Oman expands grid connectivity

10 December 2023

Oman’s power and water sector has awarded an annual average of approximately $1.5bn-worth of contracts over the past 11 years – a relatively low value compared to the total awarded every year by some of its GCC neighbours.

However, 2023 can still be considered a good year for the sultanate, as contracts worth an estimated $1.2bn have been awarded.

This is an improvement on the performance of the previous two years, which saw very limited project activity within the sector, with contract awards valued at just $104m in 2021 and $244m in 2022.

Having adopted a policy to not procure further gas-fired thermal power plants, Oman awarded the contracts to develop its second and third utility-scale solar photovoltaic (PV) plants in early 2023.

The Manah 1 and 2 solar PV independent power projects (IPPs) each have a capacity of 500MW. Wadi Noor Solar Company, comprising France’s EDF Renewables and South Korea’s Korea Western Power Company (Kowepo), will deliver and maintain the Manah 1 solar IPP project for 20 years.

Another team, comprising Singapore’s Sembcorp Industries and China-headquartered Jinko Power Technology, will develop the Manah 2 IPP scheme. The country’s first utility-scale solar project, Ibri 2, became operational in 2021. 

Oman’s Ministry of Regional Municipalities & Water Resources also awarded a $108m contract for the construction of a flood protection dam in Wadi Ajay Gorge in Muscat in early 2023. The rest of the awarded contracts comprise water and power transmission pipeline projects across the sultanate.

Demand growth

Nama Power & Water Procurement Company (PWP), formerly Oman Power & Water Procurement Company (OPWP),  expects peak electricity demand for the main interconnected system (MIS), the sultanate’s main electricity grid, to grow by an average of 3.54 per cent annually from 2022 to 2029, reaching 8,350MW at the end of the forecast period.

Most of this growth is expected to occur in the near term, as the economy recovers from the effects of the Covid-19 pandemic, according to PWP’s most recent Seven-Year Statement, which covers the years 2023-29. It is also higher compared to the 2.5 per cent average annual peak demand growth rate seen between 2015 and 2022.

PWP’s low-case forecast scenario shows an average annual peak demand growth of 1.3 per cent, with the base growing from 6,628MW to just over 7,200MW. A high-case scenario, on the other hand, indicates an annual demand growth of 5.2 per cent, which can drive the demand to reach 9,430MW.

Annual peak demand growth in the smaller Dhofar grid is expected to average 5 per cent between 2022 and 2029.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November. The 400-kilovolt (kV), 670-kilometre (km) project required an investment of about $966m.

The first phase of Oman’s North-South Interconnection project, known as Rabt, became operational in November

The project enables the MIS, serving the northern half of the Oman grid, to connect with Nihada in Al-Dhahirah Governorate and Duqm Special Economic Zone (SEZ) in Al-Wusta Governorate.

Al-Wusta offers an optimal location for solar and wind projects, which the country aims to develop as part of its green energy ambitions.

Also part of Rabt's first phase, the isolated networks of Petroleum Development Oman and the Rural Areas Electricity Company (Tanweer) in Duqm SEZ, have been interconnected.

A second phase is being planned for Rabt. To be launched later this year, it will comprise a 500km, 400kV transmission line from Duqm to Dhofar.

Water requirements

Peak water demand in the MIS is expected to increase by an average of 2 per cent annually between 2022 and 2029, while peak water demand in Dhofar is expected to grow by an average of 7 per cent a year.

To meet the expected demand rise in the MIS, several independent water projects are being developed or planned. These include the Barka 5 scheme, which has a capacity of 100,000 cubic metres a day (cm/d) and is expected to come online in 2024. Ghubrah 3, which has three times as much capacity, is expected to be operational two years later.

A third project, a replacement capacity for the Barka zone of about 102,000 cm/d, is also expected to be added in 2024.

Future projects

In addition to the second phase of Rabt, Oman is in the early procurement phase of several solar and wind projects, in line with meeting demand growth and replacing expiring contracted capacity.

The power and water purchase agreement for the gas-fired Barka 2 independent water and power facility, for instance, expires in 2024, while the contract for the Barka 3 IPP expires in 2028.

KPMG Lower Gulf, a subsidiary of the Netherlands-based consultancy company, has been selected to provide financial advisory services to Nama PWP for the Ibri 3 solar IPP, which will have a capacity of 500MW. Ibri 3, along with the planned 100MW Jalaan Bani Bul Ali wind power project, will cater to the MIS.

Another key scheme being planned to connect to the MIS is Oman’s first waste-to-energy plant in Barkah. When complete, the facility is expected to treat 4,500 tonnes of municipal waste a day, produce 130MW-150MW of energy, and reduce the carbon footprint of Oman's landfills by 1.3 million tonnes annually.

For the Duqm grid, a 100MW wind IPP is being planned, in addition to a potential concentrated solar power plant. These plants are expected to become operational in 2026 and 2028, respectively. A 100MW wind project is also being planned for Dhofar, although there has been no fixed target for when it is expected to become operational.

In May, it was also announced that Oman Electricity Transmission Company is planning a second link to the GCC grid. The planned 400kV power transmission link is scheduled to start operations in the first quarter of 2026.

Hydrogen hubs

There are major plans to develop green hydrogen hubs in Duqm and Dhofar, in line with Oman's ambition to produce up to 1.25 million tonnes a year of green hydrogen by 2030.

The proposed projects will integrate renewable energy plants that will supply power to the electrolyser plants, which split water into hydrogen and oxygen, as well as the other units of the facilities.    

The government has so far awarded land concessions to international consortiums looking to develop integrated green hydrogen and ammonia facilities in the country.

The programme will have a potentially significant impact in terms of Oman’s future gross renewable energy capacity growth, with some of the earliest announced projects requiring several gigawatts of wind and solar power.

However, since most of the planned projects include captive renewable energy power plants, they will not necessarily affect the Omani utility companies' future capacity procurement plans. 

On the other hand, water demand may be affected as the electrolysis plants require pure water to be split into hydrogen and oxygen.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11354723/main.jpg
Jennifer Aguinaldo
Related Articles
  • Qatar’s new $8bn investment spices up global LNG race

    13 March 2026

     

    In the midst of the conflict between Iran and the US and Israel, which has spilled over into the GCC region, QatarEnergy has temporarily halted production of liquefied natural gas (LNG) in the country and declared force majeure on LNG shipments after its energy assets came under attack.

    When the fog of war clears, however, and the Strait of Hormuz reopens to oil and gas flows, the global economy will look to QatarEnergy to swiftly restore regular LNG cargoes in order to bring gas prices down from record highs.

    Beyond that short-term role, the recent $8bn investment the Qatari giant has committed to building two new LNG processing trains will also cement its position as a reliable long-term supplier, while further intensifying the race among global LNG producers to carve out larger market shares in an increasingly gas-hungry world.

    North Field West – a game changer

    The state-owned company has progressed from the front-end engineering and design (feed) phase to the engineering, procurement and construction (EPC) stage of its North Field West LNG project at pace.

    It awarded the main EPC contract for the scheme – covering two LNG processing trains with a total capacity of 16 million tonnes a year (t/y) – to a joint venture comprising France’s Technip Energies, Greece/Lebanon-based Consolidated Contractors Company (CCC) and Gulf Asia Contracting on 25 February.

    The contract, estimated to be worth $8bn, was awarded just a month after Japan-based Chiyoda Corporation won the project’s feed contract.

    Such a short interval between the feed and EPC phases for a project as large as North Field West LNG would typically be considered improbable. Industry sources suggest QatarEnergy may have been in discussions with Chiyoda and the Technip Energies-CCC consortium for at least a year regarding the feed and EPC contracts, respectively – particularly given the two-year gap between the project’s announcement in February 2024 and the start of the EPC phase.

    Chiyoda, Technip Energies and CCC are also involved in the first two phases of QatarEnergy’s $40bn North Field LNG expansion project. A consortium of Chiyoda and Technip Energies is executing EPC works on the North Field East project, which involves the construction of four LNG trains with a combined capacity of 32 million t/y, following the award of a $13bn contract in February 2021. Meanwhile, a Technip Energies-CCC consortium is carrying out EPC works on two 7.8 million t/y LNG trains as part of the North Field South project, having secured a $10bn contract in May 2023.

    More significant, however, is the speed with which QatarEnergy is advancing its strategic objective of reaching a total LNG production capacity of 142 million t/y by the end of the decade, from 77.5 million t/y at present.

    With all three phases of the North Field LNG expansion programme now under EPC execution – and North Field East scheduled for commissioning later this year – QatarEnergy appears firmly on track to become one of the world’s largest LNG suppliers over the long term, reinforcing Qatar’s economic future in the process.

    US domination

    While QatarEnergy is on course to increase its LNG production capacity by 83% by 2030 through the overall North Field LNG expansion programme, it is still some way behind the US, which is set to account for over half of the total global LNG liquefaction projects by 2030.

    There are 40 new-build and expansion LNG liquefaction projects planned or under way in the US, according to UK analytics firm GlobalData. Among these, two projects stand out.

    The first is the Rio Grande LNG production project, being developed by NextDecade in Texas, on the US Gulf of Mexico coast. Up to 10 processing trains are planned for the complex, the first three of which are in the EPC phase.

    NextDecade achieved the final investment decision on the fourth and fifth trains at the facility, estimated to cost $6.7bn each, in September and October last year. The company has awarded EPC contracts to build all five trains at the Rio Grande facility to US-based Bechtel.

