PPP activity eases back but remains strong

25 October 2024

 


This package also includesRegion remains global project finance hotspot


Public-private partnership (PPP) activity appears to be easing back in the Middle East and North Africa (Mena) region in 2024, with the total value of contract awards in the first nine months of the year coming in at $24bn, according to regional projects tracker MEED Projects.

This is 6.5% lower than the $25.6bn recorded in the same period a year earlier. The full-year total for 2023 then ended up at $41.3bn after a surge of activity in the final three months of the year.

While there are plenty of contract awards pencilled in for the final quarter of this year, too – including several large power and water projects in the Levant and the Gulf – at this stage, it appears unlikely that the gap to the record 2023 total will be bridged.

Among the projects with main contract awards due to be made before 31 December are a 10GW battery energy storage system (bess) in Saudi Arabia and the 3.7GW fifth round of the country’s renewable energy programme, both planned by Saudi Power Procurement Company.

Other major projects at a similar stage include a 10GW solar power project planned by the Renewable Energy & Energy Efficiency Organisation in Iran; the $4.3bn Aqaba-Amman water desalination and conveyance scheme backed by Jordan’s Water & Irrigation Ministry; and the $3bn, 2.3GW Facility E independent water and power project by Qatar General Electricity & Water Corporation (Kahramaa).

In total, 72 main contract awards are due to be made by the end of 2024 – almost as many as were handed out in the whole of 2023. However, there can be no certainty as to which ones will get over the line before the year’s end and which ones might suffer delays or cancellations.

Even without such projects, though, the number and value of contracts finalised in the first nine months of this year means 2024 is set to be one of the most active for PPP deal-making so far this century.

Other than last year’s record-setting run, the combined value of deals has not been this high since 2009, when a total of $29.6bn-worth of contracts were awarded. In terms of the number of awards, this year has also been among the most active. 

The 45 contracts handed out between January and the end of September is already above the annual average of 44 contracts a year over the past decade. It puts the year firmly on track to be among the top performing years in terms of the number of PPP contracts awarded. The surge in the past three years highlights the popularity that PPP deals are enjoying among Mena governments at present.

The average size of contract awards is also running well above the long-term figure, with the typical deal being worth $533m in 2024. This is down from the $574m figure of last year, but well ahead of any other performance in the past decade save the $556m figure in 2014.

Iraq, Saudi Arabia and the UAE lead

In terms of geography, the standout markets this year have been Iraq, with $11bn of PPP awards, followed by Saudi Arabia with $5.4bn and the UAE with $3bn. Between them, these three countries accounted for a total of 34 contract awards, or 75% of the figure for the whole of the Mena region in the opening nine months of the year.

Key contracts signed in these markets have included the $8bn Al-Faw refinery and petrochemicals complex in Iraq’s southern Basra province, which is being developed by the Southern Refineries Company; and a series of contracts
awarded by the National Investment Commission on seven lines of the $2.5bn Baghdad Metro.

In Saudi Arabia, there have been 15 awards across the transport, power and water sectors, including the 2GW Haden solar photovoltaic (PV) power plant, the 600MW Al-Ghat independent power producer (IPP) wind project, and expansion work at Prince Mohammad Bin Abdulaziz International airport in Medina.

In the UAE, the contract activity has been more varied, with awards in the power, water, transport, construction and industrial sectors. Among the biggest awards so far this year were a $1.5bn contract awarded by Emirates Water & Electricity Company for the 1.5GW Al-Ajban solar IPP in Abu Dhabi and a $682m contract awarded by Sharjah Electricity & Water Authority to Acwa Power for the Hamriyah seawater reverse osmosis independent water project.

Another market with high levels of activity this year is Egypt, where there has been $3.7bn-worth of contract awards, including a $2.2bn strategic warehousing scheme. The Damietta Port Authority also signed a $665m deal to deliver a second container terminal and a $500m award for the 1GW Benban solar PV power plant and 600 megawatt-hour bess in Aswan Governorate.

Bahrain, Oman, Qatar and Tunisia have each seen one or two awards apiece, with the individual awards being generally more modest in value.

Sectoral and contractual shift

On a sectoral basis, this year has seen an even broader spread of awards across different industries compared to last year.

In 2023, the power sector accounted for 55% of the total awards by value, with the water and transport sectors accounting for a further 39% between them.

This year, power has again been the main focus of activity, but its share of the total awards value has fallen to 30%, while the transport sector fell to 15%.

The chemicals and oil industries then inched ahead, with 17% each, split across the planned $8bn combined value of the Al-Faw refinery and petrochemicals complex in Iraq.

The water sector has meanwhile seen a sharp drop-off in awards, with deals in the first nine months of the year accounting for just 6.6% of the total.

These changes have contributed to another significant shift, with the type of contracts proving most popular also undergoing a change this year.

In 2023, most of the awards were either for build, own and operate or build-operate-transfer (BOT) contracts, which accounted for 34% and 32% of the total value of awards handed out, respectively. 

This was followed by build and operate and build-own-operate-transfer (BOOT) awards, worth a further 14% each.

This year, the activity has been led by BOOT contracts, which have totalled $9.2bn, or 38% of the total for the first nine months. This was driven again by the $8bn-worth of contract value accounted for by the Al-Faw Refinery in Iraq.

Following behind are BOT contracts with a total value of $5.4bn, representing 22% of the total, most of which has
been awarded in the power sector. Design-build-finance-operate-transfer contracts worth $5bn accounted for 21% of the total with the value split across the transport and industrial sectors.

The picture could yet change in the final quarter of the year. In recent years, the last three months have been the busiest period for contract signings. In 2021, 38% of the year’s awards were made in Q4, with this figure increasing to 66% in 2022, before receding again to 38% in 2023 – but yet again with more than a third of all awards being made in the last quarter.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12694682/main.gif
Dominic Dudley
Related Articles
  • Saudi water sector hits sharp slowdown

    8 September 2026

     

    Saudi Arabia’s water sector has recorded a sharp slowdown in contract awards this year, with $3.94bn of new contracts awarded as of early September.

    According to regional project tracker MEED Projects, this is well below the $10.7bn recorded in 2025, $13bn in 2024 and a record $15.3bn in 2023.

    The slowdown comes as several major projects remain in the procurement process, with some yet to reach financial close or contract award, while tender deadlines for other schemes have been pushed back.

    Among the largest is the estimated $2bn Riyadh-Qassim independent water transmission pipeline. The 859-kilometre project will have a transmission capacity of 685,000 cubic metres a day (cm/d). Vision Invest was selected as the preferred bidder last December; however, more than eight months later, an official developer’s agreement has not yet been signed.

    Similarly, the Arana and Hadda independent sewage treatment plant (ISTP) projects have yet to reach the financial close originally targeted for the second quarter. The two schemes will provide a combined treatment capacity of 350,000 cm/d.

    Delays extend further down the procurement pipeline. The latest developer bid deadline for the estimated $150m Riyadh East ISTP is 29 September, almost a year after the request for proposals (RFP) was issued in October 2025.

    Procurement for the main contracts for the Jubail-Buraidah and Ras Mohaisen-Baha-Mecca independent water transmission system projects could also slip into 2027, amid delivery-model changes by Water Transmission Company.

    New awards

    The market received a boost in September when Saudi Arabia’s National Water Company (NWC) announced it had signed a SR1.3bn ($347m) deal with a Saudi-Chinese consortium for package 10 of its long-term operations and maintenance programme.

    The consortium – comprising China’s Jiangsu United Water Technology and Saudi-based Armada Holding – will rehabilitate, operate and maintain nine sewage treatment plants (STPs) with a combined design capacity of more than 337,000 cm/d. Based on the latest procurement timeline, it is unclear whether the selected consortium for package 11 will be formally announced this year. Packages 12 and 14 remain under tender while package 16 is next in line, with its RFP not expected to be issued before November.

    NWC is the second-largest awarding entity by value in 2026, accounting for $1.09bn, or about 28% of the total. Saudi Aramco is the largest, with $2.15bn, meaning the two organisations account for more than 82% of awards so far this year.

