Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Israeli offensive leaves Beirut in limbo

    5 June 2026

     

    Lebanon is being held in economic and political limbo by Israel’s open-ended offensive in the south, which has killed more than 3,500 people since March and is characterised by strategic objectives that offer no clear end in sight.

    Political leaders in Tel Aviv are justifying the operation on the grounds of eliminating Hezbollah – a far‑fetched goal against a dispersed guerrilla organisation, as with Hamas in Gaza – while ignoring overtures from Lebanon’s leadership for a ceasefire.

    The recently formed Lebanese government, meanwhile, continues to look impotent: unable to secure its territory from Israeli incursions or Hezbollah activity, and unable to deliver on promises of stability, reform, IMF funding and reconstruction.

    Echoes of the past

    The overarching shape of Israel’s military campaign is ominously familiar, echoing the 1978, 1982, 1985 and 2006 Israeli invasions of southern Lebanon – all entailing creeping encroachment without strategic resolution.

    Since fighting resumed on 2 March 2026, Israeli forces have gradually pushed north, crossing north of the Litani for the first time since the 2006 Lebanon war and seizing Beaufort Castle above Nabatieh on 31 May.

    Israeli Prime Minister Benjamin Netanyahu has framed the goal as establishing a “security zone” – the same term and concept Israel used to justify the occupation of a roughly 800-square-kilometre belt of southern Lebanon from 1985 to 2000.

    That occupation was a debacle for Israel’s military and ended in unilateral withdrawal.

    Israeli analysts are already drawing the modern parallels as the cost of holding ground in southern Lebanon rises, driven by Hezbollah’s deployment of cheap fibre‑optic first‑person‑view (FPV) drones that inflict a steady drip of Israeli casualties and losses.

    As with Russia in Ukraine, Tel Aviv is being tactically embarrassed by the advent of these fibre‑optic drones, which are immune to jamming and – of particular concern to Israeli forces – are too small to be reliably detected and intercepted by conventional counter‑drone systems.

    This leap in Hezbollah’s operational threat – based on cheap technology that can be locally assembled – has sharply raised the price of maintaining a military presence in the country.

    In an attempt to exact a retaliatory price, Israel’s air strikes rose by 110% between 19-22 May and 23-26 May as Hezbollah’s drone successes accumulated, according to conflict monitor Acled. But the underlying tactical dilemma remains.

    Israeli politicians, irate at the situation, have demanded escalation and intensified strikes on civilian areas, including in Beirut  – only to face US pushback.

    Tehran as the lever

    Planned strikes on Beirut, including on 3 June, have been held off in recent weeks under pressure from Washington after Tehran made Lebanon a bargaining chip in its wider negotiations with the US, repeatedly suspending talks following Israeli escalation in the Levant country.

    Tehran has also gone further than walkouts, warning it could respond directly if Israel strikes Beirut – adding an explicit threat of retaliation to diplomatic pressure.

    With a Gulf ceasefire and the reopening of the Strait of Hormuz both riding on the outcome, Washington is strongly motivated to keep Israel from striking Beirut.

    In this way, Iran is one of the few powers wielding any leverage over Israel’s actions in Lebanon – even if that leverage is a source of discomfort for Lebanon’s leaders, for whom Tehran’s clout contrasts starkly with their own lack of influence.

    That protection nevertheless remains narrowly tied to the Lebanese capital, with Washington turning a blind eye to Israel’s ongoing destruction of civilian infrastructure in Lebanon’s south.

    Within the border belt that Tel Aviv has dubbed the “yellow line” – amounting to about 7% of Lebanese territory – Israeli forces have accelerated the demolition of villages since the April truce and barred residents from returning.

    More than a million people, overwhelmingly Shia from the south and the Bekaa, have been displaced since March, and UN human-rights experts have pointed to the blanket evacuation orders and levelling of housing as mirroring Israel’s conduct in Gaza.

    The Lebanese state remains trapped in inaction, partially of its own making. Beirut was initially close to indifferent to renewed strikes on Hezbollah, whose unilateral re-entry into the war it had condemned for endangering the state.

    But as the strikes have shifted methodically towards civilian areas, Beirut’s restraint satisfies no one: the domestic audience wants protection, while Israel and the US want decisive Lebanese army action against Hezbollah.

    Yet the Lebanese army – still adhering in spirit to the November 2024 ceasefire framework and loath to move seriously against Hezbollah for fear of stoking civil war – has remained aloof from the conflict.

    Parliament speaker Nabih Berri, who is close to Hezbollah and maintains dialogue with the group, says it would honour a genuine ceasefire if only Washington could deliver one.

    But repeated attempts to shore up the ceasefire have remained conditional on the Lebanese army stepping up to rein in Hezbollah, while failing to guarantee an end to Israel’s destruction of civilian structures in areas it is occupying.

    On 3 June, a fourth round of US‑mediated trilateral talks produced a fresh ceasefire announcement, hailed in Washington as a step towards comprehensive peace.

    Yet its conditions – a complete halt to Hezbollah fire, the group’s withdrawal south of the Litani and Lebanese army control of undefined “pilot zones”– merely reiterate past failed protocols. The declaration was unsigned by Hezbollah and unenforceable by Beirut.

    Within hours, Hezbollah leader Naim Qassem rejected the declaration, stating that any ceasefire must cover the south and begin with Israeli withdrawal, not Hezbollah’s.

    Both Israeli strikes and Hezbollah attacks have continued since the ostensible deal.

    Recovery on hold

    The economic cost to Lebanon, meanwhile, compounds by the day. The country entered 2026 already in crisis: cumulative GDP down close to 40% since 2019, the pound down 98%, public debt at 150% of GDP, and reserves as low as $11bn as of June 2025.

    The government of President Joseph Aoun and Prime Minister Nawaf Salam staked its credibility on a long‑deadlocked IMF programme finally unlocking external support. The war has upended this, driving away investment and delaying reform.

    The World Bank’s November 2024 assessment – covering only the previous round of fighting, before the March resumption – placed the economic cost at $14bn and recovery needs at $11bn, figures that the current war is now inflating by the day.

    Lebanon’s Bank Audi has warned of zero growth this year if the war continues, versus a pre‑escalation projection of reconstruction‑led recovery. Tourism, historically a fifth of the economy and the engine of the 2024 rebound, has been the biggest casualty.

    Looking ahead, no reconstruction can be financed while the destruction continues, and no IMF programme can advance while the state cannot ensure stability.

    Iran’s leverage may be keeping the bombs off Beirut, but the south’s entrenchment as a war zone is only deepening – with hopes for recovery receding further with every village levelled.

    While the costly occupation is imposing a rising political price on the Israeli government that may, in time, bring it to an end, this will be little consolation for those displaced – many of whom now have no communities to return to, and homes built over decades that are gone.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17120249/main.gif
    John Bambridge
  • Morocco tenders Falit dam project

    5 June 2026

    Morocco’s Ministry of Equipment & Water has opened an international tender for the construction of the Falit dam in Figuig province.

    According to local media reports, the project has an estimated budget of MD428m ($46m), with commissioning expected between 2029 and 2030.

    The bid submission deadline is 15 July.

    The dam will be built on the Moulouya River north of Bouarfa in eastern Morocco. The roller-compacted concrete structure will be 59 metres high and have a storage capacity of 25 million cubic metres.

    The project is intended to provide drinking water supplies, support agricultural irrigation and enhance flood protection in the region.

    Figuig is one of Morocco’s driest regions. It is also vulnerable to flash floods caused by sporadic but intense rainfall events.

    Reported ministry data indicates that annual flows at the project site can reach 40.8 million cubic metres in wet years. Long-term average flows are estimated at about 10.3 million cubic metres a year.

    The dam will include a spillway and a bottom outlet equipped with a 1,500-millimetre pipe. The outlet will have a discharge capacity of 28 cubic metres a second and will allow the reservoir to be emptied within 15 days if required.

    Morocco dam infrastructure

    The Figuig region is also home to the Kheng Grou dam project, which is designed to have a storage capacity of 1.07 billion cubic metres.

    According to regional project tracker MEED Projects, the dam is on track to be completed by the end of the year.

    Morocco-headquartered Bioui Travaux is the engineering, procurement and construction (EPC) contractor for the project, valued at $96m. 

    Another local firm Novec is acting as the main contractor on the project.

    The Falit dam tender comes as Morocco continues to invest in new dams, desalination plants and water transfer schemes to address growing pressure on water resources.

    The country currently has over $13bn-worth of dam projects under construction, the largest of which is the Ratba dam project in the province of Taounate.

    Construction is also set to begin on the $238m Bou Ahmed Dam project, covering 259 hectares, in the province of Chefchaouen. According to MEED Projects data, this was the only major dam contract awarded last year.

    The joint venture of Societe Generale des Travaux du Maroc and Stam Morocco, a subsidiary of the TGCC group, will carry out EPC works on the project.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17120660/main.jpg
    Mark Dowdall
  • Saudi Energy commissions 2.5GW battery storage project

    5 June 2026

    Saudi Energy, formerly Saudi Electricity Company, has commissioned a major 2.5GW battery energy storage project across five regions in Saudi Arabia.

    The project, which serves power grids in Riyadh, Rabigh, Dawadmi, Jouf and Qassim, completed all grid-tied charging and discharging tests at the end of May, said Chinese supplier NR Electric in a statement.

    National Grid Saudi Arabia, a wholly owned subsidiary of Saudi Energy, awarded Saudi firm Alfanar Company and China’s BYD Energy Storage the contract to build and install five battery energy storage system (bess) facilities with a total combined installed capacity of up to 2,500MW, equivalent to a rated capacity of up to 12,500 megawatt-hours, in January 2025.

    Alfanar was appointed as the project’s engineering, procurement and construction contractor, while BYD Energy Storage was responsible for the design, supply, supervision of installation, testing and commissioning, and maintenance of the bess plants.

    The 12.5 gigawatt-hour (GWh) project is the world’s largest grid-scale energy storage deployment, requiring 2,364 system cabinets in total.

    NR Electric said it supplied the project’s grid-forming control technology and more than 2,000 power conversion system units.

    The main applications for the planned bess facilities include load shifting, black start, frequency regulation and voltage support.

    They are expected to replace part-load operation of existing power plants by charging and discharging electricity according to system load variations and primary and secondary reserves, among other potential applications.

    Shenzhen-based BYD previously announced that the five bess plants would take its total deployments in Saudi Arabia to about 15.1GWh.

    It deployed its bess products on Saudi Arabia’s first on-grid bess plant in Bisha, one of 17 projects globally with a capacity of over 1GWh that entered operations in 2024.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17120197/main.jpg
    Mark Dowdall
  • Kuwait prepares to tender refinery project deal

    5 June 2026

    State-owned downstream operator Kuwait National Petroleum Company (KNPC) has announced that it is preparing to tender a contract to develop a gauging system for a tank farm at the Mina Al-Ahmadi refinery.

    The system will replace an older, now obsolete system at the South Liquid Tank Farm.

    The contract will include engineering, procurement, construction, testing and commissioning of the new gauging system.

    KNPC is planning to invite 24 companies to participate in the bidding process.

    These are:

    • JGC Corporation (Japan)
    • Almeer Technical Services Co. (Kuwait)
    • CTCI Corporation (Taiwan)
    • Kellogg Brown & Root (US)
    • Kentz Overseas (UAE)
    • IMCO Engineering & Construction Company (Kuwait)
    • National Petroleum Construction Company (UAE)
    • Sinopec Luoyang Engineering (China)
    • Sinopec Engineering Incorporation (China)
    • Tecnicas Reunidas (Spain)
    • SK Ecoplant (South Korea)
    • Gulf Spic General Trading & Contracting Company (Kuwait)
    • Hyundai Engineering (South Korea)
    • Enppi (Egypt)
    • Hyundai Engineering & Construction (South Korea)
    • Saipem (Italy)
    • Technip Energies (France)
    • Larsen & Toubro (India)
    • Hanwha Engineering & Construction Corporation (South Korea)
    • Sinopec Engineering Group (China)
    • Samsung E&A (South Korea)
    • Daewoo Engineering & Construction (South Korea)
    • Fluor (US)
    • Hyundai Heavy Industries (South Korea)

    If a company has not been included in the list and would like to participate in the tender, it can file a complaint with the chairman of Kuwait’s Higher Purchase Committee within 30 days.

    The Mina Al-Ahmadi refinery has been attacked and damaged as part of the regional war that broke out after the US and Israel attacked Iran on 28 February.

    Several units were shut down at Kuwait’s largest oil refinery after it was hit by drones and fires broke out in the morning of 20 March 2026.

    The refinery normally processes about 730,000 barrels of oil a day.

    Kuwait’s oil and gas sector has been severely disrupted by the ongoing regional conflict, which has led to a dramatic drop in crude exports via the Strait of Hormuz.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17119568/main.gif
    Wil Crisp
  • Kuwait tenders downstream consultancy contract

    5 June 2026

    State-owned downstream operator Kuwait National Petroleum Company (KNPC) has tendered a consultancy contract focused on a liquid sulphur degassing facility for four sulphur recovery units at the Mina Al-Ahmadi refinery.

    This type of unit removes dissolved hydrogen sulphide and other sulphur compounds from molten sulphur before it is stored, loaded onto trucks, or exported.

    This makes the sulphur safer to handle and reduces emissions.

    A total of 21 companies have been invited to participate in the tender.

    These are:

    • Asprofos Single Member Engineering Societe Anonyme (Greece)
    • Enereco (Italy)
    • EPC Constructions India (India)
    • Engineering for the Petroleum & Process Industries (Enppi) (Egypt)
    • Gulf Spic General Trading & Contracting Company (Kuwait)
    • Heavy Engineering Industries & Shipbuilding Company (Kuwait)
    • ILF Consulting Engineers (Austria)
    • Larsen & Toubro (India)
    • Litwin PEL (UAE)
    • Mott MacDonald (UK)
    • National Petroleum Construction Company (UAE)
    • Penspen International (UK)
    • Petro6 Engineering & Construction (India)
    • Petrocil Engineers & Consultants Pvt. (India)
    • PL Engineering (India)
    • Processes Unlimited (US)
    • Tebodin (Netherlands)
    • Technip Energies France (France)
    • Tecnicas Reunidas (Spain)
    • Triune Energy Services (India)
    • Toyo Engineering Corporation (Japan)

    A pre-tender meeting for the project is scheduled for 8 June 2026, and the bid closing date is 25 June 2026.

    The Mina Al-Ahmadi refinery has been attacked and damaged as part of the regional war that broke out after the US and Israel attacked Iran on 28 February.

    Several units were shut down at Kuwait’s largest oil refinery after it was hit by drones and fires broke out in the morning of 20 March 2026.

    The refinery normally processes about 730,000 barrels of oil a day.

    Kuwait’s oil and gas sector has been severely disrupted by the ongoing regional conflict, which has led to a dramatic drop in crude exports via the Strait of Hormuz.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes: