QatarEnergy LNG prepares to receive decarbonisation bids

20 March 2025

Register for MEED’s 14-day trial access 

QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

  • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung C&T (South Korea)

The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

The EPC scope of work on the project covers the following:

  • QG North complex:
    • Installation of four new electric-driven compressors
    • New power substation for power import from Kahramaa 65MW
    • New ITR for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Pig launcher
       
  • QG South complex:
    • Installation of two new electric-driven compressors
    • Integration with South injection system unit 85
    • Solvent reformulation for South trains 1/23
    • New power substation for power import from Kahramaa 35MW
    • New SIH for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Chillers package
    • Pig launcher
       
  • RLIC corridors
    • Common 22-inch export pipeline stretching 18 kilometres
    • Power tie-in RLF3 with Kahramaa
    • Electric cables
    • Fiber optic cable
       
  • Lot W15
    • Six injection wells by QatarEnergy LNG subsurface
    • Six injection flowlines and metring skid
    • Six wellhead control panels
    • Power tie-in from Barzan
    • Substation
    • Pig receiver
    • Access road and fencing

QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

North Field LNG expansion

Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

EPC works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.


February's special report on Qatar includes: 

> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
Indrajit Sen
Related Articles
  • Syria seeks interest for $1.16bn Euphrates dam

    7 October 2026

    Register for MEED’s 14-day trial access 

    Syria’s Ministry of Energy has invited expressions of interest (EoIs) for the development of the Halabiyeh-Zalabiyeh dam project on the Euphrates River.

    The project has an indicative total cost of $1.16bn, according to the ministry’s EoI document. This includes $433.7m for the dam and hydropower plant and $729.6m for the pumped-storage power plant (PSP). 

    The scheme includes an 81MW hydroelectric power plant and a pumped-storage facility with a capacity of up to 1,200MW. The project will also include the construction of the dam and associated water-storage infrastructure. 

    The ministry seeks interest from qualified local and international companies, investors and other entities. Interested parties can participate in studies, design, financing, construction, and operation and maintenance of the project. 

    The ministry is considering several potential development structures, including build-own-operate-transfer, build-operate-transfer and public-private partnership models, as well as an engineering, procurement and construction (EPC) structure. It has said it is also open to proposals covering consultancy and financing services.

    The EoI covers several stages, including pre-feasibility and feasibility studies, financing and bankability studies, detailed and executive design, EPC execution, and operation and maintenance.

    The technical specifications envisage a 23-metre-high dam with a reservoir storage capacity of about 219 million cubic metres.

    The hydropower plant will have three generating units, while the 1,200MW PSP will have 3.5 hours of storage capacity and four reversible units.

    The deadline for submitting EoIs is 10 November, with enquiries accepted until 26 October.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20336025/main.jpg
    Mark Dowdall
  • Arada launches UAE construction arm with Roberts

    7 October 2026

    Register for MEED’s 14-day trial access 

    UAE developer Arada has integrated Australian contractor Roberts into the UAE market as part of its wider business strategy.

    Arada acquired Roberts in 2025 after entering the Australian market. The tier-one contractor delivers projects in the healthcare, education, commercial, residential, hospitality, industrial, life sciences and defence sectors.

    At the time of the acquisition, Arada said it planned to invest about $20m in Roberts. The investment is intended to give the developer greater control over the delivery of its Australian projects and support Roberts’ expansion into markets including the UAE.

    Arada has said it could invest up to $100m in Roberts’ expansion into new sectors and markets. The company is targeting $1bn in annual revenue from Roberts by 2028.

    Roberts has established a UAE office, with a head office team already in place. Arada said the contractor’s capabilities will support the delivery of its high-rise residential and social infrastructure projects.

    The contractor’s first UAE project will be phase two of Arada Central Business District, a commercial development within Aljada in Sharjah. Arada is developing the AED35bn ($9.5bn) mixed-use project.

    Roberts is also providing preconstruction services for several Arada projects in Dubai and Sharjah, ahead of starting site work.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20334926/main.jpg
    Yasir Iqbal
  • Expo Riyadh sets October deadline for Saudi Arabia pavilion

    7 October 2026

     

    Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, has set a deadline of 25 October for bids for a contract to build the Saudi Arabia pavilion.

    The tender was issued on 19 May, with an initial bid submission deadline of 26 August.

    The pavilion is a major asset located within the KSA District on the eastern side of the Expo 2030 Riyadh masterplan, in the Loop of Nations district.

    Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.

    Last month, MEED reported that ERC had received contractor interest on 14 September for a contract to design and build a convention centre in the site’s Collaboration District.

    ERC also tendered a contract to deliver the Souq areas within the Expo site, as MEED exclusively reported on 8 September.

    These areas are divided into five precincts, with a total development area of about 300,000 square metres.

    Also in September, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to construct a new metro station serving the Expo 2030 site.

    In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle (EV) charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.

    That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, as well as EV charging stations.

    The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated north of the Saudi capital, the site will be near the future King Salman International airport and will provide direct access to Riyadh landmarks.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20334856/main.jpg
    Yasir Iqbal
  • Kuwait on track to hit oil production target

    7 October 2026

    Kuwait is on track to meet its target of having 4 million barrels a day (b/d) of oil production capacity by 2035, according to Kuwait Petroleum Corporation (KPC) chief executive Shaikh Nawaf Al-Sabah.

    Al-Sabah also said Kuwait is on course to increase non-associated gas production to 2 billion cubic feet a day by 2040.

    His comments come amid an ongoing crisis in Kuwait’s oil and gas sector linked to the regional conflict that began when the US and Israel attacked Iran on 28 February.

    The subsequent war has significantly disrupted shipping through the Strait of Hormuz, which is a crucial export route for Kuwaiti crude oil.

    Kuwait is currently producing around 2 million b/d of oil, down from 2.6 million b/d before the US and Israel attack.

    Speaking at a conference in London, Al-Sabah said: “We have the capacity to go back up to our current maximum sustainable capacity of 3 million b/d, if we have the export routes available, and this comes down to the ability to move oil through the Strait.”

    KPC is investing $9bn-$10bn a year in capital expenditure to meet its oil and gas production goals, according to Al-Sabah.

    He said: “We are doing this because we recognise that it is our hydrocarbons that will be most in demand a decade from now, and two decades from now – in fact, for the rest of our lifetimes.”

    Project Seef

    KPC is pushing ahead with the Al-Seef project, which focuses on developing three large offshore oil discoveries, Al-Sabah said.

    The offshore fields are known as Nokhatha, Julaia and Jazza. The development was first announced in February this year, about two weeks before the US and Israel attack on Iran.

    Al-Sabah said KPC is continuing with the project and believes the three fields collectively hold more than 3 billion barrels of recoverable oil.

    He said: “We are asking international oil companies to partner with us to develop those resources under an operating services contract.

    “So, we’re moving ahead according to the exact same schedule that we had put together even before the war began.”

    Al-Sabah did not say which international oil companies KPC has approached to help develop the three offshore fields.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20315147/main.jpg
    Wil Crisp
  • Roshn plans new flagship development in Riyadh

    7 October 2026

     

    Saudi developer Roshn Group plans to develop its next flagship scheme in north Riyadh, spanning an area of 13.7 square kilometres. 

    Roshn is looking to appoint lead design consultants to deliver detailed design, tender documentation and construction documents across the scheme, known as Plot 1.

    The scope covers all infrastructure, utilities, public realm works and site adaptation of Roshn’s residential prototypes, split across two work packages.

    Part 1 covers phases A, B and E, which collectively span about 7.8 million square metres (sq m) and will comprise 17,000 units.

    Part 2 includes phases C and D, which will span about 4.7 million sq m and comprise more than 15,000 units.

    The development is bordered by Expo 2030, King Abdulaziz Park, the Sports Innovation Lab Zone and the National Housing Company-developed Khozam district.

    It will be a residential-led mixed-use development, also featuring retail, offices, hospitality, education and civic facilities.

    Connectivity is a core plank of the masterplan, with two metro stations planned: one at the existing Line 4/proposed Line 7 interchange and another dedicated Line 7 stop. The scheme would also be served by the future Qiddiya high-speed rail and a possible King Salman Road diversion.

    Plot 1 builds on Roshn’s existing footprint in the capital, notably the multi-phase Sedra community, as the developer expands beyond single-family housing into mixed-use districts under its Roshn 3.0 strategy.

    Last month, Roshn Group announced that it had signed a preliminary agreement with Talaat Moustafa Group (TMG) Saudi, the local subsidiary of Egyptian developer Talaat Moustafa Group, to establish a joint venture to explore and develop a mixed-use project in Riyadh.

    Under the agreement, TMG will hold a 51% stake in the joint company, while Roshn Group will hold 49%.

    The agreement sets out a framework for the two groups to assess a potential partnership for the project’s phased development, which is planned as a residential-led, mixed-use community featuring retail, commercial, hospitality, leisure, healthcare and education facilities, alongside parks and public spaces.

    Roshn Group and TMG Saudi plan to conduct detailed master planning and develop the project’s business case.

    Preliminary studies indicate the development could include more than 55,000 residential units across all phases.

    Roshn Group did not disclose the exact project location in its announcement.

    As a Public Investment Fund-owned developer, Roshn remains a key vehicle for delivering Vision 2030’s housing programme, which targets 70% Saudi home ownership, alongside the kingdom’s wider quality-of-life and economic diversification agendas.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19786131/main.jpg
    Yasir Iqbal