Region to continue robust spending on oil and gas
29 December 2024

The upstream oil and gas industry in the Middle East and North Africa (Mena) region recorded more than $53bn of capital expenditure (capex) on oil and gas production projects in 2023.
It was forecast that the sector might never repeat that level of spending on engineering, procurement and construction (EPC) contracts, especially with hydrocarbons producers striving to achieve their net-zero carbon emissions goals and broader sustainability commitments.
Abu Dhabi National Oil Company (Adnoc) led capex on Mena production projects in 2023, largely due to its $17bn spending on the Hail and Ghasha offshore sour gas development project.
Saudi Aramco was the second-largest spender in the region in 2023, on the back of the estimated $10bn-worth of EPC contracts it awarded for the second expansion phase of its Jafurah unconventional gas development. It also maintained spending on offshore field upgrade works, awarding about $5.3bn-worth of engineering, procurement, construction and installation (EPCI) contracts.
Yet upstream project spending in 2024 year-to-date has surpassed 2023’s level, with Mena hydrocarbons producers collectively spending more than $58bn on oil and gas production capacity maintenance and expansion projects.
Record year
Iran emerged as the largest spender in the Mena upstream sector in 2024, with the country’s capex exceeding $22bn. State-owned Pars Oil & Gas Company spent $20bn on EPC contracts in March, on a project to boost gas output capacity at the South Pars field.
Iran shares the South Pars field with Qatar, where it is known as North Field. The natural gas reserve in the Gulf’s waters is estimated to hold 1,800 trillion cubic feet of gas and 50 billion barrels of condensates.
Pars Oil & Gas Company aims to produce 90 trillion cubic feet of gas and 2 billion barrels of condensates from the latest expansion phase of the South Pars field development. The company expects to generate $900bn in total revenues from the expansion project.
Qatar was the second-largest spender in the region in 2024, with state enterprise QatarEnergy advancing its North Field production sustainability (NFPS) project, which aims to support its liquefied natural gas (LNG) expansion programme with gas feedstock.
QatarEnergy LNG, a subsidiary of QatarEnergy, awarded Italian contractor Saipem an estimated $4bn EPCI contract in September as part of the second phase of its NFPS project.
Saipem was awarded two packages, the scope of which encompasses EPCI work on a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.
Separately, in January, Qatar’s North Oil Company awarded $6bn-worth of contracts for four engineering, procurement, construction, installation and commissioning packages on a project to increase oil production from its Al-Shaheen offshore oil field by about 100,000 barrels a day (b/d).
The project, known as Ruya, is the third capacity-expansion phase of the Al-Shaheen oil field, which has a production potential of 300,000 b/d at present. North Oil Company – a joint venture of QatarEnergy (70%) and France’s TotalEnergies (30%), which has been the operator of Al-Shaheen since July 2017 – aims to increase the field’s output through the Ruya project.
Saudi offshore spending
In late January 2024, the Saudi Energy Ministry directed Aramco to abandon its campaign to expand its oil production spare capacity from 12 million b/d to 13 million b/d by 2027. As a consequence, Aramco cancelled the tendering process for at least 15 tenders involving the EPCI of structures at offshore oil and gas fields.
Since that decision, however, Aramco has gone the other way, spending an estimated $4.5bn in 2024 on offshore EPCI contracts, known in the Aramco ecosystem as CRPOs.
Saipem has been the biggest beneficiary of Aramco’s offshore spending, winning all of the CRPOs awarded in 2024. In early May, Aramco awarded the contractor CRPO 143, which involves replacing an oil line between the Berri and Manifa oil fields in the kingdom’s Gulf waters.
Aramco then awarded Saipem the contract for CRPO 138, which involves laying a trunkline at the Abu Safah offshore field. The contract is estimated to be worth $500m.
The firm then scooped three major CRPOs in August, starting with CRPOs 132 and 139, the combined value of which is estimated to be about $1bn. In early September, Saipem began work on the two contracts, which involve the EPCI of structures to upgrade the Marjan, Zuluf and Safaniya offshore field developments.
