Oman pursues utility and grid expansion
5 December 2024

Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
-
Bahrain opens bids for 1.2GW Sitra IWPP19 June 2026
-
-
Chinese firms win $506m Saudi housing project deals18 June 2026
-
Diriyah awards $727m Waldorf Astoria superblock deal17 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Aramco issues tender for gas pipeline at Ras Tanura refinery19 June 2026

Register for MEED’s 14-day trial access
Contractors are preparing bids for a Saudi Aramco tender involving the replacement of a pipeline that is part of the Gas Line Abqaiq – Ras Tanura (GART) transmission network.
The GART grid transports associated gas and natural gas liquids (NGL) from the Abqaiq oil processing complex as feedstock, northwards to the Ras Tanura refinery in Saudi Arabia’s Eastern Province.
The aim of the project is to replace the GART-22 pipeline that connects the Juaymah export terminal on the Gulf coast in the Eastern Province to the Ras Tanura refinery, to ensure reliable fuel gas supply and meet ongoing demand.
The basic scope of work on the project is to install a new, 24-inch pipeline system that will replace the GART-22 line and the abandoned GART-24 line. It will cover a distance of 18 kilometres between Juaymah and the Ras Tanura terminal.
The scope also includes the installation of associated scraper trap facilities (launcher and receiver), pressure control valves, motor-operated valves and gas detection and sampling systems.
Aramco issued the tender for the project in May and has set a deadline of 30 June for contractors to submit proposals.
The following contractors, among others, are understood to be bidding for the project:
- ACE Pipeline Arabia
- Combined Group Contracting Company
- Gas Arabian Services Company
- Max Streicher Saudi Arabia
- National Basics Company
- Saad Ali Alessa Group
- Sicim
- Sinopec Engineering Group Saudi
- Tecton Engineering & Construction
Ras Tanura refinery complex
The Ras Tanura refinery is the oldest, and one of the largest, crude oil refineries in Saudi Arabia. The complex has a refining capacity of 550,000 barrels a day (b/d).
The facility also has a 305,000 b/d NGL processing facility, a 960,000 b/d crude stabilisation facility, combined steam and gas turbine electrical power generation plants with a summer capacity of 145MW and a winter capacity of 158MW, and a combined 150-pound and 600-pound steam capacity of 6,217 million pounds an hour.
It has 75 crude oil and products storage tanks with a combined capacity of 5.8 million barrels.
The Ras Tanura refinery’s major facilities include a 325,000 b/d crude distillation unit, a 225,000 b/d gas condensate distillation unit, a 50,000 b/d hydrocracker and 107,000 b/d of catalytic reforming capacity.
The facility is Aramco’s only refinery to contain a Visbreaker processing unit, which has a 60,000 b/d capacity.
The Visbreaker reduces the quantity of residual oil produced in the distillation of crude oil and increases the yield of more valuable middle distillates, heating oil and diesel.
The refinery complex also produces 17,000 b/d of asphalt, more than any other refinery in Saudi Arabia.
Ras Tanura receives crude feedstock from the Abqaiq, Safaniya and Manifa oil field developments.
Crude is typically transferred to Ras Tanura through a pipeline and can also be supplied by ship.
Most of Ras Tanura’s production is transferred to the Dhahran bulk plant for domestic use, while some products are exported from the nearby Ras Tanura shipping terminal.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17332850/main.JPG -
Bahrain opens bids for 1.2GW Sitra IWPP19 June 2026
Register for MEED’s 14-day trial access
Two developers have submitted bids for the 1.2GW Sitra independent water and power plant (IWPP), according to details published by Bahrain’s Tender Board.
The offers were made by Abu Dhabi National Energy Company (Taqa) and Saudi Arabia's Acwa. The technical element of the bid was opened on 18 June.
The Sitra IWPP is a combined-cycle gas turbine plant and is expected to have a generation capacity of about 1,200MW of electricity. The project’s seawater reverse osmosis desalination facility will have a production capacity of 30 million imperial gallons a day.
The build, own and operate project is being procured by Bahrain’s Electricity & Water Authority (EWA) under a public-private partnership framework for 20-25 years.
According to a source, "evaluation will be done on technical bids and put up to a tender board for approval".
Financials will be opened only after the technical element has been approved.
Other major IWPP projects in the region have also recorded relatively low bidder particpation in recent weeks, reflecting the level of investment required for such projects.
Earlier this month, MEED reported that just two bids had been received for the first phase of Kuwait’s Al-Khairan IWPP project.
Three consortiums and two individual companies had previously prequalified to participate in the tender.
In 2024, Bahrian's EWA received statements of qualifications from nine firms interested in bidding for the Sitra IWPP. Seven international companies and consortiums were then prequalified to bid last year.
Sitra grid works
Meanwhile, firms are still awaiting awards for two separate contracts related to the establishment of new Sitra 400kV grid substations.
The first contract involves transformer and reactor works for the establishment of the substations.
Switzerland-headquartered Hitachi Energy submitted the lowest bid of BD17.8m ($47.1m). Germany’s Siemens Energy submitted an offer of BD23.9m ($63.2m).
The second contract involves 400kV and 220kV feeder cable works for the same Sitra 400kV grid substations. Three South Korean companies previously bid for the contract.
Bids for both contracts were opened in March.
In September, Siemens Energy won a contract worth BD48.1m ($127m) to build a 400kV transmission substation in Sitra to provide the transmission link for the planned Sitra IWPP.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17329853/main.jpg -
Jordan starts international stadium construction works18 June 2026
Register for MEED’s 14-day trial access
Jordan has started preliminary excavation and site preparation work at its Al-Hussein Bin Abdullah II International Stadium, located east of the capital city of Amman.
The project is part of the first phase of the Amra City development master plan.
The development is being implemented by Jordan Cities & Facilities Development Company, a Jordan Investment Fund-owned company.
The main works are expected to begin early next year, with the stadium slated for completion in 2029.
The project will cover an area of about 1 million square metres and the stadium will have a capacity of 50,000 spectators.
The stadium is being built within the Amra City development, which is located about 40 kilometres (km) from downtown Amman and 35km from Zarqa City and Queen Alia International airport.
The project forms part of Jordan's Economic Modernisation Vision (EMV) 2023-25.
The EMV – Amman’s flagship reform programme – aims to increase real income per capita by an average of 3% annually, create 1 million jobs, and more than double the country’s GDP over the next decade.
The strategy envisages a leading role for the private sector, which is expected to account for 73% of the estimated $58.8bn investment required.
To achieve these targets, a substantial pipeline of public-private partnership (PPP) projects is planned in sectors including water desalination, school construction, clean energy, green hydrogen, transport and road infrastructure.
Last year, the PPP unit at the Investment Ministry said it was targeting seven key PPP projects in 2025.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17325757/main.png -
Chinese firms win $506m Saudi housing project deals18 June 2026
Register for MEED’s 14-day trial access
Saudi Arabia’s Municipalities & Housing Ministry has awarded contracts worth over SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.
The first contract has been awarded to China Architectural Construction Corporation for the construction of 2,010 housing units at the Al-Ruba residential project in Riyadh. The contract value is SR875m ($233m).
The other contract has been awarded to China State Construction Engineering Corporation for the Al-Rasha Al-Faisaliah residential project in Dammam. The project comprises 2,426 housing units, and the contract value is over SR1bn ($266m).
The contracts were announced during the official visit of Majed Al-Hogail, Saudi Municipalities & Housing Minister, to China, where he also signed six memorandums of understanding (MoUs) between Saudi and Chinese firms. The MoUs aim to accelerate housing development, localise advanced construction technologies and enhance public-private sector collaboration.
MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.
By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and to become one of the 10 wealthiest cities in the world.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17322994/main.png -
Diriyah awards $727m Waldorf Astoria superblock deal17 June 2026

