QatarEnergy LNG prepares to receive decarbonisation bids

20 March 2025

Register for MEED’s 14-day trial access 

QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

  • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung C&T (South Korea)

The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

The EPC scope of work on the project covers the following:

  • QG North complex:
    • Installation of four new electric-driven compressors
    • New power substation for power import from Kahramaa 65MW
    • New ITR for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Pig launcher
       
  • QG South complex:
    • Installation of two new electric-driven compressors
    • Integration with South injection system unit 85
    • Solvent reformulation for South trains 1/23
    • New power substation for power import from Kahramaa 35MW
    • New SIH for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Chillers package
    • Pig launcher
       
  • RLIC corridors
    • Common 22-inch export pipeline stretching 18 kilometres
    • Power tie-in RLF3 with Kahramaa
    • Electric cables
    • Fiber optic cable
       
  • Lot W15
    • Six injection wells by QatarEnergy LNG subsurface
    • Six injection flowlines and metring skid
    • Six wellhead control panels
    • Power tie-in from Barzan
    • Substation
    • Pig receiver
    • Access road and fencing

QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

North Field LNG expansion

Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

EPC works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.


February's special report on Qatar includes

> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
Indrajit Sen
Related Articles
  • Qatar seeks to establish new industrial area in Mesaieed

    16 July 2026

    Qatar’s Ministry of Commerce & Industry and state enterprise QatarEnergy have signed an agreement to cooperate on evaluating and allocating hydrocarbon-derived resources to support the establishment of a new medium industries area in Mesaieed Industrial City.

    Under the terms of reference signed between the parties, QatarEnergy will implement a governance mechanism for the allocation of hydrocarbon-derived feedstock to qualifying industrial investment opportunities for the proposed new medium industries area in Mesaieed Industrial City.

    “The agreed terms of reference stipulate the evaluation and allocation of hydrocarbon-derived resources, natural gas, power and related natural resources to downstream derivative industrial investment opportunities,” QatarEnergy said in a statement.

    “It will also ensure the optimal use of national resources and enhance the added value of the industrial sector by establishing a joint governance framework to evaluate and allocate resources required by qualified industrial investment opportunities,” it added.

    QatarEnergy currently operates crude oil refining facilities, including natural gas liquids units, as well as petrochemical production complexes and other units in the hydrocarbon value chain, in Mesaieed Industrial City, situated around 45 kilometres south of Doha.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17688383/main.jpg
    Indrajit Sen
  • Bahri signs deal for two offshore vessels with Dubai shipyard

    16 July 2026

    Bahri Logistics, a division of Saudi Arabia’s national shipping company Bahri, has placed an order for the construction of two advanced offshore support vessels with Dubai-based Grandweld Shipyard.

    Grandweld will custom-build the two vessels to meet Bahri’s operational requirements for offshore activities at Ras Tanura port in Saudi Arabia, one of the world’s busiest oil and gas bunkering and export hubs.

    The vessels will be built at Grandweld’s shipyard in Dubai Maritime City and are expected to be delivered in August, following a 12-month building period.

    The vessels will feature the latest navigation and safety technologies. They are designed to perform multiple offshore support functions, including vessel clearance, crew changes and emergency response, while adhering to international maritime standards.

    The newbuild agreement with Grandweld aligns with Bahri’s broader strategy “to modernise its fleet, enhance technical capabilities, and adopt more energy-efficient and environmentally responsible designs”.

    “Through continued investments in technology, infrastructure and fleet diversification, Bahri Logistics aims to deliver smarter, more sustainable logistics solutions that contribute to the Saudi Green Initiative and the kingdom’s long-term economic diversification goals,” the Saudi Stock Exchange-listed (Tadawul) company said in a statement.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17687877/main.jpg
    Indrajit Sen
  • Egypt intensifies efforts to create petroleum stockpile

    16 July 2026

    Egypt is intensifying its efforts to secure and maintain a sufficient strategic stockpile of petroleum products, according to a statement from the country’s cabinet and its Ministry of Petroleum & Mineral Resources.

