Region advances LNG projects with pace

30 August 2024

 

Global liquefied natural gas (LNG) liquefaction capacity is expected to more than double by 2028, potentially increasing from 473 million tonnes a year (t/y) in 2023 to 968 million t/y in 2028 through new build and expansion projects, according to a recent report by GlobalData.

North America dominates globally among the regions, in terms of new build and expansion liquefaction capacity growth, contributing around 54% of the total global capacity additions or 268 million t/y by 2028, GlobalData says in the report. 

The Middle East comes in at second position, followed by the Former Soviet Union, with capacity additions of 78 million t/y and 71 million t/y, respectively. 

Since the start of this decade, there has been a sharp increase in investments in the Middle East and North Africa (Mena), and particularly in the Gulf region, in projects to expand LNG production. Capital expenditure close to $45bn has been made by Mena hydrocarbon producers in the past 10 years on various LNG projects, mainly for output capacity building, MEED Projects data shows. Almost three-fourths of that spending took place in the past four years, and predominantly in the GCC.

A desire to cater to the steady growth expected in global LNG demand and dominate the global supply market is fuelling the wave of investments into large-scale production capacity expansions and terminal construction by Gulf players.

Qatar guns for top spot

Qatar has been jostling with the US and Australia for the status of being the largest LNG provider to the world for many years now. The three countries have all clinched the top spot, only to be unseated by another the very next month.

However, when its mammoth North Field LNG expansion programme begins to come online later this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making steady progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company (CCC) in May last year.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

Qatar is, however, not stopping at that. QatarEnergy, in February, announced a third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project derives its name from the western zone of Qatar’s North Field offshore gas reserve, from where it will draw feedstock for LNG production.

Oman moves up the ladder

Oman has been supplying LNG to customers, mainly in Asia, for many years now. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

As recently as late July, the Omani government announced that Oman LNG will build a new train at its Qalhat LNG production complex in Sur, located in the sultanate’s South Al-Sharqiyah governorate. Oman LNG will perform the preliminary engineering study for the planned LNG train.

The LNG train will have an output capacity of 3.8 million t/y. When commissioned in 2029, it will increase Oman LNG’s total production capacity to 15.2 million t/y.

Aside from Oman LNG, France’s TotalEnergies has now committed itself to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies achieved final investment decision earlier this year for a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies leads a joint venture named Marsa LNG, which is the Sohar LNG terminal project developer. Marsa LNG was formed in December 2021 through an agreement between TotalEnergies and the sultanate’s state energy holding company OQ. The partners own 80% and 20% stakes, respectively.

Marsa LNG intends to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbon concessions in the sultanate, particularly from Blocks 10 and 11; an LNG bunkering terminal and storage units located in Sohar port; and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has picked France-based Technip Energies to perform EPC works on the estimated $1bn LNG terminal project.

Adnoc gives shape to ambitions

Abu Dhabi National Oil Company (Adnoc) has been a relatively smaller LNG producer in comparison to its GCC peers. Adnoc Group subsidiary, Adnoc Gas, operates three large gas processing trains on Das Island. At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The first and second trains were commissioned in the 1970s and have a combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s, with a capacity of 3.2 million t/y.

Adnoc Gas’ LNG production and export capability, however, will receive a major fillip when a new greenfield terminal it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade. The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.

Adnoc awarded the full EPC contract and achieved the final investment decision for the LNG terminal complex in June. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy was awarded the EPC contract, worth $5.5bn.

Jordan takes a step forward

Jordan imports more than 90% of its oil, gas and refined product needs and therefore has a strong economic case for developing projects to boost its domestic hydrocarbon infrastructure, particularly for gas.

The country recently took a key step forward when Aqaba Development Corporation awarded the main EPC contract in August for a project to develop the Sheikh Sabah Al-Ahmad Al-Jaber Al-Sabah LNG onshore regasification facility at the port of Aqaba.

The contract was won by a consortium of Singapore-based AG&P and South Korea’s Gas Entec, along with their local partner, Jordan’s Issa Haddadin.

In a statement, Gas Entec said that the facility will have the capacity to process 720 million cubic feet a day of natural gas. 

“Jordan relies heavily on natural gas for its power and industrial needs, but faces challenges with supply reliability,” Gas Entec said.

“The new LNG terminal will provide Jordan with the flexibility to access LNG from various global suppliers, ensuring a stable and secure energy source.”

Global LNG demand set for steady growth

https://image.digitalinsightresearch.in/uploads/NewsArticle/12432924/main.gif
Indrajit Sen
Related Articles
  • March 2026: Data drives regional projects

    27 March 2026

    Click here to download the PDF

    Includes: Commodity tracker | Top 10 global contractors | Brent spot price | Construction output


    MEED’s April 2026 report on Saudi Arabia includes:

    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16146608/main.gif
    MEED Editorial
  • Redefining the region’s arbitration landscape

    27 March 2026

     

    In the midst of increasing international investments and commercial transactions in the Middle East, arbitration remains a key component for the resolution of complex commercial disputes. Its effectiveness, however, depends not only on arbitral tribunals, but also on how national courts define their roles in oversight and enforcement.

    Recent trends in the Middle East have shown a more disciplined judicial approach with a clearer delineation of roles between courts and arbitral tribunals.

    Enforcement: a narrower approach

    Enforcement of foreign awards has been a key area of development.

    In the UAE, the Committee for the Unification of Federal and Local Judicial Principles ruled in Petition No. 1 of 2025 that an award shall be valid and enforceable provided the arbitrators sign only the final page. Referring to earlier Dubai Court of Cassation decisions (1), the Committee noted that procedural rules should not be used to defeat substantive rights and that legal procedures are meant to serve justice, not to create technical barriers. 

    The Dubai Court of Cassation adopted the same approach, confirming that arbitrators are not required to sign every page of the award and that issues already examined during arbitration, including signatory capacity, cannot be reopened at the enforcement stage. (2) 

    A similar emphasis on clarity can be seen in Saudi Arabia, where the Arbitration Law is currently under review, with the aim of modernising the legislative framework and enhancing predictability. The draft reform includes clearer provisions regarding court–tribunal interaction, permits courts to stay annulment proceedings or enforcement challenges for up to 60 days to enable tribunals to cure defects, and confirms that partial and interim awards have the authority of a final judgment and are directly enforceable.

    The ADGM and Dubai Courts have also introduced a system of reciprocal enforcement of ratified arbitral awards without the need to re-examine the underlying award.

    These developments therefore suggest a narrower approach and a reduced scope for expansive review at the enforcement stage.

    Recent trends have shown a more disciplined judicial approach with a clearer delineation of roles between courts and arbitral tribunals

    Judicial intervention: limits of review

    Courts have also refined the scope of annulment and supervisory review.

    The Abu Dhabi Court of Cassation clarified that annulment is not an appeal on the merits. Courts may not reweigh evidence or revisit a tribunal’s interpretation of the law. The grounds of annulment remain limited to the statutory grounds set out in the Federal Arbitration Law. (3)

    Egyptian courts likewise limit grounds for annulment to exhaustively listed statutory grounds, excluding reassessment of the merits.

    In the wider regional landscape, Morocco’s arbitration reform demonstrates a similar trajectory. The updated framework modernises the regime and clarifies the supportive role of domestic courts, reinforcing a structured balance between oversight and arbitral autonomy.

    Across these jurisdictions, review powers are increasingly exercised within defined legal parameters rather than through re-examination of arbitral reasoning.

    Public policy: a limited exception

    Public policy continues to be a ground for refusing enforcement, but recent decisions suggest it is applied with greater restraint. For instance, in the UAE, the imposition of compound interest is not considered to be in contravention of public policy. (4) At the DIFC level, the Court specified that the refusal on public policy grounds is subject to a high standard and is only justified where enforcement would “violate the forum state’s most basic notions of morality and justice”. (5)

    Saudi Arabia recognises sharia compliance and public policy as potential grounds for refusal. While rooted in the foundations of its legal system, they operate within defined statutory boundaries.

    Public policy therefore functions as a defined safeguard rather than a vehicle for broad review.

    Implications for cross-border activity

    Where enforcement review is confined to the grounds set out in the New York Convention and annulment remains limited to statutory bases, the interaction between tribunals and courts becomes more predictable. In disputes involving assets across multiple states, this delineation contributes to greater certainty at the post-award stage.

    The complementary role of the ICC

    Institutional practice operates alongside these developments.

    The ICC Court and its Secretariat ensure proceedings are conducted with care, independence, impartiality and integrity, in strict compliance with the Court’s obligations and duties under its rules. In doing so, the Court and the Secretariat monitor cases to safeguard due process and procedural fairness.

    One of the distinctive features of ICC arbitration and a cornerstone of the Rules is the Court’s scrutiny of all draft awards. Such a process serves to enhance the quality of the award, improve its general accuracy and persuasiveness; and maximise its legal effectiveness by identifying any defects that could be used in an attempt to have it set aside at the place of arbitration or resist its enforcement elsewhere. 

    In complex, multi-contract and multi-jurisdictional disputes, this scrutiny plays an important role in safeguarding enforceability across different jurisdictions. 

    As courts continue to define the limits of intervention, institutional discipline and judicial oversight increasingly operate side by side, reinforcing confidence in arbitration across the Middle East.


    1. Dubai Court of Cassation – Cases No. 109/2022 and No. 403/2020  2. Dubai Court of Cassation – Appeals Nos. 778 and 887 of 2025  3. Abu Dhabi Court of Cassation – Cases Nos. 1115/2024 and No. 166/2024  4. Dubai Court of Cassation – Appeals Nos. 778 and 887 of 2025  5. DIFC Court of Appeal’s decision dated 9 January 2025


    About the author
    Laetitia Rabbat is deputy counsel, ICC International Court of Arbitration, Abu Dhabi

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16145450/main.gif
  • Algeria tenders multibillion-dollar railway construction

    27 March 2026

    Algeria’s state railway company, the Agence Nationale d’Etudes et de Suivi de la Realisation des Investissements Ferroviaires (Anesrif), has tendered two contracts worth more than $2.5bn for the construction of the Laghouat-Ghardaia-El-Meniaa railway line.

    The contract scope covers the construction of 495 kilometres (km) of railway in two sections, the acquisition of rolling stock and other associated works.

    The tenders were issued on 25 March, with bids due by 24 May.

    The first line will run between Laghouat and Ghardaia, covering 265km. It will include 21 viaducts, one tunnel, 55 pipe crossings and five stations.

    The project is split into four sections:

    • Section A: Laghouat-Bellil (72.6km)
    • Section B: Bellil-Bouzbier (40.4km)
    • Section C: Bouzbier-Oued N’chou (69km)
    • Section D: Oued N’chou-Metlili (47km)

    Passenger trains will operate at up to 220 kilometres per hour (km/h), and freight trains at up to 100km/h. The railway will largely follow national road RN01.

    The construction cost of this section is expected to be about $1.4bn.

    The second line will run from Ghardaia to El-Meniaa. The 230km railway will start at Metlili station and extend south to El-Meniaa.

    The line will serve Mansourah, Hassi Lefhel and El-Meniaa, as well as the planned new town of Hassi El-Gara.

    It will comprise six viaducts, 35 railway structures and three stations.

    Passenger trains will operate at up to 220km/h, while freight trains will run at up to 100km/h.

    This section is expected to cost $1.2bn.

    Earlier this month, MEED reported that Anesrif had formally started the procurement process for its multibillion-dollar Laghouat-Ghardaia-El-Meniaa railway project.

    International and local firms were given until 8 March to submit expressions of interest for the overall client’s engineer role on the 495km development.

    Consultancies were also given until 12 March to bid for two separate contracts covering project supervision and control of the first 265km section between Laghouat and Ghardaia, and the 230km line between Ghardaia and El-Meniaa.

    The project received major backing in December last year when the African Development Bank approved a €747.32m ($870m) loan to finance it.

    In September last year, MEED reported that Algeria’s Prime Minister, Nadir Larbaoui, had signed an executive decree that “formalised the declaration of public utility of two strategic sections of the future Algiers-Tamanrasset railway line”.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16156750/main.jpg
    Yasir Iqbal
  • Roshn tenders Marafy residential plots in Jeddah

    27 March 2026

     

    Saudi gigaproject developer Roshn has tendered a contract inviting firms to bid for the development of two mixed-use residential plots at its Marafy project in Jeddah.

    The first plot comprises low-rise residential buildings covering more than 92,000 square metres (sq m). The development will feature about 304 residential units.

    The second plot comprises canal-side low-rise buildings offering more than 357 residential units across an area of over 96,000 sq m.

    The bid submission deadline is 19 April.

    Roshn began construction on its Marafy project in February 2024.

    The mixed-use development, launched in August 2023, will serve over 130,000 residents and feature an 11-kilometre-long man-made canal.

    In October 2023, Roshn awarded a SR690m ($184m) early works contract to the local Projects Company for Marine Services. The contract scope includes ground excavation and shore protection works.

    Marafy will comprise several districts, including Roshn’s existing Alarous integrated residential development.

    MEED previously reported that Roshn had appointed US-based Jacobs and Wimberly Allison Tong & Goo as the project consultants.

    In a statement, Roshn said the Marafy districts will connect to each other and to the rest of Jeddah via an intermodal transport system including water taxis, bus lines, a dedicated metro station and a direct canal link to King Abdulaziz International airport.

    Established in 2018, Roshn aims to increase homeownership among Saudi citizens to 70%. The company plans to develop more than 395,000 residential units in Riyadh, Mecca, Asir and the Eastern Region.

    Roshn is developing the Sedra community in northeast Riyadh, which is masterplanned to include 30,000 homes built in eight phases.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16156314/main.jpeg
    Yasir Iqbal
  • Libya pipeline expected to take 10 days to repair

    27 March 2026

     

    Repairs to a key oil pipeline connected to Libya’s Sharara field are expected to take 10 more days to complete, according to industry sources.

    The damage to the pipeline has reduced Libya’s oil production by several hundred thousand barrels a day, sources said.

    “The country is losing out on a lot of revenue right now because of this pipeline problem,” said one source. “The country should be producing more oil right now in order to capitalise on high oil prices, but in fact the country has reduced production.

    “Hopefully, all of the repairs will be conducted without issues and the pipeline will be brought back online in 10 days.”

    Earlier this week, Libya’s security authorities recovered two exploded projectiles from a damaged crude oil pipeline connected to the Sharara oil field.

    The two exploded ‌projectiles were an M-62 Russian-made missile weighing approximately 250kg and remnants of a 130mm rocket.

    The ministry posted photos on its verified Facebook page showing the remains of the projectiles on the ground near what appeared to be the damaged pipeline.

    “The projectiles were handled according to approved technical and security procedures, the site was fully secured, and ​the necessary measures were taken to ensure the safety of the area ​and prevent any potential risks,” the ministry said.

    Last week, after a fire broke out at the pipeline, Libya’s state-owned National Oil Corporation (NOC) redirected flow from the Sharara oil field via the El-Feel pipeline to Mellitah port and through the Hamada pipeline to storage tanks in Zawiya.

    These alternative routes do not have the same capacity as the pipeline that has been taken offline, and the incident has forced the El-Feel oil field into a full shutdown.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16148117/main.png
    Wil Crisp