Region boosts LNG spending

29 April 2024

 

This package also includes: Gulf players secure future of LNG projects 


There has been a sharp rise in investment in projects aimed at expanding the production of liquefied natural gas (LNG) in the Gulf region since the start of this decade.

A capital expenditure of close to $38bn has been made by Middle East and North Africa hydrocarbons producers in the past 10 years, mainly on projects to increase LNG output capacity, according to data from regional projects tracker MEED Projects.

Almost three quarters of that spending has taken place in the past four years, and predominantly in the GCC.

The rise in the importance of natural gas, and therefore LNG, as an energy transition fuel has led to strong growth in its demand worldwide. Global trade in LNG reached 404 million tonnes in 2023, up from 397 million tonnes in 2022, with tight supplies of LNG constraining growth, energy major Shell said in a recent report.

Global LNG demand is expected to rise by more than 50% by 2040, as industrial coal-to-gas switching gathers pace in China and countries in south and southeast Asia use more LNG to support their economic growth.

Gulf players are keen to cater to this growing demand and dominate the global supply market, fuelling a wave of investment in large-scale production-boosting projects and terminal construction schemes. 

The total LNG production capacity of the GCC is expected to reach an estimated 200 million tonnes a year (t/y) by 2030, cementing the region’s position as the world’s largest LNG supplier.

Taking the lead

Qatar has been jostling with the US and Australia for the title of world’s largest LNG provider for many years. Each of these three producers have clinched the top spot at different points, only to be unseated by one of the others again.

However, when its North Field LNG expansion starts to come online later in this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company in May 2023.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

And Doha is not stopping there. QatarEnergy announced a third phase of its North Field LNG expansion programme in February. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

Muscat moves up

Oman has been supplying LNG to customers, mainly in Asia, for many years. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

France’s TotalEnergies has also committed to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies has achieved final investment decision on a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies is leading the Marsa LNG joint venture, which is developing the Sohar LNG terminal project. Marsa LNG was formed in December 2021 by TotalEnergies and OQ, with the partners owning 80% and 20% stakes, respectively.

Marsa LNG plans to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbons concessions in Oman, particularly from the sultanate’s Blocks 10 and 11. 

The joint venture is also planning an LNG bunkering terminal and storage units located in Sohar port, and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has selected France’s Technip Energies to perform EPC works on the estimated $1bn project.

Adnoc’s ambitions

Abu Dhabi National Oil Company (Adnoc) has historically been one of the GCC’s smaller LNG producers. Adnoc Group subsidiary Adnoc Gas operates three large gas processing trains on Das Island. 

At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The facility’s first and second trains were commissioned in the 1970s and have a total combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s and has a capacity of 3.2 million t/y.

The LNG production and export capability of Adnoc Gas will receive a major boost when a new greenfield terminal that it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade.

The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y. The facility will ship LNG mainly to key Asian markets, such as Pakistan, India, China, South Korea and Japan.

In March, Adnoc Group announced that it had issued a limited notice to proceed to a consortium of contractors for early EPC works on the Ruwais LNG terminal project. 

The limited notice to proceed was given to a consortium led by Technip Energies, consisting of Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy.

The overall value of the export terminal project is estimated to be more than $5bn. Adnoc is expected to issue the full EPC contract award for the Ruwais project in June this year.

 Gulf players secure future of LNG projects 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11717834/main.gif
Indrajit Sen
Related Articles
  • Oman invites bids for Musandam renewables study

    25 August 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.

    The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.

    The consultant will be required to determine which technologies are technically and economically justified for the governorate.

    The bid submission deadline is 24 September.

    The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.

    Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.

    Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.

    The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity. 

    Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.

    The bid submissions deadline is 10 September.

    The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.

    Bidding for this tender closes on 26 August.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg
    Mark Dowdall
  • US launches sanctions campaign against Iran

    25 August 2026

    The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.

    The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.

    The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.

    The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.

    Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.

    Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.

    Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.

    Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.

