Region boosts LNG spending

29 April 2024

 

This package also includes: Gulf players secure future of LNG projects 


There has been a sharp rise in investment in projects aimed at expanding the production of liquefied natural gas (LNG) in the Gulf region since the start of this decade.

A capital expenditure of close to $38bn has been made by Middle East and North Africa hydrocarbons producers in the past 10 years, mainly on projects to increase LNG output capacity, according to data from regional projects tracker MEED Projects.

Almost three quarters of that spending has taken place in the past four years, and predominantly in the GCC.

The rise in the importance of natural gas, and therefore LNG, as an energy transition fuel has led to strong growth in its demand worldwide. Global trade in LNG reached 404 million tonnes in 2023, up from 397 million tonnes in 2022, with tight supplies of LNG constraining growth, energy major Shell said in a recent report.

Global LNG demand is expected to rise by more than 50% by 2040, as industrial coal-to-gas switching gathers pace in China and countries in south and southeast Asia use more LNG to support their economic growth.

Gulf players are keen to cater to this growing demand and dominate the global supply market, fuelling a wave of investment in large-scale production-boosting projects and terminal construction schemes. 

The total LNG production capacity of the GCC is expected to reach an estimated 200 million tonnes a year (t/y) by 2030, cementing the region’s position as the world’s largest LNG supplier.

Taking the lead

Qatar has been jostling with the US and Australia for the title of world’s largest LNG provider for many years. Each of these three producers have clinched the top spot at different points, only to be unseated by one of the others again.

However, when its North Field LNG expansion starts to come online later in this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company in May 2023.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

And Doha is not stopping there. QatarEnergy announced a third phase of its North Field LNG expansion programme in February. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

Muscat moves up

Oman has been supplying LNG to customers, mainly in Asia, for many years. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

France’s TotalEnergies has also committed to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies has achieved final investment decision on a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies is leading the Marsa LNG joint venture, which is developing the Sohar LNG terminal project. Marsa LNG was formed in December 2021 by TotalEnergies and OQ, with the partners owning 80% and 20% stakes, respectively.

Marsa LNG plans to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbons concessions in Oman, particularly from the sultanate’s Blocks 10 and 11. 

The joint venture is also planning an LNG bunkering terminal and storage units located in Sohar port, and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has selected France’s Technip Energies to perform EPC works on the estimated $1bn project.

Adnoc’s ambitions

Abu Dhabi National Oil Company (Adnoc) has historically been one of the GCC’s smaller LNG producers. Adnoc Group subsidiary Adnoc Gas operates three large gas processing trains on Das Island. 

At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The facility’s first and second trains were commissioned in the 1970s and have a total combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s and has a capacity of 3.2 million t/y.

The LNG production and export capability of Adnoc Gas will receive a major boost when a new greenfield terminal that it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade.

The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y. The facility will ship LNG mainly to key Asian markets, such as Pakistan, India, China, South Korea and Japan.

In March, Adnoc Group announced that it had issued a limited notice to proceed to a consortium of contractors for early EPC works on the Ruwais LNG terminal project. 

The limited notice to proceed was given to a consortium led by Technip Energies, consisting of Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy.

The overall value of the export terminal project is estimated to be more than $5bn. Adnoc is expected to issue the full EPC contract award for the Ruwais project in June this year.

 Gulf players secure future of LNG projects 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11717834/main.gif
Indrajit Sen
Related Articles
  • Adnoc Onshore selects contractors for well tie-ins project

    27 October 2026

     

    Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.

    Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields. 

    The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.

    Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.

    Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.

    The project budget is estimated at $1.2bn.

    Bidders for the contract are understood to have included:

    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Jereh (China)
    • Kalpataru Projects International (India)
    • Matrix Construction (UAE)
    • Robt Stone Middle East (UAE)
    • Target Engineering Construction Company (UAE)

    The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg
    Indrajit Sen
  • Ashghal tenders Al-Udeid air base access road works

    27 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.

    The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road. 

    The tender was issued on 22 October, with a submission deadline of 22 November.

    The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.

    Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.

    The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.

    The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.

    The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.

    Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.

    The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.

    Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.

    Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.

    For joint-venture bids, the lead partner must hold the required classification grade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg
    Yasir Iqbal
  • Saudi Arabia gauges interest for Al-Ula wastewater expansion

    27 October 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) is conducting market sounding for the first phase of the Mughayra wastewater treatment plant (WWTP) expansion before formally starting its tendering process, according to industry sources.

    The project is valued at SR400m ($107m) and is intended to increase the Mughayra plant’s wastewater treatment capacity to 62,000 cubic metres a day.

    RCU is gauging interest from potential contractors and has not yet issued a prequalification questionnaire, a source said.

    The scheme forms part of Saudi Arabia’s broader investment drive to develop its cultural and tourism offering across Al-Ula.

    The commission launched its Journey Through Time Masterplan in April 2021, with implementation scheduled in three phases through 2035. The masterplan covers infrastructure development, water management and irrigation, alongside the regeneration of a 9-kilometre cultural oasis.

    French engineering firm Artelia previously noted in its 2025 annual corporate report that it is involved in the design phase of the Mughayra WWTP.

    RCU is also developing strategic potable-water storage infrastructure in Al-Ula, including a design-and-build project covering a 50,000-cubic-metre reservoir at Hub 06 and a 15,000-cubic-metre reservoir at Hub 08.

