QatarEnergy LNG prepares to receive decarbonisation bids

20 March 2025

Register for MEED’s 14-day trial access 

QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

  • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung C&T (South Korea)

The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

The EPC scope of work on the project covers the following:

  • QG North complex:
    • Installation of four new electric-driven compressors
    • New power substation for power import from Kahramaa 65MW
    • New ITR for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Pig launcher
       
  • QG South complex:
    • Installation of two new electric-driven compressors
    • Integration with South injection system unit 85
    • Solvent reformulation for South trains 1/23
    • New power substation for power import from Kahramaa 35MW
    • New SIH for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Chillers package
    • Pig launcher
       
  • RLIC corridors
    • Common 22-inch export pipeline stretching 18 kilometres
    • Power tie-in RLF3 with Kahramaa
    • Electric cables
    • Fiber optic cable
       
  • Lot W15
    • Six injection wells by QatarEnergy LNG subsurface
    • Six injection flowlines and metring skid
    • Six wellhead control panels
    • Power tie-in from Barzan
    • Substation
    • Pig receiver
    • Access road and fencing

QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

North Field LNG expansion

Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

EPC works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.


February's special report on Qatar includes: 

> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
Indrajit Sen
Related Articles
  • Neom’s industrial pivot gathers pace

    1 October 2026

    Commentary
    Colin Foreman
    Editor

    Reprioritisation has been the buzzword in Saudi Arabia over the past two years and nowhere has that been more evident than at Neom. 

    The slowdown of development at The Line and the postponement of the 2029 Asian Winter Games at Trojena have dominated international headlines. As these projects scale back, Oxagon’s industrial and logistics base has become the $500bn gigaproject’s flagship development. There are tangible results: in August, the $8.5bn Neom Green Hydrogen project was commissioned, marking Neom’s most significant completion to date. 

    Construction activity elsewhere at Oxagon supports this trend. The AI data-centre campus being developed by Humain and DataVolt has broken ground on its first 100MW phase, backed by $5bn of investment and targeted for service in 2028. Neom has issued an expression of interest for a rail line linking the Port of Neom to Saudi Arabia Railways’ North-South network, tenders are out for an industrial wastewater plant and the upgrade of Highway 55, and the port itself is advancing towards a 2030 capacity target of 1.5 million TEUs. 

    The regional conflict that began in February has strengthened the business case by giving Oxagon’s Red Sea port added strategic weight as a second maritime gateway outside the Strait of Hormuz, at a time when Riyadh has committed to directing about 80% of the Public Investment Fund’s portfolio into domestic investment.

    These developments reflect a kingdom recalibrating rather than retreating

    Elsewhere, Saudi Arabia’s wider projects market is holding steady despite conflict-related disruption, with contract awards reaching $68bn so far this year. The regional power market is also diversifying, with Aljomaih, EDF and Kepco all more than tripling net capacity in recent years as Acwa retains its lead.

    These developments reflect a kingdom recalibrating rather than retreating, with priority given to projects capable of delivering commercial returns.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20178338/main.gif
    Colin Foreman
  • Contractor wins Dammam airport water infrastructure deal

    1 October 2026

    Saudi Arabia-based Alkhorayef Water & Power Technologies has won an SR80m ($21.3m) contract to rehabilitate water and wastewater infrastructure at King Fahd International airport in Dammam in the kingdom’s Eastern Province.

    The contract was awarded by Dammam Airports Company (DACO), and work is scheduled to be completed within 18 months, the firm said in a disclosure to the Saudi Exchange (Tadawul) on 29 September.

    The scope covers the design, construction, supply, installation, replacement, rehabilitation and integration of water and wastewater infrastructure.

    It includes pumps, storage tanks and reservoirs, reverse osmosis facilities, piping and tie-ins, as well as electrical and instrumentation works.

    The award comes as DACO advances a wider programme of investment at King Fahd International airport.

    DACO signed more than SR1.2bn ($320m) in agreements in June covering airport infrastructure, including a new power station, a medium-voltage distribution network and upgrades to the existing electrical grid. 

    In September, it also appointed WSP Middle East, the regional arm of Canadian engineering firm WSP, to develop the airport’s expansion under its masterplan.

    The expansion is intended to increase annual passenger capacity to more than 19.3 million by 2030, with a longer-term target of 32 million passengers. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20169118/main.jpg
    Mark Dowdall
  • Kuwait tenders LNG project

    1 October 2026

     

    State-owned Kuwait Integrated Petroleum Industries Company (Kipic) has tendered a project to develop a reliquefaction unit at the Al-Zour liquefied natural gas (LNG) import terminal.

    The project focuses on developing a boil-off gas (BOG) unit at the terminal, with bids due on 22 December.

    A meeting for contractors to discuss the project is scheduled for 18 October.

    The project scope includes engineering, procurement and construction works, along with pre-commissioning, commissioning and performance testing services.

    The list of prequalified companies is:

    • Fluor (US)
    • GS Engineering & Construction (South Korea)
    • Tecnicas Reunidas (Spain)
    • Larsen & Toubro (India)
    • Hyundai Engineering (South Korea)
    • CTCI Corporation (Taiwan)
    • Daewoo Engineering & Construction (South Korea)
    • Hyundai Engineering & Construction (South Korea)
    • Saipem (Italy)
    • Samsung Engineering (South Korea)
    • Sinopec Engineering (China)
    • JGC Holdings (Japan)
    • KBR (US)
    • China National Petroleum Corporation (China)
    • Technip (France)

    A BOG unit at an LNG facility captures, compresses and processes natural gas vapours that evaporate from cryogenic storage tanks, enabling the gas to be recycled back into the system rather than flared.

    In April, MEED revealed that contractors expected the project to be worth about $200m.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20168625/main2005.jpg
    Wil Crisp
  • Riyadh approaches contractors for 2km tower

    1 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Public Investment Fund (PIF) has reached out to contractors as part of a market-sounding exercise for the construction of the proposed 2-kilometre megatall tower project.

    MEED understands that a PIF subsidiary, the Tower District Real Estate Development Company, is undertaking the process.

    It is understood that several experienced international contractors, as well as some prominent local contractors, have been approached.

    The latest development follows PIF receiving offers in June last year from firms seeking a contract to provide project management consultancy (PMC) services for a new central business district (CBD) on the outskirts of Riyadh, which includes the proposed 2km tower.

    The PMC role covers both the tower and the surrounding district.

    Firms understood to have been invited to bid include US-based Aecom, Jacobs, Parsons and Turner, as well as the UK’s Mace.

    UK-based Foster & Partners is working as the architect for the tower after winning a design competition launched in late 2022.

    Record breaker

    The proposed tower would be more than double the height of the world’s tallest building, Dubai’s Burj Khalifa, which stands 828 metres tall. It is expected to be at least several hundred metres taller than the 1,000-metre-plus tower under construction in Jeddah.

    Contractors that have priced megatall towers in the region say a 2km-tall structure could cost about $5bn to construct, depending on the final design.

    The 2km tower and the surrounding CBD – known as Project Rise – sit within a larger masterplanned development to the north of Riyadh called the North Pole.


    MEED’s October 2026 report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20156496/main.jpg
    Yasir Iqbal
  • Singapore’s Temasek plans Middle East expansion

    1 October 2026

    Singapore’s Temasek plans to open offices in Riyadh and Abu Dhabi early next year as it targets investment and partnership opportunities in Saudi Arabia, the UAE, Qatar and the wider region.

    The state-owned investor had a net portfolio value of S$518bn ($401bn) as of 31 March 2026.

    It said the new offices will serve as regional hubs for Temasek and its portfolio companies, with some businesses expected to co-locate to work more closely with partners and pursue deals alongside the group. The openings are subject to regulatory approvals.

    Temasek said it will also step up engagement with institutions in Qatar, although it has not announced plans to establish an office there.

    The company said the expansion reflects its confidence in the region’s long-term fundamentals and the economic transformation being driven by national diversification programmes.

    It added that a presence in Riyadh and Abu Dhabi will also support investment activity beyond the region by improving access to opportunities across the wider Middle East, Central Asia and Africa.

    Several Temasek-owned or Temasek-backed companies are already active in the GCC, providing a platform for the group’s planned expansion.

    These include Singapore-headquartered engineering and consultancy firm Surbana Jurong, which has been involved in masterplanning and advisory work on major regional developments, alongside other portfolio companies with interests spanning infrastructure, logistics, financial services and technology.

    According to data from regional project tracker MEED Projects, Surbana Jurong is involved in several major projects in Saudi Arabia, including King Abdulaziz International airport (KAIA) in Jeddah, Jeddah Islamic Port, Red Sea Global’s Amaala masterplan, the Trojena dams scheme, Oxagon, King Salman International airport and Saudi Arabia Railway’s North-South Phosphate Railway 3.

    The firm has also worked on projects in the wider region, including the West Link project, Urban Loop, Musaffah Innovation District masterplan, Etihad Rail’s high-speed rail programme and Abu Dhabi airport’s Midfield Terminal.

    Surbana Jurong has also secured masterplanning contracts from Abu Dhabi’s Department of Municipalities & Transport and Abu Dhabi Ports.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20157511/main.jpg
    Yasir Iqbal