    On the investments front, the overseas-focused energy investment vehicle of Abu Dhabi National Oil Company (Adnoc), XRG, acquired an indirect 11.7% stake in the first phase of the project from Global Infrastructure Partners (GIP), part of US asset manager BlackRock, in September last year. In February 2026, XRG entered into another transaction with GIP to raise its overall participation in the Rio Grande LNG project by acquiring additional 7.6% equity interests in trains four and five of the scheme.

    Additionally, as part of that transaction, another Adnoc Group subsidiary, Adnoc Trading, entered into a 20-year offtake agreement with NextDecade last year to purchase 1.9 million t/y of LNG from Rio Grande train four, on a free-on-board basis at a Henry Hub-indexed price. France’s TotalEnergies and Saudi Aramco are the other LNG offtakers for train four.

    Separately, the Commonwealth LNG facility in the US state of Louisiana has also received backing from Abu Dhabi. Expected to start operations in 2030, the facility is designed to produce up to 9.5 million metric t/y of LNG.

    Commonwealth LNG is a project of US-based alternative asset manager Kimmeridge Energy Management Company and Abu Dhabi’s sovereign wealth fund Mubadala Investment Company through their joint venture Caturus.

    Caturus was formed in August 2025 when Kimmeridge announced a rebranding that saw Commonwealth LNG and Kimmeridge’s upstream operations combined under a new integrated platform. At the same time, Mubadala acquired a 24.1% equity stake in Caturus, providing financial backing for the new entity to proceed with the Commonwealth LNG project.

    Also in August, Caturus awarded Technip Energies the contract for EPC works on the Commonwealth LNG project. The French contractor had previously performed the project’s feed work.

    Moreover, Aramco subsidiary Aramco Trading signed a 20-year agreement to buy 1 million metric t/y of LNG from the Commonwealth LNG facility in February, increasing offtake deals secured by Caturus to cover 8 million metric t/y of the project’s total planned output capacity.

    Positive outlook

    The growth in LNG production capacity in the US, as well as in wider North America, is driven by several factors, including abundant natural gas reserves, the shale gas revolution and advancements in hydraulic fracturing and horizontal drilling.

    While it might be a challenge for QatarEnergy to compete with US players in combined liquefaction capacity, its strength and success will lie in clinching long-term offtake deals with customers in Asia, where the bulk of global LNG demand growth is expected.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15954252/main3511.jpg
    Indrajit Sen
  • Bahrain opens bids for first solar IPP project

    13 March 2026

    Two companies have made offers for a contract to develop Bahrain’s first solar photovoltaic (PV) independent power project (IPP).

    Bahrain’s Electricity & Water Authority (EWA) opened bids for the Bilaj Al-Jazayer solar IPP project on 12 March.

    The bidders include Saudi Arabia’s Acwa, formerly Acwa Power, and UAE-headquartered Yellow Door Energy.

    The 150 MWac Bilaj Al-Jazayer solar IPP project will be Bahrain’s first grid-connected solar PV power plant developed under a public-private partnership (PPP) framework on a build-own-operate basis. It will be delivered as a long-term concession and is intended to come online by 2027.

    The proposed site covers more than 1 square kilometre, with the private sector responsible for end-to-end development, including financing, design, construction and operation.

    Last August, EWA held a market consultation event during which it outlined plans for the country’s first solar PV IPP. The main contract was then tendered in October.

    EWA said Yellow Door Energy’s proposal was “accepted with conditions”, but did not disclose further details.

    The local KPMG Fakhro is the financial consultant, the US’ WSP Parsons Brinckerhoff is the technical consultant, and the UK’s Trowers & Hamlins is the legal consultant.

    Bahrain’s clean energy targets, as set by its national plans, include 20% renewables by 2035, and net-zero emissions by 2060.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968088/main.jpg
    Mark Dowdall
  • DP World sees Red Sea port volumes rising as Hormuz shuts

    13 March 2026

    Register for MEED’s 14-day trial access 

    Dubai-based ports operator DP World is preparing for higher throughput at its Red Sea terminals as the Iran conflict approaches its second week, CEO Yuvraj Narayan said on Thursday.

    With the Strait of Hormuz effectively closed and tanker attacks escalating, shipping movements into Gulf ports have fallen.

    The disruption began after US and Israeli strikes on Iran, rattling energy and freight markets and cutting access through what is widely seen as the world’s most critical oil corridor.

    Since most major Gulf ports rely on the narrow Strait of Hormuz, the shutdown is weighing on regional trade flows.

    Narayan said Jebel Ali, DP World’s main hub in Dubai, has not suffered any infrastructure damage and is operating normally, but inbound vessel arrivals are down. Some cargo is still moving through terminals on the eastern side of the strait, he added.

