Power tariffs have room to improve

2 October 2023

 

Click here for MEED's 2023 GCC power developer ranking

A number of variables affect private power production costs or tariffs in the GCC region. These include capacity, power-purchase agreement (PPA) duration, capital, development and fuel costs, as well as the expected internal rate of return by investors.

Between 2015 and 2020, solar photovoltaic (PV) projects in the GCC states benefitted from the rapid decline in module prices, low interest rates and large-scale projects.

During that period, solar independent power producer (IPP) projects managed to achieve world-record low tariffs. This trend peaked in 2021, when Saudi utility developer Acwa Power offered to develop the Shuaibah 1 solar IPP project for $cents1.04 a kilowatt-hour ($c/kWh).

Covid-19-related supply chain constraints triggered record-high solar PV module costs, as well as global inflation, setting tariffs on a different course. Former Acwa Power CEO Paddy Padmanathan warned in June 2022 that solar tariffs could be heading towards $c2.0/kWh, nearly twice the world’s lowest solar tariff achieved the year before.

More recently, a team of France’s EDF, UAE-based Abu Dhabi Future Energy Company (Masdar) and local firm Nesma offered $c1.68/kWh for Saudi Arabia’s 1,100MW Hinakiyah solar scheme. This is 62 per cent higher than the Shuaibah 1 tariff and only 39 per cent lower than the offer made for the 300MW Sakaka solar PV project in 2018-19.

A senior regional executive at France’s Engie, which has not bid for a single renewable energy project in the region since 2016, sees an opportunity in the current market and is planning to resume bidding for upcoming renewable energy projects, particularly wind IPPs.

“It is more sustainable, unlike what we have seen in the past, where there was a lot of competition, very few transactions and a high likelihood of projects incurring some losses,” Francois-Xavier Boul, Engie’s managing director for renewables in the Middle East and North Africa and head of business development for Africa, Middle East and Asia, told MEED.

Gas-fired tariff

Contracts for almost 7,000MW of private gas-fired capacity in Abu Dhabi and 1,500MW in Oman will expire between 2024 and 2030.

Negotiations between the offtakers and project companies will determine whether these contracts are extended and the plants are reconfigured, or terminated and the plants are dismantled.

This presents a double-edged opportunity for developers that have a significant gas-fired fleet. The termination of existing contracts requires private developers to win large new projects to offset lost capacity if they are to maintain or improve their current rankings or market share.

Unlike a public tendering process, direct negotiations are the norm for most brownfield IPP assets, which means offtakers and developers are not obliged to disclose prices.

Tariffs that bidders proposed in 2019 for Abu Dhabi’s Fujairah F3 IPP, the last gas-fired IPP contract awarded in the GCC, could provide a reference point in terms of future trends in gas-fired IPP tariffs.

At the time, Japan’s Marubeni, which eventually won the contract, submitted the second-lowest bid of AEDfils16.812 a kilowatt hour (AEDfils/kWh). Another team led by France’s Engie submitted the lowest bid of AEDfils16.7901/kWh for the F3 contract, while a team of France’s EDF and Japan’s Jera submitted a tariff price of AEDfils17.109/kWh.

The tariffs offered by bidders for Saudi Arabia’s Qassim and Taiba IPPs, once disclosed by Saudi Power Procurement Company, will confirm future gas IPP tariff trends. 

As things stand, a further decline for solar tariffs in the GCC, particularly in Saudi Arabia, may still be on the cards, according to Abdulaziz al-Mubarak, Masdar’s managing director and country manager for Saudi Arabia. “World-record-low levelised electricity costs are a result of the input for each project. The kingdom offers robust contractual agreements, good pre-development work and a robust local EPC ecosystem that these projects can tap,” he says. 

MEED's 2023 GCC power developer ranking

https://image.digitalinsightresearch.in/uploads/NewsArticle/11167570/main.gif
Jennifer Aguinaldo
Related Articles
  • Oman’s growth forecast points upwards

    24 December 2025

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15306449/main.gif
    MEED Editorial
  • December 2025: Data drives regional projects

    23 December 2025

    Click here to download the PDF

    Includes: Top inward FDI locations by project volume | Brent spot price | Construction output


    MEED’s January 2026 report on Oman includes:

    > COMMENT: Oman steadies growth with strategic restraint
    > ECONOMY: Oman pursues diversification amid regional concerns
    > BANKING: Oman banks feel impact of stronger economy
    > OIL & GAS: LNG goals galvanise Oman’s oil and gas sector

    > POWER & WATER: Oman prepares for a wave of IPP awards
    > CONSTRUCTION: Momentum builds in construction sector

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15306140/main.gif
    MEED Editorial
  • Local firm bids lowest for Kuwait substation deal

    22 December 2025

    The local Al-Ahleia Switchgear Company has submitted the lowest price of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare (PAHW).

    The bid was marginally lower than the two other offers of KD35.1m and KD35.5m submitted respectively by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.

    PAHW is expected to take about three months to evaluate the prices before selecting the successful contractor.

    The project is one of several transmission and distribution projects either out to bid or recently awarded by Kuwait’s main affordable housing client.

    This year alone, it has awarded two contracts worth more than $100m for cable works at its 1Z, 2Z, 3Z and 4Z 400kV substations at Al-Istiqlal City, and two deals totalling just under $280m for the construction of seven 132/11kV substations in the same township.

    Most recently, it has tendered two contracts to build seven 132/11kV main substations at its affordable housing project, west of Kuwait City. The bid deadline for the two deals covering the MS-01 through to MS-08 substations is 8 January.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305745/main.gif
    Edward James
  • Saudi-Dutch JV awards ‘supercentre’ metals reclamation project

    22 December 2025

    The local Advanced Circular Materials Company (ACMC), a joint venture of the Netherlands-based Shell & AMG Recycling BV (SARBV) and local firm United Company for Industry (UCI), has awarded the engineering, procurement and construction (EPC) contract for the first phase of its $500m-plus metals reclamation complex in Jubail.

    The contract, estimated to be worth in excess of $200m, was won by China TianChen Engineering Corporation (TCC), a subsidiary of China National Chemical Engineering Company (CNCEC), following the issue of the tender in July 2024.

    Under the terms of the deal, TCC will process gasification ash generated at Saudi Aramco’s Jizan refining complex on the Red Sea coast to produce battery-grade vanadium oxide and vanadium electrolyte for vanadium redox flow batteries. AMG will provide the licensed technology required for the production process.

    The works are the first of four planned phases at the catalyst and gasification ash recycling ‘Supercentre’, which is located at the PlasChem Park in Jubail Industrial City 2 alongside the Sadara integrated refining and petrochemical complex.

    Phase 2 will expand the facility to process spent catalysts from heavy oil upgrading facilities to produce ferrovanadium for the steel industry and/or additional battery-grade vanadium oxide.

    Phase 3 involves installing a manufacturing facility for residue-upgrading catalysts.

    In the fourth phase, a vanadium electrolyte production plant will be developed.

    The developers expect a total reduction of 3.6 million metric tonnes of carbon dioxide emissions a year when the four phases of the project are commissioned.

    SARBV first announced its intention to build a metal reclamation and catalyst manufacturing facility in Saudi Arabia in November 2019. The kingdom’s Ministry of Investment, then known as the Saudi Arabian General Investment Authority (Sagia), supported the project.

    In July 2022, SARBV and UCI signed the agreement to formalise their joint venture and build the proposed facility.

    The project has received support from Saudi Aramco’s Namaat industrial investment programme. Aramco, at the time, also signed an agreement with the joint venture to offtake vanadium-bearing gasification ash from its Jizan refining complex.

    Photo credit: SARBV

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305326/main.gif
    Edward James
  • QatarEnergy LNG awards $4bn gas project package

    22 December 2025

    QatarEnergy LNG, a subsidiary of state-owned QatarEnergy, has awarded the main engineering, procurement, construction and installation (EPCI) contract for a major package for the second phase of its North Field Production Sustainability (NFPS) project.

    A consortium comprising the Italian contractor Saipem and state-owned China Offshore Oil Engineering Company (COOEC) has secured the EPCI contract for the COMP5 package. The contract value is $4bn, with Saipem declaring its share to be worth $3.1bn.

    Milan-headquartered Saipem said the contract will run for about five years. The scope of work comprises engineering, procurement, fabrication and installation of two compression complexes, each including a compression platform, a living quarters platform, a flare platform supporting the gas combustion system, and the related interconnecting bridges. Each complex will have a total weight of about 68,000 tonnes.

    Offshore installation operations will be carried out by Saipem’s De He construction vessel in 2029 and 2030.

    MEED previously reported that the following contractors submitted bids for the NFPS phase two COMP5 package:

    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem/China Offshore Oil Engineering Company (Italy/China)

    QatarEnergy LNG, formerly Qatargas, is said to have issued the tender for the NFPS phase two COMP5 package in the first quarter of the year.

    Contractors submitted technical bids for the COMP5 package in late June, while commercial bids were submitted by 8 October, as per sources.

    Based upon initial evaluation of bids by QatarEnergy LNG, L&TEH has emerged as the lowest bidder for the COMP5 package, followed by McDermott, with the consortium of Saipem and COOEC in third place, MEED reported in late October.

    In the weeks following that, the project operator is said to have engaged all bidders for a final round of negotiations, during which the consortium of Saipem and COOEC is believed to have “clinched the deal”, according to sources.

    The detailed scope of work on the COMP5 package covers the EPCI work on the following:

    • Two gas compression platforms, each weighing 30,000-35,000 tonnes, plus jacket
    • Two living quarters platforms, plus jacket
    • Two gas flare platforms, plus jacket
    • Brownfield modification work at two complexes
    NFPS scheme

    QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme requires the state enterprise to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the estimated $40bn-plus programme.

    QatarEnergy has already invested billions of dollars in engineering, procurement and construction works on the two phases of the NFPS project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.

    The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.

    Saipem has been the most successful contractor on the second NFPS phase, securing work worth a total of $8.5bn.

    QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities. The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.

    The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.

    Following that, Saipem won combined packages COMP3A and COMP3B of the NFPS project’s second phase in September last year.

    The scope of work on the combined packages encompasses the EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

    Separately, QatarEnergy LNG awarded McDermott the contract for the NFPS second phase package known as EPCI 1, or COMP1, in July 2023. The scope of work on the estimated $1bn-plus contract is to install a subsea gas pipeline network at the North Field gas development.

    In March this year, India’s Larsen & Toubro Energy Hydrocarbon (LTEH) won the main contract for the combined 4A and 4B package, which is the fourth package of the second phase of the NFPS project and is estimated to be valued at $4bn-$5bn.

    The main scope of work on the package is the EPCI of two large gas compression systems that will be known as CP8S and CP4N, each weighing 25,000-35,000 tonnes. The contract scope also includes compression platforms, flare gas platforms and other associated structures.

    LTHE sub-contracted detailed engineering and design works on the combined 4A and 4B package to French contractor Technip Energies.

    NFPS first phase

    Saipem is also executing the EPCI works on the entire first phase of the NFPS project, which consists of two main packages.

    Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.

    QatarEnergy LNG awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.

    Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.

    The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.

    In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.

    QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.

    Saipem’s scope of work on the package, which is known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.

    Saipem performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305330/main2239.jpg
    Indrajit Sen