QatarEnergy LNG prepares to receive decarbonisation bids
20 March 2025

Register for MEED’s 14-day trial access
QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).
Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.
The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:
- Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
- Larsen & Toubro Energy Hydrocarbon (India)
- Samsung C&T (South Korea)
The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.
The EPC scope of work on the project covers the following:
- QG North complex:
- Installation of four new electric-driven compressors
- New power substation for power import from Kahramaa 65MW
- New ITR for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Pig launcher
- QG South complex:
- Installation of two new electric-driven compressors
- Integration with South injection system unit 85
- Solvent reformulation for South trains 1/23
- New power substation for power import from Kahramaa 35MW
- New SIH for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Chillers package
- Pig launcher
- RLIC corridors
- Common 22-inch export pipeline stretching 18 kilometres
- Power tie-in RLF3 with Kahramaa
- Electric cables
- Fiber optic cable
- Lot W15
- Six injection wells by QatarEnergy LNG subsurface
- Six injection flowlines and metring skid
- Six wellhead control panels
- Power tie-in from Barzan
- Substation
- Pig receiver
- Access road and fencing
QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.
North Field LNG expansion
Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.
The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.
QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
EPC works on the two projects are making progress.
QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.
QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.
When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.
In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.
This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.
February's special report on Qatar includes:
> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

Exclusive from Meed
-
-
Doosan confirms Saudi Jafurah 2 cogen contract2 June 2026
-
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait receives bids for Al-Khairan phase one IWPP2 June 2026

