QatarEnergy LNG prepares to receive decarbonisation bids

20 March 2025

Register for MEED’s 14-day trial access 

QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

  • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung C&T (South Korea)

The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

The EPC scope of work on the project covers the following:

  • QG North complex:
    • Installation of four new electric-driven compressors
    • New power substation for power import from Kahramaa 65MW
    • New ITR for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Pig launcher
       
  • QG South complex:
    • Installation of two new electric-driven compressors
    • Integration with South injection system unit 85
    • Solvent reformulation for South trains 1/23
    • New power substation for power import from Kahramaa 35MW
    • New SIH for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Chillers package
    • Pig launcher
       
  • RLIC corridors
    • Common 22-inch export pipeline stretching 18 kilometres
    • Power tie-in RLF3 with Kahramaa
    • Electric cables
    • Fiber optic cable
       
  • Lot W15
    • Six injection wells by QatarEnergy LNG subsurface
    • Six injection flowlines and metring skid
    • Six wellhead control panels
    • Power tie-in from Barzan
    • Substation
    • Pig receiver
    • Access road and fencing

QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

North Field LNG expansion

Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

EPC works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.


February's special report on Qatar includes

> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
Indrajit Sen
Related Articles
  • Riyadh sets December deadline for Prince Mishaal Road

    20 November 2025

     

    The Royal Commission for Riyadh City (RCRC) has allowed contractors until 3 December to submit bids for a contract to develop Prince Mishaal Bin Abdulaziz Road Axis-Taif Road in Riyadh.

    The previous deadline was 19 November.

    The scope of work covers general road improvement works, including street upgrades, drainage works, relocation of existing utilities, dry and wet utilities, and other associated infrastructure. RCRC is investing in improving the road network in and around the kingdom's capital.

    Earlier in November, MEED reported that RCRC had begun post-tender clarifications with bidders for a contract covering upgrade works on Najm Al-Din Al-Ayoubi Road in Riyadh.

    The scope of work covers general road improvement works, including upgrades to three bridges at Al-Zahabi Road, Abdulrahman Adakhel Road and Atia Al-Saady Road.

    In February, RCRC announced plans to develop eight road projects in Riyadh at an estimated cost of more than SR8bn ($2bn).

    The projects form part of the second group in the Riyadh Ring Roads and Main Axes development programme.

    The schemes include:

    • The northern part of the Prince Turki Bin Abdulaziz Al-Awwal Road development project, with a length of more than 6 kilometres (km). The scope includes the development of two main intersections, the construction of three bridges and a tunnel.
    • The middle section of the Al-Thumama Road Axis development project. The scheme will cover about 10km and includes the development of five main intersections and the construction of 11 bridges and five tunnels.
    • The Imam Abdullah Bin Saud Road development project, which will stretch about 9km and includes the development of four main intersections, the construction of three bridges and two tunnels.
    • The Dirab Road development project, which will cover 9km and includes the development of two main intersections and the construction of nine bridges.
    • The Imam Muslim Road development project, which stretches 12km and includes the development of four main intersections and the construction of four bridges. The project will serve as the future extension of the Prince Turki Bin Abdulaziz Al-Awwal Road Axis to the south.
    • The road network development project surrounding King Abdullah Financial Centre, with a length of 20km. This includes the development of three main intersections and the construction of 19 bridges.
    • The construction of a bridge at the intersection of King Salman Road in the east with Abu Bakr Al-Siddiq Road in the north.
    • The first package of engineering modifications for crowded sites in Riyadh, encompassing improvements to alleviate traffic congestion during peak times.

    In August last year, RCRC confirmed it had awarded four contracts worth SR13bn ($3.46bn) as part of the first phase of the programme to develop the city’s road network.

    RCRC said the first phase will develop the axis of the main and ring roads to improve traffic movement in the city.

    Other major projects by RCRC include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park and the Green Riyadh project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15123861/main.jpg
    Yasir Iqbal
  • Riyadh advances with rail link prequalifications

    20 November 2025

     

    Saudi Arabia Railways (SAR) is expected to begin the second stage of the prequalification process for a contract covering the construction of a new railway line, known as the Riyadh Rail Link, which will run from the north to the south of Riyadh.

    MEED understands that the consortiums need to propose self-funded financing arrangements for the project as part of the new round of prequalifications.

    Contractors submitted their initial prequalification documents earlier this month.

    The scope of work includes constructing a 35-kilometre-long double-track railway line connecting SAR’s North-South Railway to the Eastern Railway network.

    The contract also covers the procurement, construction and installation of associated infrastructure such as viaducts, civil works, utility installations, signalling systems and other related works.

    The project is expected to form a key component of the Saudi Landbridge railway.

    The Saudi Landbridge is an estimated $7bn project comprising more than 1,500km of new track. Its core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrades to the existing Riyadh-Dammam line and a link between King Abdullah Port and Yanbu.

    The start of tendering activity for the Riyadh Rail Link project makes the construction of the Saudi Landbridge more likely. 

    The project is one of the kingdom’s most anticipated infrastructure programmes. Plans to develop it were first announced in 2004, but the project was put on hold in 2010 before being revived a year later.

    Key stumbling blocks were rights-of-way issues, route alignment and its high cost.

    In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.

    If it proceeds, the Landbridge will be one of the largest railway projects ever undertaken in the Middle East – and among the biggest globally.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15123411/main.jpg
    Yasir Iqbal
  • Local contractor bids low for $629m Kuwait oil project

    20 November 2025

    Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid on a contract to develop oil and gas facilities at the Sabriya and Bahra oil fields.

    The scope of the project is focused on developing a water separation facility next to Gathering Centre 23 (GC-23) and GC-24.

    It also includes developing an injection facility at GC-31.

    The full list of bidders for the project is:

    • Mechanical Engineering & Contracting Company (MECC) – KD193m ($629m)
    • Spetco – KD229m
    • Alghanim International – KD239m

    The tender was issued on 15 December 2024, with an initial bid submission deadline of 16 March 2025.

    The bid deadline was extended more than 10 times before prices were submitted.

    The client on the project is state-owned upstream operator Kuwait Oil Company (KOC).

    The scope of the project includes:

    • Installation of a high-integrity pressure protection system
    • Installation of chemical injection systems
    • Installation of effluent water transfer pumps
    • Installation of a low-pressure (LP) gas pipeline from the new LP gas knockout drum (KOD) to existing LP separator gas crude accumulator (inside GC-23 & 24)
    • Installation of interconnecting piping, instrumentation, electrical and civil works
    • Installation of a new oil recovery system with pumps, flowmeter and analyser
    • Installation of the substation and its equipment/systems
    • Installation of tie-ins for process and utilities from/to existing GC-30 to new injection facility
    • Installation of sludge collection, treatment and disposal system
    • Associated facilities

    Kuwait is trying to boost project activity in its upstream sector.

    The country’s national oil company, Kuwait Petroleum Corporation, aims to increase oil production capacity to 4 million barrels a day (b/d) by 2035.

    In August, Kuwait announced that it was producing 3.2 million b/d.

    Earlier this month, KOC said it was planning to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15120909/main.png
    Wil Crisp
  • Oman’s Marafiq retenders Duqm desalination plant

    20 November 2025

    Register for MEED’s 14-day trial access 

    Oman-based Central Utilities Company (Marafiq) has reissued the main contract tender for its planned seawater reverse osmosis (RO) desalination plant in Duqm.

    The revised submission deadline is 25 November.

    The project has an estimated budget of $100m and will supply industrial water and support wastewater services in the Duqm Special Economic Zone.

    The scheme involves building a seawater RO plant, an intake system, pre-treatment facilities, pumping stations, metering stations, pipelines and associated infrastructure.

    Marafiq is developing the project in its capacity as the authorised utilities provider for the Duqm Special Economic Zone.

    The company intends to develop a plant with a capacity of 45 million litres a day to serve industrial customers, including a planned hot-briquetted iron (HBI) facility proposed by an international steel manufacturer at Duqm Port. 

    Spain’s Cobra Group and Oman’s Global Chemicals & Maintenance System were previously prequalified to bid for the engineering, procurement and construction contract.

    The main contract was initially tendered in December 2024, with the bid submission deadline in February. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15116821/main.jpg
    Mark Dowdall
  • Wood Group wins Iraq oil contract

    20 November 2025

    Register for MEED’s 14-day trial access 

    Aberdeen-based Wood Group has won a contract to deliver project management and engineering services for PetroChina at the West Qurna-1 oil field in southern Iraq, according to a statement from the company.

    Under the terms of the contract, Wood will manage engineering, procurement and construction (EPC) projects at the field. 

    Located approximately 50 kilometres northwest of Basra, West Qurna-1 holds more than 20 billion barrels of recoverable reserves.

    Ellis Renforth, Wood’s president of operations for the Europe, Africa and Middle East region, said: “This contract award deepens our decade-long partnership at West Qurna-1 and reflects the continued trust placed in Wood to deliver complex energy solutions in Iraq. 

    “We’re proud to combine our global expertise with a strong local workforce to help support Iraq’s energy ambitions.”

    The contract will be delivered by nearly 200 Wood employees based in Iraq and the UAE, the company said.

    On 17 November, in a vote, 88% of Wood Group’s shareholders backed the company’s takeover by Dubai-based Sidara.

    The vote came after months of delay, while Wood struggled to agree its accounts with its auditor.

    The company’s accounts were eventually published on 30 October, showing a pre-tax loss of more than £2bn and evidence that the auditor was still not satisfied with the figures going back several years.

    Wood Group accepted a $292m conditional takeover bid from Sidara in August.

    As of February, Wood Group employed 35,000 people across about 60 countries, many in consulting and engineering roles.

    In the Middle East, the company has project contracts in Iraq, Kuwait, Oman, Qatar, Saudi Arabia and the UAE, where it has opened its third office in Sharjah.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15122155/main.png
    Wil Crisp