Just days later, Aramco awarded Saipem CRPO 127, a $2bn contract that involves EPCI of topsides and jackets for wellhead platforms, a tie-in platform jacket and topside, rigid flowlines, submarine composite cables and fibre optic cables at the Marjan oil and gas field.
Jafurah development
Aramco has also made swift progress in 2024 on successive expansion phases of its programme to produce and process gas from the Jafurah unconventional development in Saudi Arabia. Spending on the Jafurah expansion projects, along with offshore contracts, helped to make the kingdom the third-biggest upstream spender in the Mena region.
Aramco awarded contracts on 30 June for the Jafurah second expansion phase, which aims to raise processing potential to up to 2 billion cubic feet a day (cf/d) of raw gas. Aramco awarded 16 contracts, worth about $12.4bn, for EPC works and drilling services for the second expansion phase.
Within weeks of those awards, a consortium of Spanish contractor Tecnicas Reunidas and China’s Sinopec Group announced that it had been selected by Aramco to carry out EPC works on the third expansion phase at Jafurah, worth $2.24bn. The EPC scope mainly covers building three gas compression plants, each capable of processing 200 million cf/d. Aramco officially awarded the contract to the Tecnicas Reunidas/Sinopec consortium in late September.

Capex to hold steady
While the Mena upstream oil and gas industry may not be able to match its 2024 level of project capex in 2025, the sector is expected to maintain a robust level of spending, especially with national energy companies striving to achieve their strategic long-term oil and gas production capacity goals before the end of the decade.
Data from regional projects tracker MEED Projects suggests that the Mena upstream sector could invest about $40bn on projects in 2025, with gas output expansion schemes predicted to dominate spending.
In line with its target to increase gas production by 60% by 2030, with 2021 as its baseline, Aramco is on course to further advance its Jafurah unconventional gas production programme. It issued the main EPC tender for the fourth expansion phase of the programme in July, within days of selecting the main contractors for the third phase.
Contractors are preparing bids for the project, the scope of which is similar to that of the third expansion phase, and which is therefore understood to be valued at $2.5bn.
Saudi Arabia’s spending on offshore brownfield and greenfield EPCI contracts is set to remain high, with the tendering process under way for eight more Aramco CRPOs.
Four tenders were issued in August for CRPOs 149, 150, 152 and 153, which cover the EPCI works on the Arabiyah, Hasbah and Marjan offshore oil field developments. Of the four CRPOs, contractors in Saudi Aramco’s Long-Term Agreement (LTA) pool have submitted bids for 149, 152 and 153.
Separately, LTA contractors are also preparing bids for four tenders worth a total of $4bn, which will further expand the Zuluf offshore field development.
Meanwhile, Iran is expected to give shape to its plan for gas extraction from its North Pars field, along with raising output from its onshore and offshore oil fields. Increasing production is vital for Tehran in order to maintain steady volumes of exports to earn vital revenue for its economy, which has been crippled by years of international sanctions.
Pars Oil & Gas Company is estimated to have allocated $15bn to the North Pars gas field development project. However, with the project being in the study phase, and with Iran’s cash-strapped government barely able to provide support to its population, the scheme could see little to no progress in 2025.
In the UAE, with the deadline approaching for Adnoc’s target of raising crude output capacity to 5 million b/d by 2027, it is anticipated that the company will funnel billions of dollars into increasing the production potential of its onshore and offshore oil fields.
Adnoc Group subsidiary Adnoc Offshore is evaluating bids for three packages of a multibillion-dollar project to boost oil production at the Lower Zakum offshore hydrocarbons concession in Abu Dhabi. The goal of the first phase of the Lower Zakum long-term development plan is to raise the asset’s output capacity to 520,000 b/d by 2027 and maintain that level until 2034.
Adnoc Offshore has also started the tendering exercise for front-end engineering and design work on the second expansion phase of the Umm Shaif offshore oil field.