    The Egyptian government is closely monitoring regional developments and their potential repercussions on the energy sector, according to the statement.

    Egyptian Prime Minister Mostafa Madbouly said that the government is implementing flexible plans and looking at alternative scenarios so that it can respond quickly to emergencies while ensuring the uninterrupted supply of fuel to citizens and key industrial sectors.

    Egypt is intensifying its efforts to build up strategic stockpiles amid heightened uncertainty about future global oil and gas supplies.

    Since the US and Israel attacked Iran on 28 February, there has been significant disruption to shipping through the Strait of Hormuz, which is a key transit route for oil and gas exports from the Middle East.

    On top of this, the regional war has involved multiple direct attacks on refineries in the GCC, increasing uncertainty about the future availability of refined products.

    Aside from Motafa Madbouly, the meeting was also attended by Hassan Abdullah, who is governor of the Central Bank, Minister of Finance Ahmed Koguk and Minister of Petroleum and Minerals Karim Badawi.

    During the meeting, Badawi gave a presentation on the available quantities of different petroleum products and explained the details of the procedures currently being implemented to increase the strategic stock of petroleum products.

    A review of the coordination framework and joint work between the Ministry of Finance and the Central Bank also took place during the meeting.

    This was in order to ensure the management of financial tools needed to strengthen the country’s strategic inventory, according to the statement.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17685719/main.jpg
    Wil Crisp
  • Tunisia orders $86m of trainsets from Chinese supplier

    16 July 2026

    Tunisian public transport operator Transtu has finalised an $86m agreement with China’s CRRC Nanjing Puzhen.

    CRRC will supply 18 new electric trainsets for the capital’s northern suburban rail network, which links Tunis to La Goulette and La Marsa.

    Each new trainset will be air-conditioned and capable of carrying up to 400 passengers, including 90 seated riders, with a top speed of 100 km/h. Once operational, the trains are expected to run at six-minute intervals during rush hour and every 12 minutes during off-peak hours.

    The deal forms part of a broader fleet renewal effort by Transtu, which has struggled in recent years with operational setbacks that have taken a toll on the quality of public transport across Greater Tunis.

    The acquisition is designed to boost capacity on the heavily used line as ridership continues to grow, while also enhancing safety standards and overall service quality.

    Funding for the project comes jointly from the European Bank for Reconstruction & Development and the European Investment Bank.

    Beyond the trainsets, the contract includes five years of maintenance coverage, a supply of spare parts and maintenance equipment, and an underfloor wheel lathe aimed at improving long-term fleet reliability.

    This latest investment fits into Tunisia’s larger railway modernisation strategy, under which the government plans to invest $12bn by 2040 to expand and upgrade the country’s rail infrastructure.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17683957/main.jpg
    Yasir Iqbal
  • PIF developer tenders 365-metre Mecca residential tower

    16 July 2026

     

    Rua Al-Haram Al-Makki has tendered the main construction package for the Ajyad residential tower, a 365-metre high-rise development in Mecca’s central area, close to the grand mosque.

    The bid submission deadline is 30 September. 

    Rua Al-Haram Al-Makki Company was established in October 2017 and is a wholly owned subsidiary of Saudi Arabia’s Public Investment Fund.

    The project team includes US-based Marriott International as residential operator, Hanmi Global Saudi as project management consultant, Saudi Diyar Consultants as construction supervision consultant, and PLP Architecture as lead design consultant and construction-stage design guardian.

    The tower rises 84 floors with four basement levels. It comprises a total of 212 units, including 82 three-bedroom apartments, 85 four-bedroom units, 29 penthouses and 16 duplex villas.

    The scheme has a gross floor area of 209,231 square metres (sq m) and a built-up area of 242,976 sq m.

    The site is currently being cleared by a demolition contractor, with the existing mat foundation and retaining walls to be handed over to the main contractor, who will build the new superstructure on the retained raft.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17683664/main.jpg
    Yasir Iqbal