Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Saudi Landbridge rail scheme to be delivered by 203421 January 2026
-
Firms submit bids for Dorra gas scheme PMC21 January 2026
-
Libya announces $2.7bn Misurata Port expansion21 January 2026
-
Ras Al-Khaimah awards sewage PPP contract20 January 2026
-
Dubai tenders Al-Maktoum airport metro link20 January 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Landbridge rail scheme to be delivered by 203421 January 2026
Register for MEED’s 14-day trial access
Saudi Arabia Railways (SAR) has said that it will deliver the Saudi Landbridge project through a "new mechanism" by 2034, after failing to reach an agreement with a Chinese consortium for the construction of the project.
In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said that the consortium failed to meet local content requirements, and the project will now be delivered in several phases through a different procurement model.
The project has been under negotiation between Saudi Arabia and China-backed investors keen to develop it on a public-private-partnership basis.
Al-Malik said that the project cost is about SR100bn ($26.6bn).
It comprises more than 1,500 kilometres (km) of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.
Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.
The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.
In April last year, MEED exclusively reported that SAR had issued a tender for the lead design consultancy services contract on the Saudi Landbridge railway network.
MEED understands that the scope covered the concept design and options for the preliminary and issued-for-construction design stages on the network.
MEED reported that the launch of a design tender directly by SAR suggested that Riyadh was looking at other options to develop it alongside the Chinese proposal.
In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.
If it proceeds, the Saudi Landbridge will be one of the largest railway projects ever undertaken in the Middle East and one of the biggest globally. Based on typical design timeframes, tenders for construction are likely to be ready by mid-2026, although the question of how it will be financed will need to be answered before it can proceed to the next step.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15475837/main.gif -
Firms submit bids for Dorra gas scheme PMC21 January 2026

Register for MEED’s 14-day trial access
Engineering firms have submitted bids to Al-Khafji Joint Operations (KJO) for a tender covering project management consultancy (PMC) for the multibillion-dollar Dorra gas field facilities development project.
MEED reported last March that KJO was pushing forwards with a project to produce gas from the Dorra offshore field, located in Gulf waters in the Neutral Zone shared by Saudi Arabia and Kuwait.
KJO has divided the engineering, procurement and construction (EPC) scope of work on the project to produce gas from the Dorra field into four EPC packages – three offshore and one onshore.
The broad scope of services under the tender involves providing PMC for EPC works for the Dorra gas facilities development project.
Firms submitted bids for the PMC tender by the deadline of 19 January, sources told MEED.
KJO issued the tender for PMC services for EPC works on the Dorra gas facilities development project on 29 September. Engineering firms were initially given until 24 November to submit bids for the tender, with that deadline then extended until 15 December and then finally until 19 January, according to sources.
Sources said that the following firms, among others, are understood to be bidding for the PMC tender:
- Fluor (US)
- KBR (US)
- Kent (Saudi Arabia/UAE)
- Tecnicas Reunidas (Spain)
- Wood (UK)
- Worley (Australia)
KJO hosted a job explanation meeting with the bidders for the tender on 15 October, the sources said.
KJO offshore and onshore facilities
KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company (AGOC) and KPC subsidiary Kuwait Gulf Oil Company (KGOC), is moving forward with its Dorra gas field facilities project. KJO has divided the project’s scope of work into four EPC packages – three offshore and one onshore.
Indian contractor Larsen & Toubro Energy Hydrocarbon (L&TEH) has won package 1 of the Dorra facilities project, which covers the EPC of seven offshore jackets and the laying of intra-field pipelines. The contract awarded by KJO to L&TEH is estimated to be valued between $140m and $150m, MEED reported in October.
Contractors are presently preparing to submit bids for the remaining three packages — offshore packages 2A and 2B, and onshore package 3 by 26 January, sources told MEED. KJO has extended the bid submission deadlines for these packages multiple times.
The EPC scope of work for package 2A includes Dorra gas field wellhead topsides, flowlines and umbilicals. Package 2B involves the central gathering platform complex, export pipelines and cables. Package 3 includes the EPC of onshore gas processing facilities.
Saudi Arabia and Kuwait are pressing ahead with their ambitious plan to jointly produce 1 billion cubic feet a day (cf/d) of gas from the Dorra gas field, located in the waters of their shared Neutral Zone. Discovered in 1965, the Dorra gas field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.
Saudi Arabia and Kuwait have been producing oil from the Neutral Zone – primarily from the onshore Wafra field and offshore Khafji field – since at least the 1950s. With a growing need to increase natural gas production, both countries have been working to exploit the Dorra offshore field, understood to be the only gas field in the Neutral Zone.