Another Adnoc Group subsidiary, Adnoc Onshore, has made a significant capex investment in growing crude output from its main Bab, Northeast Bab, Bu Hasa and Southeast fields. As a result, it is on course to award more contracts in 2025 to maintain and eventually increase output from these fields through its P5 projects, which aim to achieve an oil production potential of 5 million b/d by 2027.
Exclusive from Meed
-
-
-
Oman reaches financial close on 120MW wind project12 August 2026
-
Kuwait utilities investment shifts towards water11 August 2026
-
Syrian court gives death penalty to Bashar Al-Assad11 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Contractor kicks off EPC work on Uthmaniyah gas compression package12 August 2026
Register for MEED’s 14-day trial access
Saudi Arabia-based Saipem Nasser Saeed Al‑Hajri Contracting Company (SNSH) – a joint venture of Italian contractor Saipem and local contractor Nasser Saeed Al‑Hajri & Partners Company for Contracting – has kicked off work on the Uthmaniyah gas compression plant package in Saudi Arabia.
The package forms part of a wider Saudi Aramco project to boost gas compression capacity at the Shedgum and Uthmaniyah processing plants in the Eastern Province.
The Shedgum and Uthmaniyah plants currently receive about 870 million cubic feet a day (cf/d) and 1.2 billion cf/d of Khuff raw gas, respectively. Through the multibillion-dollar project, Aramco aims to increase the compression and processing capacity of both plants, as well as build new pipelines to enhance gas transportation.
Aramco formally awarded the key engineering, procurement and construction (EPC) contract for the Uthmaniyah gas compression plant package to SNSH in June.
The value of the contract won by SNSH is estimated at $1.24bn, sources previously told MEED. Separately, Milan-headquartered Saipem said its share of the contract is €900m ($1.04bn) and that the EPC works will run for 42 months.
The scope covers the EPC of a new compression plant serving the non-associated Uthmaniyah gas field, Saipem said in its statement. Saipem added that “the new compression plant will extend the production life of the field, helping to support the growing energy demand of the Kingdom of Saudi Arabia”.
The contract for the Uthmaniyah gas compression plant package is the first EPC project awarded under Aramco’s National EPC Champion programme, Euronext Milan-listed Saipem said.
Shedgum and Uthmaniyah gas compression project
The Uthmaniyah gas compression plant contract is one of nine EPC packages under the broader Shedgum and Uthmaniyah gas compression project. The packages are:
- Shedgum gas compression facility and SGP in-plant works
- Uthmaniyah gas compression facility and UGP in-plant works
- Shedgum gas compression pipelines package
- Uthmaniyah gas compression pipelines package
- Shedgum and Uthmaniyah central temporary construction facilities
- Shedgum and Uthmaniyah early works site preparation
- Operation and maintenance of Saudi Aramco Project Management Team temporary construction facilities and accommodation
- Shedgum and Uthmaniyah gas compression plant PIA
- Shedgum and Uthmaniyah gas compression plant PSA.
Aramco has awarded package 6 (early works site preparation) to local firm Al-Shalawi International Company Trading & Contracting, sources told MEED.
Aramco is also understood to be in discussions with India’s Larsen & Toubro Energy Hydrocarbon (L&T), among other bidders, for package 1 (Shedgum gas compression facility and SGP in-plant works), sources said.
Separately, Aramco was said to be in negotiations with a consortium of China’s Sinopec and Dammam-based Al‑Qahtani Pipe Coating Industries for package 4 (Uthmaniyah gas compression pipelines). However, the consortium fell short of providing bond guarantees and did not meet other Aramco requirements, leading to its break-up, sources told MEED. Aramco may now open discussions with other bidders for the package.
Meanwhile, Khobar-based Arkad Engineering & Construction has emerged as the lowest bidder for package 3 (Shedgum gas compression pipelines), with Aramco expected to award the contract in June, according to sources.
Contractors submitted bids for packages of the Shedgum and Uthmaniya gas compression capacity expansion project in January, MEED previously reported.
