Oman gas contract is worth $683m
12 December 2025

The contract that Petroleum Development Oman (PDO) has awarded to Kuwait-based Spetco to develop an integrated natural gas facility is worth $683m, according to industry sources.
The facility, which will produce natural gas from the Budour and Tayseer fields in Oman, will be constructed over a 30-month period under the terms of the contract, sources said.
In September, MEED reported that PDO had awarded Spetco the main design, build, own, operate and maintain (DBOOM) contract for the combined Budour-Tayseer sour gas processing facility project.
PDO recently held an official signing ceremony with Spetco for the DBOOM contract, which has an operations and maintenance period of 15 years.
The project aims to expand the capacity of the existing gas production and processing facilities at Tayseer. It represents the second development phase of the gas field.
Through the project, PDO is also seeking to appraise, produce and process sweet gas from the Budour field, which is about 50 kilometres (km) west of the Tayseer field.
The following firms, among others, are understood to have submitted proposals to PDO:
- Enerflex (Canada)
- Jereh Group (China)
- Spetco (Kuwait)
The three developers originally submitted proposals for the project by 30 November 2024.
PDO issued the DBOOM tender for the Budour‑Tayseer combined gas processing facility project in the first quarter of 2024, after completing a prequalification exercise in June 2023.
MEED previously reported that PDO suspended the DBOOM tendering exercise earlier this year and tested an alternative execution model, initiating a front‑end engineering and design (feed) to engineering, procurement and construction (EPC) competition.
PDO floated a prequalification document for the feed-to-EPC contest in March. Contractors submitted responses to the prequalification questionnaire by the deadline of 27 April.
The feed-to-EPC competition model involves the project operator selecting contractors to execute feed work and then choosing the contractor with the most competitive feed proposal to execute EPC works on the project, while also compensating the other contestants for their work.
However, PDO did not select contractors to take part in the feed‑to‑EPC contest and is understood to have cancelled the exercise, sources told MEED. The client eventually reverted to the DBOOM model.
Tayseer and Budour field development
The Tayseer field was discovered in November 2014 after the successful well-testing of Tay-1. It is approximately 50km north of the Birba field and 20km west of the Al-Noor production station.
Since the Tayseer field is part of the A1C platform carbonate, which has proven aquifer support in the Budne A1C field, some formation water production can be expected.
PDO developed the Tayseer field through a project in 2016. US-based Exterran was awarded a design, build and operate contract in 2017.
Currently, three Tayseer wells are being processed in the existing Tayseer early development facility and sweet gas from the facility is being exported to PDO’s South Oman gas pipeline.
As part of the expansion phase, new production wells will be drilled at Tayseer. The produced gas will be processed at a new sour gas processing facility located at Budour.
The Budour A4C non-associated gas field was discovered in 2001 and appraised until 2009. The field has never been appraised since. The development concept for the Budour non-associated gas field involves depletion through a standalone sour gas processing facility, with sweet gas exported to the South Oman gas pipeline.
No formation water is expected, so only the condensation water requires handling and disposal. New production wells are to be drilled at Budour and production from those wells will be processed at the planned new sour gas processing facility.
The DBOOM contractor was required to provide the following on-plot facilities and services as part of the project:
- Inlet production/ test manifold
- Well testing
- Inlet separation
- Sour gas processing facility, including export gas compressors
- Sulphur recovery and storage
- Crude de-salting
- Condensate stabilisation
- Condensate storage and export
- Produced water treatment
- Storage, export and raw water treatment with all the associated plant utilities
- Controls and instrumentation
The planned combined Budour-Tayseer sour gas processing facility is projected to have a capacity of 78.39 million cubic feet a day (cf/d) and unstabilised condensate of 1,167 cubic metres a day (cm/d). The facility will handle gas exports of about 70 million cf/d, stabilised condensate exports of 950 cm/d and will have a water handling capacity of 340 cm/d.
Outside the scope of services under the original DBOOM contract, PDO intended to build off-plot facilities to support the Budour-Tayseer combined gas processing facility.
These were:
- Wellhead hook-ups
- Sour gas flowlines from the wellhead to the on-plot facilities
- Remote manifold station at the Tayseer field
- Wash water distribution network from the on-plot facility boundaries to gas production wellheads
- Sour gas production pipeline from the Tayseer field to the Budour field
- Sweet gas export pipeline from the on-plot facility to the Salalah gas line
- Condensate export pipeline from the on-plot facility to the main oil line
- Produced water pipeline from the on-plot facility to the Marmul water treatment plant in southeastern Oman for further processing and deep water disposal
- Raw water supply line from the water supply well to the on-plot facility and electrical overhead line from the PDO grid to the DBOOM facility
READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF
Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges
Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:
|
> AGENDA 1: Regional rail construction surges ahead
> INDUSTRY REPORT 1: Larsen & Toubro climbs EPC contractor ranking
> INDUSTRY REPORT 2: Chinese firms expand oil and gas presence
> CONSTRUCTION: Aramco Stadium races towards completion
> RENEWABLES: UAE moves ahead with $6bn solar and storage project
> INTERVIEW: Engie pivots towards renewables projects
> BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
|
Exclusive from Meed
-
Algeria tenders upstream oil project contract25 June 2026
-
-
Chinese firm wins $265m Saudi hospital contract24 June 2026
-
Kuwait extends deadline for $718m drainage tender24 June 2026
-
Contractor wins Emaar Dubai Harbour project deal24 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Algeria tenders upstream oil project contract25 June 2026
Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.
The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.
Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.
It also says the project aims to improve production yields and quality.
The contract includes both initial and detailed studies as well as the supply of all equipment and materials.
It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.
The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg -
MECC submits lowest bid on three Kuwaiti oil and gas contracts25 June 2026

Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).
The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds
Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.
The bidders were:
- MECC: KD65,760,000 ($212m)
- Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
- Amco Engineering & Construction: KD73,446,100 ($237m)
- Combined Group Contracting Company: KD76,186,000 ($246m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)
Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.
The bidders were:
- MECC: KD30,760,000 ($99m)
- Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
- Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
- Industrial Company for Electrical Projects: KD36,375,520 ($118m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
- Combined Group Contracting Company: KD37,790,000 ($122m)
Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.
The bidders were:
- MECC: KD35,760,000 ($116m)
- Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
- Amco Engineering & Construction: KD39,736,800 ($128m)
- Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
- Industrial Company for Electrical Projects: KD43,238,265 ($140m)
- Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
- Combined Group Contracting Company: KD43,650,000 ($141m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)
Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.
A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.
Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg -
Chinese firm wins $265m Saudi hospital contract24 June 2026
Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.
Construction is expected to take three years from the start date.
Prince Mohammed Bin Fahd University awarded the contract.
Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.
The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.
Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.
The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.
Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.
China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.
China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.
GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg -
Kuwait extends deadline for $718m drainage tender24 June 2026

Kuwait’s Ministry of Public Works (MPW) has extended the deadline for a major drainage tender estimated to be worth about KD222m ($718m).
The new bid submission deadline is 19 July.
The tender scope covers the construction of rainwater drainage networks across the residential areas of Sabah Al-Ahmad, South Sabah Al-Ahmad, Al-Khairan and Al-Wafra.
The MPW floated the tender on 22 March. The most recent deadline was 21 June.
According to regional projects tracker MEED Projects, the works include the construction of a major concrete sewer, three collection basins and extensive stormwater drainage basins.
Rainwater collection tanks will be connected through an independent network, with outlets to the sea via the Nuwaiseeb exit to manage overflow.
The infrastructure will also filter pollutants such as oils, minerals and sediments to protect water quality and support environmental sustainability.
The project aims to reduce surface runoff, prevent street and urban flooding, and improve groundwater recharge.
Kuwait’s MPW currently has several contracts out for tender for infrastructure works across various parts of the country.
Also, in March, the client released two additional tenders covering the construction of a treated water system in Kuwait’s southern region and another in Kuwait’s northern region.
Bids for both projects are due by 28 June.
Meanwhile, the MPW is planning to begin construction of the $3.3bn North Kabd sewage treatment plant, which has a planned capacity of up to 1 million cubic metres a day.
China State Construction Engineering Corporation (CSCEC) won the contract to build the plant earlier this year.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17411675/main.jpg -
Contractor wins Emaar Dubai Harbour project deal24 June 2026

Register for MEED’s 14-day trial access
Local construction firm Al-Sahel Contracting Company has won a contract to build The Bristol Luxury Hotels & Resorts project in Dubai.
The contract was awarded by local real estate developer Emaar Properties.
The Bristol Luxury Hotels & Resorts is located at Emaar Beachfront in Dubai Harbour.
The project comprises a 54-storey mixed-use building with about 150 hotel keys and 227 one- to four-bedroom apartments.
Enabling works have been completed by local firm Dutch Foundation.
Dubai-based Mirage Leisure & Development is the project’s consultant.
Construction is expected to be completed by 2028.
The contract award follows Emaar’s appointment of Dubai-based Aroma International Building Contracting to build the Address Grand Downtown tower.
The award also comes shortly after Emaar reported strong operating momentum in 2025, led by record property sales of AED80.4bn ($21.9bn), up 16% year on year.
The company’s revenue backlog from property sales rose to AED155bn ($42bn), supporting visibility on future revenue recognition.
Total revenue for 2025 reached AED49.6bn ($13.5bn), a 40% year-on-year increase. Earnings before interest, taxes, depreciation and amortisation grew 33% to AED25.6bn ($7bn), while net profit before tax rose 36% to AED25.7bn ($7bn).
Emaar’s platform continued to support performance across property development, malls, hospitality, leisure and international operations.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17411104/main.jpg
