Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • GCC projects market holds its nerve

    1 November 2026

     

    The war in the Gulf is now inflicting deep damage on the region’s economies. In its October World Economic Outlook, the IMF forecasts contraction in every GCC state except Oman in 2026. Saudi Arabia’s real GDP is projected to shrink by 3.3%, after 4.6% growth in 2025, and the UAE’s by 3.9%, after 6.2% growth.

    The IMF expects Kuwait’s economy to contract by 16.7%, Qatar’s by 15.6% and Bahrain’s by 11.3%, as energy and transport disruption cuts exports. Oman, with routes outside the Strait of Hormuz, is forecast to grow by 4.1%.

    The fund has cut its 2026 forecast for the Middle East and Central Asia by 2.2 percentage points since April, to a contraction of 0.3%, citing a longer closure of the strait than it had previously assumed. The revision for Saudi Arabia is 6.4 percentage points. The IMF now assumes the strait will reopen in March 2027, with a return to prewar conditions broadly by October 2027.

    There is little sign of an early end to hostilities. On 10 October, a Houthi-attributed strike on a passenger terminal at Riyadh’s King Khalid International Airport killed 12 people and injured 309, according to Saudi Arabia’s General Authority of Civil Aviation. Airport operations were suspended and several international airlines cancelled flights.

    Yet the region’s projects market is holding up far better than its economies. Data from MEED Projects shows that contract awards in 2026 have proved resilient, with clients across the GCC continuing to commit capital to new schemes.

    The GCC projects market has absorbed almost eight months of conflict better than its economies

    Resilient awards

    The UAE leads the regional market for a second consecutive year, with the value of contract awards 6.1% higher than in the same period of 2025. Oman and Kuwait are also running ahead of last year’s pace, despite the IMF’s forecast that Kuwait’s economy will contract by about a sixth.

    Saudi Arabia has awarded $68.8bn of contracts so far this year, 13% less than in the same period of 2025. Given that the kingdom has been the main target of the Houthi campaign, and was already revising its spending priorities before the conflict, the decline is modest.

    The comparison is against a high base. The past three years have seen unprecedented GCC capital expenditure, supported by higher oil prices, residential demand and national vision programmes. More than three quarters has been concentrated in Saudi Arabia and the UAE.

    The gap between economic output and project spending reflects the nature of the projects market. Governments and state-linked entities can sustain capital budgets through a downturn using reserves and borrowing. GDP contraction, by contrast, reflects lost oil and gas exports, tourism and trade.

    The UAE’s performance this year has been driven by the gas and transport sectors, which have recorded the strongest growth. Construction, the country’s largest sector, has declined as the real estate market has cooled.

    Abu Dhabi has been the standout performer. Contract awards in the capital are up 35% on the same period of last year, with growth across the construction, gas, oil and transport sectors.

    Public spending is a central reason for that resilience. Fitch Ratings expects Abu Dhabi’s spending to rise by 19% this year, equivalent to 3.7% of GDP, to support the non-oil economy. Data from the Central Bank of the UAE shows consolidated government capital expenditure rose to AED18.6bn ($5.1bn) in Q1 2026 from
    AED2bn in Q1 2025.

    Fitch expects UAE infrastructure and government-related entity capital spending to rise significantly in 2026 and 2027, both to strengthen resilience against future conflicts and stimulate the economy. Emirates have already accelerated tendering on several projects.

    Transport remains a priority. Plans include further sections of the national passenger rail network, a high-speed rail link between Dubai and Abu Dhabi, a light rail system in Abu Dhabi and the Dubai Metro Gold Line. The $35bn expansion of Al-Maktoum International airport in Dubai is moving towards delivery with the award of the first major construction packages.

    Economic headwinds

    Both the IMF and Fitch expect a strong rebound once the strait reopens. The IMF forecasts 2027 growth of 7.7% in the UAE, 7.9% in Saudi Arabia, 18.8% in Qatar and 17.1% in Kuwait. Fitch forecasts UAE non-oil growth of 6.1% next year. Paul Gamble, senior director at Fitch, cautioned that prolonged insecurity “will call into question logistical advantages” that underpin the UAE’s growth model.

    Beneath the headline award totals, there are warning signs. Regional contract awards performed well between March and June, but the value of work awarded in recent months has dropped sharply compared with the same months of 2025. According to MEED Projects, the main cause is a fall in the number of tenders being issued, particularly in real estate.

    The timing is significant. The strong period included the April ceasefire, when clients appear to have pressed ahead expecting a short conflict. Tendering slowed as hostilities resumed. In July, Iranian attacks reached Bahrain, Kuwait, Qatar, Jordan and Oman, while Houthi escalation against Saudi Arabia began.

    The pattern suggests conflict fatigue may be setting in, with clients deferring projects amid a war with no clear end date. As tendering is a leading indicator, the impact on awards is likely to become more visible in coming months.

    In Saudi Arabia, monthly performance has been mixed as the market adjusts to revised spending priorities and the regional conflict. Most sectors are up on last year, with the exception of power and water, which has struggled in 2026, possibly as a result of overbuilding in the past three years. The kingdom’s gigaprojects have continued their retreat. Awards peaked at $31.7bn in 2023 and fell to $14.4bn in 2025. The total so far in 2026 is $9.4bn, most of it for work at Qiddiya, Diriyah and Rua Al-Madinah.

    The GCC has more than $3.4tn of known, planned and unawarded projects over the next 10 to 15 years

    Dubai slowdown

    The clearest signal of the conflict’s impact on the projects market comes from Dubai. The emirate’s market performed strongly until May. Since then, activity has been subdued, and contract awards for the year to date are 0.6% lower than in the same period of 2025.

    The main cause is a decline in residential contract awards. Data from Bayut and the Dubai Land Department shows a marked fall in the value of off-plan sales since late February, when the war began. Residential construction awards have fallen in step, with no sign of the time lag that would normally be expected.

    Third-quarter figures from Savills confirm the trend. Residential transactions fell 38% year on year to 34,500, and transaction value dropped 46% to AED70.8bn ($19.3bn) from AED132.2bn. The decline was concentrated in the off-plan segment, where value fell to AED45.7bn in Q3 from AED61.3bn in Q2, while ready-market value rose to AED25.1bn from AED21.3bn.

    Developers have sharply reduced new launches. Savills recorded about 5,000 units launched in Q3, taking the total for the year to date to about 50,000, roughly 64% below the same period of 2025. Fewer launches mean fewer construction contracts, which explains why residential awards have fallen so quickly. More than 525,000 units are scheduled for delivery between 2027 and 2030, which Fitch says could add pressure to a sector accounting for 8% of non-oil GDP if population growth weakens.

    Escaping Hormuz

    The conflict is also generating new project demand. Saudi Arabia is prioritising ports and transport infrastructure on the Red Sea coast, along with new pipelines to the Red Sea and to Oman. The UAE is developing ports and transport links to the east coast and Oman, and additional pipelines to Fujairah. Fitch anticipates new and expanded road, rail, pipeline and port infrastructure in Oman and Saudi Arabia as GCC states seek routes that bypass the strait.

    The IMF’s forecasts underline the value of those routes. It describes Saudi Arabia as “somewhat less affected” than its neighbours because of its more diversified export routes, while Oman is the only GCC state forecast to grow this year. Houthi strikes on Aramco facilities in Yanbu in September show that Red Sea infrastructure is not beyond reach, however. Defence spending is rising in both Saudi Arabia and the UAE, and repair and rehabilitation work will add to the pipeline once hostilities end.

    The long-term fundamentals remain strong: the GCC has more than $3.4tn of known, planned and unawarded projects over the next 10 to 15 years, about half of it in Saudi Arabia. Many of the kingdom’s priorities are tied to fixed dates, with Riyadh hosting the World Expo in 2030 and Saudi Arabia hosting the Fifa World Cup in 2034.

    The capacity to fund this pipeline depends on oil revenues. MEED’s assessment is that crude prices must remain above $70-$80 a barrel for spending levels to be maintained. With exports through Hormuz disrupted, the volume of oil Gulf producers can move to market matters as much as the price.

    The GCC projects market has absorbed almost eight months of conflict better than its economies. The question for the final quarter is whether the slowdown in tendering is a temporary pause or the start of a sustained retreat. If the IMF’s assumption of a March 2027 reopening of the strait holds, clients will be setting their 2027 budgets with a rebound in sight. If it slips, the resilience of contract awards will face a sterner test. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21078685/main.gif
    Colin Foreman
  • Ashghal tenders Mekeines-Umm Bab link road

    30 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has tendered a contract for the design and construction of the Mekeines to Umm Bab Link Road and associated infrastructure.

    The tender was issued on 29 October, with a bid submission deadline of 22 December.

    The scope comprises:

    • Highway works, including main carriageways, access roads, grade-separated ramps, junctions and tie-ins to existing networks
    • Dedicated non-motorised user facilities, footpaths and shared-use cycle paths
    • Structural installations, including camel underpasses, a QatarEnergy culvert and gateway monumentation
    • Extensive dry and wet utilities, encompassing Kahramaa potable water and electrical transmission networks, surface water drainage, street lighting and dedicated communication networks for Ooredoo, the Qatar National Broadband Network and the Qatar Armed Forces

    Under the scope of work, the appointed contractor will execute full design verification and turnkey construction under Ashghal’s standard Building and Engineering Design and Build General Conditions of Contract (2018 Edition) on a lump-sum basis. Engineering subconsultants must hold Grade 1 or International classification with the Ministry of Municipality across civil, architectural, mechanical and electrical engineering disciplines.

    The contract stipulates an execution period of 1,260 calendar days (3.5 years) from the commencement date, followed by a 400-day maintenance liability period. 

      The project is open to local and international contractors classified as Grade A in roads specialisation by Qatar’s Ministry of Finance (MoF).

      Foreign firms may participate independently or within a joint venture, provided the joint venture leader holds the requisite classification, by registering through the MoF e-procurement portal with attested equivalent certification from their home countries.

      The planned corridor is located within Al-Rayyan Municipality across Zones 82 to 84 in the Al-Sheehaniya area.

      At its eastern end, the link road begins about 40 kilometres southwest of central Doha, tying into the Salwa Road Interchange 42. At the western terminus, it connects to the roundabout adjacent to Umm Bab on the Abu Samra to Dukhan road (Route 39). 

      The link road serves as a critical logistics corridor connecting western settlements, residential districts and industrial installations, including concession areas operated by QatarEnergy.

      The western 7.5km of the alignment passes directly through the QatarEnergy District, where the corridor runs parallel to active oil and gas pipelines and includes a designated gateway monument.

      https://image.digitalinsightresearch.in/uploads/NewsArticle/21041383/main.gif
      Yasir Iqbal
    • Contractors prepare bids for Petro Rabigh bottom-of-the-barrel project

      30 October 2026

       

      Contractors are preparing proposals for Saudi Arabia’s Rabigh Refining & Petrochemical Company (Petro Rabigh) for a major project to increase output and improve the efficiency of its integrated refining and petrochemicals complex in Rabigh, on the kingdom’s Red Sea coast.

      Petro Rabigh’s downstream complex, which is majority-owned by Saudi Aramco, includes a topping refinery with a 340,000-barrel-a-day (b/d) crude-distillation unit, a 47,000 b/d hydrotreater, a 12 million-cubic-feet-a-day hydrogen plant, a 75,000 b/d naphtha Merox unit and a 60,000 b/d kerosene Merox unit. The complex also includes supporting utilities, product tankage and a marine terminal.

      The main objective of the bottom-of-the-barrel project is to convert low-value, high-sulphur fuel oil and heavy-residue streams – which account for about 20% to 22% of refinery output – into higher-value, cleaner products, including diesel and lighter distillates.

      Petro Rabigh aims to achieve residue-conversion capacity of about 64,000 to 75,000 b/d by adding integrated fuel-oil upgrading and diesel-treatment units.

      The company issued the main tender for engineering, procurement and construction (EPC) works earlier this year. Contractors have until 19 November to submit proposals, sources told MEED.

      The following companies are understood to be among those bidding for the project:

      • CTCI Corporation (Taiwan)
      • JGC Corporation (Japan)
      • Larsen & Toubro (India) / Technip Energies (France)
      • Tecnicas Reunidas (Spain)

      The overall scope of work on the project covers the construction of the following units:

      • A light-naphtha isomerisation unit
      • A deasphalting and dewaxing unit
      • An ebullated-bed processing unit
      • A sulphur block, comprising sulphur-recovery, acid-gas-removal, sour-water-stripping and sulphur-forming units
      • Sales-gas allocation facilities and associated pipeline works
      • Utilities outside battery limits
      • Auxiliary piping modifications
      • Utility and hydrocarbon tie-ins

      Petro Rabigh appointed Australia-headquartered Worley last year to carry out front-end engineering and design (feed) work for the bottom-of-the-barrel project.

      MEED also reported that Petro Rabigh appointed Worley to provide engineering and project-management consultancy (PMC) services for the project in the first quarter of this year.

      Under the contract, Worley will carry out engineering studies and PMC functions. It will also support the development of cost estimates, project-specific execution procedures and technical procedures in line with Saudi Aramco guidelines. The work covers both the design-basis scoping-paper stage and the subsequent feed stage.

      Petro Rabigh will draw on Worley’s expertise in design, procurement and processing technologies, including light-naphtha isomerisation; vacuum-residue processing through deasphalting and dewaxing; an ebullated-bed configuration integrated with the diesel-hydrotreating section; and unconverted-oil hydrotreatment.

      Worley recently confirmed its contract award from Petro Rabigh, saying it will deliver engineering, project management, procurement support and related consultancy services for projects across its client’s portfolio.

      The scope includes developing design-basis documents, conducting technical evaluations, preparing cost estimates, supporting feed tender packages and providing detailed engineering and execution-phase support as projects advance through development and delivery.

      The services will support the evaluation and development of potential new facilities and infrastructure across the complex, including process units, utilities, sulphur recovery facilities and associated infrastructure.

      “The work will help Petro Rabigh advance future projects aimed at enhancing the long-term value and performance of its refining and petrochemicals operations,” Worley said in a statement on 28 October.

      Separately, Petro Rabigh awarded US-based KBR a 10-year maintenance contract in February to support its polymer plants in Rabigh.

      KBR’s Technology Led Industrial Solutions business line will execute the operations and maintenance contract, sources told MEED. The business operates within the Houston-headquartered company’s Technology Solutions portfolio.

      In March 2024, Petro Rabigh also awarded KBR a similar five-year asset-condition-monitoring contract. Under that programme, KBR is providing predictive-maintenance services at Petro Rabigh’s main plant.

      https://image.digitalinsightresearch.in/uploads/NewsArticle/21032785/main.jpg
      Indrajit Sen
    • Contractors submit Riyadh Expo KSA pavilion bids

      30 October 2026

       

      Contractors submitted bids on 25 October for a contract to design and build the Saudi Arabia pavilion at the Expo 2030 Riyadh site.

      The facility will include exhibition halls, VIP and protocol areas, event and performance spaces, meeting rooms, food and retail outlets, and back-of-house facilities.

      The pavilion will host exhibitions, cultural and commercial showcases and official events throughout the six-month expo.

      External public realm works are also included.

      Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, issued the main tender on 19 May, as MEED exclusively reported.

      Earlier this week, ERC appointed UK-based Mace as procurement advisory consultant for Expo 2030 Riyadh, supporting procurement activities across the programme.

      Under the appointment, Mace will provide procurement services and advise on the management and delivery of procurement activities, with the aim of supporting the expo’s wider programme objectives.

      Expo 2030 Riyadh will run from October 2030 to March 2031 with the theme Foresight for Tomorrow, with host authorities projecting approximately 42 million visits.

      The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event.

      Situated north of the Saudi capital, the site is located near the future King Salman International airport and will provide direct access to Riyadh landmarks.

      The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched Expo 2030 Riyadh Company – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.

      https://image.digitalinsightresearch.in/uploads/NewsArticle/21031590/main.jpg
      Yasir Iqbal
    • Oman announces $790m industrial investment deals

      30 October 2026

      Oman’s Public Authority for Special Economic Zones and Free Zones has signed 28 investment agreements worth more than RO304m ($790m) for new projects and expansions across the country’s special economic zones, free zones and industrial cities.

      The agreements cover more than 2 million square metres (sq m) of land and span industrial manufacturing, food production, logistics, recycling and commercial activities.

      About $383.6m of the investment has been allocated to industrial cities operated by the Public Establishment for Industrial Estates (Madayn). Sohar Free Zone accounted for $152m, followed by the Special Economic Zone at Duqm (Sezad) with $143.1m, Salalah Free Zone with $85.6m and Khazaen Economic City with more than $27m.

      The projects are expected to support Oman’s efforts to diversify its economy, expand industrial production and attract private investment in line with Oman Vision 2040.

      Investment deals

      In Sohar Industrial City, Atlas Steel will invest more than $291.1m in a plant producing iron and steel products on a site of about 440,000 sq m.

      Fujian Mancheng Industries & Investment will invest $52m in a ceramics facility covering more than 241,000 sq m. Other investments in Madayn’s industrial cities include an $18.2m phosphate and nitrogen fertiliser plant planned by Gulf Company for Organic and Biological Fertilisers in Raysut, as well as projects involving structural metal products, paper and corrugated cardboard, and oil and gas equipment and services in Raysut, Ibri and Nizwa.

      In Sohar Free Zone, Sohar Automotive & Advanced Industries Company will invest $98.8m in an automobile assembly complex covering 317,000 sq m. The complex aims to attract vehicle manufacturers, automotive supply-chain companies and advanced-manufacturing businesses.

      Voltamp High Voltage Transformers has announced a $39m investment in a plant that will produce power and electrical-distribution transformers for regional and international markets.

      Lalan Middle East will invest a further $3.9m to expand its medical-device manufacturing facility.

      ALSO READ: Oman’s Madayn prepares $637m investment drive

      In Sezad, Al-Jazir Feed Plant will invest $104m in a shrimp-feed facility to support an integrated shrimp-farming project.

      In Salalah Free Zone, Al-Nawras Industries will invest $50m in a steel-structures manufacturing facility, while Integrated Gypsum Company will invest $20m in gypsum-products production. Marai Dhofar will invest $15.6m in the production of Italian cheeses and other dairy products.

      Projects in Khazaen Economic City include a plant by Aleemit International Services to manufacture electric-vehicle chargers and components, with an investment of more than $8.8m, and a $6.5m facility by Joger Modular Building Technologies to produce precast-concrete building components.

      Additional investments in Khazaen include construction materials, ready-mix concrete, industrial units, logistics facilities and warehouses.

      https://image.digitalinsightresearch.in/uploads/NewsArticle/21016368/main.jpg
      Indrajit Sen