Qatar chemical projects take a step forward
20 January 2025

Qatar has invested tens of billions of dollars this decade in its giant North Field liquefied natural gas (LNG) expansion programme, as well as projects to increase gas production from the massive North Field offshore reserve.
Along with raising gas and LNG production capacity, state enterprise QatarEnergy has also sought to derive greater economic value from its natural gas output by allocating significant capital expenditure (capex) to ethane-based petrochemical projects.
Engineering, procurement and construction (EPC) works are progressing on the Ras Laffan petrochemicals project, which will consist of an ethane cracker with an output capacity of 2.1 million tonnes a year (t/y) of ethylene, making it the largest ethane cracker in the Middle East and one of the largest in the world. When the facility is commissioned in 2026, it will raise Qatar’s ethylene production potential by nearly 70%.
QatarEnergy and US-based Chevron Phillips Chemical (CPChem) have allocated a capex budget of $6bn to the Ras Laffan petrochemicals project, making it one of the largest chemical investments in Qatar.
Ras Laffan Petrochemicals, a 70:30 joint venture of QatarEnergy and CPChem, is the operator of the Ras Laffan project. Chevron and Phillips 66 are each 50% stakeholders in CPChem.
Ras Laffan project EPC works
QatarEnergy and CPChem signed the final investment decision agreement and awarded the two main contracts for EPC works for the Ras Laffan petrochemicals complex in January 2023.
A consortium of South Korea’s Samsung E&A and Taiwan-based CTCI Corporation won the EPC contract for the main ethylene plant. Samsung E&A is in charge of the major ethylene production facilities. Its scope of work includes furnaces, ethane (C2) hydrogenation, the hydrogen purification unit and three main compressors. CTCI is responsible for the utility infrastructure, including steam/condensate collecting and boiler feed water.
The EPC contract for the polyethylene plant was awarded to Italian contractor Maire Tecnimont, which announced the value of its contract to be $1.3bn.
Maire Tecnimont is required to execute the EPC of the main polyethylene plant, which includes two polyethylene units with a capacity of 1 million t/y and 680,000 t/y, respectively, together with the associated utilities and offsite facilities. The Italian contractor’s scope of work also covers engineering services, equipment and material supply, and construction activities up to mechanical completion.
US-headquartered industrial digitalisation services provider Emerson was awarded the main automation contract for the Ras Laffan petrochemicals project.
In November last year, the Samsung E&A and CTCI consortium secured another contract from Ras Laffan Petrochemical, worth $418m, to build the main ethylene storage plant for the upcoming facility.
Qapco petrochemicals project
Meanwhile, front-end engineering and design works continue on Qatar Petrochemical Company’s (Qapco) project to build a large-scale integrated petrochemicals production complex in Ras Laffan Industrial City (RLIC). The complex will feature propane dehydrogenation (PDH) and polypropylene (PP) production plants.
Qapco’s planned petrochemicals facility is estimated to have a production capacity of 1 million t/y of propylene, which will be converted into 1.08 million t/y of polypropylene grades, including co-polymer products. The propylene to polypropylene conversion will be done by two 540,000 t/y-capacity processing trains and achieved by adding an ethylene comonomer.
Propane and butane, sourced from units within RLIC, will be the main feedstock for the PDH and PP plants.
Qapco is expected to start the main EPC tendering process for the integrated petrochemicals production complex in the first quarter of this year.
Industrial salt project
Separately, QatarEnergy signed a tripartite memorandum of understanding in September last year between its subsidiary Mesaieed Petrochemical Holding Company (MPHC), Qatar Industrial Manufacturing Company (QIMC) and Turkiye’s Atlas Yatirim Planlama to create a new entity called Qatar Salt Products Company (QSalt).
QSalt will build a salt production plant in the Um Al-Houl area of Qatar at an estimated cost of $275m. MPHC will be the largest shareholder in QSalt with a 40% stake, while QIMC and Atlas Yatirim Planlama will hold a 30% stake each. QatarEnergy subsidiary Qapco and MPHC subsidiary Qatar Vinyl Company (QVC) will operate the facility.
Qapco is an 80:20 joint venture of Industries Qatar and France’s TotalEnergies. QatarEnergy, in turn, owns the majority 51% stake in Industries Qatar.
MPHC, in which QatarEnergy holds the majority 57.85% stake, owns a 55.2% stake in QVC.
The new plant in Um Al-Houl will produce industrial salts essential for the petrochemicals industry, along with bromine, potassium chlorides and demineralised water, which will be produced at a later stage, “contributing to product diversification and economic growth”, QatarEnergy said.
The plant will have a production capacity of 1 million t/y, and will “significantly reduce Qatar’s reliance on imported raw materials, addressing the current import of approximately 850,000 tonnes [a year] of table and industrial salts annually”.
This facility will utilise wastewater from reverse osmosis desalination units, transforming waste from desalination processes into a valuable resource.
Exclusive from Meed
-
Drilling resumes at Iraq’s Akkas field8 October 2026
-
Neom extends bid deadline for Oxagon wastewater plant8 October 2026
-
Syria seeks interest for $1.16bn Euphrates dam7 October 2026
-
Arada launches UAE construction arm with Roberts7 October 2026
-
Expo Riyadh sets October deadline for Saudi Arabia pavilion7 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Drilling resumes at Iraq’s Akkas field8 October 2026

Drilling has resumed as part of the project to further develop Iraq’s Akkas gas field, according to industry sources.
In March, MEED reported that development of the field had been disrupted by security issues related to the US and Israel’s war with Iran.
Activity at the project site had been significantly reduced due to security concerns, which led to the evacuation of most non-Iraqi workers.
Now, the project is progressing and drilling at the field is ongoing, sources said.
One source said: “Many of the major issues that stopped drilling at the site have been dealt with in various ways, and the development of the field is proceeding.”
Iraq held a ceremony in January to mark the start of drilling operations under the current phase of development. In July of the previous year, the Iraqi Oil Ministry announced a contract with US-based oilfield services provider SLB to develop the field. Under the agreement, SLB is drilling wells to raise initial output to 100 million cubic feet a day (cf/d), with a long-term production target of 400 million cf/d.
The contract with SLB replaced a previous deal with Ukraine-based Ukrzemresurs, which has been terminated.
It also covers the construction of surface infrastructure and pipelines to connect Akkas to central processing units.
The gas produced at Akkas will fuel the Anbar combined-cycle power plant, which the Electricity Ministry is building.
Akkas gas field development
Located in western Anbar province, Akkas holds an estimated 5.6 trillion cubic feet of proven natural gas reserves. The field was discovered in 1992 and entered initial production in 1993, but efforts to develop it commercially have faced repeated delays.
Development rights were originally awarded to a consortium of South Korea’s Kogas and Kazakhstan’s KazMunaiGas (KMG) during Iraq’s third licensing round in 2010. After KMG withdrew, Kogas took over as sole operator under revised contractual terms before work was subsequently halted.
In April 2024, the Oil Ministry signed an agreement with Ukraine’s Ukrzemresurs targeting 100 million cf/d within two years and 400 million cf/d within four years. However, the deal faced strong domestic political resistance.
Iraq’s parliamentary Oil and Gas Committee opposed the award, with committee member Ali Al-Mashkour telling Shafaq News Agency: “This contract involves a great waste of Iraq’s wealth, and there will be a waste of Iraq’s oil, and this confirms that Iraq is once again failing to choose reputable companies to work with in the most important economic field in the country.”
He added: “We will work to uncover and expose the suspicions in this contract during the next stage, especially since this contract was made by some representatives for specific interests, which we will reveal soon with evidence.”
The deal was subsequently terminated, paving the way for the current contract with SLB.
The development of Akkas is central to Baghdad’s broader ambition to transition from a net gas importer into an exporter. Iraq remains heavily dependent on gas imports from Iran to meet domestic electricity demand. Both the US and Saudi Arabia have backed Iraq’s efforts to develop non-associated gas fields to reduce its economic and energy dependence on Tehran.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20366494/main5816.jpg -
Neom extends bid deadline for Oxagon wastewater plant8 October 2026

Neom has extended the bid submission deadline for a contract to build a wastewater treatment plant for Oxagon, its industrial cluster.
According to a source, the new deadline is 25 October. The original deadline was 2 October.
Enowa, Neom’s energy and water utility, is tendering the contract.
The industrial wastewater treatment package will have an initial capacity of 35,000 cubic metres a day (cm/d), supplied in modular trains of 5,000 cm/d each. A separate sanitary wastewater treatment package will have a capacity of 1,000 cm/d.
The contract is structured as a design-build-operate project and covers the supply, installation and commissioning of industrial and sanitary wastewater treatment packages, as well as three years of operation and maintenance.
According to sources, local contractor Alfanar, Beijing-based PowerChina and France-based Veolia are among the companies preparing bids.
The project follows an earlier tender for the Oxagon Village Water Recycling Plant, which was cancelled despite contractors submitting bids in 2024.
MEED reported at the time that PowerChina, Alfanar and Cairo-headquartered Orascom had submitted bids for that project.
The earlier scheme included truck-receiving facilities, pretreatment, biological treatment using food chain reactor technology, tertiary treatment, sludge handling and recycled-water storage.
The latest procurement appears to take a reworked approach to wastewater treatment at Oxagon Industrial Quarter. It replaces the previous engineering, procurement and construction scheme with an interim modular and demountable facility.
The plant is designed to provide “interim wastewater treatment” capacity for Oxagon Industrial Quarter as industrial development progresses.
As MEED understands, this includes treatment systems that can be installed and subsequently removed or relocated as requirements at Oxagon evolve. The plant can be expanded to a maximum capacity of 45,000 cm/d.
The tender documents also state that Neom may consider export credit agency (ECA) financing for the project. The strength of bidders’ ECA financing proposals will form part of the commercial evaluation.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20347018/main.jpg -
Syria seeks interest for $1.16bn Euphrates dam7 October 2026
Register for MEED’s 14-day trial access
Syria’s Ministry of Energy has invited expressions of interest (EoIs) for the development of the Halabiyeh-Zalabiyeh dam project on the Euphrates River.
The project has an indicative total cost of $1.16bn, according to the ministry’s EoI document. This includes $433.7m for the dam and hydropower plant and $729.6m for the pumped-storage power plant (PSP).
The scheme includes an 81MW hydroelectric power plant and a pumped-storage facility with a capacity of up to 1,200MW. The project will also include the construction of the dam and associated water-storage infrastructure.
The ministry seeks interest from qualified local and international companies, investors and other entities. Interested parties can participate in studies, design, financing, construction, and operation and maintenance of the project.
The ministry is considering several potential development structures, including build-own-operate-transfer, build-operate-transfer and public-private partnership models, as well as an engineering, procurement and construction (EPC) structure. It has said it is also open to proposals covering consultancy and financing services.
The EoI covers several stages, including pre-feasibility and feasibility studies, financing and bankability studies, detailed and executive design, EPC execution, and operation and maintenance.
The technical specifications envisage a 23-metre-high dam with a reservoir storage capacity of about 219 million cubic metres.
The hydropower plant will have three generating units, while the 1,200MW PSP will have 3.5 hours of storage capacity and four reversible units.
The deadline for submitting EoIs is 10 November, with enquiries accepted until 26 October.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20336025/main.jpg -
Arada launches UAE construction arm with Roberts7 October 2026
Register for MEED’s 14-day trial access
UAE developer Arada has integrated Australian contractor Roberts into the UAE market as part of its wider business strategy.
Arada acquired Roberts in 2025 after entering the Australian market. The tier-one contractor delivers projects in the healthcare, education, commercial, residential, hospitality, industrial, life sciences and defence sectors.
At the time of the acquisition, Arada said it planned to invest about $20m in Roberts. The investment is intended to give the developer greater control over the delivery of its Australian projects and support Roberts’ expansion into markets including the UAE.
Arada has said it could invest up to $100m in Roberts’ expansion into new sectors and markets. The company is targeting $1bn in annual revenue from Roberts by 2028.
Roberts has established a UAE office, with a head office team already in place. Arada said the contractor’s capabilities will support the delivery of its high-rise residential and social infrastructure projects.
The contractor’s first UAE project will be phase two of Arada Central Business District, a commercial development within Aljada in Sharjah. Arada is developing the AED35bn ($9.5bn) mixed-use project.
Roberts is also providing preconstruction services for several Arada projects in Dubai and Sharjah, ahead of starting site work.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20334926/main.jpg -
Expo Riyadh sets October deadline for Saudi Arabia pavilion7 October 2026

Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, has set a deadline of 25 October for bids for a contract to build the Saudi Arabia pavilion.
The tender was issued on 19 May, with an initial bid submission deadline of 26 August.
The pavilion is a major asset located within the KSA District on the eastern side of the Expo 2030 Riyadh masterplan, in the Loop of Nations district.
Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.
Last month, MEED reported that ERC had received contractor interest on 14 September for a contract to design and build a convention centre in the site’s Collaboration District.
ERC also tendered a contract to deliver the Souq areas within the Expo site, as MEED exclusively reported on 8 September.
These areas are divided into five precincts, with a total development area of about 300,000 square metres.
Also in September, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to construct a new metro station serving the Expo 2030 site.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle (EV) charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.
That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, as well as EV charging stations.
The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated north of the Saudi capital, the site will be near the future King Salman International airport and will provide direct access to Riyadh landmarks.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDFIndustry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.
Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:
> AGENDA: Oxagon takes centre stage at Neom> MARKET FOCUS: Saudi projects hold steady> INDUSTRY REPORT: MEED’s 2026 GCC power developer ranking> LEADERSHIP: The future city does not need to hang above the groundTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/20334856/main.jpg