Region advances LNG projects with pace

30 August 2024

 

Global liquefied natural gas (LNG) liquefaction capacity is expected to more than double by 2028, potentially increasing from 473 million tonnes a year (t/y) in 2023 to 968 million t/y in 2028 through new build and expansion projects, according to a recent report by GlobalData.

North America dominates globally among the regions, in terms of new build and expansion liquefaction capacity growth, contributing around 54% of the total global capacity additions or 268 million t/y by 2028, GlobalData says in the report. 

The Middle East comes in at second position, followed by the Former Soviet Union, with capacity additions of 78 million t/y and 71 million t/y, respectively. 

Since the start of this decade, there has been a sharp increase in investments in the Middle East and North Africa (Mena), and particularly in the Gulf region, in projects to expand LNG production. Capital expenditure close to $45bn has been made by Mena hydrocarbon producers in the past 10 years on various LNG projects, mainly for output capacity building, MEED Projects data shows. Almost three-fourths of that spending took place in the past four years, and predominantly in the GCC.

A desire to cater to the steady growth expected in global LNG demand and dominate the global supply market is fuelling the wave of investments into large-scale production capacity expansions and terminal construction by Gulf players.

Qatar guns for top spot

Qatar has been jostling with the US and Australia for the status of being the largest LNG provider to the world for many years now. The three countries have all clinched the top spot, only to be unseated by another the very next month.

However, when its mammoth North Field LNG expansion programme begins to come online later this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making steady progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company (CCC) in May last year.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

Qatar is, however, not stopping at that. QatarEnergy, in February, announced a third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project derives its name from the western zone of Qatar’s North Field offshore gas reserve, from where it will draw feedstock for LNG production.

Oman moves up the ladder

Oman has been supplying LNG to customers, mainly in Asia, for many years now. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

As recently as late July, the Omani government announced that Oman LNG will build a new train at its Qalhat LNG production complex in Sur, located in the sultanate’s South Al-Sharqiyah governorate. Oman LNG will perform the preliminary engineering study for the planned LNG train.

The LNG train will have an output capacity of 3.8 million t/y. When commissioned in 2029, it will increase Oman LNG’s total production capacity to 15.2 million t/y.

Aside from Oman LNG, France’s TotalEnergies has now committed itself to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies achieved final investment decision earlier this year for a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies leads a joint venture named Marsa LNG, which is the Sohar LNG terminal project developer. Marsa LNG was formed in December 2021 through an agreement between TotalEnergies and the sultanate’s state energy holding company OQ. The partners own 80% and 20% stakes, respectively.

Marsa LNG intends to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbon concessions in the sultanate, particularly from Blocks 10 and 11; an LNG bunkering terminal and storage units located in Sohar port; and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has picked France-based Technip Energies to perform EPC works on the estimated $1bn LNG terminal project.

Adnoc gives shape to ambitions

Abu Dhabi National Oil Company (Adnoc) has been a relatively smaller LNG producer in comparison to its GCC peers. Adnoc Group subsidiary, Adnoc Gas, operates three large gas processing trains on Das Island. At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The first and second trains were commissioned in the 1970s and have a combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s, with a capacity of 3.2 million t/y.

Adnoc Gas’ LNG production and export capability, however, will receive a major fillip when a new greenfield terminal it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade. The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.

Adnoc awarded the full EPC contract and achieved the final investment decision for the LNG terminal complex in June. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy was awarded the EPC contract, worth $5.5bn.

Jordan takes a step forward

Jordan imports more than 90% of its oil, gas and refined product needs and therefore has a strong economic case for developing projects to boost its domestic hydrocarbon infrastructure, particularly for gas.

The country recently took a key step forward when Aqaba Development Corporation awarded the main EPC contract in August for a project to develop the Sheikh Sabah Al-Ahmad Al-Jaber Al-Sabah LNG onshore regasification facility at the port of Aqaba.

The contract was won by a consortium of Singapore-based AG&P and South Korea’s Gas Entec, along with their local partner, Jordan’s Issa Haddadin.

In a statement, Gas Entec said that the facility will have the capacity to process 720 million cubic feet a day of natural gas. 

“Jordan relies heavily on natural gas for its power and industrial needs, but faces challenges with supply reliability,” Gas Entec said.

“The new LNG terminal will provide Jordan with the flexibility to access LNG from various global suppliers, ensuring a stable and secure energy source.”

Global LNG demand set for steady growth

https://image.digitalinsightresearch.in/uploads/NewsArticle/12432924/main.gif
Indrajit Sen
Related Articles
  • Iraq’s first LNG terminal to be completed in June

    27 April 2026

    Iraq’s first liquefied natural gas (LNG) import terminal is expected to be completed in early June, according to the country’s Ministry of Electricity.

