Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Adnoc Onshore selects contractors for well tie-ins project

    27 October 2026

     

    Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.

    Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields. 

    The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.

    Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.

    Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.

    The project budget is estimated at $1.2bn.

    Bidders for the contract are understood to have included:

    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Jereh (China)
    • Kalpataru Projects International (India)
    • Matrix Construction (UAE)
    • Robt Stone Middle East (UAE)
    • Target Engineering Construction Company (UAE)

    The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg
    Indrajit Sen
  • Ashghal tenders Al-Udeid air base access road works

    27 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.

    The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road. 

    The tender was issued on 22 October, with a submission deadline of 22 November.

    The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.

    Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.

    The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.

    The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.

    The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.

    Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.

    The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.

    Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.

    Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.

    For joint-venture bids, the lead partner must hold the required classification grade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg
    Yasir Iqbal
  • Saudi Arabia gauges interest for Al-Ula wastewater expansion

    27 October 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) is conducting market sounding for the first phase of the Mughayra wastewater treatment plant (WWTP) expansion before formally starting its tendering process, according to industry sources.

    The project is valued at SR400m ($107m) and is intended to increase the Mughayra plant’s wastewater treatment capacity to 62,000 cubic metres a day.

    RCU is gauging interest from potential contractors and has not yet issued a prequalification questionnaire, a source said.

    The scheme forms part of Saudi Arabia’s broader investment drive to develop its cultural and tourism offering across Al-Ula.

    The commission launched its Journey Through Time Masterplan in April 2021, with implementation scheduled in three phases through 2035. The masterplan covers infrastructure development, water management and irrigation, alongside the regeneration of a 9-kilometre cultural oasis.

    French engineering firm Artelia previously noted in its 2025 annual corporate report that it is involved in the design phase of the Mughayra WWTP.

    RCU is also developing strategic potable-water storage infrastructure in Al-Ula, including a design-and-build project covering a 50,000-cubic-metre reservoir at Hub 06 and a 15,000-cubic-metre reservoir at Hub 08.

    Local contractor Bin Omairah previously confirmed that it is serving as the engineering, procurement and construction contractor for the storage facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950333/main.jpg
    Mark Dowdall
  • Qatari firm wins $147m Syria road deal

    27 October 2026

    Qatari contractor Al-Mohannadi for Roads, Trading & Contracting has signed a $147m contract with Syria’s General Directorate of Roads to rehabilitate and expand a 215-kilometre (km) highway corridor connecting to the Iraqi border.

    The project covers the rehabilitation and dualisation of a 170km section linking the Al-Busairi junction to the Al-Tanf border crossing, alongside the construction of a 45km link between the Al-Sabaa Biyar junction and Al-Busairi. Work is scheduled for completion within 900 days.

    The agreement was signed in Damascus by Moaz Najjar, director-general of the General Directorate of Roads, and Abdullah Adnan Al-Zattam, chief executive of Al-Mohannadi, in the presence of Syrian Transport Minister Yarob Badr and Finance Minister Mohammad Yusr Barnieh.

    The upgrade is intended to restore and expand one of Syria’s primary overland arteries to Iraq, which has suffered significant deterioration and capacity bottlenecks following years of conflict. The Al-Tanf corridor represents the most direct overland link between Damascus, central Syrian industrial centres and Baghdad.

    The project is designed to accommodate heavier commercial freight vehicles and reduce transit times between the two countries.

    The investment also forms part of broader efforts to re-establish Syria’s role as a regional transit corridor connecting Mediterranean ports with landlocked trade routes into Iraq and the wider region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950332/main.gif
    Yasir Iqbal
  • Adnoc showcases $16.3bn local manufacturing potential

    27 October 2026

    Abu Dhabi National Oil Company (Adnoc Group) has identified more than AED60bn ($16.3bn) in local manufacturing opportunities through 2030.

    The Abu Dhabi energy company also announced changes to its procurement, supplier registration and In-Country Value (ICV) localisation frameworks.

    The measures were announced at the second Make it with Adnoc Forum, held in Abu Dhabi on October 25. They are intended to give manufacturers, suppliers and investors greater visibility of future demand and a faster, clearer route to compete for Adnoc contracts, the company said.

    The more than 200 manufacturing opportunities cover products required for Adnoc’s projects and operations, including:

    • Rotating equipment and power
    • Electrical, control and automation systems
    • Drilling and completion equipment
    • Chemicals and catalysts
    • Piping, fabrication and heavy equipment
    • Spare parts and advanced manufacturing

    Many of the identified products are currently imported, Adnoc said. “Manufacturing them in the UAE shortens lead times, reduces exposure to global supply disruptions and strengthens the resilience of Adnoc’s operations,” it said in its statement.

    Adnoc, the UAE Ministry of Industry & Advanced Technology and the Abu Dhabi Investment Office (Adio) will work together to connect manufacturers with these opportunities. The collaboration will combine visibility of Adnoc’s demand, access to the national industrial database and financing through the National Industrial Resilience Fund, the company said.

    Adnoc also signed two memorandums of understanding on the sidelines of the forum with Adio and Kezad Group.

    ICV scheme expansion

    Adnoc announced the expansion of its Local+ programme, part of its ICV framework, to more than 100 UAE manufacturers, compared with 70 at its launch in May. The programme gives UAE-made products priority in Adnoc projects by requiring engineering, procurement and construction (EPC) contractors bidding for new tenders to source relevant products from manufacturers approved under the programme.

    Separately, Adnoc announced a redesign of its supplier registration and prequalification process. The company is targeting a reduction of up to 80% in the time required for suppliers to complete the process and become eligible to compete for Adnoc opportunities.

    The new model halves the number of required documents and removes prequalification requirements for 60% of service categories.

    A single window brings together registration, qualification and compliance, with requirements tailored to the nature of the work and its level of risk. Artificial intelligence will support document verification and the reuse of existing data, reducing repetitive submissions and administrative processing.

    ALSO READ:
    Adnoc steps up crude oil capacity expansion
    Adnoc funnels billions into boosting gas processing

    “Adnoc’s enhanced ICV model will more closely connect procurement decisions with commercial value and suppliers’ contribution to the UAE economy. Under the new model, commercial and ICV offers will be integrated into a single evaluation model,” the company said.

    “The previous bid-matching approach will be retired, encouraging suppliers to submit their most competitive commercial and ICV offers from the outset. Requirements will be proportionate to contract size and scope.

    “The model also enhances the administration of ICV-related retention payments. Where retention applies, automated calculation and release processes through the Adnoc Supplier Hub will improve transparency, reduce manual follow-up and support suppliers’ cash flow as obligations are met.”

    Alongside the ICV and registration enhancements, Adnoc outlined a new commercial approach built around four strategic shifts: agile, competitive, strategic and forward-looking.

    “The approach will advance simpler procurement and faster decision-making, contracting models aligned with project and market dynamics, targeted commercial negotiations and earlier visibility of Adnoc’s future demand.”

    Since its launch in 2018, Adnoc’s ICV programme has directed more than AED307bn ($83.6bn) into the UAE economy, the company said. By the end of 2025, it had also supported the localisation of more than 130 products, the development of 95 UAE factories, and employment opportunities for more than 27,500 Emiratis at participating private sector companies.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20948385/main5518.jpg
    Indrajit Sen