QatarEnergy LNG prepares to receive decarbonisation bids
20 March 2025

Register for MEED’s 14-day trial access
QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).
Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.
The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:
- Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
- Larsen & Toubro Energy Hydrocarbon (India)
- Samsung C&T (South Korea)
The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.
The EPC scope of work on the project covers the following:
- QG North complex:
- Installation of four new electric-driven compressors
- New power substation for power import from Kahramaa 65MW
- New ITR for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Pig launcher
- QG South complex:
- Installation of two new electric-driven compressors
- Integration with South injection system unit 85
- Solvent reformulation for South trains 1/23
- New power substation for power import from Kahramaa 35MW
- New SIH for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Chillers package
- Pig launcher
- RLIC corridors
- Common 22-inch export pipeline stretching 18 kilometres
- Power tie-in RLF3 with Kahramaa
- Electric cables
- Fiber optic cable
- Lot W15
- Six injection wells by QatarEnergy LNG subsurface
- Six injection flowlines and metring skid
- Six wellhead control panels
- Power tie-in from Barzan
- Substation
- Pig receiver
- Access road and fencing
QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.
North Field LNG expansion
Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.
The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.
QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
EPC works on the two projects are making progress.
QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.
QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.
When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.
In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.
This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.
February's special report on Qatar includes:
> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

Exclusive from Meed
-
Bahrain extends deadline for Hawar Island water station25 November 2025
-
November 2025: Data drives regional projects25 November 2025
-
Bahrain pursues reform amid strain25 November 2025
-
Chinese firms expand oil and gas presence25 November 2025
-
UK firm wins Saudi airport masterplan update deal25 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Bahrain extends deadline for Hawar Island water station25 November 2025
Bahrain’s Electricity & Water Authority (Ewa) has extended the bid submission deadline for the main contract to build a new water distribution station on Hawar Island.
The deadline, initially set for 23 November, has been moved to 7 December.
The $15m project covers the construction of two steel ground storage tanks with a capacity of one million gallons each, pumping stations, motors, pipelines and associated facilities.
The scheme forms a key part of Bahrain’s wider plans to develop Hawar Island, which currently has limited utility infrastructure and relies on water transported from the mainland.
The government is advancing tourism-led investment on the island, including eco-resorts and hospitality developments that require reliable potable water supplies.
The tender is linked to Ewa’s ongoing procurement for a new seawater reverse osmosis (SWRO) desalination plant on Hawar.
The engineering, procurement and construction contract for the SWRO facility, designed to produce one million imperial gallons a day, is currently out to tender, with bids due on 30 November.
According to Ewa, the desalination plant will connect with two related contracts.
One of these covers the construction of the new water distribution station, while the second covers offshore seawater intake and outfall systems.
The main desalination contractor will be required to ensure its design and construction align with these works so that all three components function together as one integrated system.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15149229/main.jpg -
November 2025: Data drives regional projects25 November 2025
Click here to download the PDF
Includes: Top 10 global contractors | Brent Spot Price | Construction output
MEED's 2025 EPC contractor ranking
MEED’s December 2025 report on Bahrain includes:
> COMMENT: Manama pursues reform amid strain
> GVT & ECONOMY: Bahrain’s cautious economic evolution
> BANKING: Mergers loom over Bahrain’s banking system
> OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
> POWER & WATER: Bahrain advances utility reform
> CONSTRUCTION: Bahrain construction faces major slowdown
> TRANSPORT: Air Asia aviation deal boosts connectivityTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15149339/main.gif -
Bahrain pursues reform amid strain25 November 2025
Commentary
John Bambridge
Analysis editorCautious optimism defines Bahrain’s current economic moment as the country presses ahead with a broad agenda of diversification, reform and targeted investment. Yet the more assertively Manama moves to reshape its future, the more the tension between its ambition and its fiscal constraints becomes evident as the defining feature of its policymaking.
Bahrain’s projects sector, which has now been shrinking for the past seven years, is emblematic of the country’s constricted spending. This year, contract awards have fallen to their lowest value in a decade. This signals a decisive shift to a more disciplined investment strategy aligned with fiscal realities and a more selective approach to forward-looking capital spending.
The diminished projects market is in turn a challenge for the financial sector, which now faces a receding pool of project financing and other contracting loans. This is giving further impetus to the potential consolidation of local lenders in the overbanked market, which is also beset by thinning margins, rising compliance costs and pressure to scale amid financial system modernisation. While it could create short-term pain, consolidation should boost the financial health of legacy lenders and provide stability in a sector increasingly being defined by new digital banking models and innovation.
Yet even as some sectors change, Bahrain’s government remains deeply reliant on hydrocarbons, which continues to drive exploration, including in the technically complex Khaleej Al-Bahrain basin. These activities reflect the practical need to maintain oil revenues in the medium term and, should additional recoverable reserves be discovered, a potent source of optimism.
Manana is meanwhile looking to overhaul the utilities sector by creating a dedicated regulator and new national operator. The reforms should make space for greater private participation, drawing more capital into power and water projects while improving efficiency and reducing state expenditure in an aspirationally positive step towards greater long-term sustainability.
Even as fiscal concerns narrow Manama’s policy options, it continues to secure strategic wins. A new aviation agreement with Air Asia establishes Bahrain as a regional hub for one of Asia’s largest low-cost carriers. This move opens new connectivity corridors and, alongside the renewal of direct Gulf Air routes to the US, reinforces Bahrain’s position as a gateway between regions, promising benefits for tourism, logistics and services.
Overall, Bahrain’s economic trajectory remains delicately balanced – marked by reform-driven progress yet tempered by fiscal constraint. But in threading this needle, Manama shows that cautious optimism can still be a powerful catalyst for change.

MEED’s December 2025 report on Bahrain includes:
> GVT & ECONOMY: Bahrain’s cautious economic evolution
> BANKING: Mergers loom over Bahrain’s banking system
> OIL & GAS: Bahrain remains in pursuit of hydrocarbon resources
> POWER & WATER: Bahrain advances utility reform
> CONSTRUCTION: Bahrain construction faces major slowdown
> AVIATION: Bahrain signs game-changer aviation deal with Air AsiaTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15109785/main.gif -
Chinese firms expand oil and gas presence25 November 2025

> This package also includes: Larsen & Toubro climbs EPC contractor ranking
Chinese contractors have been present in the oil and gas projects market in the Middle East and North Africa (Mena) region since the turn of this century, but largely remained on the fringes. In a hydrocarbons market that has traditionally been dominated by European and American contractors, and those from Japan and South Korea, Chinese firms have become a rising force, especially since the start of the decade.Economic competitiveness in bid battles, significant improvement in engineering and technological capabilities and commitment to execution schedules have been primary factors behind the success of Chinese contractors in the regional oil and gas projects market since 2020.
Competitive edge
Traditionally, Chinese engineering, procurement and construction (EPC) contractors have enjoyed a lower cost base than their international competitors. This comes from lower manpower costs, access to cheaper materials and equipment, and financial support from state banks.
In addition, Chinese firms have typically had a different attitude to risk than many other contractors. Instead of seeking to turn a profit on specific projects, Chinese firms have entered markets cautiously and, as their knowledge of the local market grew, built a commanding long-term position.More recently, the edge that Chinese contractors enjoy has come from the technical experience they have gained from delivering large-scale, complex projects in their domestic market. While in the past Chinese contractors were only considered capable of delivering basic construction work, they now have some of the best project references in the world.
Regional leaders
Chinese EPC contractors have strengthened their performance in the Mena oil and gas projects market, particularly since the end of the Covid-19 pandemic. Since 2023, the combined value of projects won by Chinese firms has consistently remained well over $13bn, with them winning key contracts on major projects.
The largest EPC scheme under execution by a Chinese contractor in the region is on a project to maintain and increase the oil production potential of the Bul Hanine offshore oil field development in Qatar. China Offshore Oil Engineering Company won contracts worth $4bn for the two main EPC packages of the project in the third quarter of 2025.Also this year, Abu Dhabi’s Taziz awarded the main EPC contract to build a complex of specialty chemicals plants in the Taziz Industrial Chemicals Zone at Ruwais Industrial City to China National Chemical Engineering & Construction Corporation Seven (CC7).