    The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg
    Colin Foreman
  • Iraq-GCC grid link delayed amid security concerns

    25 August 2026

    Iraq has postponed the planned commissioning of its 500MW electricity interconnection with Kuwait despite completing about 96% of the project.

    According to local media reports, Iraq Electricity Ministry spokesman Ahmed Turki said: “The announcement of the completion of the electricity interconnection project with Kuwait has been postponed due to the security situation and the current events in the region.”

    The project had been scheduled to be completed and commissioned in September, connecting Iraq to the six-member Gulf Cooperation Council (GCC) electricity network.

    The GCC-Iraq grid link involves a double-circuit 400-kilovolt (kV) transmission line from the Wafra station in Kuwait to the Al-Faw station in south Iraq, with a total transmission capacity of 1,800MW and a length of 295 kilometres.

    As MEED previously reported, construction on the project began in June 2023, with an initial completion period of 24 months.

    Earlier that year, the GCC Interconnection Authority (GCCIA) awarded contracts to the following contractors: KEC International (local), Kalpataru Power Transmission (India), Calik Enerji (Turkiye), Cegelec Saudi Arabia (local/France) and National Contracting Company (NCC).

    In January 2020, Iraq signed a memorandum of understanding to import 500MW of electricity from the GCCIA.

    The project was initially due to begin operating in April this year. However, in May, Iraq Electricity Ministry spokesman Ahmed Mousain said the interconnection line had reached an area in Kuwait where Kuwaiti forces were deployed because of the US-Iran war, with the security situation disrupting the project’s final stages. 

    Iraq currently produces about 28GW of electricity, according to the Electricity Ministry, but demand during peak summer periods is estimated at more than 50GW. The shortfall continues to cause widespread outages and put pressure on the national grid.

    In parallel, Iraq’s power sector is undergoing one of its largest expansion programmes in decades as the government attempts to address chronic electricity shortages, diversify fuel sources and strengthen regional grid connectivity. As of May, over $40bn-worth of projects were under execution, following $4.2bn in new contracts last year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18963936/main.jpg
    Mark Dowdall
  • L&T announces Jafurah fourth expansion phase contract award

    24 August 2026

     

    Indian contracting conglomerate Larsen & Toubro (L&T) has announced that its subsidiary, L&T Energy Hydrocarbon Onshore (LTEH Onshore), has won a contract to undertake a gas compression facilities project “for a prestigious client in the Middle East”.

    LTEH Onshore received the letter of award during India’s 2026 financial year, which starts on 1 April, Mumbai-headquartered L&T said in a statement, describing the order as ‘ultra-mega’ – a term the company uses for contracts valued at more than INR150bn ($1.57bn).

    The project involves the engineering, procurement and construction (EPC) of gas compression plants, comprising gas inlet facilities, gas compression systems, condensate and produced-water handling systems, propane refrigeration systems and all associated utilities, L&T said in its statement on 24 August.

    “The facilities will be developed for new onshore installations to process sour gas in compliance with applicable client standards, codes and project requirements,” the Bombay Stock Exchange-listed company said.

    To meet the power requirements of the gas compression plants, L&T’s Power Transmission & Distribution business will execute two 230kV extra-high-voltage substations, L&T added.

    MEED understands that the contract award relates to the fourth expansion phase of the Jafurah unconventional gas development in Saudi Arabia, for which Saudi Aramco selected LTEH for EPC works earlier this year.

    MEED previously reported that LTEH started work on the Jafurah fourth expansion phase during the second quarter of the year, with sources estimating the contract value at around $1.5bn.

    The main scope of work on the Jafurah fourth expansion phase project involves the EPC of two gas compression trains at the giant gas basin in the kingdom’s Eastern Province. Each plant will be able to process up to 200 million cubic feet a day (cf/d).

    The detailed scope of work involves the EPC of the following process and utilities units at the south field of the Jafurah reserve:

    • Two gas compression trains of 200 million cf/d capacity each, measuring 400 metres by 400 metres
    • Gas compression plant inlet area
    • Gas compression plant condensate and produced-water handling
    • Instrumentation and plant air unit
    • Nitrogen generation unit
    • Raw/potable/water utilities
    • Chemical injection systems
    • Diesel systems
    • Flare and flare gas recovery systems
    • Gas compression plant burn pit
    • Closed drain system
    • Oily water system
    • Sanitary water system
    • Stormwater system
    • Firewater system
    • Fire and gas protection system
    • All buildings located within the gas compression plant, excluding security buildings
    • Outside battery limit buildings

    Contractors submitted proposals for the Jafurah fourth expansion phase project by the deadline of 15 January 2025, MEED previously reported. After the bids were submitted, Aramco initially asked contractors to extend their bid validity until the end of September, as it needed more time to evaluate the proposals.

    The Saudi energy giant then asked contractors to extend the validity of their base proposals until February this year, and the bidders complied, MEED reported.

    Along with requesting a second bid-validity extension, Aramco also sought an alternative set of commercial proposals from contractors, sources said. Bidders submitted the second price option to the client in December, the sources added.

    The following contractors are among those that are understood to have submitted bids for the Jafurah fourth expansion phase project:

    • China Petroleum Engineering & Construction
    • Larsen & Toubro Energy Hydrocarbon (India)
    • Samsung E&A (South Korea)
    • Tecnicas Reunidas (Spain) / Sinopec Group (China)

    Aramco issued the main tender for the project in July 2024. Contractors invited to bid were initially set a deadline of 15 October that year to submit technical bids and their In-Kingdom Total Value Add (IKTVA) credentials. Commercial bids were due to be submitted by 31 October, with the deadline extended to 31 December, then to 15 January, 2025.

    Jafurah gas development phases

    The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning around 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.

    Aramco brought the greenfield Jafurah gas processing plant online in early December, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.

    The Saudi oil company had earlier said it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane and 630,000 barrels a day (b/d) of high-value liquids by 2030.

    Aramco has said that, at peak production, its unconventional gas programme is expected to generate electricity equivalent to displacing 500,000 b/d of oil.

    Along with overseeing EPC works on the Jafurah fourth expansion phase project, Aramco is also nearing a decision on awarding the main EPC contract for the fifth expansion phase of the mammoth Jafurah unconventional gas development programme.

    MEED recently reported that a frontrunner has emerged for the main EPC contract for the Jafurah fifth expansion phase, whose scope is similar to the programme’s fourth phase that has been awarded to LTEH.

    Dubai-headquartered Wood Group has carried out the front-end engineering and design (feed) on the fifth expansion phase.

    Progress on the fourth and fifth expansion phases of the Jafurah unconventional gas development programme continues as EPC work on the third phase advances.

    In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for the Jafurah third expansion phase. The value of the contract is estimated to be $2.24bn.

    The objective of the third expansion phase of Jafurah is similar to that of the fourth phase of development. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.

    The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants and installing other utilities units, piping systems and safety equipment.

    The selection of contractors for the third expansion phase of the Jafurah development came within weeks of Aramco officially awarding EPC contracts for the second expansion phase, which aims to raise its processing potential to up to 2 billion cf/d of raw gas produced from the Jafurah field.

    Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.

    The EPC scope of work on the project involves the construction of gas compression facilities and associated pipelines and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.

    The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:

    • Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
    • Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
    • Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
    • Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
    • Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
    • Riyas NGL package 6 – site preparation works – $107mMofarreh Alharbi & Partners (Saudi Arabia)
    • Riyas NGL package 9 – temporary construction facilities – $80mMofarreh Alharbi & Partners

    Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.

    In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.

    The Jafurah unconventional gas development programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.

    Prior to the commissioning of the Jafurah gas plant in the last quarter of this year, Aramco completed an $11bn lease-and-leaseback deal in late October for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.

    Under the transaction, which Aramco started in August, a newly formed subsidiary – Jafurah Midstream Gas Company (JMGC) – will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids (NGL) fractionation facility.

    After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.

    Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, The Arab Energy Fund (TAEF) and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962987/main4448.jpg
    Indrajit Sen
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall