Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Egypt approves plans for 869MW wind power plant22 June 2026
-
Local firm signs Jeddah drainage contracts22 June 2026
-
Saudi firm signs Uzbekistan water treatment PPP22 June 2026
-
Qiddiya seeks contractors for indoor arena project22 June 2026
-
Egypt signs gas deal with Harbour Energy22 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt approves plans for 869MW wind power plant22 June 2026
Egypt’s Cabinet has approved plans for French renewable energy developer Voltalia to develop an 869MW wind power project.
The scheme will be built on land allocated by the New & Renewable Energy Authority (NREA), according to a statement posted by the Cabinet following its most recent weekly meeting.
Voltalia will make an initial investment of $53m and has committed to achieving commercial operations by December 2028.
Voltalia already operates the 32MW Ra solar plant at the Benban solar complex in Aswan and is expanding its renewable energy portfolio in Egypt.
Previously, in 2024, it signed a framework agreement with Egypt’s Taqa Arabia to develop a green hydrogen and renewable power cluster near the Ain Sokhna port in the Suez Canal Economic Zone.
The green hydrogen development is planned in two phases, each centred on a 500MW electrolyser powered by more than 1.3GW of renewable generation capacity. The project, still in its early stages, is expected to produce up to 350,000 tonnes of green ammonia a year.
Voltalia’s partnership with Taqa Arabia also includes plans for a 3.2GW hybrid wind and solar project to repower the existing 545MW Zafarana wind farm in Suez Governorate. The Cabinet statement did not indicate whether the newly approved 869MW wind project forms part of that proposal.
Meanwhile, the developer won another contract, earlier this year, to develop a 132MW solar power project in Tunisia’s Gabes region.
The project, known as Wadi, marked Voltalia’s third major solar award in the country after the Sagdoud and Menzel Habib projects awarded in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17376730/main.jpg -
Local firm signs Jeddah drainage contracts22 June 2026
Local contractor Alkhorayef Water & Power Technologies (AWPT) has announced it has signed two contracts with Jeddah Municipality to operate and maintain stormwater and surface water drainage networks across the city.
The contracts have a combined value of SR202.06m ($53.9m), and each will run for five years.
The first contract, valued at SR108.46m ($28.9m), covers the operation and cleaning of stormwater and surface water networks in the South and Al-Malisa sub-municipalities.
The second contract, worth SR93.59m ($25m), covers similar services for the Airport Sub-Municipality.
In March, MEED reported that the firm had won a long-term contract to carry out work in the airport’s sub-municipality area. The agreement was signed on 16 June.
Elsewhere, construction has yet to begin on phases one and two of the King Abdullah Road-Falasteen Road tunnel project, each valued at about $175m.
According to sources, Jeddah Municipality selected Saudi contractor Thrustboring Construction Company to build the large-diameter stormwater drainage tunnels in 2025. However, an official agreement has yet to be signed.
The municipality was also previously planning to rehabilitate the existing Al-Zahra pumping station. Prequalification for the project began in 2020; however, it is understood that the main contact tender was cancelled last year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17376097/main.jpg -
Saudi firm signs Uzbekistan water treatment PPP22 June 2026
Saudi-listed Miahona has signed a public-private partnership agreement to enhance, operate and maintain Uzbekistan’s Zomin water treatment plant in the country’s Jizzakh region.
The agreement was signed on 18 June with Uzsuvtaminot, the country’s state-owned water utility, the developer said in a filing with the Saudi stock exchange.
Miahona will carry out enhancement works and 25 years of operation and maintenance services for the existing plant, which has a design treatment capacity of 50,000 cubic metres a day
The contract marks the company’s entry into Uzbekistan’s water sector. According to the disclosure, it will enter into force once a project-related governmental decree is issued in accordance with Uzbekistan’s applicable legislation.
The contract is estimated at $105m (SR395m), with a final value to be confirmed following the issuance of the governmental decree.
MEED reported earlier this month that Uzbekistan had stepped up its engagement with Middle Eastern investors, including holding talks with Saudi Arabia’s Acwa and Vision Invest on renewable energy, water management, waste recycling, digital infrastructure and urban utility projects.
The government also recently held discussions with a UAE delegation led by Suhail Mohamed Al-Mazrouei, minister of energy and infrastructure and chairman of Etihad Water & Electricity’s Board of Directors.
At the Tashkent International Investment Forum, it signed a €197m financing package with Germany’s KfW Development Bank to support drinking water supply and wastewater projects in the Surkhandarya and Fergana regions.
The projects will cover Termez and several district centres in Surkhandarya region, as well as Kokand and Margilan in Fergana region.
This includes “the construction and reconstruction of hundreds of kilometres of drinking water and wastewater networks, pumping stations and modern wastewater treatment facilities”, deputy prime minister Jamshid Khodjaev said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17375811/main.jpg -
Qiddiya seeks contractors for indoor arena project22 June 2026

Register for MEED’s 14-day trial access
Saudi Arabian gigaproject developer Qiddiya Investment Company (QIC) has invited contractors to prequalify for a contract to build an indoor sports arena within its Qiddiya entertainment city project.
The invitation was issued on 21 May, with a submission deadline of 28 June.
The multipurpose arena is designed to International Olympic Committee standards.
It will be located in District 18, in the Uptown South area of Qiddiya.
Once completed, the indoor arena will be capable of hosting a wide range of sports, cultural and entertainment events.
The arena will feature numerous sports courts for basketball, handball, futsal, volleyball, tennis, boxing and gymnastics.
It will have a seating capacity of 18,000 spectators.
The project is scheduled for completion by 2030.
QIC’s other major projects include an e-sports arena, the National Tennis Centre, Prince Mohammed Bin Salman Stadium, a motorsports track, a racecourse, the Dragon Ball and Six Flags theme parks, and Aquarabia.
QIC opened the Six Flags theme park to the public in December last year.
The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17375504/main.jpg -
Egypt signs gas deal with Harbour Energy22 June 2026
Egypt’s Ministry of Petroleum & Mineral Resources has signed a new agreement with London-headquartered Harbour Energy.
Under the scope of the agreement, Harbour Energy will drill two new exploration wells and carry out maintenance work for one of the existing wells within the Dsouq-1 development contract.
Harbour Energy committed an initial $6m investment and a $1m signing bonus for the Dsouq concession. Total investment could rise to $18m if commercial discoveries are made.
The signing was witnessed by Egypt’s Minister of Petroleum, Karim Badawi.
He said that his ministry is continuing to implement a package of investment measures and incentives aimed at encouraging partners to increase investments and intensify exploration, development and production activities.
The agreement was signed by Syed Saleem, a member of the executive branch of the state-owned Egyptian Natural Gas Holding Company (EGAS), and Samah Sabry, the executive director of Harbour Energy for the Middle East and North Africa region.
Harbour Energy drilled two new wells in Egypt during the fiscal year 2025/2026, resulting in the addition of reserves estimated at 35 billion cubic feet of gas.
The company aims to drill three new exploration wells during the fiscal year 2026/2027.
Egypt is currently pushing to boost the production of both oil and gas in its territory.
Earlier this month, Egypt’s Ministry of Petroleum & Mineral Resources announced that it had fully settled all outstanding arrears owed to oil and gas companies.
Two years ago, in June 2024, the country owed approximately $6.1bn to partners in the oil and gas sector.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17374536/main4731.jpg
