New projects offer crossroads for utility developers
29 July 2024
Commentary
Jennifer Aguinaldo
Energy & technology editor
Following four lacklustre years, projects activity has rebounded for the region's conventional power generation sector.
At least five combined-cycle gas turbine (CCGT) plants with a total generation capacity of 14.7GW are under bid in four of the GCC states, excluding the 3GW-4GW of capacity being directly negotiated by Saudi Arabia's principal buyer, Saudi Power Procurement Company (SPPC), and Saudi Electricity Company.
However, the robust projects activity is being met with a dwindling number of bidders in some cases.
While four consortiums submitted bids in July 2023 for the contracts to develop the Taiba 1, Qassim 1, Taiba 2 and Qassim 2 independent power projects (IPPs) in Saudi Arabia, only one consortium submitted a bid on 25 July for the contract to develop Qatar's Facility E independent water and power project.
The main differentiator appears to be the presence, or absence, of a clause to deploy carbon-capture solutions during the lifecycles of the projects.
Some international developers require the inclusion of a serious carbon-capture provision for them to bid for future conventional power generation plants, the concession agreements for which usually extend 20-30 years, depending on the jurisdiction.
Given that the construction of a utility-scale conventional power plant usually takes an average of three years, a typical 25-year power-purchase agreement (PPA) implies contract expiry not earlier than 2052, overshooting most developers' 2050 net-zero targets.
SPPC has indicated that its under-construction CCGTs, and those that it plans to procure, will be carbon-capture-ready, which indicates an intention that such technology could be in place during the projects' contract duration.
Of the five CCGT schemes under bid, however, only Abu Dhabi's Taweelah C has so far required a provision for carbon-capture solutions and a shorter PPA, in line with the UAE's plan to reach net-zero carbon emissions by 2050.
The PPA for the Taweelah C IPP is expected to expire by 2049, making it several years shorter than usual.
State utility Emirates Water & Electricity Company has prequalified nine developers that can bid for the contract, the majority of which have existing and operational CCGT assets in Abu Dhabi.
There remains uncertainty about whether some international developers will decide to bid for the Taweelah C and other future contracts, as they try to reconcile their sustainable and commercial strategies.
The others see these as major opportunities to expand their presence and win long-term contracts vital to their commercial success after years of waiting for the established developers to step back.

Exclusive from Meed
-
-
Aldar launches Al-Ghadeer Gardens project19 May 2026
-
-
-
Emirates awards $5bn engineering complex deal18 May 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Construction advances on Riyadh King Salman airport19 May 2026
King Salman International Airport (KSIA) is advancing airside infrastructure works under its long-term expansion programme in Riyadh, including the delivery of a third runway and new private aviation facilities.
Construction activity on the central runway programme is progressing across several operational zones, with works covering excavation, grading, site preparation and taxiway-enabling infrastructure to support upcoming phases.
The third runway is intended to increase airfield capacity and cater to the airport’s future operational requirements.
In a separate development, KSIA has completed initial landside works for the private aviation apron, marking a milestone in the rollout of its executive aviation infrastructure.
The completed scope includes pavement markings, waterproofing systems, firefighting infrastructure chambers and final operational inspections to support readiness for the next stages.
KSIA has also secured General Authority of Civil Aviation (GACA) approval for phase one airside works, which includes the planned connection of Taxiway Alpha to the private aviation facilities, strengthening operational integration between executive aviation assets and airfield movement areas.
The packages form part of the wider KSIA masterplan, which covers about 57 square kilometres and supports Saudi Arabia’s objective of positioning Riyadh as a global aviation and logistics hub.
The airport aims to accommodate up to 100 million passengers by 2030.
Saudi Arabia plans to invest $100bn in its aviation sector. The Saudi Aviation Strategy, announced by GACA, aims to triple annual passenger traffic to 330 million travellers by 2030. It also targets air cargo growth to 4.5 million tonnes and an increase in total air connections to more than 250 destinations.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16906496/main.jpeg -
Aldar launches Al-Ghadeer Gardens project19 May 2026
Abu Dhabi-based real estate developer Aldar Properties has launched the Al-Ghadeer Gardens project, located on the Abu Dhabi-Dubai border.
The new residential development will feature 437 villas and townhouses, offering two-, three- and four-bedroom homes.
Al-Ghadeer Gardens will include more than 30,000 square metres of landscaped open space, supporting a pedestrian-friendly layout and outdoor-focused living.
As part of its sustainability and wellbeing approach, the project is targeting Estidama Pearl 2 and Fitwel 2-star certifications.
Earlier this month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).
Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.
UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.
The group attributed its performance to revenue from its development backlog and steady income from its investment properties.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16906154/main.jpg -
Iraq trucks oil from the south to Kurdish pipeline19 May 2026

Iraq is trucking crude from Basra to the north of the country to be exported via the Iraq-Turkiye Pipeline (ITP), according to industry sources.
