Oxagon takes centre stage at Neom
29 September 2026

For all the talk of cancellations, Neom completed its biggest project yet in August, commissioning the $8.5bn Neom Green Hydrogen project.
The project reflects Neom’s reprioritisation, which has seen the $500bn gigaproject shift from a speculative vision towards a delivery-focused industrial development.
This shift was clearly signalled in April, when Public Investment Fund (PIF) governor Yasir Al-Rumayyan publicly backed Oxagon, Neom’s planned industrial and manufacturing hub on the Red Sea coast. Since then, there have been increasing signs that the development is taking precedence over the rest of the giga-portfolio.
Announced strategy
Al-Rumayyan’s remarks, delivered as PIF unveiled its 2026-30 strategy, were the clearest public articulation yet of where the fund’s priorities lie. Asked whether The Line needed to be delivered, he was blunt: it would be good to have, but it was not essential.
Oxagon, on the other hand, was described as “the fundamental part of Neom”.
The comment reframed two years of speculation about scaled-back ambitions at Neom into something closer to a strategic decision, with capital following the assets capable of generating revenue, and the industrial city sitting at the top of that list.
The shift in language also matters, since PIF has been at pains to stress that no Neom projects have been formally cancelled, even as billions of dollars of contracts have been terminated or re-scoped over the past two years.
Under the new strategy, Neom has effectively been reclassified as its own reporting line within PIF’s portfolio, separated from the fund’s other domestic holdings. That separation gives Oxagon room to be judged on its own commercial merits, while distancing it from the reputational weight still carried by more conceptual elements of the wider development.
There have been increasing signs that Oxagon is taking precedence over the rest of the giga-portfolio
Conflict acceleration
The reprioritisation was already under way before the region’s latest conflict began. PIF has spent the past two years pushing Neom to identify which elements of the gigaproject were fundamental and which were aspirational, a process that has as much to do with capital discipline as geopolitics.
With the fund committing to direct roughly 80% of its $925bn portfolio towards domestic investment, while simultaneously funding Expo 2030 and the 2034 World Cup, Riyadh needed its flagship projects to start showing commercial returns rather than absorbing capital indefinitely.
Oxagon, with a port, an export-ready hydrogen plant and land that could be leased to industrial tenants, was always the part of Neom best placed to answer that requirement, and the regional conflict that began in late February only accelerated the shift. The closure of the Strait of Hormuz to a fraction of its normal commercial throughput has hit Saudi Arabia’s oil export capacity hard and pushed the kingdom into a sizeable quarterly fiscal deficit.
Riyadh has also had to contend with direct disruption to its own energy infrastructure, including the temporary closure of the East-West oil pipeline following drone strikes. Against that backdrop, an industrial city with its own deep-water port on the Red Sea, outside the Strait of Hormuz chokepoint, has taken on added strategic weight.
Oxagon offers the kingdom a second maritime gateway, one that is not exposed to the same geopolitical risks as the Gulf coast terminals that have historically carried Saudi trade. For a government having to defend every riyal of committed capital spending, a project that can plausibly generate port fees, hydrogen export revenue and data-centre hosting income within the current decade is a far easier sell than a 170-kilometre linear city that is still taking shape.
Construction ramps up
The clearest evidence of that pivot is what has actually broken ground at Oxagon recently. At a time when Neom’s recent news flow has been about contract terminations, Oxagon’s has been about starts.
The most visible of these is the artificial intelligence (AI) data-centre campus being developed by Humain, the PIF-owned AI company, in partnership with digital infrastructure developer DataVolt.
Construction on the first 100MW of a planned 360MW first phase began this year, as part of a wider 1.5GW campus that builds on the companies’ original 2025 agreement, backed by roughly $5bn of investment. The facility is designed to draw on Oxagon’s pre-zoned industrial land, renewable power and subsea cable links to Europe and Africa, with the first 100MW targeted for service in 2028.
For Neom, the project answers a question that has dogged the gigaproject for years: namely, what, beyond real estate and tourism, Oxagon actually sells.
Connectivity is following the same pattern. Neom issued an expression of interest in September for consultancy services to plan a freight rail line of more than 400km linking the Port of Neom at Oxagon to Saudi Arabia Railways’ North-South Railway at the Al-Baseeta junction.
The North-South network currently serves the kingdom’s phosphate and bauxite mining sector, running from Al-Jalamid and Baitha to the Gulf coast industrial cluster around Ras Al-Khair, Jubail and Dammam, with branches to Riyadh and the Jordanian border.
A connection to Oxagon would give that network a second maritime outlet on the Red Sea and would finally give the Port of Neom a direct rail link into the kingdom’s interior, something it has lacked since operations began in 2022.
Cargo currently depends on road transport or an additional sea leg, a constraint that has limited the port’s usefulness beyond a regional hub.
Utilities work is quietly keeping pace with the more visible projects. Neom has tendered an industrial wastewater treatment plant at Oxagon, with proposals due in early October. The scheme has an initial capacity of 35,000 cubic metres a day, (cm/d) expandable to a maximum of 45,000 cm/d as demand grows.
The plant is expected to cater to the wider industrial developments planned at Oxagon and points towards it developing into a full-fledged industrial cluster rather than a single-phase development.
Road infrastructure has moved in parallel. A design-and-build tender is currently out for the permanent upgrade of Oxagon’s Highway 55, which connects the Red Sea coast with the mainland in northwestern Saudi Arabia.
It currently serves as the only road providing north-south connectivity between Duba and the Neom region. The project is expected to support the anticipated increase in construction activity at Oxagon and facilitate the movement of cargo vehicles from Duba Port to other parts of the country and the wider region.
These construction packages represent the unglamorous groundwork needed before an industrial city can function at scale, and that foundational build-out is already being mirrored in Neom’s external connectivity. In April, a new multimodal logistics corridor linking Europe, Egypt, Neom and the GCC was enabled, offering a faster and more flexible route for European cargo entering the region.
The most advanced element of the build-out remains the port itself. Dutch marine contractor Boskalis has completed the deepening and widening of the main access channel, and Belgian contractor Besix has finished more than 4.6km of quay wall across seven berths, some with draughts of up to 18.5 metres.
The Terminal 1 development, a 900-metre, fully automated container facility designed to be one of the first ports in the kingdom to use automated ship-to-shore cranes, is being phased in through 2026. This will take capacity from the port’s current 250,000 twenty-foot equivalent units (TEUs) towards a 2030 target of 1.5 million TEUs, and an eventual ambition of 12 million TEUs once fully built out. The facility has been described as an accelerator for the kind of integrated, end-to-end supply chain the wider Oxagon concept was built around.
A development this capital-intensive will require continued private and foreign investment
Project rationale
Set against the rest of Neom’s portfolio, Oxagon’s advantage stands out. It has the potential to produce things that can be sold, shipped or leased within a timeframe investors and government auditors can underwrite.
Green hydrogen converted into green ammonia for export; port capacity sold by the container; data-centre capacity sold by the megawatt; industrial land leased by the hectare. These are conventional infrastructure economics, not the largely unprecedented urban-planning bet represented by The Line or other components of the wider Neom masterplan.
There is also a coherence to Oxagon’s individual pieces that is harder to find elsewhere in the Neom story. A port needs rail and road connections to move cargo inland. An AI data-centre campus needs power, land and subsea connectivity – things an industrial port city is well placed to provide. A green hydrogen plant needs an export terminal close by. Each project reinforces the case for the others, in a way that an industrial city announced in 2021 as one vision among several has arguably never quite managed to replicate.
Oxagon is not without risk. Schedules have already slipped once, and a development this capital-intensive will require continued private and foreign investment if its backers are serious about reducing direct funding exposure.
The direction of travel this year has been positive. With the green hydrogen plant entering commissioning, a hyperscale AI campus breaking ground, a new rail corridor being planned and a port moving towards its next phase, Oxagon is reinforcing its position as one of the kingdom’s flagship projects for the future.
Exclusive from Meed
-
Algeria tenders 310km Tamanrasset railway16 October 2026
-
Joint venture wins $246m RCRC bridges contract16 October 2026
-
Humain tenders 100MW Riyadh AI data centre16 October 2026
-
Adnoc Onshore seeks bids for Bu Hasa field EOR project16 October 2026
-
OTTCO issues tender for Oman oil storage park expansion16 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Algeria tenders 310km Tamanrasset railway16 October 2026

Algeria’s state railway project developer, Agence Nationale d’Etudes et de Suivi de la Realisation des Investissements Ferroviaires (Anesrif), has invited national and international contractors to bid for the construction of a 310-kilometre (km) railway line between Hotel Station and Moulay Lahcen Station.
The planned line is a key segment of the proposed railway corridor connecting El-Menea, In-Salah and Tamanrasset across the southern wilayas of In-Salah and Tamanrasset.
The tender notice was issued on 12 October, with bids due by 10 November.
The tender is open to single contractors and consortiums. To qualify, single firms must have executed at least 200km of new railway lines or track-doubling works since 2010, with accepted project certificates covering sections of at least 100km, along with a cumulative 800 metres of railway bridges with individual spans exceeding 30 metres.
Bidders must also provide at least two rail-tamping machines, two ballast regulators, and a project director with an engineering degree and at least five years of railway construction management experience.
From a commercial and classification perspective, single bidders and consortium leaders must hold a category-nine (IX) professional qualification in public works.
Bidders must also demonstrate an average annual turnover in construction of at least DZ260bn ($1.96bn) across the 2023-2025 financial period.
For joint ventures, the cumulative turnover of all members must meet the $1.96bn threshold, with the consortium leader accounting for at least $1.3bn.
Offers must be accompanied by a bid bond exceeding 1% of the total bid value for submissions exceeding $7.4m, with proposals remaining valid for 90 days beyond the submission date.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20665591/main.jpg -
Joint venture wins $246m RCRC bridges contract16 October 2026

A joint venture of local contractor Mofarreh Group and Turkey-based Gulsan Holding has won an estimated SR923m ($246m) contract from the Royal Commission for Riyadh City (RCRC) to construct a series of grade-separated steel flyovers across the capital.
The contract, known as Package 2 (Groups 2 and 3), is part of RCRC’s urgent bridges programme under the wider project to build steel bridges at 10 junctions across Riyadh.
The works have a 12-month execution timeline to fast-track traffic decongestion across major arterial corridors.
The joint venture’s scope covers the engineering and construction of grade-separated steel bridge interchanges across seven key intersections:
- IC04: Al-Khair Road and King Salman Bin Abdulaziz Road
- IC05: Prince Turki Road and Imam Saud Road
- IC06: Al-Takhassosi Road and Saeed Al-Sulami Road
- IC07: Khurais Road and Al-Hareth Bin Abdullah Road
- IC08: Khurais Road and Ash-Sharq Road
- IC09: Khurais Road and Marmar Road
- IC10: Al-Kharj Road and Al-Hilla Road
The total length of the flyovers is 8.86 kilometres, excluding Junction IC10.
In addition to the structural steel superstructures, concrete bridge foundations, decks and approach ramps, the contract includes retaining walls, utility diversions, temporary phased traffic arrangements, associated roadworks, drainage networks, roadway lighting, intelligent transportation systems and landscaping.
The client received commercial proposals from several local and international contractors. Other bidders included:
- Masco
- Nesma & Partners
- Al-Omaier Trading & Contracting Company
- Yuksel Saudia
- Batco
- Modern Building Leaders
- Sapac
The urgent bridges initiative is part of Riyadh’s rapid transport infrastructure programme to improve traffic throughput, enhance safety and ease vehicular congestion across central and ring-road corridors ahead of major events, including Expo 2030 and the 2034 Fifa World Cup.
In July, Mofarreh Group and Turkiye’s Gulsan Holding formed a joint venture to bid for and deliver transport infrastructure projects in Riyadh for RCRC.
The joint venture said it will target road, bridge, viaduct and interchange projects.
Mofarreh will provide local market access and operational capacity, while Gulsan will contribute international experience in large-scale transport projects.