    Aramco’s activity has been led by two major oil field developments. In June, it awarded the $1.5bn Safaniya onshore surface facilities project: package 1 to a joint venture of Tecnimont and Consolidated Contractors Company. The package includes a water treatment and injection plant supporting upstream production.

    It also awarded the second phase of its Zuluf water treatment project to a joint venture of Almar Water Solutions and AlJomaih Energy & Water. The project will add a 308,000-cm/d treatment facility at Tanajib in the Eastern Province, supplying water for injection at the offshore Zuluf oil field.

    The concentration of awards in industrial projects this year has been notable. Against the slowdown in municipal water infrastructure procurement, much of the value awarded so far has been linked to the water requirements of oil and gas and mining developments.

    The third-largest award is the $350m Taif Ar Rjum water pipeline project, being developed by Saudi Arabian Mining Company (Maaden) in Mecca. The project will support the Ar Rjum gold mining and processing facility and is being developed under a build-own-operate-transfer model. 

    By project type, treatment projects make up the largest share of awards, at $2.85bn or about 72% of the total. Transmission projects account for $980m and cooling projects for a further $110m, while no major desalination or water storage contracts have been awarded so far this year.

    Project pipeline

    The slowdown in awards appears to reflect the timing of projects moving through procurement rather than a fundamental weakening in demand for water infrastructure.

    Saudi Arabia continues to face rising demand for desalination, wastewater treatment and water transmission as population growth and industrial expansion drive demand for water.

    Sharakat, formerly Saudi Water Partnership Company, set out the next phase of the kingdom’s water investment programme in its latest seven-year statement, published in March.

    The plan points to a significant expansion in desalination capacity. Capacity from Sharakat-procured projects is expected to increase from about 3.88 million cm/d in 2025 to roughly 7.18 million cm/d by 2031.

    The increase will be supported by seven new independent water plants (IWPs) with a combined capacity of about 2.8 million cm/d, in addition to projects already operating, under construction or in procurement.

    However, several of the planned projects have yet to move into active procurement, while others have seen their expected timelines pushed back.

    Among the schemes affected are the Ras Al-Khair, Tabuk, Shuqaiq and Jizan IWPs, which have all progressed through prequalification, but have seen changes to their expected procurement schedules.

    The largest is phase two of the Ras Al-Khair IWP, a 600,000-cm/d reverse osmosis desalination plant that has been in development for more than a decade.

    The revised schedule indicates that the $400m Al-Shuqaiq 4 IWP is expected to be the first of the seven new plants to reach commercial operation. Its main contract had been expected to be tendered later this year, but it is now understood that the first RFP will not be issued until early 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19466739/main.gif
    Mark Dowdall
  • Kuwait grants loan for GCC grid extension study

    8 September 2026

    The Kuwait Fund for Arab Economic Development has signed a KD200,000 ($647,000) grant agreement with the GCC Interconnection Authority (GCCIA) to finance a feasibility study on extending the Gulf power grid to electricity networks outside the GCC.

    The agreement was signed on 3 September by Ahmed Bin Ali Al-Ibrahim, CEO of the GCCIA, and Kuwait Fund acting director general Rashid Al-Bader.

    The study will assess opportunities to expand the GCC power interconnection system to neighbouring countries. It will examine their electricity requirements and the technical and economic feasibility of connecting their national grids to the Gulf network.

    The Kuwait Fund did not identify the countries or potential interconnection routes. However, it is understood that the study will identify potential phases for future expansion, determine priority projects and assess the most appropriate interconnection options based on technical and economic criteria.

    It will cover the proposed project’s main components, costs, implementation arrangements and expected timeframe. The study will also assess the potential economic and social benefits for GCC member states and connected countries, as well as how the GCC network would operate alongside neighbouring national grids.

    A preliminary assessment of the project’s potential environmental and social impacts will also be carried out, together with proposed mitigation measures.

    The Kuwait Fund has previously provided three loans worth a combined KD78m ($252m) to GCCIA to support expansion of the GCC power interconnection system and its connection to southern Iraq’s electricity grid.

    In August 2025, the fund announced two loans worth KD70m ($224m) for the expansion of the Gulf Power Interconnection Project. The financing included support for the Al-Wafra 400kV substation and infrastructure connecting Kuwait’s grid with Iraq. 

