No end in sight for Lebanon’s economic woes

12 June 2023

This package on Lebanon also includes:

> Political deadlock in Lebanon blocks reforms
> Lebanon moves to secure $150m solar financing
> Dar al-Handasah acquires Turkish consultant
> Eni and Total complete Lebanon gas deal

 

Experts remain pessimistic about the outlook for Lebanon’s economy as the crisis continues to worsen more than three years after it began in 2019.

The country only has a caretaker government and no president – and it is hard to see how it will implement the reforms the IMF says are needed.

On 8 June, IMF spokesperson Julie Kozack said: “Lebanon needs urgent action to implement a comprehensive economic reform programme to arrest the severe and deepening crisis and to allow Lebanon’s economy to recover.”

She added that the IMF was concerned that delays in implementing key reforms were keeping the economy severely depressed.

“We are concerned about irreversible consequences for the economy, especially for the poor citizens of Lebanon and the middle class,” she said.

Lebanon’s currency has weakened dramatically since the start of the country’s economic crisis, plunging much of the population into poverty.

In March, the Lebanese pound, officially pegged at 15,000 to the dollar, was trading at 100,000 against the dollar on the country’s parallel market, down from 1,507 before the economic crisis hit in 2019.

In May, a World Bank report stated: “The systemic failure of Lebanon’s banking system and the collapse of the currency have resulted in a large, dollarised cash-based economy.

“It not only threatens to compromise the effectiveness of fiscal and monetary policy, but also heightens the risk of money laundering, increases informality and prompts further tax evasion.”

In April 2020, the Lebanese government agreed with IMF staff to implement a series of reforms to end the crisis, but very few have been executed.

This is mainly due to the country’s ongoing political deadlock.

Lebanon has had no head of state since President Michel Aoun’s term ended at the end of October 2022, worsening the country’s political paralysis at a time when important policy decisions are needed to get the economy back on track.

According to the IMF, the economic outlook for Lebanon is highly uncertain and depends on policy actions taken by the authorities to carry out the agreed reforms.

Kozack said: “Timely implementation of these reforms is critical to end the current crisis and prevent a further deterioration in living standards of the people of Lebanon.”

She added: “Lebanon will need strong financial support from the broader international community and the financial needs of Lebanon over the next several years are very large given the magnitude of the economic crisis.”

Bailout prospects

While the IMF has said that Lebanon will need significant financial support from other countries to help it get through its economic crisis, it is unclear where that support will come from.

Nicholas Blanford, a non-resident senior fellow with the Atlantic Council’s Middle East programmes, says it is unlikely that Saudi Arabia will be willing to bail the country out financially as it has done in the past.

He said: “Saudi Arabia has pumped billions of dollars into Lebanon over the years, including helping with the reconstruction programme in the 1990s after the civil war. Saudi has also helped Lebanon financially through various economic slumps.”

The change of leadership in Saudi Arabia when King Salman came to the throne in 2015 led to a change in policy regarding financial bailouts for Lebanon, according to Blanford.

“It seems like Saudi feels that it got very little in return for its past investment in Lebanon due to the fact that Hezbollah remains a dominant force in the country politically and militarily.

“The Americans and the French have, for several years, been pressing the Saudis to show more interest in Lebanon as a pushback against Iranian influence, but, so far, they haven’t shown much interest.”

The Lebanese are keeping their fingers crossed that economically viable quantities of oil and gas are found, but there is also a huge amount of scepticism given the state of the political system here and the nature of the politicians
Nicholas Blanford, Atlantic Council’s Middle East programmes

In October last year, Lebanon and Israel agreed a deal to end a long-running maritime border dispute in the Mediterranean Sea, clearing the way for increased oil and gas exploration activity in Lebanese waters.

Following the deal, in May this year, it was announced that a consortium led by France’s TotalEnergies would start drilling for oil and gas off the country's coast at the beginning of September.

While it is possible that new hydrocarbon discoveries in Lebanese waters could help ease the country’s economic problems over the long term, it is doubtful that this would provide any benefit in the short term, according to Blanford.

“The Lebanese are keeping their fingers crossed that economically viable quantities of oil and gas are found, but there is also a huge amount of scepticism given the state of the political system here and the nature of the politicians themselves.”

Blanford believes that many Lebanese citizens are worried that if commercially viable quantities of hydrocarbons are found, they are ultimately only likely to benefit the country’s oligarchs rather than the general public.

Due to the wide range of severe political and economic problems that Lebanon faces, there is unlikely to be any improvement over the coming months unless common ground is found between the country’s rival political blocs.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10932005/main.gif
Wil Crisp
Related Articles
  • Saudi Arabia raises electricity tariffs

    26 October 2026

    Saudi Energy, formerly Saudi Electricity Company, has announced revised electricity tariffs, which will take effect on 1 January 2027. 

