PPP activity rebounds in 2023

26 October 2023

 

This report on project finance and PPP also includes: Liquidity drives project finance appetite


There has been an increase in both the number and value of public-private partnership (PPP) contract awards made across the Middle East and North Africa region in 2023, according to data from regional projects tracker MEED Projects.

The total value of PPP deals from January to early October has already overtaken the value of awards made in 2022. To date, $21.3bn of PPP deals have been finalised in 2023, compared to $18.1bn in 2022, representing a rise of 18 per cent.

With most of the final quarter of the year still to go, there is every chance that the 2021 total of $22.6bn will also be surpassed. In the five years before that, the total was at most about $12bn a year, underlining the healthy position of the market at the moment.

However, the longer-term record high of $29.6bn, set in 2009, still appears to be out of reach.

In numerical terms the picture is more balanced, with 34 PPP contract awards to date in 2023, compared to 44 in 2022 and 47 in 2021. However, the average size of PPP contracts being handed out this year is significantly up, at $627m an award so far in 2023 compared to $401m in 2022 and $482m in 2021.

Water and transport lead the way

The surge in deal-making has been particularly evident in the water sector, where $9.3bn-worth of deals have been signed this year, far ahead of last year’s figure of $3.6bn.

The largest of these is a $2.2bn contract for Abu Dhabi National Oil Company’s Mirfa seawater treatment plant. A consortium of Orascom Construction and Metito has been appointed to develop the project.

Just behind this in terms of value is the $2.1bn contract to install a water transmission pipeline from the Ar-Rayis1 independent water plant to Rabigh for Saudi Water Partnerships Company. The contract was won by a consortium of Cobra Group, Al-Khorayef Water & Power Technologies and Orascom Construction.

The transport sector has also been performing well, with $5.3bn-worth of contracts in 2023, significantly more than the $428m in 2022. The biggest schemes include a $2.2bn contract for Iran’s Roads & Urban Development Ministry to expand capacity at Tehran’s Imam Khomeini International airport, for which a joint venture of Hycan Automobile Technology Company and Khatam al-Anbia was appointed in September.

Another major contract is the $1.9bn deal that Saudi Ports Authority (Mawani) signed with China Harbour Engineering Company to upgrade Terminal 1 and expand Terminal 2 at King Abdulaziz Port in Dammam.

Construction and power struggle

There has been a relative decline in other areas, however, and most notably in construction. The high level of activity seen in the sector in 2022 has not been sustained, with contract values falling by two-thirds so far this year to $1.6bn. The number of PPP awards in the sector has also fallen, from 14 in 2022 to seven so far in 2023 – the lowest figure for this part of the market since 2019.

The power sector looks set to continue its recovery, with several solar and wind independent power projects (IPPs) in Saudi Arabia expected to be awarded before the end of the year. An estimated $4.9bn-worth of deals have been awarded in the first nine months of 2023. 

The expected award of the Saudi IPP contracts, as well as the third solar photovoltaic project in Abu Dhabi, indicates that the total value of power deals this year could equal or exceed that of last year.

PPP deals in the power sector – which pioneered the model in the region – account for 139 of the 332 contracts awarded between 2015 and 2023. This is followed by the water sector with a further 86 contracts, construction with 50 awards and transport with 31 deals. The remaining contracts were awarded in the chemicals, oil and gas and industrial sectors.

Within the power sector there has been a preference for build, own and operate (BOO) contracts, with 84 in total over the period, worth a combined $30.1bn; and build, operate and transfer (BOT) contracts, of which there have been a further 76, worth $20.1bn. In the water sector, the contracts are more evenly spread between BOO, BOT and build-own-operate-transfer (BOOT) schemes, while both the transport and construction sectors tend to favour BOT models.

Across all sectors, BOT, BOO and BOOT contracts account for 77 per cent of all contracts by value in the period under review. BOT emerged as the frontrunner in 2023 in terms of the value of awards, having been second to BOO contracts last year.

For most of the past decade, these two contract models have been the dominant ones, although BOOT was far ahead of the pack in 2021 thanks to the award of a $6bn contract that year by Algeria’s Transport Ministry for the development of El-Hamdania Port.

Gulf economies remain dominant

The most important markets in the region for PPP deals in 2023 are Saudi Arabia, with $11.6bn-worth of contract awards, followed by the UAE with $5.7bn and Iran with $2.2bn – the latter almost wholly because of the Tehran airport deal.

Among the other major contracts in these markets is a $2bn deal signed by Red Sea Global in September with a team of Masdar, EDF and Korea East-West Power Company for a multi-utilities package at the Amaala development, including a solar power plant, battery storage, sewage treatment and a desalination plant.

Also notable is Etihad Rail’s $800m contract with National Infrastructure Construction Company and National Projects & Construction in early October for the first phase of the light rail network in Abu Dhabi.

No other country has yet broken through the $1bn mark in terms of PPP contract awards in 2023, although Oman may yet do so. So far this year, the sultanate has seen the award of $824m-worth of projects, including two $400m contracts awarded by Oman Wastewater Services Company to develop solar power plants at Manah, southwest of Muscat.

This year’s figure is the highest for the sultanate in several years and marks a step-change from its recent performance. In 2021 and 2022, PPP contracts worth just $50m and $60m were signed, respectively.

Other markets have been performing more poorly. Both Egypt and Iraq have seen the level of activity slump significantly, with just $520m-worth of contracts in Egypt so far this year, compared to $3.6bn in 2022. Iraq has seen no PPP contract awards in 2023 at all, after two bumper years in which $8.5bn worth of deals were finalised in 2021 and $3.7bn in 2022.

The fall in these markets is a further sign of the wider problems facing their economies and could be a signal that private-sector actors are increasingly wary of signing up to long-term deals in such uncertain economic and political environments.

Among other, smaller markets, there have been signs of activity in both Bahrain and Tunisia, with one and two deals respectively this year, after no activity was recorded in either market last year. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11227112/main.gif
Dominic Dudley
Related Articles
  • Lowest bidder emerges for Kuwait Airport Terminal 2 operations

    19 October 2026

     

    Ireland’s DAA International has emerged as the lowest bidder for the contract to operate, manage and maintain the new passenger Terminal 2 (T2) at Kuwait International airport, submitting an offer of KD419m ($1.35bn).

    Official price-opening records released by Kuwait’s Central Agency for Public Tenders on behalf of the Directorate General of Civil Aviation show three international airport operators submitted commercial bids for the tender.

    DAA International’s proposal undercut its nearest rival by about 45%. Turkiye’s TAV Airports Holding submitted the second-lowest offer at KD764.15m ($2.46bn), while South Korea’s Incheon International Airport Corporation bid KD959.48m ($3.1bn).

    All three proposals were marked as approved in the tender committee’s price disclosure.

    The contract entails the operation, management and improvement of training, maintenance and development services across Terminal 2 and its associated aircraft parking aprons.

    The remit also includes corporate management of centralised operation and maintenance across the broader Kuwait International airport model, centralising operational procedures, systems integration and service delivery across the aviation hub.

    Technical documents indicate the winning operator will oversee facility management, terminal operational readiness, passenger processing systems, apron operations and staff development programmes before and after the complex’s commercial launch.

    MEED reported in June 2023 that six airport operators had initially been invited to bid for the Terminal 2 operating concession.

    Terminal 2 is the centrepiece of Kuwait International airport’s multibillion-dollar expansion, aimed at boosting total handling capacity to 25 million passengers a year.

    Turkish contractor Limak Insaat is executing the main terminal building under an estimated $4.34bn contract awarded in 2016.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20747061/main.png
    Yasir Iqbal
  • Dubai tenders Al-Maktoum-Dubai South drainage scheme

    19 October 2026

    Dubai Municipality has invited contractors to submit bids by 5 November for the construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South

    The project, designated TF-06-C2, involves approximately 20 kilometres of pipelines with diameters ranging from 400mm to 3,000mm. The works will use deep trenchless construction and conventional open-cut methods. 

    The scheme is one of four projects, for which a project management consultancy (PMC) tender was issued earlier this month.

    The tender for TF-06-S1 Supervision of Stormwater Drainage System Projects – Package 4 was issued on 6 October.

    The consultancy covers the following projects:

    • TF-06-C1: Construction of a stormwater pond connecting Al-Maktoum Airport and Dubai South
    • TF-06-C2: Construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
    • TF-07-C1: Construction of a stormwater drainage system on Sheikh Zayed Bin Hamdan Road connecting developers
    • TF-24-C1: Connecting developers’ areas to the stormwater networks in Dubailand 

    The projects are part of Dubai Municipality’s wider Tasreef programme, intended to increase Dubai’s rainwater drainage capacity by 700% by 2033 and provide capacity for the emirate’s needs for the next 100 years.

    Investment in the UAE water sector has been dominated by stormwater drainage and network resilience schemes this year, as Dubai Municipality advances procurement under its AED30bn ($8.1bn) Tasreef programme.

    TF-07-C1

    As previously reported, contractors are preparing to submit bids on 22 October for the main construction contract for TF-07-C1.

    The project covers more than 100 million square metres between Sheikh Mohammed Bin Zayed Road and Emirates Road, and from Expo Road to Dubailand.

    It will provide stormwater infrastructure and service connections for more than 20 private developers and Al-Yalayis 5, as well as supporting major roads in the Jebel Ali area. The construction scope includes a major gravity drainage system with pipeline diameters of up to 3,000mm.

    TF-24-C1

    Bids for TF-24-C1 were submitted on 1 October, with Nael Construction & Contracting, Al-Nasr Contracting Company and Al-Kharafi & Sons understood to be among the bidders. 

    The project will connect developers’ areas in Dubailand to the stormwater network. It includes 18km of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.

    As MEED understands, the main contract tender for TF-06-C1 has yet to be released.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20746611/main.jpg
    Mark Dowdall
  • Contractor wins $44m Morocco rail stations deal

    19 October 2026

    Morocco’s national railway operator, Office National des Chemins de Fer (ONCF), has awarded a MD437.6m ($44.5m) contract to local firm Jet Contractors to build five railway stations along the Benguerir-Marrakech corridor.

