QatarEnergy LNG prepares to receive decarbonisation bids
20 March 2025

Register for MEED’s 14-day trial access
QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).
Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.
The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:
- Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
- Larsen & Toubro Energy Hydrocarbon (India)
- Samsung C&T (South Korea)
The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.
The EPC scope of work on the project covers the following:
- QG North complex:
- Installation of four new electric-driven compressors
- New power substation for power import from Kahramaa 65MW
- New ITR for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Pig launcher
- QG South complex:
- Installation of two new electric-driven compressors
- Integration with South injection system unit 85
- Solvent reformulation for South trains 1/23
- New power substation for power import from Kahramaa 35MW
- New SIH for DCS/ESD/F&G
- Tie-ins with utility units
- Dehydration package
- Chillers package
- Pig launcher
- RLIC corridors
- Common 22-inch export pipeline stretching 18 kilometres
- Power tie-in RLF3 with Kahramaa
- Electric cables
- Fiber optic cable
- Lot W15
- Six injection wells by QatarEnergy LNG subsurface
- Six injection flowlines and metring skid
- Six wellhead control panels
- Power tie-in from Barzan
- Substation
- Pig receiver
- Access road and fencing
QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.
North Field LNG expansion
Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.
The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.
QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
EPC works on the two projects are making progress.
QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.
QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.
When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.
In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.
This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.
February's special report on Qatar includes:
> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

Exclusive from Meed
-
UAE to withdraw from Opec and Opec+ alliance28 April 2026
-
NWC tenders package 14 of sewage treatment programme28 April 2026
-
Construction begins on Aman Dubai Hotel and Residences28 April 2026
-
Regional war deepens Kuwait oil sector’s tender crisis28 April 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
UAE to withdraw from Opec and Opec+ alliance28 April 2026
The UAE has announced its decision to withdraw from Opec and the Opec+ alliance from 1 May.
In a statement, the UAE Ministry of Energy said the move followed a “comprehensive review” of its production policy.
“While near-term volatility, including disruptions in the Arabian Gulf and the Strait of Hormuz, continues to affect supply dynamics, underlying trends point to sustained growth in global energy demand over the medium to long term,” the statement, issued on 28 April, said.
“This decision follows decades of constructive cooperation. The UAE joined Opec in 1967 through the Emirate of Abu Dhabi and continued its membership following the formation of the United Arab Emirates in 1971. Throughout this period, the UAE has played an active role in supporting global oil market stability and strengthening dialogue among producing nations.”
The announcement was timed to coincide with an Opec ministerial meeting in Vienna and was communicated through state news agency Wam.
Abu Dhabi National Oil Company (Adnoc) has set a target of raising production capacity to 5 million barrels a day (b/d) by 2027 – up from a current capacity of around 4.85 million b/d, though the country has been constrained to producing approximately 3.4 million b/d under Opec+ quota agreements.
Membership of a quota-constrained group sits uneasily with that ambition. The non-oil economy now accounts for roughly 75% of the UAE’s GDP, reducing the political cost of rupture with the organisation.
The Iran war wiped out 7.88 million b/d of Opec production in March, cutting group output 27% to 20.79 million b/d – the steepest supply collapse in the organisation’s recorded history, exceeding the Covid-19 demand shock of May 2020 and the disruptions of both the 1970s oil crisis and the 1991 Gulf War. Gulf producers have been struggling to route exports through the Strait of Hormuz amid Iranian threats and attacks on vessels, further straining the group’s cohesion.
Against that backdrop, the UAE’s departure deals a significant blow to Opec and its de facto leader, Saudi Arabia, which has sought to project unity despite persistent internal disagreements over quotas and geopolitics.
The US-Israeli war on Iran since late February has had a detrimental effect on a number of Gulf states, including the UAE.
The UAE was targeted by thousands of Iranian ballistic missiles and drones, damaging strategic oil and gas facilities, denting Dubai’s appeal as a luxury tourism hotspot and slowing oil exports to a trickle.
Whereas some Gulf states have urged dialogue with Iran, the UAE has maintained a more hawkish position. Analysts say that position is partially due to its reliance on the Strait of Hormuz for oil exports and the UAE’s unwillingness to see Iran cement itself as a regional power in the Gulf.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16596229/main.gif -
NWC tenders package 14 of sewage treatment programme28 April 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s National Water Company (NWC) has tendered a contract for the construction of 10 sewage treatment plants as part of the next phase of its long-term operations and maintenance (LTOM) sewage treatment programme.
According to the original scope, the Eastern A Cluster (LTOM14) package will have a total treatment capacity of 184,440 cubic metres a day (cm/d) at an estimated cost of $180m.
The bid submission deadline is 30 September.
The tender follows recent contract awards for North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11) and the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).
MEED exclusively reported that a consortium comprising China’s Jiangsu United Water Technology, the UAE’s Prosus Energy and Saudi Arabia’s Armada Holding had been appointed as a contractor for each of these projects.
Package 11 will have a combined capacity of about 440,000 cm/d at an estimated cost of about SR211m ($56.3m).
Package 12 will have a combined treatment capacity of 337,800 cm/d at an estimated cost of about SR203m ($54.1m).
In April, NWC also opened finanical bids for North Western B Cluster (LTOM12) of its sewage treatment programme.
The contract covers the construction and upgrade of seven sewage treatment plants with a combined capacity of about 162,000 cm/d.
MEED previously reported that the following companies had submitted proposals:
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- Civil Works Company (Saudi Arabia)
- Miahona (Saudi Arabia)
- Beijing Enterprises Water Group – BEWG (Hong Kong)
- Al-Yamama (Saudi Arabia)
These bids are currently under evaluaton, with an award expected in the coming weeks, a source said.
The tender for the North Western C Cluster (LTOM13) project had been put on hold, although it is understood that this is now likely to be the next package to be tendered.
Under the original scope, this package covers the construction of 10 sewage treatment plants.
In total, the LTOM programme comprises 19 packages split into two phases. This contract for LTOM10 was the first to be awarded under the second phase of NWC’s rehabilitation of sewage treatment plants programme.
As MEED understands, there have been several discussions in recent months regarding changes in scope details and potential expansions. This involves potentially grouping some upcoming projects.
NWC previously awarded $2.5bn-worth of contracts in the first phase. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years. Phase two of the programme includes 10 packages covering 117 treatment plants.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16591851/main.jpg -
Construction begins on Aman Dubai Hotel and Residences28 April 2026
Dubai-based developer H&H Development and Switzerland’s Aman Group have broken ground on the Aman Dubai Hotel and Residences project in Dubai’s Jumeirah area.
The project’s enabling works contract has been awarded to local firm Swissboring.
Foundation works are expected to start this quarter.
The developers said ground improvement works have now been completed. Another local firm, DBB Contracting, carried out the works.
The project comprises a hotel, 78 branded residences and villas.
Singapore-headquartered architectural firm Kerry Hill Architects is the project consultant.
Dubai real estate developments continue to dominate the UAE’s construction market, with schemes worth more than $323bn either under execution or in planning.
This aligns with a GlobalData forecast that the UAE construction sector will grow by 3% in real terms in 2026, supported by infrastructure, energy and utilities, and residential projects.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16591687/main.jpg -
Regional war deepens Kuwait oil sector’s tender crisis28 April 2026
Commentary
Wil Crisp
Oil & gas reporterContractors in Kuwait expect the regional conflict and disruption to shipping to worsen the country’s existing oil and gas tendering problems, causing long-term disruption in the sector.
In the months prior to the US and Israel attacking Iran on 28 February, contract tenders worth an estimated $9.1bn were cancelled after bids came in above the projects’ allocated budgets.
Contractors largely blamed the cancellations on long delays to tender processes after budgets had been set.
The delays, which often extended for several years, meant inflation drove up the cost of materials and labour, making it almost impossible for contractors to submit bids within the original budgets.
One industry source said: “The reason all of these contracts were cancelled was because the tender processes for large projects had started moving again after stalling for a long time.
“Bids came in and unfortunately they were over budget. It was then expected that tender processes would restart and these projects would ultimately be awarded – but now the war means that Kuwait is facing a whole new wave of project delays and nobody knows when it is going to end.”
War impact
Many industry insiders believe delays caused by the war and the closure of the Strait of Hormuz will once again seriously disrupt projects, just as many stakeholders believed the country was about to see an uptick in project progress.
One source said: “Bid bonds are going to have to be renewed and some bidders might just use that as an opportunity to drop out of the bidding process.
“It’s also possible that work that has already been done, like feasibility studies, will no longer be relevant and will have to be repeated.”
2025 rebound
Last year, Kuwait recorded its highest total annual value for oil, gas and chemicals contract awards since 2017, according to data from regional project tracker MEED Projects.
A total of 19 contract awards with a combined value of $1.9bn were awarded.
This was more than four times the value of contract awards across the same sectors in 2024, when awards were worth just $436m.
It was also above the $1.7bn peak recorded in 2021, but it remained far lower than the values seen in 2014-17, when several large-scale, multibillion-dollar projects were awarded in the country.
The surge in the value of contract awards came after Kuwait’s emir indefinitely dissolved parliament and suspended some of the country’s constitutional articles in May 2024.
Prior to the suspension of parliament, Kuwait suffered from very low levels of project awards for several years amid political gridlock and infighting between the cabinet and parliament.
This meant important decisions about projects could not be made – a major obstacle to the progression of strategic oil projects.
Forward outlook
With several major oil and gas projects under development in late 2025 and early 2026, some expected 2026 to record a far higher volume of oil and gas contract awards than 2025.
Projects expected to be tendered – and potentially awarded – this year included a $3.3bn onshore production facility due to be developed next to the Al-Zour refinery.
This project has already been delayed and put on hold as a result of fallout from the US and Israel’s conflict with Iran.
Had it been awarded, it would have been the biggest single oil and gas contract award in Kuwait in more than 10 years.
Now, as a result of the conflict, many of the large tenders expected to take place this year are likely to be significantly delayed.
One source said: “Right now, everyone in the oil and gas sector is waiting for some sort of sign of improving stability before they make a decision and there’s a lot of uncertainty.
“The state-owned oil companies aren’t communicating with contractors like they normally do and the price of a lot of materials has increased dramatically.”
Even if the standoff between the US and Iran over reopening the Strait of Hormuz is resolved in the near future, it is likely to take months or years before Kuwait’s oil and gas project market regains the momentum it had at the beginning of 2026.
Given the lack of flexibility within Kuwait’s existing tendering system, delays can easily lead to tenders being cancelled, and the conflict’s inflationary impact will make it even harder for contractors to meet budgets set before the latest disruption.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16590560/main0421.png -
Partners launch feed-to-EPC contest for Duqm petchems project27 April 2026

Register for MEED’s 14-day trial access
Omani state energy conglomerate OQ Group and Kuwait Petroleum International (KPI), the overseas subsidiary of Kuwait Petroleum Corporation, have initiated a feed-to-EPC competition among contractors to develop a major petrochemicals complex at Duqm.
Under a feed-to-EPC model, the project operator selects contractors to carry out front-end engineering and design (feed). It then awards the engineering, procurement and construction (EPC) contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.
OQ8, the 50:50 joint venture of OQ and KPI, is understood to have issued the tender for the Duqm petrochemicals project’s feed-to-EPC competition in mid-March, with a deadline of 6 May for contractors to submit proposals, sources told MEED.
Several local and international contractors based in Oman are believed to be participating in the competition, according to sources.
OQ Group CEO Ashraf Bin Hamad Al-Maamari and KPI’s CEO Shafi Bin Taleb Al-Ajmi signed an agreement on 3 February, during the Kuwait Oil & Gas Show and Conference, to develop a major petrochemicals-producing complex in Oman’s Duqm. The parties did not disclose details at the time.
ALSO READ: Duqm petrochemicals revival provides fillip to Gulf projects market
The agreement represented a significant step forward in Oman and Kuwait’s long-held plans to jointly develop a petrochemicals complex next to the existing Duqm refinery, which will benefit from favourable feedstock access and strong cost competitiveness.
The planned facility will also benefit from in Al-Wusta governorate, along Oman’s Arabian Sea coastline.
OQ8 had struggled to make meaningful progress on the Duqm petrochemicals project since the plan was conceived as early as 2018, for a variety of reasons.
The original plan for the Duqm petrochemicals facility, estimated at $7bn, centred on a mixed-feed steam cracker with a capacity to produce 1.6 million tonnes a year (t/y) of ethylene. The project also included a polypropylene (PP) plant with a capacity of 280,000 t/y and a high-density polyethylene (HDPE) plant with a capacity of 480,000 t/y.
The complex was also expected to include an aromatics plant, as well as storage facilities for naphtha and liquefied petroleum gas (LPG).
The project’s prospects were temporarily boosted when Saudi Basic Industries Corporation (Sabic) expressed interest in investing by signing a non-binding memorandum of understanding with OQ in December 2021.
Reuters reported in December that Sabic was withdrawing from the project, leaving OQ to look for other partners. The new agreement between OQ and KPI is understood to have followed the Saudi chemical giant’s departure.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577785/main.jpg
