Region to continue robust spending on oil and gas

29 December 2024

 

The upstream oil and gas industry in the Middle East and North Africa (Mena) region recorded more than $53bn of capital expenditure (capex) on oil and gas production projects in 2023. 

It was forecast that the sector might never repeat that level of spending on engineering, procurement and construction (EPC) contracts, especially with hydrocarbons producers striving to achieve their net-zero carbon emissions goals and broader sustainability commitments.

Abu Dhabi National Oil Company (Adnoc) led capex on Mena production projects in 2023, largely due to its $17bn spending on the Hail and Ghasha offshore sour gas development project.

Saudi Aramco was the second-largest spender in the region in 2023, on the back of the estimated $10bn-worth of EPC contracts it awarded for the second expansion phase of its Jafurah unconventional gas development. It also maintained spending on offshore field upgrade works, awarding about $5.3bn-worth of engineering, procurement, construction and installation (EPCI) contracts.

Yet upstream project spending in 2024 year-to-date has surpassed 2023’s level, with Mena hydrocarbons producers collectively spending more than $58bn on oil and gas production capacity maintenance and expansion projects.

Record year

Iran emerged as the largest spender in the Mena upstream sector in 2024, with the country’s capex exceeding $22bn. State-owned Pars Oil & Gas Company spent $20bn on EPC contracts in March, on a project to boost gas output capacity at the South Pars field.

Iran shares the South Pars field with Qatar, where it is known as North Field. The natural gas reserve in the Gulf’s waters is estimated to hold 1,800 trillion cubic feet of gas and 50 billion barrels of condensates.

Pars Oil & Gas Company aims to produce 90 trillion cubic feet of gas and 2 billion barrels of condensates from the latest expansion phase of the South Pars field development. The company expects to generate $900bn in total revenues from the expansion project.

Qatar was the second-largest spender in the region in 2024, with state enterprise QatarEnergy advancing its North Field production sustainability (NFPS) project, which aims to support its liquefied natural gas (LNG) expansion programme with gas feedstock.

QatarEnergy LNG, a subsidiary of QatarEnergy, awarded Italian contractor Saipem an estimated $4bn EPCI contract in September as part of the second phase of its NFPS project.

Saipem was awarded two packages, the scope of which encompasses EPCI work on a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

Separately, in January, Qatar’s North Oil Company awarded $6bn-worth of contracts for four engineering, procurement, construction, installation and commissioning packages on a project to increase oil production from its Al-Shaheen offshore oil field by about 100,000 barrels a day (b/d).

The project, known as Ruya, is the third capacity-expansion phase of the Al-Shaheen oil field, which has a production potential of 300,000 b/d at present. North Oil Company – a joint venture of QatarEnergy (70%) and France’s TotalEnergies (30%), which has been the operator of Al-Shaheen since July 2017 – aims to increase the field’s output through the Ruya project.

Saudi offshore spending

In late January 2024, the Saudi Energy Ministry directed Aramco to abandon its campaign to expand its oil production spare capacity from 12 million b/d to 13 million b/d by 2027. As a consequence, Aramco cancelled the tendering process for at least 15 tenders involving the EPCI of structures at offshore oil and gas fields.

Since that decision, however, Aramco has gone the other way, spending an estimated $4.5bn in 2024 on offshore EPCI contracts, known in the Aramco ecosystem as CRPOs. 

Saipem has been the biggest beneficiary of Aramco’s offshore spending, winning all of the CRPOs awarded in 2024. In early May, Aramco awarded the contractor CRPO 143, which involves replacing an oil line between the Berri and Manifa oil fields in the kingdom’s Gulf waters.

Aramco then awarded Saipem the contract for CRPO 138, which involves laying a trunkline at the Abu Safah offshore field. The contract is estimated to be worth $500m. 

The firm then scooped three major CRPOs in August, starting with CRPOs 132 and 139, the combined value of which is estimated to be about $1bn. In early September, Saipem began work on the two contracts, which involve the EPCI of structures to upgrade the Marjan, Zuluf and Safaniya offshore field developments.

