QatarEnergy achieves strategic oil and gas goals in 2025

12 January 2026

 

QatarEnergy made significant progress towards achieving its strategic oil and gas production expansion objectives in 2025, while also firming up plans for the next phase of its mammoth North Field liquefied natural gas (LNG) programme.

The state enterprise spent almost $20bn last year on projects ranging from gas production expansion and oil output capacity building to carbon capture and sequestration, making it the strongest year for capital expenditure in Qatar’s hydrocarbon sector since 2021.

QatarEnergy announced the North Field West project – the third expansion phase of its estimated $40bn North Field LNG programme – in February 2024. However, progress on the project was initially slow, with North Field West remaining in the early planning stages for much of the year.

Momentum picked up in the second half of the year, as QatarEnergy began the prequalification process and issued tenders for various work packages related to the North Field West LNG project. Notably, the company completed the prequalification exercise for dredging works.

More importantly, QatarEnergy awarded a contract in December for the engineering, procurement, construction and installation (EPCI) of four offshore jackets and associated facilities at the giant North Field gas reserve in Qatari waters.

US-headquartered McDermott International won the contract, which is estimated to be worth about $200m. The new jackets will boost gas production from the North Field reservoirs, providing additional gas feedstock for the North Field West LNG project.

North Field LNG expansion scheme

The North Field West project will have an LNG production capacity of 16 million tonnes a year (t/y), delivered through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The project will draw feedstock from the western zone of Qatar’s offshore North Field gas reserve and is expected to increase QatarEnergy’s total LNG production capacity to 142 million t/y upon commissioning in 2030.

Meanwhile, EPCI works on the first two phases of the North Field expansion programme — North Field East and North Field South — continue to advance. These projects will raise Qatar’s LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

QatarEnergy is understood to have spent nearly $30bn on the North Field East and North Field South LNG projects, which, once fully operational, will add 48 million t/y of supply to the global LNG market.

The North Field East project aims to boost QatarEnergy’s LNG output to 110 million t/y. The $13bn main EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

In May 2023, QatarEnergy awarded the $10bn main EPC contract for the North Field South project to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company. The contract covers the EPCI of two LNG trains, each with a capacity of 7.8 million t/y.

North Field Production Sustainability

QatarEnergy’s North Field LNG expansion programme requires large volumes of gas to be pumped from the offshore North Field to feed the three phases of the estimated $40bn-plus programme. The state enterprise aims to secure these incremental gas volumes through the North Field Production Sustainability (NFPS) project.

QatarEnergy has already invested billions of dollars in EPCI works across two phases of the NFPS project since 2021. The second phase primarily involves the construction of gas compression facilities to sustain and gradually increase gas production from the North Field over the long term.

In 2025 alone, QatarEnergy subsidiary QatarEnergy LNG spent approximately $8bn on awarding contracts for two key EPCI packages under the second phase of the NFPS programme.

In March, India’s Larsen & Toubro Energy Hydrocarbon (LTEH) won the main contract for the combined 4A and 4B package, the fourth package of the second NFPS phase, estimated to be worth between $4bn and $5bn. The scope of work includes the EPCI of two large gas compression systems – CP8S and CP4N – each weighing between 25,000 and 35,000 tonnes, as well as compression platforms, flare gas platforms and other associated structures.

LTEH later subcontracted the detailed engineering and design work for the combined 4A and 4B package to Technip Energies.

In December, a consortium comprising Italian contractor Saipem and state-owned China Offshore Oil Engineering Company (COOEC) secured the EPCI contract for the COMP5 package. The contract is valued at $4bn, with Saipem’s share declared at $3.1bn.

Milan-headquartered Saipem said the contract will run for approximately five years. The scope of work includes the engineering, procurement, fabrication and installation of two compression complexes, each comprising a compression platform, living quarters platform, flare platform supporting the gas combustion system and related interconnecting bridges. Each complex will have a total weight of about 68,000 tonnes.

CO2 capture and sequestration

Last year, QatarEnergy also made a significant investment in the development of a large-scale carbon dioxide (CO₂) sequestration complex at Ras Laffan Industrial City (RLIC). Once commissioned, the facility will be capable of capturing 4.1 million t/y of CO₂ from QatarEnergy LNG’s production operations at RLIC.

South Korea’s Samsung C&T won the contract to build the Ras Laffan CO₂ sequestration facility in November, with the project estimated to be valued at between $2bn and $2.5bn.

