Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Contractor groups prequalify for Dubai Metro Gold Line

    13 October 2026

     

    Six contracting groups submitted prequalification statements on 9 October for the contract to build Dubai Metro’s new Gold Line.

    The Roads & Transport Authority (RTA) issued the request for qualification notice for the project in June, as MEED exclusively reported.

    The consortiums formed to bid for the main contract are:

    • Alstom / China Railway Engineering Corporation / National Projects Construction / Dogus Construction (France/China/local/Turkiye)
    • CRRC / Limak / Mapa Group (China/Turkiye/Turkiye)
    • Hitachi / China Harbour Engineering Company / China State Construction Engineering Corporation (Japan/China/China)
    • Siemens / Petrojet / Concord Engineering & Contracting / Rowad Modern Engineering (Germany/Egypt/Egypt/Egypt)
    • Hassan Allam / IC Ictas / Siemens (Egypt/Turkiye/Germany)
    • Larsen & Toubro / Powerchina / Wade Adams (India/China/local)

    Dubai officially announced the Gold Line in April.

    In a post on social media site X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, said the project would cost about AED34bn ($9.2bn).

    The Gold Line will increase the Dubai Metro network’s total length by 35%. The project is scheduled to be completed in September 2032.

    The fully underground line will extend for more than 42 kilometres and include 18 stations. It will pass through 15 areas of Dubai and serve 1.5 million residents.

    The project is expected to connect more than 55 under-construction real estate developments.

    The Gold Line will begin at Al-Ghubaiba in Bur Dubai and terminate at Jumeirah Golf Estates. It will connect with the existing Red and Green lines and integrate with the Etihad Rail passenger network.

    The contractor will be responsible for the design and construction of all civil works, electromechanical equipment, rolling stock and rail systems. The selected contractor will also be required to support systems maintenance and operations during an initial three-year period.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the Dubai Metro Gold Line project.

    Stage one covers concept design; stage two, preliminary design; stage three, tender-document preparation; stage four, construction supervision; and stage five, the defects-liability period.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20531469/main.png
    Yasir Iqbal
  • Egypt discusses technology cooperation with SLB

    13 October 2026

    Egypt is in talks with US-based oilfield services company SLB to expand technical cooperation in the country’s oil and gas sector, according to a statement from the Ministry of Petroleum & Mineral Resources.

    Egyptian Minister of Petroleum and Mineral Resources Karim Badawi met SLB chief executive Olivier Le Peuch in Riyadh, the ministry said.

    During the meeting, they discussed ways to strengthen their strategic partnership and expand cooperation in technology and digital transformation.

    They also discussed how SLB could support exploration and production activities, with the aim of increasing output and attracting further investment in Egypt’s oil and gas sector.

    Badawi emphasised the importance of extending the existing partnership with SLB, including its role in technology transfer and the development of technical capabilities in Egypt’s oil sector, according to the statement.

    He said Egypt should build on existing areas of cooperation and deploy advanced technological solutions to reduce exploration risk, increase recovery and production rates from existing fields, and improve operational efficiency.

    Badawi and Le Peuch also discussed progress on a seismic survey project being undertaken by SLB in partnership with France-based Viridien.

    The project includes an ocean-bottom node seismic survey covering about 95,000 square kilometres of Egypt’s eastern Mediterranean waters.

    The discussion focused on the data processing and analysis schedule, the steps required to prepare and release preliminary results, and the drilling schedule.

    Badawi and Le Peuch also discussed expanding the use of horizontal drilling technologies in Egypt. This would involve identifying suitable locations and developing a commercial and contractual model for their deployment.

    The Ministry of Petroleum & Mineral Resources and SLB are also exploring opportunities to expand the use of artificial intelligence in reservoir management and production optimisation.

    This work is being explored in partnership with the Egyptian General Petroleum Corporation and Egyptian Natural Gas Holding Company.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20517735/main.jpg
    Wil Crisp
  • Kuwait tenders gas export pipeline

    13 October 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) has tendered a contract to develop a gas export pipeline.

    The 24-inch-diameter pipeline will extend from Booster Station 171 (BS-171) to the Intermediate Slug Catcher (ISC) facility in southeastern Kuwait, passing through the tie-in point known as TP-1.

    The bid deadline is 5 January 2027. A preliminary online meeting to discuss the project is scheduled for mid-November.

    BS-171 was inaugurated in February 2018. It serves as a central gas-treatment facility for gas and condensate from several gathering centres in West Kuwait and other areas.

    The feeder gathering centres include GC-17, GC-27, GC-28 and GC-16.

    BS-171 was Kuwait’s first facility designed specifically to handle acid gas.

    The ISC facility is located about 80 kilometres from BS-171.

    KOC announced plans to tender the project last year. At the time, it said that the scope would include the installation of bidirectional pig traps above the new pipeline.

    A pig trap is a section of piping that enables a pipeline pig – a device used to clean, inspect or maintain a pipeline – to be launched or received.

