Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Bidders get more time for Jebel Ali sewage EPC contract29 April 2026
-
Kuwait Oil Company prepares to sign flowline contract29 April 2026
-
-
UAE to withdraw from Opec and Opec+ alliance28 April 2026
-
NWC tenders package 14 of sewage treatment programme28 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Bidders get more time for Jebel Ali sewage EPC contract29 April 2026
Dubai Municipality has extended the deadline for contractors to submit bids for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.
Contractors now have until June to submit offers, a source told MEED. Bidding had been expected to close on 30 April.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d), with the expansion estimated to cost $300m.
The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
The main element of the expansion involves modifications to the secondary treatment process at Jebel Ali STP phase two.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
Future expansion
It is understood that the project is part of long-term plans to treat about 1.05 million cm/d once all future phases are completed.
According to sources, this includes a Jebel Ali-based build-operate-transfer (BOT) project to be developed under a public-private partnership (PPP) model.
It is understood that the prequalification process for this will begin in the coming months.
In February, MEED exclusively revealed that the municipality is preparing to tender the main construction package for the Warsan STP by the end of the year.
As MEED understands, the Warsan STP had previously been planned as a PPP project.
The main package will now be procured as an engineering, procurement and construction contract, a source said.
The project involves the construction of a sewage treatment plant with a capacity of about 175,000 cm/d, including treatment units, sludge handling systems and associated infrastructure.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16608027/main.jpg -
Kuwait Oil Company prepares to sign flowline contract29 April 2026

State-owned upstream operator Kuwait Oil Company (KOC) is preparing to sign a contract worth KD174.2m ($565m) with Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco), according to industry sources.
The contract is focused on developing flowlines and associated works in North Kuwait.
One source said: “The contract is expected to be signed soon and everything associated with the contract award process is moving very smoothly.”
Heisco announced in a stock exchange statement earlier this month that it had received a formal contract award letter for the project.
While progress on the project is moving smoothly for now, the project may be impacted by fallout from the US and Israel’s war with Iran in the future.
The project requires a large volume of pipelines to be transported into Kuwait, which would normally be shipped through the Strait of Hormuz.
Heisco was the fourth-lowest bidder for the contract.
Also this month, Heisco submitted the lowest bid for a project to upgrade part of the Mina Abdullah refinery’s export infrastructure.
It submitted a bid of KD11,919,652 ($38.6m) for the project to implement renovation works on the artificial island that forms part of the port at the refinery.
The only other bidder was Kuwait’s International Marine Construction Company (IMCC), which submitted a bid of KD12,480,113 ($40.4m).
https://image.digitalinsightresearch.in/uploads/NewsArticle/16599814/main.png -
Algerian-Indian team makes oil and gas discovery in Libya29 April 2026
A consortium of state-owned companies from India and Algeria has made an oil and gas discovery in Libya’s Ghadames basin.
The consortium comprises Algeria’s Sonatrach International Petroleum Exploration & Production (Sipex), Oil India and Indian Oil Corporation.
The discovery was made in the Area 95/96 block, which is located near Libya’s border with Algeria.
In a statement, India’s Ministry of Petroleum & Natural Gas said that the well was completed to a final depth of 8,440 feet and achieved production of 13 million cubic feet of gas a day and 327 barrels of condensate a day during testing.
The hydrocarbons were extracted from the Awynat Wanin and Awyn Kaza formations.
The ministry added: “The discovery reflects the growing global footprints of Indian energy companies, importance of strategic international alliances, and our commitment to strengthening national energy security through overseas assets acquisition by national oil companies.”
The consortium won the exploration and production rights for the block, which covers an area of nearly 7,000 square kilometres, during Libya’s fourth oil and gas licensing round in December 2007.
Stakeholders are expecting a surge in oil and gas project activity in Libya after the country’s rival legislative bodies recently approved a unified state budget for the first time in more than 13 years.
The Central Bank of Libya confirmed on 11 April that both chambers had endorsed the budget, saying that it was a key step towards restoring financial stability after prolonged division.
The budget is valued at LD190bn ($29.95bn), and LD12bn ($1.9bn) has been allocated to the NOC.
An additional LD40bn ($6.3bn) has been allocated for “development projects”.
Libya has stated that a joint committee has been formed to help prioritise development projects, and the projects have been listed in the budget.
The development comes at a time when Libya’s oil and gas sector could be positioned to make windfall revenues as oil and gas prices remain high due to fallout from the US and Israel’s war with Iran.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16599813/main.png -
UAE to withdraw from Opec and Opec+ alliance28 April 2026
The UAE has announced its decision to withdraw from Opec and the Opec+ alliance from 1 May.
