Oman expands grid connectivity
10 December 2023
Oman’s power and water sector has awarded an annual average of approximately $1.5bn-worth of contracts over the past 11 years – a relatively low value compared to the total awarded every year by some of its GCC neighbours.
However, 2023 can still be considered a good year for the sultanate, as contracts worth an estimated $1.2bn have been awarded.
This is an improvement on the performance of the previous two years, which saw very limited project activity within the sector, with contract awards valued at just $104m in 2021 and $244m in 2022.
Having adopted a policy to not procure further gas-fired thermal power plants, Oman awarded the contracts to develop its second and third utility-scale solar photovoltaic (PV) plants in early 2023.
The Manah 1 and 2 solar PV independent power projects (IPPs) each have a capacity of 500MW. Wadi Noor Solar Company, comprising France’s EDF Renewables and South Korea’s Korea Western Power Company (Kowepo), will deliver and maintain the Manah 1 solar IPP project for 20 years.
Another team, comprising Singapore’s Sembcorp Industries and China-headquartered Jinko Power Technology, will develop the Manah 2 IPP scheme. The country’s first utility-scale solar project, Ibri 2, became operational in 2021.
Oman’s Ministry of Regional Municipalities & Water Resources also awarded a $108m contract for the construction of a flood protection dam in Wadi Ajay Gorge in Muscat in early 2023. The rest of the awarded contracts comprise water and power transmission pipeline projects across the sultanate.
Demand growth
Nama Power & Water Procurement Company (PWP), formerly Oman Power & Water Procurement Company (OPWP), expects peak electricity demand for the main interconnected system (MIS), the sultanate’s main electricity grid, to grow by an average of 3.54 per cent annually from 2022 to 2029, reaching 8,350MW at the end of the forecast period.
Most of this growth is expected to occur in the near term, as the economy recovers from the effects of the Covid-19 pandemic, according to PWP’s most recent Seven-Year Statement, which covers the years 2023-29. It is also higher compared to the 2.5 per cent average annual peak demand growth rate seen between 2015 and 2022.
PWP’s low-case forecast scenario shows an average annual peak demand growth of 1.3 per cent, with the base growing from 6,628MW to just over 7,200MW. A high-case scenario, on the other hand, indicates an annual demand growth of 5.2 per cent, which can drive the demand to reach 9,430MW.
Annual peak demand growth in the smaller Dhofar grid is expected to average 5 per cent between 2022 and 2029.
The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November. The 400-kilovolt (kV), 670-kilometre (km) project required an investment of about $966m.
The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November
The project enables the MIS, serving the northern half of the Oman grid, to connect with Nihada in Al-Dhahirah Governorate and Duqm Special Economic Zone (SEZ) in Al-Wusta Governorate.
Al-Wusta offers an optimal location for solar and wind projects, which the country aims to develop as part of its green energy ambitions.
Also part of Rabt's first phase, the isolated networks of Petroleum Development Oman and the Rural Areas Electricity Company (Tanweer) in Duqm SEZ, have been interconnected.
A second phase is being planned for Rabt. To be launched later this year, it will comprise a 500km, 400kV transmission line from Duqm to Dhofar.
Water requirements
Peak water demand in the MIS is expected to increase by an average of 2 per cent annually between 2022 and 2029, while peak water demand in Dhofar is expected to grow by an average of 7 per cent a year.
To meet the expected demand rise in the MIS, several independent water projects are being developed or planned. These include the Barka 5 scheme, which has a capacity of 100,000 cubic metres a day (cm/d) and is expected to come online in 2024. Ghubrah 3, which has three times as much capacity, is expected to be operational two years later.
A third project, a replacement capacity for the Barka zone of about 102,000 cm/d, is also expected to be added in 2024.
Future projects
In addition to the second phase of Rabt, Oman is in the early procurement phase of several solar and wind projects, in line with meeting demand growth and replacing expiring contracted capacity.
The power and water purchase agreement for the gas-fired Barka 2 independent water and power facility, for instance, expires in 2024, while the contract for the Barka 3 IPP expires in 2028.
KPMG Lower Gulf, a subsidiary of the Netherlands-based consultancy company, has been selected to provide financial advisory services to Nama PWP for the Ibri 3 solar IPP, which will have a capacity of 500MW. Ibri 3, along with the planned 100MW Jalaan Bani Bul Ali wind power project, will cater to the MIS.
Another key scheme being planned to connect to the MIS is Oman’s first waste-to-energy plant in Barkah. When complete, the facility is expected to treat 4,500 tonnes of municipal waste a day, produce 130MW-150MW of energy, and reduce the carbon footprint of Oman's landfills by 1.3 million tonnes annually.
For the Duqm grid, a 100MW wind IPP is being planned, in addition to a potential concentrated solar power plant. These plants are expected to become operational in 2026 and 2028, respectively. A 100MW wind project is also being planned for Dhofar, although there has been no fixed target for when it is expected to become operational.