    The revised tariff schedule, published on the company’s official website, covers residential, commercial, industrial, agricultural, charitable and government customers.

    The largest percentage increase in consumption rates is 16.7%, for residential customers using up to 6,000 kilowatt-hours (kWh) a month. Residential customers will pay 21 halalas/kWh for monthly consumption of up to 6,000kWh, up from 18 halalas. For consumption above 6,000kWh, the rate will rise from 30 to 33 halalas/kWh, a 10% increase.

    The industrial tariff will increase by 15%, from 20 to 23 halalas/kWh. Commercial customers, private healthcare facilities and private educational facilities will pay 25 halalas/kWh, up from 22 halalas, for consumption up to 6,000kWh a month, and 35 halalas/kWh above that level, up from 32 halalas.

    Tariffs for charities and government customers will also increase. In addition to consumption-based charges, customers will pay a fixed monthly fee based on the capacity of their electricity meter. This replaces the previous separate charge for meter reading, maintenance and billing, with VAT applied to the revised tariffs. 

    Electricity investment

    The new tariffs coincide with changes to water consumption tariffs announced by the National Water Company, also effective from 1 January 2027.

    King Salman Bin Abdulaziz Al-Saud directed support measures following a proposal presented by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.

    This includes raising the minimum wage required for Saudi nationals to count as full employees towards private sector localisation quotas under the Nitaqat programme. 

    The tariff changes come as Saudi Arabia plans substantial investment in its electricity infrastructure. In September 2025, Saudi Energy announced plans to invest SR220bn ($58.7bn) in power infrastructure projects between 2025 and 2030.

    A June 2025 report by Fitch Ratings forecast negative free cash flow of about SR16bn a year over the period and rising leverage, reflecting the financial demands of the programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20924301/main.jpg
    Mark Dowdall
  • Dubai Municipality confirms AED3bn Tasreef drainage awards

    26 October 2026

    Dubai Municipality has confirmed it has awarded four contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.

    The projects will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. The works include constructing and extending main stormwater drainage lines with diameters of up to three metres.

    The four packages are part of Dubai’s AED30bn Tasreef programme, which aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.

    The contracts have been awarded to China State Construction Engineering Corporation (CSCEC) and three local firms: Arifco Group, Nael Construction & Contracting (NCC) and Detech Contracting. Dubai Municipality did not state which projects the awards relate to.

    According to sources, the contract awards include packages TF-15-C1, TF-15-C2 and TF-13-C1.

    The first package, TF-15-C1, involves the construction of 21 kilometres of main and secondary drainage lines along Al-Wasl Road and in surrounding areas. It will cover Za’abeel 2, Al-Wasl, Jumeirah 1 and 2, Al-Bada’a, Al-Satwa and Dubai World Trade Centre. The estimated $100m contract was awarded to Detech in July, as exclusively reported by MEED.

    The second package, TF-15-C2, covers the corridor between Sheikh Zayed Road and Al-Khail Road. It includes about 14km of main drainage lines serving Al-Quoz Industrial Areas 1, 3 and 4, and Al-Barsha 1. In July, MEED reported that CSCEC had won the engineering, procurement and construction contract for this project.

    The third package, TF-13-C1, covers Al-Marmoom, where 23km of drainage infrastructure will be developed. According to a source, Arifco has been awarded this contract.

    The final package covers Jumeirah and Umm Suqeim, where about 42km of main drainage lines will serve Umm Suqeim 1, 2 and 3; Umm Al-Sheif; Jumeirah 3; Al-Safa 1 and 2; and Al-Manara.

    In May, MEED reported that NCC had been awarded a contract to build a sewage and stormwater drainage system, DS-204. However, it is unconfirmed whether this relates to the same project.

    Earlier, in February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.

    These included two contracts awarded to Detech and one to CSCEC for stormwater drainage infrastructure. In addition, two consultancy contracts were awarded for the study and design of drainage systems in selected areas across the emirate.

    Cumulatively valued at AED2.5bn, the new projects will serve 30 vital areas, spanning approximately 430 million square metres and supporting an estimated population of three million residents by 2040.

    Previously, in April 2025, an earlier package of awards was announced under phase one of the Tasreef programme. The overall masterplan aims to expand Dubai’s rainwater drainage capacity by 700% by 2033.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20923924/main4827.jpg
    Mark Dowdall
  • Nakheel awards $259m Dubai Islands buildings contract

    26 October 2026

    Dubai-based master developer Nakheel, part of Dubai Holding Real Estate, has awarded local firm Parkway International Contracting a construction contract valued at about AED950m ($259m) for phases two and four of Bay Grove Residences on Dubai Islands.

    The package covers 617 residential units across eight buildings, ranging from one to four bedrooms, together with basement structures, infrastructure and community amenities including swimming pools, sports courts and fitness centres.

