Region advances LNG projects with pace

30 August 2024

 

Global liquefied natural gas (LNG) liquefaction capacity is expected to more than double by 2028, potentially increasing from 473 million tonnes a year (t/y) in 2023 to 968 million t/y in 2028 through new build and expansion projects, according to a recent report by GlobalData.

North America dominates globally among the regions, in terms of new build and expansion liquefaction capacity growth, contributing around 54% of the total global capacity additions or 268 million t/y by 2028, GlobalData says in the report. 

The Middle East comes in at second position, followed by the Former Soviet Union, with capacity additions of 78 million t/y and 71 million t/y, respectively. 

Since the start of this decade, there has been a sharp increase in investments in the Middle East and North Africa (Mena), and particularly in the Gulf region, in projects to expand LNG production. Capital expenditure close to $45bn has been made by Mena hydrocarbon producers in the past 10 years on various LNG projects, mainly for output capacity building, MEED Projects data shows. Almost three-fourths of that spending took place in the past four years, and predominantly in the GCC.

A desire to cater to the steady growth expected in global LNG demand and dominate the global supply market is fuelling the wave of investments into large-scale production capacity expansions and terminal construction by Gulf players.

Qatar guns for top spot

Qatar has been jostling with the US and Australia for the status of being the largest LNG provider to the world for many years now. The three countries have all clinched the top spot, only to be unseated by another the very next month.

However, when its mammoth North Field LNG expansion programme begins to come online later this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making steady progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company (CCC) in May last year.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

Qatar is, however, not stopping at that. QatarEnergy, in February, announced a third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project derives its name from the western zone of Qatar’s North Field offshore gas reserve, from where it will draw feedstock for LNG production.

Oman moves up the ladder

Oman has been supplying LNG to customers, mainly in Asia, for many years now. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

As recently as late July, the Omani government announced that Oman LNG will build a new train at its Qalhat LNG production complex in Sur, located in the sultanate’s South Al-Sharqiyah governorate. Oman LNG will perform the preliminary engineering study for the planned LNG train.

The LNG train will have an output capacity of 3.8 million t/y. When commissioned in 2029, it will increase Oman LNG’s total production capacity to 15.2 million t/y.

Aside from Oman LNG, France’s TotalEnergies has now committed itself to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies achieved final investment decision earlier this year for a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies leads a joint venture named Marsa LNG, which is the Sohar LNG terminal project developer. Marsa LNG was formed in December 2021 through an agreement between TotalEnergies and the sultanate’s state energy holding company OQ. The partners own 80% and 20% stakes, respectively.

Marsa LNG intends to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbon concessions in the sultanate, particularly from Blocks 10 and 11; an LNG bunkering terminal and storage units located in Sohar port; and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has picked France-based Technip Energies to perform EPC works on the estimated $1bn LNG terminal project.

Adnoc gives shape to ambitions

Abu Dhabi National Oil Company (Adnoc) has been a relatively smaller LNG producer in comparison to its GCC peers. Adnoc Group subsidiary, Adnoc Gas, operates three large gas processing trains on Das Island. At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The first and second trains were commissioned in the 1970s and have a combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s, with a capacity of 3.2 million t/y.

Adnoc Gas’ LNG production and export capability, however, will receive a major fillip when a new greenfield terminal it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade. The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.

Adnoc awarded the full EPC contract and achieved the final investment decision for the LNG terminal complex in June. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy was awarded the EPC contract, worth $5.5bn.

Jordan takes a step forward

Jordan imports more than 90% of its oil, gas and refined product needs and therefore has a strong economic case for developing projects to boost its domestic hydrocarbon infrastructure, particularly for gas.

The country recently took a key step forward when Aqaba Development Corporation awarded the main EPC contract in August for a project to develop the Sheikh Sabah Al-Ahmad Al-Jaber Al-Sabah LNG onshore regasification facility at the port of Aqaba.

The contract was won by a consortium of Singapore-based AG&P and South Korea’s Gas Entec, along with their local partner, Jordan’s Issa Haddadin.

In a statement, Gas Entec said that the facility will have the capacity to process 720 million cubic feet a day of natural gas. 

“Jordan relies heavily on natural gas for its power and industrial needs, but faces challenges with supply reliability,” Gas Entec said.

“The new LNG terminal will provide Jordan with the flexibility to access LNG from various global suppliers, ensuring a stable and secure energy source.”

Global LNG demand set for steady growth

https://image.digitalinsightresearch.in/uploads/NewsArticle/12432924/main.gif
Indrajit Sen
Related Articles
  • Saudi Landbridge rail scheme to be delivered by 2034

    21 January 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia Railways (SAR) has said that it will deliver the Saudi Landbridge project through a "new mechanism" by 2034, after failing to reach an agreement with a Chinese consortium for the construction of the project.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said that the consortium failed to meet local content requirements, and the project will now be delivered in several phases through a different procurement model.

    The project has been under negotiation between Saudi Arabia and China-backed investors keen to develop it on a public-private-partnership basis.

    Al-Malik said that the project cost is about SR100bn ($26.6bn).

    It comprises more than 1,500 kilometres (km) of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.

    In April last year, MEED exclusively reported that SAR had issued a tender for the lead design consultancy services contract on the Saudi Landbridge railway network.

    MEED understands that the scope covered the concept design and options for the preliminary and issued-for-construction design stages on the network.

    MEED reported that the launch of a design tender directly by SAR suggested that Riyadh was looking at other options to develop it alongside the Chinese proposal.

    In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.

    If it proceeds, the Saudi Landbridge will be one of the largest railway projects ever undertaken in the Middle East and one of the biggest globally. Based on typical design timeframes, tenders for construction are likely to be ready by mid-2026, although the question of how it will be financed will need to be answered before it can proceed to the next step.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15475837/main.gif
    Yasir Iqbal
  • Firms submit bids for Dorra gas scheme PMC

    21 January 2026

     

    Register for MEED’s 14-day trial access 

    Engineering firms have submitted bids to Al-Khafji Joint Operations (KJO) for a tender covering project management consultancy (PMC) for the multibillion-dollar Dorra gas field facilities development project.

    MEED reported last March that KJO was pushing forwards with a project to produce gas from the Dorra offshore field, located in Gulf waters in the Neutral Zone shared by Saudi Arabia and Kuwait.

    KJO has divided the engineering, procurement and construction (EPC) scope of work on the project to produce gas from the Dorra field into four EPC packages – three offshore and one onshore.

    The broad scope of services under the tender involves providing PMC for EPC works for the Dorra gas facilities development project.

    Firms submitted bids for the PMC tender by the deadline of 19 January, sources told MEED.

    KJO issued the tender for PMC services for EPC works on the Dorra gas facilities development project on 29 September. Engineering firms were initially given until 24 November to submit bids for the tender, with that deadline then extended until 15 December and then finally until 19 January, according to sources.

    Sources said that the following firms, among others, are understood to be bidding for the PMC tender:

    • Fluor (US)
    • KBR (US)
    • Kent (Saudi Arabia/UAE)
    • Tecnicas Reunidas (Spain)
    • Wood (UK)
    • Worley (Australia)

    KJO hosted a job explanation meeting with the bidders for the tender on 15 October, the sources said.

    KJO offshore and onshore facilities

    KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company (AGOC) and KPC subsidiary Kuwait Gulf Oil Company (KGOC), is moving forward with its Dorra gas field facilities project. KJO has divided the project’s scope of work into four EPC packages – three offshore and one onshore.

    Indian contractor Larsen & Toubro Energy Hydrocarbon (L&TEH) has won package 1 of the Dorra facilities project, which covers the EPC of seven offshore jackets and the laying of intra-field pipelines. The contract awarded by KJO to L&TEH is estimated to be valued between $140m and $150m, MEED reported in October.

    Contractors are presently preparing to submit bids for the remaining three packages — offshore packages 2A and 2B, and onshore package 3 by 26 January, sources told MEED. KJO has extended the bid submission deadlines for these packages multiple times.

    The EPC scope of work for package 2A includes Dorra gas field wellhead topsides, flowlines and umbilicals. Package 2B involves the central gathering platform complex, export pipelines and cables. Package 3 includes the EPC of onshore gas processing facilities.

    Saudi Arabia and Kuwait are pressing ahead with their ambitious plan to jointly produce 1 billion cubic feet a day (cf/d) of gas from the Dorra gas field, located in the waters of their shared Neutral Zone. Discovered in 1965, the Dorra gas field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.

    Saudi Arabia and Kuwait have been producing oil from the Neutral Zone – primarily from the onshore Wafra field and offshore Khafji field – since at least the 1950s. With a growing need to increase natural gas production, both countries have been working to exploit the Dorra offshore field, understood to be the only gas field in the Neutral Zone.

    The Dorra facilities project is one of three major multibillion-dollar projects launched by subsidiaries of Saudi Aramco and Kuwait Petroleum Corporation (KPC) to produce and process gas from the Dorra field that have been advancing over the past few months.

    AGOC onshore Khafji gas plant

    Meanwhile, AGOC has extended the bid submission deadline for seven EPC packages as part of a project to construct the Khafji gas plant, which will process gas from the Dorra field onshore Saudi Arabia, until 22 April.

    MEED previously reported that AGOC had issued main tenders for the seven EPC packages earlier in 2025. Contractors were initially set deadlines of 24 October for technical bid submissions and 9 November for submission of commercial bids, which was then extended by AGOC until 22 December.

    The seven EPC packages cover a wide range of works, including open-art and licensed process facilities, pipelines, industrial support infrastructure, site preparation, overhead transmission lines, power supply systems, and main operational and administrative buildings.

    France-based Technip Energies has carried out a concept study and front-end engineering and design (feed) work on the entire Dorra gas field development programme.

    Progress has been hampered by a geopolitical dispute over ownership of the Dorra gas field. Iran, which refers to the field as Arash, claims it partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development. Kuwait and Saudi Arabia maintain that the field lies entirely within their jointly administered Neutral Zone – also known as the Divided Zone – and that Iran has no legal basis for its claim.

    In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.

    Since that show of strength and unity, projects targeting production and processing of gas from the Dorra field have gained momentum.

    KGOC onshore processing facilities

    KGOC has initiated early engagement with contractors for the main EPC tendering process for a planned Dorra onshore gas processing facility, which is to be located in Kuwait.

    KGOC is in the feed stage of the project, which is estimated to be valued at up to $3.3bn, and is now expected to issue the main EPC tender in the second quarter of this year, MEED recently reported.

    The proposed facility will receive gas via a pipeline from the Dorra offshore field, which is being separately developed by KJO. The complex will have the capacity to process up to 632 million cf/d of gas and 88.9 million barrels a day of condensates from the Dorra field.

    The facility will be located near the Al-Zour refinery, owned by another KPC subsidiary, Kuwait Integrated Petroleum Industries Company (Kipic).

    A 700,000-square-metre plot has been allocated next to the Al-Zour refinery for the gas processing facility, and discussions regarding survey work are ongoing. The site may require shoring, backfilling and dewatering.

    The onshore gas processing plant will also supply surplus gas to KPC’s upstream business, Kuwait Oil Company (KOC), for possible injection into its oil fields.

    Additionally, KGOC plans to award licensed technology contracts to US-based Honeywell UOP and Shell subsidiary Shell Catalysts & Technologies for the plant’s acid gas removal unit and sulphur recovery unit, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15472237/main3457.jpg
    Indrajit Sen
  • Libya announces $2.7bn Misurata Port expansion

    21 January 2026

    Register for MEED’s 14-day trial access 

    Libya has announced the $2.7bn expansion of Misurata Port, led by Terminal Investment Limited.

    The consortium comprises Switzerland's Mediterranean Shipping Company and Qatari firm Maha Capital Partners.

    The project is being implemented under a public-private partnership model, and is the first of its kind in the country's non-oil sector

    The expansion aims to increase the port's container-handling capacity to 4 million containers a year.

    Misurata Free Zone (MFZ) is Libya’s largest free zone, spanning an area of 2,576 hectares.

    According to an MFZ statement, the expansion includes:

    • Expanding container-handling capacity to accommodate larger vessels and more complex logistics chains;  
    • Integrating port operations with MFZ’s industrial ecosystem to support small and medium-sized entities, manufacturing and value-added services;
    • Deploying modern terminal equipment and digital systems;  
    • Enhancing safety, performance and environmental standards in line with global benchmarks;
    • Creating long-term employment opportunities.

    The Libyan Prime Minister’s Office said the expanded port is expected to generate around $600m in annual operating revenues, create about 8,400 direct jobs and support nearly 60,000 indirect jobs.

    The investment scope includes:

    • Five ship-to-shore (STS) gantry cranes
    • 10 mobile harbour cranes 
    • Eight rubber-tired gantry (RTG) cranes  
    • 32 reach stackers
    • Eight other pieces of equipment, like trucks and forklifts

    The project's first phase will raise container-handling capacity to 1.5 million 20-foot equivalent units (TEU), increase throughput by 7% and develop and manage berths to 2,000 metres in total.

    It also includes installing six RTG cranes and three STS cranes, developing 56 acres of container yards, building a 2,096-square-metre (sq m) refrigerated container warehouse and constructing an additional 7,500 sq m facility.

    An advanced terminal operating system will also be implemented.

    The second phase will add a further 2.5 million TEUs of capacity, construct a 2,500-metre breakwater, build a new 1,200-metre berth and a new 60-acre container yard, and deepen the port to 17 metres.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15471059/main.jpg
    Yasir Iqbal
  • Ras Al-Khaimah awards sewage PPP contract

    20 January 2026

    A consortium of Abu Dhabi National Energy Company (Taqa), France’s Saur and the local Etihad Water & Electricity (Etihad WE) has signed a contract to develop and operate a wastewater treatment plant in the UAE’s northern emirate of Ras Al-Khaimah.

    The Rakwa wastewater infrastructure project is Ras Al-Khaimah’s first public-private partnership (PPP) for a sewage treatment plant.

    It is being developed in partnership with Ras Al-Khaimah’s Public Services Department and Investment & Development Office.

    The $120m project entails developing a wastewater treatment plant with a capacity of 60,000 cubic metres a day (cm/d), expandable to 150,000 cm/d. 

    On 9 January, MEED exclusively reported that the consortium was set to be awarded the contract. The consortium is being led by Ajman-based Emirates Utilities Development Company, a subsidiary of Etihad WE.

    US/India-based Synergy Consulting is the financial advisory consultant to Taqa and EtihadWE on this project.

    MEED previously reported that two bidding consortiums had submitted bids for the contract. The other bidding consortium comprised the UAE’s Metito Utilities and Omani firm Sogex.

    The scope of the build, own, operate and transfer scheme will include extensive sewerage and distribution works in addition to the main treatment plant.

    Future PPP project

    For its part, Etihad WE is preparing to procure another utility PPP project in Ras Al-Khaimah.

    The project involves expanding the capacity of an existing seawater reverse osmosis plant in Ghalilah, which became operational in 2015. 

    The state-owned utility recently appointed Austria’s ILF Consulting Engineers to provide technical advisory services for the project, which is expected to be tendered this year.

    If successfully procured, it will be the first independent water project in Ras Al-Khaimah.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15465691/main.jpg
    Mark Dowdall
  • Dubai tenders Al-Maktoum airport metro link

    20 January 2026

     

    Register for MEED’s 14-day trial access 

    Dubai's Roads & Transport Authority (RTA) has invited consultants to bid for the design contract for the Route 2020 extension.

    The extended line will start from the Expo 2020 metro station and connect with Al-Maktoum International airport's West Terminal.

    The extension to the line will run for about 3 kilometres (km) and will feature two stations.

    MEED understands that the invitation to bid was issued earlier in January with a submission deadline of mid-March.

    The existing Route 2020 metro link is a 15km-long line branching off the existing Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks, 3.2km of tunnels, and has five elevated stations and two underground stations.

    In 2016, the RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain's Acciona, Turkiye's Gulermak and France's Alstom.

    Dubai's plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to Al-Maktoum International airport. There are long-term plans for further extensions.

    Other metro projects

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    The other metro lines in the pipeline are the Purple Line and the Pink Line, both of which are in the early stages of development.

    Firms are also bidding to update the emirate’s rail masterplan. Also in October 2025, MEED reported that 10 firms had submitted offers to undertake the project.

    The rail masterplan study will update and modify the RTA’s rail network, which includes the Dubai Metro and Dubai Tram. These plans will support Dubai’s 2040 urban masterplan, which aims for all residents to be within a 30-minute metro or light-rail trip to their place of work. 

    The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.

    There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services as well as a high-speed rail connection.

    In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.

    The Blue Line consists of 14 stations, including three interchange stations at Al-Jaddaf, Al-Rashidiya and International City 1, as well as a station in Dubai Creek Harbour. By 2040, daily ridership on the Blue Line is projected to reach 320,000 passengers. It will be the first Dubai Metro line to cross Dubai Creek and will do so on a 1,300-metre viaduct.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15465636/main.jpg
    Yasir Iqbal