The Saudi energy giant is understood to have started the solicitation of interest process for the main EPC contract tendering exercise in the fourth quarter of 2024.
Aramco subsequently issued the tenders for the EPC packages of the scheme during the second quarter of last year and set an initial bid submission deadline of 17 August.
Aramco then extended the bid submission deadline to 17 November, 7 December, and then to January, according to sources.
In line with its aim of increasing gas production and processing capacity by 80% by 2030, with 2021 as its baseline, Aramco is investing significant capital in gas projects in the kingdom.
Photo credit: Saipem via
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18366754/main.jpg -
KJO selects contractors for Dorra gas project offshore packages12 August 2026

Al-Khafji Joint Operations (KJO) has selected contractors for two major offshore packages under its multibillion-dollar Dorra field facilities development project. The Dorra gas field is located in the waters of the Saudi-Kuwait Neutral Zone.
KJO – jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary Kuwait Gulf Oil Company – has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.
US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.
A consortium of India’s Larsen & Toubro Energy Hydrocarbon (L&TEH) and Italian contractor Saipem has secured package 2B, sources told MEED. Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.
MEED reported in March that the L&TEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.
Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.
Offshore package scopes
The EPC scope of work on the two offshore packages of the Dorra gas field facilities project is as follows:
Package 2A – Dorra gas field wellhead topsides, flowlines and umbilicals
- Seven gas wellhead platforms or topsides, with production routed to the central gathering platform
- Corrosion-resistant, alloy-lined intra-field flowlines and umbilicals connecting the gas wellhead platforms to the central gathering platform and the auxiliary platform
Package 2B: Dorra central gathering platform complex, export pipelines and cables
- Central gathering platform
- Auxiliary platform
- Dorra accommodation platform
- Flare platform
- Bridge platform
- Pipelines for gas and condensate transmission to each shareholder
- Produced water pipeline from the central gathering platform to Al-Khafji field and from the planned onshore processing facility next to the Al-Zour refinery in Kuwait to Al-Khafji field
- Recovered monoethylene glycol (MEG) pipeline from Al-Khafji field to the central gathering platform
- Control and power system linking Al-Khafji onshore facilities to offshore units
- Offshore central control room at Dorra accommodation platform.
Regarding the first offshore package, MEED reported in October last year that KJO awarded India’s L&TEH a contract estimated at $140m-$150m. Offshore package 1 covers the EPC of seven offshore jackets and the laying of intra-field pipelines.
Separately, KJO is understood to be holding discussions for package 3 with Spanish contractor Tecnicas Reunidas, which emerged as the lowest bidder, as MEED reported in March. Sources said a final client decision on the award is pending.
Onshore package scope
The scope of work on the only onshore package of the Dorra gas field facilities project is as follows:
Package 3: Onshore gas processing facilities
- Buildings to be constructed as part of KJO’s Dorra project onshore package include:
- Dorra control building
- Operator building
- Operations, maintenance and engineering building
- Process interface building
- Onshore 115/69kV substation
- Two gas-insulated substations
- Warehouse
- Maintenance building
- Mosque
- Telecommunications tower radio building
- Beach valve substation at the planned onshore processing facility next to the Al-Zour refinery in Kuwait
- Processing facilities for KJO’s onshore package:
- Produced water receiving and treatment
- Sour water stripping and treated water system
- Rich MEG storage tank
- MEG regeneration and reclamation
- Recovered hydrocarbons system
- Lean MEG storage and supply
- Fresh MEG storage and supply
- Beach valve stations at Al-Khafji and Al-Zour
- Utilities:
- Instrument and plant air system
- Nitrogen generation system
- Diesel storage and distribution system
- Fuel gas system
- Closed drain and slop tank system
- Hazardous area open drains system
- Industrial water system
- Drinking water system
- Flare gas recovery system and a low-pressure flare system
- Fire water system
- Emergency diesel generator
- Sewage treatment
Discovered in 1965, the Dorra gas field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.
Saudi Arabia and Kuwait have been pressing ahead with their plan to jointly produce 1 billion cubic feet a day (cf/d) of gas from the Dorra gas field.
The two countries have been producing oil from the Neutral Zone – primarily from the onshore Wafra field and offshore Khafji field – since at least the 1950s. With a growing need to increase natural gas production, they have been working to exploit the Dorra offshore field, understood to be the only gas field in the Neutral Zone.
Progress has been hampered by a dispute over ownership of the Dorra gas field. Iran, which refers to the field as Arash, claims it partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development. Kuwait and Saudi Arabia maintain that the field lies entirely within their jointly administered Neutral Zone – also known as the Divided Zone – and that Iran has no legal basis for its claim.
In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.
France-based Technip Energies has performed the entire concept study and feed work on the overall Dorra gas field development programme.
ALSO READ:
https://image.digitalinsightresearch.in/uploads/NewsArticle/18365989/main3026.jpg -
Oman reaches financial close on 120MW wind project12 August 2026
Register for MEED’s 14-day trial access
Oman’s 120MW Jaalan Bani Bu Ali (JBB) wind independent power project (IPP) has reached financial close, according to the consortium developing the project.
The project is being developed by a consortium comprising French firm EDF Power Solutions, Oman’s Al-Khadra Partners and OQ Alternative Energy.
Located in South Al-Sharqiyah Governorate, about 440 kilometres from the Port of Duqm, the project will comprise 16 wind turbines, each with a capacity of 7.7MW.
Commercial operations are expected to begin in the third quarter of 2027. The JBB project is EDF Power Solutions’ first wind project in Oman.
Oman’s Nama Power & Water Procurement (Nama PWP) signed a 20-year power purchase agreement (PPA) to develop, finance, build and operate the project last December.
As exclusively reported by MEED, a consortium of Chinese companies also signed the engineering, procurement and construction (EPC) contract to build the plant that same month.
The consortium comprises China Energy Engineering Corporation, PowerChina, East China Electric Power Design & Research Institute and Hunan Thermal Power, all headquartered in Beijing.
Once operational, the wind farm is expected to generate enough renewable electricity to supply more than 13,500 Omani households annually. It is also expected to avoid more than 270,000 tonnes of carbon dioxide emissions a year.
The project supports Oman’s target of increasing the share of renewable energy in its national electricity mix to at least 30% by 2030. It also supports the country’s Net Zero 2050 target.
In May, Muscat-based Monenco Consulting Engineers won a consultancy contract for a grid station project linked to the Jaalan Bani Bu Ali wind farm project.
The contract was awarded by China Energy Engineering Corporation, the lead EPC contractor for the Jaalan Bani Bu Ali IPP.
The scope includes engineering and detailed design consultancy services for the grid station and associated overhead line linked to the wind farm, which is expected to begin construction by the end of the third quarter.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18364806/main.jpg -
Kuwait utilities investment shifts towards water11 August 2026

China State Construction Engineering Corporation recently signed a contract for Kuwait’s North Kabd wastewater treatment plant, the country’s largest wastewater infrastructure project to date.
The award, following more than a decade of planning, propelled Kuwait’s water sector contract awards to more than $4bn as of early August, according to regional project tracker MEED Projects.
The facility will have a treatment capacity of up to 1 million cubic metres a day (cm/d), with the $3.3bn contract covering the design, construction, operation and maintenance of the plant over a 10-year period.
It marks a significant recovery for the sector after several years of subdued activity and the first time since 2020 that annual water awards have exceeded $1bn.
North Kabd is the largest of several major water projects awarded this year, alongside contracts covering desalination and the expansion and rehabilitation of water distribution infrastructure.
Desalination and distribution
These include a $316m contract awarded to local firm United Gulf Construction (UGC) by the Ministry of Electricity, Water & Renewable Energy (MEWRE) for the rehabilitation and expansion of the Doha water distribution complex.
