Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Firms submit Jebel Ali sewage PPP prequalifications24 July 2026
-
-
-
Qiddiya tenders Dragon Ball theme park package24 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms submit Jebel Ali sewage PPP prequalifications24 July 2026

Dubai Municipality received statements of qualification on 23 July from firms interested in delivering phase three of the Jebel Ali sewage treatment plant (STP) expansion project.
Known as DS150/3, the project will be delivered under a public-private partnership (PPP) model on a design, build, finance, own, operate and transfer basis.
The project involves the development of a new water resource recovery facility with an ultimate treatment capacity of up to 1 million cubic metres a day (cm/d).
It is being procured through Dubai Municipality’s sewerage and recycled water projects department and will be delivered via a two-stage operational approach over a 30-year concession period.
It is understood that the following firms are among those likely to qualify for the project:
- Acciona (Spain)
- Alkhorayef (Saudi Arabia)
- Besix (Belgium)
- Etihad WE (UAE)
- GS Inima (Spain)
- Metito (UAE)
- Miahona (Saudi Arabia)
- Samsung E&A (South Korea)
- Saur (France)
- Suez (France)
- Taqa Water Solutions (UAE)
- Veolia (France)
The municipality issued a request for qualifications notice in May with an intial bid submission deadline of 18 June. UK-headquartered Deloitte is acting as financial adviser, Aecom is the project's technical adviser and CMS is the legal adviser.
Dubai Municipality said the project will also include additional land uses and community-focused amenities as part of broader sustainability and urban integration objectives.
Phase one and two expansion
On 9 July, firms submitted bids for an engineering, procurement and construction contract covering the expansion of the Jebel Ali STP phases one and two.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d, following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cm/d, with the expansion estimated to cost $300m.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17735401/main.jpg -
Contractors submit interest for Riyadh Expo substructure24 July 2026

Contractors have submitted expressions of interest on 23 July for a contract to deliver the early works and substructure works for several assets at the Expo 2030 Riyadh site.
Expo 2030 Riyadh Company (ERC) is tasked with delivering the Expo 2030 Riyadh venue. Saudi sovereign wealth vehicle, the Public Investment Fund, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for the event.
The assets include the Icon; the convention centre; and thematic pavilions, including the Culture of Wisdom, Place & Planet and Adaptation & Innovation pavilions.
The Icon will be located at the entrance of the Expo 2030 Riyadh site, within the Collaboration Precinct.
The structure will be connected to the metro station and will serve as a gateway to the event.
It will be 66 metres tall and will comprise an observation platform, food and beverage (F&B) outlets and other features.
The convention centre will cover about 22,000 square metres. It will be the first point of arrival for visitors to the expo.
The Culture of Wisdom pavilion will be a 25-metre-tall building that will feature exhibition galleries, innovation laboratories and conference and learning spaces.
The Place & Planet building will also be 25 metres tall, and will include indoor and outdoor exhibition spaces, F&B and retail facilities and support areas.
The Adaptation & Innovation pavilion will be located within the Loop of Nations precinct and will comprise a 29-metre-tall building.
Construction progress
The tendering of the pavilion structures followed progress on the site’s infrastructure development works.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.
The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – are split into three packages:
- Lot 1 covers the main utilities corridor;
- Lot 2 includes the northern cluster of the Nature Corridor;
- Lot 3 comprises the southern cluster of the Nature Corridor.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17739044/main.jpg -
Oil price rises above $100 a barrel after Red Sea attacks24 July 2026
Oil prices rose to their highest level in nearly two months on 23 July after the latest escalation in the US-Iran conflict threatened severe new disruptions to global energy supplies.
Global benchmark Brent crude closed 7% higher, at $100.69 a barrel on 23 July. Earlier in the trading day, it rose as high as $102 a barrel. That is its highest level in eight weeks, since the end of May.
Brent was trading at over $100 a barrel in the early hours of 24 July, but later pared gains to settle around $99.63 a barrel as of 11am Gulf Standard Time (GST).
The surge in the Brent price came after Iran-backed Houthi rebels claimed attacks on two Saudi oil tankers in the Red Sea following their announcement of a naval blockade on Saudi Arabia.
It appeared to be the first time since the regional war began that attacks on oil tankers and other commercial ships had extended beyond the Strait of Hormuz, opening up a new front in the volatile conflict.
The Houthi threat is unsettling to oil markets because millions of barrels a day pass through the Bab El-Mandeb Strait to reach global markets.
ALSO READ: Opec+ holds the line on unwinding of production cuts
About 12%-15% of global maritime trade, worth more than $1tn, transits the waterway every year.
It has also served as an alternative to the Strait of Hormuz, where traffic remains largely at a standstill, with ship crossings falling to single digits on 21 July.
Since the start of July, oil prices have risen about 35%. Those prices are more than 60% higher than at the start of the year. This has erased much of the progress made in bringing prices down after the US and Iran signed a memorandum of understanding in mid-June.
The interim peace deal has now collapsed, with US President Donald Trump threatening on 22 July to blow up an Iranian bridge or power plant for every vessel Tehran attacks.
This was followed by the Houthi claim to have hit two tankers in the Red Sea.
The UK’s Maritime Trade Office reported a tanker “struck by an unknown projectile” north of the Bab El-Mandeb Strait, and state-run Saudi Press Agency (Spa) reported that a vessel named Encelia was set ablaze by an attack while it was sailing overnight in the Red Sea, citing an unidentified source from the General Authority of Transport. Spa did not mention the other vessel, which is understood to be called Layla.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17739553/main4051.jpg -
Qiddiya tenders Dragon Ball theme park package24 July 2026