Two developer consortiums have submitted bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, according to a source.
Bids were received by the Kuwait Authority for Partnership Projects (Kapp) on 1 June.
The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant.
The bidders include:
- Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia)
- Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
The Al-Khairan IWPP is being procured by Kapp in partnership with the Ministry of Electricity, Water & Renewable Energy (MEWRE).
The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate in the tender.
Ernst & Young, BNP Paribas, AtkinsRealis and Addleshaw Goddard are financial advisers on the project. Chadbourne & Parke is acting as legal adviser.
The winning bidder will sign a set of public-private partnership agreements covering financing, design, construction, operation and transfer of the project. The energy conversion and water-purchase agreement is expected to cover a 25-year supply period.
Future phases
The Al-Khairan IWPP project is expected to run on low-sulphur fuel oil as the primary fuel and to accommodate crude oil, gas oil and natural gas as backup fuels. Future phases will further expand capacity.
It is understood that the estimated $750m second phase of the Al-Khairan IWPP project will add a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant.
The project, first mooted over a decade ago, remains in the early development stages, with no plans currently to advance to procurement in 2026, a source said.
According to the source, the immediate focus is on advancing plans for the 3,600MW Nuwaiseeb power and water desalination IWPP project.
The Nuwaiseeb IWPP plant will have a desalination capacity of 75 million imperial gallons a day.
Kapp plans to release a transaction advisory tender for the project by the end of the year.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17072685/main.jpg -
Doosan confirms Saudi Jafurah 2 cogen contract2 June 2026
South Korea’s Doosan Enerbility has confirmed it has signed an engineering, procurement and construction (EPC) contract worth about $556m for the second phase of the Jafurah combined heat and power (CHP) plant in Saudi Arabia.
The project is being developed by Korea Electric Power Corporation (Kepco) in partnership with Saudi Aramco.
Doosan said the contract covers design, equipment supply, installation, construction and commissioning of the facility.
The Jafurah CHP phase 2 project will be built near the Jafurah gas field, about 400 kilometres east of Riyadh. Once operational, it will generate 330MW of electricity and produce 465 tonnes of steam an hour for the nearby gas field.
According to the firm, the project’s main steam turbine will be supplied by Doosan Skoda Power, a subsidiary of Doosan Enerbility.
WSP is acting as the project management consultant for the project, which is scheduled for completion in 2029.
The Jafurah gas development is part of Aramco’s $3.2bn unconventional resources programme, which aims to develop shale gas in three areas. Jafurah lies southeast of Ghawar, the world’s largest conventional oil field.
The programme is part of Riyadh’s plans under Vision 20230 to ensure the kingdom remains self-sufficient in gas supply amid rising demand from the residential and industrial power sectors.
Jafurah phase one
In February 2025, MEED exclusively reported that talks were under way to expand the capacity of the $500m Jafurah cogeneration independent steam and power plant (ISPP).
Construction works were completed on the facility last November.
At the time of its procurement, the plant’s first phase was to have a power capacity of 270-320MW, and a low-pressure (LP) steam demand of 77-166 thousand pounds an hour (klb/hr) and high-pressure (HP) steam demand of 29-126 klb/hour by 2023.
The LP and HP steam demand will increase to 283-373 klb/hr and 66-321 klb/hr by 2027, respectively.
The oil giant issued the letter of award to Kepco for the contract to develop the Jafurah ISPP scheme in July 2022.
Kepco subsequently awarded South Korea’s Doosan Heavy Industries & Construction the project’s EPC contract.
US/India-based Synergy Consulting provided financial advisory services to Kepco on its bid.
Sumitomo Mitsui Banking Corporation (SMBC) served as the client’s financial adviser for the project. Germany’s Fichtner Consulting Engineers is technical consultant, while the UK’s Wood Group is project management consultant.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17072199/main.jpg -
Al-Mabanee submits lowest bids for Kuwait infrastructure2 June 2026
Kuwait’s Public Authority for Housing Welfare (PAHW) has opened commercial bids for two major infrastructure and public buildings packages at South Al-Mutlaa Residential City.
Local firm Al-Mabanee United Company has emerged as the lowest bidder for both contracts, submitting combined offers worth KD44m. Both packages entail the construction, completion and maintenance of services, infrastructure works and public buildings for different district centres within the city.
The first contract covers the infrastructure and public buildings for the N3 District Centre. PAHW received proposals from eight bidders, with Al-Mabanee United Company submitting the lowest price at KD20.9m. The second-lowest offer was submitted by The Contractor General Trading & Contracting Company at KD22.4m, followed by Golden Engineering Group for General Trading & Contracting at KD22.7m, though Golden Engineering Group was flagged for not providing a bid bond.
Al-Khonaini General Trading & Contracting Company, operating as Inshat Al-Khonaini, ranked fourth with a bid of KD22.7m, followed closely by Kuwait Industrial Centre Company at KD22.8m. Combined Group Contracting Company submitted a bid of KD23.8m, Al-Dar Engineering & Construction Company bid KD25.7m, and China’s Sichuan Road & Bridge Group Corporation submitted the highest active proposal at KD29m.
The second contract is for identical infrastructure and public building works at the N1 District Centre. Al-Mabanee United Company submitted the lowest bid of KD22.8m. Its closest competitor was The Contractor General Trading & Contracting Company, which submitted an offer of KD23.9m.
Al-Khonaini General Trading & Contracting Company came in third with a bid of KD24.2m, followed by Kuwait Industrial Centre Company at KD24.4m and Golden Engineering Group for General Trading & Contracting at KD24.4m. Combined Group Contracting Company placed a bid of KD26m, Al-Dar Engineering & Construction Company bid KD26.5m, and United Construction Company, known as Al-Inshat Al-Muttahida, submitted an offer of KD 30.9m. Al-Ghanim International General Trading & Contracting filed the highest bid at KD344m and was also noted for lacking a bid bond.
South Mutlaa Residential City is a large-scale planned development designed to accommodate around 400,000 residents in a modern, fully serviced urban environment. Once completed, it will offer contemporary housing alongside extensive logistical services and a wide range of public and commercial areas, including hospitals, schools and other social services.
The project also includes major infrastructure works such as approximately 150 kilometres of roads and related structures, lighting and other public works, as well as integrated systems for water distribution, rainwater collection and sewage. In addition, it will provide the civil infrastructure needed for electricity distribution, telecommunications networks and traffic control to support a well-connected, functional city.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17071938/main.gif -
Local developer secures finance for three Riyadh projects2 June 2026
Qimam Noshoz for Real Estate Development Company, a subsidiary of Saudi Arabia’s Banan Real Estate Company, has signed a sharia-compliant credit facility agreement worth SR84m ($22.4m) with Riyad Bank to fund three commercial, hospitality and sports developments in the kingdom.
The financing agreement is split into two distinct tranches to align with the projects’ development timelines. The first tranche consists of SR49m with a maturity duration of seven years, while the remaining SR35m has been secured for an eight-year term.
Qimam Noshoz will utilise the capital to fund construction works for the Al-Rahmaniyah Gem and Al-Wadi District Gem projects. Both of these projects are already leased to the fitness operator Armah Sports Company. The other project is an independent hotel located within the Al-Wadi District.
The Al-Wadi development is designed as an integrated commercial complex spanning approximately 7,818.5 square metres of land, with a built-up area of about 975 square metres. It includes a men’s gym, a women’s gym and a hotel building.
The Al-Rahmaniyah project is an integrated commercial development combining fitness facilities with retail. The asset features men’s and women’s gyms operating alongside an independent commercial zone.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17071628/main.jpg -
SLB wins $385m contract for Kuwait oil research centre2 June 2026
Schlumberger Oilfield Eastern, a unit of the US-headquartered oilfield services company SLB, has been awarded a KD118m ($385m) contract to develop an oil and gas research centre in Kuwait.
The contract was awarded by the state-owned upstream operator Kuwait Oil Company (KOC), according to a report by Kuwait’s Al-Rai newspaper.
The Ahmadi Innovation Valley (AIV) project is planned as an advanced research and innovation hub equipped with specialised facilities and technical teams focused on applied research for Kuwait’s oil and gas sector.
The contract was awarded after the Higher Purchase Committee (HPC) of Kuwait’s national oil and gas company Kuwait Petroleum Corporation (KPC) determined the bid to be compliant with the project’s technical and commercial requirements.
In February 2025, KOC signed memorandums of understanding (MoUs) with five international oilfield service companies to support the development of the AIV initiative.
These companies were:
- SLB (US)
- Baker Hughes (US)
- Weatherford (US)
- Halliburton (US)
- National Energy Services Reunited (US)
Under the preliminary agreements, each of the five companies agreed to establish a world-class research and development centre at the project site, focused on helping KOC meet challenges in the upstream sector.
KOC’s CEO Ahmad Jaber Al-Eidan had said in February 2025 that the project will enable Kuwait to keep pace with global transformations while investing in advanced technologies to ensure the sector’s sustainability and achieve operational excellence.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17063475/main.gif