The companies said the new venture will support knowledge transfer and localisation, and promote the use of international engineering and construction standards aligned with Saudi Arabia’s Vision 2030 infrastructure and sustainability goals.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20663255/main.png -
Humain tenders 100MW Riyadh AI data centre16 October 2026

Register for MEED’s 14-day trial access
Saudi artificial intelligence infrastructure developer Humain has issued a request for proposals for an engineering, procurement and construction (EPC) contract to deliver a 100MW artificial intelligence (AI) data centre facility in Riyadh’s Al-Saad area.
The tender was issued on 17 September, with bids due by 8 November.
The contract includes core-and-shell works; civil works; mechanical, electrical and plumbing installation; testing and commissioning; and site infrastructure across a 350,200-square-metre plot.
The project also includes an optional expansion phase that could raise total site capacity to 200MW.
The initial 100MW development is split into two equal 50MW phases, structured across two single-storey IT buildings housing four 25MW data halls.
Phase one targets a ready-for-service date by October 2028, followed by phase two in January 2029.
Under the optional phase three, an additional 100MW facility would be brought online by July 2029.
The data centre will be designed to support high-density graphics processing unit clusters and AI-compute workloads, with rack densities of 240kW to 250kW.
The facility will be built to Uptime Institute Tier III topology and LEED Silver standards as a baseline, targeting LEED Gold.
The operational design targets an annualised power usage effectiveness below 1.35.
Power will be delivered through four 33kV connections supplied by Saudi Electricity Company from two separate high-voltage/medium-voltage primary substations. The scope requires 15 transformers, 15 static 2,250kW IT uninterruptible power supply (UPS) units, and 450kW mechanical UPS systems with lithium-ion battery storage for each 25MW block.
Backup emergency diesel generators will be provided on an owner-furnished, contractor-installed basis, with the EPC contractor handling their installation, connection and testing. Fuel storage will provide 24 hours of autonomous run-time, split between on-site underground bulk tanks and generator belly tanks.
Thermal management combines air and liquid cooling. High-density server racks will be equipped with direct-to-chip liquid cooling loops using coolant distribution units and technical water distribution, paired with air-cooled chillers operating in dual high- and low-temperature loops, alongside fan-wall units.
The total construction timeline is capped at 25 months from site handover or contract signing, with pre-execution early mobilisation scheduled to start in January 2027.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20661045/main.jpg -
Adnoc Onshore seeks bids for Bu Hasa field EOR project16 October 2026

Register for MEED’s 14-day trial access
The onshore oil and gas business of Abu Dhabi National Oil Company (Adnoc Onshore) has sought bids from contractors for a key project to increase the oil production capacity of the Bu Hasa oil field, primarily through enhanced oil recovery (EOR) techniques.
The main objective of the Bu Hasa-Shuaiba EOR Unit 1 (Phase 1) project is to achieve a targeted 70% increase in oil production, extend the Bu Hasa field development’s production plateau and maximise the field’s potential in an economical manner.
The project aims to confirm and validate the optimum EOR technology for the top-ranked reservoirs/units; assess incremental recovery on top of the improved oil recovery (IOR) wedge; extend the field plateau for as long as is economically feasible; and achieve an ultimate recovery factor of 70% from the Shuaiba reservoir. It will evaluate and execute the recommended EOR option through pattern phasing for any technology proven by Adnoc.
Adnoc Onshore is understood to have issued the tender for the project on 20 September, with an initial technical bid submission deadline of 8 October, according to sources. The client later extended the technical bid submission deadline to 17 October, sources told MEED.
The chosen contractor will execute the project under a hybrid contracting strategy comprising:
- A lump sum (turnkey) EPC scope covering the complete pipeline system from East Hub to the separation plant
- A call-out-based scope for execution of all WAG injector and WSW tie-in works
Unless otherwise specified, all activities defined under the contractor’s scope will be deemed included within the lump-sum contract price. This will cover engineering, procurement, construction, testing, pre-commissioning and support to commissioning for a complete and operable system.
At the Bu Hasa field development, three remote degassing stations (RDS-1/2/3) and two satellite stations, Bida Al-Qemzan and Huwaila, are currently in operation. Production from oil wells completed in Shuaiba, Thamama B, Thamama F, Bida Al-Qemzan and Huwaila is routed via individual flowlines to the three remote degassing stations and the Bida Al-Qemzan and Huwaila stations across different parts of the field.