    Phase two comprises 360 homes across four buildings, with main construction scheduled for completion in late 2028.

    Phase four includes 257 homes across four buildings, with completion targeted for the second quarter of 2029.

    The award follows an earlier contract valued at about AED800m ($218m) awarded to local contractor Metac General Contracting Company for phases one and three, covering 537 homes across seven buildings.

    Together, the two contracts total more than AED1.75bn ($476m) and account for all 1,154 planned homes across the 15 buildings of Bay Grove Residences.

    Project activity on Dubai Islands has gathered pace in recent months. Earlier this month, Nakheel awarded local firm Mar Marine & Building Contracting a contract for marine and coastal works on Island B. The scope includes constructing breakwaters, removing existing rock revetments and creating a new 320-metre beach near the Bay Villas development, as well as remedial and refurbishment works along approximately 3 kilometres of the island’s western shoreline.

    In August 2025, Nakheel awarded Fibrex Contracting a AED2.6bn ($708m) construction contract for the Bay Villas residential project. That followed a AED527m ($143m) contract awarded to Al-Nasr Contracting Company in April 2026 for primary infrastructure and utilities on Island B.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20923389/main.jpg
    Yasir Iqbal
  • Morocco plans second high-speed rail phase to Agadir

    26 October 2026

    Morocco has outlined a second rail investment cycle for 2030-35, which includes beginning construction of a high-speed rail extension from Marrakech to Agadir and connecting Essaouira to the national rail network.

    The pipeline forms part of the government’s 2026-31 programme, presented to parliament last week.

    The Marrakech-Agadir link is estimated to cost close to MD55bn ($5.5bn) and will cover a 240-kilometre (km) route through the High Atlas Mountains via Chichaoua. Civil engineering structures, including tunnels and viaducts, are expected to account for nearly 70% of the alignment.

    In September, the government issued a decree declaring the Marrakech-Agadir and Chichaoua-Essaouira rail corridors to be of public utility, paving the way for land acquisition and expropriation procedures.

    Under the long-term masterplan Plan Rail Maroc 2040, Essaouira is expected to connect to the network via a separate line branching off at Chichaoua, designed for operating speeds of up to 200km an hour. The mainline to Agadir is designed for speeds of up to 320km/h.

    The 2030-35 cycle also includes rehabilitating the Casablanca-Khouribga-Oued Zem line; constructing a new line between Oued Zem and Beni Mellal via Bejaad, with a branch to Fquih Ben Salah; doubling and upgrading the 140km Benguerir-Safi line; expanding capacity on the Fez-Oujda corridor; and building new-generation passenger stations.

    The plans follow Morocco’s ongoing MD134bn ($13.4bn) 2024-30 rail investment programme, which focuses on completing the Kenitra-Marrakech high-speed line ahead of the 2030 Fifa World Cup.

    The programme also includes developing regional express network services across five regions, electrifying the Fez-Oujda line and completing a freight rail link to the Nador West Med port.

    Work on the Kenitra-Marrakech line had reached about 30% by May 2026, with commercial services targeted to begin in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20920349/main.jpg
    Yasir Iqbal
  • Riyadh tenders King Salman Stadium works

    26 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Sports Ministry has tendered a contract covering early works at King Salman International Stadium in Riyadh.

    The scope includes enabling works, site preparation and initial construction activities.

    The tender was issued on 11 October, with a submission deadline of 19 November.

    The stadium will cover about 660,000 square metres (sq m) and seat 92,000. Facilities will include a 150-seat royal suite, 120 hospitality suites, 300 VIP seats and 2,200 dignitary seats.

    The wider development will include sports facilities covering more than 360,000 sq m, including two training fields and fan zones; a closed sports hall; an Olympic-sized swimming pool; an athletics track; and outdoor courts for volleyball, basketball and padel.

    The stadium is set to host the final of the 2034 Fifa World Cup and will serve as the Saudi national football team’s main base.

    US-based architectural firm Populous is the lead architect for the stadium.

    Construction of the stadium is expected to be completed by 2029.

    The stadium will be located next to King Abdulaziz Park.

    Firms submitted prequalification statements for the main design-and-build contract in February.

    Saudi stadium plans

    In August 2024, MEED reported that Saudi Arabia planned to build 11 new stadiums and refurbish four facilities for the 2034 Fifa World Cup. 

    Eight stadiums will be located in Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom.

    A further 10 cities will host training bases: Al-Baha, Jazan, Taif, Medina, Alula, Umluj, Tabuk, Hail, Al-Ahsa and Buraidah.

    There are expected to be 134 training sites in the kingdom, including 61 existing facilities and 73 new venues.

    Saudi Arabia was officially selected to host the 2034 Fifa World Cup during an online convention of Fifa member associations at the Fifa Congress on 11 December 2024.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20919233/main.jpg
    Yasir Iqbal