Pressure builds for truce in Gaza conflict

9 February 2024

Pressure is mounting on Israel to accede to a ceasefire and hostage-prisoner exchange agreement after a visit to the region by US Secretary of State Anthony Blinken and amid ongoing negotiations between the warring parties under Egyptian and Qatari mediation.

Blinken’s visit focused on nudging Israel towards some sort of ceasefire agreement that would see the release of the hostages, but the US overture was again rebuffed by the Netanyahu government, which continues to bristle at the prospect of a truce.

As if in reaction to the pressure, the Israeli side has ratcheted up its own rhetoric again in the past week. It has asserted that its goal remains the complete dismantling of Hamas, and announced that it would launch a military operation in Rafah, the Egypt-Gaza border crossing area and a designated safe zone.

Nevertheless, there is dwindling political space, both internationally and domestically, for the Israeli government to manoeuvre away from a truce. Even Israel’s allies are tiring of the conflict and anger is building in Israel over the failure to secure the return of the hostages.

For more neutral parties around the world, the indictment of Israel at the International Court of Justice (ICJ) for plausibly committing crimes amounting to genocide has doubled up the existing risk of complicity with war crimes with the risk of complicity with genocide.

The case has changed the calculus for governments and companies with ties to Israel. It has already led to counteractions, including the suspension of export licences by the government of the Belgian province of Wallonia – in addition to an existing arms suspension by Spain.

In Japan, major arms manufacturer Itochu announced that its aviation arm would end its collaboration with Israel’s largest weapons company, Elbit Systems, citing the ICJ ruling, Japan’s respect for the court, and its obligation to avoid complicity.

Mismatched expectations

Back at the negotiating table, Hamas has itself increased the pressure on Israel by establishing its own amenability to a ceasefire and hostage release – suggesting a three-phased release of Israeli hostages on one side and Palestinian prisoners and administration detainees on the other side.

Each phase would last 45 days, for a total term of 135 days, with the first phase focusing on the release of detained Israeli women, children, elderly and the sick in exchange for 1,500 Palestinian detainees.

The second phase would then see male detainees released, followed by the bodies of those killed in the fighting or during the siege and bombardment of the Gaza Strip in the third phase.

Hamas also stated the requirement that at least 500 trucks of aid and fuel be allowed into the Gaza Strip daily, that residents have freedom of movement, and that border crossings be opened.

The Hamas deal outline also contained requirements unlikely to appeal to the Israeli government. These include the requirement that 60,000 temporary homes and 300,000 tents be let into the strip and that Israel commit to rebuilding the destroyed infrastructure within three years.

The demand not just for the delivery of humanitarian aid – as already obliged to be provided under international law and as reiterated by the ICJ – but for actual material assistance appears almost fantastical given the fanatical tilt of much of Netanyahu’s far-right cabinet.

Pressure from all sides

The Israeli government’s immediate response to Hamas’ outline was one of dismissal and pushback. While this was expected, there remains considerable momentum behind the scenes for some sort of a deal under the multilateral negotiations in Egypt.

Israeli Prime Minister Benjamin Netanyahu’s chosen response was to state off camera that Israel would not end the war but push on to “total victory” over Hamas. Yet behind the bluster of this reaction, the news was floated that Israel’s Mossad intelligence agency was studying the terms.

Meanwhile, those close to the deal remain optimistic about a positive outcome in another one to two weeks. Such a timescale would also benefit Israel by allowing it to present the deal as proof of progress under the ICJ provisional measures that it is required to report on at the end of the month.

The other deadline is the start of Ramadan on 9 March, when Muslims around the globe are bound by faith to pay particular attention to those less fortunate around them. The optics for Israel, and in turn for the US, will be disastrous if the unfettered killing continues in this period.

In his pre-departure remarks, Blinken reiterated the US position that Palestinian civilian casualties in Gaza were too high and affirmed that there was “space” for a potential truce agreement in a clear contradiction of Netanyahu’s messaging.

This repudiation of the Israeli position has become part of a discernible pattern of commentary from the US establishment in recent days that gives the appearance that Washington is increasingly interested in distancing itself from the Israeli government.

After four months of unconditional support for Israel, and amid flagging US presidential polling numbers in connection with the ongoing violence, a recalibration is under way – with Joe Biden late on 8 February declaring Israel’s actions “over the top”.

Former US secretary of state and Democrat insider Hillary Clinton was also interviewed in a move that appears highly choreographed to blame Netanyahu for failing the hostages while labelling him “not trustworthy” and calling for him to leave office.

The upshot of all this is that despite the resistance to a deal from the Israeli government, external and internal pressure is now reaching the point where resisting a ceasefire is incurring an exorbitant political cost – one that even Netanyahu may find himself unable to pay.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11504887/main.gif
John Bambridge
Related Articles
  • EtihadWE tenders $150m Ajman substation project

    21 July 2026

    The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.

    Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.

    The bid submission deadline is 10 August.

    According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.

    The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.

    Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.

    This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.

    EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.

    In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg
    Mark Dowdall
  • Seven seeks contractors for Dammam water park and hotel

    21 July 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg
    Yasir Iqbal
  • Al-Ula appoints equestrian village early works contractor

    21 July 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.

    The contract was awarded to Al-Khobar-based Al-Shalawi International Company.

    Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.

    Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.

    RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.

    The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.

    These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg
    Yasir Iqbal
  • Contractors await decision on Riyadh airport sewage plant

    21 July 2026

     

    Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.

    It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg
    Mark Dowdall
  • Dubai Municipality awards Tasreef drainage contract

    21 July 2026

     

    Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.

    It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.

    The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.

    The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.

    In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.

    The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
    Mark Dowdall