Qiddiya Investment Company (QIC) has tendered a contract to undertake the back-of-house works on the Dragon Ball theme park in Qiddiya, Saudi Arabia.
The scope covers the construction of plant rooms, facilities management buildings, workshops, storage warehouses and central processing kitchens.
It also includes a monorail service depot, a fire station, parking, utilities and other associated infrastructure.
The bid submission deadline is 13 September.
The Dragon Ball theme park will cover more than 500,000 square metres and will have seven themed zones inspired by the Japanese media franchise, including Kame House, Capsule Corporation and Beerus’ Planet.
The park will offer more than 30 rides with five main attractions, including a rollercoaster that passes through a 70-metre landmark based on the series’ wish-granting dragon Shenron.
The development will also include themed hotels.
In September 2024, US-based firm Falcon’s Creative Group announced that it is undertaking the masterplan and attraction design and is the creative lead for the theme park.
QIC formally launched the Dragon Ball theme park in March 2024.
The announcement came after QIC signed an agreement with Japanese firm Toei Animation, the producer of the Dragon Ball anime series.
The Dragon Ball theme park is one of several major projects within the wider Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a horse racing venue, a performing arts centre, the Speed Park and Six Flags theme parks and Aquarabia waterpark.
The project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17738622/main.jpg -
Saudi Arabia appoints developer for hybrid power plant24 July 2026

Saudi Arabia-based Lamar Holding has signed a contract to develop a hybrid power plant at the Empty Quarter (Rub Al-Khali) land port in Saudi Arabia, according to a source.
The public-private partnership (PPP) project aims to reduce diesel fuel use with renewable energy and ensure a long-term power supply at the Empty Quarter land port. It includes the construction of 15MW of total hybrid installed capacity, installation of a 7 megawatt-peak solar photovoltaic system and eight 1MW internal combustion engines.
In March, MEED exclusively reported that Lamar had been given preferred bidder status and was in advanced discussions with Saudi Arabia’s Zakat, Tax & Customs Authority (Zatca) for the contract.
MEED understands that the proposed plant will have the capacity to produce 25 gigawatt-hours of electricity annually. It will be implemented under a design, build, finance, operate, maintain and transfer contract model for 25 years, excluding the construction period.
US/India-based Synergy Consulting is acting as financial advisor to Lamar on the project. Egyptian firm Eternal Consultation Engineering Services is acting as the technical support consultant and Dubai-headquartered Aktech is the technical consultant for the project.
Lamar Holding and Dubai’s SirajPower submitted bids for the Empty Quarter hybrid power plant project in July 2025, as previously reported by MEED.
Zatca, in collaboration with the National Centre for Privatisation & PPP, had previously prequalified the following four companies to bid for the contract in October 2024:
- Alfanar Company (Saudi Arabia)
- Lamar Holding (Saudi Arabia)
- Olayan Energy (Saudi Arabia) / Enerwhere Sustainable Energy (UAE)
- Siraj Power for Renewable Energy (UAE)
Prior to that, in July 2024, 12 Saudi companies and local branches of international companies, along with 11 overseas-based companies, submitted statements of qualifications for the contract.
In addition to building and operating the power plant, the project scope includes ensuring the facility operates to defined requirements and output specifications. It also involves managing power generation and the connection to the Zatca interface point for the entire project term.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17733327/main.jpg