PPP activity rebounds in 2023
26 October 2023

This report on project finance and PPP also includes: Liquidity drives project finance appetite
There has been an increase in both the number and value of public-private partnership (PPP) contract awards made across the Middle East and North Africa region in 2023, according to data from regional projects tracker MEED Projects.
The total value of PPP deals from January to early October has already overtaken the value of awards made in 2022. To date, $21.3bn of PPP deals have been finalised in 2023, compared to $18.1bn in 2022, representing a rise of 18 per cent.
With most of the final quarter of the year still to go, there is every chance that the 2021 total of $22.6bn will also be surpassed. In the five years before that, the total was at most about $12bn a year, underlining the healthy position of the market at the moment.
However, the longer-term record high of $29.6bn, set in 2009, still appears to be out of reach.
In numerical terms the picture is more balanced, with 34 PPP contract awards to date in 2023, compared to 44 in 2022 and 47 in 2021. However, the average size of PPP contracts being handed out this year is significantly up, at $627m an award so far in 2023 compared to $401m in 2022 and $482m in 2021.
Water and transport lead the way
The surge in deal-making has been particularly evident in the water sector, where $9.3bn-worth of deals have been signed this year, far ahead of last year’s figure of $3.6bn.
The largest of these is a $2.2bn contract for Abu Dhabi National Oil Company’s Mirfa seawater treatment plant. A consortium of Orascom Construction and Metito has been appointed to develop the project.
Just behind this in terms of value is the $2.1bn contract to install a water transmission pipeline from the Ar-Rayis1 independent water plant to Rabigh for Saudi Water Partnerships Company. The contract was won by a consortium of Cobra Group, Al-Khorayef Water & Power Technologies and Orascom Construction.
The transport sector has also been performing well, with $5.3bn-worth of contracts in 2023, significantly more than the $428m in 2022. The biggest schemes include a $2.2bn contract for Iran’s Roads & Urban Development Ministry to expand capacity at Tehran’s Imam Khomeini International airport, for which a joint venture of Hycan Automobile Technology Company and Khatam al-Anbia was appointed in September.
Another major contract is the $1.9bn deal that Saudi Ports Authority (Mawani) signed with China Harbour Engineering Company to upgrade Terminal 1 and expand Terminal 2 at King Abdulaziz Port in Dammam.
Construction and power struggle
There has been a relative decline in other areas, however, and most notably in construction. The high level of activity seen in the sector in 2022 has not been sustained, with contract values falling by two-thirds so far this year to $1.6bn. The number of PPP awards in the sector has also fallen, from 14 in 2022 to seven so far in 2023 – the lowest figure for this part of the market since 2019.
The power sector looks set to continue its recovery, with several solar and wind independent power projects (IPPs) in Saudi Arabia expected to be awarded before the end of the year. An estimated $4.9bn-worth of deals have been awarded in the first nine months of 2023.
The expected award of the Saudi IPP contracts, as well as the third solar photovoltaic project in Abu Dhabi, indicates that the total value of power deals this year could equal or exceed that of last year.
PPP deals in the power sector – which pioneered the model in the region – account for 139 of the 332 contracts awarded between 2015 and 2023. This is followed by the water sector with a further 86 contracts, construction with 50 awards and transport with 31 deals. The remaining contracts were awarded in the chemicals, oil and gas and industrial sectors.
Within the power sector there has been a preference for build, own and operate (BOO) contracts, with 84 in total over the period, worth a combined $30.1bn; and build, operate and transfer (BOT) contracts, of which there have been a further 76, worth $20.1bn. In the water sector, the contracts are more evenly spread between BOO, BOT and build-own-operate-transfer (BOOT) schemes, while both the transport and construction sectors tend to favour BOT models.
Across all sectors, BOT, BOO and BOOT contracts account for 77 per cent of all contracts by value in the period under review. BOT emerged as the frontrunner in 2023 in terms of the value of awards, having been second to BOO contracts last year.