    The project forms part of the wider Kenitra-Marrakech high-speed rail development programme.

    Jet Contractors will build one high-speed rail station and four regional express rail stations.

    These include two stations in Benguerir, and one each at Sidi Bou Othmane, Sidi Ghanem and Marrakech Stadium.

    The scope of work includes construction and fit-out of the stations and associated infrastructure, including concrete structures, platforms, ancillary facilities, passageways, circulation areas and connection zones within the stations.

    It also covers architectural finishing works; testing and commissioning of electrical networks; and all mechanical, electrical and plumbing services.

    The contractor will also provide all safety, security and protection systems, including alarms, fire detection and firefighting systems, and surveillance systems.

    Morocco awarded multiple civil works contracts in 2024 to international and local firms to build its Kenitra-Marrakech high-speed railway line.

    The rail project is part of a $37bn strategy to connect more of Morocco’s cities, ports and airports by rail. It will stretch 375 kilometres from Kenitra on the northwest coast to Marrakech in the south.

    The project is divided into seven lots, each measuring 36km to 64km. The rail link will pass through cities including Rabat, Sale and Casablanca.

    The link will extend the Al-Boraq high-speed rail line between Tangier, Rabat and Casablanca. The line began operating in 2018 and was Africa’s first high-speed railway system.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20745963/main.jpg
    Yasir Iqbal
  • Firms submit Dubai multibillion-dollar road scheme interest

    19 October 2026

     

    Register for MEED’s 14-day trial access 

    Contractors submitted expressions of interest on 10 October for a design-and-build contract for a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.

    Dubai’s Roads & Transport Authority (RTA) held an online meeting after the submissions to prepare for the prequalification phase of tendering, expected to start in a few weeks.

    The scope covers about 30 kilometres (km) of works.

    These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.

    The RTA floated the expression of interest notice to contractors in early September.

    The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.

    Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.

    The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through traffic while existing at-grade lanes served local access.

    The plans ultimately became standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.

    The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.

    Planning for growth

    Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20745908/main.jpg
    Yasir Iqbal
  • Libya seeks offshore contractors for $8bn gas project

    19 October 2026

    Libya’s Mellitah Oil & Gas Company (MOG) has invited companies to prequalify for a major offshore package as part of its Mellitah Complex Expansion & CO2 Management Integrated Development Project, which is estimated to be worth about $8bn.

    The package is estimated at around $3bn and focuses on developing offshore pipelines and subsea systems for the “E” Offshore Installation Project and CO2 project.

    The deadline to submit prequalification documents is 5 November. The contract will use the engineering, procurement, installation and commissioning (EPIC) model.

    MOG is a joint venture of Libya’s National Oil Corporation and Italian oil and gas company Eni.

    This is not the first time MOG has invited submissions for the offshore pipelines and subsea systems package. The company originally launched a prequalification process for the EPIC contract in 2021, but the project experienced delays and the process was eventually cancelled. The prequalification process was restarted nearly three years later, but it was also ultimately abandoned.

    Complex expansion

    As part of the Mellitah Complex Expansion & CO2 Management Integrated Development Project, two offshore structures – Structure A and Structure E – will be developed in Libya’s offshore block NC 41.

    Structure A is in the central-western part of the area, about 80 kilometres (km) from the Libyan coast, with a water depth of 95-105 metres.

    Structure E is located in the central-eastern part of the area, about 130km from the Libyan coast, in a water depth of 205-235 metres.

    The scope of the wider project includes:

    • A new wellhead platform installed in 96 metres of water as part of the development of Structure A
    • A new production platform installed in about 220 metres of water depth as part of the development of Structure E
    • Modification of the existing Sabratha platform
    • Sealines and subsea systems for structures A and E
    • Upgrading the existing onshore Mellitah complex
    Project contract awards

    In June 2024, MOG awarded an offshore engineering, procurement and construction (EPC) contract worth €1.2bn ($1.28bn), which was part of the Mellitah Complex Expansion & CO2 Management Integrated Development Project.

    The contract was awarded to a consortium of three Italian companies: Rosetti Marino, Kerry Project Logistics and Gruppo Antonini.

    In a statement, Rosetti Marino said its share of the project contract was worth €400m ($428m), comprising 33% of the total contract value.

    Rosetti Marino said its scope of work includes EPC and load-out activities to deliver the topside of the approximately 6,000-tonne gas production wellhead platform, named WHP-A, to be installed off the coast of Libya.

    Project setbacks

    During 2023 and 2024, several setbacks affected the Mellitah Complex Expansion & CO2 Management Integrated Development Project.

    In November 2023, MOG restarted the prequalification process for an upstream offshore package worth an estimated $700m.

    The project scope involves modifications to the offshore Sabratha platform at the Bahr Essalam field.

    Less than two months later, MOG restarted prequalification for a second package as part of the integrated development project.

    The scope of the second package covers key sealine and subsea systems.

    No reason was given for restarting the prequalification process for two of the project’s packages.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20738707/main.jpg
    Wil Crisp