PPP activity eases back but remains strong
25 October 2024

This package also includes: Region remains global project finance hotspot
Public-private partnership (PPP) activity appears to be easing back in the Middle East and North Africa (Mena) region in 2024, with the total value of contract awards in the first nine months of the year coming in at $24bn, according to regional projects tracker MEED Projects.
This is 6.5% lower than the $25.6bn recorded in the same period a year earlier. The full-year total for 2023 then ended up at $41.3bn after a surge of activity in the final three months of the year.
While there are plenty of contract awards pencilled in for the final quarter of this year, too – including several large power and water projects in the Levant and the Gulf – at this stage, it appears unlikely that the gap to the record 2023 total will be bridged.
Among the projects with main contract awards due to be made before 31 December are a 10GW battery energy storage system (bess) in Saudi Arabia and the 3.7GW fifth round of the country’s renewable energy programme, both planned by Saudi Power Procurement Company.
Other major projects at a similar stage include a 10GW solar power project planned by the Renewable Energy & Energy Efficiency Organisation in Iran; the $4.3bn Aqaba-Amman water desalination and conveyance scheme backed by Jordan’s Water & Irrigation Ministry; and the $3bn, 2.3GW Facility E independent water and power project by Qatar General Electricity & Water Corporation (Kahramaa).
In total, 72 main contract awards are due to be made by the end of 2024 – almost as many as were handed out in the whole of 2023. However, there can be no certainty as to which ones will get over the line before the year’s end and which ones might suffer delays or cancellations.
Even without such projects, though, the number and value of contracts finalised in the first nine months of this year means 2024 is set to be one of the most active for PPP deal-making so far this century.
Other than last year’s record-setting run, the combined value of deals has not been this high since 2009, when a total of $29.6bn-worth of contracts were awarded. In terms of the number of awards, this year has also been among the most active.
The 45 contracts handed out between January and the end of September is already above the annual average of 44 contracts a year over the past decade. It puts the year firmly on track to be among the top performing years in terms of the number of PPP contracts awarded. The surge in the past three years highlights the popularity that PPP deals are enjoying among Mena governments at present.
The average size of contract awards is also running well above the long-term figure, with the typical deal being worth $533m in 2024. This is down from the $574m figure of last year, but well ahead of any other performance in the past decade save the $556m figure in 2014.
Iraq, Saudi Arabia and the UAE lead
In terms of geography, the standout markets this year have been Iraq, with $11bn of PPP awards, followed by Saudi Arabia with $5.4bn and the UAE with $3bn. Between them, these three countries accounted for a total of 34 contract awards, or 75% of the figure for the whole of the Mena region in the opening nine months of the year.
Key contracts signed in these markets have included the $8bn Al-Faw refinery and petrochemicals complex in Iraq’s southern Basra province, which is being developed by the Southern Refineries Company; and a series of contracts
awarded by the National Investment Commission on seven lines of the $2.5bn Baghdad Metro.
In Saudi Arabia, there have been 15 awards across the transport, power and water sectors, including the 2GW Haden solar photovoltaic (PV) power plant, the 600MW Al-Ghat independent power producer (IPP) wind project, and expansion work at Prince Mohammad Bin Abdulaziz International airport in Medina.
In the UAE, the contract activity has been more varied, with awards in the power, water, transport, construction and industrial sectors. Among the biggest awards so far this year were a $1.5bn contract awarded by Emirates Water & Electricity Company for the 1.5GW Al-Ajban solar IPP in Abu Dhabi and a $682m contract awarded by Sharjah Electricity & Water Authority to Acwa Power for the Hamriyah seawater reverse osmosis independent water project.
Another market with high levels of activity this year is Egypt, where there has been $3.7bn-worth of contract awards, including a $2.2bn strategic warehousing scheme. The Damietta Port Authority also signed a $665m deal to deliver a second container terminal and a $500m award for the 1GW Benban solar PV power plant and 600 megawatt-hour bess in Aswan Governorate.
Bahrain, Oman, Qatar and Tunisia have each seen one or two awards apiece, with the individual awards being generally more modest in value.
Sectoral and contractual shift
On a sectoral basis, this year has seen an even broader spread of awards across different industries compared to last year.
In 2023, the power sector accounted for 55% of the total awards by value, with the water and transport sectors accounting for a further 39% between them.
This year, power has again been the main focus of activity, but its share of the total awards value has fallen to 30%, while the transport sector fell to 15%.
The chemicals and oil industries then inched ahead, with 17% each, split across the planned $8bn combined value of the Al-Faw refinery and petrochemicals complex in Iraq.
The water sector has meanwhile seen a sharp drop-off in awards, with deals in the first nine months of the year accounting for just 6.6% of the total.
These changes have contributed to another significant shift, with the type of contracts proving most popular also undergoing a change this year.
In 2023, most of the awards were either for build, own and operate or build-operate-transfer (BOT) contracts, which accounted for 34% and 32% of the total value of awards handed out, respectively.
This was followed by build and operate and build-own-operate-transfer (BOOT) awards, worth a further 14% each.
This year, the activity has been led by BOOT contracts, which have totalled $9.2bn, or 38% of the total for the first nine months. This was driven again by the $8bn-worth of contract value accounted for by the Al-Faw Refinery in Iraq.
Following behind are BOT contracts with a total value of $5.4bn, representing 22% of the total, most of which has
been awarded in the power sector. Design-build-finance-operate-transfer contracts worth $5bn accounted for 21% of the total with the value split across the transport and industrial sectors.
The picture could yet change in the final quarter of the year. In recent years, the last three months have been the busiest period for contract signings. In 2021, 38% of the year’s awards were made in Q4, with this figure increasing to 66% in 2022, before receding again to 38% in 2023 – but yet again with more than a third of all awards being made in the last quarter.
Exclusive from Meed
-
Riyadh Expo sets November bid deadline for Souq construction29 October 2026
-
Iraq oilfield water scheme to hit milestone next year29 October 2026
-
Dubai tenders Al-Awir sewerage and stormwater works29 October 2026
-
Adnoc Onshore selects contractors for well tie-ins project27 October 2026
-
Ashghal tenders Al-Udeid air base access road works27 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Riyadh Expo sets November bid deadline for Souq construction29 October 2026

Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has allowed contractors until 11 November to submit bids for a contract to deliver the Souq areas within the Expo site.
The tender was floated on 30 July, with an initial submission deadline of 9 October.
The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).
The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works.
The precincts comprise:
- Precinct 1 – The Icon: 41,417 sq m
- Precinct 2 – Place & Planet: 62,306 sq m
- Precinct 3 – Culture of Wisdom: 67,112 sq m
- Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m
- Precinct 5 – Adaptation & Innovation: 82,358 sq m
The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.
The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, connecting the site’s iconic and thematic assets.
The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.
Site progress
Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.
Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to build a new metro station serving the Expo 2030 site.
In April, ERC awarded two contracts to local firm Al-Yamama Company for the next phase of infrastructure works at the site.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.
That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.
The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20998514/main.jpg -
Iraq oilfield water scheme to hit milestone next year29 October 2026

China Petroleum Pipeline Engineering (CPP) expects to start laying pipeline for Iraq’s Common Seawater Supply Project (CSSP) in Basra in mid- or late next year, according to industry sources.
The project is behind schedule, partly because importing sections of pipeline is proving challenging due to disruptions to shipping through the Strait of Hormuz.
The project is being managed by state-owned Basra Oil Company (BOC), with Australia’s ILF acting as a project management consultant after completing the front-end engineering design (feed).
Under current plans, the pipelines will be buried, which is expected to make them more secure than if they were installed on the surface.
Phased development
The client for the first phase of the CSSP is France’s TotalEnergies in partnership with QatarEnergy and BOC.
The first phase is split into two packages currently under execution and will ultimately have the capacity to transport 5 million barrels a day (b/d) of water.
The first package focuses on developing pipelines, and the second on developing a water treatment facility.
CPP is executing the pipeline package contract.
It signed a $2.5bn contract with BOC for the package in September last year.
Also in September 2025, South Korea’s Hyundai announced that it had signed a contract worth 4.39tn won ($3.16bn) for the processing plant package.
In September this year, MEED reported that early groundworks had started for both packages of the first phase of the CSSP.
Phase one of the project is scheduled to start up in late 2028 or early 2029.
Earlier this month, US-headquartered Exxon Mobil signed a memorandum of understanding related to the project’s second phase, which is expected to add 2.5 million b/d of water capacity.
The CSSP will inject processed water into several of Iraq’s biggest oil fields. These include Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon. Water from the project will also be used in the Maysan and Dhi Qar fields.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20981033/main.jpg -
Dubai tenders Al-Awir sewerage and stormwater works29 October 2026

Dubai Municipality has invited contractors to bid for a contract to build sewerage and stormwater infrastructure in New Al-Awir 1st.
The project (DS317-C1) comprises about 95 kilometres of sewerage gravity network, excluding house connections, and about 105km of stormwater pipelines. The scope also includes house connection pipes, a stormwater pond and oil interceptors.
According to tender documents seen by MEED, the tender was issued on 23 October, with a bid submission deadline of 12 November.
The project comes amid wider residential and infrastructure development in Al-Awir 1. In January 2025, Dubai’s Roads & Transport Authority (RTA) announced plans to build 16.5km of internal roads in the area, including a new entrance from Emirates Road.
In February 2025, MEED exclusively reported that the RTA had selected a local firm to undertake the road construction works.
The Mohammed Bin Rashid Housing Establishment has also reported progress on housing projects in Al-Awir as part of a wider programme to develop residential communities across Dubai.
The sewerage and stormwater project is relatively large compared with recent stormwater tenders, with the total cost estimated at up to AED1bn ($272m).
The works will include approximately 69.2km of house connection pipes and 4,630 inspection chambers. The sewerage network will also include about 1,511 manholes, while the stormwater network will comprise approximately 1,247 manholes.
Contractors will also be required to use no-dig construction methods for sections of the pipeline. The scope includes ground investigations, utility protection and traffic management.
The bill of quantities specifies a stormwater pond with a composite volume of approximately 1.2 million cubic metres.
Earlier this week, Dubai Municipality confirmed it had awarded contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.
The projects are part of Dubai’s AED30bn Tasreef programme and will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom.
The overall programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20977734/main.jpg -
Adnoc Onshore selects contractors for well tie-ins project27 October 2026

Register for MEED’s 14-day trial access
Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.
Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields.
The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.
According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.
Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.
Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.
The project budget is estimated at $1.2bn.
Bidders for the contract are understood to have included:
- Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
- Jereh (China)
- Kalpataru Projects International (India)
- Matrix Construction (UAE)
- Robt Stone Middle East (UAE)
- Target Engineering Construction Company (UAE)
The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.
Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.
ALSO READ:
https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg -
Ashghal tenders Al-Udeid air base access road works27 October 2026

Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.
The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road.
The tender was issued on 22 October, with a submission deadline of 22 November.
The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.
Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.
The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.
The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.
The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.
Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.
The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.
Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.
Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.
For joint-venture bids, the lead partner must hold the required classification grade.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg