Qatar chemical projects take a step forward

20 January 2025

 

Qatar has invested tens of billions of dollars this decade in its giant North Field liquefied natural gas (LNG) expansion programme, as well as projects to increase gas production from the massive North Field offshore reserve.

Along with raising gas and LNG production capacity, state enterprise QatarEnergy has also sought to derive greater economic value from its natural gas output by allocating significant capital expenditure (capex) to ethane-based petrochemical projects.

Engineering, procurement and construction (EPC) works are progressing on the Ras Laffan petrochemicals project, which will consist of an ethane cracker with an output capacity of 2.1 million tonnes a year (t/y) of ethylene, making it the largest ethane cracker in the Middle East and one of the largest in the world. When the facility is commissioned in 2026, it will raise Qatar’s ethylene production potential by nearly 70%.

QatarEnergy and US-based Chevron Phillips Chemical (CPChem) have allocated a capex budget of $6bn to the Ras Laffan petrochemicals project, making it one of the largest chemical investments in Qatar.

Ras Laffan Petrochemicals, a 70:30 joint venture of QatarEnergy and CPChem, is the operator of the Ras Laffan project. Chevron and Phillips 66 are each 50% stakeholders in CPChem.

Ras Laffan project EPC works

QatarEnergy and CPChem signed the final investment decision agreement and awarded the two main contracts for EPC works for the Ras Laffan petrochemicals complex in January 2023.

A consortium of South Korea’s Samsung E&A and Taiwan-based CTCI Corporation won the EPC contract for the main ethylene plant. Samsung E&A is in charge of the major ethylene production facilities. Its scope of work includes furnaces, ethane (C2) hydrogenation, the hydrogen purification unit and three main compressors. CTCI is responsible for the utility infrastructure, including steam/condensate collecting and boiler feed water.

The EPC contract for the polyethylene plant was awarded to Italian contractor Maire Tecnimont, which announced the value of its contract to be $1.3bn.

Maire Tecnimont is required to execute the EPC of the main polyethylene plant, which includes two polyethylene units with a capacity of 1 million t/y and 680,000 t/y, respectively, together with the associated utilities and offsite facilities. The Italian contractor’s scope of work also covers engineering services, equipment and material supply, and construction activities up to mechanical completion.

US-headquartered industrial digitalisation services provider Emerson was awarded the main automation contract for the Ras Laffan petrochemicals project.

In November last year, the Samsung E&A and CTCI consortium secured another contract from Ras Laffan Petrochemical, worth $418m, to build the main ethylene storage plant for the upcoming facility.

Qapco petrochemicals project

Meanwhile, front-end engineering and design works continue on Qatar Petrochemical Company’s (Qapco) project to build a large-scale integrated petrochemicals production complex in Ras Laffan Industrial City (RLIC). The complex will feature propane dehydrogenation (PDH) and polypropylene (PP) production plants.

Qapco’s planned petrochemicals facility is estimated to have a production capacity of 1 million t/y of propylene, which will be converted into 1.08 million t/y of polypropylene grades, including co-polymer products. The propylene to polypropylene conversion will be done by two 540,000 t/y-capacity processing trains and achieved by adding an ethylene comonomer.

Propane and butane, sourced from units within RLIC, will be the main feedstock for the PDH and PP plants.

Qapco is expected to start the main EPC tendering process for the integrated petrochemicals production complex in the first quarter of this year.

Industrial salt project

Separately, QatarEnergy signed a tripartite memorandum of understanding in September last year between its subsidiary Mesaieed Petrochemical Holding Company (MPHC), Qatar Industrial Manufacturing Company (QIMC) and Turkiye’s Atlas Yatirim Planlama to create a new entity called Qatar Salt Products Company (QSalt).

QSalt will build a salt production plant in the Um Al-Houl area of Qatar at an estimated cost of $275m. MPHC will be the largest shareholder in QSalt with a 40% stake, while QIMC and Atlas Yatirim Planlama will hold a 30% stake each. QatarEnergy subsidiary Qapco and MPHC subsidiary Qatar Vinyl Company (QVC) will operate the facility.

Qapco is an 80:20 joint venture of Industries Qatar and France’s TotalEnergies. QatarEnergy, in turn, owns the majority 51% stake in Industries Qatar.

MPHC, in which QatarEnergy holds the majority 57.85% stake, owns a 55.2% stake in QVC.

The new plant in Um Al-Houl will produce industrial salts essential for the petrochemicals industry, along with bromine, potassium chlorides and demineralised water, which will be produced at a later stage, “contributing to product diversification and economic growth”, QatarEnergy said.

The plant will have a production capacity of 1 million t/y, and will “significantly reduce Qatar’s reliance on imported raw materials, addressing the current import of approximately 850,000 tonnes [a year] of table and industrial salts annually”.

This facility will utilise wastewater from reverse osmosis desalination units, transforming waste from desalination processes into a valuable resource.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13257580/main.gif
Indrajit Sen
Related Articles
  • Parsons wins role on Elon Musk-backed Dubai Loop project

    4 May 2026

    US-based Parsons Corporation has been appointed to deliver programme management services for the Dubai Loop transportation system.

    The contract was awarded by Elon Musk-backed firm The Boring Company, which signed a construction agreement with Dubai’s Roads & Transport Authority (RTA) in February.

    Parsons’ scope of work includes independent design verification, stakeholder management, permitting and no-objection certificate (NOC) support, and multidisciplinary design reviews for the project’s first phase.

    The first phase comprises a 6.4-kilometre route with four stations, linking the Dubai International Financial Centre (DIFC) and Dubai Mall.

    Stations will be located at DIFC 2, ICD Brookfield Place, Dubai Mall Zabeel Parking and Burj Khalifa.

    The first phase is expected to cost about AED565m ($154m) and to be delivered within one year after design work and other preparations are completed. Tunnelling is expected to begin in the second half of this year.

    Next phase

    The second phase will connect Dubai World Trade Centre and DIFC with Business Bay.

    The tunnels will extend up to 22km and include 19 stations.

    The total cost across both phases is expected to be around AED2bn ($545m), with completion scheduled within three years.

    The pilot route is expected to serve around 13,000 passengers a day, while the full route is projected to have a capacity of about 30,000 passengers a day.

    The RTA and The Boring Company signed a memorandum of understanding on the sidelines of the World Governments Summit in Dubai in February last year to explore the development of the Dubai Loop transportation system.

    The Dubai Loop is expected to be similar to The Boring Company’s Las Vegas Convention Centre (LVCC) Loop project. The LVCC Loop is a 2.7km underground tunnel system that connects different convention centre halls, reducing walking time across the site to about two minutes.

    The LVCC Loop has been in operation since 2021. It uses Tesla Model 3 cars to carry passengers between five stations. The Boring Company began construction in November 2019 at an estimated cost of $49m.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16672074/main.jpg
    Yasir Iqbal
  • Humain tenders infrastructure for 6GW data centre campus

    4 May 2026

    Saudi artificial intelligence (AI) infrastructure company Humain, owned by the Public Investment Fund (PIF), has issued a tender inviting firms to develop infrastructure for its planned 6GW hyperscale AI data centre campus in Riyadh.

    The project will be delivered on an early contractor involvement (ECI) basis. Under the ECI process, selected contractors are required to submit methodologies and design proposals, after which one team will be selected to deliver the construction works.

    Firms have until 8 May to submit proposals.

    The development will be built on a 24-square-kilometre site in the Al-Saad area in east Riyadh. It will be delivered in two phases across six plots, each with a capacity of 1GW.

    The scope of infrastructure work covers:

    • Construction of 380kV/132kV/33kV electrical distribution network, two substations with a capacity of 500MVA and 200MVA, bulk supply point (2,000MVA)
    • Water network and fire protection systems
    • Sewage treatment plant and wastewater network
    • Stormwater systems
    • Roads
    • Underground cable and fibre optic networks
    • Landscaping works

    The client is being supported by Canadian engineering firm Hatch, France’s Egis and US-based firm JLL.

    Humain was launched in May last year to operate and invest across the AI value chain.

    Humain is building full-stack AI capabilities across four core areas: next-generation data centres, hyper-performance infrastructure and cloud platforms, and advanced AI models, including Allam.

    Also in May 2025, Humain signed preliminary deals with US chipmakers AMD and Nvidia to build multibillion-dollar advanced digital infrastructure in the kingdom.

    AMD said it will invest up to $10bn to deploy 500MW of AI compute capacity in Saudi Arabia over the next five years.