The oil is being loaded into trucks at fields in Basra before being driven to the north, where it is injected into the pipeline network at Khurmala Dome, in the northern section of the Kirkuk field.
Once it has entered the network at Khurmala Dome, it is transported to the main ITP export pipeline and eventually to the port of Ceyhan in Turkiye, where it can be loaded onto ships.
The volumes of crude being transported using trucks have surged in Iraq since the US and Israel attacked Iran on 28 February, starting a regional conflict that has disrupted shipping through the Strait of Hormuz.
One source said: “Most of the crude that is being trucked out of Iraqi oil fields at the moment is going to Syria, but some is being trucked to the north where it is being funnelled through the pipeline.”
Even with the additional volumes being trucked from the south, Iraq is struggling to boost exports using the ITP.
At the end of March, Amer Khalil, the director-general of Iraq’s state-run North Oil Company, said that Iraq was exporting 200,000 barrels a day (b/d) through the ITP.
At the time, he said that the pipeline, which runs from Kirkuk in Iraqi Kurdistan to the port of Ceyhan in Turkiye, was expected to start transporting 300,000 b/d “in the near future”.
As of early May, the pipeline was still exporting about 200,000 b/d, despite having a nameplate capacity of 1.4 million b/d.
One of the factors said to be stopping increased volumes from being shipped through the pipeline is that several key oil fields in northern Iraq evacuated staff and stopped production after the US and Israel started their war with Iran.
Another factor is that Iraq has not invested in domestic pipeline infrastructure to pipe production from Basra to Kurdistan, where it could be exported via the Kurdish ITP route.
READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDFGlobal energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.
Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:
> REGIONAL LNG: War undermines business case for Middle East LNG> CAPITAL MARKETS: Damage avoidance frames debt issuance> MARKET FOCUS: Conflict tests UAE diversificationTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16902345/main1824.jpg -
Kuwaiti oil services company secures credit facility19 May 2026
The Kuwaiti drilling and oilfield services provider Action Energy Company (AEC) has secured a new credit facility and renewed and expanded an existing facility in order to support the company’s rig fleet expansion.
The new facility and the expansion were obtained from two Kuwaiti banks and had a combined value of KD40.9m ($132.8m).
In its statement, AEC said that the facilities support the financing and deployment of new rigs linked to contract awards previously announced with the state-owned upstream operator Kuwait Oil Company (KOC).
The company added: “They further reinforce AEC’s financing structure and strengthen its ability to execute its contracted fleet expansion plan through 2026 and beyond, while maintaining a disciplined approach to capital allocation.”
The new credit facility was obtained from Kuwait International Bank (KIB).
It is worth KD7.3m ($23.7m) and will finance two new 750-horsepower (HP) rigs.
The renewal and expansion of the existing facility is worth KD33.6m ($109.1m) and was obtained from Commercial Bank of Kuwait (CBK) to finance four new 1,500 HP rigs and one 1,000 HP rig, in addition to the renewal of the existing facilities.
AEC announced its financial and operational performance for the first quarter earlier this month.
The company reported a net profit of KD2.2m ($7.1m).
The company’s revenue grew by 69.2% year-on-year, primarily driven by the expansion of the operating rig fleet from 13 rigs in the first quarter of 2025 to 20 rigs in the first quarter of 2026, including the full-quarter contribution of 10 new rigs deployed during 2025.
The company is benefitting from a substantial multi-year contracted backlog with KOC.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16902234/main.jpg -
Emirates awards $5bn engineering complex deal18 May 2026
Register for MEED’s 14-day trial access
Emirates Airline has awarded a AED19bn ($5bn) contract to build one of the world's largest engineering complexes in Dubai South.
The contract was awarded to Beijing-headquartered China Railway Construction Corporation (CRCC).
CRCC is being supported by French firm Artelia, as the project consultant.
The complex will cover over 1 million square metres (sq m).
It will comprise 77,000 sq m of dedicated workshop space for maintenance and repairs, 380,000 sq m of storage and logistics capacity, a 50,000 sq m administrative building for Emirates Engineering and 15,000 sq m of training facilities.
It will be the world's only complex with a capacity to service 28 wide-body aircraft simultaneously.
The airline officially broke ground on the project on 18 May.
The groundbreaking ceremony was attended by Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and CEO of Emirates Group; Tim Clark, president of Emirates Airline; Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai South; and Dai Hegen, chairman of CRCC.
The facility will enable large-scale retrofits, cabin redesigns and structural modifications to be performed in-house, thereby reducing turnaround times.
The engineering complex is scheduled for completion in 2030 and will be located at Al-Maktoum International airport.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16895218/main.jpg