QatarEnergy LNG prepares to receive decarbonisation bids

20 March 2025

Register for MEED’s 14-day trial access 

QatarEnergy LNG is preparing to receive bids from contractors on 7 April for a carbon dioxide (CO2) sequestration complex project covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

The following contractors are among those that are understood to be preparing bids for engineering, procurement and construction (EPC) works on the QatarEnergy LNG CO2 sequestration project:

  • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Samsung C&T (South Korea)

The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex. The CO2 captured from the trains is to be compressed and injected into new injection wells, for which new compression trains and pipelines need to be installed.

The EPC scope of work on the project covers the following:

  • QG North complex:
    • Installation of four new electric-driven compressors
    • New power substation for power import from Kahramaa 65MW
    • New ITR for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Pig launcher
       
  • QG South complex:
    • Installation of two new electric-driven compressors
    • Integration with South injection system unit 85
    • Solvent reformulation for South trains 1/23
    • New power substation for power import from Kahramaa 35MW
    • New SIH for DCS/ESD/F&G
    • Tie-ins with utility units
    • Dehydration package
    • Chillers package
    • Pig launcher
       
  • RLIC corridors
    • Common 22-inch export pipeline stretching 18 kilometres
    • Power tie-in RLF3 with Kahramaa
    • Electric cables
    • Fiber optic cable
       
  • Lot W15
    • Six injection wells by QatarEnergy LNG subsurface
    • Six injection flowlines and metring skid
    • Six wellhead control panels
    • Power tie-in from Barzan
    • Substation
    • Pig receiver
    • Access road and fencing

QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 for the execution of the front-end engineering and design (feed) work on the project, as well as to prepare the EPC scope of work.

North Field LNG expansion

Meanwhile, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, continues to press forward with its North Field LNG expansion programme.

The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

EPC works on the two projects are making progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

This story has been updated. A previous version wrongly stated that bids were submitted on 13 March.


February's special report on Qatar includes

> COMMENT: Doha works to reclaim spotlight
> ECONOMY: Qatar economy rebounds alongside diplomatic activity
> BANKING: Qatar banks look to calmer waters in 2025
> UPSTREAM: QatarEnergy strives to raise gas and oil production capacity
> DOWNSTREAM: Qatar chemical projects take a step forward
> POWER & WATER: Facility E award jumpstarts Qatar’s utility projects
> CONSTRUCTION: Qatar construction shows signs of recovery
> DATABANK: Qatar maintains stable growth heading

https://image.digitalinsightresearch.in/uploads/NewsArticle/13525489/main2030.jpg
Indrajit Sen
Related Articles
  • Jedco maps next phase of Jeddah airport expansion

    22 September 2026

     

    Jeddah Airports Company (Jedco) has outlined plans for the next phase of expansion at King Abdulaziz International airport (KAIA) in Jeddah.

    The programme comprises six upcoming contractor packages spanning airside works, terminal upgrades and utilities as Jedco advances its long-term expansion plans.

    The opportunities include airfield rehabilitation; a five-year construction framework covering multiple workstreams and facility types; a Terminal 3A (T3A) package; Terminal 1 (T1) optimisation; a fuel farm; and Concourse C works.

    The packages cover terminal buildings and ancillary facilities, runways, taxiways and aprons, hangars, fuel systems, airside facilities, supporting infrastructure and utility networks.

    Tendering and award activity will be staggered over the next two years. Airfield rehabilitation is targeted for Q3 2026. The construction framework is scheduled for Q4 2026 and will run for five years.

    The T3A package is planned for Q1 2027 and will be delivered under an early contractor involvement contract. Local contractors are encouraged to bid as part of a joint venture with an experienced international partner.

    T1 optimisation is planned for Q4 2027, the fuel farm for Q2 2027, and Concourse C – currently the latest of the six milestones – for Q2 2028.

    The new packages add detail to Jedco’s wider expansion plans disclosed in 2023, when it was reported that the company would invest SR115bn ($31bn) to increase KAIA’s capacity to 114 million passengers a year, with an overall completion target of 2031.

