Region boosts LNG spending

29 April 2024

 

This package also includes: Gulf players secure future of LNG projects 


There has been a sharp rise in investment in projects aimed at expanding the production of liquefied natural gas (LNG) in the Gulf region since the start of this decade.

A capital expenditure of close to $38bn has been made by Middle East and North Africa hydrocarbons producers in the past 10 years, mainly on projects to increase LNG output capacity, according to data from regional projects tracker MEED Projects.

Almost three quarters of that spending has taken place in the past four years, and predominantly in the GCC.

The rise in the importance of natural gas, and therefore LNG, as an energy transition fuel has led to strong growth in its demand worldwide. Global trade in LNG reached 404 million tonnes in 2023, up from 397 million tonnes in 2022, with tight supplies of LNG constraining growth, energy major Shell said in a recent report.

Global LNG demand is expected to rise by more than 50% by 2040, as industrial coal-to-gas switching gathers pace in China and countries in south and southeast Asia use more LNG to support their economic growth.

Gulf players are keen to cater to this growing demand and dominate the global supply market, fuelling a wave of investment in large-scale production-boosting projects and terminal construction schemes. 

The total LNG production capacity of the GCC is expected to reach an estimated 200 million tonnes a year (t/y) by 2030, cementing the region’s position as the world’s largest LNG supplier.

Taking the lead

Qatar has been jostling with the US and Australia for the title of world’s largest LNG provider for many years. Each of these three producers have clinched the top spot at different points, only to be unseated by one of the others again.

However, when its North Field LNG expansion starts to come online later in this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company in May 2023.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

And Doha is not stopping there. QatarEnergy announced a third phase of its North Field LNG expansion programme in February. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

Muscat moves up

Oman has been supplying LNG to customers, mainly in Asia, for many years. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

France’s TotalEnergies has also committed to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies has achieved final investment decision on a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies is leading the Marsa LNG joint venture, which is developing the Sohar LNG terminal project. Marsa LNG was formed in December 2021 by TotalEnergies and OQ, with the partners owning 80% and 20% stakes, respectively.

Marsa LNG plans to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbons concessions in Oman, particularly from the sultanate’s Blocks 10 and 11. 

The joint venture is also planning an LNG bunkering terminal and storage units located in Sohar port, and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has selected France’s Technip Energies to perform EPC works on the estimated $1bn project.

Adnoc’s ambitions

Abu Dhabi National Oil Company (Adnoc) has historically been one of the GCC’s smaller LNG producers. Adnoc Group subsidiary Adnoc Gas operates three large gas processing trains on Das Island. 

At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The facility’s first and second trains were commissioned in the 1970s and have a total combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s and has a capacity of 3.2 million t/y.

The LNG production and export capability of Adnoc Gas will receive a major boost when a new greenfield terminal that it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade.

The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y. The facility will ship LNG mainly to key Asian markets, such as Pakistan, India, China, South Korea and Japan.

In March, Adnoc Group announced that it had issued a limited notice to proceed to a consortium of contractors for early EPC works on the Ruwais LNG terminal project. 

The limited notice to proceed was given to a consortium led by Technip Energies, consisting of Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy.

The overall value of the export terminal project is estimated to be more than $5bn. Adnoc is expected to issue the full EPC contract award for the Ruwais project in June this year.

 Gulf players secure future of LNG projects 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11717834/main.gif
Indrajit Sen
Related Articles
  • Riyadh Expo sets November bid deadline for Souq construction

    29 October 2026

     

    Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has allowed contractors until 11 November to submit bids for a contract to deliver the Souq areas within the Expo site.

    The tender was floated on 30 July, with an initial submission deadline of 9 October.

    The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).

    The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works. 

    The precincts comprise:

    • Precinct 1 – The Icon: 41,417 sq m
    • Precinct 2 – Place & Planet: 62,306 sq m 
    • Precinct 3 – Culture of Wisdom: 67,112 sq m  
    • Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m  
    • Precinct 5 – Adaptation & Innovation: 82,358 sq m

    The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.

    The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, connecting the site’s iconic and thematic assets.

    The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.

    Site progress

    Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.

    Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to build a new metro station serving the Expo 2030 site.

    In April, ERC awarded two contracts to local firm Al-Yamama Company for the next phase of infrastructure works at the site.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.

    That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20998514/main.jpg
    Yasir Iqbal
  • Iraq oilfield water scheme to hit milestone next year

    29 October 2026

     

    China Petroleum Pipeline Engineering (CPP) expects to start laying pipeline for Iraq’s Common Seawater Supply Project (CSSP) in Basra in mid- or late next year, according to industry sources.

    The project is behind schedule, partly because importing sections of pipeline is proving challenging due to disruptions to shipping through the Strait of Hormuz.

    The project is being managed by state-owned Basra Oil Company (BOC), with Australia’s ILF acting as a project management consultant after completing the front-end engineering design (feed).

    Under current plans, the pipelines will be buried, which is expected to make them more secure than if they were installed on the surface.

    Phased development

    The client for the first phase of the CSSP is France’s TotalEnergies in partnership with QatarEnergy and BOC.

    The first phase is split into two packages currently under execution and will ultimately have the capacity to transport 5 million barrels a day (b/d) of water.

    The first package focuses on developing pipelines, and the second on developing a water treatment facility.

    CPP is executing the pipeline package contract.

    It signed a $2.5bn contract with BOC for the package in September last year.

    Also in September 2025, South Korea’s Hyundai announced that it had signed a contract worth 4.39tn won ($3.16bn) for the processing plant package.

    In September this year, MEED reported that early groundworks had started for both packages of the first phase of the CSSP.

    Phase one of the project is scheduled to start up in late 2028 or early 2029.

    Earlier this month, US-headquartered Exxon Mobil signed a memorandum of understanding related to the project’s second phase, which is expected to add 2.5 million b/d of water capacity.

    The CSSP will inject processed water into several of Iraq’s biggest oil fields. These include Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon. Water from the project will also be used in the Maysan and Dhi Qar fields.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20981033/main.jpg
    Wil Crisp
  • Dubai tenders Al-Awir sewerage and stormwater works

    29 October 2026

     

    Dubai Municipality has invited contractors to bid for a contract to build sewerage and stormwater infrastructure in New Al-Awir 1st.

    The project (DS317-C1) comprises about 95 kilometres of sewerage gravity network, excluding house connections, and about 105km of stormwater pipelines. The scope also includes house connection pipes, a stormwater pond and oil interceptors.

    According to tender documents seen by MEED, the tender was issued on 23 October, with a bid submission deadline of 12 November.

    The project comes amid wider residential and infrastructure development in Al-Awir 1. In January 2025, Dubai’s Roads & Transport Authority (RTA) announced plans to build 16.5km of internal roads in the area, including a new entrance from Emirates Road.

    In February 2025, MEED exclusively reported that the RTA had selected a local firm to undertake the road construction works.

    The Mohammed Bin Rashid Housing Establishment has also reported progress on housing projects in Al-Awir as part of a wider programme to develop residential communities across Dubai.

    The sewerage and stormwater project is relatively large compared with recent stormwater tenders, with the total cost estimated at up to AED1bn ($272m).

    The works will include approximately 69.2km of house connection pipes and 4,630 inspection chambers. The sewerage network will also include about 1,511 manholes, while the stormwater network will comprise approximately 1,247 manholes.

    Contractors will also be required to use no-dig construction methods for sections of the pipeline. The scope includes ground investigations, utility protection and traffic management.

    The bill of quantities specifies a stormwater pond with a composite volume of approximately 1.2 million cubic metres.

    Earlier this week, Dubai Municipality confirmed it had awarded contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.

    The projects are part of Dubai’s AED30bn Tasreef programme and will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. 

    The overall programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20977734/main.jpg
    Mark Dowdall
  • Adnoc Onshore selects contractors for well tie-ins project

    27 October 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.

    Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields. 

    The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.

    Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.

    Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.

    The project budget is estimated at $1.2bn.

    Bidders for the contract are understood to have included:

    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Jereh (China)
    • Kalpataru Projects International (India)
    • Matrix Construction (UAE)
    • Robt Stone Middle East (UAE)
    • Target Engineering Construction Company (UAE)

    The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg
    Indrajit Sen
  • Ashghal tenders Al-Udeid air base access road works

    27 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.

    The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road. 

    The tender was issued on 22 October, with a submission deadline of 22 November.

    The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.

    Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.

    The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.

    The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.

    The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.

    Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.

    The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.

    Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.

    Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.

    For joint-venture bids, the lead partner must hold the required classification grade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg
    Yasir Iqbal