    Ports in the UAE that sit outside Hormuz have limited headroom to absorb the shortfall. Khorfakkan can handle about 5 million 20-foot equivalent units (TEUs) and Fujairah under 1 million TEUs, which Narayan indicated would not be enough to offset lost volume from Jebel Ali or Abu Dhabi’s Khalifa Port.

    Jebel Ali alone processed 15.6 million TEUs last year, out of DP World’s 56.1 million TEUs globally.

    DP World is rolling out rerouting options and other operational measures to keep supply chains moving. Narayan said the company’s Red Sea assets, such as Jeddah in Saudi Arabia and Sokhna in Egypt, are likely to see increased traffic, though he did not quantify the additional volumes or specify cargo types.

    He cautioned that logistical and security risks remain elevated.

    Earlier this week, DP World announced record financial results for 2025, with revenue up 22% to $24.4bn and adjusted earnings before interest, taxes, depreciation and amortisation (Ebitda) up 18% to $6.4bn, delivering a 26.3% margin, as MEED reported.

    DP World said that this performance was driven by strong momentum across its ports and terminals and logistics business.

    The group’s gross throughput rose 5.8% to 93.4 million TEUs.

    Profit for the year increased 32.2% to $1.96bn, and operating cash flow grew 14% to $6.3bn.

    Return on capital employed increased to 9.9% in 2025, up from 8.9% in 2024, reflecting stronger earnings despite ongoing geopolitical and trade uncertainty.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968045/main.jpg
    Yasir Iqbal
  • Frontrunner emerges for Saudi sewage treatment project

    13 March 2026

     

    A consortium led by China’s Jiangsu United Water Technology has emerged as the frontrunner for a contract to build and upgrade two sewage treatment plants in Saudi Arabia, according to sources.

    The contract covers the North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11), part of the next phase of National Water Company’s (NWC) long-term operations and maintenance (LTOM) sewage treatment programme.

    The consortium comprising United Water, Prosus Energy (UAE) and Armada Holding (Saudi Arabia) offered “the lowest tariff” for the project, sources told MEED.

    It is understood that Turkey’s Kuzu has made the next-lowest bid.

    The development, estimated to cost about $211m, will have a combined capacity of about 440,000 cubic metres a day (cm/d).

    In February, MEED exclusively reported that six bidders were competing for the contract.

    The other companies that have submitted proposals include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • VA Tech Wabag (India)
    • Aguas de Valencia (Spain)

    LTOM11, also known as the North Western A Cluster, forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    The scheme is being procured on an engineering, procurement and construction (EPC) basis with a long-term operations component.

    The main contract was tendered last year, with an award initially expected by the end of 2025.

    It is now understood that NWC is preparing to offer the main contract in the second quarter.

    As previously reported, Saudi Arabia’s NWC is also evaluating five bids for package 12 of its long-term operations and maintenance (LTOM12) sewage treatment programme.

    Known as the North Western B Cluster, LTOM12 forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    In January, the same United Water-led consortium won the main contract for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).

    That project includes the rehabilitation and operation of nine sewage treatment plants located across the Hail, Qassim, Al-Jouf and Northern Borders provinces

    NWC is also preparing to tender a contract for the construction of 10 sewage treatment plants as part of package 14 of the programme.

    The final details of the Eastern A Cluster (LTOM14) package are being finalised, with a tender likely to be issued in March or April, sources told MEED.


    READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

    Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

    Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968035/main.jpg
    Mark Dowdall
  • Medina tenders Sikkah Al-Hadid PPP project

    13 March 2026

    Saudi entities including Al-Madinah Regional Municipality, in collaboration with the Ministry of Municipalities & Housing and the National Centre for Privatisation & PPP (NCP), have floated a request for proposal (RFP) notice for the development of the Sikkah Al-Hadid project.

    The project will be procured through build-own-operate-transfer contracts with a 50-year duration, using a public-private partnership (PPP) model.

    The deadline for bid submission is 23 June.

    The project will be located to the west of Medina on an 84,657-square-metre (sq m) site. 

    It includes a four-storey medical centre with a capacity of up to 200 beds and a shopping mall offering retail, food and beverage, and other entertainment facilities.

    In January last year, NCP asked firms to express their interest and prequalify for a contract to develop two mixed-use developments in Medina, which included the Sikkah Al-Hadid project and the Dhul Hulaifah project.

    The Dhul Hulaifah project will be built on a 30,112 sq m site located six kilometres from the Prophet’s Mosque. 

    The development will consist of a four-star hotel integrated with retail and healthcare facilities.

    MEED previously reported that Saudi Arabia had announced a P&PPP pipeline comprising 200 projects across 16 sectors.

    This pipeline aims to attract local and international investors and ensure their readiness to participate in the schemes tendered to the market.

    The initiative comes as the kingdom strives to increase the attractiveness of its economy and raise the private sector’s contribution to GDP.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968021/main.jpg
    Yasir Iqbal