In May, it was also announced that Oman Electricity Transmission Company is planning a second link to the GCC grid. The planned 400kV power transmission link is scheduled to start operations in the first quarter of 2026.
Hydrogen hubs
There are major plans to develop green hydrogen hubs in Duqm and Dhofar, in line with Oman's ambition to produce up to 1.25 million tonnes a year of green hydrogen by 2030.
The proposed projects will integrate renewable energy plants that will supply power to the electrolyser plants, which split water into hydrogen and oxygen, as well as the other units of the facilities.
The government has so far awarded land concessions to international consortiums looking to develop integrated green hydrogen and ammonia facilities in the country.
The programme will have a potentially significant impact in terms of Oman’s future gross renewable energy capacity growth, with some of the earliest announced projects requiring several gigawatts of wind and solar power.
However, since most of the planned projects include captive renewable energy power plants, they will not necessarily affect the Omani utility companies' future capacity procurement plans.
On the other hand, water demand may be affected as the electrolysis plants require pure water to be split into hydrogen and oxygen.
Exclusive from Meed
-
Bidders await NWC decision on sewage contract17 February 2026
-
Dubai tenders Al-Maktoum airport superstructure17 February 2026
-
Contractors submit revised prices for Habshan 7 project17 February 2026
-
Dubai seeks contractors for Jebel Ali STP expansion16 February 2026
-
AD Ports to develop Douala port in Cameroon16 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Bidders await NWC decision on sewage contract17 February 2026

Saudi Arabia’s National Water Company (NWC) is evaluating five bids for package 12 of its long-term operations and maintenance (LTOM12) sewage treatment programme.
Known as the North Western B Cluster, LTOM12 forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.
The contract covers the construction and upgrade of seven sewage treatment plants with a combined capacity of about 162,000 cubic metres a day (cm/d).
As MEED understands, the companies that have submitted proposals include:
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- Civil Works Company (Saudi Arabia)
- Miahona (Saudi Arabia)
- Beijing Enterprises Water Group – BEWG (Hong Kong)
- Al-Yamama (Saudi Arabia)
Earlier this month, MEED exclusively reported that six contractors are competing for the North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11), which has an estimated value of about $211m.
The project involves the construction and upgrade of two sewage treatment plants with a combined capacity of about 440,000 cm/d.
The scheme is being procured on an engineering, procurement and construction (EPC) basis with a long-term operations component.
It is understood that contracts for LTOM11 and LTOM12 will be awarded in May.
In January, a consortium of United Water (China), Prosus Energy (UAE) and Armada Holding (Saudi Arabia) won the main contract for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).
This contract was the first to be awarded under the second phase of NWC’s rehabilitation of sewage treatment plants programme.
NWC previously awarded $2.7bn-worth of contracts for the first phase of its LTOM programme. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15670141/main.jpg -
Dubai tenders Al-Maktoum airport superstructure17 February 2026

Dubai Aviation Engineering Projects (DAEP) has tendered three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.
Interested bidders have until 23 March to submit their proposals.
MEED understands that the selected contractor will undertake superstructure works on three packages:
- West Terminal and concourse one
- Concourse two
- Concourse three
Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.
According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.
It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.
In August, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport.
The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
Construction progress
Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.
Construction on the project’s first phase is expected to be completed by 2032.
The government approved the updated designs and timelines for its largest construction project in April 2024.
In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
The statement added that the project will create housing demand for 1 million people around the airport.
In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.
Project history
The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.
An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.
Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15669879/main.jpg -
Contractors submit revised prices for Habshan 7 project17 February 2026

Adnoc Gas has received revised commercial proposals from contractors for engineering, procurement and construction (EPC) works on a major project to add a new gas processing train at its Habshan complex in Abu Dhabi.
Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), processes about 10 billion standard cubic feet a day (cf/d) of gas across several sites, including its Asab, Bab, Bu Hasa and Habshan facilities, as well as a natural gas liquids (NGL) fractionation plant at Ruwais.
The Habshan complex is one of the largest gas processing facilities in the UAE and across the Middle East and North Africa. Its output capacity is 6.1 billion cf/d. The complex comprises five trains and 14 processing units that receive gas feedstock from onshore and offshore fields in Abu Dhabi.
With Adnoc Group pressing ahead with its P5 programme to raise oil production potential to 5 million barrels a day by 2027, high volumes of associated gas are set to enter the grid.
The new train at the Habshan complex, which Adnoc Gas expects to commission in 2029, will play a key role in handling these additional gas volumes.
MEED previously reported that contractors had submitted commercial bids for the new Habshan 7 gas train project to Adnoc Gas by the deadline of 10 December.
Following an initial evaluation of commercial bids received, Adnoc Gas sought “best offers” from contractors for the project. Bidders submitted their revised prices by 6 February, according to sources.
The following contractors are understood to be competing for the Habshan 7 project’s main EPC contract, as per sources:
- Enppi (Egypt) / Petrojet (Egypt)
- Jereh (China)
- Larsen & Toubro Energy Hydrocarbon (India)
- Petrofac (UK)
- Sinopec (China)
- Wison Engineering (China)
MEED previously reported that contractors submitted technical bids for the project to Adnoc Gas by the deadline of 6 October.
Adnoc Gas intends to install the Habshan 7 train adjacent to the Habshan 5 train. This will enable the new train to utilise the ullage in the Habshan 5 sulphur recovery and tail gas treatment units and optimise operations.
The scope of work on the Habshan 7 gas train project covers the EPC of the following units:
- New high-pressure pipeline from the main Habshan complex to the new gas train
- Separation and condensate stabiliser unit
- Acid gas removal unit
- Mercury removal unit
- Deep NGL recovery unit
- Sales gas and residue gas compressor
- NGL product storage and transfer pump, as well as metering skid
- Utility units (IA, N2, PW, FW, steam generation, DM)
- Flare unit, to be located in Habshan 5 on common derrick
- Flare gas recovery package
- Water treatment package
- Non-process buildings, to be located outside the Habshan 5 train
- Power generation system
- NGL pipeline from Habshan 5 to Ruwais, based on an existing pipeline assessment
- Sales gas pipeline from Habshan 5 to sales gas network.
UK-headquartered Wood Group has performed the concept study and initial engineering design for the project.
The Habshan 7 gas train project represents the third phase of Adnoc Gas’ Rich Gas Development programme and is estimated to be valued at $3.5bn-$4bn, according to the company’s chief financial officer, Peter Van Driel.
In a recent call with journalists to discuss Adnoc Gas’ financial results for the full year and fourth quarter of 2025, Van Driel said Adnoc Gas expects to achieve a final investment decision on the Habshan 7 gas train project, which is designed to increase the company’s production of high-value liquids such as liquefied petroleum gas, naphtha and condensates, in the first quarter of 2026.
Adnoc Gas issued the main EPC tender for the new Habshan 7 gas train project to contractors between 5 and 8 August, MEED previously reported. It later extended the initial technical bid submission deadline from mid‑September to 6 October.
In April, MEED reported that Adnoc Gas had started an early engagement process with contractors for the EPC tendering phase of the Habshan 7 gas train project.
Prior to that, Adnoc Gas issued an expression of interest (EoI) document for the project in March, to which contractors submitted responses by 8 April.
Separately, Adnoc Gas also completed the EoI exercise for early civil and site preparation works on the Habshan 7 project in June, and is understood to have issued the main tender in the third quarter.
ALSO READ: Adnoc Gas stalls decision on Ruwais NGL project
https://image.digitalinsightresearch.in/uploads/NewsArticle/15663150/main5247.jpg -
Dubai seeks contractors for Jebel Ali STP expansion16 February 2026
Dubai Municipality has invited contractors to prequalify for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d).
The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.
The bid submission deadline is 2 April.
Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.
As MEED understands, the project is part of long-term plans to treat about 1.05 million cm/d a day once all future phases are completed.
The main element of the expansion, which is estimated to cost $300m, involves modifications to the secondary treatment process at Jebel Ali STP phase two.
This includes conversion to Moving Bed Biofilm Reactor or Integrated Fixed-Film Activated Sludge systems.
The project also includes decommissioning existing surface aerators. New blowers and associated works will be installed as part of the upgrade.
UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15661388/main.jpg -
AD Ports to develop Douala port in Cameroon16 February 2026
Abu Dhabi’s AD Ports Group and Africa Ports Development (APD) have signed an agreement to design, build and operate a new dry bulk terminal at the Port of Douala in Cameroon.
AD Ports Group will invest about AED320m ($87m) in the development of the terminal’s first phase, which will comprise two berths and more than 450 metres of quay wall, with an annual handling capacity of about 4 million tonnes of dry bulk cargo.
Construction is expected to begin this year, and the first phase is slated for completion in 2028.
The concession period is 30 years.
AD Ports Group has committed to long-term investments and operations across Africa, including in Egypt, Morocco, Tunisia, Kenya, Tanzania, Angola and the Republic of the Congo.
The latest announcement comes shortly after it signed an agreement with Jordan’s Aqaba Development Corporation (ADC) to manage and operate the Aqaba multipurpose port.
AD Ports will manage and operate the port under a 30-year concession agreement.
In December last year, AD Ports Group signed a shareholder agreement with Tajikistan’s private industrial firm Avesto Group to establish a new joint venture that will provide integrated logistics and freight forwarding services across Tajikistan.
Under the agreement, the joint venture will initially operate as an asset-light freight forwarder. It will have exclusive rights to consolidate and manage all freight and logistics activities across Avesto Group’s subsidiaries, while also offering services to third-party customers in the wider market.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15661385/main.jpg
