Red Sea wind farm starts operations
16 April 2025
Register for MEED’s 14-day trial access
The 500MW initial phase of the Gulf of Suez wind farm in Ras Ghareb, Egypt, has started commercial operations six months ahead of schedule, according to the project's developer, Red Sea Wind Energy.
Red Sea Wind Energy is developing the project on a build, own and operate basis. It comprises a consortium of France’s Engie with a 35% stake; the local Orascom Construction, which holds 25%; Japan’s Toyota Tsusho Corporation with 20%; and Eurus Energy Holdings Corporation with 20%.
The completion of the 500MW wind farm phase takes Oracom Construction's renewable energy portfolio to 912.5MW of wind farms, in addition to three water projects in Egypt, the UAE and Saudi Arabia.
The Cairo-based firm is also responsible for executing the engineering, procurement and construction (EPC) work on the balance of the plant, as well as all carrying out civil and electrical works at the Ras Ghareb wind farm.
Red Sea Wind Energy reached financial close on the 150MW expansion of the 500MW Gulf of Suez wind farm project in January this year, at the same time as it announced that the first 306MW of the project had started commercial operations.
The original project has a capacity of 500MW, which reached financial close in early 2023.
The expansion adds another 150MW, with the original lenders together extending a further co-financing totalling $106m, MEED previously reported.
Orascom said the project's 150MW new phase is financed by the same partners that financed the original 500MW project capacity.
Non-recourse project financing is provided by Japan Bank for International Cooperation (JBIC) in coordination with Sumitomo Mitsui Banking Corporation (SMBC), Norinchukin Bank, France's Societe Generale under a Nippon Export & Investment Insurance (Nexi) cover, and the London-based European Bank for Reconstruction & Development (EBRD).
HSBC Bank Egypt acted as the working capital bank and onshore security agent.
JBIC signed a loan agreement of approximately $51m with Red Sea Wind Energy to finance the project, MEED reported in November last year.
JBIC confirmed at the time that the total loan of $106m was co-financed with the other four banks.
It is understood that the 150MW expansion required an additional investment of about $127m.
According to Nexi, it will provide cover for an approximately $35m loan extended by the commercial banks, as well as for the interest rate swap agreement guaranteed by SMBC.
The project company has been developing the 500MW onshore wind farm, which is located in the Ras Ghareb region facing the Red Sea, approximately 200 kilometres southeast of Cairo. It consists of 84 wind turbine generators.
The 150MW expansion of the project entails the addition of a further 20 wind turbine generators.
The consortium will operate and maintain the plant under a 25-year power-purchase agreement (PPA) with the Egyptian Electricity Transmission Company (EETC). Egypt’s Finance Ministry is backing the EETC’s obligations under the PPA.
This project marked the first co-financing by JBIC and EBRD since the signing of a memorandum of understanding (MoU) in October 2022, and the first joint project by Nexi and EBRD since an MoU in October 2020.
MEED reported in March 2023 that JBIC had signed a loan agreement to finance up to $240m of the project.
Exclusive from Meed
-
Read the October 2026 MEED Business Review30 September 2026
-
Aramco receives interest for major gas processing plant30 September 2026
-
Libya refinery expected to be worth more than $600m30 September 2026
-
Joint venture wins $230m Ras El-Hekma buildings30 September 2026
-
Neom tenders Oxagon freight rail design30 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Read the October 2026 MEED Business Review30 September 2026
Download / Subscribe / 14-day trial access For all the talk of cancellations and cutbacks, Neom is still building – and its biggest completed project to date offers a clue to where the $500bn gigaproject is heading. Our October Agenda feature examines how Oxagon is moving to the centre of Neom’s strategy, as investment shifts towards projects with the potential to generate tangible commercial returns, from green hydrogen and ports to AI data centres and logistics infrastructure.
Read the full analysis in the October issue of MEED Business Review.As Neom reshapes its priorities, Saudi Arabia’s wider project market continues to show resilience. Contract awards have reached $68bn in 2026, despite regional conflict and economic uncertainty, with activity spanning energy, infrastructure, power and the future economy.