The five-year project includes a new pump station and will add about 130 million imperial gallons of storage capacity, while increasing pumping capacity to 220 million imperial gallons a day (MIGD).
UGC was also selected in February to upgrade the Hawally water distribution complex in Kuwait’s Hawalli Governorate. The facility serves one of Kuwait’s most densely populated governorates, with the project intended to address chronic low water pressure, particularly during peak summer demand, and improve continuity of supply.
The upgrade will increase freshwater storage capacity by 66 million gallons and raise potable-water pumping capacity to 54.5 million gallons a day.
In April, Kuwait’s Central Agency for Public Tenders approved MEWRE’s recommendation to award a $371m contract for phase two of the Doha seawater reverse osmosis (SWRO) desalination plant.
A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag will carry out the project, which will have a capacity of about 272,000 cm/d.
Upcoming water awards
Meanwhile, Kuwait’s Ministry of Public Works (MPW) has been progressing several tenders for major water infrastructure projects covering rainwater drainage and treated water systems in the country’s southern and northern regions.
In July, local Combined Group Contracting submitted the lowest bid for a contract to develop a major treated water system in the southern region. The contractor submitted a price of about $515m for the scheme, according to a company disclosure.
For the smaller northern treated water system, Contractor General Trading & Contracting submitted the lowest bid of $169m.
In what is already a standout year for Kuwait’s water sector, further awards could push activity significantly higher. More than $1bn of water projects are currently under bid evaluation, indicating further evidence of a sustained recovery in the months ahead.
Power sector activity
Kuwait’s power sector recorded just $271m of contract awards by early August, according to MEED Projects, putting activity well below recent annual levels.
This compares with a record full-year total of $5.5bn in 2025 and $2.7bn in both 2024 and 2023.
Several large-scale generation projects have been slow to advance, with deadline extensions a notable feature in recent months. The outlook is stronger, however, with these projects now progressing through procurement and significant awards expected in the months ahead.
Kuwait is advancing the 1,800MW Al-Khairan phase one independent water and power project (IWPP), for which two developer consortiums led by Abu Dhabi National Energy Company (Taqa) and Saudi Arabia’s Acwa submitted bids in June.
The project will also include a desalination plant with a capacity of 125 MIGD. A second phase of the Al-Khairan IWPP, estimated at $750m, is understood to include a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant. The project remains in the early development stages, with tendering not expected until at least 2027.
Renewable energy programme
The Kuwait Authority for Partnership Projects (Kapp) is also progressing the Al-Dibdibah power and Al-Shagaya renewable energy programme in partnership with Kuwait’s MEWRE.
The contract to develop the 1,100MW phase three, zone one solar photovoltaic (PV) project is expected to be confirmed soon, with a consortium led by Abu Dhabi Future Energy Company (Masdar) previously reported to be the frontrunner.
A separate 500MW solar PV project is also being procured under phase three, zone two of the same programme, with bids submitted on 26 July. If the contract is awarded by the end of the year, the two Shagaya contracts would add about $2bn to the value of power sector awards.
Another notable development was the 25-year energy conversion and water purchase agreement signed in February for the Al-Zour North IWPP phases two and three. The signing marked a key step towards financial close on the estimated $4bn project. Once completed, the facility will add 2,700MW of power and 120 MIGD of desalinated water to Kuwait’s supply network
The Shagaya, Khairan and Zour North projects form a key part of Kuwait’s generation portfolio. The country is aiming to reach 22,100MW of installed renewable energy capacity by 2030, under a 20-year strategy announced in March 2025 that extends to 2050.
Kuwait is also continuing to invest in existing generation plants. MEWRE is evaluating bids for the $1.7bn upgrade of the Subiya power and water plant, including the conversion of units from open-cycle to combined-cycle operation and the modernisation of existing facilities.
Battery energy storage systems
In the near to medium term, more than $10bn-worth of power projects are under bid evaluation. This includes several battery energy storage system projects with a planned total storage capacity of 1.5GW.
In June, Kuwait approved sites in Al-Mutlaa and Jaber Al-Ahmad cities for the development of the projects. The projects will be implemented in phases, with the first phase providing 500MW of storage capacity. The first facilities are expected to be operational by summer 2027 and will supply stored energy to the electricity grid during periods of peak demand.
Elsewhere, MEWRE continues to evaluate offers from Shanghai Electric Group and local firm Heavy Engineering Industries & Shipbuilding Company (Heisco) for the estimated $400m engineering, procurement and construction contract to rehabilitate and modernise eight boilers at the Subiya power generation and water distillation station. The bid bond validity has been extended to 23 August, indicating that the procurement process remains ongoing.
MEED’s September 2026 report on Kuwait also includes:
> ECONOMY: Kuwait shows tentative signs of economic development
> BANKING: Necessity is the mother of invention for Kuwaiti lenders
> OIL & GAS: Regional war to have lasting impact on Kuwaiti oil sector
> CONSTRUCTION: Kuwait construction holds up despite regional strifehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18333042/main.gif -
Syrian court gives death penalty to Bashar Al-Assad11 August 2026
Register for MEED’s 14-day trial access
A Syrian court has sentenced former president Bashar Al-Assad to death after trying him in absentia, convicting him of crimes committed during the country’s nearly 14 years of civil war.
It is the first such ruling under Syria’s transitional authorities, who ousted Al-Assad in December 2024 and vowed justice and accountability for crimes committed under his rule.
Al-Assad fled to Moscow as Islamist-led forces closed in on Damascus after a lightning offensive.
In a Damascus court, Judge Fakhr Al-Din Al-Aryan convicted Al-Assad of crimes including “premeditated murder, the intentional killing of more than one person, the intentional killing of children under 15 years … torture, torture leading to death, and deprivation of liberty on multiple occasions” — acts the court classified as crimes against humanity and war crimes.
“He is therefore sentenced to death,” the judge said in his ruling.
The court also sentenced six former military and security officials to death in absentia, including Al-Assad’s brother Maher, who ran the army’s elite Fourth Division and also fled the country.
Those convicted included former defence minister Fahd Al-Freij and Louay Al-Ali, who headed military intelligence in Daraa province in 2011.
ALSO READ: Syria charts post-war reconstruction course
The officials were convicted of crimes including murder, incitement to murder, torture leading to death and repeated deprivation of liberty, also classified as crimes against humanity and war crimes.
Former security official Atif Najib – the only defendant tried in person – was also sentenced to death for crimes against humanity committed while he headed political security in Daraa province, the cradle of the country’s 2011 uprising.
Najib, a cousin of Al-Assad who was arrested in January last year, was convicted of crimes including murder, the intentional killing of children under 15 and torture leading to death.
The acts attributed to him are “crimes against humanity”, the court said as it handed down “the harshest punishment … which is the death penalty”.
ALSO READ: US lifts sanctions on Syria after the EU takes similar action
Syria began proceedings in April against Al-Assad and other officials, accused both in person and in absentia of atrocities during the civil war, which erupted after the former authorities’ brutal repression of pro-democracy protesters.
More than half a million people were killed and millions displaced, while tens of thousands disappeared, many into the country’s brutal prison system.
The uprising began in Daraa in March 2011 after 15 students were arrested for allegedly writing anti-government slogans on the city’s walls.
Residents said the students were tortured, prompting protests demanding their release that ended in bloodshed.
Security forces suppressed demonstrations and fired live ammunition to disperse sit-ins at several locations.
Najib was dismissed after the crackdown as protests spread to other provinces.
Judge Al-Aryan said Najib had denied the charges and shown “no remorse”.
Al-Assad took power in Syria in 2000 in an unopposed election following the death of his father, Hafez Al-Assad, who was president from 1971.
ALSO READ: Syria exports first crude oil batch in 14 years
https://image.digitalinsightresearch.in/uploads/NewsArticle/18331541/main.gif