    Jedco has recently awarded several significant contracts linked to the airport’s upgrade programme.

    In November 2024, a joint venture of local Algihaz Contracting and Turkey’s TAV was awarded a contract to rehabilitate the South Terminal to serve Umrah and Hajj pilgrims, with Singapore’s Surbana Jurong acting as consultant.

    Earlier that year, Jedco also awarded France’s Alstom a contract to increase the capacity of the Innovia automated people mover at Terminal 1, including new cars and upgrades to signalling, communications and controls.

    Surbana Jurong is expected to play a leading role in future KAIA expansion plans and is currently providing technical advisory and project management consultancy for more than 100 capital projects for Jedco, valued at over SR6bn ($1.6bn).

    These upgrades are expected to boost KAIA’s annual capacity in line with Saudi Arabia’s Vision 2030 and National Aviation Strategy, enhancing the experience for domestic travellers and millions of Hajj and Umrah pilgrims.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19877992/main.jpg
    Yasir Iqbal
  • Contractor wins $105m Medina university hospital deal

    22 September 2026

     

    Riyadh-based construction firm Al-Mansouria General Contracting Company has been awarded a SR396m ($105.6m) contract to complete the remaining construction works on the Taiba University Hospital project in Medina.

    The contract scope includes structural completion, remaining civil works, mechanical, electrical and plumbing installations, specialised clinical fit-outs and medical gas infrastructure to bring the long-stalled facility into operation.

    Located on King Khalid Road along Medina’s Third Ring Road, the teaching hospital will have a capacity of 563 beds.

    The contract duration is three years, with delivery targeted for late 2029.

    The latest award follows a prolonged procurement cycle that began more than a decade ago as part of a public budget drive to expand Saudi Arabia’s higher education infrastructure.

    The project’s first phase was initially signed in December 2011 with local firm Al-Muhaidib Contracting under a SR500m ($133.3m) contract.

    Groundbreaking for the eight-storey complex took place in July 2013. The project covers a gross floor area of more than 200,000 square metres.

    Progress stalled shortly thereafter due to reported structural delays and the reallocation of public capital budgets across the kingdom’s social infrastructure pipeline.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19870032/main.jpg
    Yasir Iqbal
  • Oman tenders Thumrait Industrial City infrastructure

    22 September 2026

     

    Oman’s Public Establishment for Industrial Estates (Madayn) has tendered an estimated RO15m ($39m) contract to develop infrastructure for Thumrait Industrial City.

    The tender was issued on 14 September, with bids due by 12 November.

    The scope covers site-wide utilities and services, including an internal road network, stormwater channels and culverts. It also includes installing sewerage and water networks, along with landscaping works.

    In addition, Madayn intends to build plug-and-play industrial units and a facilities building.

    The first phase of the development will cover about 120,000 square metres (sq m).

    Thumrait Industrial City is located in Oman’s Dhofar Governorate and spans an area of more than four million sq m.

    The project location is close to concession blocks, quarry sites and the Najd agricultural areas. It is positioned to attract industrial investments in sectors such as mining and minerals processing (including gypsum and cement), food production, and a range of light and general manufacturing activities.

    In March, Madayn said it is preparing to invest more than RO245m ($637m) to upgrade and expand infrastructure across its industrial cities between 2026 and 2030, as part of efforts to attract new investment and advance economic diversification.

    According to media reports, Madayn chief executive Dawood Bin Salim Al-Hadabi said the programme is part of an expanded, phased plan aligned with Oman Vision 2040 and the authority’s long-term Madayn 2040 strategy.

    The objective is to deepen Oman’s industrial base and spread growth across the sultanate’s governorates.

    Madayn said the pipeline comprises about 90 strategic projects to improve industrial-city infrastructure, extend serviced land and increase the overall ease of doing business for investors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19866218/main.jpg
    Yasir Iqbal
  • Kuwait halves drilling contractor pool

    22 September 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) has reduced the number of approved contractors for onshore drilling and shallow-well maintenance from 51 to 24.

