance operational efficiency, and support the Aviation Programme and Saudi Vision 2030 objectives.

    King Fahd International airport is the kingdom’s third-largest airport by annual passenger traffic, behind Jeddah’s King Abdulaziz International and Riyadh’s King Khaled International.

    DACO was formed in July 2017 to manage, operate and develop King Fahd International airport in Saudi Arabia’s Eastern Province.

    It was established as part of the broader Saudi Vision 2030 privatisation and economic reform programme to corporatise the aviation sector, increase operational efficiency, upgrade infrastructure, and transition state-run airports into commercially viable, world-class regional aviation hubs.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19639910/main.jpg
    Yasir Iqbal
  • Dubai seeks contractors for multibillion-dollar road scheme

    14 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai’s Roads & Transport Authority (RTA) is seeking contractors to design and build a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.

    MEED understands that the scope covers the construction of about 30 kilometres (km) of works.

    These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.

    The RTA floated the expression of interest notice to contractors in early September, with a submission deadline of 10 October.

    The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.

    Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.

    The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through-traffic while the existing at-grade lanes served local access.

    The plans ultimately progressed as standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.

    The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.

    Planning for growth

    Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19639621/main.gif
    Yasir Iqbal
  • Kuwait postpones contractor meeting for $3.3bn gas project

    14 September 2026

     

    State-owned Kuwait Gulf Oil Company (KGOC) has rescheduled a key meeting about the development of the planned onshore gas plant next to the Al-Zour refinery, according to industry sources.

    The project was tendered last month with an estimated budget of $3.3bn and a bid deadline of 29 December 2026.

    If it goes ahead as planned, the project is expected to be the country’s biggest oil and gas sector contract award in more than a decade.

    The meeting with contractors is now scheduled for 14 October 2026. Previously, it was scheduled to take place on 14 September.

    Sources said contractors have not been told why the meeting date was pushed back.

    While the date for the initial meeting with contractors has been postponed, the bid deadline of 29 December 2026 remains the same, according to industry sources.

    The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    In February, MEED reported that at least seven companies had shown interest in participating in the tender.

    Contractors that sent representatives to previous meetings to discuss the project include:

    • Samsung E&A (South Korea)
    • Larsen & Toubro (India)
    • Tecnicas Reunidas (Spain)
    • Saipem (Italy)
    • Hyundai Engineering & Construction (South Korea)
    • Hyundai Engineering Company (South Korea)
    • JGC (Japan)

    The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.

    Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.

    It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.

    Iran disputes ownership of the field, referring to it as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.

    The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19639451/main.jpg
    Wil Crisp