Oman pursues utility and grid expansion

5 December 2024

 

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.

These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.

“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.

In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.

The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.

The tendering process is also under way for around 1,000MW of wind IPP schemes.

In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.

Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.

The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.

Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.

Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.

Expiring capacities

While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.

These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.

The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:

  • Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
  • Barka 2 IWPP: 703MW / 120,000 cm/d
  • Rusail IPP: 184MW
  • Manah IPP: 179MW

According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.

It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.

Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.

Peak demand forecast

Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.

In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.

Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.

In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.

The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.

Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.

The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.

According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.

Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

Water sector

The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.

According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.

Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.

The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.

GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.

Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.

A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.

Other upcoming projects

In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.

PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.

PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.

PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13017866/main.jpg
Jennifer Aguinaldo
Related Articles
  • Chinese contractor wins Morocco solar plant deal

    10 August 2026

    China Harbour Engineering Company (CHEC), a subsidiary of China Communications Construction Company (CCCC), has won a contract to build a solar photovoltaic (PV) power plant in Fez in northern Morocco.

    Known as GreenPower Morocco 4 (GPM4), the project is being developed by Moroccan company GPM Holding through its utility-scale solar subsidiary GPM Parks.

    The project covers engineering design, equipment procurement and installation, construction of an operation and maintenance building, grid connection and commissioning. It also includes upgrades to the associated substation.

    According to CHEC, the completed plant will supply electricity to the local grid, although it did not disclose the project’s capacity or contract value. 

    The project is being developed under Law 13-09, which provides Morocco’s framework for private renewable energy generation.

    According to its website, GPM Holding is also developing another solar PV project called GreenPower Morocco 2 (GPM2). This follows the completion of its first solar project, the 34MW project (GPM1) commissioned in Tangier in 2024. 

    GPM1 was developed by Green Power Morocco, a special purpose vehicle owned by GPM Holding and UAE-based Amea Power. The $30m project covers 75 hectares and includes 91,000 PV panels. It is expected to generate about 66,149MWh a year.

    The project has a 25-year power purchase agreement in place with Amendis, a subsidiary of Veolia Morocco. PowerChina was the main engineering, procurement and construction (EPC) contractor.

    Chinese contractors have previously been involved in other projects in Morocco’s renewable energy sector.

    Shandong Electric Power Construction Company (Sepco 3), a subsidiary of PowerChina, was part of the EPC consortium for the 200MW Noor 2 concentrated solar plants and 150MW Noor 3 concentrated solar power projects at the Noor Ouarzazate complex.

    New contract awards have been limited in Morocco in 2026, although six solar PV plants are now in the execution stage under phases one and two of the 305MW Noor Atlas solar PV programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18263680/main.jpg
    Mark Dowdall
  • Aramco puts out fire at Jizan refinery after Houthi strike

    10 August 2026

    Saudi Aramco said it had extinguished a fire that broke out at its Jizan refinery on Saudi Arabia’s Red Sea coast after the facility was hit in drone strikes by Yemen-based Houthi rebels on 9 August.

    The kingdom’s Ministry of Energy said the fire occurred at an Aramco refinery facility in Jizan and that emergency authorities had completed the necessary procedures to deal with the incident.

    The energy ministry did not say what started the fire, saying only that the incident caused no injuries.

    The Houthi rebels later claimed responsibility for the attack.

    The province of Jizan lies close to Saudi Arabia’s border with Yemen and has repeatedly been targeted by the Houthis in attacks on the kingdom’s energy infrastructure.

    The strike on the Jizan refinery was the second attack on the facility by the Houthis in as many weeks. Aramco shut the refinery on 27 July following a similar drone strike, which, according to media reports, damaged the integrated gasification combined-cycle unit and tank farm at the complex.

    On a call with investors to discuss Aramco’s second-quarter results, CEO Amin Nasser said recent attacks on the company’s facilities in the world’s top oil-exporting country had caused some disruption to production, but that he was confident operations could be restored quickly. He said the attacks had had no material operational or financial impact.

    Jizan refinery complex

    Saudi Aramco’s sprawling Jizan refinery complex entered operations in 2021.

    Aramco undertook the estimated $16bn-plus project in late 2010. The scheme consists of a refinery with an output capacity of 400,000 barrels a day (b/d), a major marine terminal and a 4GW combined-cycle power plant in Baish, in Saudi Arabia’s southwestern Jizan region.

    The Jizan refinery covers an area of 12 square kilometres. The complex processes Arabian Heavy and Arabian Medium crude grades to produce 80 million b/d of gasoline, 250 million b/d of diesel and more than 1 million tonnes a year of petrochemical products such as benzene and paraxylene.

    A multiple-pier marine terminal supports the supply of crude oil from oil fields located mainly in the kingdom’s Eastern Province to the refinery, as well as the export of surplus refined products to overseas markets. The terminal has been designed to accommodate very large crude carriers.

    A 4,000MW combined-cycle power plant uses approximately 90,000 b/d of vacuum residue from the refinery to generate electricity, hydrogen and water for the refinery, while conveying excess power to the national grid.

    The hydrocracker unit comprises two parallel trains with a combined capacity of 54,500 b/d. The diesel hydrotreater plant comprises two trains, each with a capacity of 87,500 b/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18262347/main.jpg
    Indrajit Sen
  • Shamal picks Dutco for Dubai Zoo site homes

    10 August 2026

    Dubai-based Shamal Holding has awarded local contractor Dutco Construction the main construction works contract for a low-rise residential project on the site of the former Dubai Zoo in Jumeirah 1.

    The project will comprise 90 low-rise homes and is designed as a residential leasing community that will remain under Shamal’s ownership, with all homes offered for premium leasing.

    The development will retain mature trees from the former zoo and is planned around shared courtyards, landscaped open spaces and a central park. Residents will have access to a clubhouse, wellness area, children’s play area, family pool, lounge and gym.

    The architect is DXB Lab. The local H&H is the development manager for the project.

    Dutco has previously worked with Shamal on infrastructure elements of the Dubai Harbour and Dubai Harbour Marinas developments.

    Shamal’s wider real estate portfolio includes the Naia Island, Dubai Harbour and Nad Al-Sheba Gardens developments. The company also holds hospitality and leisure assets, including partnerships with Jumeirah, Hilton and Baccarat, and operates attractions such as Skydive Dubai and Deep Dive Dubai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18262386/main.png
    Colin Foreman
  • WEBINAR: Mena Oil & Gas Projects Market 2026-27

    10 August 2026

    Webinar: Mena Oil & Gas Projects Market 2026-27 
    Thursday 27 August 2026 | 11:00 AM GST  |  Register now


    Agenda:

    • Summary of the Mena oil, gas and petrochemicals projects market 
    • Overview of major megaprojects, including project programmes
    • Analysis of active contracts and spending to date
    • Review of top contracts by work already awarded
    • Long-term capital expenditure outlays and forecasts
    • Key contracts expected to be tendered and awarded over the next 18 months
    • Leading clients, contractors and market participants
    • Spending by segment: oil, gas and petrochemicals (upstream, downstream, onshore and offshore) 
    • Audience Q&A 

    Hosted by: Indrajit Sen, MEED’s oil & gas editor

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18260597/main.gif
    Indrajit Sen
  • Spanish firm renews Yanbu desalination O&M contract

    10 August 2026

    Spain’s Aqualia has announced it has renewed a contract to operate and maintain three floating desalination plants in Yanbu on Saudi Arabia’s Red Sea coast.

    The contract was awarded by the National Shipping Company of Saudi Arabia (Bahri) and will run until 14 September 2028, with an option to extend for a further two years.

    The three reverse osmosis (RO) plants are mounted on barges and have a combined production capacity of 150,000 cubic metres a day (cm/d). Each plant has a capacity of 50,000 cm/d.

    The three plants were originally deployed at Al-Shuqaiq and are designed to be relocated along Saudi Arabia’s coastline according to water demand. The barges are currently located at Yanbu.

    The $255m floating desalination project was commissioned for the Saudi Water Authority in 2022, with Bahri as the developer and UAE-based Metitio as the main contractor.

    Bahri is publicly listed on the Saudi Exchange but has significant government ownership, with the Public Investment Fund (PIF) holding 22.5% and Saudi Aramco Development Company owning 20% of the company.

    Aqualia is providing operation and maintenance services in Saudi Arabia through its joint venture Haji Abdullah Alireza Integrated Services Company (Haaisco), in which it holds a 51% stake.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18259350/main.jpg
    Mark Dowdall