Qatar chemical projects take a step forward

20 January 2025

 

Qatar has invested tens of billions of dollars this decade in its giant North Field liquefied natural gas (LNG) expansion programme, as well as projects to increase gas production from the massive North Field offshore reserve.

Along with raising gas and LNG production capacity, state enterprise QatarEnergy has also sought to derive greater economic value from its natural gas output by allocating significant capital expenditure (capex) to ethane-based petrochemical projects.

Engineering, procurement and construction (EPC) works are progressing on the Ras Laffan petrochemicals project, which will consist of an ethane cracker with an output capacity of 2.1 million tonnes a year (t/y) of ethylene, making it the largest ethane cracker in the Middle East and one of the largest in the world. When the facility is commissioned in 2026, it will raise Qatar’s ethylene production potential by nearly 70%.

QatarEnergy and US-based Chevron Phillips Chemical (CPChem) have allocated a capex budget of $6bn to the Ras Laffan petrochemicals project, making it one of the largest chemical investments in Qatar.

Ras Laffan Petrochemicals, a 70:30 joint venture of QatarEnergy and CPChem, is the operator of the Ras Laffan project. Chevron and Phillips 66 are each 50% stakeholders in CPChem.

Ras Laffan project EPC works

QatarEnergy and CPChem signed the final investment decision agreement and awarded the two main contracts for EPC works for the Ras Laffan petrochemicals complex in January 2023.

A consortium of South Korea’s Samsung E&A and Taiwan-based CTCI Corporation won the EPC contract for the main ethylene plant. Samsung E&A is in charge of the major ethylene production facilities. Its scope of work includes furnaces, ethane (C2) hydrogenation, the hydrogen purification unit and three main compressors. CTCI is responsible for the utility infrastructure, including steam/condensate collecting and boiler feed water.

The EPC contract for the polyethylene plant was awarded to Italian contractor Maire Tecnimont, which announced the value of its contract to be $1.3bn.

Maire Tecnimont is required to execute the EPC of the main polyethylene plant, which includes two polyethylene units with a capacity of 1 million t/y and 680,000 t/y, respectively, together with the associated utilities and offsite facilities. The Italian contractor’s scope of work also covers engineering services, equipment and material supply, and construction activities up to mechanical completion.

US-headquartered industrial digitalisation services provider Emerson was awarded the main automation contract for the Ras Laffan petrochemicals project.

In November last year, the Samsung E&A and CTCI consortium secured another contract from Ras Laffan Petrochemical, worth $418m, to build the main ethylene storage plant for the upcoming facility.

Qapco petrochemicals project

Meanwhile, front-end engineering and design works continue on Qatar Petrochemical Company’s (Qapco) project to build a large-scale integrated petrochemicals production complex in Ras Laffan Industrial City (RLIC). The complex will feature propane dehydrogenation (PDH) and polypropylene (PP) production plants.

Qapco’s planned petrochemicals facility is estimated to have a production capacity of 1 million t/y of propylene, which will be converted into 1.08 million t/y of polypropylene grades, including co-polymer products. The propylene to polypropylene conversion will be done by two 540,000 t/y-capacity processing trains and achieved by adding an ethylene comonomer.

Propane and butane, sourced from units within RLIC, will be the main feedstock for the PDH and PP plants.

Qapco is expected to start the main EPC tendering process for the integrated petrochemicals production complex in the first quarter of this year.

Industrial salt project

Separately, QatarEnergy signed a tripartite memorandum of understanding in September last year between its subsidiary Mesaieed Petrochemical Holding Company (MPHC), Qatar Industrial Manufacturing Company (QIMC) and Turkiye’s Atlas Yatirim Planlama to create a new entity called Qatar Salt Products Company (QSalt).

QSalt will build a salt production plant in the Um Al-Houl area of Qatar at an estimated cost of $275m. MPHC will be the largest shareholder in QSalt with a 40% stake, while QIMC and Atlas Yatirim Planlama will hold a 30% stake each. QatarEnergy subsidiary Qapco and MPHC subsidiary Qatar Vinyl Company (QVC) will operate the facility.

Qapco is an 80:20 joint venture of Industries Qatar and France’s TotalEnergies. QatarEnergy, in turn, owns the majority 51% stake in Industries Qatar.

MPHC, in which QatarEnergy holds the majority 57.85% stake, owns a 55.2% stake in QVC.

The new plant in Um Al-Houl will produce industrial salts essential for the petrochemicals industry, along with bromine, potassium chlorides and demineralised water, which will be produced at a later stage, “contributing to product diversification and economic growth”, QatarEnergy said.

The plant will have a production capacity of 1 million t/y, and will “significantly reduce Qatar’s reliance on imported raw materials, addressing the current import of approximately 850,000 tonnes [a year] of table and industrial salts annually”.

This facility will utilise wastewater from reverse osmosis desalination units, transforming waste from desalination processes into a valuable resource.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13257580/main.gif
Indrajit Sen
Related Articles
  • Contractors submit revised bids for Dukhan field facilities upgrade

    6 October 2026

     

    Contractors have submitted revised proposals to QatarEnergy for a key tender to upgrade facilities at the Dukhan oil field in Qatar, about 80 kilometres west of Doha.

    Following the submission of the initial round of bids for the project on 9 August, QatarEnergy requested revised proposals from contractors, which they submitted by 27 September, sources told MEED.

    The following local contractors, among others, are understood to be bidding for the DPFU Phase 1B (Part 2) tender, according to information obtained by MEED Projects:

    • Doha Petroleum Construction Company (Dopet)
    • Galfar Al-Misnad Engineering & Contracting
    • Qatar Engineering & Construction Company (Q-con)

    QatarEnergy originally stipulated a bond validity of 150 days (until 23 December) and a bid validity of 120 days (until 23 November) for the project.

    The engineering, procurement, installation and commissioning scope covers upgrades to 56 oil manifolds, 108 gas-lift manifold slots, chemical injection systems and key pumping facilities, along with associated piping, instrumentation, control, electrical and civil works.

    The scope includes the demolition of obsolete equipment, degassing station enhancements, and full testing and handover. It also encompasses additional capacity enhancement works under Part 3, mainly the installation of new oil export and produced-water transfer pumps, along with supporting facility modifications.

    The project involves complex interfaces and shutdown-critical activities, requiring expertise in live-plant integration.

    QatarEnergy issued the tender for the DPFU Phase 1B (Part 2) project on 8 June and initially set a bid submission deadline of 26 July, later extending it to 9 August.

    Dukhan, Qatar’s first and only onshore oil field, was discovered in 1938, with oil production starting in 1939-40. The country currently produces about 1.8 million barrels a day (b/d) of crude, with the Dukhan field accounting for about 350,000 b/d.

    The Dukhan oil field covers about 80km by 8km and consists of four reservoirs: Khatiyah, Fahahil, Jaleha and Diyab. The first three are oil reservoirs. The more recently developed Diyab reservoir contains non-associated gas and is estimated to hold around 2 billion barrels of crude oil reserves. Diyab lies on Dukhan’s southern flank.

    ALSO READ: QatarEnergy selects contractors for offshore oil field expansion
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20306273/main5440.jpg
    Indrajit Sen
  • Dubai issues PMC tender for four stormwater projects

    6 October 2026

     

    Dubai Municipality has invited consultants to bid for a contract to provide construction supervision services for four stormwater projects.

    The bid submission deadline is 29 October.

    All four projects are part of the municipality’s Tasreef programme, intended to increase Dubai’s rainwater drainage capacity by 700% by 2033 and provide capacity for the emirate’s needs for the next 100 years.

    The tender for TF-06-S1 Supervision of Stormwater Drainage System Projects – Package 4 was issued on 6 October.

    The consultancy covers the following projects:

    • TF-06-C1: Construction of a stormwater pond connecting Al-Maktoum Airport and Dubai South
    • TF-06-C2: Construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
    • TF-07-C1: Construction of a stormwater drainage system on Sheikh Zayed Bin Hamdan Road connecting developers
    • TF-24-C1: Connecting developers’ areas to the stormwater networks in Dubailand 

    In documents seen by MEED, the municipality said it will require a dedicated supervision team for each project.