    The terminal, which has an estimated investment value of $450m, is being developed at the Port of Khor Al-Zubair and will have a capacity of 750 million standard cubic feet a day (cf/d).

    Ministry spokesperson Ahmed Mousa told the Iraqi News Agency that “work is proceeding at an accelerated pace to complete the LNG platform”, noting that “the government has set 1 June as the date for finishing the project”.

    In October last year, US-based Excelerate Energy signed a commercial agreement with a subsidiary of Iraq’s Ministry of Electricity to develop the floating LNG terminal.

    The contract was signed at the office of Iraq’s Prime Minister Mohammed Shia Al-Sudani during a ceremony attended by senior officials from both countries, including the US deputy secretary of energy James Danly.

    The contract included a five-year agreement for regasification services and LNG supply with extension options, featuring a minimum contracted offtake of 250 million cf/d.

    Ahmed Mousa said that “under the contract, the company is responsible for completing the facility as well as securing the agreed gas quantities from any source, in line with the specified terms”.

    He added: “Work is continuing according to the planned timelines to complete the project on schedule, as part of the Ministry of Electricity’s plans to keep pace with peak summer loads.”

    Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.

    Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.

    Recently, Iraq’s oil and gas sector has been disrupted by fallout from the US and Israel’s attack on Iran on 28 February and the subsequent regional conflict.

    Over recent weeks, Iraq’s oil exports have collapsed by about 80% amid problems shipping crude through the Strait of Hormuz.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577746/main.jpg
    Wil Crisp
  • Iraqi LNG import terminal raises questions about energy strategy

    27 April 2026

    Commentary
    Wil Crisp
    Oil & gas reporter

    Iraq’s first LNG import terminal is set to come online in early June, at a time when global LNG prices are likely to remain close to their highest levels in more than three years.

    The disruption to global oil and gas exports in the wake of the US and Israel’s attack on Iran on 28 February led to LNG prices soaring, with natural gas prices in Asia and Europe rising to their highest levels since January 2023 during March.

    So far, there has been little progress towards a diplomatic or military solution to reopen the Strait of Hormuz, and most analysts do not forecast significant price declines in the near term.

    On 24 April, the International Energy Agency (IEA) said that the combined effect of short-term supply losses and slower capacity growth could result in a cumulative loss of around 120 billion cubic metres of LNG supply between 2026 and 2030.

    While the IEA expects new liquefaction projects in other regions to offset these losses over time, it still believes the crisis will lead to prolonged tight market conditions through 2026 and 2027.

    This means that Iraq will likely have to pay elevated prices for imported LNG for some time to come – if it can receive shipments at all.

    The port of Khor Al-Zubair is located in the Arabian Gulf, and LNG shipments from the US or Australia would need to pass through the Strait of Hormuz before reaching the terminal.

    This will only be possible if a solution is found to the ongoing blockade of the shipping route.

    Investment debate

    Iraq’s project to develop a floating LNG terminal is estimated to cost $450m, and many in Iraq may question whether this was the best use of these funds.

    While it may have been difficult for Iraqi policymakers to foresee the attack by the US and Israel on Iran and its impact on LNG markets, Iraq had several strong options to enhance domestic energy security rather than turning to LNG imports.

    The most obvious of these was investing in infrastructure to enable it to utilise its domestic gas reserves.

    According to the World Bank’s 2025 Global Gas Flaring Tracker Report, in 2024, Iraq burned off more unused gas than any other country, except Russia and Iran, which ranked first and second, respectively.

    That year, an estimated total of more than 18 billion cubic metres of natural gas was flared in Iraq due to a lack of infrastructure to properly capture and process it.

    It is highly likely that projects to gather and process this gas would have been more reliable and cost-effective than investing in a new floating LNG terminal, which increases the country’s exposure to global LNG price fluctuations and shipping disruptions.

    Other options could have included developing domestic gas fields or investing in solar and battery storage projects, which have become increasingly affordable in recent years.

    The cost of solar panels has fallen by more than 95% over the past decade.

    Power shortfall

    As things stand, Iraq is likely to face severe electricity shortages this summer.

    On 21 April, Iraq’s Ministry of Electricity said it plans to produce 30,000MW this summer, well short of the predicted peak demand of around 55,000MW.

    Ahmed Musa, a spokesperson for the Electricity Ministry, told the state-run Iraqi News Agency that the shortfall will result in planned outages across the country.

    He also said that even meeting the 30,000MW target is contingent on sufficient gas supplies.

    If Iraq experiences the same level of power outages as last year – or worse – many are likely to view the $450m spent on an LNG import terminal as a waste of money and an expensive symbol of poor planning.

    Power cuts this summer could stoke unrest at a time that is already politically precarious due to the ongoing regional conflict.

    In recent years, electricity shortages have repeatedly fuelled protests in Iraq during the summer months, particularly in Basra, where blackouts and poor public services have driven people to take to the streets.

    If the Strait of Hormuz does not reopen soon, Iraq’s economic crisis will deepen, and electricity shortages are likely to further undermine the country’s stability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577743/main.jpg
    Wil Crisp
  • Kuwait approves Doha desalination plant award

    27 April 2026

    Kuwait’s Central Agency for Public Tenders has approved the recommendation of the Ministry of Electricity & Water to award a KD114.28m ($371.5m) contract to supply, install, operate and maintain the second phase of the Doha seawater reverse osmosis (SWRO) desalination plant.

    A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag has been selected for the project, with the award understood to be pending final approval from the Audit Bureau.

    The project will deliver a production capacity of about 60 million imperial gallons a day (MIGD) and will include the desalination plant with full reverse osmosis trains, pre- and post-treatment systems, recarbonation equipment, booster pumps, and safety and filtration systems.

    The total project duration is 96 months. The Doha SWRO desalination plant is part of Kuwait’s broader programme to expand water production capacity and reduce reliance on thermal desalination methods.

    MEED previously reported that the Heisco/Wabag joint venture submitted the lowest bid. Bidders and prices included:

    • Heavy Engineering Industries & Shipbuilding / Wabag: $373.2m
    • Cox Water (Spain): $538.1m
    • Orascom Construction (Egypt): $568.4m

    In April 2025, MEED reported that Kuwait had retendered the contract for the facility after the ministry cancelled the initial tender in June 2024.

    The Ministry of Electricity & Water awarded South Korea’s Doosan Heavy Industries & Construction – now known as Doosan Enerbility – a $422m contract in May 2016 to build the 60 MIGD Doha 1 SWRO plant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577722/main.jpg
    Mark Dowdall
  • Firms prepare bids for 250MW Airtrunk data centre

    27 April 2026

     

    Contractors are preparing to submit commercial offers by 4 May for a contract to build a 250MW data centre in Riyadh.

    The project is being co-developed by Australian firm AirTrunk in collaboration with Saudi Arabia’s artificial intelligence (AI) infrastructure company Humain, which is owned by the Public Investment Fund (PIF).

    The bidders include:

    • El-Seif Engineering Contracting / Larsen & Toubro (local/India)
    • FCC / Alfanar Projects (Spain/local)
    • Albawani / Orascom (local/Egypt)
    • Nesma & Partners (local
    • James L Williams (UAE)
    • Alec (UAE)

    In October last year, AirTrunk and Humain announced a $3bn partnership to build data centres in Saudi Arabia, marking AirTrunk’s first move into the region.

    The firms said they would, along with AirTrunk investor Blackstone, “develop a long-term strategic partnership focused on financing, developing and operating next-generation data centres and AI infrastructure across the kingdom”.

    This was followed by Humain signing a $1.2bn financing agreement with the state-backed National Infrastructure Fund to support the expansion of AI and digital infrastructure projects in Saudi Arabia. The agreement was signed in January on the sidelines of the World Economic Forum in Davos, Switzerland.

    Humain said the deal will support its plan to develop up to 250MW of hyperscale AI data centre capacity in the kingdom.

    According to a joint statement, the data centres will use graphics processing units for AI training and inference, serving Humain’s customers locally, regionally and globally.

    The National Infrastructure Fund and Humain will also explore launching an AI data centre investment platform, with the two organisations acting as anchor investors to enable local and international institutional investors to back the scale-up of Humain’s AI programme.

    The National Infrastructure Fund is Saudi Arabia’s lead development financing partner for infrastructure and operates under the supervision of the National Development Fund.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577720/main.jpg
    Yasir Iqbal
  • Diriyah confirms $490m museum construction contract

    27 April 2026

    Saudi gigaproject developer Diriyah Company has formally announced the award of a SR1.84bn ($490m) construction contract for its Saudi Arabia Museum of Contemporary Art (SAMoCA) within the Diriyah development in Riyadh.

    The contract has been awarded to a consortium comprising Egyptian contractor Hassan Allam Construction and Saudi Arabia’s Albawani.

    In February, MEED exclusively reported that the contractors were preparing to start construction work on the project. MEED understands Diriyah Company awarded the contract to the consortium in December last year.

    The announcement follows Diriyah Company’s award of an estimated SR2.5bn ($666m) contract to build the Pendry superblock package in the DG2 area.

    The Pendry superblock includes the construction of the Pendry Hotel alongside residential and commercial assets. The package will cover 75,365 square metres and is located in the northwestern district of the DG2 area.

    In February, Diriyah Company also awarded a SR717m ($192m) contract for the construction of the One Hotel, located in the Diriyah Two area of the masterplan, with a gross floor area of more than 31,000 sq m.

    The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh city centre, it will span 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577413/main.jpg
    Yasir Iqbal