Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg