Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Frontrunners emerge for Saudi Arabia’s seventh solar IPP round

    17 November 2026

     

    Register for MEED’s 14-day trial access 

    Four bidders are understood to be leading the race for contracts to develop four solar photovoltaic (PV) independent power projects (IPPs) under the seventh round of Saudi Arabia’s National Renewable Energy Programme (NREP).

    Round seven comprises the 1,400MW Tabjal 2, 600MW Mawqqaq, 600MW Tathleeth and 500MW South Al-Ula solar IPPs.

    Saudi Power Procurement Company (SPPC) is procuring the renewables programme, with the Energy Ministry supervising it.

    Developers submitted bids in September, as MEED reported exclusively.

    According to industry sources, the following bidders and bidding groups have emerged as frontrunners to win one project each:

    • Aljomaih (Saudi Arabia) / TotalEnergies (France)
    • EDF (France) / Saudi Energy
    • Etihad Water & Electricity (UAE) / Korea Electric Power Corporation (South Korea)
    • Wahajpeak (Saudi Arabia)

    An award for Wahajpeak would mark the company’s first major infrastructure award in the region since US-based infrastructure investment firm Stonepeak established it in 2025. 

    At least some solar contracts are expected to be finalised by year-end.

    In addition to the four solar plants, round seven comprises two wind IPPs with a total combined capacity of 5,300MW. 

    In October, MEED exclusively reported that consortiums had submitted bids for the two wind projects: the 1,300MW Bilgah and 900MW Shagra schemes.

    These include:

    • Abu Dhabi Future Energy (Masdar) / EDF (France) / Saudi Energy
    • EtihadWE (UAE) / Nesma Renewable Energy (Saudi Arabia) / Korea Electric Power Corporation (Kepco, South Korea)

    The request for proposals (RFPs) for both wind and solar were issued in January.

    As MEED reported, 16 developers qualified to bid as both managing and technical members of consortiums for the four solar PV projects. A further six companies qualified to bid as managing members only.

    For the wind IPPs, SPPC qualified 13 developers in the managing and technical members category and a further six companies in the managing members category only.

    Round eight

    SPPC will release the RFP notices in December for the eighth round of its renewable energy procurement programme, as exclusively reported by MEED.

    The round comprises three solar and wind projects with a combined capacity of 3.2GW.

    SPPC issued the request for qualifications (RFQ) notice on 11 November. Developers have until 22 November to submit qualification documents, as MEED reported last week.

    Round eight includes the following projects:

    • 900MW Tamir solar PV project in Riyadh
    • 1GW Sharq Al-Amwaj solar PV project in Asir
    • 1.3GW Al-Muzairah wind project in Mecca

    The NREP is designed to increase renewable generation capacity and reduce liquid-fuel use in power generation.

    Saudi Arabia aims for renewable energy and energy storage systems to account for about 50% of the kingdom’s electricity generation mix by 2030.

    Earlier rounds under the NREP have already deployed large capacities. In October 2025, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP. These were four solar PV IPPs and one wind IPP, with a total combined capacity of 4,500MW.

    The Aljomaih / TotalEnergies joint venture won the contract to develop the 400MW Al-Sufun solar IPP. Two of the three remaining solar IPPs in round six were awarded to Masdar, while the joint venture of EDF and Saudi Energy was selected to develop the 600MW Samtah solar IPP.

    A consortium of the UAE’s Etihad Water & Electricity, Saudi Arabia’s Nesma Renewable Energy and Korea Electric Power Corporation (South Korea) won the contract to develop the 1,500MW Dawadmi wind IPP, the only wind project in the round.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21466519/main.jpg
    Mark Dowdall
  • Al-Ula launches $6.8bn PPP project opportunities

    17 November 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Royal Commission for AlUla (RCU) has announced six public-private partnership (PPP) investment opportunities with a combined estimated value of SR25.4bn ($6.8bn).

    The schemes cover road infrastructure, water storage, wastewater treatment, solid waste management and the expansion of Al-Ula International airport.

    They are progressing under the National Centre for Privatisation’s approved privatisation plan, with requests for proposals (RFP) expected from the second quarter of 2027 through early 2028.

    The opportunities are:

    Secondary roads expansion: RCU plans to develop 18 secondary roads and utility corridors totalling about 1,400 kilometres (km). The SR17bn ($4.5bn) project includes new roads and networks for water supply, electricity, telecommunications, street lighting and stormwater drainage.

    The project covers 22 million square metres (sq m) and will be delivered using a design-build-finance-operate-maintain (DBFOM) model.

    The concession will run for about 20 years and will use availability-based payments. The private partner will operate and maintain the roads, while the utility infrastructure will be handed over to the relevant entities.

    The RFP process for the project packages is planned to start in early 2028, with phased completion targeted by 2033. Expressions of interest are due by 30 September 2027.

    Highways and primary roads expansion: The SR4bn ($1bn) opportunity covers the development and upgrade of five primary roads and associated utility networks, totalling 204km.

    The scope includes new roads, rehabilitation works, cycling paths and traffic-calming measures. It also includes water, electricity, telecommunications and stormwater-drainage infrastructure. The investment area is 3 million sq m.

    The scheme will be procured as a DBFOM project with availability-based payments and a 15-year concession. The concessionaire will operate and maintain the roads, while utilities will be handed over to the relevant entities.

    RCU expects to begin the RFP process in early 2028 and has set phased completion by 2032. Expressions of interest are due by 30 September 2027.

    Al-Ula International airport expansion: The SR2bn ($532m) airport project will include a 30,000 sq m passenger terminal with a capacity for up to 3 million passengers a year, a 5,000 sq m cargo terminal with equestrian facilities and a 10,000 sq m private aviation terminal.

    The scope also includes general aviation and helicopter facilities, a runway extension to 3,000 metres, roads, parking, maintenance facilities, utilities and fuel facilities.

    The project has a gross floor area of 45,000 sq m and covers a 7 million sq m site.

    About 1 million sq m of land will be available for associated commercial development, including logistics, retail, hospitality and aviation services.

    The project will use a build-transfer-operate model with a concession period of up to 35 years.

    RCU expects to launch the RFP in the third quarter of 2027 and is targeting completion by 2032. The interest submission deadline is 30 June 2027.

    Integrated solid waste management system: The SR1bn ($266m) project involves developing and operating an integrated solid waste management system over a 1.4 million sq m area.

    The scope includes a resource management park; a waste transfer station with a capacity of 76,000 tonnes a year; recycling facilities with a capacity of 45,000 tonnes a year; organic waste treatment facilities; and construction and demolition waste-processing facilities with a capacity of 220,000 tonnes a year.

    It also includes engineered landfill cells with a combined capacity of 5 million cubic metres and associated infrastructure.

    The project will be delivered through a DBFOM concession lasting 30 years, including three years of construction and 27 years of operations.

    Payments will comprise performance-based payments, waste gate fees and transfer fees.

    RCU expects to issue the RFP in the second quarter of 2027. The deadline for interest is 31 May 2027.

    Strategic water storage tanks: RCU plans to develop and operate five strategic potable-water storage tanks with a combined capacity of 295,000 cubic metres. The SR900m ($239m) scheme is intended to provide between three and four days of potable-water reserves.

    The project includes pumping stations, water connection networks and supporting infrastructure to serve urban districts, heritage sites, Al-Ula International airport and new development areas.

    The investment area covers 75,000 sq m.

    The project will be structured as a DBFOM concession lasting about 15 years, including two to three years of construction and 12 to 13 years of operations and maintenance.

    The availability-based payment mechanism will be linked to performance and water quality.

    RCU expects to issue the RFP in the fourth quarter of 2027, with phased completion targeted by 2031. Interested companies have until 30 November 2027 to submit their interest.

    Wastewater treatment plant enhancement and operation: The SR454m ($120m) wastewater scheme will rehabilitate Al-Ula’s existing wastewater treatment plant and expand its capacity using moving-bed biofilm reactor technology.

    The existing plant has a capacity of 8,000 cubic metres a day (cm/d). The first phase will add 18,000 cm/d, followed by a 36,000 cm/d second phase, increasing overall capacity to 62,000 cm/d.

    The 501,000 sq m project includes treated wastewater storage and pumping facilities, control systems and supporting infrastructure.

    The project will be delivered using a build-own-operate-transfer model with a 26-year concession. This comprises three years for construction and rehabilitation and 23 years of operations. The payment structure will include capacity, output and supplemental payments.

    RCU expects to launch the RFP in the second quarter of 2027. The deadline for interest is 31 May 2027.

    RCU was established in 2017 to develop and protect Al-Ula as a cultural, heritage, tourism and economic destination.

    The commission launched its masterplan in 2021, setting out a long-term development programme centred on the Hegra Historic City, Nabataean Horizon, Jabal Ikmah, Dadan and Al-Ula Old Town districts.

    The wider Al-Ula programme includes heritage conservation, hotels and resorts, cultural venues, residential projects, agricultural development, transport systems and enabling infrastructure.

    The latest opportunities form part of the infrastructure programme required to support the region’s planned tourism, residential and commercial development.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21465369/main.png
    Yasir Iqbal
  • Consortium closes financing on 900MW Egypt wind farm

    17 November 2026

    A developer consortium led by France’s Engie has announced financial close on a 900MW wind farm near Ras Shokeir in Egypt’s Gulf of Suez.

    Known as Gulf of Suez Wind Farm 3, the project is being developed on a build-own-operate basis under a 25-year power purchase agreement with Egyptian Electricity Transmission Company.

    The consortium comprises Engie (35%), Egypt’s Orascom Construction (25%) and Aeolus (40%), an African renewable energy independent power project platform of Toyota Tsusho Corporation.

    Construction began in June, and the project will connect to the grid in three phases. The first 300MW is forecast to enter commissioning in January 2028, while the full 900MW capacity is scheduled to be operational in summer 2028.

