QatarEnergy LNG prepares to receive decarbonisation bids
20 March 2025

Register for MEED’s 14-day trial access
QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).
Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.
The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:
- Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
- Larsen & Toubro Energy Hydrocarbon (India)
- Samsung C&T (South Korea)
The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.
The EPC scope of work on the project covers the following:
- QG North complex:
- Installation of four new electric-driven compressors
- New power substation for power import from Kahramaa 65MW
- New ITR for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Pig launcher
- QG South complex:
- Installation of two new electric-driven compressors
- Integration with South injection system unit 85
- Solvent reformulation for South trains 1/23
- New power substation for power import from Kahramaa 35MW
- New SIH for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Chillers package
- Pig launcher
- RLIC corridors
- Common 22-inch export pipeline stretching 18 kilometres
- Power tie-in RLF3 with Kahramaa
- Electric cables
- Fiber optic cable
- Lot W15
- Six injection wells by QatarEnergy LNG subsurface
- Six injection flowlines and metring skid
- Six wellhead control panels
- Power tie-in from Barzan
- Substation
- Pig receiver
- Access road and fencing
QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.
North Field LNG expansion
Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.
The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.
QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
EPC works on the two projects are making progress.
QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.
QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.
When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.
In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.
This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.
February's special report on Qatar includes:
> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

Exclusive from Meed
-
Qatar invites bids for major power grid expansion22 April 2026
-
-
Riyadh awards Expo 2030 infrastructure work22 April 2026
-
Trump confirms UAE currency swap talks22 April 2026
-
Egyptian and Chinese firms sign green hydrogen deal22 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms submit Qiddiya high-speed rail EPC prequalifications22 April 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s Royal Commission for Riyadh City, in collaboration with Qiddiya Investment Company (QIC) and the National Centre for Privatisation & PPP, received bids on 16 April from firms for the engineering, procurement, construction and financing (EPCF) package of the Qiddiya high-speed rail project in Riyadh.
Firms interested in bidding for the project on a public-private partnership (PPP) basis have been given until 30 April to submit their prequalification statements, as MEED reported earlier this month.
The prequalification notice was issued on 19 January, and a project briefing session was held on 23 February at Qiddiya Entertainment City.
The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at speeds of up to 250 kilometres an hour, reaching Qiddiya in 30 minutes.
The line is expected to be developed in two phases. The first phase will connect Qiddiya with KAFD and King Khalid International airport.
The second phase will start from a development known as the North Pole and travel to the New Murabba development, King Salman Park, central Riyadh and Industrial City in the south of the city.
In November last year, MEED reported that more than 145 local and international companies had expressed interest in developing the project, including 68 contracting companies, 23 design and project management consultants, 16 investment firms, 12 rail operators, 10 rolling stock providers and 16 other services firms.
In November 2023, MEED reported that French consultant Egis had been appointed as the technical adviser for the project. UK-based consultancy Ernst & Young is acting as the transaction adviser, and Ashurst is the legal adviser.
Qiddiya is one of Saudi Arabia’s five official gigaprojects and covers a total area of 376 square kilometres (sq km), with 223 sq km of developed land.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16514433/main.gif -
Qatar invites bids for major power grid expansion22 April 2026
Qatar General Electricity & Water Corporation (Kahramaa) has invited bids for a major power transmission expansion project covering substations and extra-high-voltage cables.
The bid submission deadline is 14 May.
The engineering, procurement and construction (EPC) contract covers new substations at multiple voltage levels. It also includes the supply and installation of 400kV extra-high-voltage power cables.
The project is divided into the following packages:
- Substation packages S1 and S2 cover new 132/11kV substations
- Package S3 covers new 66/11kV substations
- Package S4 includes a new 400/220/132kV substation, along with upgrades and modifications to existing 400kV and 220kV substations
- Package S5 covers new 132/11kV substations and upgrades to existing 132kV and 66kV substations
- Cable packages C1 and C2 cover 400kV cables
The bid bond is set at QR7m ($1.9m) for the full tender, while bids for individual packages require a QR1m ($0.27m) bond per package.
Kahramaa stated that foreign companies not registered in Qatar may participate, subject to meeting specified conditions, including registration and certification requirements.
It added that it may increase or decrease the scope during the contract period in line with Qatar’s Tenders & Auctions Law.
Kahramaa procurement plan
Kahramaa’s 2026 procurement plan includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
Electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16513966/main.jpg -
Riyadh awards Expo 2030 infrastructure work22 April 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, has awarded two contracts for the next phase of infrastructure works at the site.
The contracts were awarded to local firm Al-Yamama Company. Their scope covers the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
ERC did not disclose the contract values or project timelines.
The awards follow ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covers about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communication systems, and electric vehicle charging stations.
The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – is split into three packages:
- Lot 1 covers the main utilities corridor
- Lot 2 includes the northern cluster of the nature corridor
- Lot 3 comprises the southern cluster of the nature corridor
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.
The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC, a wholly owned subsidiary, in June last year to build and operate facilities for Expo 2030.
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16512261/main.jpg -
Trump confirms UAE currency swap talks22 April 2026
Register for MEED’s 14-day trial access
US President Donald Trump has confirmed that Washington is considering a currency swap agreement with the UAE.
During an interview with US broadcaster CNBC, Trump acknowledged that the arrangement is being considered. “It is [under consideration], but it’s been a good country. It’s been a good ally of ours,” Trump stated, noting that the request stems from a liquidity challenge rather than a solvency issue.
Addressing the scale of the conflict’s impact on the federation, he added, “UAE got hit with 1,400 missiles. Now, fortunately, they had the Patriots, and they had a great defence … but they did get hit hard. They were hit the hardest of the group, actually.”
The president also emphasised the strength of the bilateral economic relationship and his personal regard for the country’s leadership. “They’re really led by incredible people,” Trump told CNBC. “A year ago, I went there and I got them to invest $1tn in the United States. So, yeah, if I could help them, I would.”
An early report by the Wall Street Journal said that high-level talks were initiated by UAE Central Bank governor Khaled Mohamed Balama, who recently met with Treasury secretary Scott Bessent and Federal Reserve officials in Washington.
The UAE’s move is viewed as a precautionary effort to protect the dirham’s peg to the dollar and maintain its position as a global financial hub. The conflict has already inflicted significant damage on Emirati oil-and-gas infrastructure and disrupted tanker traffic through the Strait of Hormuz, which has historically been the primary source of the nation’s dollar revenues.
While swap lines are traditionally managed by the Federal Reserve and reserved for major economies with deep ties to US markets, the Trump administration may look to the Treasury Department for a solution. Trump referenced a recent $20bn swap for Argentina facilitated by Secretary Bessent through the Exchange Stabilisation Fund as a potential model for the UAE.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16512000/main.jpg -
Egyptian and Chinese firms sign green hydrogen deal22 April 2026
A group of Egyptian companies and China’s UEG have signed a preliminary agreement to explore developing a Mediterranean green hydrogen hub in the port city of Alexandria.
The memorandum of understanding was signed by:
- Abu Qir Fertilisers & Chemicals Company (Egypt)
- AlexFert (Egypt)
- Orascom Construction (Egypt)
- UEG Green Hydrogen Development Holding (China)
In a joint statement, the companies said: “The collaboration marks a significant step toward advancing Egypt’s position as a regional leader in green hydrogen and sustainable energy solutions.
“The proposed project aims to develop a large-scale green hydrogen production facility powered by renewable energy, with integration into existing ammonia production infrastructure.”
Under the terms of the deal, UEG and Orascom Construction will lead feasibility studies for 500MW of renewable energy generation and 480 tonnes a day (t/d) of green hydrogen production.
Abu Qir and AlexFert will evaluate the integration of green hydrogen into ammonia production processes and support access to local resources and infrastructure.
The renewable energy will be a mix of wind and solar, according to the statement.
Hany Dahy, the chairman of Abu Qir Fertilisers & Chemicals Company, said: “This partnership reflects Abu Qir’s commitment to leading the transition toward low-carbon ammonia production, leveraging our existing assets while integrating green hydrogen solutions.”
Joe Williams, the chief executive of the Green Hydrogen Organisation, said: “The announcement of this project comes at a crucial time, as geopolitical tensions in the Middle East highlight the importance of diversifying energy and fuel supply chains.
“Developing integrated green ammonia and fertiliser production in Alexandria supports local industrial value, and strengthens long-term energy and food security.
“As green ammonia production scales in Egypt, it can also be used as a clean shipping fuel given Egypt’s strategic maritime location.”
The preliminary agreement establishes a framework for cooperation while the parties conduct technical, commercial and regulatory assessments.
Subject to the outcomes, the partners intend to negotiate definitive agreements for the project’s development, according to their statement.
Abu Qir Fertilisers established North Abu Qir for Agricultural Nutrients in May 2023 to develop a major Egyptian fertiliser project designed to produce 2,400 t/d of ammonium nitrate.
Located next to Abu Qir Fertilisers in Alexandria, on a site formerly occupied by the Rakta paper manufacturing facility, the project is a joint venture with a capital investment of £E10bn ($190m), of which Abu Qir Fertilisers holds a 45% stake.
The state-owned companies Egyptian General Petroleum Corporation and Egyptian Petrochemicals Holding Company hold stakes of 45% and 10%, respectively.
The project focuses on the production of ammonia and nitric acid.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16498782/main.jpg

