QatarEnergy LNG prepares to receive decarbonisation bids

20 March 2025

Register for MEED’s 14-day trial access 

QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

  • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung C&T (South Korea)

The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

The EPC scope of work on the project covers the following:

  • QG North complex:
    • Installation of four new electric-driven compressors
    • New power substation for power import from Kahramaa 65MW
    • New ITR for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Pig launcher
       
  • QG South complex:
    • Installation of two new electric-driven compressors
    • Integration with South injection system unit 85
    • Solvent reformulation for South trains 1/23
    • New power substation for power import from Kahramaa 35MW
    • New SIH for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Chillers package
    • Pig launcher
       
  • RLIC corridors
    • Common 22-inch export pipeline stretching 18 kilometres
    • Power tie-in RLF3 with Kahramaa
    • Electric cables
    • Fiber optic cable
       
  • Lot W15
    • Six injection wells by QatarEnergy LNG subsurface
    • Six injection flowlines and metring skid
    • Six wellhead control panels
    • Power tie-in from Barzan
    • Substation
    • Pig receiver
    • Access road and fencing

QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

North Field LNG expansion

Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

EPC works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.


February's special report on Qatar includes

> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
Indrajit Sen
Related Articles
  • Kuwait tenders two Al-Mutlaa City construction packages

    2 September 2026

    Register for MEED’s 14-day trial access 

    Kuwait’s Public Authority for Housing Welfare (PAHW) has tendered two contracts covering the construction of public buildings across five districts at its Al-Mutlaa City residential project.

    The first tender covers construction in the N5 and N6 districts, while the second covers N1, N3 and N4.

    The tenders were issued on 30 August, with a bid submission deadline of 30 September.

    The project is a housing scheme located 38.3 kilometres northwest of the Kuwait metropolitan area.

    It covers approximately 104 square kilometres and is expected to house up to 400,000 people.

    The mixed-use development will include residential, social, commercial and light industrial areas.

    In March 2023, MEED reported that PAHW had appointed France-based Egis as a project management consultant for the Al-Mutlaa City development.

    Under the agreement, Egis is providing programme-level service management, construction logistics and interface management services.

    The scope of work also includes cost management, a digital programme management system and a project management information system for the scheme.

    Al-Mutlaa City is one of the largest housing infrastructure projects being developed by the government as part of Kuwait’s Vision 2035.

    UK analytics firm GlobalData expects Kuwait’s construction industry to grow at an average annual rate of 7.1% in 2025-28, supported by investment in renewable energy, transport and oil and gas projects, as well as spending under the New Kuwait 2035 National Development Plan.

    Under this strategy, the government plans to invest KD350m ($1.1bn) to develop several sports projects in the country.

    The residential construction sector is expected to register average annual growth of 3.8% in 2025-28, supported by the government’s plan to build 65,500 housing units by 2029 through five projects.


    MEED’s September 2026 report on Kuwait includes:

    > COMMENT: Kuwait keeps dealmaking alive under fire
    > GOVERNMENT: Kuwait shows tentative signs of economic development
    > BANKING: Necessity is the mother of invention for Kuwaiti lenders
    > OIL & GAS: Regional war to have lasting impact on Kuwaiti oil sector
    > POWER & WATER: Kuwait utilities investment shifts towards water
    > CONSTRUCTION: Kuwait construction holds up despite regional strife
    > MARKET TALK: Kuwait stands resilient amid regional tensions

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19245517/main.png
    Yasir Iqbal
  • Preferred bidders emerge for Zatca residential PPP

    2 September 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Zakat, Tax and Customs Authority (Zatca), through the National Centre for Privatisation and PPP (NCP), has selected preferred bidders to develop residential buildings at various land ports across the kingdom.

    The project covers developments across nine land ports, separated into two packages.

    Local firm Saudi Arabian Trading & Construction Company has been selected as the preferred bidder for the first package, which includes the Al-Batha, Salwa, Al-Raqi, Jadidat Arar, Al-Wadiah and Empty Quarter sites.

    Bahrain-headquartered Lamar Holding is the preferred bidder for the second package, which includes land ports at Al-Hadithah, Halat Ammar and Al-Durrah.

    The project will be implemented as a public-private partnership (PPP) on a design, build, finance, operate, maintain and transfer basis, with a contract duration of 23 years, including the construction period.

    The contract covers the construction and management of new residential buildings and associated facilities at the land ports, as well as the rehabilitation of existing facilities.

    The project is the latest scheme in the kingdom’s PPP pipeline. In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.

    Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.

    In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19244076/main.jpg
    Yasir Iqbal
  • NWC confirms $347m Saudi sewage treatment plant deal

    2 September 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s National Water Company (NWC) has signed a contract worth more than SR1.3bn ($347m) with a Saudi-Chinese consortium to rehabilitate, operate and maintain nine sewage treatment plants (STPs).

    The 15-year contract covers plants located across the Hail, Qassim, Al-Jouf and Northern Borders provinces. The plants have a combined treatment design capacity of more than 337,000 cubic metres a day (cm/d).

    MEED exclusively reported in January that the consortium comprising China’s Jiangsu United Water Technology and Saudi-based Armada Holding had won the contract for the project.

    The contract is for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10) and includes an initial three-year period for rehabilitation and upgrade works, followed by long-term operation and maintenance.

    As MEED understands, United Water will be responsible for design, financing, operation and part of the construction works. Saudi Arabia’s Armada Holding will handle construction, equipment import customs clearance and local business communications. UAE-registered Prosus Holding will act as the financial investor.

    LTOM packages

    The same consortium is also expected to sign a contract for Package 11 of the LTOM programme in the coming months.

    In April, MEED exclusively reported that the consortium won the contract for this project, which will have a combined capacity of about 440,000 cm/d.

    Bids for North Western B Cluster (LTOM12) remain under evaluation. The contract covers the construction and upgrade of seven STPs with a combined capacity of about 162,000 cm/d.

    NWC also tendered the Eastern A Cluster (LTOM14) package in April, covering the upgrade of six existing STPs with a capacity expansion of 30,000 cm/d at the Al-Jarodia STP.

    This will increase total treatment capacity from about 263,000 cm/d to approximately 293,000 cm/d, with an estimated cost of $180m.

    The bid submission deadline is 30 September.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19242964/main.jpg
    Mark Dowdall
  • Egypt signs PPA for 1GW Ras Shokeir wind farm

    2 September 2026

    Register for MEED’s 14-day trial access 

    A joint venture of the local Hassan Allam Utilities Energy and Infinity Power has signed a power purchase agreement (PPA) with Egyptian Electricity Transmission Company (EETC) for the development of the 1GW Ras Shokeir wind project in Egypt.

    The project is located in Egypt’s Red Sea Governorate, within the Gulf of Suez wind corridor. It will cover approximately 143 square kilometres.

    The PPA has a 25-year term. The project will supply electricity to Egypt’s national grid.

    Ras Shokeir is expected to generate enough electricity to power more than 1.2 million Egyptian homes. It is also expected to avoid more than 1.36 million tonnes of CO2 emissions annually.

    The PPA was signed by EETC chairperson Mona Rizk and Infinity Power co-founder and CEO Nayer Fouad, representing the Infinity Power-Hassan Allam consortium.

    The signing brings the project closer to development as Egypt seeks to expand its renewable energy capacity. Egypt has set a target for renewable energy to make up 42% of the electricity mix by 2030 and 65% by 2040.

    This includes the 500MW Amunet 2 wind project, which is being developed by UAE-headquartered Amea Power following the commissioning of the first Amunet wind project in June 2025.

    Hassan Allam Utilities Energy and Infinity Power are also developing Egypt’s $560m West Minya solar plant, which will combine 1,000MWac of solar photovoltaic capacity with a 600MWh battery energy storage system.

    In June, MEED reported that a joint venture of Hassan Allam Construction and India’s Sterling & Wilson Renewable Energy had won the engineering, procurement and construction contract for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19242701/main1603.jpg
    Mark Dowdall
  • Iraq looks to accelerate oil pipeline projects

    2 September 2026

    Iraq’s Ministry of Oil has held talks with a delegation from Qatari company UCC on accelerating the progress of two major pipeline projects, according to a statement from Iraq’s Office of Media and Government Communication.

    The first proposed pipeline route extends from Basra, in southern Iraq, to Haditha, located about 200 kilometres northwest of Baghdad, then on to Faysh Khabur, which lies on the border with Syria and near the border with Turkiye.

    The second pipeline extends from Haditha to Syria’s coastal city of Baniyas.

    Discussions covered the contract type, implementation timeline and “other technical matters”, according to the statement released by the Iraqi government.

    During the meeting, Iraq’s Minister of Oil, Basem Mohammed Khudair Al-Abadi, emphasised the need to expedite the tendering process for the project contracts.

    He said all obstacles to progress on the projects needed to be eliminated.

    He also said weekly meetings will be held between relevant parties to reach agreements on the economic models for the pipelines and their routes.

    The Ministry of Oil said UCC is leading a consortium of companies developing the projects.

    It added that the consortium includes US-based Chevron, the investment company TI Capital and France’s TotalEnergies.

    In July, Iraq’s cabinet approved Basra Oil Company signing a ​heads of agreement and a non-disclosure agreement with the consortium to explore possible future oil pipeline projects.

    Under the terms of the agreement, the consortium will prepare technical and financial feasibility studies for strategic export pipeline projects.

    Also in July, US-based KBR was awarded a consultancy contract for the section of pipeline due to extend from Basra to Haditha.

    In April, Iraq announced the allocation of $1.5bn for the Basra-Haditha route, while the larger scheme is estimated at around $5bn.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19241649/main.jpg
    Wil Crisp