Combined production from the wells at each of these stations is routed to the central degassing stations (CDS) via transfer lines ranging from 16 inches to 24 inches in diameter. In addition, some wells in the central part of the field are connected directly to the CDS.
Previous studies have identified carbon dioxide (CO2) flooding as a promising tertiary recovery mechanism in the Shuaiba reservoir, delivering incremental recovery on top of the IOR wedge (P5 project), extending the field plateau as long as economically feasible, and achieving an ultimate recovery factor of 70% from the Bu Hasa Shuaiba units.
Located 200 kilometres south of Abu Dhabi city, Bu Hasa is Adnoc Onshore’s westernmost producing field. It is one of Abu Dhabi's biggest onshore assets, with crude oil production capacity of 650,000 b/d. It is also one of the Adnoc Group’s oldest oil fields, having been discovered in 1962 and in production since May 1965.
As part of the ongoing Bu Hasa Integrated Field Development Project (BUIFDP), 13 new well pads and two pad hubs have been added to the field. Oil, gas and water produced at these sites will be collected at a central gathering facility, then sent through production headers and transfer lines to the CDS for processing.
Adnoc Onshore is the Adnoc Group’s largest oil-producing subsidiary, accounting for 2 million b/d of oil and about 7 billion cubic feet a day of associated gas production from four main onshore field developments in Abu Dhabi: Bab, Bu Hasa, North East Bab and South East.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20639750/main0548.jpg -
OTTCO issues tender for Oman oil storage park expansion16 October 2026

Register for MEED’s 14-day trial access
Oman Tank Terminal Company (OTTCO) has issued the main tender for a major project related to the expansion of the Ras Markaz crude oil storage complex at Duqm, on the sultanate’s Arabian Sea coast.
The project, titled Trade Bridge, involves the engineering, procurement and construction (EPC) of eight large storage tanks, each with a capacity of 650,000 barrels. This will increase the Ras Markaz terminal’s total storage capacity by 5.2 million barrels.
The project represents the next expansion phase (phase 1.4) of the Ras Markaz oil storage terminal within the Special Economic Zone at Duqm (Sezad).
State-owned OTTCO issued the prequalification notice for the project on 28 July, with contractors submitting initial responses by 4 August and final responses by 19 August, MEED previously reported.
According to sources, OTTCO issued the main tender for EPC works on Project Trade Bridge in the weeks following completion of the prequalification exercise.
The following contractors, among others, are understood to have been prequalified by OTTCO to bid for Project Trade Bridge:
- China Petroleum Pipeline Engineering Company (China)
- China Tianchen Engineering Corporation (China)
- Daqing Oilfield Construction Group Company (China)
- Enppi Muscat (local branch of Egypt-based Enppi)
- Gulf Petrochemical Services & Trading (Oman)
- Hualu Engineering & Technology Company (China)
- Rotary Engineering (Singapore)
- Sinopec Ningbo Engineering Company (China)
OTTCO commissioned the first phase of the Ras Markaz crude oil storage park, covering 10 square kilometres and with a capacity of 26.7 million barrels, in December 2022.
The storage facility has two parts. The first is a marine services area, which includes a floating station for crude imports and exports. This zone is about 7 kilometres offshore and is connected via two 42-inch pipelines and associated facilities.
In water depths of up to 42 metres, the floating station can accommodate very large crude carriers. It is linked to four main pumps that transfer crude oil to the storage area, which is located more than 120 metres above sea level. OTTCO could add pumps at a later stage to keep pace with future demand for oil storage.
The second part of the storage facility features oil pumping systems, water treatment facilities, reservoirs, power station networks and other associated systems.
Region’s largest oil storage park
OTTCO will build the Ras Markaz oil storage facility in five phases over several years across an area of about 40 square kilometres, for which it signed a land agreement with Sezad in July 2017.
It will be able to hold 200 million barrels of crude a year. Total investment in the scheme is understood to be $5.2bn.
The storage terminal in the first phase of the Ras Markaz facility is connected to the estimated $7bn Duqm refinery and other oil-derivatives production plants at Sezad via a pipeline that will supply crude feedstock to the refinery when required.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20638090/main0749.jpg