The EPC contract is valued at $1.99bn, with work expected to be completed by Q4 2028. The chemicals cluster, known as Project Salt, will produce 1.9 million tonnes a year of marketable polyvinyl chloride (PVC), ethylene dichloride (EDC), vinyl chloride monomer (VCM) and caustic soda.
Chinese contractors have also enjoyed success in Saudi Arabia, with Aramco having awarded several key EPC contracts to Chinese firms since 2023. China Petroleum Engineering & Construction Company, Sepco and Sinopec Petroleum Services are executing EPC works on four out of the 17 packages of the third expansion phase of Aramco’s Master Gas System project.
Sinopec Group has played a significant role in Aramco’s Jafurah unconventional gas development in Saudi Arabia. In a consortium with Spanish contractor Tecnicas Reunidas, in 2024 Sinopec won packages one and two of the Riyas natural gas liquids scheme, part of the second Jafurah unconventional gas expansion phase. The combined value of the two EPC contracts was $3.2bn.
Just weeks after securing these EPC contracts, the consortium also won the contract to deliver the entire scope of work on the scheme’s third expansion phase, valued at $2.24bn.
In Iraq, China Petroleum Engineering (CPE) won a major contract in August to carry out EPC works on a package covering a major seawater transmission pipeline to be built in Basra as part of the larger Common Seawater Supply Project, which is one of four main components of the estimated $10bn Gas Growth Integrated Project masterplan.
Work on the $2.52bn contract will be carried out by CPE’s engineering arm, China Petroleum Pipeline Engineering.
China has built up extensive resources, from skilled personnel to technical know-how. As the domestic market shows signs of slowing, these resources are being deployed internationally, supporting the growing presence of Chinese contractors in the Mena region.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15149182/main.gif -
Ineco appointed for Spain-Morocco tunnel study25 November 2025
Spanish engineering firm Ineco has been commissioned to conduct an exploratory tunnel study to validate the feasibility of the railway connection linking Spain and Morocco.
According to reports in Spanish media, the $1m contract will establish a detailed technical roadmap for the project.
Ineco’s scope of work includes the preliminary design of the exploratory tunnel, revisions to previous studies, and a comprehensive update of the route, geology, geotechnical conditions, security systems, terminals and associated installations.
Ineco will validate the critical geological conditions of the Strait, particularly in the areas where the project’s greatest risks are located.
The study is expected to be completed by August next year.
The latest development comes after German company Herrenknecht completed its study in October. Herrenknecht said it found the project feasible to undertake due to the availability of the technology needed to execute it.
The media reports added that clients will further study the project and make a final decision in 2027 regarding tendering.
Recent developments
MEED reported in August that Ineco had secured an estimated €350,000 ($409,000) contract to carry out a financial feasibility study for the proposed infrastructure.
UK-based Vodafone also won a contract to provide advanced telecommunications support to teams working on the project.
These developments followed the appointment of Herrenknecht in January for a €296,400 ($307,483) contract to conduct a drilling feasibility study.
The Spanish government revived the Morocco-Spain undersea rail link in June last year, after allocating about $2.5m for a renewed design study.
Project background
The project, originally launched in 2003, was put on hold following the 2008 financial crisis. It has undergone several rounds of feasibility studies, but remains in the planning phase after nearly two decades of funding-related delays.
The proposed design includes a double-track railway and a service tunnel extending 38.5 kilometres (km) between Tarifa in Spain and Tangier in Morocco. Of this, 28km will run beneath the Mediterranean Sea at a maximum depth of 475 metres.
Each single-track tunnel will have an inner diameter of 7.9 metres, while the service gallery will be 6 metres in diameter.
The project is being jointly developed by Morocco’s National Society for Strait of Gibraltar Studies and Spain’s Sociedad Espanola de Estudios para la Comunicacion Fija a Traves del Estrecho de Gibraltar.
In 2006, Swiss engineering firm Lombardi Engineering was selected to design the tunnel. Preliminary studies were completed two years later.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15148660/main.jpg