Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Middle East becomes a hub as rail networks mature

    21 November 2025

     

    The resurgence in investment in metro and intercity lines means the region is no longer an emerging market for the global rail industry. It is now an established hub with an expanding network of projects and, increasingly, the need for ongoing servicing, upgrades and new technologies.

    “We are reaching a point where it is not just about building new lines. Customers are now understanding that it is not enough to just buy new trains – they also need long-term partnerships to service and maintain them efficiently,” says Martin Vaujour, Alstom’s Africa, Middle East and Central Asia region president.

    Alstom, which has supplied rolling stock and systems for major schemes in the region such as the Riyadh Metro, is now seeing growing demand for both new-build contracts and service agreements. “There are still lots of new investments,” he says, “but also growing activity in signalling projects, service projects and spare parts – areas that used to be small but are now taking off. That is a [source] of satisfaction for me, because those businesses are less risky, have better margins and create long-term relationships with customers.”

    The change is an important development as the region becomes a mature market with diverse opportunities for the rail industry. “There was a time when countries would just buy materials with export credit,” says Vaujour. “Now, they are supporting local capacity to service and maintain trains. The mindset is evolving, and that is a very positive sign.”

    Saudi expansion

    Buoyed by the opening of Riyadh Metro at the end of 2024, Saudi Arabia remains an important market. “They are happy with the success [of Riyadh Metro],” says Vaujour. “There is extension work on the existing lines, new rolling stock being discussed and a potential Line 7 project. The network is expanding, and that is a great success story.”

    The next wave of growth in Saudi Arabia includes the planned Qiddiya Express high-speed line, which has recently attracted expressions of interest. 

    “That project has been on our radar for some time,” says Vaujour. “It is under the umbrella of the Royal Commission for Riyadh City, which is very well organised and structured. That gives the project strength and credibility.”

    The scheme is being developed as a public-private partnership, a model that Vaujour says fits Saudi Arabia’s stable economic environment. “Public-private partnerships (PPPs) take longer to put together because they are more complex to structure, but in countries like Saudi Arabia – stable and with the capacity to raise debt – why not?” he says. 

    “We are fine with PPPs. We have experience from France, the UK and Spain.”

    While Alstom does not invest directly, it plays a key role in structuring deals. “We are facilitators and advisers,” says Vaujour. 

    “Our job is to accompany the customer, to adjust and iterate with them, and to help find the best solution. PPP is one of the tools in the box – not the simplest one, but one that works.”

    The challenge in the market today is not a lack of opportunity, but deciding where to focus. 

    “Our main problem is not the market; it is how to be selective,” he says. “We have more than enough opportunities to ensure a nice trajectory of growth. The difficulty is to pick our battles and fight for the right ones.”

    The challenge in the market today is not a lack of opportunity, but deciding where to focus

    Shifting focus

    In Africa and Central Asia, Alstom has long-term locomotive and commuter train partnerships that offer years of visibility. In the Gulf, by contrast, the model remains dominated by engineering, procurement and construction-style projects. 

    “It is more big projects, where civil contractors team up with us to deliver metros or airport people movers,” says Vaujour.

    As regional urban transport networks become established, attention is turning to intercity and high-speed rail. “In the Gulf, the Abu Dhabi-Dubai high-speed project is probably the most advanced, while Qiddiya Express and upgrades to the Haramain line in Saudi Arabia could also accelerate momentum.”

    Interest in high-speed connections between Riyadh, Doha and Kuwait is also growing, although such schemes will depend on electrification. “High-speed rail comes with electrification,” Vaujour notes. “And that means significant investment.”

    In addition to new infrastructure, the rail sector is being reshaped by technology. Alstom is investing in clean traction systems, such as hydrogen and battery-powered trains, as well as in autonomous operations.

    “Hydrogen and battery traction are progressing, but they are still in an early stage,” says Vaujour. “Diesel will continue to dominate freight for some time, because there is no clean technology yet that can deliver that level of power. But for passenger services, we are starting to see progress.”

    Driverless trains are another major growth area. “Customers everywhere are interested, partly because it is increasingly hard to find drivers, and also because software drives more efficiently than humans. It is more energy-efficient and reduces wear and tear,” says Vaujour.

