Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Local firm executing Yasref tail gas treatment project14 April 2026
-
Kuwait sets April deadline for $718m drainage tender14 April 2026
-
Local firm makes hydrocarbon discovery in Oman’s Block 714 April 2026
-
-
Saudi firm wins $64.2m steel pipe orders from Aramco14 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Local firm executing Yasref tail gas treatment project14 April 2026

Yanbu Aramco Sinopec Refining Company (Yasref) is overseeing progress on a key project to build a tail gas treatment unit (TGTU) at its crude refinery complex, located in Yanbu on the west coast of Saudi Arabia.
Yasref is a joint venture in which Saudi Aramco owns the majority 62.5% stake and China Petroleum & Chemical Corporation (Sinopec) owns the other 37.5%. The Yasref refinery was commissioned in 2015 and has a crude oil refining capacity of 400,000 barrels a day (b/d).
The aim of the project, which Yasref calls the tail gas synergy project, is to significantly reduce emissions of sulphur dioxide (SO₂) and hydrogen sulphide (H₂S) from its production complex. The 'synergy' comes from integrating primary treatment (such as the Claus process, which typically recovers about 95-97% of sulphur) with advanced secondary treatment in a TGTU, to achieve overall sulphur recovery of nearly 99.9%.
Yasref awarded the main contract for the tail gas synergy project to Jeddah-based contractor Carlo Gavazzi Arabia earlier this year, according to information obtained by MEED Projects, with the contract estimated at $80m.
The local branch of London-headquartered Berkeley Engineering Consultants is acting as the project’s main consultant, according to MEED Projects.
The scope of work on Yasref’s tail gas synergy project includes the following:
- Construction of downstream TGTU with catalytic hydrogenation reactor and amine absorber train
- Modification of existing sulphur recovery units
- Construction of acid gas removal units employing amine solvent systems
- Construction of desulphurisation units including carbonyl sulphide hydrolysis
- Construction of associated utilities and auxiliary infrastructure: thermal exchangers, power and steam supplies, flare knockout drums
- Installation of safety and security systems hydrogen sulphide detection, overpressure relief, firewater deluge, access control, safety instrumented systems
- Integration of emission monitoring and process control instrumentation.
In April last year, Aramco, Sinopec and Yasref signed a venture framework agreement for a potential petrochemicals expansion of the Yasref refinery complex into a major integrated petrochemicals facility. The project would include a large-scale mixed-feed steam cracker with a capacity of 1.8 million tonnes a year (t/y) and a 1.5 million-t/y aromatics complex, along with associated downstream derivatives.
MEED understands that the Yasref petrochemicals expansion project, which is also referred to as Yasref+, is part of Aramco’s $100bn liquids-to-chemicals programme.
The central ambition of the strategic programme is to derive greater economic value from every barrel of crude produced in Saudi Arabia by converting 4 million b/d of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.
ALSO READ: Saudi downstream projects market enters lean period
https://image.digitalinsightresearch.in/uploads/NewsArticle/16383830/main3043.jpg -
Kuwait sets April deadline for $718m drainage tender14 April 2026
Kuwait’s Ministry of Public Works has set a 21 April deadline for a major tender estimated to be worth about KD222m ($718m).
The tender scope covers the construction of rainwater drainage networks across the residential areas of Sabah Al-Ahmad, South Sabah Al-Ahmad, Al-Khairan and Al-Wafra.
The Ministry of Public Works floated the tender on 22 March.
According to regional projects tracker MEED Projects, the works include the construction of a major concrete sewer, three collection basins and extensive stormwater drainage basins.
Rainwater collection tanks will be connected through an independent network, with outlets to the sea via the Nuwaiseeb exit to manage overflow.
The infrastructure will also filter pollutants such as oils, minerals and sediments to protect water quality and support environmental sustainability.
The project aims to reduce surface runoff, prevent street and urban flooding, and improve groundwater recharge.
UK analytics firm GlobalData expects Kuwait’s construction industry to grow by 5.1% in 2026-29, supported by government investment in the oil and gas sector aimed at raising production, as well as investment in the infrastructure sector.
In the short term, growth will be boosted by planned expenditure under the 2025-26 budget, which was approved in March 2025.
The construction industry in Kuwait is expected to record an annual average growth rate of 4.9% in 2026-29, supported by investments in renewable energy, transport, and oil and gas projects.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16383203/main.jpg -
Local firm makes hydrocarbon discovery in Oman’s Block 714 April 2026
Omani oil and gas exploration and production company Masar Petroleum has announced a discovery in the Hasirah Ridge in the sultanate’s Block 7.
Masar Petroleum was the inaugural operator to appraise and produce hydrocarbons from the Hasirah reservoir in Block 7 in 2017.
Building on that experience, Masar Petroleum has now successfully drilled a new exploration well south of its existing discoveries, validating the concept of the Hasirah Ridge — a geological trend 5 kilometres wide and 30km long mapped across Block 7 using 2D seismic data.
This discovery represents the first step towards unlocking the Ridge’s prospective resource base of 100 million to 380 million barrels, Masar Petroleum said in a statement.
Following this discovery, a planned 3D seismic survey and exploration and appraisal programme is expected to advance the development of the new resources by the end of 2028.
First production from this field is expected to come on stream during the last quarter of this year.
Masar Petroleum plans to rapidly advance appraisal and development opportunities across Block 7.
“Masar is a proud Omani E&P company that has delivered significant value through a continuous and focused effort on unlocking our potential,” Abdulsattar AlMurshidi, CEO of Masar Petroleum, said.
ALSO READ: Oman offers five hydrocarbon exploration blocks in new bidding round
https://image.digitalinsightresearch.in/uploads/NewsArticle/16383075/main2121.jpg -
Bidders get more time for Saudi water transmission projects14 April 2026

Saudi Arabia’s Water Transmission Company (WTCO) has extended the bid submission deadlines for engineering, procurement and construction (EPC) contracts for two major independent water transmission system projects.
The Jubail-Buraidah and Ras Mohaisen-Baha-Mecca transmission projects were first tendered last September under the public-private partnership model.
The deadlines for qualified contractors to submit technical and financial bids had initially been extended to March.
The new bid submission deadline for the Jubail-Buraidah project is 30 April.
Scheduled to begin construction in 2027, the scheme comprises an approximately 348-kilometre-long greenfield water transmission system with a capacity of 840,650 cubic metres a day (cm/d), delivering water from the Ashmasiah reservoirs to cities and towns in Al-Qassim province.
The project is large by WTCO standards. The company’s second phase of the Khobar-Hofuf system, completed in 2024, was 140km in length, with a capacity exceeding 530,000 cm/d.
Ras Mohaisen-Baha-Mecca
For the Ras Mohaisen-Baha-Mecca water transmission system project, the new bid submission deadline is 7 May.
The project involves constructing an approximately 325km-long greenfield independent water transmission system with a capacity of 542,000 cm/d, delivering water from Ras Mohaisen to the Adham and Aradhiyah regions.
Prequalification for both projects closed on 15 January.
It is understood that local firms Alkhorayef Water & Power Technologies and Mutlaq Al-Ghowairi Contracting Company (MGC) are among those qualified to bid for the Ras Mohaisen contract.
MGC secured the EPC contract for an even larger independent water transmission pipeline project in June last year.
The project, also linking Jubail and Buraidah, spans 587km and carries 650,000 cm/d.
According to regional project tracker MEED Projects, construction works recently commenced on the project, which is estimated to cost about SR8.5bn ($2.2bn).
WTCO is also planning to tender a contract for phase two of the Ras Mohaisen water transmission system project. This includes laying water transmission pipelines 408km in length with a capacity of 400,000 cm/d. This project is estimated to cost around $600m.
It is understood that the main contract tender will be issued in 2027.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16383056/main.jpg -
Saudi firm wins $64.2m steel pipe orders from Aramco14 April 2026
Saudi Arabia-based Arabian Pipes Company has announced it has won orders from Saudi Aramco to supply steel pipes, totalling SR241m ($64.2m).
Under the terms of the contracts, Arabian Pipes Company will supply steel pipes over contract durations of nine months and 11 months, commencing from the date of signing.
“These contract awards reinforce Arabian Pipes Company’s strong position as a key supplier to the kingdom’s energy sector and highlight its continued commitment to supporting major oil and gas infrastructure projects in Saudi Arabia,” the company said in a filing with the Saudi Exchange (Tadawul), where its shares trade.
The company added that the orders will contribute positively to its financial performance over the contract period.
Arabian Pipes Company last secured a contract from Aramco in August 2024, when it won an eleven-month steel pipe supply order worth approximately $28.53m.
Prior to that, in July 2024, the company won a contract worth SR293m ($78.1m) to supply steel pipes for the second expansion phase of Aramco’s Jafurah unconventional gas development. That contract had a duration of 10 months.
The order was placed as a subcontract by Denys Arabia, the main contractor performing engineering, procurement and construction works on one of the Jafurah second expansion phase project packages.
MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16382513/main2830.jpg