Qatar chemical projects take a step forward

20 January 2025

 

Qatar has invested tens of billions of dollars this decade in its giant North Field liquefied natural gas (LNG) expansion programme, as well as projects to increase gas production from the massive North Field offshore reserve.

Along with raising gas and LNG production capacity, state enterprise QatarEnergy has also sought to derive greater economic value from its natural gas output by allocating significant capital expenditure (capex) to ethane-based petrochemical projects.

Engineering, procurement and construction (EPC) works are progressing on the Ras Laffan petrochemicals project, which will consist of an ethane cracker with an output capacity of 2.1 million tonnes a year (t/y) of ethylene, making it the largest ethane cracker in the Middle East and one of the largest in the world. When the facility is commissioned in 2026, it will raise Qatar’s ethylene production potential by nearly 70%.

QatarEnergy and US-based Chevron Phillips Chemical (CPChem) have allocated a capex budget of $6bn to the Ras Laffan petrochemicals project, making it one of the largest chemical investments in Qatar.

Ras Laffan Petrochemicals, a 70:30 joint venture of QatarEnergy and CPChem, is the operator of the Ras Laffan project. Chevron and Phillips 66 are each 50% stakeholders in CPChem.

Ras Laffan project EPC works

QatarEnergy and CPChem signed the final investment decision agreement and awarded the two main contracts for EPC works for the Ras Laffan petrochemicals complex in January 2023.

A consortium of South Korea’s Samsung E&A and Taiwan-based CTCI Corporation won the EPC contract for the main ethylene plant. Samsung E&A is in charge of the major ethylene production facilities. Its scope of work includes furnaces, ethane (C2) hydrogenation, the hydrogen purification unit and three main compressors. CTCI is responsible for the utility infrastructure, including steam/condensate collecting and boiler feed water.

The EPC contract for the polyethylene plant was awarded to Italian contractor Maire Tecnimont, which announced the value of its contract to be $1.3bn.

Maire Tecnimont is required to execute the EPC of the main polyethylene plant, which includes two polyethylene units with a capacity of 1 million t/y and 680,000 t/y, respectively, together with the associated utilities and offsite facilities. The Italian contractor’s scope of work also covers engineering services, equipment and material supply, and construction activities up to mechanical completion.

US-headquartered industrial digitalisation services provider Emerson was awarded the main automation contract for the Ras Laffan petrochemicals project.

In November last year, the Samsung E&A and CTCI consortium secured another contract from Ras Laffan Petrochemical, worth $418m, to build the main ethylene storage plant for the upcoming facility.

Qapco petrochemicals project

Meanwhile, front-end engineering and design works continue on Qatar Petrochemical Company’s (Qapco) project to build a large-scale integrated petrochemicals production complex in Ras Laffan Industrial City (RLIC). The complex will feature propane dehydrogenation (PDH) and polypropylene (PP) production plants.

Qapco’s planned petrochemicals facility is estimated to have a production capacity of 1 million t/y of propylene, which will be converted into 1.08 million t/y of polypropylene grades, including co-polymer products. The propylene to polypropylene conversion will be done by two 540,000 t/y-capacity processing trains and achieved by adding an ethylene comonomer.

Propane and butane, sourced from units within RLIC, will be the main feedstock for the PDH and PP plants.

Qapco is expected to start the main EPC tendering process for the integrated petrochemicals production complex in the first quarter of this year.

Industrial salt project

Separately, QatarEnergy signed a tripartite memorandum of understanding in September last year between its subsidiary Mesaieed Petrochemical Holding Company (MPHC), Qatar Industrial Manufacturing Company (QIMC) and Turkiye’s Atlas Yatirim Planlama to create a new entity called Qatar Salt Products Company (QSalt).

QSalt will build a salt production plant in the Um Al-Houl area of Qatar at an estimated cost of $275m. MPHC will be the largest shareholder in QSalt with a 40% stake, while QIMC and Atlas Yatirim Planlama will hold a 30% stake each. QatarEnergy subsidiary Qapco and MPHC subsidiary Qatar Vinyl Company (QVC) will operate the facility.

Qapco is an 80:20 joint venture of Industries Qatar and France’s TotalEnergies. QatarEnergy, in turn, owns the majority 51% stake in Industries Qatar.

MPHC, in which QatarEnergy holds the majority 57.85% stake, owns a 55.2% stake in QVC.

The new plant in Um Al-Houl will produce industrial salts essential for the petrochemicals industry, along with bromine, potassium chlorides and demineralised water, which will be produced at a later stage, “contributing to product diversification and economic growth”, QatarEnergy said.

The plant will have a production capacity of 1 million t/y, and will “significantly reduce Qatar’s reliance on imported raw materials, addressing the current import of approximately 850,000 tonnes [a year] of table and industrial salts annually”.

This facility will utilise wastewater from reverse osmosis desalination units, transforming waste from desalination processes into a valuable resource.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13257580/main.gif
Indrajit Sen
Related Articles
  • UAE firm acquires majority stake in African power producer

    31 August 2026

    Abu Dhabi-based ePointZero has announced a deal to acquire a 90% stake in pan-African independent power producer Azura Power Holdings.

    The transaction will give the subsidiary of UAE investment group 2PointZero control of 752MW of operating power generation capacity across Nigeria, Senegal and Mozambique.

    The company will acquire the respective stakes held by existing shareholders Actis and Africa50 through an acquisition vehicle established with Amaya Capital, an Africa-focused investment firm based in London.

    Amaya Capital founded Azuro Power in 2010 and will retain a 10% minority stake in the company, which also has a development pipeline of more than 1.5GW of planned power projects.

    The pipeline includes expansions at existing sites, as well as new gas and renewable energy projects and battery energy storage systems.

    Azuro Power’s operating portfolio comprises the 461MW Azura-Edo power plant in Nigeria, the 116MW Tobene power plant in Senegal and the 175MW Central Termica de Ressano Garcia plant in Mozambique. The company’s operating assets generate around 10% of each country’s grid baseload power, the statement said.

    The company’s projects have received financing and support from development finance institutions including the World Bank, British International Investment, German Investment & Development Company, the US International Development Finance Corporation, the Dutch entrepreneurial development bank, the International Finance Corporation, the Multilateral Investment Guarantee Agency and France’s Proparco.

    The deal, subject to regulatory approvals and other customary closing conditions, marks ePointZero’s entry into African power generation and follows the acquisition of a 20% stake in Egypt’s Elsewedy Electric in 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19171095/main.jpg
    Mark Dowdall
  • Contract award nears for Saudi Landbridge Riyadh section

    31 August 2026

     

    Saudi Arabia Railways (SAR) is preparing to award the main construction contract for the design-and-build of the Riyadh Rail Link, a new north-to-south railway line across the capital.

    MEED understands that the commercial proposals were opened two weeks ago, with a decision expected imminently.

    SAR began the post-tender clarifications with bidders in July, as MEED reported.

    The bidders include:

    • China Civil Engineering Construction Corporation / Al-Ayuni Investment & Contracting (China/local)
    • Nesma & Partners / China Harbour Engineering Company (local/China)
    • Al-Rashid Trading & Contracting / IC Ictas Construction / Saipem (local/Turkiye/Spain)
    • Saudi Binladin Group (local)

    In June, MEED exclusively reported that contractors submitted their commercial proposals on the 30th of that month.

    The scope includes a 35-kilometre double-track line connecting SAR’s North-South Railway to the Eastern Railway network.

    Issued on 29 January, the tender also covers the procurement, construction and installation of associated infrastructure, including viaducts, civil works, utility diversions/installations, signalling systems and other related works.

    Once delivered, the Riyadh Rail Link is expected to become a key component of the Saudi Landbridge railway.

    In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and that the project would instead be delivered in several phases under a different procurement model.

    Negotiations have been under way between Saudi Arabia and China-backed investors interested in developing the scheme through a public-private partnership (PPP). Al-Malik put the project cost at about SR100bn ($26.6bn).

    Overall, it comprises more than 1,500km of new track. A core element is a 900km railway between Riyadh and Jeddah, providing the capital with direct freight access to King Abdullah Port on the Red Sea.

    Other key elements include upgrading the existing Riyadh-Dammam line, a bypass around the capital known as the Riyadh Link, and a connection between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. First announced in 2004, it was put on hold in 2010 before being revived a year later. Rights-of-way issues, route alignment and the high cost have been among the main stumbling blocks.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19161887/main.gif
    Yasir Iqbal
  • Prequalification begins for Dammam suburb boulevard PPP

    31 August 2026

    Saudi Arabia’s Ministry of Municipalities & Housing, in collaboration with Ashraq Development Company and the National Centre for Privatisation & PPP, has issued a request for qualification (RFQ) notice for the development of the King Fahd suburb boulevard project in Dammam.

    The notice was issued on 27 August, with a submission deadline of 22 October.

    The public-private partnership (PPP) project will be delivered using a design, build, finance, operate, maintain and transfer model, with a 43-year contract term.

    The project is located in Al-Bayda Governorate and features a 4 kilometre (km) mixed-use zone along a central boulevard, forming part of a larger 7.3km corridor.

    The project will be developed in two phases and span about 1 million square metres.

    According to a statement: “The private sector partner will be responsible for developing and operating the boulevard, which includes leisure and recreational facilities, public parks, entertainment venues, retail outlets, office spaces, hospitality zones, pedestrian walkways and road networks.”

    The project is the latest addition to the growing number of PPP projects in the kingdom. 

    In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.

    Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.

    In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19160560/main.jpg
    Yasir Iqbal
  • Contractors submit bids for Kuwait power transmission works

    31 August 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has received bids for two tenders covering power transmission works at the South Saad Al-Abdullah residential development.

    The first tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the third phase of the development. 

    According to sources, five contractors submitted bids on 26 August. The local Sayed Hamid Behbehani & Sons made the lowest offer of $104.2m.

    The bids include:

    • Sayed Hamid Behbehani & Sons: $104.2m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.5m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    The second PAHW tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the fourth phase of the project. 

    According to sources, five contractors also submitted bids on 26 August, with A-Ahleia Switchgear making the lowest offer of $103.3m.

    The bids include:

    • Al-Ahleia Switchgear: $103.3m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.7m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118.3m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    Both projects were initially tendered in May. As reported by MEED, PAHW previously issued addendums for both substation tenders, revising the qualification requirements for bidders.

    According to the revised requirements, contractors must be approved by Kuwait’s Ministry of Electricity, Water & Renewable Energy and have experience supplying and installing at least 10 132kV substations in Kuwait.

    The addendums also introduced requirements related to transformer and gas-insulated switchgear manufacturing approvals, as well as operational performance records for installed equipment.

    Sabah Al-Ahmad residential city

    Meanwhile, bids remain under evaluation for two 132kV underground cable tenders for the South Sabah Al-Ahmad residential development, tendered by PAHW in May.

    The first cable tender covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts in the project’s fourth phase. 

    MEED previously reported that Egytech Cables, a subsidiary of Egypt’s Elsewedy Electric, was the lowest bidder with an offer of $42.37m.

    The second cable tender covers the supply, extension and maintenance of 132kV underground cables linked to substations serving the N5, N6, N8 and N10 districts in the project’s third phase. 

    Egytech Cables submitted the lowest offer of $39.95m. TBEA Shandong Luneng Taishan Cable submitted a bid of $41.89m, along with Riyadh Cables ($42.05m) and The Contractor General Trading & Contracting ($44.97m).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19151780/main.jpg
    Mark Dowdall
  • Eni plans to drill 230 oil and gas wells in Egypt

    31 August 2026

    Italy’s Eni is planning to drill 230 new oil and gas wells in Egypt, according to a statement from the country’s Ministry of Petroleum & Mineral Resources.

    Eni’s chief executive, Claudio Descalzi, discussed his plans for exploration and development in Egypt on 25 August during a meeting with Egypt’s Prime Minister Mostafa Madbouly and the Minister of Petroleum and Mineral Resources Karim Badawi.

    During the meeting, Descalzi said that the company has plans to drill 30 exploration wells in addition to 200 development wells.

    Descalzi said his company plans to intensify its exploration and development programmes, especially in the Mediterranean and Western Sahara regions, to increase production of natural gas and crude oil.

    He said that his company plans to use the latest seismic imaging and artificial intelligence technologies as a key part of its exploration and development plans.

    In a separate statement, Eni also said that it is working with UK-headquartered BP and state-owned Egyptian General Petroleum Corporation (EGPC) to reach a final investment decision (FID) for a project to develop the major gas discovery of Denise West in Egypt’s Temsah concession.

    Eni made the discovery in February and says it holds about 2 trillion cubic feet of gas and 130,000 barrels of condensate.

    It is targeting first gas in less than two years and expects to reach FID “in the next few months”, according to its statement.

    Eni’s total investments in Egypt have reached a value of $8.5bn, according to the statement from Egypt’s Ministry of Petroleum & Mineral Resources.

    During the meeting on 25 August, Descalzi also stressed the importance of linking Cyprus’ Cronos gas field to Egyptian export infrastructure.

    In July, Eni reached the FID to develop the Cronos project in deep waters offshore Cyprus, targeting the first Cypriot gas to market in 2028.

    Production is expected to reach a plateau of 500 million standard cubic feet a day.

    In October last year, Egypt and Cyprus signed provisional agreements to connect Cyprus’ Cronos gas field to Egypt’s gas infrastructure.

    The agreements were signed by parties including Egypt’s Ministry of Petroleum and Mineral Resources, Eni, and the French oil and gas company TotalEnergies.

    Connecting the Cronos field to Egypt is expected to involve the tendering of a major subsea pipeline project.

    This will allow gas to be transported and processed in existing Zohr facilities in Egypt, then transferred and liquefied at the Damietta LNG plant for export as LNG to international markets, primarily Europe.

    At the meeting on 25 August, Descalzi said the planned project to connect the Cronos field to Egypt will be considered a model for regional cooperation in the gas sector and will enhance Egypt’s status as a regional gas hub.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19079059/main.jpg
    Wil Crisp