    The chosen contractor will need to provide:

    • Valves
    • Piping
    • Fittings
    • Civil services
    • Structural services
    • Electrical and instrumentation services
    • Tie-ins
    • Testing services
    • Pre-commissioning services
    • Commissioning services

    The ISC facility is a major gas-handling facility in Kuwait’s Burgan area. It receives sour gas from West Kuwait oil fields before the gas is transported onwards to the Mina Al-Ahmadi gas-processing facilities.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20517716/main.jpg
    Wil Crisp
  • Developers prepare bids for 1GW Oman bess scheme

    12 October 2026

     

    Developers are preparing to submit bids for almost 1GW of standalone battery energy storage (bess) projects in Oman, a source close to the project has confirmed to MEED.

    The independent power producer (IPP) scheme includes the installation of five bess facilities with a combined power capacity of 950MW and storage capacity of 3,800MWh. Nama Power & Water Procurement Company (PWP) is procuring it.

    According to sources close to the project, a developer’s tender was floated in the summer. An initial bid submission deadline has since been extended, with bids expected to be submitted in the coming weeks.

    The largest project is a 500MW facility in Sohar, Al-Batinah North governorate, with a storage capacity of 2,000MWh. The Sohar facility is expected to connect to the grid at 220kV. The site covers approximately 149,535 square metres.

    Four further installations are planned at Al-Mabellah in Muscat governorate, Ayjah in South Al-Sharqiyah, the Jalan Bani Bu Ali wind farm site in South Al-Sharqiyah, and Sadah in Dhofar.

    The Al-Mabellah and Ayjah facilities are each planned to have a capacity of 100MW and storage capacity of 400MWh. Both are expected to connect to the grid at 132kV.

    The Jalan Bani Bu Ali installation is planned to have a capacity of 150MW and storage capacity of 600MWh. It is expected to connect to the Sadah wind farm and Jalan Bani Bu Ali wind farm substations.

    The Sadah installation is planned to have a capacity of 100MW and storage capacity of 400MWh. It is expected to connect to the Sadah wind farm substations at 132kV.

    US/India-based Synergy Consulting is the financial adviser for the procurement; Germany’s Fichtner is the technical adviser; and Germany-headquartered CMS is the legal adviser.

    Utility-scale storage

    In May, Oman’s Authority for Public Services Regulation (APSR) opened technical bids for a consultancy contract supporting a planned 1,000MW/four-hour bess project.

    As previously reported, APSR issued the request for proposals in April as part of wider plans to increase the share of renewable energy in the sultanate. 

    The sultanate’s first utility-scale solar photovoltaic (PV) plant integrated with battery energy storage (Ibri 3) entered construction at the beginning of the year, comprising a 500MW solar PV plant and a 100MWh bess system.

    Also in May, state offtaker Nama Power & Water Procurement Company signed a power purchase agreement with local firm O-Green for Oman’s first round-the-clock renewable energy project.

    Renewable energy is expected to increase from 4% of the generation mix in 2024 to 30% by 2030, driving the push for more utility-scale storage projects.

    Over roughly the same period, demand is forecast to double, reaching 10 terawatt-hours by 2031.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20511976/main.jpg
    Mark Dowdall
  • Frontrunner emerges for Saudi Arabia’s GCC rail link design

    12 October 2026

     

    French engineering firm Systra has emerged as the frontrunner to provide design consultancy services for the Saudi Arabian section of the GCC railway network, which is intended to link all six member states.

    The tender covers the concept, preliminary and issued-for-construction design stages. Saudi Arabia Railways (SAR) requires the selected consultant to review, update and complete the existing preliminary design.

    Consultants submitted proposals on 14 July, as MEED reported.

    The consultants who submitted bids included: 

    • AtkinsRealis with Khatib & Alami
    • Deutsche Bahn with ARX
    • Egis with Sener
    • Idom with Dar Al-Handasah
    • Systra

    Saudi Arabia’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, on Saudi Arabia’s border with the UAE. 

    Tendering is also ongoing for a separate contract involving design management and review to oversee engineering works on the GCC railway network.

    The tender was issued on 9 September, with a submission deadline of 18 October, as MEED exclusively reported.

    The tender seeks a consultant to manage, audit and verify deliverables produced by SAR’s separately appointed design services consultant, rather than carry out the design itself.

    Construction will be tendered separately through competitive bidding once designs are approved.

    The GCC railway will run for about 672km inside Saudi Arabia, linking the kingdom’s existing network to Kuwait, Qatar, the UAE and Bahrain, with four sections of about 141km, 200km, 151km and 21km, respectively.

    The line is planned as a single-track, non-electrified corridor for mixed freight and passenger traffic, with a maximum axle load of 32.4 tonnes and passing loops for bidirectional working.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to cover about 2,186km in total.

    The route length within each member state is as follows:

    • UAE – 684km
    • Saudi Arabia – 672km
    • Oman – 306km
    • Qatar – 283km
    • Kuwait – 145km
    • Bahrain – 36km

    The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80km/h–120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20510318/main.gif
    Yasir Iqbal