Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Dubai tenders stormwater drainage projects14 August 2026
-
Construction completed on $8.5bn Neom hydrogen project14 August 2026
-
Lamprell announces Abu Dhabi offshore project contract14 August 2026
-
Hitachi Energy signs Erbil substations deal14 August 2026
-
Contracts signed for Algerian phosphate project14 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai tenders stormwater drainage projects14 August 2026
Dubai Municipality has issued three tenders for stormwater and sewerage infrastructure projects serving Hind City, Dubailand and surrounding areas.
The projects cover drainage networks for Hind 4, connections to the stormwater network in Dubailand and a stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman.
The three tenders were issued through the municipality’s Sewerage and Recycled Water Projects Department.
All three have bid submission deadlines of 10 September.
Hind 3 and Hind 4 are two of four zones within Hind City. The Dubai government renamed the Al-Minhad area and surrounding areas as Hind City in 2023. The 83.9-square-kilometre area is served by Emirates Road, Dubai–Al-Ain Road and Jebel Ali–Lehbab Road.
The DS-316-C1 project covers the construction of sewer and stormwater networks in Hind 4. The stormwater network will include gravity drainage pipelines with diameters of up to 1,600 millimetres (mm), while the sewer network will include pipelines of up to 800mm.
The TF-24-C1 project will connect developers’ areas in Dubailand to the stormwater network. It includes 18 kilometres (km) of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.
The TF-25-C1 project involves the construction of a 9.2km stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman. The trunk line will include gravity drainage pipelines with diameters of up to 2,800mm. It will also serve main roads along its alignment, including sections of Dubai–Al-Ain Road, and is designed to accommodate stormwater flows from part of Emirates Road.
The projects are intended to strengthen flood resilience and improve the reliability of Dubai’s drainage infrastructure.
Latest awards
Dubai has continued to accelerate investment in stormwater infrastructure under the Tasreef programme in recent months.
In July, MEED exclusively reported that Dubai Municipality had awarded the estimated $100m engineering, procurement and construction contract for the TF-15-C1 package of its Tasreef rainwater drainage network programme to local firm DeTech Contracting.
The municipality has also recently awarded the TF-15-C2 and DS-204-C1 packages to China State Construction Engineering Corporation and Nael Construction & Contracting, respectively.
The overall masterplan aims to expand Dubai’s rainwater drainage capacity by 700% by 2033 and serve the emirate for the next century.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18585485/main.jpg -
Construction completed on $8.5bn Neom hydrogen project14 August 2026
Construction work on the $8.5bn Neom Green Hydrogen project at Oxagon in Saudi Arabia has been completed, with the facility entering the commissioning stage ahead of commercial operations targeted for 2027.
The project is being developed by Neom Green Hydrogen Company (NGHC), a joint venture of Saudi-listed Acwa, US-headquartered industrial gases group Air Products and Neom.
Acwa's chief financial officer, Abdulhameed Al-Muhaidib, said during the company’s recent H1 2026 earnings call that construction has been completed and commissioning activities are now under way.
"It’s really more now into commissioning and the target to go into commercial operation next year," he told investors.
The project is designed to produce up to 600 tonnes a day of green hydrogen, which will be converted into green ammonia for export. It is supported by about 4GW of solar and wind power generation capacity, with the renewable power that is generated being used to produce hydrogen through electrolysis.
As previously reported by MEED, Air Products is also the exclusive offtaker for green ammonia produced at the facility under a 30-year agreement.
NGHC said in March that its renewable power generation assets, including the wind and solar farms, and transmission grid, had reached approximately 95% completion.
India’s Larsen & Toubro (L&T) is the engineering, procurement and construction (EPC) contractor for the project’s renewable energy and transmission and distribution package.
L&T’s EPC scope includes a 2,200MW solar plant, a 1,370MW wind farm, a 400MW battery energy storage system and a transmission network extending 190 kilometres.
The project reached financial close in 2023. Once operational, the facility is expected to produce up to 1.2 million tonnes a year of green ammonia for export.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18567177/main.jpg -
Lamprell announces Abu Dhabi offshore project contract14 August 2026

Saudi Arabia/UAE-based Lamprell has announced it has won an engineering, procurement, construction and installation (EPCI) contract for a project in Abu Dhabi, for which it will “support the delivery of subsea pipeline infrastructure that will help strengthen offshore energy production and processing capabilities”.
The project includes the engineering, procurement and fabrication of approximately 50 kilometres (km) of subsea pipeline systems, along with associated flowlines, subsea connections and testing, Lamprell said in a statement.
With the engineering, procurement and construction (EPC) activities having been completed, preparations are under way for the offshore installation phase, Lamprell added, without revealing further details about the project, its client or value of the contract.