But with $91.5bn of projects completed this year, new awards will be crucial to maintaining momentum into 2027.
This edition also includes MEED’s 2026 power developer ranking, revealing the companies driving the region’s rapidly expanding power market.
The issue also explores key trends shaping the region, from AI’s growing demands on grid capacity and the implications of ICE Futures Abu Dhabi’s wind-down for Gulf commodity markets, to how the Hormuz crisis is redirecting oil companies’ focus to North Africa. Our Leadership feature asks whether the future city really needs to hang above the ground.
We hope our valued subscribers enjoy the October 2026 issue of MEED Business Review.

Must-read sections in the October 2026 issue of MEED Business Review include:
> AGENDA: Oxagon takes centre stage at NeomINDUSTRY REPORT:
MEED’s 2026 power developer ranking
> Regional power market diversifies
> Battery storage broadens IPP market> POWER: AI is creating a grid capacity problem
> LEGAL: What IFAD’s wind-down means for Gulf commodity markets
> OIL: Oil companies focus on North Africa amid Hormuz crisis
> LEADERSHIP: The future city does not need to hang above the ground
> SAUDI ARABIA MARKET FOCUS:
> COMMENT: Saudi projects hold steady
> GOVERNMENT: Riyadh looks to reset its regional defence outlook
> ECONOMY: Conflict bolsters case for Saudi economic diversification
> BANKING: Saudi lenders readjust to lower lending and deposit climate
> UPSTREAM: Aramco upstream spending gathers pace
> DOWNSTREAM: Sabic steps up Saudi petchems investment
> POWER: Saudi Arabia’s power award activity slows
> WATER: Saudi water sector hits sharp slowdown
> CONSTRUCTION: Saudi construction defies the headwinds
> TRANSPORT: Saudi infrastructure pushes forward amid conflict
> DATABANK: Saudi data indicates project spending shift> MEED COMMENTS:
> Dubai Inc steps in as developers turn cautious
> Saudi Arabia redirects towards AI
> Kuwait plans biggest oil and gas contract award in 10 years
> Saudi Arabia battery storage awards provide fresh lift> GULF PROJECTS INDEX: Saudi Arabia and UAE lead Gulf index gains
> AUGUST 2026 CONTRACTS: Middle East contract awards
> ECONOMIC DATA: Data drives regional projects
> OPINION: The boomers’ last act
> BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts
To see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20134595/main.gif -
Aramco receives interest for major gas processing plant30 September 2026

Saudi Aramco has received expressions of interest from contractors to participate in the main tendering exercise for a project to expand the Alhada gas processing plant, located about 85 kilometres northwest of Jubail in Saudi Arabia’s Eastern Province.
The Alhada gas processing plant expansion is critical to Aramco’s goal of increasing gas production capacity by 80% by 2030 from a 2021 baseline.
Aramco issued a solicitation of interest document for the main tendering exercise in early September, with contractors submitting responses by 17 September, sources told MEED.
The engineering, procurement and construction (EPC) scope of work has been divided into three main packages, sources said.
The first EPC package relates to the main gas treatment facilities, primarily three processing trains, along with:
- Three acid gas removal units
- Triethylene glycol (TEG) dehydration unit
- Two high-pressure and two low-pressure flares
- Two flare gas recovery units
- Two T&l flares
- Two burn pits
- A digital twin
The acid gas removal units will treat sour gas by removing hydrogen sulphide and carbon dioxide to produce sales gas, as well as acid-gas feed for the downstream acid gas enrichment unit and sulphur recovery unit.
The acid gas removal units will also process gas from the flare gas recovery units through a dedicated amine contactor to meet specifications for use as fuel gas. The TEG dehydration unit will then remove water from the treated gas to meet sales-gas specifications.
The project’s second EPC package covers the sulphur recovery units. The third package involves inlet channels for monoethylene glycol, as well as common utilities and supporting structures.
ALSO READ: Contractors express interest in sixth Jafurah expansion phase
https://image.digitalinsightresearch.in/uploads/NewsArticle/20127671/main4900.jpg -
Libya refinery expected to be worth more than $600m30 September 2026

The main contract for Libya’s planned South Refinery project is expected to be worth more than $600m, according to industry sources.
The project, located in Ubari in southern Libya, has gained momentum over the past year. The main contract is expected to be procured under an engineering, procurement and construction (EPC) model.
In March, US-based engineering company KBR was awarded a contract by Zallaf Exploration, Production & Refining of Oil & Gas Company to provide project management and technical services for the project.
Under the terms of the contract, KBR will provide contract management, project management and supporting technical services throughout the project’s EPC phases.
The EPC work is expected to take 50 months, and the facility will be designed to process 30,000 barrels a day (b/d) of crude oil.
The refinery is expected to produce:
- Propane and butane for domestic and industrial uses
- Gasoline
- Kerosene
- Diesel
- Fuel oil
In March, KBR said that the project was aligned with its “long-standing commitment to advancing vital oil and gas infrastructure in Libya”.
Libya currently operates five main refineries with a combined nameplate capacity of 380,000 b/d, but actual throughput is closer to 180,000 b/d due to poor maintenance and damage from military clashes.
In addition to the South Refinery project, Libya also plans to upgrade the Zawiya refinery and carry out projects at the Serir, Brega, Tobruk and Ras Lanuf refineries.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20124329/main.jpg -
Joint venture wins $230m Ras El-Hekma buildings30 September 2026
A joint venture of UK-based Innovo Build and Egypt’s Redcon Construction has won a contract worth about E£12bn ($230m) to carry out infrastructure and construction works for the DP03 East package of the Wadi Yemm development at Ras El-Hekma on Egypt’s North Coast.
Wadi Yemm is being developed by the UAE’s Modon Development as the first phase of its Ras El-Hekma masterplan, which will comprise 17 planned districts.
DP03 East has a built-up area of 323,000 square metres and is scheduled for completion within 21 months.
The scope of work includes more than 660 residential units – comprising standalone villas and townhouses – as well as public service areas, lakes, a commercial mall, landscaping and roadworks.
The delivery of units at Wadi Yemm is expected to begin in the third quarter of 2029.
Ras El-Hekma is located on a spur of land on Egypt’s northern Mediterranean coast, about 240 kilometres west of Alexandria.
Abu Dhabi-based holding company ADQ appointed Modon Holding as master developer for the Ras El-Hekma project in 2024. Modon will oversee the overall development, which covers more than 170 million square metres (sq m).
Modon will develop the first phase, covering 50 million sq m. The remaining 120 million sq m will be developed in partnership with private developers, under the supervision of the recently established ADQ subsidiary Ras El-Hekma Urban Development Project Company and Modon.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20123189/main.jpg -
Hassan Allam wins $1bn Cairo mixed-use project deal30 September 2026
Register for MEED’s 14-day trial access
Grova Developments, the real estate development arm of Egypt’s Hassan Allam Holding, has awarded Hassan Allam Construction a $1bn contract to deliver the Grova Westfields project in West Cairo.
Hassan Allam Construction’s scope of work includes a 150-key five-star hotel, branded residences, luxury villas and apartments, as well as infrastructure and landscaping works.
The project spans about 1.2 million square metres and is being developed in partnership with the Egyptian Kuwaiti Company for Real Estate Development.
Broadway Malyan has been appointed to lead the master planning and architectural design.
In October last year, Hassan Allam Construction announced that it had won a $550m contract to build another mixed-use development spanning more than 128 hectares in New Cairo.
That development comprises villas, townhouses, commercial and office space, mixed-use buildings, infrastructure and other associated facilities.
Hassan Allam Properties is co-developing the project with Grova Developments.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20123048/main.jpeg