    The consultancy will cover construction supervision, including the deployment of resident engineers, civil engineers, inspectors, quantity surveyors, land surveyors and planning engineers. Mechanical engineers will also be required, along with health and safety personnel and NOC engineers, depending on the project. 

    TF-07-C1 is the same strategic stormwater drainage project that Dubai Municipality recently tendered for construction, with contractors preparing to submit bids on 22 October.

    The project covers more than 100 million square metres between Sheikh Mohammed Bin Zayed Road and Emirates Road, and from Expo Road to Dubailand.

    It will provide stormwater infrastructure and service connections for more than 20 private developers and Al-Yalayis 5, as well as supporting major roads in the Jebel Ali area. The construction scope includes a major gravity drainage system with pipeline diameters of up to 3,000mm.

    TF-24-C1 is one of three water infrastructure tenders issued by the municipality in August, as reported by MEED. The project will connect developers’ areas in Dubailand to the stormwater network. It includes 18 kilometres (km) of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.

    Bidding for the engineering, procurement and construction contract was recently extended to 1 October, with Nael Construction & Contracting and Al-Nasr Contracting Company among those expected to make an offer for the project.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20305174/main.jpg
    Mark Dowdall
  • Aramco nears contract award for Jafurah fifth expansion phase

    6 October 2026

     

    Saudi Aramco is believed to be close to awarding the main contract for a major project representing the fifth expansion phase of the Jafurah unconventional gas development programme in Saudi Arabia.

    The main scope of work for the fifth expansion phase of Jafurah involves the engineering, procurement and construction (EPC) of three gas compression plants at the gas basin in the kingdom’s Eastern Province. Each plant will be capable of processing up to 200 million cubic feet a day (cf/d).

    Indian contractor Larsen & Toubro Energy Hydrocarbon (L&TEH) is the favourite to win the main EPC contract, according to sources.

    “Negotiations between Aramco and L&T have reached an advanced stage and the [Indian] contractor is now in pole position to clinch the deal,” one source told MEED.

    MEED previously reported that China Petroleum Engineering & Construction Company (CPECC) was in a favourable position to secure the main EPC contract for the Jafurah fifth expansion phase, based on Aramco’s initial evaluation of proposals. The situation remained subject to change as Aramco negotiated with the project’s other bidders, MEED reported in August.

    Aramco set 19 July as the final deadline for proposals, and contractors submitted their bids by that date, MEED previously reported.

    ALSO READ: Aramco receives interest for major gas processing plant

    The Saudi energy giant is understood to have issued the main EPC tender for the project in the first quarter of this year.

    Aramco issued a solicitation of interest for the Jafurah fifth expansion phase in mid-November, with contractors submitting responses by 30 November, MEED previously reported.

    UK-headquartered Wood Group has carried out the front-end engineering and design for the project.

    The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning about 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.

    Aramco recently brought the greenfield Jafurah gas processing plant online, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.

    The company previously stated that it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane and 630,000 barrels a day (b/d) of high-value liquids by 2030.

    Aramco has said that its unconventional gas programme, at peak production, is expected to generate electricity equivalent to displacing 500,000 b/d of oil.

    Jafurah gas development phases

    Alongside nearing an EPC contract award decision for the fifth expansion phase at Jafurah, MEED also recently reported that Aramco had completed the solicitation of interest process with contractors for the unconventional gas programme’s sixth phase.

    The main scope of work on the Jafurah sixth expansion phase is similar to the fifth phase, and involves the EPC of three gas compression plants at the giant gas reserve, each with an output capacity of 200 million cf/d.

    Aramco also kicked off EPC works on the Jafurah fourth expansion phase in the second quarter of the year.

    MEED reported in April that Aramco had selected Mumbai-headquartered L&TEH as the main contractor for the fourth phase, which sources estimate could be valued at about $1.5bn.

    The main scope of work on Jafurah’s fourth expansion phase involves the EPC of two gas compression trains at the gas basin. Each plant will be able to process up to 200 million cf/d.

    EPC work on the third phase of the Jafurah unconventional gas development programme is also advancing.

    In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for phase three. The contract is estimated at $2.24bn.

    The objective of the third expansion phase is similar to that of the fourth phase. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.