“Working alongside our sister company Algihaz Marine Contractors, the project demonstrates the value of combining complementary engineering, fabrication and offshore installation capabilities to deliver complex subsea infrastructure safely, efficiently and to a high standard,” the company said in a .
MEED understands the contract award relates to the first package of the Umm Shaif Gas Cap development project in Abu Dhabi, for which Abu Dhabi National Oil Company (Adnoc Group) and its foreign partners announced achieving a $6.2bn final investment decision (FID) in July.
MEED previously reported that Adnoc had awarded the EPCI contract for the package related to EPCI and fabrication of a 30,000-tonne gas compression system and associated subsea pipelines, flowlines and other structures, to a consortium of India’s Larsen & Toubro Energy Hydrocarbon (L&TEH) and Lamprell.
Larsen & Toubro (L&T) confirmed its contract award from Adnoc Group subsidiary Adnoc Offshore earlier in August, describing the order as “ultra-mega”, a term the company uses for contracts valued at more than Rs150bn ($1.57bn).
Mumbai-headquartered L&T added that the contract will be executed through a consortium, with its subsidiary L&TEH Offshore serving as the lead partner, without mentioning Lamprell.
The Umm Shaif Gas Cap reserve is located within the offshore Umm Shaif and Nasr hydrocarbons concession, which is operated by Adnoc as the majority stakeholder. The other stakeholders in the concession are Italy’s Eni, France’s TotalEnergies and China National Petroleum Corporation (CNPC).
Through this project, Adnoc and its concession partners intend to produce up to 600 million cubic feet a day (cf/d) of natural gas by unlocking the Umm Shaif Gas Cap in Abu Dhabi’s Gulf waters.
Adnoc, in its 21 July statement, said the FID includes three EPC packages totalling $5.1bn for large-scale offshore infrastructure, awarded to consortiums comprising UAE and international contractors. The company did not disclose the contractors or the scope of work.
MEED reported in May that the following contractors had emerged as frontrunners for the two offshore packages and one onshore package of the Umm Shaif Gas Cap and surface pressure boosting project:
- First offshore package – fabrication of a 30,000-tonne gas compression system: L&TEH (India) / Lamprell (Saudi Arabia/UAE)
- Second offshore package – fabrication of another 30,000-tonne gas compression system: McDermott (US)
- Onshore package – EPC of gas inlet and processing systems on Das Island: China Petroleum Engineering & Construction Company
Adnoc added that, as part of the FID, it has also awarded a $365m contract to its subsidiary Adnoc Drilling for a 14-well drilling and integrated drilling services scope, to be delivered over 18 months using three existing rigs.
Umm Shaif Gas Cap project
Adnoc Offshore, the offshore oil and gas business of Adnoc Group, is the operator of the Umm Shaif Gas Cap and surface pressure boosting project.
The primary objective is to increase gas production by 550 million cf/d and raise associated condensate output by 50,000 barrels a day (b/d).
Adnoc Offshore intends to feed about 520 million cf/d of the additional produced gas into Adnoc Group’s sales gas grid.
Adnoc Offshore is understood to have issued the main EPC tender for the Umm Shaif Gas Cap and surface pressure boosting project in the first quarter of 2025.
Contractors submitted technical bids for the three EPC packages by 30 October last year, while commercial bids were submitted by the 2 February deadline.
The following contractors are among those understood to be bidding for the three EPC packages, according to sources:
Offshore package 1:
- Saipem (Italy) / Seatrium (Singapore)
- L&TEH (India) / Lamprell (Saudi Arabia/UAE)
- NMDC Energy (UAE) / Hyundai Heavy Industries (South Korea)
Offshore package 2:
- China Offshore Oil Engineering Company (China)
- McDermott (US)
- L&TEH (India) / Lamprell (Saudi Arabia/UAE)
- NMDC Energy (UAE) / Hyundai Heavy Industries (South Korea)
Onshore package:
- Archirodon (Greece)
- China Petroleum Engineering & Construction Company (China)
- Engineering for the Petroleum & Process Industries (Egypt)
- Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
- Target Engineering Construction Company (UAE)
Australian firm Worley has performed front-end engineering and design (feed) work on the project.
Umm Shaif gas production
Adnoc Offshore operates the Umm Shaif hydrocarbons development, which is located 150km northwest of the city of Abu Dhabi. The field is located in Abu Dhabi’s offshore Umm Shaif and Nasr hydrocarbons concession, previously operated by former Adnoc Group companies Adma-Opco and Zadco.
In March and April 2018, Abu Dhabi’s Supreme Council for Financial and Economic Affairs awarded a 10% stake in the Umm Shaif and Nasr offshore block to Eni, 20% to TotalEnergies and 10% to CNPC. Adnoc Group retained the majority 60% interest. The operators produce a total of about 460,000 b/d of oil from the Umm Shaif and Nasr block.
Gas is produced from the Umm Shaif Khuff and Uweinat reservoirs, as well as from the Arab C and Arab D Early Production Scheme 2. The Umm Shaif Khuff reservoir is a formation that consists of dry gas volumetric reservoirs located in the Umm Shaif field.
Khuff reservoirs have been in production in Abu Dhabi since August 1989. Umm Shaif Khuff gas is currently produced from 28 active wells within the Umm Shaif field. A majority of these wells supply gas to Adnoc Group subsidiaries Adnoc LNG and Adnoc Gas Processing, with the rest supporting oil reservoirs at the Umm Shaif field through gas injection.
The Umm Shaif Super Complex (USSC) processes and transports oil, condensates and natural gas in separate pipelines to Das Island for further processing and export. The condensates collected from the USSC are transported to Das Island through an 18-inch pipeline stretching 34.4km, or are spiked into the 36-inch Adnoc main oil line.
The gas collected from the USSC is transported to Das Island through two 46-inch pipelines, which also run 34.4km.
Pressure at the Umm Shaif Khuff gas reservoirs will start to decline by the end of 2028. The flowing wellhead pressures at some of the Khuff gas wellhead towers are likely to reduce, so boosting well deliverability and increasing the flowrates is necessary.
Therefore, new Khuff surface pressure boosting facilities are required to maintain the plateau – with a goal of achieving a 90% gas recovery factor – and increase production beyond the end of the plateau by lowering pressure at the Khuff reservoirs.
Project tendering exercise
Adnoc Offshore has been working to advance the Umm Shaif Gas Cap project since at least 2019 and has experimented with several project execution models.
According to the original schedule, the project was due to be commissioned in 2023, but progress slowed down, primarily due to the Covid-19 pandemic.
Adnoc Offshore launched a feed-to-EPCI competition for the project in May 2019 and selected the following three entities based on their feed submissions:
- McDermott (US)
- National Petroleum Construction Company (UAE; now NMDC Energy) / TechnipFMC (France)
- Saipem (Italy) / Petrofac (UK)
Technical bids for the EPCI works on the estimated $1.5bn project were submitted in January 2020 and commercial bids were submitted by August of that year.
The Saipem/Petrofac consortium emerged as the lowest bidder for the project in September 2020, MEED reported.
Petrofac is understood to have ultimately withdrawn from the consortium and was replaced by state-owned China Petroleum Engineering & Construction Company (CPECC).
In 2022, the Saipem/CPECC consortium was understood to be the sole remaining bidder for the Umm Shaif Gas Cap project. Adnoc Offshore engaged the consortium for a revised feed exercise and subsequently received commercial offers on a single-source basis.
In 2023, Adnoc Offshore cancelled the tendering process for the project and later decided to proceed with a conventional EPC-based project execution model.
The operator then appointed Worley to undertake feed works on the renewed Umm Shaif Gas Cap project in 2024. Worley has a legacy of involvement in the Umm Shaif hydrocarbons development.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18556614/main1931.jpg -
Hitachi Energy signs Erbil substations deal14 August 2026
Switzerland-headquartered Hitachi Energy has annnounced it has signed an agreement to supply high-voltage equipment for three 132/33kV substations being developed in Erbil in northern Iraq.
The substations are being built by Iraqi electrical contractor Hero Company under a ID100bn ($76.3m) contract signed with the Kurdistan Region's Electricity Ministry in May.
In a statement, Hitachi said it will act as the main technology provider for the project, which has a combined capacity of 753 megavolt-amperes.
According to local media reports, the substations will be located in Shamamak, Hasarok and Timar. The ministry said the projects are to be completed within two years.
Hitachi Energy says it has supplied more than 120 mobile substations and delivered more than 30 transmission substations in Iraq over the past 15 years. It also says it has upgraded assets including Iraq's National Control Centre.
Iraq’s power and water sector is currently undergoing one of its largest expansion programmes in decades amid chronic electricity and water shortages.
In 2025, it recorded its largest year of investment on record, with more than $17bn in combined contract awards.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18548939/main3553.jpg -
Contracts signed for Algerian phosphate project14 August 2026
Algeria’s national oil and gas company Sonatrach and the Algerian Chinese Fertilisers Company (ACFC) has signed two engineering, procurement and construction (EPC) contracts for the country’s planned phosphate integrated project in Tebessa Province.
ACFC was created in March 2022 by Algerian companies Asmidal and Manadjim El-Djazair (Manal), which own 56% of the company, and Chinese groups Wuhuan and Tianan, which own the remaining 44% stake.
