Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Adnoc builds long-term oil and gas production potential

    7 April 2026

     

    Between 2023 and 2024, Abu Dhabi National Oil Company (Adnoc Group) spent an estimated $37bn on projects critical to achieving its upstream targets: increasing oil production capacity to 5 million barrels a day (b/d) by 2027 and attaining gas self-sufficiency by the end of the decade.

    The state energy company spent more than $22.5bn in 2023 alone, marking the highest annual oil and gas project spending on record in the UAE. The Hail and Ghasha sour gas development – accounting for approximately $17bn – remains the single-largest contract award in the country’s hydrocarbons sector.

    A slowdown in capital expenditure (capex) following two years of elevated spending is therefore in line with expectations. While engineering, procurement and construction (EPC) contract awards for upstream projects declined in 2025 and into this year, Adnoc has still committed close to $10bn over the past 15 months.

    The largest award during this period came from Adnoc Offshore, which let contracts worth $7.5bn for three EPC packages under the Lower Zakum Long-Term Development Plan (LTDP-1). Spain’s Tecnicas Reunidas and Abu Dhabi-based NMDC Energy and Target Engineering Construction Company were selected last February to execute the works.

    The Lower Zakum field, located 65 kilometres northwest of Abu Dhabi, is majority-owned by Adnoc Offshore (60%). Other stakeholders include an Indian consortium led by ONGC Videsh (10%), Japan’s Inpex (10%), China National Petroleum Corporation (10%), Italy’s Eni (5%) and France’s TotalEnergies (5%).

    Adnoc Offshore aims to increase production capacity at Lower Zakum to 520,000 b/d by 2027 and sustain that level through 2034.

    Offshore contracts in 2026

    So far this year, Adnoc Offshore has awarded contracts for two key projects: the Satah Al-Razboot (Sarb) deep gas development and the expansion of the Nasr oil field.

    Adnoc achieved final investment decision (FID) on the Sarb project in January and awarded the main EPC contract to US-based McDermott International. The contract is estimated to be worth around $500m, sources told MEED.

    The project is expected to deliver 200 million cubic feet a day (cf/d) of gas by the end of the decade – enough to power more than 300,000 homes.

    The scope includes the EPC of an offshore wellhead tower with four gas production wells, which will be connected to Das Island for processing through Adnoc Gas facilities. Works also include the installation of pipelines and intra-field connections linking the Sarb field to Das Island.

    Also in January, Adnoc Offshore awarded McDermott a $942m contract for the Nasr-115 project, which will increase production capacity at the Nasr offshore field to 115,000 b/d. The field is located about 130km northwest of Abu Dhabi.

    McDermott’s scope covers full EPCI services for two topside structures, a new manifold tower, a jacket, a bridge, associated pipelines, subsea cables and brownfield modifications.

    Strategic projects in queue

    Over the next 12-18 months, Adnoc’s upstream spending is expected to shift from meeting near-term production targets –now largely within reach – to building longer-term capacity beyond 2030.

    Following $1.3bn in EPC awards in 2024 for the Upper Zakum expansion to 1.2 million b/d, Adnoc Offshore is advancing the next phase, which will increase capacity to 1.5 million b/d.

    Located 84km offshore, Upper Zakum is the world’s second-largest offshore oil field. Adnoc Offshore has divided the EPC scope into three packages, with contractors submitting commercial bids for the UZ1.5MMBD project in February.

    Adnoc Offshore is also progressing the Umm Shaif gas cap and surface pressure boosting project, aimed at increasing gas production by 550 million cubic feet a day (cf/d) and condensate output by 50,000 b/d. About 520 million cf/d of additional gas is expected to be fed into Adnoc’s sales gas network.

    The first phase of the project has been split into three EPC packages:

    • Offshore package 1: fabrication of a 30,000-tonne gas compression system
    • Offshore package 2: fabrication of a 30,000-tonne gas compression system
    • Onshore package: EPC of gas inlet and processing systems at Das Island

    Adnoc Offshore is currently evaluating commercial bids submitted in February for these packages.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285814/main.gif
    Indrajit Sen
  • Contractor wins Oman housing substation contract

    7 April 2026

    Oman’s Public Authority for Social Insurance has awarded a contract for the supply, installation, execution and maintenance of a main power substation for its affordable housing project.

    The contract was awarded to Kuwait-based Al-Ahleia Switchgear Company.

    The project comprises a 400/132/11kV main substation for the Affordable Housing Project, known locally as Al-Masaken Al-Muyassara.

    The tender was announced last November, with the bid envelopes opened on 16 December 2025.

    Al-Ahleia Switchgear submitted another bid in March for a contract to build three 132/11kV main transformer stations for Kuwait’s Public Authority for Housing Welfare (PAHW).

    As reported by MEED, the company’s price of KD10.5m ($34.1m) was the lowest of two offers for the engineering, procurement and construction (EPC) contract.

    Separately, in December, Al-Ahleia Switchgear submitted the lowest bid of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s PAHW.

    The bid was marginally lower than the two other offers submitted by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285335/main5555.jpg
    Mark Dowdall
  • UAE reviews $1.63bn fourth federal road project

    7 April 2026

    UAE authorities on 6 April unveiled details of the AED6bn ($1.63bn) fourth federal corridor scheme, a major highway programme aimed at boosting inter-emirate connectivity, increasing road capacity and easing congestion.

    The project comprises a 68-kilometre corridor with 10 major interchanges, four flyovers and six to eight lanes in each direction.

    Officials provided technical updates on the corridor, including revised connection points and coordination with local authorities to finalise route alignments in line with broader development plans.

    Suhail Mohamed Al-Mazrouei, minister of energy and infrastructure, said the programme underscores the central role of infrastructure in the UAE’s development agenda and competitiveness. He was speaking while chairing the first meeting of the UAE Infrastructure and Housing Council this year.

    The council also reviewed progress on federal infrastructure initiatives aimed at improving transport efficiency and strengthening coordination between federal and local authorities.

    Al-Mazrouei said the next phase will focus on accelerating the delivery of high-impact projects to enhance transport system performance and support the shift towards smart and sustainable mobility in line with population growth and urban expansion.

    The council also assessed progress on linking Ajman to the third and fourth federal corridors, which is expected to provide alternative routes, improve traffic flow and further enhance mobility between the emirates.

    On public transport, the council reviewed a study on transport links between Dubai, Sharjah and Ajman to address rising commuting demand.

    The proposed plan includes 10 priority routes incorporating bus rapid transit and dedicated lanes, with connections to key hubs such as the Dubai Metro and city centres.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285296/main.jpg
    Yasir Iqbal
  • Kingdom Holding Company signs Riyadh project deal

    7 April 2026

    Saudi Arabia’s Kingdom Holding Company has signed an agreement with Sumou Real Estate Company under which Sumou will manage the development, marketing and sale of a 3-million-square-metre land plot in Riyadh.

    The scheme is expected to generate about SR4bn ($1bn) in total sales.

    In a Tadawul disclosure, Kingdom Holding Company said its subsidiaries, Kingdom Real Estate Development Company and Trade Centre Company, have appointed Sumou as the exclusive development manager for the site.

    The project is scheduled to be implemented over 36 months, starting once the masterplans are approved by the relevant authorities.

    In a separate stock exchange statement, Sumou said it will be paid 6.5% of total infrastructure development costs and 2.5% of project sales, in addition to the brokerage commission paid by buyers.

    Kingdom Holding Company said the agreement aligns with its long-term strategy for its Riyadh landbank, which originally totalled around 20 million sq m and is being developed in phases.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16284668/main.jpg
    Yasir Iqbal
  • Saudi Arabia’s Jubail industrial city hit by missile debris

    7 April 2026

    Explosions were reported in Saudi Arabia’s Jubail industrial city on 7 April. Saudi authorities said the country’s air defence systems intercepted seven ballistic missiles targeting the Eastern Province, with debris landing near energy facilities, primarily in Jubail.

    Jubail is one of the world’s largest petrochemical production hubs, with an annual output of about 60 million tonnes, accounting for an estimated 6% to 8% of global supply.

    The incident places renewed focus on the kingdom’s flagship petrochemical cluster, where majority state-owned Saudi Basic Industries Corporation (Sabic) is a key investor.

    Jubail also hosts major downstream oil, gas and petrochemical assets operated by Saudi Aramco, US-based Dow and France’s TotalEnergies, underscoring the industrial zone’s international significance.

    Saudi officials said damage assessments are ongoing.

    The developments follow an Israeli strike on 6 April targeting a major petrochemical complex in Iran’s southern Asaluyeh region, described as the country’s largest industrial hub.

    Separately, authorities closed the King Fahd Causeway – the main bridge linking Saudi Arabia and Bahrain – early on 7 April as a precaution amid heightened security concerns.

    The King Fahd Causeway Authority said in a post on X that vehicle movement had been “suspended as a precautionary measure” due to Iranian attacks targeting Saudi Arabia’s Eastern Province.

    The 25-kilometre bridge is Bahrain’s only road link to the Arabian Peninsula.

    US President Donald Trump has issued an ultimatum for Iran to reopen the Strait of Hormuz and threatened to bomb Iranian power plants and bridges if Tehran does not comply by 8pm EDT on 7 April.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16283711/main2424.jpg
    Indrajit Sen