Saudi gigaproject developer Diriyah Company has awarded a SR2.7bn ($727m) contract for the main construction works on the development’s Waldorf Astoria superblock.
The contract was awarded to the joint venture of Hassan Allam Construction Saudi and UCC Saudi, the local branch of Qatar’s Urbacon Holding.
The Waldorf Astoria superblock is a mixed-use development comprising a Waldorf Astoria hotel, Waldorf Astoria-branded residences, commercial and residential facilities, and office space.
The Waldorf Astoria hotel will feature 200 keys, while the residential component will comprise 47 branded residences.
The project is located on the Grand Boulevard South and Northern Arterial Road in the Boulevard Northwestern district at Diriyah Gate 2.
Diriyah Company tendered the contract in November last year, with submissions due in January, as MEED reported.
Diriyah Company Group CEO Jerry Inzerillo said: “We are delighted to announce this latest major construction contract for the Waldorf Astoria superblock as we continue to progress at pace across the Diriyah development area. The Waldorf Astoria will be a world-class addition to our growing portfolio of globally renowned hospitality brands, further strengthening Diriyah’s appeal as a globally significant destination that offers world-class hospitality and lifestyle experiences.
“Together with our partners, we look forward to delivering another landmark development that supports the kingdom’s Vision 2030 ambitions and contributes to the continued growth and success of Diriyah.”
Hassan Allam, chairman and CEO of Hassan Allam Holding, said: “We are proud to support the development of one of the kingdom’s most ambitious and transformative destinations and to continue our partnership with Diriyah Company in bringing its vision to life.
“Drawing on more than 90 years of experience across the Mena region, we remain committed to delivering the highest standards of quality and excellence on landmark projects that are helping shape the kingdom’s future.”
Ramez Al-Khayyat, UCC Holding president and group CEO, said: “Being awarded this contract by Diriyah Company marks another important milestone in our growing partnership and reinforces our shared commitment to delivering world-class developments across the kingdom. This project builds on our ongoing collaboration in Diriyah, including the delivery of four luxury hotels and the Royal Diriyah Equestrian and Polo Club in Wadi Safar.
“We value the opportunity to contribute once again to one of Saudi Arabia’s most ambitious and prestigious urban development destinations, supporting the vision of creating a world-class cultural, hospitality and lifestyle hub.”
The latest award follows Diriyah Company’s award of an estimated SR730m ($195m) construction contract for civic quarter buildings within the Diriyah development to local contractor Al-Rashid Trading & Contracting Company (RTCC).
In April, Diriyah announced a SR1.84bn ($490m) construction contract to build the Saudi Arabia Museum of Contemporary Art (SAMoCA) within the Diriyah development. The contract was awarded to a consortium of Egyptian contractor Hassan Allam Construction Saudi and Saudi Arabia’s Albawani.
In March, Diriyah Company awarded an estimated SR2.5bn ($666m) contract to build the Pendry superblock in the DG2 area.
The Pendry superblock includes the construction of the Pendry Hotel alongside residential and commercial assets. The package will cover 75,365 square metres and is located in the northwestern district of the DG2 area.
The previous month, Diriyah Company also awarded a SR717m ($192m) contract for the construction of the One Hotel, located in the Diriyah Two area of the masterplan, with a gross floor area of more than 31,000 sq m.
The Diriyah masterplan envisages the city as a cultural and lifestyle tourism destination. Located northwest of Riyadh’s city centre, it will cover 14 square kilometres and combine 300 years of history, culture and heritage with hospitality facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17287718/main.jpg