    In October, PIF and Saudi Aramco signed a non-binding term sheet setting out key terms under which Aramco would acquire a minority stake in Humain, with PIF retaining majority ownership.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16671267/main.jpg
    Yasir Iqbal
  • Abu Dhabi selects consortium for 2.5GW Taweelah C IPP

    4 May 2026

     

    Register for MEED’s 14-day trial access 

    A consortium of Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore) has been selected to develop the Taweelah C independent power producer (IPP) project in Abu Dhabi.

    The consortium will sign a power purchase agreement (PPA) in mid-May, a source told MEED.

    The combined-cycle gas turbine (CCGT) plant will have a capacity of 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.

    It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction (EPC) contractor.

    Last September, MEED reported that state offtaker Emirates Water & Electricity Company (Ewec) had received three bids for the facility.

    The bidders included:

    • Al-Jomaih Energy & Water Company / Sembcorp Industries
    • Sumitomo Corporation (Japan) / Korea Overseas Infrastructure & Urban Development Corporation / Korean Midland Power
    • Korea Western Power Company / Etihad Water & Electricity (UAE) / Kyuden International (Japan)

    At the time, Mohamed Al-Marzooqi, chief asset development and management officer at Ewec, said the bids would make Taweelah C “one of the lowest tariff CCGT projects in the region”.

    The carbon-capture-ready facility had been scheduled to begin commercial operations in the fourth quarter of 2028.

    This was based on the initial timeline for a PPA to be signed in the fourth quarter of 2025.

    Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.

    Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared to 2019.

    Ewec is also expanding its low-carbon water desalination capacity, with the Taweelah reverse osmosis (RO) plant already operating as the world’s largest RO facility and additional projects, such as the Mirfa 2 RO and Shuweihat 4 RO, under way.

    By 2030, it expects 95% of Abu Dhabi’s installed water capacity to come from RO technology.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670622/main0858.jpg
    Mark Dowdall
  • Dubai launches Blue Line metro tunnelling works

    4 May 2026

    Dubai has announced the launch of tunnelling works for the Dubai Metro Blue Line extension project.

    In a post on X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President, Prime Minister and Ruler of Dubai, announced the start of operations of the tunnel boring machine (TBM), which the Roads & Transport Authority (RTA) has named ‘Al-Wugeisha’.

    The TBM is 163 metres long, weighs more than 2,000 tonnes and will operate around the clock. The post added that its average excavation rate ranges from 13 to 17 metres a day.

    The Blue Line will connect the existing Red and Green lines. It will be 30 kilometres (km) long, with 15.5km underground and 14.5km above ground.

    The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.

    In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project to a consortium comprising Turkiye’s Limak Holding and Mapa Group, along with the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).

    The consortium is responsible for all civil works, electromechanical works, rolling stock and rail systems. After completing the project, it will assist with maintenance and operations for an initial three-year period.

    According to an official statement, the Blue Line will have a capacity of 46,000 passengers an hour in both directions.

    The project is scheduled for completion in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670584/main.jpeg
    Yasir Iqbal
  • Firms submit Jeddah distribution centre bids

    4 May 2026

     

    Contractors submitted bids on 26 April for an estimated SR140m ($37m) contract to build a distribution centre in Jeddah.

    Saudi Logistics Services Company (SAL) launched the tender on 11 March, as previously reported by MEED. The project will cover an area of about 37,000 square metres. Egyptian firm Cosmos-E Engineers & Consultants has been appointed as the project consultant.

    This tender follows the start of construction by Egyptian contractor Rowad Modern Engineering, a subsidiary of Elsewedy Electric Group, on the expansion of SAL’s facilities at King Khalid International airport in Riyadh. The scope of work includes rehabilitating and upgrading existing infrastructure, as well as constructing new supporting facilities and services.

    SAL also launched the tendering process in September last year for its SR4.2bn ($1bn) logistics zone in northern Riyadh, MEED previously reported. UAE-based Global Engineering Consultants is the consultant for that development.

    The logistics hub aims to meet demand for customised warehouses near King Khalid International airport and the Riyadh Metro. The project aligns with Vision 2030 and the National Transport & Logistics Strategy, which aims to strengthen the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670338/main.gif
    Yasir Iqbal