Just days later, Aramco awarded Saipem CRPO 127, a $2bn contract that involves EPCI of topsides and jackets for wellhead platforms, a tie-in platform jacket and topside, rigid flowlines, submarine composite cables and fibre optic cables at the Marjan oil and gas field.

Jafurah development

Aramco has also made swift progress in 2024 on successive expansion phases of its programme to produce and process gas from the Jafurah unconventional development in Saudi Arabia. Spending on the Jafurah expansion projects, along with offshore contracts, helped to make the kingdom the third-biggest upstream spender in the Mena region.

Aramco awarded contracts on 30 June for the Jafurah second expansion phase, which aims to raise processing potential to up to 2 billion cubic feet a day (cf/d) of raw gas. Aramco awarded 16 contracts, worth about $12.4bn, for EPC works and drilling services for the second expansion phase.

Within weeks of those awards, a consortium of Spanish contractor Tecnicas Reunidas and China’s Sinopec Group announced that it had been selected by Aramco to carry out EPC works on the third expansion phase at Jafurah, worth $2.24bn. The EPC scope mainly covers building three gas compression plants, each capable of processing 200 million cf/d. Aramco officially awarded the contract to the Tecnicas Reunidas/Sinopec consortium in late September.

Capex to hold steady

While the Mena upstream oil and gas industry may not be able to match its 2024 level of project capex in 2025, the sector is expected to maintain a robust level of spending, especially with national energy companies striving to achieve their strategic long-term oil and gas production capacity goals before the end of the decade.

Data from regional projects tracker MEED Projects suggests that the Mena upstream sector could invest about $40bn on projects in 2025, with gas output expansion schemes predicted to dominate spending.

In line with its target to increase gas production by 60% by 2030, with 2021 as its baseline, Aramco is on course to further advance its Jafurah unconventional gas production programme. It issued the main EPC tender for the fourth expansion phase of the programme in July, within days of selecting the main contractors for the third phase.

Contractors are preparing bids for the project, the scope of which is similar to that of the third expansion phase, and which is therefore understood to be valued at $2.5bn.

Saudi Arabia’s spending on offshore brownfield and greenfield EPCI contracts is set to remain high, with the tendering process under way for eight more Aramco CRPOs.

Four tenders were issued in August for CRPOs 149, 150, 152 and 153, which cover the EPCI works on the Arabiyah, Hasbah and Marjan offshore oil field developments. Of the four CRPOs, contractors in Saudi Aramco’s Long-Term Agreement (LTA) pool have submitted bids for 149, 152 and 153. 

Separately, LTA contractors are also preparing bids for four tenders worth a total of $4bn, which will further expand the Zuluf offshore field development.

Meanwhile, Iran is expected to give shape to its plan for gas extraction from its North Pars field, along with raising output from its onshore and offshore oil fields. Increasing production is vital for Tehran in order to maintain steady volumes of exports to earn vital revenue for its economy, which has been crippled by years of international sanctions.

Pars Oil & Gas Company is estimated to have allocated $15bn to the North Pars gas field development project. However, with the project being in the study phase, and with Iran’s cash-strapped government barely able to provide support to its population, the scheme could see little to no progress in 2025.

In the UAE, with the deadline approaching for Adnoc’s target of raising crude output capacity to 5 million b/d by 2027, it is anticipated that the company will funnel billions of dollars into increasing the production potential of its onshore and offshore oil fields. 

Adnoc Group subsidiary Adnoc Offshore is evaluating bids for three packages of a multibillion-dollar project to boost oil production at the Lower Zakum offshore hydrocarbons concession in Abu Dhabi. The goal of the first phase of the Lower Zakum long-term development plan is to raise the asset’s output capacity to 520,000 b/d by 2027 and maintain that level until 2034. 

Adnoc Offshore has also started the tendering exercise for front-end engineering and design work on the second expansion phase of the Umm Shaif offshore oil field.

Another Adnoc Group subsidiary, Adnoc Onshore, has made a significant capex investment in growing crude output from its main Bab, Northeast Bab, Bu Hasa and Southeast fields. As a result, it is on course to award more contracts in 2025 to maintain and eventually increase output from these fields through its P5 projects, which aim to achieve an oil production potential of 5 million b/d by 2027. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13100083/main.gif
Indrajit Sen
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp