Region advances LNG projects with pace

30 August 2024

 

Global liquefied natural gas (LNG) liquefaction capacity is expected to more than double by 2028, potentially increasing from 473 million tonnes a year (t/y) in 2023 to 968 million t/y in 2028 through new build and expansion projects, according to a recent report by GlobalData.

North America dominates globally among the regions, in terms of new build and expansion liquefaction capacity growth, contributing around 54% of the total global capacity additions or 268 million t/y by 2028, GlobalData says in the report. 

The Middle East comes in at second position, followed by the Former Soviet Union, with capacity additions of 78 million t/y and 71 million t/y, respectively. 

Since the start of this decade, there has been a sharp increase in investments in the Middle East and North Africa (Mena), and particularly in the Gulf region, in projects to expand LNG production. Capital expenditure close to $45bn has been made by Mena hydrocarbon producers in the past 10 years on various LNG projects, mainly for output capacity building, MEED Projects data shows. Almost three-fourths of that spending took place in the past four years, and predominantly in the GCC.

A desire to cater to the steady growth expected in global LNG demand and dominate the global supply market is fuelling the wave of investments into large-scale production capacity expansions and terminal construction by Gulf players.

Qatar guns for top spot

Qatar has been jostling with the US and Australia for the status of being the largest LNG provider to the world for many years now. The three countries have all clinched the top spot, only to be unseated by another the very next month.

However, when its mammoth North Field LNG expansion programme begins to come online later this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making steady progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company (CCC) in May last year.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

Qatar is, however, not stopping at that. QatarEnergy, in February, announced a third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project derives its name from the western zone of Qatar’s North Field offshore gas reserve, from where it will draw feedstock for LNG production.

Oman moves up the ladder

Oman has been supplying LNG to customers, mainly in Asia, for many years now. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

As recently as late July, the Omani government announced that Oman LNG will build a new train at its Qalhat LNG production complex in Sur, located in the sultanate’s South Al-Sharqiyah governorate. Oman LNG will perform the preliminary engineering study for the planned LNG train.

The LNG train will have an output capacity of 3.8 million t/y. When commissioned in 2029, it will increase Oman LNG’s total production capacity to 15.2 million t/y.

Aside from Oman LNG, France’s TotalEnergies has now committed itself to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies achieved final investment decision earlier this year for a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies leads a joint venture named Marsa LNG, which is the Sohar LNG terminal project developer. Marsa LNG was formed in December 2021 through an agreement between TotalEnergies and the sultanate’s state energy holding company OQ. The partners own 80% and 20% stakes, respectively.

Marsa LNG intends to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbon concessions in the sultanate, particularly from Blocks 10 and 11; an LNG bunkering terminal and storage units located in Sohar port; and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has picked France-based Technip Energies to perform EPC works on the estimated $1bn LNG terminal project.

Adnoc gives shape to ambitions

Abu Dhabi National Oil Company (Adnoc) has been a relatively smaller LNG producer in comparison to its GCC peers. Adnoc Group subsidiary, Adnoc Gas, operates three large gas processing trains on Das Island. At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The first and second trains were commissioned in the 1970s and have a combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s, with a capacity of 3.2 million t/y.

Adnoc Gas’ LNG production and export capability, however, will receive a major fillip when a new greenfield terminal it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade. The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.

Adnoc awarded the full EPC contract and achieved the final investment decision for the LNG terminal complex in June. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy was awarded the EPC contract, worth $5.5bn.

Jordan takes a step forward

Jordan imports more than 90% of its oil, gas and refined product needs and therefore has a strong economic case for developing projects to boost its domestic hydrocarbon infrastructure, particularly for gas.

The country recently took a key step forward when Aqaba Development Corporation awarded the main EPC contract in August for a project to develop the Sheikh Sabah Al-Ahmad Al-Jaber Al-Sabah LNG onshore regasification facility at the port of Aqaba.

The contract was won by a consortium of Singapore-based AG&P and South Korea’s Gas Entec, along with their local partner, Jordan’s Issa Haddadin.

In a statement, Gas Entec said that the facility will have the capacity to process 720 million cubic feet a day of natural gas. 

“Jordan relies heavily on natural gas for its power and industrial needs, but faces challenges with supply reliability,” Gas Entec said.

“The new LNG terminal will provide Jordan with the flexibility to access LNG from various global suppliers, ensuring a stable and secure energy source.”

Global LNG demand set for steady growth

https://image.digitalinsightresearch.in/uploads/NewsArticle/12432924/main.gif
Indrajit Sen
Related Articles
  • Contractor kicks off EPC work on Uthmaniyah gas compression package

    12 August 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia-based Saipem Nasser Saeed Al‑Hajri Contracting Company (SNSH) – a joint venture of Italian contractor Saipem and local contractor Nasser Saeed Al‑Hajri & Partners Company for Contracting – has kicked off work on the Uthmaniyah gas compression plant package in Saudi Arabia.

    The package forms part of a wider Saudi Aramco project to boost gas compression capacity at the Shedgum and Uthmaniyah processing plants in the Eastern Province.

    The Shedgum and Uthmaniyah plants currently receive about 870 million cubic feet a day (cf/d) and 1.2 billion cf/d of Khuff raw gas, respectively. Through the multibillion-dollar project, Aramco aims to increase the compression and processing capacity of both plants, as well as build new pipelines to enhance gas transportation.

    Aramco formally awarded the key engineering, procurement and construction (EPC) contract for the Uthmaniyah gas compression plant package to SNSH in June.

    The value of the contract won by SNSH is estimated at $1.24bn, sources previously told MEED. Separately, Milan-headquartered Saipem said its share of the contract is €900m ($1.04bn) and that the EPC works will run for 42 months.

    The scope covers the EPC of a new compression plant serving the non-associated Uthmaniyah gas field, Saipem said in its statement. Saipem added that “the new compression plant will extend the production life of the field, helping to support the growing energy demand of the Kingdom of Saudi Arabia”.

    The contract for the Uthmaniyah gas compression plant package is the first EPC project awarded under Aramco’s National EPC Champion programme, Euronext Milan-listed Saipem said.

    Shedgum and Uthmaniyah gas compression project

    The Uthmaniyah gas compression plant contract is one of nine EPC packages under the broader Shedgum and Uthmaniyah gas compression project. The packages are:

    1. Shedgum gas compression facility and SGP in-plant works
    2. Uthmaniyah gas compression facility and UGP in-plant works
    3. Shedgum gas compression pipelines package
    4. Uthmaniyah gas compression pipelines package
    5. Shedgum and Uthmaniyah central temporary construction facilities
    6. Shedgum and Uthmaniyah early works site preparation
    7. Operation and maintenance of Saudi Aramco Project Management Team temporary construction facilities and accommodation
    8. Shedgum and Uthmaniyah gas compression plant PIA
    9. Shedgum and Uthmaniyah gas compression plant PSA.

    Aramco has awarded package 6 (early works site preparation) to local firm Al-Shalawi International Company Trading & Contracting, sources told MEED.

    Aramco is also understood to be in discussions with India’s Larsen & Toubro Energy Hydrocarbon (L&T), among other bidders, for package 1 (Shedgum gas compression facility and SGP in-plant works), sources said.

    Separately, Aramco was said to be in negotiations with a consortium of China’s Sinopec and Dammam-based Al‑Qahtani Pipe Coating Industries for package 4 (Uthmaniyah gas compression pipelines). However, the consortium fell short of providing bond guarantees and did not meet other Aramco requirements, leading to its break-up, sources told MEED. Aramco may now open discussions with other bidders for the package.

    Meanwhile, Khobar-based Arkad Engineering & Construction has emerged as the lowest bidder for package 3 (Shedgum gas compression pipelines), with Aramco expected to award the contract in June, according to sources.

    Contractors submitted bids for packages of the Shedgum and Uthmaniya gas compression capacity expansion project in January, MEED previously reported.

    The Saudi energy giant is understood to have started the solicitation of interest process for the main EPC contract tendering exercise in the fourth quarter of 2024.

    Aramco subsequently issued the tenders for the EPC packages of the scheme during the second quarter of last year and set an initial bid submission deadline of 17 August.

    Aramco then extended the bid submission deadline to 17 November7 December, and then to January, according to sources.

    In line with its aim of increasing gas production and processing capacity by 80% by 2030, with 2021 as its baseline, Aramco is investing significant capital in gas projects in the kingdom.

    Photo credit: Saipem via


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18366754/main.jpg
    Indrajit Sen
  • KJO selects contractors for Dorra gas project offshore packages

    12 August 2026

     

    Al-Khafji Joint Operations (KJO) has selected contractors for two major offshore packages under its multibillion-dollar Dorra field facilities development project. The Dorra gas field is located in the waters of the Saudi-Kuwait Neutral Zone.

    KJO – jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary Kuwait Gulf Oil Company – has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.

    US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.

    A consortium of India’s Larsen & Toubro Energy Hydrocarbon (L&TEH) and Italian contractor Saipem has secured package 2B, sources told MEED. Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.

    MEED reported in March that the L&TEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.

    Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.

    Offshore package scopes

    The EPC scope of work on the two offshore packages of the Dorra gas field facilities project is as follows:

    Package 2A – Dorra gas field wellhead topsides, flowlines and umbilicals

    • Seven gas wellhead platforms or topsides, with production routed to the central gathering platform
    • Corrosion-resistant, alloy-lined intra-field flowlines and umbilicals connecting the gas wellhead platforms to the central gathering platform and the auxiliary platform

    Package 2B: Dorra central gathering platform complex, export pipelines and cables

    • Central gathering platform
    • Auxiliary platform
    • Dorra accommodation platform
    • Flare platform
    • Bridge platform
    • Pipelines for gas and condensate transmission to each shareholder
    • Produced water pipeline from the central gathering platform to Al-Khafji field and from the planned onshore processing facility next to the Al-Zour refinery in Kuwait to Al-Khafji field
    • Recovered monoethylene glycol (MEG) pipeline from Al-Khafji field to the central gathering platform
    • Control and power system linking Al-Khafji onshore facilities to offshore units
    • Offshore central control room at Dorra accommodation platform.

    Regarding the first offshore package, MEED reported in October last year that KJO awarded India’s L&TEH a contract estimated at $140m-$150m. Offshore package 1 covers the EPC of seven offshore jackets and the laying of intra-field pipelines.

    Separately, KJO is understood to be holding discussions for package 3 with Spanish contractor Tecnicas Reunidas, which emerged as the lowest bidder, as MEED reported in March. Sources said a final client decision on the award is pending.

    Onshore package scope

    The scope of work on the only onshore package of the Dorra gas field facilities project is as follows:

    Package 3: Onshore gas processing facilities

    • Buildings to be constructed as part of KJO’s Dorra project onshore package include:
      • Dorra control building
      • Operator building
      • Operations, maintenance and engineering building
      • Process interface building
      • Onshore 115/69kV substation
      • Two gas-insulated substations
      • Warehouse
      • Maintenance building
      • Mosque
      • Telecommunications tower radio building
      • Beach valve substation at the planned onshore processing facility next to the Al-Zour refinery in Kuwait
         
    • Processing facilities for KJO’s onshore package:
      • Produced water receiving and treatment
      • Sour water stripping and treated water system
      • Rich MEG storage tank
      • MEG regeneration and reclamation
      • Recovered hydrocarbons system
      • Lean MEG storage and supply
      • Fresh MEG storage and supply
      • Beach valve stations at Al-Khafji and Al-Zour
         
    • Utilities:
      • Instrument and plant air system
      • Nitrogen generation system
      • Diesel storage and distribution system
      • Fuel gas system
      • Closed drain and slop tank system
      • Hazardous area open drains system
      • Industrial water system
      • Drinking water system
      • Flare gas recovery system and a low-pressure flare system
      • Fire water system
      • Emergency diesel generator
      • Sewage treatment

    Discovered in 1965, the Dorra gas field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.

    Saudi Arabia and Kuwait have been pressing ahead with their plan to jointly produce 1 billion cubic feet a day (cf/d) of gas from the Dorra gas field.

    The two countries have been producing oil from the Neutral Zone – primarily from the onshore Wafra field and offshore Khafji field – since at least the 1950s. With a growing need to increase natural gas production, they have been working to exploit the Dorra offshore field, understood to be the only gas field in the Neutral Zone.

    Progress has been hampered by a dispute over ownership of the Dorra gas field. Iran, which refers to the field as Arash, claims it partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development. Kuwait and Saudi Arabia maintain that the field lies entirely within their jointly administered Neutral Zone – also known as the Divided Zone – and that Iran has no legal basis for its claim.

    In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.

    France-based Technip Energies has performed the entire concept study and feed work on the overall Dorra gas field development programme.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18365989/main3026.jpg
    Indrajit Sen
  • Oman reaches financial close on 120MW wind project

    12 August 2026

    Register for MEED’s 14-day trial access 

    Oman’s 120MW Jaalan Bani Bu Ali (JBB) wind independent power project (IPP) has reached financial close, according to the consortium developing the project.

    The project is being developed by a consortium comprising French firm EDF Power Solutions, Oman’s Al-Khadra Partners and OQ Alternative Energy.

    Located in South Al-Sharqiyah Governorate, about 440 kilometres from the Port of Duqm, the project will comprise 16 wind turbines, each with a capacity of 7.7MW.

    Commercial operations are expected to begin in the third quarter of 2027. The JBB project is EDF Power Solutions’ first wind project in Oman.

    Oman’s Nama Power & Water Procurement (Nama PWP) signed a 20-year power purchase agreement (PPA) to develop, finance, build and operate the project last December.

    As exclusively reported by MEED, a consortium of Chinese companies also signed the engineering, procurement and construction (EPC) contract to build the plant that same month.

    The consortium comprises China Energy Engineering Corporation, PowerChina, East China Electric Power Design & Research Institute and Hunan Thermal Power, all headquartered in Beijing.

    Once operational, the wind farm is expected to generate enough renewable electricity to supply more than 13,500 Omani households annually. It is also expected to avoid more than 270,000 tonnes of carbon dioxide emissions a year.

    The project supports Oman’s target of increasing the share of renewable energy in its national electricity mix to at least 30% by 2030. It also supports the country’s Net Zero 2050 target.

    In May, Muscat-based Monenco Consulting Engineers won a consultancy contract for a grid station project linked to the Jaalan Bani Bu Ali wind farm project.

    The contract was awarded by China Energy Engineering Corporation, the lead EPC contractor for the Jaalan Bani Bu Ali IPP.

    The scope includes engineering and detailed design consultancy services for the grid station and associated overhead line linked to the wind farm, which is expected to begin construction by the end of the third quarter.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18364806/main.jpg
    Mark Dowdall
  • Kuwait utilities investment shifts towards water

    11 August 2026

     

    China State Construction Engineering Corporation recently signed a contract for Kuwait’s North Kabd wastewater treatment plant, the country’s largest wastewater infrastructure project to date.

    The award, following more than a decade of planning, propelled Kuwait’s water sector contract awards to more than $4bn as of early August, according to regional project tracker MEED Projects.

    The facility will have a treatment capacity of up to 1 million cubic metres a day (cm/d), with the $3.3bn contract covering the design, construction, operation and maintenance of the plant over a 10-year period.

    It marks a significant recovery for the sector after several years of subdued activity and the first time since 2020 that annual water awards have exceeded $1bn.

    North Kabd is the largest of several major water projects awarded this year, alongside contracts covering desalination and the expansion and rehabilitation of water distribution infrastructure.

    Desalination and distribution

    These include a $316m contract awarded to local firm United Gulf Construction (UGC) by the Ministry of Electricity, Water & Renewable Energy (MEWRE) for the rehabilitation and expansion of the Doha water distribution complex.

    The five-year project includes a new pump station and will add about 130 million imperial gallons of storage capacity, while increasing pumping capacity to 220 million imperial gallons a day (MIGD).

    UGC was also selected in February to upgrade the Hawally water distribution complex in Kuwait’s Hawalli Governorate. The facility serves one of Kuwait’s most densely populated governorates, with the project intended to address chronic low water pressure, particularly during peak summer demand, and improve continuity of supply.

    The upgrade will increase freshwater storage capacity by 66 million gallons and raise potable-water pumping capacity to 54.5 million gallons a day.

    In April, Kuwait’s Central Agency for Public Tenders approved MEWRE’s recommendation to award a $371m contract for phase two of the Doha seawater reverse osmosis (SWRO) desalination plant.

    A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag will carry out the project, which will have a capacity of about 272,000 cm/d.

    Upcoming water awards

    Meanwhile, Kuwait’s Ministry of Public Works (MPW) has been progressing several tenders for major water infrastructure projects covering rainwater drainage and treated water systems in the country’s southern and northern regions.

    In July, local Combined Group Contracting submitted the lowest bid for a contract to develop a major treated water system in the southern region. The contractor submitted a price of about $515m for the scheme, according to a company disclosure.

    For the smaller northern treated water system, Contractor General Trading & Contracting submitted the lowest bid of $169m.

    In what is already a standout year for Kuwait’s water sector, further awards could push activity significantly higher. More than $1bn of water projects are currently under bid evaluation, indicating further evidence of a sustained recovery in the months ahead.

    Power sector activity

    Kuwait’s power sector recorded just $271m of contract awards by early August, according to MEED Projects, putting activity well below recent annual levels.

    This compares with a record full-year total of $5.5bn in 2025 and $2.7bn in both 2024 and 2023.

    Several large-scale generation projects have been slow to advance, with deadline extensions a notable feature in recent months. The outlook is stronger, however, with these projects now progressing through procurement and significant awards expected in the months ahead.

    Kuwait is advancing the 1,800MW Al-Khairan phase one independent water and power project (IWPP), for which two developer consortiums led by Abu Dhabi National Energy Company (Taqa) and Saudi Arabia’s Acwa submitted bids in June.

    The project will also include a desalination plant with a capacity of 125 MIGD. A second phase of the Al-Khairan IWPP, estimated at $750m, is understood to include a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant. The project remains in the early development stages, with tendering not expected until at least 2027.

    Renewable energy programme

    The Kuwait Authority for Partnership Projects (Kapp) is also progressing the Al-Dibdibah power and Al-Shagaya renewable energy programme in partnership with Kuwait’s MEWRE.

    The contract to develop the 1,100MW phase three, zone one solar photovoltaic (PV) project is expected to be confirmed soon, with a consortium led by Abu Dhabi Future Energy Company (Masdar) previously reported to be the frontrunner.

    A separate 500MW solar PV project is also being procured under phase three, zone two of the same programme, with bids submitted on 26 July. If the contract is awarded by the end of the year, the two Shagaya contracts would add about $2bn to the value of power sector awards.  

    Another notable development was the 25-year energy conversion and water purchase agreement signed in February for the Al-Zour North IWPP phases two and three. The signing marked a key step towards financial close on the estimated $4bn project. Once completed, the facility will add 2,700MW of power and 120 MIGD of desalinated water to Kuwait’s supply network

    The Shagaya, Khairan and Zour North projects form a key part of Kuwait’s generation portfolio. The country is aiming to reach 22,100MW of installed renewable energy capacity by 2030, under a 20-year strategy announced in March 2025 that extends to 2050.

    Kuwait is also continuing to invest in existing generation plants. MEWRE is evaluating bids for the $1.7bn upgrade of the Subiya power and water plant, including the conversion of units from open-cycle to combined-cycle operation and the modernisation of existing facilities.

    Battery energy storage systems

    In the near to medium term, more than $10bn-worth of power projects are under bid evaluation. This includes several battery energy storage system projects with a planned total storage capacity of 1.5GW.

    In June, Kuwait approved sites in Al-Mutlaa and Jaber Al-Ahmad cities for the development of the projects. The projects will be implemented in phases, with the first phase providing 500MW of storage capacity. The first facilities are expected to be operational by summer 2027 and will supply stored energy to the electricity grid during periods of peak demand.

    Elsewhere, MEWRE continues to evaluate offers from Shanghai Electric Group and local firm Heavy Engineering Industries & Shipbuilding Company (Heisco) for the estimated $400m engineering, procurement and construction contract to rehabilitate and modernise eight boilers at the Subiya power generation and water distillation station. The bid bond validity has been extended to 23 August, indicating that the procurement process remains ongoing.


    MEED’s September 2026 report on Kuwait also includes:

    > ECONOMY: Kuwait shows tentative signs of economic development
    > BANKING: Necessity is the mother of invention for Kuwaiti lenders
    > OIL & GAS: Regional war to have lasting impact on Kuwaiti oil sector
    > CONSTRUCTION: Kuwait construction holds up despite regional strife

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18333042/main.gif
    Mark Dowdall
  • Syrian court gives death penalty to Bashar Al-Assad

    11 August 2026

    Register for MEED’s 14-day trial access 

    A Syrian court has sentenced former president Bashar Al-Assad to death after trying him in absentia, convicting him of crimes committed during the country’s nearly 14 years of civil war.

    It is the first such ruling under Syria’s transitional authorities, who ousted Al-Assad in December 2024 and vowed justice and accountability for crimes committed under his rule.

    Al-Assad fled to Moscow as Islamist-led forces closed in on Damascus after a lightning offensive.

    In a Damascus court, Judge Fakhr Al-Din Al-Aryan convicted Al-Assad of crimes including “premeditated murder, the intentional killing of more than one person, the intentional killing of children under 15 years … torture, torture leading to death, and deprivation of liberty on multiple occasions” — acts the court classified as crimes against humanity and war crimes.

    “He is therefore sentenced to death,” the judge said in his ruling.

    The court also sentenced six former military and security officials to death in absentia, including Al-Assad’s brother Maher, who ran the army’s elite Fourth Division and also fled the country.

    Those convicted included former defence minister Fahd Al-Freij and Louay Al-Ali, who headed military intelligence in Daraa province in 2011.

    ALSO READ: Syria charts post-war reconstruction course

    The officials were convicted of crimes including murder, incitement to murder, torture leading to death and repeated deprivation of liberty, also classified as crimes against humanity and war crimes.

    Former security official Atif Najib – the only defendant tried in person – was also sentenced to death for crimes against humanity committed while he headed political security in Daraa province, the cradle of the country’s 2011 uprising.

    Najib, a cousin of Al-Assad who was arrested in January last year, was convicted of crimes including murder, the intentional killing of children under 15 and torture leading to death.

    The acts attributed to him are “crimes against humanity”, the court said as it handed down “the harshest punishment … which is the death penalty”.

    ALSO READ: US lifts sanctions on Syria after the EU takes similar action

    Syria began proceedings in April against Al-Assad and other officials, accused both in person and in absentia of atrocities during the civil war, which erupted after the former authorities’ brutal repression of pro-democracy protesters.

    More than half a million people were killed and millions displaced, while tens of thousands disappeared, many into the country’s brutal prison system.

    The uprising began in Daraa in March 2011 after 15 students were arrested for allegedly writing anti-government slogans on the city’s walls.

    Residents said the students were tortured, prompting protests demanding their release that ended in bloodshed.

    Security forces suppressed demonstrations and fired live ammunition to disperse sit-ins at several locations.

    Najib was dismissed after the crackdown as protests spread to other provinces.

    Judge Al-Aryan said Najib had denied the charges and shown “no remorse”.

    Al-Assad took power in Syria in 2000 in an unopposed election following the death of his father, Hafez Al-Assad, who was president from 1971.

    ALSO READ: Syria exports first crude oil batch in 14 years

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18331541/main.gif
    MEED Editorial