For most of the past decade, these two contract models have been the dominant ones, although BOOT was far ahead of the pack in 2021 thanks to the award of a $6bn contract that year by Algeria’s Transport Ministry for the development of El-Hamdania Port.
Gulf economies remain dominant
The most important markets in the region for PPP deals in 2023 are Saudi Arabia, with $11.6bn-worth of contract awards, followed by the UAE with $5.7bn and Iran with $2.2bn – the latter almost wholly because of the Tehran airport deal.
Among the other major contracts in these markets is a $2bn deal signed by Red Sea Global in September with a team of Masdar, EDF and Korea East-West Power Company for a multi-utilities package at the Amaala development, including a solar power plant, battery storage, sewage treatment and a desalination plant.
Also notable is Etihad Rail’s $800m contract with National Infrastructure Construction Company and National Projects & Construction in early October for the first phase of the light rail network in Abu Dhabi.
No other country has yet broken through the $1bn mark in terms of PPP contract awards in 2023, although Oman may yet do so. So far this year, the sultanate has seen the award of $824m-worth of projects, including two $400m contracts awarded by Oman Wastewater Services Company to develop solar power plants at Manah, southwest of Muscat.
This year’s figure is the highest for the sultanate in several years and marks a step-change from its recent performance. In 2021 and 2022, PPP contracts worth just $50m and $60m were signed, respectively.
Other markets have been performing more poorly. Both Egypt and Iraq have seen the level of activity slump significantly, with just $520m-worth of contracts in Egypt so far this year, compared to $3.6bn in 2022. Iraq has seen no PPP contract awards in 2023 at all, after two bumper years in which $8.5bn worth of deals were finalised in 2021 and $3.7bn in 2022.
The fall in these markets is a further sign of the wider problems facing their economies and could be a signal that private-sector actors are increasingly wary of signing up to long-term deals in such uncertain economic and political environments.
Among other, smaller markets, there have been signs of activity in both Bahrain and Tunisia, with one and two deals respectively this year, after no activity was recorded in either market last year.
Exclusive from Meed
-
Iraq’s first LNG terminal to be completed in June27 April 2026
-
-
Kuwait approves Doha desalination plant award27 April 2026
-
Firms prepare bids for 250MW Airtrunk data centre27 April 2026
-
Diriyah confirms $490m museum construction contract27 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iraq’s first LNG terminal to be completed in June27 April 2026
Iraq’s first liquefied natural gas (LNG) import terminal is expected to be completed in early June, according to the country’s Ministry of Electricity.
The terminal, which has an estimated investment value of $450m, is being developed at the Port of Khor Al-Zubair and will have a capacity of 750 million standard cubic feet a day (cf/d).
Ministry spokesperson Ahmed Mousa told the Iraqi News Agency that “work is proceeding at an accelerated pace to complete the LNG platform”, noting that “the government has set 1 June as the date for finishing the project”.
In October last year, US-based Excelerate Energy signed a commercial agreement with a subsidiary of Iraq’s Ministry of Electricity to develop the floating LNG terminal.
The contract was signed at the office of Iraq’s Prime Minister Mohammed Shia Al-Sudani during a ceremony attended by senior officials from both countries, including the US deputy secretary of energy James Danly.
The contract included a five-year agreement for regasification services and LNG supply with extension options, featuring a minimum contracted offtake of 250 million cf/d.
Ahmed Mousa said that “under the contract, the company is responsible for completing the facility as well as securing the agreed gas quantities from any source, in line with the specified terms”.
He added: “Work is continuing according to the planned timelines to complete the project on schedule, as part of the Ministry of Electricity’s plans to keep pace with peak summer loads.”
Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.
Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.
Recently, Iraq’s oil and gas sector has been disrupted by fallout from the US and Israel’s attack on Iran on 28 February and the subsequent regional conflict.
Over recent weeks, Iraq’s oil exports have collapsed by about 80% amid problems shipping crude through the Strait of Hormuz.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577746/main.jpg -
Iraqi LNG import terminal raises questions about energy strategy27 April 2026
Commentary
Wil Crisp
Oil & gas reporterIraq’s first LNG import terminal is set to come online in early June, at a time when global LNG prices are likely to remain close to their highest levels in more than three years.
The disruption to global oil and gas exports in the wake of the US and Israel’s attack on Iran on 28 February led to LNG prices soaring, with natural gas prices in Asia and Europe rising to their highest levels since January 2023 during March.
So far, there has been little progress towards a diplomatic or military solution to reopen the Strait of Hormuz, and most analysts do not forecast significant price declines in the near term.
On 24 April, the International Energy Agency (IEA) said that the combined effect of short-term supply losses and slower capacity growth could result in a cumulative loss of around 120 billion cubic metres of LNG supply between 2026 and 2030.
While the IEA expects new liquefaction projects in other regions to offset these losses over time, it still believes the crisis will lead to prolonged tight market conditions through 2026 and 2027.
This means that Iraq will likely have to pay elevated prices for imported LNG for some time to come – if it can receive shipments at all.
The port of Khor Al-Zubair is located in the Arabian Gulf, and LNG shipments from the US or Australia would need to pass through the Strait of Hormuz before reaching the terminal.
This will only be possible if a solution is found to the ongoing blockade of the shipping route.
Investment debate
Iraq’s project to develop a floating LNG terminal is estimated to cost $450m, and many in Iraq may question whether this was the best use of these funds.
While it may have been difficult for Iraqi policymakers to foresee the attack by the US and Israel on Iran and its impact on LNG markets, Iraq had several strong options to enhance domestic energy security rather than turning to LNG imports.
The most obvious of these was investing in infrastructure to enable it to utilise its domestic gas reserves.
According to the World Bank’s 2025 Global Gas Flaring Tracker Report, in 2024, Iraq burned off more unused gas than any other country, except Russia and Iran, which ranked first and second, respectively.
That year, an estimated total of more than 18 billion cubic metres of natural gas was flared in Iraq due to a lack of infrastructure to properly capture and process it.
It is highly likely that projects to gather and process this gas would have been more reliable and cost-effective than investing in a new floating LNG terminal, which increases the country’s exposure to global LNG price fluctuations and shipping disruptions.
Other options could have included developing domestic gas fields or investing in solar and battery storage projects, which have become increasingly affordable in recent years.
The cost of solar panels has fallen by more than 95% over the past decade.
Power shortfall
As things stand, Iraq is likely to face severe electricity shortages this summer.
On 21 April, Iraq’s Ministry of Electricity said it plans to produce 30,000MW this summer, well short of the predicted peak demand of around 55,000MW.
Ahmed Musa, a spokesperson for the Electricity Ministry, told the state-run Iraqi News Agency that the shortfall will result in planned outages across the country.
He also said that even meeting the 30,000MW target is contingent on sufficient gas supplies.
If Iraq experiences the same level of power outages as last year – or worse – many are likely to view the $450m spent on an LNG import terminal as a waste of money and an expensive symbol of poor planning.
Power cuts this summer could stoke unrest at a time that is already politically precarious due to the ongoing regional conflict.
In recent years, electricity shortages have repeatedly fuelled protests in Iraq during the summer months, particularly in Basra, where blackouts and poor public services have driven people to take to the streets.
If the Strait of Hormuz does not reopen soon, Iraq’s economic crisis will deepen, and electricity shortages are likely to further undermine the country’s stability.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577743/main.jpg -
Kuwait approves Doha desalination plant award27 April 2026
Kuwait’s Central Agency for Public Tenders has approved the recommendation of the Ministry of Electricity & Water to award a KD114.28m ($371.5m) contract to supply, install, operate and maintain the second phase of the Doha seawater reverse osmosis (SWRO) desalination plant.
A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag has been selected for the project, with the award understood to be pending final approval from the Audit Bureau.
The project will deliver a production capacity of about 60 million imperial gallons a day (MIGD) and will include the desalination plant with full reverse osmosis trains, pre- and post-treatment systems, recarbonation equipment, booster pumps, and safety and filtration systems.
The total project duration is 96 months. The Doha SWRO desalination plant is part of Kuwait’s broader programme to expand water production capacity and reduce reliance on thermal desalination methods.
MEED previously reported that the Heisco/Wabag joint venture submitted the lowest bid. Bidders and prices included:
- Heavy Engineering Industries & Shipbuilding / Wabag: $373.2m
- Cox Water (Spain): $538.1m
- Orascom Construction (Egypt): $568.4m
In April 2025, MEED reported that Kuwait had retendered the contract for the facility after the ministry cancelled the initial tender in June 2024.
The Ministry of Electricity & Water awarded South Korea’s Doosan Heavy Industries & Construction – now known as Doosan Enerbility – a $422m contract in May 2016 to build the 60 MIGD Doha 1 SWRO plant.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577722/main.jpg -
Firms prepare bids for 250MW Airtrunk data centre27 April 2026

Contractors are preparing to submit commercial offers by 4 May for a contract to build a 250MW data centre in Riyadh.
The project is being co-developed by Australian firm AirTrunk in collaboration with Saudi Arabia’s artificial intelligence (AI) infrastructure company Humain, which is owned by the Public Investment Fund (PIF).
The bidders include:
- El-Seif Engineering Contracting / Larsen & Toubro (local/India)
- FCC / Alfanar Projects (Spain/local)
- Albawani / Orascom (local/Egypt)
- Nesma & Partners (local
- James L Williams (UAE)
- Alec (UAE)
In October last year, AirTrunk and Humain announced a $3bn partnership to build data centres in Saudi Arabia, marking AirTrunk’s first move into the region.
The firms said they would, along with AirTrunk investor Blackstone, “develop a long-term strategic partnership focused on financing, developing and operating next-generation data centres and AI infrastructure across the kingdom”.
This was followed by Humain signing a $1.2bn financing agreement with the state-backed National Infrastructure Fund to support the expansion of AI and digital infrastructure projects in Saudi Arabia. The agreement was signed in January on the sidelines of the World Economic Forum in Davos, Switzerland.
Humain said the deal will support its plan to develop up to 250MW of hyperscale AI data centre capacity in the kingdom.
According to a joint statement, the data centres will use graphics processing units for AI training and inference, serving Humain’s customers locally, regionally and globally.
The National Infrastructure Fund and Humain will also explore launching an AI data centre investment platform, with the two organisations acting as anchor investors to enable local and international institutional investors to back the scale-up of Humain’s AI programme.
The National Infrastructure Fund is Saudi Arabia’s lead development financing partner for infrastructure and operates under the supervision of the National Development Fund.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577720/main.jpg -
Diriyah confirms $490m museum construction contract27 April 2026
Saudi gigaproject developer Diriyah Company has formally announced the award of a SR1.84bn ($490m) construction contract for its Saudi Arabia Museum of Contemporary Art (SAMoCA) within the Diriyah development in Riyadh.
The contract has been awarded to a consortium comprising Egyptian contractor Hassan Allam Construction and Saudi Arabia’s Albawani.
In February, MEED exclusively reported that the contractors were preparing to start construction work on the project. MEED understands Diriyah Company awarded the contract to the consortium in December last year.
The announcement follows Diriyah Company’s award of an estimated SR2.5bn ($666m) contract to build the Pendry superblock package in the DG2 area.
The Pendry superblock includes the construction of the Pendry Hotel alongside residential and commercial assets. The package will cover 75,365 square metres and is located in the northwestern district of the DG2 area.
In February, Diriyah Company also awarded a SR717m ($192m) contract for the construction of the One Hotel, located in the Diriyah Two area of the masterplan, with a gross floor area of more than 31,000 sq m.
The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh city centre, it will span 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577413/main.jpg

