QatarEnergy LNG prepares to receive decarbonisation bids
20 March 2025

Register for MEED’s 14-day trial access
QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).
Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.
The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:
- Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
- Larsen & Toubro Energy Hydrocarbon (India)
- Samsung C&T (South Korea)
The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.
The EPC scope of work on the project covers the following:
- QG North complex:
- Installation of four new electric-driven compressors
- New power substation for power import from Kahramaa 65MW
- New ITR for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Pig launcher
- QG South complex:
- Installation of two new electric-driven compressors
- Integration with South injection system unit 85
- Solvent reformulation for South trains 1/23
- New power substation for power import from Kahramaa 35MW
- New SIH for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Chillers package
- Pig launcher
- RLIC corridors
- Common 22-inch export pipeline stretching 18 kilometres
- Power tie-in RLF3 with Kahramaa
- Electric cables
- Fiber optic cable
- Lot W15
- Six injection wells by QatarEnergy LNG subsurface
- Six injection flowlines and metring skid
- Six wellhead control panels
- Power tie-in from Barzan
- Substation
- Pig receiver
- Access road and fencing
QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.
North Field LNG expansion
Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.
The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.
QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
EPC works on the two projects are making progress.
QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.
QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.
When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.
In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.
This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.
February's special report on Qatar includes:
> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

Exclusive from Meed
-
-
-
-
-
Riyadh seeks contractors for Expo Icon structure22 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Adnoc initiates oil production project at key offshore block22 July 2026

Abu Dhabi National Oil Company (Adnoc Group) and its international partner, Pakistan International Oil (PIOL), have initiated a project to produce oil from Offshore Block 5 in Abu Dhabi’s waters, in which they are both stakeholders.
Adnoc, the leader on the project, intends to execute it through a front-end engineering and design (feed) competition, according to sources.
The Abu Dhabi energy giant recently selected the following three contractors for the Offshore Block 5 feed competition:
- CNPC Offshore Engineering Co (China)
- Saipem (Italy)
- Sinopec (China)
Offshore Block 5 covers 6,223 square kilometres in Gulf waters near the Zakum field and is located 100 kilometres northeast of the city of Abu Dhabi.
Abu Dhabi’s Supreme Council for Financial & Economic Affairs awarded a production concession agreement for Offshore Block 5 to Adnoc and PIOL in June 2025, with Adnoc holding the majority 60% participating interest and PIOL the other 40%.
Prior to that, Adnoc had signed an exploration concession agreement in August 2021 with PIOL, which is a consortium of four Pakistani state-owned companies – Pakistan Petroleum, Mari Petroleum Company, Oil & Gas Development Company and Government Holdings (Private).
The Pakistani consortium is understood to have invested up to $304.7m in exploration and appraisal drilling, including a participation fee, to explore for and appraise oil and gas opportunities in Offshore Block 5.
Potential oil production from Offshore Block 5 is expected to contribute to Adnoc Group’s objective of achieving an oil production capacity of 5 million barrels a day (b/d) by 2027 – a campaign known as Accelerated Integrated Programme 5. The Abu Dhabi energy giant currently has a spare capacity of 4.85 million b/d.
Pakistan, which is heavily reliant on energy imports for its economy, will also benefit from potential oil production by its companies from the Abu Dhabi concession.
ALSO READ: Adnoc announces FID on $6.2bn Umm Shaif gas cap project
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17726345/main.jpg -
Chinese contractor appointed for 500MW Oman solar plant22 July 2026
China's Shanxi Installation Group has secured an estimated $222m engineering, procurement and construction (EPC) contract for the 500MW Al-Kamil 1 solar independent power project (IPP) in Oman.
In a filing on the Hong Kong stock exchange, the company said the deal marks its first major project in the Middle East.
The contract covers the EPC, grid connection, testing and commissioning of the utility-scale solar photovoltaic (PV) plant, as well as 2.5 years of operations and maintenance.
A consortium comprising France's EDF Power Solutions, Oman National Engineering & Investment Company and OQ Alternative Energy signed the power purchase agreement for the project with Nama Power & Water Procurement Company (Nama PWP) in June.
Nama PWP is the sole procurer of new electricity generation capacity in Oman.
The Al-Kamil 1 solar IPP is EDF Power Solutions' third renewable energy project in Oman, following the 500MW Manah 1 solar PV IPP and the 120MW JBB wind IPP.
As MEED has previously reported, the Al-Kamil 1 project is part of Nama PWP's renewable energy development pipeline, which also includes the 400MW Sinaw and 280MW Marsa solar IPPs.
Nama PWP is currently tendering supervisory services for the Marsa IPP, with a bid submission deadline of 26 July.
The pipeline also comprises the 800MW Mahout and 300MW Duqm 2 wind IPPs, both targeted for commissioning between 2027 and 2029.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17725741/main.jpg -
Fluor wins feed contract for key Bahrain aromatics facility22 July 2026
Bahrain’s Gulf Petrochemical Industries Company (GPIC) has awarded US-based consultant Fluor a contract for front-end engineering and design (feed) on an aromatics facility in the country.
The project will be an expansion of GPIC’s existing petrochemicals facility in Bahrain’s downstream complex in Sitra, which produces ammonia, urea and methanol.
The new aromatics facility will utilise “commercially-proven process technologies” to produce approximately 1.2 million metric tonnes a year (t/y) of paraxylene and 500,000 metric t/y of benzene, Texas-headquartered Fluor said.
Paraxylene and benzene are critical building blocks for plastics, polyester fibers and packaging materials, supporting global demand for high‑performance consumer and industrial products.
Founded in 1979, GPIC is a joint venture of Bahraini state energy enterprise Bapco Energies, known at the time as Nogaholding; chemicals giant Saudi Basic Industries Corporation (Sabic); and Petrochemical Industries Company – a subsidiary of state energy conglomerate Kuwait Petroleum Corporation. The three partners hold equal stakes of 33.3% in GPIC.
GPIC utilises locally available natural gas as feedstock to manufacture high-quality chemicals and fertilisers for domestic consumption and export, including 1,200 metric tonnes a day (t/d) of ammonia, 1,200 metric t/d of methanol and 1,700 metric t/d of granular urea.
ALSO READ: Bahrain taps consultants for studying use of nuclear power
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17725737/main1255.jpg -
Firms submit bids for second Hassyan SWRO pipeline contract22 July 2026
Dubai Electricity & Water Authority (Dewa) has received bids from three contractors for a second pipeline contract relating to the Hassyan seawater reverse osmosis (SWRO) network expansion.
Project two requires contractors to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the plant's phase two network.
Local firm Tristar Engineering & Construction submitted the lowest offer of AED792.59m ($215.8m), according to tender results published by the state utility.
Green Oasis General Contracting (UAE) submitted a bid of AED800.02m ($217.8m) and Wade Adams Contracting (UAE) made the other compliant offer of AED989.65m ($269.5m).
In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.
Earlier in July, eight contractors submitted bids for project one of the Hassyan pipeline network expansion.
Dewa also has a third contract out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.
Project three was tendered on 26 January and has a bid submission deadline of 29 July.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17723861/main.jpg -
Riyadh seeks contractors for Expo Icon structure22 July 2026

Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has asked contractors to express interest in the construction of the Icon, one of the key landmarks at the site.
The structure will be located at the entrance of the Expo 2030 Riyadh site, within the Collaboration Precinct.
ERC issued the expressions of interest notice on 20 July. The deadline for submissions of interest is 23 July.
The structure will be connected to the metro station and will serve as a gateway to the event.
It will be 66 metres tall and will comprise an observation platform, food and beverage outlets and other features.
The total built-up area will be approximately 16,279 square metres and it will be able to accommodate more than 1,450 visitors an hour during the event.
The contract duration is 29 months from the start of construction.
ERC tendered the contract for the construction of the Saudi Arabia pavilion at the site in May.
The pavilion is a major asset located within the venue's KSA District, on the eastern side of the Expo 2030 Riyadh masterplan, within the Loop of Nations district.
Construction progress
The tendering of the pavilion structure followed swift progress on the site’s infrastructure development works.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.
The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – are split into three packages:
- Lot 1 covers the main utilities corridor;
- Lot 2 includes the northern cluster of the nature corridor;
- Lot 3 comprises the southern cluster of the nature corridor.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17723204/main.jpg