Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Seven seeks contractors for Dammam water park and hotel

    21 July 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg
    Yasir Iqbal
  • Al-Ula appoints equestrian village early works contractor

    21 July 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.

    The contract was awarded to Al-Khobar-based Al-Shalawi International Company.

    Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.

    Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.

    RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.

    The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.

    These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg
    Yasir Iqbal
  • Contractors await decision on Riyadh airport sewage plant

    21 July 2026

     

    Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.

    It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg
    Mark Dowdall
  • Dubai Municipality awards Tasreef drainage contract

    21 July 2026

     

    Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.

    It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.

    The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.

    The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.

    In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.

    The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
    Mark Dowdall
  • Qatari Diar unveils $30bn Egypt project masterplan

    21 July 2026

    Qatari Diar, the real estate arm of the Qatar Investment Authority, has announced the masterplan for its $30bn Alam Al-Roum project on Egypt’s north coast.

    The masterplan was developed by US-based architectural firm Skidmore, Owings & Merrill.

    The master-planning team also includes US-based landscape architecture firm SWA; UK-headquartered marina design and operations consultant Marina Projects; and French transport and traffic engineering consultant Setec.

    The development will cover more than 20 million square metres and include 7.2 kilometres of private beachfront on the Mediterranean Sea.

    The site is about 20 minutes from Marsa Matrouh and 50 minutes from Ras El-Hekma.

    According to a statement, the project includes $3.5bn in direct cash investment and is designed as an integrated, year-round Mediterranean destination.

    Alam Al-Roum expands Qatari Diar Egypt’s portfolio, which includes CityGate, New Giza and The St Regis Cairo.

    Qatari Diar and Egypt’s New Urban Communities Authority signed the project agreement for Alam Al-Roum in November 2025.

    The estimated value of the deal to Egypt is $7.5bn. Under the agreement, Cairo will receive an upfront payment of $3.5bn by late December 2025 for the initial land purchase and is expected to receive an in-kind stake in the project, estimated to be worth $1.8bn.

    Qatari Diar’s broader investment plans for the area include spending up to $26.2bn in addition to the $3.5bn already allocated for the land purchase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707658/main.jpg
    Yasir Iqbal