Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Dubai advances Auto Market construction6 May 2026
-
-
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai advances Auto Market construction6 May 2026

The construction works on the Dubai Auto Market, which is set to become one of the world’s largest and most advanced automotive trading hubs, are progressing.
Enabling works are under way, being carried out by local contractor Rad International Road Construction.
US-based engineering firm Aecom is serving as the project consultant.
In November last year, Dubai Municipality signed a partnership agreement with DP World’s Economic Zones division to establish and manage the market, as MEED reported. Under the agreement, DP World will provide integrated logistics and zone management services, including e-commerce and trade finance solutions.
The Dubai Auto Market will span a 22 million-square-foot complex, to be developed by DP World. It is planned to include more than 1,500 showrooms, clustered workshop zones, warehouses and multi-storey parking facilities, alongside a convention centre, hotel, auction house, retail outlets, and food and beverage areas.
The facility is designed to handle more than 800,000 vehicles a year, including new and used electric, hybrid and conventional models.
The UAE’s construction industry is projected to expand by 5% in real terms in 2026, supported by rising foreign direct investment (FDI), growth in the construction sector and increased oil sector activity.
According to the UAE’s Federal Competitiveness and Statistics Centre, construction value added rose by 8.8% year on year (YoY) in Q2 2025, following YoY growth of 7% in Q1 2025 and 10.8% in Q4 2024.
The commercial construction sector is forecast to grow by 6.4% in 2026 and to record average annual growth of 4.9% from 2027 to 2030, supported by investment in tourism and hotel facilities.
The industrial construction sector is expected to expand by 4.1% in real terms in 2026, then to average 4.4% annually from 2027 to 2030, supported by improved investment in manufacturing facilities.
The infrastructure construction sector is projected to grow by 5.8% in real terms in 2026, before averaging 4.3% annual growth from 2027 to 2030, supported by the government’s focus on improving regional connectivity through road and rail development.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16700367/main.png -
Saudi Arabia extends bid deadline for solar projects6 May 2026

Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), has extended the deadline for developers bidding for four solar projects under the seventh round of the National Renewable Energy Programme (NREP).
Round seven of the NREP comprises solar photovoltaic (PV) and wind independent power producer (IPP) projects with a combined capacity of 5,300MW. The renewables programme is being led and supervised by the Ministry of Energy.
The four solar PV projects comprise:
- 1,400MW Tabjal 2 solar PV IPP (Tabrijal, Al-Jouf province)
- 600MW Mawqqaq solar PV IPP (Mawqqaq, Hail province)
- 600MW Tathleeth solar PV IPP (Tathleeth, Aseer province)
- 500MW South Al-Ula solar PV IPP (Al-Ula, Medina province)
The projects were tendered in January, with an initial bid submission deadline of 30 April.
The new deadline is 30 June.
The solar projects are the latest in a string of large-scale power and water developments across the region to have bidding extended in recent weeks.
In the UAE, the bid deadline for the seventh phase of Dubai Electricity & Water Authority’s Mohammed Bin Rashid Al-Maktoum Solar Park was recently pushed back to 1 July.
Bids for the 1,300MW Bilgah and 900MW Shagra wind IPPs are currently still due by 14 May, according to a source.
In January, MEED reported that 16 developers qualified to bid as both managing and technical members for the four solar PV projects under the seventh round of the NREP.
These include:
- Abu Dhabi Future Energy Company (Masdar)
- Alfanar Company (Saudi Arabia)
- Al-Gihaz Holding Company (Saudi Arabia)
- EDF Power Solutions (France)
- Kahrabel (Engie) (UAE / France)
- Sembcorp Utilities (Singapore)
- Jinko Power (HK) (China)
- TotalEnergies Renewables (France)
- Al-Jomaih Energy & Water (Saudi Arabia)
- Korea Electric Power Corporation (Kepco) (South Korea)
- Nesma Renewable Energy (Saudi Arabia)
- Korea Western Power (South Korea)
- Marubeni Corporation (Japan)
- SPIC Shanghai Electric Power (China)
- WahajPeak Holdings (Saudi Arabia)
- FAS Energy for Trading Company (Saudi Arabia)
A further six companies qualified to bid as a managing member only for the solar PV projects. These include:
- Saudi Electricity Company (Saudi Arabia)
- Grupo Empresarial Enhol (Spain)
- Power Construction Corporation of China (Power China) (China)
- GD Power Development (China)
- Gulf Development Public Company (Thailand)
- Reliance NU Energies Private (India)
The renewable energy programme aims to supply 50% of the kingdom’s electricity from renewable energy by 2030.
Earlier rounds under the NREP have already put in place large capacities. Last October, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP.
These comprise four solar PV IPP projects and one wind IPP project with a total combined capacity of 4,500MW.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16700361/main.jpg -
EtihadWE awards EPC contract for Fujairah IWP6 May 2026
Etihad Water & Electricity (EtihadWE) has awarded an engineering, procurement and construction (EPC) contract for the Fujairah 1 independent water producer (IWP) project.
The agreement was signed with a consortium of UAE-based NMDC Infra and Spain’s Lantania Aguas.
The EPC works will be delivered by Lantania NMDC Water. The company was formed after NMDC Infra acquired a 51% stake in Lantania Aguas in January 2026.
Fujairah 1 is the second desalination project procured by EtihadWE under a public-private partnership (PPP) model. It follows the 150-million-imperial-gallon-a-day (MIGD) Naqa’a IWP in Umm Al-Quwain.
The project involves developing a 60 MIGD seawater reverse osmosis (SWRO) desalination plant. The total investment is valued at AED1.046bn ($285m), the utility said in a statement.
The plant will be located at the Port of Fujairah on the Gulf of Oman and will include storage capacity equivalent to 18 hours of production.
Construction is expected to take about 30 months. Initial operations will begin at partial capacity, followed by ramp-up to full output.
Details of the water offtake agreement for Fujairah 1 have not been disclosed. EtihadWE previously signed a 35-year water-purchase agreement for the Naqa’a project.
Mohammed Al-Shehhi, CEO of the development and investment arm of EtihadWE, said the company is “currently developing multiple SWRO projects to be announced in due course”.
In January, Dubai International Financial Centre-based Deloitte Professional Services submitted the lowest bid for a contract to provide consultancy services to Dubai Electricity & Water Authority (Dewa) and EtihadWE.
The contract scope includes conducting a pre-feasibility study for an SWRO IWP and water transmission pipelines project.
The study will assess potential project sites, optimal plant capacity, technical and commercial parameters and the viability of associated water transmission infrastructure.
According to a source, the study’s consultant has not yet been appointed.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16700218/main.jpg -
June deadline for Riyadh section of Saudi Landbridge6 May 2026

