Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Miral commits $3.2bn Yas Island investments14 September 2026
-
Contractors prepare bids for Oxagon wastewater plant14 September 2026
-
Saudi Arabia shuts East-West oil pipeline after drone strikes14 September 2026
-
WSP wins Dammam airport expansion design works14 September 2026
-
Dubai seeks contractors for multibillion-dollar road scheme14 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Miral commits $3.2bn Yas Island investments14 September 2026
Abu Dhabi’s Miral has announced plans to invest over AED12bn ($3.2bn) in Yas Island over the next five years.
According to a statement, the investment will fund a pipeline of new projects, as well as expansions and enhancements to existing attractions, supporting Abu Dhabi’s Tourism Strategy 2030.
The next phase of development will focus on expanding Yas Island’s theme parks and attractions, while introducing new immersive rides and experiences that reflect changing visitor expectations.
The investment will also strengthen the island’s hospitality offering through additional hotel rooms and enhancements to its overall accommodation portfolio.
The investment is separate from the previously announced Disney project.
Miral recently started the expansion works of its Harry Potter-themed expansion at the Warner Bros World Yas Island entertainment destination in Abu Dhabi.
The scope of the Warner Bros World phase two expansion includes adding 63,000 square metres (sq m) to the existing theme park.
This will include a Harry Potter-themed zone with three new rides called Diagon Alley, Hogwarts Castle and The Forbidden Forest, along with retail outlets and food and beverage facilities.
Yas Waterworld
Miral has developed a series of theme parks and other entertainment-related attractions on Yas Island, working with several local and international contractors.
In July last year, Miral opened a new 16,900 sq m expansion of its Yas Waterworld park to the public.
The expansion added 3.3 kilometres of slide sections to the park. The addition of 18 new rides and attractions, bringing the total number of rides to more than 60, is expected to increase visitor capacity by 20%.
Construction was carried out by local contractor Alec.
Disney park
The Walt Disney Company and Miral signed an agreement in May to build a Disney theme park resort on Yas Island.
Disney, which is based in the US, said the Abu Dhabi site will be its seventh theme park resort. The others are in California and Florida in the US, Paris in France, Hong Kong and Shanghai in China, and Tokyo in Japan.
In a statement, Disney noted that the UAE is located within a four-hour flight of one-third of the world’s population, making it a significant gateway for tourism. It is also home to one of the world’s busiest airline hubs, with 120 million passengers travelling through Abu Dhabi and Dubai each year.
The Disney theme park resort in Abu Dhabi will include entertainment areas, themed accommodations, dining venues and retail experiences.
In 2023, Miral opened SeaWorld Abu Dhabi, also on Yas Island. Alec was the contractor for the estimated $565m project.
In 2018, Miral opened the Warner Bros theme park on Yas Island. Belgium’s Besix was the contractor for the estimated $531m project.
Other Miral projects have included the Etihad Arena and the indoor climbing and skydive centre Clymb. Bam International of the Netherlands was the contractor for the arena and Germany’s Zublin was the contractor for Clymb.
Yas Island was launched as a project in 2006 by local developer Aldar Properties. The original centrepiece attractions were the Yas Marina Circuit, which hosts Formula 1 motor racing’s annual Abu Dhabi Grand Prix, and the Ferrari World theme park.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19645816/main.jpg -
Contractors prepare bids for Oxagon wastewater plant14 September 2026

Contractors are preparing to submit bids to build a wastewater treatment plant for Oxagon, Neom’s industrial cluster.
The industrial wastewater treatment package will have an initial capacity of 35,000 cubic metres a day (cm/d), supplied in modular trains of 5,000 cm/d each. A separate sanitary wastewater treatment package will have a capacity of 1,000 cm/d.
The contract is structured as a design-build-operate project and covers the supply, installation and commissioning of industrial and sanitary wastewater treatment packages, as well as three years of operation and maintenance.
Bids are due on 2 October, a source close to the project told MEED.
It is understood that Neom’s water utility Enowa issued the request for proposals earlier this year. The plant is designed to provide “interim wastewater treatment” capacity for Neom’s Oxagon Industrial Quarter as industrial development in the area progresses.
Enowa has described the treatment systems as interim and de-mountable, allowing them to be installed and subsequently removed or relocated as requirements at Oxagon develop. The plant can be expanded to a maximum of 45,000 cm/d.
The tender documents also state that Neom may consider export credit agency (ECA) financing for the project, with the strength of bidders’ ECA financing proposals forming part of the commercial evaluation.
The project follows an earlier tender for the Oxagon Village Water Recycling Plant, which was cancelled despite contractors submitting bids in 2024.
MEED reported at the time that Beijing-based PowerChina, the local Alfanar Company and Cairo-headquartered Orascom had submitted bids for the project. It is understood that these firms are also likely to participate in the latest tender.
The earlier scheme included truck receiving facilities, pretreatment, biological treatment using food chain reactor technology, tertiary treatment, sludge handling and recycled-water storage.
The latest procurement appears to represent a reworked approach to wastewater treatment at Oxagon Industrial Quarter, with the previous engineering, procurement and construction scheme replaced by an interim, modular and de-mountable facility.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19640903/main.jpg -
Saudi Arabia shuts East-West oil pipeline after drone strikes14 September 2026
Saudi Arabia has temporarily closed its 1,200-kilometre East-West pipeline after it was targeted by multiple drones launched from Iraq, disrupting one of the kingdom’s most critical energy export routes and threatening global oil supplies already strained by conflict across the region.
The Ministry of Energy said the pipeline, which connects the Abqaiq oil field in the east to the Red Sea port of Yanbu, was hit in the Riyadh and Medina regions on 12 September. Specialised teams have begun securing the facility and assessing damage. A Foreign Ministry statement said the attack resulted in injuries and “some damage that is currently being addressed”.
The closure removes about 4 million barrels a day from the global market, representing 4% of world oil supply. The pipeline’s role has become increasingly critical since the US-Iran conflict forced a near-complete shutdown of flows through the Strait of Hormuz in March.
Saudi Arabia has been using the East-West route to bypass the chokepoint, but the assault has left the kingdom dependent on substantially reduced Hormuz exports and Red Sea shipping routes now threatened by Iran-backed Houthi forces in Yemen.
Iraqi Prime Minister Ali Al-Zaidi’s office confirmed the drone strike on the East-West Pipeline originated in the Maysan province, which borders Iran. The government formally condemned the attack, announced an investigation into the Maysan operations command and dismissed its commander. No armed group has claimed responsibility, but security analysts attribute the strike to Iran-backed militias operating from Iraqi territory.
Riyadh said it was not retaliating “at this stage”, choosing instead to support Iraqi efforts to prevent further strikes from its territory.
The attack comes amid wider regional upheaval. Houthi forces have rapidly advanced along Yemen’s coast, seizing the strategic Mokha port and the Zuqar Island in the southern Red Sea, moving closer to the Bab El-Mandab strait. Saudi authorities said the group simultaneously launched dozens of drones and missiles at the southern kingdom on 11 September, striking civilian and economic targets and injuring 73 people.
Oil analysts and traders reported that Yanbu’s storage capacity, estimated at around 35 million barrels, now holds supplies sufficient for only five to seven days of exports without pipeline operations. Storage facilities at Egypt’s Ain Sokhna and Sidi Kerir ports have similar constraints. Repair timelines remain uncertain, with sources citing estimates ranging from days to five or six weeks.
The dual disruption of both the pipeline and Red Sea shipping has compressed global energy supplies. Energy analysts warned that without pipeline repairs, oil prices could return to the $120-a-barrel peak reached earlier in the regional conflict.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19641513/main.gif -
WSP wins Dammam airport expansion design works14 September 2026
WSP Middle East, the regional arm of Canadian engineering firm WSP, has won a design contract to expand King Fahd International airport in Dammam, Saudi Arabia.
Dammam Airports Company (DACO) awarded the contract.
The scope includes designing passenger terminal expansions, facility upgrades, and improvements to airport entrances and access roads.
It also covers the development of baggage-handling systems, digital services and other associated infrastructure.
The expansion works will be carried out in line with the airport’s approved masterplan, which targets serving more than 19 million passengers a year by 2030.
The plan also aims to increase air cargo capacity to more than 600,000 tonnes a year and raise aircraft operational capacity to 77 movements per hour, supported by comprehensive expansions to infrastructure, runways and general aviation facilities.
This contract forms part of DACO’s ongoing efforts to strengthen the airport ecosystem, enhance operational efficiency, and support the Aviation Programme and Saudi Vision 2030 objectives.
King Fahd International airport is the kingdom’s third-largest airport by annual passenger traffic, behind Jeddah’s King Abdulaziz International and Riyadh’s King Khaled International.
DACO was formed in July 2017 to manage, operate and develop King Fahd International airport in Saudi Arabia’s Eastern Province.
It was established as part of the broader Saudi Vision 2030 privatisation and economic reform programme to corporatise the aviation sector, increase operational efficiency, upgrade infrastructure, and transition state-run airports into commercially viable, world-class regional aviation hubs.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19639910/main.jpg -
Dubai seeks contractors for multibillion-dollar road scheme14 September 2026

Register for MEED’s 14-day trial access
Dubai’s Roads & Transport Authority (RTA) is seeking contractors to design and build a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.
MEED understands that the scope covers the construction of about 30 kilometres (km) of works.
These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.
The RTA floated the expression of interest notice to contractors in early September, with a submission deadline of 10 October.
The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.
Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.
The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through-traffic while the existing at-grade lanes served local access.
The plans ultimately progressed as standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.
The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.
Planning for growth
Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.
In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan.
In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.
The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19639621/main.gif