Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Sharjah developer launches Al-Mamzar towers scheme

    9 June 2026

    Local real estate developer Alef Group has launched a mixed-use development in the Al-Mamzar area of Sharjah. The Linar project is valued at AED4bn ($1.1bn) and comprises five residential towers and one commercial tower. Across the development, the 50- to 55-floor towers will offer a total of 2,620 residential units.

    With 325 metres of sea-facing frontage overlooking Al-Mamzar Beach, the development also includes retail and service spaces. Tower A, which forms part of Phase 1 of the project, is expected to be completed from 2030 onwards. 

    In a statement, the developer said that following strong demand for expressions of interest (EoIs) in Tower A, Alef Group expanded EoIs to include towers B and C. All Phase 1 EoIs have now been fully reserved, representing a total of 1,572 residential units with a combined value of over AED2bn. The group is preparing to open EoIs for towers D and E.

    In April, Alef Group awarded Abu Dhabi-based construction firm A&M International a AED750m contract to build the next phases of its Hayyan residential community in Sharjah. The scope includes the construction of more than 700 villas and townhouses across three clusters – Samr 1, Samr 2 and Deem – along with Hayyan Mall, a clubhouse and associated infrastructure works.

    The Hayyan masterplan includes seven residential clusters: Alma, Arim 1, Arim 2, Arim 3, Samr 1, Samr 2 and Samr 3.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17157150/main1720.jpg
    Colin Foreman
  • Record investment drives Jordan’s utilities market

    9 June 2026

     

    In April, Jordan signed the final technical and legal agreement for its landmark National Water Carrier Project, paving the way for the financial close of the kingdom’s largest planned water infrastructure project to date.

    The agreement represents a significant step forward for the scheme, which is now projected to reach $5.6bn in total costs, including financing, up from earlier estimates of $3.5bn.

    Paris-based investment and utility firms Meridiam and Suez were awarded the contract last year to develop the project in partnership with Jordan’s Water & Irrigation Ministry.

    Since then, multiple large-scale financing agreements have been put in place for the project, which is expected to supply about 40% of Jordan’s drinking water needs.

    While new contract awards have been limited in 2026, the successful execution of the Aqaba-Amman Water Desalination and Conveyance scheme will help reassure the market that large-scale infrastructure projects of this nature can move forward.

    The project is set to reduce the benchmark water cost from about $3 a cubic metre in 2024 to approximately $2.7 and is crucial to addressing Jordan’s severe water scarcity.

    Prime Minister Jafar Hassan recently said that the scheme, along with the Aqaba Port railway project, represented “the largest level of foreign investment in the kingdom’s history”.

    For its part, the government has said it will contribute $722m to the Aqaba-Amman project, representing the largest single capital expenditure in the state budget.

    Upcoming projects

    Looking forward, there is a healthier pipeline of new water projects, led by a two-phased wastewater treatment project at Wadi Zarqa.

    The first phase will have an initial capacity to treat 150,000 cubic metres a day (cm/d) of wastewater by 2030.

    The $150m second phase covers an independent sewage treatment plant with a capacity of 200,000 cm/d. Both tenders are expected to be released in the coming months.

    Two larger projects, valued at $300m each, are currently in the planning stages. Both are managed by Yarmouk Water Company and involve major transmission pipeline works in Ajloun and Irbid as part of the Jordan Water Sector Efficiency Project.

    The Jordan Water Sector Efficiency Project is a World Bank-backed programme aimed at reducing water losses, improving utility performance and enhancing the efficiency of water services across the kingdom.

    Power contracts

    Jordan’s power sector is set for a record-breaking year following the announcement that a $900m combined-cycle gas turbine (CCGT) plant will be developed in partnership with Etihad Development Company, a subsidiary of the UAE’s Etihad Water & Electricity (EtihadWE).

    The project will be developed under a build-own-operate model with Jordan’s National Electric Power Company (Nepco) purchasing electricity under a 25-year power-purchase agreement.

    For context, Jordan’s power sector saw just $33m in total contract awards in 2025, according to MEED Projects.

    The full-year total last exceeded $100m in 2022, when there were $111m of contract awards. The plant is expected to meet about 10% of Jordan’s electricity demand once operational.

    The kingdom has also been looking at other forms of power generation, such as Jordan’s first 450MW pumped hydroelectric energy storage project near Al-Mujib Dam.

    Earlier this year, US-headquartered K&M Advisors and France’s Artelia were appointed as transaction advisers to carry out the final feasibility study for the project, which is expected to be tendered in the third quarter of 2026.

    The Ministry of Energy & Mineral Resources (MEMR) is also planning to undertake the construction of a 1,000MW wind power plant and battery energy storage system near the Port of Aqaba in Jordan.

    The renewable energy scheme could potentially support the kingdom’s emerging green hydrogen industry, including a separate planned $1bn green ammonia and hydrogen project in Aqaba.

    In May, the project became the first publicly announced green ammonia project in Jordan to receive development approval from the Council of Ministers.

    The project would be developed by Jordan Green Ammonia, a special-purpose vehicle funded by the UAE-based 7Fidelity Group and Poland’s Hynfra.

    The project in Aqaba is expected to produce 100,000 tonnes a year of green ammonia from 2030

    Of approximately $6bn-worth of power projects in the pre-execution phase, it is worth noting that about $4.4bn are still in the early study or feed stages.

    Near-term awards are likely to come from several smaller substation and power generation schemes.

    Jordan-Syria power link

    Among the wider pipeline of regional opportunities, Jordan’s power sector could also benefit from efforts to restore electricity connectivity with neighbouring Syria.

    Syria’s Public Establishment for Transmission & Distribution of Electricity recently tendered a contract to repair the 400kV high-voltage interconnector transmission lines between the two countries.

    The works form part of Syria’s $146m Electricity Emergency Project, which is being financed through a World Bank grant and aims to restore critical electricity infrastructure across the country.

    The rehabilitation of the Syria-Jordan interconnector is expected to enable the import of up to 600MW of electricity and represents one of several initiatives under way to rebuild Syria’s power network following years of conflict and underinvestment.

    More broadly, Syria is emerging as an active power market in its own right. In April, Germany’s Siemens Energy signed manufacturing agreements for major power plant projects being developed by a consortium led by Qatar’s UCC Holding.

    The contracts cover combined-cycle power packages for the Zayzoun and Deir Azzour power plant projects, announced last year as part of a $7bn memorandum of understanding between the consortium and Syria’s Ministry of Energy.

    The May 2025 agreements include four combined-cycle gas turbine power plants in Traifawi, Homs and Zayzoun, Deir-Azzour and Mehardeh in Hama with an installed capacity of 4GW.

    Additionally, a 1GW solar power plant will be developed in Wedian Al-Rabee in Syria’s southern region.

    Most of these projects, awarded under concession agreements following a strategic memorandum of understanding framework, are due to come online in 2029.

    After years of inactivity, this is considerable progress. The next step is attracting sufficient interest in new and upcoming tenders. This will signal whether international contractors are ready to re-engage with the country’s power sector.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17157016/main.gif
    Mark Dowdall
  • PIF-owned Ardara tenders Al-Wadi sewer package

    9 June 2026

     

    Ardara, a subsidiary of Saudi Arabia’s Public Investment Fund (PIF), has issued a tender for the trunk sewer diversion and associated works package at its Al-Wadi development in Abha in Saudi Arabia’s Asir region.

    The scope includes the construction of rainwater and flood drainage networks, roads and transport infrastructure, and associated works within the wider Al-Wadi project.

    The bid submission deadline is 15 June.

    The sewer diversion package, valued at about $20m, is part of Ardara’s wider Al-Wadi development in Abha. The company, launched by PIF in 2023, is developing the 2.5-square-kilometre Al-Wadi destination in Abha as a mixed-use tourism and lifestyle development. The project will include residential, hospitality, commercial and recreational assets. 

    As MEED understands, the sewer diversion works are expected to facilitate the development of future phases of the Al-Wadi project by relocating existing wastewater infrastructure within the site.

    The tender follows demolition works completed on the site last year.

    Previously, in 2024, US-based Parsons was appointed to provide project management and supervision services for the project.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17156098/main.jpg
    Mark Dowdall
  • Abu Dhabi selects team for 3.3GW Al-Nouf IPP

    9 June 2026

     

    State utility Emirates Water & Electricity Company (Ewec) has selected a preferred developer and contractor for the 3.3GW Al-Nouf independent power producer (IPP) project in Abu Dhabi, according to sources.

    Located within the newly established Al-Nouf complex, the facility will be the largest single-site, carbon-capture-ready, combined-cycle gas turbine plant in the UAE. 

    Japan’s Sumitomo Corporation has been selected as the preferred developer, with the power-purchase agreement (PPA) expected to be signed in the coming weeks, sources said.

    It is also understood that a joint venture of Spain’s Tecnicas Reunidas and Egypt’s Orascom Construction has been picked as the preferred engineering, procurement and construction (EPC) contractor.

    Three developer consortiums submitted bids earlier this year, along with Sumitomo as the only company to bid individually.

    The bidders included:

    • Aljomaih Energy & Water (Saudi Arabia) / Sembcorp Industries (Singapore) / EDF Power Solutions (France)
    • Engie (France) / Korea Overseas Infrastructure & Urban Development Corporation (Kind) / Korea Western Power Company (Kowepo)
    • Korea Electric Power Corporation (Kepco) / Etihad Water & Electricity (EtihadWE) (UAE)
    • Sumitomo (Japan) 

    Ewec issued a request for proposals for the project last August. It had previously received statements of qualifications for the contract in April 2025.

    This follows confirmation earlier this month that Ewec has signed a PPA with a developer consortium for the 2.5GW Taweelah C IPP project.

    A team of UK-based Alderbrook Finance and US-based Sargent & Lundy is providing financial and technical advisory services to Ewec for the Taweelah C IPP.

    As MEED previously reported, both projects are following the model of Abu Dhabi’s IPP programme, in which developers enter into a long-term agreement with Ewec as the sole procurer. 

    This involves the development, financing, construction, operation, maintenance and ownership of the plant, with the successful developer or developer consortium owning up to 40% of the entity. The remaining equity will be held indirectly by the Abu Dhabi government.

    The project site for the Al-Nouf plant was selected for its ability to accommodate both seawater-cooled power generation and reverse osmosis desalination technologies. The plant will have the capacity to support several utility-scale energy and desalination projects in the future.

    The facility is scheduled to begin commercial operations in the third quarter of 2029.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17155245/main.jpg
    Mark Dowdall
  • Zoom launches new Saudi data centre at center3

    9 June 2026

    Zoom has announced a new data centre in Saudi Arabia to boost in-kingdom capacity for government and enterprise customers requiring local data residency.

    In a statement, Zoom said the data centre is located within center3, a Saudi-headquartered provider of carrier-neutral data centres and subsea cable systems linking Europe, Asia and Africa. Zoom said the data centre builds on its broader investment plans in the kingdom, including a $75m commitment made last year focused on artificial intelligence (AI)-enabled innovation and the advanced infrastructure required to scale it.

    Zoom said its existing regional data centre, established in 2023, already supports customers with local data residency requirements, while the new site will enhance services for government entities, enterprises and critical national infrastructure organisations.

    AI is an important part of Saudi Arabia’s economic growth plans leading up to 2030. In January, government officials confirmed that as the global economy is evolving rapidly with the rise of AI, some projects such as The Line at Neom have slowed down, while other projects related to the World Cup, Expo 2030, technology and AI have accelerated. 

    The largest AI project in the kingdom is being developed by Humain, which is owned by the Public Investment Fund (PIF). In May, it issued a tender inviting firms to develop infrastructure for its planned 6GW hyperscale AI data centre campus in Riyadh.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17155250/main.jpg
    Colin Foreman