In a statement, the UAE Ministry of Energy said the move followed a “comprehensive review” of its production policy.
“While near-term volatility, including disruptions in the Arabian Gulf and the Strait of Hormuz, continues to affect supply dynamics, underlying trends point to sustained growth in global energy demand over the medium to long term,” the statement, issued on 28 April, said.
“This decision follows decades of constructive cooperation. The UAE joined Opec in 1967 through the Emirate of Abu Dhabi and continued its membership following the formation of the United Arab Emirates in 1971. Throughout this period, the UAE has played an active role in supporting global oil market stability and strengthening dialogue among producing nations.”
The announcement was timed to coincide with an Opec ministerial meeting in Vienna and was communicated through state news agency Wam.
Abu Dhabi National Oil Company (Adnoc) has set a target of raising production capacity to 5 million barrels a day (b/d) by 2027 – up from a current capacity of around 4.85 million b/d, though the country has been constrained to producing approximately 3.4 million b/d under Opec+ quota agreements.
Membership of a quota-constrained group sits uneasily with that ambition. The non-oil economy now accounts for roughly 75% of the UAE’s GDP, reducing the political cost of rupture with the organisation.
The Iran war wiped out 7.88 million b/d of Opec production in March, cutting group output 27% to 20.79 million b/d – the steepest supply collapse in the organisation’s recorded history, exceeding the Covid-19 demand shock of May 2020 and the disruptions of both the 1970s oil crisis and the 1991 Gulf War. Gulf producers have been struggling to route exports through the Strait of Hormuz amid Iranian threats and attacks on vessels, further straining the group’s cohesion.
Against that backdrop, the UAE’s departure deals a significant blow to Opec and its de facto leader, Saudi Arabia, which has sought to project unity despite persistent internal disagreements over quotas and geopolitics.
The US-Israeli war on Iran since late February has had a detrimental effect on a number of Gulf states, including the UAE.
The UAE was targeted by thousands of Iranian ballistic missiles and drones, damaging strategic oil and gas facilities, denting Dubai’s appeal as a luxury tourism hotspot and slowing oil exports to a trickle.
Whereas some Gulf states have urged dialogue with Iran, the UAE has maintained a more hawkish position. Analysts say that position is partially due to its reliance on the Strait of Hormuz for oil exports and the UAE’s unwillingness to see Iran cement itself as a regional power in the Gulf.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16596229/main.gif -
NWC tenders package 14 of sewage treatment programme28 April 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s National Water Company (NWC) has tendered a contract for the construction of 10 sewage treatment plants as part of the next phase of its long-term operations and maintenance (LTOM) sewage treatment programme.
According to the original scope, the Eastern A Cluster (LTOM14) package will have a total treatment capacity of 184,440 cubic metres a day (cm/d) at an estimated cost of $180m.
The bid submission deadline is 30 September.
The tender follows recent contract awards for North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11) and the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).
MEED exclusively reported that a consortium comprising China’s Jiangsu United Water Technology, the UAE’s Prosus Energy and Saudi Arabia’s Armada Holding had been appointed as a contractor for each of these projects.
Package 11 will have a combined capacity of about 440,000 cm/d at an estimated cost of about SR211m ($56.3m).
Package 12 will have a combined treatment capacity of 337,800 cm/d at an estimated cost of about SR203m ($54.1m).
In April, NWC also opened finanical bids for North Western B Cluster (LTOM12) of its sewage treatment programme.
The contract covers the construction and upgrade of seven sewage treatment plants with a combined capacity of about 162,000 cm/d.
MEED previously reported that the following companies had submitted proposals:
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- Civil Works Company (Saudi Arabia)
- Miahona (Saudi Arabia)
- Beijing Enterprises Water Group – BEWG (Hong Kong)
- Al-Yamama (Saudi Arabia)
These bids are currently under evaluaton, with an award expected in the coming weeks, a source said.
The tender for the North Western C Cluster (LTOM13) project had been put on hold, although it is understood that this is now likely to be the next package to be tendered.
Under the original scope, this package covers the construction of 10 sewage treatment plants.
In total, the LTOM programme comprises 19 packages split into two phases. This contract for LTOM10 was the first to be awarded under the second phase of NWC’s rehabilitation of sewage treatment plants programme.
As MEED understands, there have been several discussions in recent months regarding changes in scope details and potential expansions. This involves potentially grouping some upcoming projects.
NWC previously awarded $2.5bn-worth of contracts in the first phase. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years. Phase two of the programme includes 10 packages covering 117 treatment plants.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16591851/main.jpg