    As the Middle East’s networks expand, upgrading existing infrastructure is becoming as important as building new lines. Signalling systems are central to this evolution. “You cannot just create new lines every year – it is too expensive,” says Vaujour. “Signalling allows you to double train frequency. It is what makes networks more efficient.”

    The evolution reflects a wider transformation of the region’s rail sector. “The Middle East has become an established rail hub,” says Vaujour. “It is no longer just about building – it is about operating, maintaining and evolving.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15131845/main.gif
    Colin Foreman
  • Riyadh sets December deadline for Prince Mishaal Road

    20 November 2025

     

    The Royal Commission for Riyadh City (RCRC) has allowed contractors until 3 December to submit bids for a contract to develop Prince Mishaal Bin Abdulaziz Road Axis-Taif Road in Riyadh.

    The previous deadline was 19 November.

    The scope of work covers general road improvement works, including street upgrades, drainage works, relocation of existing utilities, dry and wet utilities, and other associated infrastructure.

    RCRC is investing in improving the road network in and around the kingdom's capital.

    Earlier in November, MEED reported that RCRC had begun post-tender clarifications with bidders for a contract covering upgrade works on Najm Al-Din Al-Ayoubi Road in Riyadh.

    The scope of work covers general road improvement works, including upgrades to three bridges at Al-Zahabi Road, Abdulrahman Adakhel Road and Atia Al-Saady Road.

    In February, RCRC announced plans to develop eight road projects in Riyadh at an estimated cost of more than SR8bn ($2bn).

    The projects form part of the second group in the Riyadh Ring Roads and Main Axes development programme.

    The schemes include:

    • The northern part of the Prince Turki Bin Abdulaziz Al-Awwal Road development project, with a length of more than 6 kilometres (km). The scope includes the development of two main intersections, the construction of three bridges and a tunnel.
    • The middle section of the Al-Thumama Road Axis development project. The scheme will cover about 10km and includes the development of five main intersections and the construction of 11 bridges and five tunnels.
    • The Imam Abdullah Bin Saud Road development project, which will stretch about 9km and includes the development of four main intersections, the construction of three bridges and two tunnels.
    • The Dirab Road development project, which will cover 9km and includes the development of two main intersections and the construction of nine bridges.
    • The Imam Muslim Road development project, which stretches 12km and includes the development of four main intersections and the construction of four bridges. The project will serve as the future extension of the Prince Turki Bin Abdulaziz Al-Awwal Road Axis to the south.
    • The road network development project surrounding King Abdullah Financial Centre, with a length of 20km. This includes the development of three main intersections and the construction of 19 bridges.
    • The construction of a bridge at the intersection of King Salman Road in the east with Abu Bakr Al-Siddiq Road in the north.
    • The first package of engineering modifications for crowded sites in Riyadh, encompassing improvements to alleviate traffic congestion during peak times.

    In August last year, RCRC confirmed it had awarded four contracts worth SR13bn ($3.46bn) as part of the first phase of the programme to develop the city’s road network.

    RCRC said the first phase will develop the axis of the main and ring roads to improve traffic movement in the city.

    Other major projects by RCRC include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park and the Green Riyadh project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15123861/main.jpg
    Yasir Iqbal
  • Riyadh advances with rail link prequalifications

    20 November 2025

     

    Saudi Arabia Railways (SAR) is expected to begin the second stage of the prequalification process for a contract covering the construction of a new railway line, known as the Riyadh Rail Link, which will run from the north to the south of Riyadh.

    MEED understands that the consortiums need to propose self-funded financing arrangements for the project as part of the new round of prequalifications.

    Contractors submitted their initial prequalification documents earlier this month.

    The scope of work includes constructing a 35-kilometre-long double-track railway line connecting SAR’s North-South Railway to the Eastern Railway network.

    The contract also covers the procurement, construction and installation of associated infrastructure such as viaducts, civil works, utility installations, signalling systems and other related works.

    The project is expected to form a key component of the Saudi Landbridge railway.

    The Saudi Landbridge is an estimated $7bn project comprising more than 1,500km of new track. Its core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrades to the existing Riyadh-Dammam line and a link between King Abdullah Port and Yanbu.

    The start of tendering activity for the Riyadh Rail Link project makes the construction of the Saudi Landbridge more likely. 

    The project is one of the kingdom’s most anticipated infrastructure programmes. Plans to develop it were first announced in 2004, but the project was put on hold in 2010 before being revived a year later.