Building oil output capacity

In addition to advancing its gas production and LNG ambitions, QatarEnergy committed substantial capital expenditure last year towards increasing oil output capacity from its offshore fields.

In August, QatarEnergy selected contractors for the EPC works on a project to maintain and increase production potential at the Bul Hanine offshore oil field. The EPC scope was divided into three main packages, with COOEC awarded the first two packages and Qatari contractor Doha Petroleum Construction Company (Dopet) selected for the third. Additionally, COOEC appointed US-based KBR to provide detailed engineering services for the first and second packages.

Separately, in September, QatarEnergy awarded the main EPC contract for a project to add a fifth natural gas liquids (NGL) train at its NGL complex in Mesaieed Industrial City. Indian contractor L&T Energy Hydrocarbon won the contract.

The project, estimated to be worth $2.5bn, aims to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.

Looking ahead, QatarEnergy is expected to award EPC contracts this year for another major project to expand oil production capacity at the ageing Maydan Mahzam offshore oil field. The company floated the main tender for the estimated $4bn-$5bn project in 2025. Contractors submitted technical bids for two key EPC packages in September and are preparing to submit commercial bids by 1 March.

The project scope includes the installation of topsides, jackets, subsea cables and umbilicals, as well as brownfield modifications to existing facilities, to maintain the field’s oil production potential over the long term.

https://image.digitalinsightresearch.in/uploads/NewsArticle/15417037/main.jpg
Indrajit Sen
Related Articles
  • Al-Maktoum airport is key to Dubai’s aviation hub status

    27 November 2026

    Commentary
    Colin Foreman
    Editor

    Dubai’s position as a global aviation hub is central to its economy, and the expansion of Al-Maktoum International airport is critical to maintaining that role.

    On 26 November, Dubai awarded AED56.5bn ($15bn) of contracts for the airport expansion, taking the total value of contracts awarded to more than AED80bn ($21.8bn). A workforce of 14,000 is working on the project, which will provide capacity for more than 260 million passengers a year when complete.

    The economic stakes are high. A study published by Emirates Group and Dubai Airports in October 2024 found that aviation accounted for 27% of Dubai’s GDP in 2023. The sector contributed AED137bn ($37.3bn) in gross value added and supported 631,000 jobs – about one in five jobs in the emirate. The study forecast that aviation’s share of GDP would rise to 32% by 2030, contributing AED196bn in gross value added and supporting 816,000 jobs.

    This year has demonstrated both the vulnerability and resilience of Dubai’s aviation model. Regional conflict has disrupted commercial air traffic across the Gulf since 28 February. Emirates Group’s profit before tax fell 66% year on year to AED4.1bn in the six months to 30 September, while Emirates carried 21.8 million passengers, down 22% on the prior-year period.

    However, the network recovered quickly. By 30 September, Emirates was operating 91% of its pre-disruption network, serving 150 airports in 78 countries and territories. Emirates SkyCargo revenue rose 52%, the fleet increased to 289 aircraft, and the airline broke ground in May on a $5.1bn maintenance facility at Al-Maktoum International airport.

    Maintaining that connectivity will require additional capacity. If aviation accounts for almost one-third of Dubai’s economy by 2030, as Emirates Group and Dubai Airports forecast, Al-Maktoum International airport will be central to the emirate’s ability to retain its position in global air travel.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21894329/main.jfif
    Colin Foreman
  • Emaar tenders Dubai Creek Harbour mall

    27 November 2026

     

    Register for MEED’s 14-day trial access 

    Dubai developer Emaar Properties has invited contractors to submit bids by 9 December for the main construction package of the Dubai Creek Harbour mall, known as Dubai Square.

    The development covers a total retail, hospitality and commercial area of 2.6 million square metres, and is scheduled to open within three years.

    Emaar unveiled Dubai Square in December 2025 as the anchor of its AED180bn ($49bn) Dubai Creek Harbour development.

    The scheme has undergone several redesigns. MEED first reported on Emaar’s plans for a major retail centre at Dubai Creek Harbour in 2016. At the time, the project was envisioned to surpass Dubai Mall as the world’s largest retail destination, though its scale and layout have since evolved.

    The mall will connect directly to the planned Dubai Creek Tower at the centre of the development.

    UK-headquartered Brewer Smith Brewer Group is the project’s lead consultant, executive architect, architect of record and structural engineer. It is also the construction supervision consultant.

    Dubai-based contractor Dutco Construction began mobilising last year for early site works.

    In March last year, MEED reported that Emaar was preparing to relaunch development of both the tower and the mall. The developer had earmarked roughly AED14bn ($3.81bn) for the two assets as part of a wider AED65bn ($18bn), five-year capital expenditure programme.

    Progress on the tower has been slower. First launched in 2015, it was promoted as the world’s tallest structure, designed to exceed the 828-metre Burj Khalifa. The original design was led by Spanish architect Santiago Calatrava and UK-based RMJM. The project stalled after concrete pile-cap works were completed in 2018.

    In 2023, Emaar founder Mohamed Alabbar confirmed design works were continuing following an international design competition. In January 2026, Alabbar stated that a tender for the redesigned tower would be issued within three months. He later said the tender would be deferred until regional geopolitical tensions ease.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21892263/main.jpg
    Yasir Iqbal
  • Contractor wins Arabian Beauty Horses Village in Qatar

    27 November 2026

     

    Qatar’s Culture Village Foundation (Katara) has awarded Qatar Trading & Contracting Group a QR574m ($158m) contract to build the Arabian Beauty Horses Village in Al-Uqdah Zone 74, in the Al-Khor area.

    The project will include supporting infrastructure and public facilities designed for Arabian show horses and equestrian operations in the Al-Uqdah district.

    Zone 74 is already an important centre for Qatar’s equestrian sector, anchored by the Al-Uqdah Equestrian Complex. The Qatar Racing & Equestrian Club began operating the complex in 2020 in coordination with Qatar’s Ministry of Culture and Sports.

    The Arabian Beauty Horses Village is part of a broader, multistage state strategy to develop Al-Uqdah, on the outskirts of Al-Khor, as Qatar’s second major equestrian hub, alongside Al-Rayyan and Al-Shaqab in Doha.

    According to UK analytics firm GlobalData, Qatar’s commercial construction sector is expected to grow at an average annual rate of 4.5% between 2025 and 2028, supported by investment in hotels, logistics facilities and data centres.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21890026/main.jpg
    Yasir Iqbal
  • King Salman airport sets new infrastructure bid deadline

    27 November 2026

     

    Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has set a 10 January deadline for bids for the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.

    The tender was issued on 26 October, with an initial bid-submission deadline of 6 December.

    The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.

    The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and part of Mohamed bin Faraj Road 5333, west of Junction 6.

    It also includes new roads, ramps, service roads and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.

    Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.

    The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.

    Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.

    Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.

    The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.

    Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.

    Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.

    The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21887157/main3955.png
    Yasir Iqbal
  • PIF secures inaugural A+ rating from S&P

    26 November 2026

    Saudi Arabia’s Public Investment Fund (PIF) has received an inaugural A+ long-term foreign and local currency issuer credit rating from S&P Global Ratings, with a stable outlook.

    The fund’s existing A-1 short-term rating from S&P is unchanged. PIF said its ratings are in line with those of Saudi Arabia.

    PIF said S&P’s assessment cited its diversified funding profile, moderate leverage and its focus on value realisation under its 2026-30 strategy. The agency also pointed to the fund’s role in driving the kingdom’s economic transformation.

    “The inaugural A+ long-term rating from S&P marks an important milestone in the continued development of PIF’s credit profile and our long-term funding plan,” said Ziyad Alfawzan, head of capital finance strategy at PIF.

    The new rating makes PIF one of a small number of sovereign wealth funds with long-term credit ratings from all three leading agencies.

    Moody’s Ratings confirmed PIF’s Aa3 long-term issuer rating and aa3 baseline credit assessment in September after a periodic review, with a stable outlook. In October, Fitch Ratings affirmed the fund’s long-term foreign and local currency issuer default ratings at A+, also with a stable outlook.

    The Moody’s rating is one notch higher than the A+ grades from S&P and Fitch.

    Debt is an increasingly important source of funding for PIF as it pays for domestic investment programmes and gigaprojects.

    The fund raised $2bn in January from a 10-year sukuk, its first debt sale of 2026. In May, it raised $7bn from a three-tranche bond, its first hard-currency public issuance since the Iran conflict disrupted regional capital markets.

    A full set of long-term ratings is likely to widen PIF’s investor base for future bond and sukuk issuance. The fund also borrows through loans and other debt instruments as part of its funding mix.

    PIF is entering what it calls the value realisation phase of its strategy, covering 2026 to 2030. Over this period, it aims to deliver sustainable financial returns while continuing to drive the diversification of the Saudi economy.


    MEED’s latest report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21868102/main.gif
    Colin Foreman