    Local contractor Bin Omairah previously confirmed that it is serving as the engineering, procurement and construction contractor for the storage facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950333/main.jpg
    Mark Dowdall
  • Qatari firm wins $147m Syria road deal

    27 October 2026

    Qatari contractor Al-Mohannadi for Roads, Trading & Contracting has signed a $147m contract with Syria’s General Directorate of Roads to rehabilitate and expand a 215-kilometre (km) highway corridor connecting to the Iraqi border.

    The project covers the rehabilitation and dualisation of a 170km section linking the Al-Busairi junction to the Al-Tanf border crossing, alongside the construction of a 45km link between the Al-Sabaa Biyar junction and Al-Busairi. Work is scheduled for completion within 900 days.

    The agreement was signed in Damascus by Moaz Najjar, director-general of the General Directorate of Roads, and Abdullah Adnan Al-Zattam, chief executive of Al-Mohannadi, in the presence of Syrian Transport Minister Yarob Badr and Finance Minister Mohammad Yusr Barnieh.

    The upgrade is intended to restore and expand one of Syria’s primary overland arteries to Iraq, which has suffered significant deterioration and capacity bottlenecks following years of conflict. The Al-Tanf corridor represents the most direct overland link between Damascus, central Syrian industrial centres and Baghdad.

    The project is designed to accommodate heavier commercial freight vehicles and reduce transit times between the two countries.

    The investment also forms part of broader efforts to re-establish Syria’s role as a regional transit corridor connecting Mediterranean ports with landlocked trade routes into Iraq and the wider region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950332/main.gif
    Yasir Iqbal
  • Adnoc showcases $16.3bn local manufacturing potential

    27 October 2026

    Abu Dhabi National Oil Company (Adnoc Group) has identified more than AED60bn ($16.3bn) in local manufacturing opportunities through 2030.

    The Abu Dhabi energy company also announced changes to its procurement, supplier registration and In-Country Value (ICV) localisation frameworks.

    The measures were announced at the second Make it with Adnoc Forum, held in Abu Dhabi on October 25. They are intended to give manufacturers, suppliers and investors greater visibility of future demand and a faster, clearer route to compete for Adnoc contracts, the company said.

    The more than 200 manufacturing opportunities cover products required for Adnoc’s projects and operations, including:

    • Rotating equipment and power
    • Electrical, control and automation systems
    • Drilling and completion equipment
    • Chemicals and catalysts
    • Piping, fabrication and heavy equipment
    • Spare parts and advanced manufacturing

    Many of the identified products are currently imported, Adnoc said. “Manufacturing them in the UAE shortens lead times, reduces exposure to global supply disruptions and strengthens the resilience of Adnoc’s operations,” it said in its statement.

    Adnoc, the UAE Ministry of Industry & Advanced Technology and the Abu Dhabi Investment Office (Adio) will work together to connect manufacturers with these opportunities. The collaboration will combine visibility of Adnoc’s demand, access to the national industrial database and financing through the National Industrial Resilience Fund, the company said.

    Adnoc also signed two memorandums of understanding on the sidelines of the forum with Adio and Kezad Group.

    ICV scheme expansion

    Adnoc announced the expansion of its Local+ programme, part of its ICV framework, to more than 100 UAE manufacturers, compared with 70 at its launch in May. The programme gives UAE-made products priority in Adnoc projects by requiring engineering, procurement and construction (EPC) contractors bidding for new tenders to source relevant products from manufacturers approved under the programme.

    Separately, Adnoc announced a redesign of its supplier registration and prequalification process. The company is targeting a reduction of up to 80% in the time required for suppliers to complete the process and become eligible to compete for Adnoc opportunities.

    The new model halves the number of required documents and removes prequalification requirements for 60% of service categories.

    A single window brings together registration, qualification and compliance, with requirements tailored to the nature of the work and its level of risk. Artificial intelligence will support document verification and the reuse of existing data, reducing repetitive submissions and administrative processing.

    ALSO READ:
    Adnoc steps up crude oil capacity expansion
    Adnoc funnels billions into boosting gas processing

    “Adnoc’s enhanced ICV model will more closely connect procurement decisions with commercial value and suppliers’ contribution to the UAE economy. Under the new model, commercial and ICV offers will be integrated into a single evaluation model,” the company said.

    “The previous bid-matching approach will be retired, encouraging suppliers to submit their most competitive commercial and ICV offers from the outset. Requirements will be proportionate to contract size and scope.

    “The model also enhances the administration of ICV-related retention payments. Where retention applies, automated calculation and release processes through the Adnoc Supplier Hub will improve transparency, reduce manual follow-up and support suppliers’ cash flow as obligations are met.”

    Alongside the ICV and registration enhancements, Adnoc outlined a new commercial approach built around four strategic shifts: agile, competitive, strategic and forward-looking.

    “The approach will advance simpler procurement and faster decision-making, contracting models aligned with project and market dynamics, targeted commercial negotiations and earlier visibility of Adnoc’s future demand.”

    Since its launch in 2018, Adnoc’s ICV programme has directed more than AED307bn ($83.6bn) into the UAE economy, the company said. By the end of 2025, it had also supported the localisation of more than 130 products, the development of 95 UAE factories, and employment opportunities for more than 27,500 Emiratis at participating private sector companies.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20948385/main5518.jpg
    Indrajit Sen