    Key stumbling blocks were rights-of-way issues, route alignment and its high cost.

    In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.

    If it proceeds, the Landbridge will be one of the largest railway projects ever undertaken in the Middle East – and among the biggest globally.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15123411/main.jpg
    Yasir Iqbal
  • Indian contractor bids lowest for $381m Kuwait oil project

    20 November 2025

    Indian contractor Megha Engineering & Infrastructure (Meil) has submitted the lowest bid for an upstream oil project in Kuwait, according to information published by the country’s Central Agency for Public Tenders (Capt).

    The company submitted a bid of KD117m ($381m), outbidding six other companies that participated in the tender.

    The scope of the project is focused on a water separation facility at the Al-Rawdatain facility in Kuwait.

    The water separation facility is being developed at Gathering Centre 25 (GC-25) and a pumping facility is being developed at GC-30.

    The full list of bids submitted is:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    The client on the project is state-owned upstream operator Kuwait Oil Company (KOC).

    The scope of the project includes:

    • Installation of three-phase low-pressure (LP) wet separator package
    • Installation of low-pressure gas knock out drum (KOD)
    • Installation of a high-integrity pressure protection system (HIPPS)
    • Installation of wet crude oil header connection
    • Installation of LP gas pipelines
    • Installation of effluent water (EW) balance tank
    • Installation of effluent water transfer pumps
    • Installation of fuel gas sweetening modular package
    • Installation of chemical injection systems
    • Installation of inline analysers
    • Installation of high-pressure flare
    • Installation of oil recovery system with pumps, flowmeter and analyser
    • Interconnecting piping, instrumentation, electrical and civil works
    • Installation of fire water network
    • Installation of potable water system
    • Installation of control room
    • Installation of substation cabling
    • Related civil, structural, piping, mechanical, electrical and instrumentation works
    • Installation of crude oil lines
    • Installation of tie-ins for process and utilities
    • Installation of effluent water pipeline

    In October, KOC awarded Meil a separate contract for its planned project to develop a gas sweetening and recovery facility in West Kuwait.

    Hyderabad-based Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February this year.

    Kuwait is trying to boost project activity in its upstream sector.

    The country’s national oil company, Kuwait Petroleum Corporation, is aiming to increase oil production capacity to 4 million barrels a day (b/d) by 2035.

    In August, Kuwait announced that it was producing 3.2 million b/d.

    Earlier this month, KOC said it was planning to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15120910/main.png
    Wil Crisp
  • Local contractor bids low for $629m Kuwait oil project

    20 November 2025

    Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid on a contract to develop oil and gas facilities at the Sabriya and Bahra oil fields.

    The scope of the project is focused on developing a water separation facility next to Gathering Centre 23 (GC-23) and GC-24.

    It also includes developing an injection facility at GC-31.

    The full list of bidders for the project is:

    • Mechanical Engineering & Contracting Company (MECC) – KD193m ($629m)
    • Spetco – KD229m
    • Alghanim International – KD239m

    The tender was issued on 15 December 2024, with an initial bid submission deadline of 16 March 2025.

    The bid deadline was extended more than 10 times before prices were submitted.

    The client on the project is state-owned upstream operator Kuwait Oil Company (KOC).

    The scope of the project includes:

    • Installation of a high-integrity pressure protection system
    • Installation of chemical injection systems
    • Installation of effluent water transfer pumps
    • Installation of a low-pressure (LP) gas pipeline from the new LP gas knockout drum (KOD) to existing LP separator gas crude accumulator (inside GC-23 & 24)
    • Installation of interconnecting piping, instrumentation, electrical and civil works
    • Installation of a new oil recovery system with pumps, flowmeter and analyser
    • Installation of the substation and its equipment/systems
    • Installation of tie-ins for process and utilities from/to existing GC-30 to new injection facility
    • Installation of sludge collection, treatment and disposal system
    • Associated facilities

    Kuwait is trying to boost project activity in its upstream sector.

    The country’s national oil company, Kuwait Petroleum Corporation, aims to increase oil production capacity to 4 million barrels a day (b/d) by 2035.

    In August, Kuwait announced that it was producing 3.2 million b/d.

    Earlier this month, KOC said it was planning to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15120909/main.png
    Wil Crisp