    Firms that are no longer qualified include major contractors such as Italy’s Saipem, Oklahoma-based Helmerich & Payne and Houston-based Patterson-UTI Energy.

    The latest list still includes a wide range of Kuwaiti, regional and international companies, according to the latest update on its electronic system, published on 21 September 2026.

    The full list of contractors that are now qualified to participate in tenders is:

    • Burgan Company for Well Drilling, Trading & Maintenance (Kuwait)
    • Kuwait Drilling Company (Kuwait)
    • Sun Drilling Kuwait (Kuwait)
    • TDL Kuwait for Oil Rigs & Natural Gas Extraction Activities, Services and Facilities (Kuwait)
    • United Precision Drilling (Kuwait)
    • Abraj Energy Services (Oman)
    • Adnoc Drilling Company (UAE)
    • Arabian Drilling Company (Saudi Arabia)
    • Anton Oilfield Services (China)
    • China Oilfield Services (China)
    • Egyptian Drilling Company (Egypt)
    • CNPC Bohai Drilling Engineering Company (China)
    • Great Wall Drilling Company (China)
    • John Energy (India)
    • Kerui Oilfield Service (China)
    • KCA Deutag Drilling (Germany)
    • Mohammed Al-Barwani Petroleum Services (Oman)
    • Nabors Drilling International (US)
    • National Drilling & Services Company (Oman)
    • Sea & Land Drilling Contractors (Oman)
    • Sinopec International Petroleum Service Corporation (China)
    • Karamay Jianye Energy (China)
    • Modern Drilling Company (Egypt)
    • Grey Wolf Drilling International (US)

    An earlier list, which was published on 11 February, included 51 qualified companies.

    The reduction in qualified drilling contractors follows KOC’s notice on 27 April this year, informing existing qualified contractors that they would need to reapply.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19863744/main3435.jpg
    Wil Crisp
  • Abu Dhabi expects 45% emissions cut as electricity demand rises

    21 September 2026

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based Emirates Water & Electricity Company (Ewec) expects carbon emissions from power and water production to fall by more than 45% by 2035 as the UAE expands renewable energy and reverse osmosis (RO) desalination.

    The state offtaker's latest long-term system planning forecasts emissions will decline from about 42 million tonnes in 2019 to approximately 23 million tonnes in 2035.

    The reduction is expected despite annual electricity demand that is forecast to rise by about 70% in 2026-33.

    Ewec said the expansion of renewable energy and the shift towards RO desalination will be the principal drivers of the reduction.

    The company plans to increase Abu Dhabi's solar capacity to 14GW by 2030 and more than 35GW by 2035. This will be supported by up to 15GW of battery storage capacity.

    According to regional project tracker MEED Projects, Ewec has over $16bn-worth of power and water projects in the execution stage as part of its long-term procurement programme to increase renewable energy and low-carbon water production capacity.

    This includes a 5.2GW Abu Dhabi solar and battery energy storage system (bess) round-the-clock renewable energy project, as well as three 1.5GW solar photovoltaic independent power projects (IPP): Al-Ajban, Al-Khazna and Al-Zarraf.

    It also comprises the 1GW Al-Dhafra open-cycle gas turbine power plant, the 2.5GW Taweelah C combined-cycle gas turbine (CCGT) plant and a separate 400MW bess IPP.

    As previously reported, it is expected that the developer's agreement for the 3.3GW Al-Nouf 1 CCGT IPP will be signed by the end of the year, while contractors are preparing to submit bids for a separate 2.6GW power plant project in Ajman.

    The expansion of solar and battery storage is expected to reduce the system's reliance on gas-fired generation. However, gas-fired generation will continue to provide flexibility to support the system and balance intermittent renewable power output, according to Ewec. 

    The offtaker also expects RO desalination to account for more than 95% of total water production by 2035, with the procurement programme supporting the Abu Dhabi Department of Energy's Clean Energy Strategic Target 2035 for electricity production and the UAE Net Zero by 2050 Strategy.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19849749/main.jpg
    Mark Dowdall