Oil pipeline shutdown has cost Iraq $20bn

25 September 2024

Register for MEED's 14-day trial access 

Members of the Association of the Petroleum Industry of Kurdistan (Apikur) have said that the shutdown of the Iraq-Turkiye oil export pipeline (ITP) has cost Iraq $20bn, and are calling for the immediate resumption of exports through the pipeline.

Oil exports through the pipeline stopped after a Paris-based arbitration court ruled in favour of Baghdad against Ankara, saying the latter had breached a 1973 agreement by allowing Erbil to begin independent oil exports in 2014.

In a statement, the organisation said: “As world leaders gather in New York for the United Nations General Assembly, Apikur member companies call for the government of Iraq to engage with the Kurdistan Regional Government (KRG) and international oil companies (IOCs) to resolve outstanding issues and immediately restore exports through the ITP.”

Prior to the halt of exports through the ITP in March 2023, approximately 450,000 barrels a day of oil were sent from Iraq via Turkiye to international markets.

Apikur said that it was “encouraged” by recent comments by Iraqi Prime Minister Mohammed Shia Al-Sudani, when he said that the pipeline could be opened by the end of the year.

The organisation said: “Apikur member companies are prepared to resume exports, contingent upon reaching agreements that provide for payment surety for past and future exports, direct payment and preservation of commercial and economic terms.

“Should such agreements require modifications to existing contracts, Apikur member companies are willing to consider this if agreed between the government of Iraq, the KRG and individual IOCs.

“Apikur member companies agree with public statements made by the KRG that direct sales agreements between IOCs and Iraq’s SOMO offer the best option for resolving the current situation – those agreements should provide the IOCs with surety for payment through upfront payment, escrow arrangements or payments in-kind at Ceyhan Port.”

SOMO is the State Organisation for Marketing of Oil, an Iraqi national entity. 

Apikur said that Iraq and all stakeholders will gain approximately $1bn a month in revenue from oil sales and that a total of $20bn has been lost to all parties since the halt of ITP oil exports in March 2023.

Myles Caggins, a spokesperson for Apikur, said: “Apikur member companies call for formal tripartite meetings with government of Iraq and KRG officials to immediately restore exports through the Iraq-Turkiye Pipeline.”

He added: “With $20bn lost to all parties, including the people of Iraq, Apikur member companies seek mutually beneficial solutions and prompt follow-through action from the government of Iraq officials who have publicly stated that re-opening the Iraq-Turkiye Pipeline is a priority.”

The international companies that are members of Apikur are Norway’s DNO, UK-headquartered Genel Energy, London-listed Gulf Keystone Petroleum, Dallas-headquartered HKN Energy and Canada’s ShaMaran Petroleum.

Many IOCs have reported significantly lower revenues due to the pipeline closure and have had to make cuts to their workforces in the region.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12591778/main0902.jpg
Wil Crisp
Related Articles
  • Egyptian contractor wins Abu Dhabi Ramhan Island deal

    4 September 2026

    Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.

    The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.

    Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.

    The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.

    The development comprises two residential towers offering 187 residential units.

    The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.

    The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.

    Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.

    The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.

    Mohamed Alabbar launched the Ramhan Island development in May 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg
    Yasir Iqbal
  • Dubai sets deadline for Jebel Ali waste-to-energy PPP

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.

    The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.

    The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.

    The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.

    Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.

    It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.

    That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.

    The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.

    Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.

    In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.

    Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.

    The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation. 

    The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg
    Mark Dowdall
  • Egypt to invest $4.5bn in refinery upgrades

    4 September 2026

    Egypt is planning to invest $4.5bn in refinery upgrades, according to the country’s Minister of Petroleum and Mineral Resources, Karim Badawi.

    Egyptian refineries are operating at 80% of capacity compared with 66% two years ago, according to Badawi, who wants further increases in utilisation of existing facilities.

    “We aim to invest around $4.5bn to develop existing refineries and build new units to reduce imports and achieve self-sufficiency in refined products,” he said in a statement.

    In May, Egypt said that it had increased its fuel import budget by almost 40% for the 2026-27 fiscal year amid higher global prices driven by the Iran war, which started when the US and Israel launched an attack on Iran on 28 February.

    Brent crude prices are up about a third since the conflict started, trading at more than $90 a barrel for most of this month so far.

    Badawi said a decline in Egypt’s oil and gas production between 2021 and 2024 occurred because foreign companies were reluctant to invest in the country’s energy sector due to unpaid government debts.

    He said: “We have settled all the debt, which reached $6.1bn in June 2024. As a result, hydrocarbon exploration and production activity grew by nearly 20% this year.

    “We are now moving in the right direction to increase oil and gas output gradually.”

    Despite the ongoing push to develop projects in the country’s oil and gas sector, several key projects have seen significant delays in recent years.

    These include a $2bn hydrocracking complex package that forms part of the wider Assiut oil refinery upgrade project.

    Earlier this month, MEED revealed that mechanical completion of the hydrocracking package is now unlikely to be reached until early next year due to complications in the final stages of construction.

    The hydrocracking complex package has experienced extensive delays over several years.

    In April this year, Badawi called for work to accelerate on the Assiut oil refinery upgrade project, saying it is important for reducing the country’s spending on imported refined products.

    At the time, the oil ministry said the project was 88% complete, with trial operations planned by the end of the year.

    Assiut Oil Refining Company (ASORC), a subsidiary of state-owned Egyptian General Petroleum Corporation, is the project operator.

    France’s Technip Energies is the main contractor, performing engineering, procurement and construction work on the Assiut hydrocracking complex under a $2bn contract awarded by ASORC in February 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19353521/main.jpg
    Wil Crisp
  • North Field West platform bidders get extra time

    4 September 2026

     

    QatarEnergy has granted contractors additional time to prepare bids for a key tender for the engineering, procurement, construction and installation (EPCI) of large platforms for the giant North Field gas field in Qatari waters.

    The tender, issued earlier this year, forms part of the wider North Field West (NFW) project, the third and last phase of the state enterprise’s North Field liquefied natural gas (LNG) expansion programme.

    The core scope comprises the EPCI of four production deck modules (PDMs) and associated structures. The new PDMs will increase gas production from North Field reservoirs and provide additional gas feedstock for the NFW LNG development.

    QatarEnergy has set 15 September as the deadline for technical bid submissions, while commercial bids are due on 10 November, according to sources.

    The previous deadlines for submission of technical and commercial bids were 30 August and 25 October, respectively, MEED previously reported.

    The following contractors, among others, are understood to be bidding:

    • China Offshore Oil Engineering Company (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem (Italy)

    Before issuing the PDM tender, QatarEnergy awarded McDermott a contract for the EPCI of four offshore jackets that will also support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.

    North Field LNG expansion

    QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three giant projects are progressing.

    QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.

    QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.

    In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.

    Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.

    QatarEnergy took the final investment decision on NFW this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting (GAC) in February.

    Chiyoda carried out the front-end engineering and design (feed) work for the NFW LNG project.

    The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.

    In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and LPG.

    With all three phases now under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers over the long term.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19352006/main.jpg
    Indrajit Sen
  • Contractors prepare Dubai Metro Gold Line prequalifications

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Contractors are preparing to submit their prequalification statements on 7 September for a contract to build the new Gold Line as part of the Dubai Metro network’s expansion.

    Dubai’s Roads & Transport Authority (RTA) issued the request for qualification notice for the project in June, with an initial submission deadline of 17 August, as MEED exclusively reported.

    This followed the RTA’s invitation to contractors to express interest in building the new Gold Line in May.

    Dubai officially announced the launch of the new Gold Line in April.

    In a post on social media site X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, said the project will cost about AED34bn ($9.2bn).

    The Gold Line will increase the Dubai Metro network’s total length by 35%.

    The project is scheduled for completion in September 2032.

    The Gold Line will be a fully underground network covering more than 42 kilometres, with 18 stations.

    It will pass through 15 areas in Dubai, benefiting 1.5 million residents.

    The project is expected to provide connectivity to over 55 under-construction real estate development projects.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai and end at Jumeirah Golf Estates.

    It will connect to Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger line.

    The contractor will be responsible for the design and build of all civil works, electromechanical equipment, rolling stock and rail systems.

    The selected contractor will also be required to assist in the systems maintenance and operations during an initial three-year period.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the Dubai Metro Gold Line project.

    Stage one covers concept design, stage two covers preliminary design, stage three covers the preparation of tender documents, stage four encompasses construction supervision, and stage five covers the defects and liability period.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19350865/main.png
    Yasir Iqbal