Saudi Arabia Railways (SAR) has set a 2 June bid submission deadline for a design-and-build contract to construct the Riyadh Rail Link, a new railway line running north to south across Riyadh.
The tender was issued on 29 January. The previous bid submission deadline was 29 April.
The scope of work includes constructing a 35-kilometre-long double-track railway line connecting SAR’s North-South railway to the Eastern railway network.
The contract also covers the procurement, construction and installation of associated infrastructure such as viaducts, civil works, utility installations, signalling systems and other related works.
The project is expected to form a key component of the Saudi Landbridge railway.
In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.
In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements and that the project would now be delivered in several phases under a different procurement model.
The project has been under negotiation between Saudi Arabia and China-backed investors keen to develop it through a public-private partnership.
Al-Malik said that the project cost is about SR100bn ($26.6bn).
It comprises more than 1,500km of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.
Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.
The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16698846/main.jpg -
Bid deadline extended for Kuwait oil pipeline6 May 2026
State-owned upstream operator Kuwait Oil Company (KOC) has extended the bid deadline for a project to develop a crude oil pipeline in the country.
The invitation to bid was originally tendered in October last year, with a bid deadline of 18 January 2026.
Since then, the deadline has been extended several times, and the latest announced bid deadline is 31 May 2026.
The new pipeline will have a diameter of 20 inches and will carry the crude oil blend known as Ratawi-Burgen.
The project scope will involve replacing a 30-kilometre section of the pipeline known as CR-058.
The pipeline originates from the Wafra field and feeds crude oil into the larger 36-inch CR-088 crude oil pipeline.
The pipelines on this network have had documented corrosion issues in the past, which were linked to slow flow rates within the pipelines.
The Wafra field is located in the Partitioned Zone between Kuwait and Saudi Arabia.
Both countries equally share the natural resources contained in this region.
Kuwait is currently pushing to increase its oil production capacity.
In 2024, Kuwait Petroleum Corporation’s chief executive, Sheikh Nawaf Al-Sabah, reiterated that his company plans to increase Kuwait’s oil production capacity to 4 million barrels a day (b/d) by 2035.
In September last year, Kuwaiti Oil Minister Tareq Al‑Roumi announced that the country’s oil production capacity had reached 3.2 million b/d, its highest level in more than 10 years.
Kuwait had a similar capacity in the late 2000s, peaking at a recorded 3.3 million b/d in 2010.
Since the US and Israel’s attack on Iran on 28 February, Kuwait’s oil and gas sector has been rocked by the disruption to shipping through the Strait of Hormuz, through which all of the country’s crude is normally exported.
Kuwait recorded zero crude oil exports in April for the first time since the end of the Gulf War in 1991, according to shipping monitor TankerTrackers.com.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16691664/main5905.jpg


.gif)