    The Al-Wafra substation facilitates electricity exchanges and enables Kuwait to access surplus power available through the GCC interconnection system.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461053/main.jpg
    Mark Dowdall
  • Chinese firm to set up $300m anode facility in the UAE

    8 September 2026

    Beijing-headquartered Sunstone Development has signed a memorandum of understanding (MoU) with the UAE Ministry of Investment to develop an anode production facility in the UAE, with an estimated investment of about $300m.

    The MoU follows Sunstone’s December 2025 joint-venture agreement with Emirates Global Aluminium (EGA) to build the project.

    Upon completion, the plant is expected to replace most of EGA’s current anode imports and support the UAE’s ambition to become one of a limited number of global anode-exporting countries, aligning with the Make It In The Emirates initiative and Operation 300bn.

    The ministry said the agreement reflects its role in helping strategic investors navigate the UAE’s investment ecosystem and convert commitments into long-term operations, in line with the National Investment Strategy 2031.

    By localising a key stage in the aluminium value chain, the facility will reduce reliance on imported anodes, enhance the competitiveness of the UAE aluminium sector and support wider economic diversification.

    The Ministry of Investment and Sunstone will establish a joint working group, chaired by the ministry, to oversee project delivery.

    The project is expected to create skilled employment opportunities for UAE nationals and residents, while strengthening domestic manufacturing capacity and industrial capabilities.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461120/main.jpg
    Yasir Iqbal
  • Riyadh tenders Expo 2030 Souq areas package

    8 September 2026

     

    Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has tendered a contract to deliver the Souq areas within the Expo site.

    The tender was floated on 30 July, with a submission deadline of 9 October.

    The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).

    The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works. 

    The precincts comprise:

    • Precinct 1 – The Icon: 41,417 sq m
    • Precinct 2 – Place & Planet: 62,306 sq m 
    • Precinct 3 – Culture of Wisdom: 67,112 sq m  
    • Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m  
    • Precinct 5 – Adaptation & Innovation: 82,358 sq m

    The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.

    The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, providing a central connection between the site’s iconic and thematic assets.

    The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.

    Site progress

    Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.

    Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City (RCRC) awarded a design-and-build contract for the construction of a new metro station catering to the Expo 2030 site.

    In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Alyamama Company.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.

    That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19457171/main.jpg
    Yasir Iqbal
  • Powering the next chapter with nuclear energy

    8 September 2026

    Commentary
    Colin Foreman
    Editor

    Nuclear energy is increasingly being viewed as essential around the world. It offers a non-CO2-emitting, steady baseload at a time when governments have made net-zero commitments. 

    In the Gulf, the UAE has spent the past 15 years building the Middle East’s first commercial nuclear plant, now supplying about a quarter of the country’s electricity. What is new is the breadth of ambition beyond Abu Dhabi. The civil nuclear cooperation deal signed between Saudi Arabia and the US in July is the most significant step in the kingdom’s nuclear programme for several years, and it lands as the region moves decisively towards atomic power.

    The logic is clear. Electricity demand from industry, desalination and digital infrastructure is climbing, and governments want reliable low-carbon supply to meet it. Saudi Arabia is targeting up to 17GW of nuclear capacity by 2040. Its first plant at Khor Duwaiheen, comprising two 1.4GW reactors, represents only about a sixth of that goal, which points to a programme rather than a one-off.

    What is new is the breadth of ambition beyond Abu Dhabi

    The opportunity extends well beyond reactors. The UAE’s nuclear programme shows the scale of the economic impact. More than 2,000 local firms secured contracts worth over $6.7bn supporting construction, operations and maintenance. 

    Saudi Arabia’s ambitions reach further still, into small modular reactors, domestic uranium and elements of the fuel cycle. At the same time, Bahrain is studying a modular plant to power its industrial base, and Egypt’s 4.8GW El-Dabaa project is already under construction, with first generation expected in 2028.

    For contractors, engineers and financiers, this is the beginning of a projects market that will unfold over decades. The reactor awards will grab the headlines, but the supporting ecosystem, from regulation and fuel supply to workforce development, is where much of the value lies.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461185/main.gif
    Colin Foreman