QatarEnergy LNG prepares to receive decarbonisation bids

20 March 2025

Register for MEED’s 14-day trial access 

QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

  • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung C&T (South Korea)

The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

The EPC scope of work on the project covers the following:

  • QG North complex:
    • Installation of four new electric-driven compressors
    • New power substation for power import from Kahramaa 65MW
    • New ITR for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Pig launcher
       
  • QG South complex:
    • Installation of two new electric-driven compressors
    • Integration with South injection system unit 85
    • Solvent reformulation for South trains 1/23
    • New power substation for power import from Kahramaa 35MW
    • New SIH for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Chillers package
    • Pig launcher
       
  • RLIC corridors
    • Common 22-inch export pipeline stretching 18 kilometres
    • Power tie-in RLF3 with Kahramaa
    • Electric cables
    • Fiber optic cable
       
  • Lot W15
    • Six injection wells by QatarEnergy LNG subsurface
    • Six injection flowlines and metring skid
    • Six wellhead control panels
    • Power tie-in from Barzan
    • Substation
    • Pig receiver
    • Access road and fencing

QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

North Field LNG expansion

Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

EPC works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.


February's special report on Qatar includes

> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
Indrajit Sen
Related Articles
  • Shell approves Egypt offshore gas project

    31 August 2026

    BG Delta, a Shell subsidiary, has reached the final investment decision for phase 12a of the West Delta Deep Marine (WDDM) development project.

    The project will be implemented in partnership with Malaysia’s Petronas and state-owned Egyptian General Petroleum Corporation (EGPC).

    Shell, Petronas and EGPC formed a joint venture called Burullus Gas Company to operate the WDDM concession.

    Phase 12a includes drilling and completing three deepwater gas wells, with production expected to begin in 2028, according to a statement from the London-headquartered company.

    The wells will be tied into existing subsea infrastructure, helping accelerate development, improve capital efficiency and limit the need for additional facilities.

    Dalia El-Gabry, the vice-president and chairperson of Shell Egypt, said: “This investment demonstrates our commitment to maximising the remaining potential in WDDM where the right technical and commercial conditions exist.

    “By leveraging existing infrastructure and our proven development experience, we can accelerate delivery while reinforcing our partnership with the Egyptian government and joint venture partners to help meet Egypt’s energy needs.”

    The new development builds on phases 10 and 11, which brought six wells online during 2024 and 2025.

    Its scope also covers facility installation, tie-in operations, commissioning and connection to existing offshore infrastructure.

    Egypt’s Ministry of Petroleum & Mineral Resources said in May that about $350m had been allocated to phase 12a.

    In April, Egypt’s Petroleum Marine Services (PMS) was awarded a contract for offshore works for phase 12 of the WDDM field development project.

    The contract awarded to PMS uses the engineering, procurement, installation and construction contract model.

    Under the scope of the contract, PMS will install the required electrical, hydraulic and mechanical connections in deep waters to tie three new gas wells into production as part of phase 12.

    The scope also includes the installation of three final triple tie-in spool bases to complete the connection between the wells.

    During phases 10 and 11 of the WDDM project, PMS laid two offshore electrical cables at water depths reaching 660 metres, in addition to carrying out well tie-in and production connection works at depths of up to 880 metres.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19078753/main.jpg
    Wil Crisp
  • Contractors appointed for Group 1 battery storage projects

    27 August 2026

     

    Register for MEED’s 14-day trial access 

    Two contractors have been appointed for engineering, procurement and construction (EPC) works on Saudi Arabia’s four Group 1 battery energy storage system (bess) projects with a combined capacity of 2,000MW, a source has confirmed to MEED.

    Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), recently signed four storage service agreements for the bess projects, which will provide four hours of storage, equivalent to 8,000 megawatt-hours (MWh), and involve a total investment of more than SR4.35bn ($1.16bn).

    Three projects were awarded to a consortium comprising Saudi Energy, Acwa and Al-Sharif Contracting & Commercial Development Company.

    According to the source, India’s Larsen & Toubro will carry out EPC works for these three projects, comprising the Al-Muwyah and Haden bess independent storage providers (ISPs) in the Mecca region, and the Al-Kahafa bess ISP in the Hail region.

    Each has a capacity of 500MW for four hours. The three projects have a combined capacity of 1,500MW and 6,000MWh.

    L&T recently announced that it had secured “a major order” for bess projects in the Middle East but did not disclose the specific projects involved.

    The fourth project, the Al-Khushaybi bess ISP in the Qassim region, was awarded to a consortium of France’s Engie and local firm Haji Abdullah Alireza & Co. This also has a capacity of 500MW for four hours. 

    China’s Sepco 3 has been appointed as the EPC contractor for this project, a source said.

    The agreements cover the first group of ISP bess projects being procured by SPPC under a build, own and operate model. The projects are supervised by the Energy Ministry.

    The projects form part of Saudi Arabia’s efforts to achieve an electricity generation mix comprising approximately 50% renewable energy by 2030.

    As previously reported, the Group 2 programme comprises six ISP projects with a total capacity of 3GW, equivalent to 12,000MWh based on a four-hour storage duration.

    Developers recently submitted a first round of clarification requests to SPPC as they prepare their bids in advance of an October deadline.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19052381/main.jpg
    Mark Dowdall
  • Accor and Al-Qimmah plan 4,000 Saudi rooms

    27 August 2026

    France’s hotel operator Accor has expanded its partnership with local firm Al-Qimmah Hospitality, a subsidiary of Saudi Arabia’s BinDawood Investment Company, to develop more than 4,000 hotel rooms in the kingdom.

    The plan focuses on building a portfolio in Mecca and Medina.

    The expanded agreement was announced in Paris during the French-Saudi Investment Roundtable. It follows a master development agreement signed in 2025. The partnership now covers five hotels in Jeddah, Mecca and Medina across the premium, midscale and economy segments.

    One planned development is an 850-room Novotel in Mecca, due to open in 2030. The agreement also covers the Mercure Makkah Shesha, ibis Styles Makkah Mesfalah, Movenpick Madinah and Swissotel Jeddah properties.

    The partnership will also support job creation and Saudi workforce development through Tamayyaz by Accor, the group’s national talent programme run with the Saudi Ministry of Tourism. The programme aims to develop and hire more than 3,000 Saudi nationals by 2030.

    Accor has operated in Saudi Arabia for more than three decades and runs 48 hotels with more than 21,600 rooms nationwide. Its pipeline includes a further 47 properties comprising more than 11,400 rooms.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19051854/main.jpg
    Colin Foreman
  • Jeddah tenders stormwater drainage contracts

    27 August 2026

    Jeddah Municipality has invited contractors to bid for a contract covering the construction of a rainwater drainage network for the Prince Fawaz neighbourhood.

    The project aims to collect and convey rainwater away from residential streets and low-lying areas. It is valued at $60m and intended to reduce flooding risks during heavy rainfall.

    The scope includes manholes, stormwater catch basins and connections to existing manholes as well as the restoration of road surfaces.

    The bid submission deadline is 12 October.

    The municipality is also progressing with a second stormwater drainage project for the first package of Zone (BC), Old Zahraa in Jeddah Governorate, with bids due on 2 September. The project is valued at about $30m.

    The two projects are part of the municipality’s wider drainage programme, which includes the flagship King Abdullah Road-Falasteen Road tunnel project.

    MEED previously reported that Saudi contractor Thrustboring Construction Company had been selected for phases one and two of the project, each valued at about $175m, covering the construction of large-diameter stormwater drainage tunnels.

    It is understood that an official agreement has yet to be signed.

    In June, MEED reported that local contractor Alkhorayef Water & Power Technologies (AWPT) had signed two contracts with Jeddah Municipality to operate and maintain stormwater and surface water drainage networks across the city.

    The contracts have a combined value of SR202.06m ($53.9m), and each will run for five years.

    The first contract, valued at SR108.46m ($28.9m), covers the operation and cleaning of stormwater and surface water networks in the South and Al-Malisa sub-municipalities.

    The second contract, worth SR93.59m ($25m), covers similar services for the Airport Sub-Municipality.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19039514/main.jpg
    Mark Dowdall
  • Saur and Nesma sign water infrastructure deal

    26 August 2026

    French firm Saur and local contractor Nesma & Partners have signed a deal to jointly “pursue the design and construction” of two recycled water plants in Riyadh.

    The memorandum of understanding (MoU) was signed during the French-Saudi Investment Roundtable Meeting in Paris on 24 August.

    It builds on an earlier agreement by the companies last September focusing on developing desalination and sewage treatment plants across the kingdom, including project development, engineering, procurement and construction, and long-term operations and maintenance.

    At the time, the companies agreed to “target industrial water treatment through concession and operations contracts”, extending the agreement beyond municipal water infrastructure.

    The latest agreement appears to mark a move from the broader partnership towards specific project opportunities in the Riyadh market. Details of the projects were not disclosed.

    In May, MEED exclusively reported that a consortium including Saur, Nesma and another local firm, Al-Bawani, was preparing to bid for the Riyadh East independent sewage treatment plant (ISTP) project, for which the submission deadline was recently extended to 29 September.

    There are almost $2.5bn-worth of water treatment projects at the pre-execution stage in Saudi Arabia, according to regional tracker MEED Projects.

    The French-Saudi Investment Roundtable Meeting was organised as part of Saudi Crown Prince and Prime Minister Mohammed Bin Salman’s state visit to France.

    Saudi Aramco also announced agreements and an MoU with French companies worth a potential combined value of more than $3.7bn.

    Among the other agreements signed during the conference was a cooperation agreement between Saudi Energy and French public investment bank Bpifrance, valued at up to $3bn, to support financing for projects to develop and expand Saudi Arabia’s power grid.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19011713/main.jpg
    Mark Dowdall