    The project is the consortium’s third wind farm in Egypt. Its two existing operational wind farms – Red Sea Wind Energy and Ras Ghareb – have a combined capacity of 912.5MW. Once the new facility is fully operational, the consortium’s wind power capacity in the country will reach 1.8GW.

    The facility will also become Engie’s largest onshore wind farm globally. Orascom Construction will execute all civil and electrical works for the balance of plant as well as supply certain local components.

    Financing for the project is being provided on a non-recourse basis by a group of development finance institutions and commercial lenders. These include the Japan Bank for International Cooperation, France’s Proparco, the Netherlands-based FMO, Societe Generale, Credit Agricole Corporate & Investment Bank and Germany’s KfW Ipex-Bank.

    Commercial lender financing is covered by Nippon Export & Investment Insurance (Nexi). HSBC Bank Egypt is acting as the working capital facility bank and onshore security agent. Equity bridge loans are being provided by KfW for Engie, Mizuho for Aeolus, and FMO and British International Investment for Orascom Construction.

    The project supports Egypt’s long-term energy strategy, including targets of more than 42% renewable energy by 2030 and 65% by 2040.

    Once operational, the wind farm is expected to generate enough electricity to supply more than 1.4 million Egyptian households and reduce carbon emissions by approximately 2 million tonnes a year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21464975/main.jpg
    Mark Dowdall
  • Emaar and Abu Dhabi firm plan $2bn projects

    17 November 2026

    Register for MEED’s 14-day trial access 

    UAE-based firms Al-Ain Asset Management and Emaar Hospitality Group have announced plans to develop five branded residential projects in Abu Dhabi with a combined investment value of AED8bn ($2.2bn).

    The developments will cover about 4.7 million square feet across prime waterfront locations in the emirate.

    The schemes will be operated under Emaar Hospitality Group’s Address, Palace and Vida brands, incorporating serviced residential units with hotel-style amenities.

    Specific plots, construction schedules and procurement packages for the five projects have not yet been disclosed.

    The initiative marks an expansion of the existing partnership between the two entities, which began in 2016 with the development of the Address Beach Resort in Dubai.

    The collaboration previously expanded into Abu Dhabi with the launch of Vida Residences Saadiyat Island.

    The recent announcement comes amid sustained momentum in the local market.

    According to GlobalData, the UAE construction industry will expand at an average annual rate of 3.9% between 2025 and 2027, driven by investments across infrastructure, energy, housing and tourism.

    The country’s residential construction sector is forecast to grow by an average of 2.7% annually between 2025 and 2028, supported by ongoing private development and government initiatives to meet population growth.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21461696/main.gif
    Yasir Iqbal
  • Libya considers tendering $1bn oil field development

    17 November 2026

    Libyan officials have discussed tendering a project to rehabilitate and develop Libya’s Dahra oil field, according to a statement from the country’s Audit Bureau.

    The head of the Audit Bureau, Khaled Shakshak, met with the head of Libya’s National Oil Corporation (NOC), Masoud Suleiman, on 15 November.

    During the meeting, they discussed options for tendering the Dahra oil field development project, which has previously been estimated at $1bn and is expected to significantly increase oil production from the field.

    The oil field in central Libya has suffered from years of poor maintenance and was sabotaged by Islamic State militants in 2015.

    Waha Oil Company announced in August 2022 that it had restarted test operations at the Al-Dhara oil field after a seven-year hiatus.

    Waha Oil Company is a joint venture of Libya’s NOC, US-based ConocoPhillips and France’s TotalEnergies.

    In August last year, MEED revealed that the field was producing 24,000 barrels a day (b/d) of oil and the US oilfield services provider Halliburton was working on the front-end engineering and design (feed) for the rehabilitation and development project.

    At the time, the project was expected to boost total production from the Al-Dhara field and neighbouring PL6 field to 130,000 b/d.

    The engineering, procurement and construction (EPC) scope of work on the project is understood to include:

    • Drilling of wells
    • Construction of platforms
    • Laying of pipelines
    • Construction of a condensate refinery
    • Installation of storage tanks
    • Installation of early production facilities
    • Installation of gas treatment units
    • Construction of a degassing station
    • Construction of other associated facilities

    Over 2026, there has been an uptick in interest in North African oil and gas assets amid continued disruption to shipping through the Strait of Hormuz, a key export route for some of the Middle East’s biggest oil and gas exporters.

    Flows through the Strait have been disrupted by a regional war that was triggered by US and Israeli attacks on Iran on 28 February.

    Countries negatively impacted by the disruption include Kuwait, Iraq, Saudi Arabia, the UAE and Qatar.

    Amid the ongoing disruption to oil and gas exports from these countries, some North African officials have promoted their oil and gas sectors as reliable alternative suppliers.

    In August, Libya’s Oil and Gas Minister Khalifa Abdel Sadig told a conference in Norway that Libya could be a “key player in providing energy security solutions” to the European Union.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21459109/main.png
    Wil Crisp