Manal and Asmidal are both subsidiaries of Sonatrach.
The new contracts are part of the Bled El-Hadba phosphate development project, which is expected to be worth $7bn.
The contracts were signed by Italy’s Saipem and China Harbour Engineering Company (CHEC) as part of the first phase of the integrated phosphate project.
Saipem’s contract is worth approximately €500m ($577m), according to a statement released by the Italian company.
Saipem was previously awarded a front-end engineering and design (feed) contract for the same project in June 2025.
The signing ceremony for the latest two EPC contracts took place at the headquarters of Sonatrach's general directorate, in the presence of members of the government, Sonatrach CEO Nour Eddine Daoudi, the ambassadors of Italy and China in Algeria, as well as officials from Saipem and CHEC.
The first phase of the project involves the construction of industrial and port infrastructure, including a phosphate extraction and enrichment complex in Bled El-Hadba with an extraction capacity of 5.5 million tons a year (t/y) and an overall production capacity of concentrated phosphate estimated at 3.2 million t/y.
Phase one also includes the construction of an integrated industrial complex in Oued Kebrit with the capacity to produce 2.4 million t/y of phosphate fertiliser and 570,000 t/y of nitrogen fertiliser.
The facility in Oued Kebrit will also produce quantities of other intermediate products.
Port infrastructure will be constructed in Annaba with the aim of enabling the establishment of an integrated industrial and logistics ecosystem.
During the signing ceremony, Minister of State and Hydrocarbons Minister Mohamed Arkab said that the project benefits from special attention from Algerian President Abdelmadjid Tebboune, within the framework of his vision to exploit natural resources, strengthen national industrialisation, create added value, diversify the national economy and promote the country’s non-hydrocarbons exports.
He said that the project will be carried out according to an “accelerated EPC fast-track method”, in order to reduce completion times and bring production online faster.
This is expected to allow the first quantities of enriched phosphate to be produced in the first quarter of 2027 and fertiliser production is expected to start during the fourth quarter of the same year.
When the project is fully operational, it is expected to produce approximately 6 million t/y of enriched phosphate and 4 million t/y of different types of phosphate and nitrogen fertilisers.
It will also produce industrial materials such as sulfuric acid, phosphoric acid and ammonia, according to Arkab.
He said that Algeria's ambition is not limited to the production of phosphate and fertilisers and also includes the establishment of an integrated industrial chain capable of creating added value, developing skills, supporting the national economy and opening new horizons for Algerian products on international markets.
Daoudi, the chairman and chief executive of Sonatrach, said that the signing of the two contracts marked the effective transition to the implementation phase of this project, which "undoubtedly constitutes a key milestone in the industrial development process in Algeria".
The scope of the EPC contract signed by Saipem covers the construction of project facilities at the Bled El-Hadba site and the Oued Kebrit site.
Saipem’s chief executive Alessandro Puliti said that his company will try to deliver the project on time and will work with three local companies on the project.
The three companies are pipeline specialist Cosider Canalisations; Algerian Industrial Projects Realisation Company, which is a subsidiary of Sonatrach; and state-owned National Civil Engineering & Building Company.
The scope of the EPC contract signed by CHEC is focused on developing the Annaba port infrastructure project.
Speaking at the signing ceremony, CHEC's deputy general manager Chen Zhong said his company is committed to completing the first and second phases of the Annaba port project within the allotted timeframe.
The wider integrated phosphates project has four main focus areas.
These are:
- The Bled El-Hadba phosphate mine
- Phosphate enrichment units
- The Oued Kebrit chemicals processing complex
- Logistics facilities, including the extension of the port of Annaba and a railway network dedicated to the transport of raw materials and finished products
In its statement, Saipem described the document that it signed with Sonatrach as a limited notice to proceed (LNTP) for the execution of phase one of the integrated phosphate project in Algeria.
It said: “The full EPC contract will be based on a contractual framework which will allow both parties to share risks and rewards during the execution, including the LNTP period which will enable Saipem to start the preliminary activities that are preparatory and critical for achieving the first project milestones.
“These include but are not limited to feed completion and detailed engineering, procurement of long lead items, as well as preliminary project mobilisation and organisation activities, pending the negotiation and finalisation of the EPC contract.”
Saipem has been present in Algeria since 1968 and has developed infrastructure for hydrocarbons treatment and transportation, power generation plants and oil well drilling.
The Bled El-Hadba phosphate mine has over 1.2 billion tonnes of estimated total reserves, including 800 million tonnes of estimated exploitable reserves, making it one of the biggest mines of its kind in the world.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18499932/main.jpg