The Dorra facilities project is one of three major multibillion-dollar projects launched by subsidiaries of Saudi Aramco and Kuwait Petroleum Corporation (KPC) to produce and process gas from the Dorra field that have been advancing over the past few months.
AGOC onshore Khafji gas plant
Meanwhile, AGOC has extended the bid submission deadline for seven EPC packages as part of a project to construct the Khafji gas plant, which will process gas from the Dorra field onshore Saudi Arabia, until 22 April.
MEED previously reported that AGOC had issued main tenders for the seven EPC packages earlier in 2025. Contractors were initially set deadlines of 24 October for technical bid submissions and 9 November for submission of commercial bids, which was then extended by AGOC until 22 December.
The seven EPC packages cover a wide range of works, including open-art and licensed process facilities, pipelines, industrial support infrastructure, site preparation, overhead transmission lines, power supply systems, and main operational and administrative buildings.
France-based Technip Energies has carried out a concept study and front-end engineering and design (feed) work on the entire Dorra gas field development programme.
Progress has been hampered by a geopolitical dispute over ownership of the Dorra gas field. Iran, which refers to the field as Arash, claims it partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development. Kuwait and Saudi Arabia maintain that the field lies entirely within their jointly administered Neutral Zone – also known as the Divided Zone – and that Iran has no legal basis for its claim.
In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.
Since that show of strength and unity, projects targeting production and processing of gas from the Dorra field have gained momentum.
KGOC onshore processing facilities
KGOC has initiated early engagement with contractors for the main EPC tendering process for a planned Dorra onshore gas processing facility, which is to be located in Kuwait.
KGOC is in the feed stage of the project, which is estimated to be valued at up to $3.3bn, and is now expected to issue the main EPC tender in the second quarter of this year, MEED recently reported.
The proposed facility will receive gas via a pipeline from the Dorra offshore field, which is being separately developed by KJO. The complex will have the capacity to process up to 632 million cf/d of gas and 88.9 million barrels a day of condensates from the Dorra field.
The facility will be located near the Al-Zour refinery, owned by another KPC subsidiary, Kuwait Integrated Petroleum Industries Company (Kipic).
A 700,000-square-metre plot has been allocated next to the Al-Zour refinery for the gas processing facility, and discussions regarding survey work are ongoing. The site may require shoring, backfilling and dewatering.
The onshore gas processing plant will also supply surplus gas to KPC’s upstream business, Kuwait Oil Company (KOC), for possible injection into its oil fields.
Additionally, KGOC plans to award licensed technology contracts to US-based Honeywell UOP and Shell subsidiary Shell Catalysts & Technologies for the plant’s acid gas removal unit and sulphur recovery unit, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15472237/main3457.jpg -
Libya announces $2.7bn Misurata Port expansion21 January 2026
Register for MEED’s 14-day trial access
Libya has announced the $2.7bn expansion of Misurata Port, led by Terminal Investment Limited.
The consortium comprises Switzerland's Mediterranean Shipping Company and Qatari firm Maha Capital Partners.
The project is being implemented under a public-private partnership model, and is the first of its kind in the country's non-oil sector
The expansion aims to increase the port's container-handling capacity to 4 million containers a year.
Misurata Free Zone (MFZ) is Libya’s largest free zone, spanning an area of 2,576 hectares.
According to an MFZ statement, the expansion includes:
- Expanding container-handling capacity to accommodate larger vessels and more complex logistics chains;
- Integrating port operations with MFZ’s industrial ecosystem to support small and medium-sized entities, manufacturing and value-added services;
- Deploying modern terminal equipment and digital systems;
- Enhancing safety, performance and environmental standards in line with global benchmarks;
- Creating long-term employment opportunities.
The Libyan Prime Minister’s Office said the expanded port is expected to generate around $600m in annual operating revenues, create about 8,400 direct jobs and support nearly 60,000 indirect jobs.
The investment scope includes:
- Five ship-to-shore (STS) gantry cranes
- 10 mobile harbour cranes
- Eight rubber-tired gantry (RTG) cranes
- 32 reach stackers
- Eight other pieces of equipment, like trucks and forklifts
The project's first phase will raise container-handling capacity to 1.5 million 20-foot equivalent units (TEU), increase throughput by 7% and develop and manage berths to 2,000 metres in total.
It also includes installing six RTG cranes and three STS cranes, developing 56 acres of container yards, building a 2,096-square-metre (sq m) refrigerated container warehouse and constructing an additional 7,500 sq m facility.
An advanced terminal operating system will also be implemented.
The second phase will add a further 2.5 million TEUs of capacity, construct a 2,500-metre breakwater, build a new 1,200-metre berth and a new 60-acre container yard, and deepen the port to 17 metres.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15471059/main.jpg -
Ras Al-Khaimah awards sewage PPP contract20 January 2026
A consortium of Abu Dhabi National Energy Company (Taqa), France’s Saur and the local Etihad Water & Electricity (Etihad WE) has signed a contract to develop and operate a wastewater treatment plant in the UAE’s northern emirate of Ras Al-Khaimah.
The Rakwa wastewater infrastructure project is Ras Al-Khaimah’s first public-private partnership (PPP) for a sewage treatment plant.
It is being developed in partnership with Ras Al-Khaimah’s Public Services Department and Investment & Development Office.
The $120m project entails developing a wastewater treatment plant with a capacity of 60,000 cubic metres a day (cm/d), expandable to 150,000 cm/d.
On 9 January, MEED exclusively reported that the consortium was set to be awarded the contract. The consortium is being led by Ajman-based Emirates Utilities Development Company, a subsidiary of Etihad WE.
US/India-based Synergy Consulting is the financial advisory consultant to Taqa and EtihadWE on this project.
MEED previously reported that two bidding consortiums had submitted bids for the contract. The other bidding consortium comprised the UAE’s Metito Utilities and Omani firm Sogex.
The scope of the build, own, operate and transfer scheme will include extensive sewerage and distribution works in addition to the main treatment plant.
Future PPP project
For its part, Etihad WE is preparing to procure another utility PPP project in Ras Al-Khaimah.
The project involves expanding the capacity of an existing seawater reverse osmosis plant in Ghalilah, which became operational in 2015.
The state-owned utility recently appointed Austria’s ILF Consulting Engineers to provide technical advisory services for the project, which is expected to be tendered this year.
If successfully procured, it will be the first independent water project in Ras Al-Khaimah.
READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds
Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:
> AGENDA: Saudi real estate to surge in 2026> BATTERIES: Batteries shape the region's energy future> INTERVIEW: Tabreed finishes the year on a high> CONTRACTORS: Managing risk in the GCC construction market> ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch> AIRSHOW: Top deals signed at Dubai Airshow 2025> MARKET FOCUS: Oman steadies growth with strategic restraintTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15465691/main.jpg -
Dubai tenders Al-Maktoum airport metro link20 January 2026

Register for MEED’s 14-day trial access
Dubai's Roads & Transport Authority (RTA) has invited consultants to bid for the design contract for the Route 2020 extension.
The extended line will start from the Expo 2020 metro station and connect with Al-Maktoum International airport's West Terminal.
The extension to the line will run for about 3 kilometres (km) and will feature two stations.
MEED understands that the invitation to bid was issued earlier in January with a submission deadline of mid-March.
The existing Route 2020 metro link is a 15km-long line branching off the existing Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks, 3.2km of tunnels, and has five elevated stations and two underground stations.
In 2016, the RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain's Acciona, Turkiye's Gulermak and France's Alstom.
Dubai's plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to Al-Maktoum International airport. There are long-term plans for further extensions.
Other metro projects
In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.
The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.
The other metro lines in the pipeline are the Purple Line and the Pink Line, both of which are in the early stages of development.
Firms are also bidding to update the emirate’s rail masterplan. Also in October 2025, MEED reported that 10 firms had submitted offers to undertake the project.
The rail masterplan study will update and modify the RTA’s rail network, which includes the Dubai Metro and Dubai Tram. These plans will support Dubai’s 2040 urban masterplan, which aims for all residents to be within a 30-minute metro or light-rail trip to their place of work.
The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.
There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services as well as a high-speed rail connection.
In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.
The Blue Line consists of 14 stations, including three interchange stations at Al-Jaddaf, Al-Rashidiya and International City 1, as well as a station in Dubai Creek Harbour. By 2040, daily ridership on the Blue Line is projected to reach 320,000 passengers. It will be the first Dubai Metro line to cross Dubai Creek and will do so on a 1,300-metre viaduct.
READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds
Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:
> AGENDA: Saudi real estate to surge in 2026> BATTERIES: Batteries shape the region's energy future> INTERVIEW: Tabreed finishes the year on a high> CONTRACTORS: Managing risk in the GCC construction market> ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch> AIRSHOW: Top deals signed at Dubai Airshow 2025> MARKET FOCUS: Oman steadies growth with strategic restraintTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15465636/main.jpg