    The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants, and installing other utilities units, piping systems and safety equipment.

    The selection of contractors for the third expansion phase came within weeks of Aramco officially awarding EPC contracts for the second phase, which aims to raise the field’s processing potential to up to 2 billion cf/d of raw gas.

    Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.

    The EPC scope of work for that project involves the construction of gas compression facilities and associated pipelines, and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.

    The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:

    • Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
    • Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
    • Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
    • Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
    • Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
    • Riyas NGL package 6 – site preparation works – $107m: Mofarreh Alharbi & Partners (Saudi Arabia)
    • Riyas NGL package 9 – temporary construction facilities – $80m: Mofarreh Alharbi & Partners

    Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.

    In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.

    The Jafurah programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.

    Aramco completed an $11bn lease-and-leaseback deal in late October 2025 for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.

    Under the transaction, a newly formed subsidiary, Jafurah Midstream Gas Company (JMGC), will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids fractionation facility.

    After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.

    Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, the Arab Energy Fund and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20299556/main3638.jpg
    Indrajit Sen
  • Joint venture wins Riyadh data centre construction deal

    6 October 2026

     

    Register for MEED’s 14-day trial access 

    Egyptian contractor Hassan Allam Construction and India’s Sterling & Wilson have won an estimated SR750m ($200m) contract to build the first phase of a data centre project in Riyadh.

    The first phase will have an IT load capacity of 16.2MW, with overall capacity reaching 50MW in the second phase.

    The scope includes civil, architectural, and mechanical, electrical and plumbing (MEP) works, infrastructure works and other associated works.

    Upon completion of both phases, the facility will comprise one 5MW standard-density hall and four high-density halls, each rated at 11.2MW.

    Saudi Arabian artificial intelligence (AI) firm Humain and Center3 – the digital infrastructure subsidiary of local telecom company STC Group – are jointly developing the project.

    The first phase is scheduled to take 16 months.

    In December last year, Center3 and Humain partnered to develop and operate AI-focused data centres across Saudi Arabia, with a planned capacity of up to 1GW.

    The partners said the first phase will deliver up to 250MW of capacity, designed for high-density AI workloads and large-scale model training.

    The venture combines Center3’s data centre operations and regional connectivity with Humain’s full-stack AI capabilities, with the latter responsible for aligning facility design with advanced compute requirements and future architectures.

    The companies said the programme will deliver purpose-built facilities engineered for high power density, low latency and resilient operations, to support large language models and other mission-critical AI applications.

    They added that the initial schemes will serve as a template for subsequent rollouts as capacity scales towards the 1GW target.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20298893/main.jpg
    Yasir Iqbal
  • Chevron signs Egypt oil and gas exploration deal

    6 October 2026

    State-owned Egyptian Natural Gas Holding Company (Egas) and US-headquartered Chevron have signed an agreement related to oil and gas exploration in Egypt’s offshore Lotus concession.

    Under the agreement, Chevron will invest at least $88m in exploration activities within the concession, according to a statement from Egypt’s Ministry of Petroleum & Mineral Resources.

    Chevron has agreed to drill two deepwater exploration wells and to reprocess 3D seismic data for the concession.

    Egypt’s Ministry of Petroleum & Mineral Resources said the agreement was part of the ministry’s “efforts to expand exploration activities and unlock new areas for petroleum investments”.

    It also said that the deal reflected Chevron’s “commitment to pumping new investments into exploration activities in Egypt”.

    In August, Egypt’s Minister of Petroleum and Mineral Resources, Karim Badawi, presented the ministry’s five-year production strategy, which aims to double Egypt’s oil and condensate output while strengthening the country’s position as a regional hub for petroleum product trading and gas liquefaction.

    Egypt has been working towards this goal by forging a range of new deals with international oil companies.

    Chevron has offshore exploration and development rights for several Egyptian concessions, including Nargis, North El-Dabaa, North West Atoll, North Simian and North Cleopatra, where it partners with Shell.

    In April, Egypt’s cabinet approved a draft version of the Lotus concession agreement between Egas and Chevron during a meeting chaired by Prime Minister Mostafa Madbouly.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20298172/main.jpeg
    Wil Crisp