Neom’s top five projects

11 October 2023

Neom has awarded major contracts over the past two years, indicating the kingdom's flagship development project is moving ahead as planned. It has also attracted local and international investment partners for the implementation of these projects.

Except for the Neom Green Hydrogen project, the majority of the contracts that have been awarded so far are for basic infrastructure such as roads, staff accommodation and utilities.

Below is a round-up of the top five projects that are under construction at Neom.

  1. NGHC Green Fuels Renewable Energy Project

Saudi Arabia’s Neom Green Hydrogen Company (NGHC), a consortium of Neom, Saudi utility developer Acwa Power and the US' Air Products is developing a green fuels renewable energy facility, which will produce hydrogen to be synthesised into carbon-free ammonia for export exclusively by Air Products to global markets.

The planned facility will integrate 4GW of renewable power from solar, wind and storage that will be used for the production of 650 tonnes a day of hydrogen and nitrogen and 1.2 million tonnes a year of green ammonia.

In June 2022, Indian contractor Larsen & Toubro (L&T) secured a major engineering, procurement, and construction (EPC) contract worth $2.7 billion from NGHC for the renewable energy package of the programme.

L&T has since awarded several sub-contracts for different elements of the project. These include the supply contract for the wind turbines to China's Envision Energy, the supply of 380 kV gas-insulated substations to US-based GE Grid Solutions, the supply of solar trackers to Spanish PV Hardware and, most recently, the contract to inverter skid solutions to Chinese company Sungrow.

  1. NEOM Community Villages: Wave 1

In June, Neom finalised SR21bn ($5.6bn) of public-private partnership (PPP) housing deals for worker accommodation. The developers for the first phase of its residential communities, also known as Wave I, include local companies Alfanar Global Development, Almutlaq Real Estate Investment Company, Nesma Holding Company and Tamasuk, which is involved through two separate partners, Al-Majal al-Arabi Group Company and Saudi Arabian Trading & Construction Company (Satco).

The scheme involves building ten communities across Neom, adding capacity for 95,000 more occupants once the project's first phase is completed. The temporary accommodation needed during Neom's construction period is being built sustainably as relocatable modular units that can be repurposed once the communities are no longer required.

The tender for a second phase of the project, known as Wave II, is expected to be issued to the market in the coming months.

 

  1. NEOM Backbone Infrastructure: Drill and Blast Running Tunnels

Tunnel projects worth over $4.6bn are in the execution phase at Neom. These include the backbone infrastructure tunnels for The Line project, which involve constructing two railway tunnels in parallel using the drill-and-blast method, one for passengers and the other for goods.

In June 2022, Neom awarded $2.7bn-worth of main contracts to the joint venture of Shibh al-Jazira Contracting, China State Construction Engineering and FCC Construction for lots two and three of this scheme.

A separate contract worth about $1.8bn was awarded by Neom for lots four and five to a team of Archirodon, Samsung Engineering and Hyundai Engineering.

Beijing-based China Railway Construction Corporation (CRCC) was awarded a contract in 2021 for the adits and portals package serving the bored tunnels.

  1. NEOM Oxagon Connector South

In May, Neom awarded a joint venture of Italy-based Webuild and Riyadh-headquartered Shibh al-Jazira Contracting (Sajco) an estimated $2bn contract to build the Connector South rail line that will link Oxagon with The Line at Neom.

The contract involves the construction of a 75-kilometre railway line, including earthworks, 14 viaducts, seven roads, nine rail underpasses, 152 culverts (pipe and box culverts), a freight line, infrastructure maintenance depots and associated facilities.

The infrastructure corridor will run south from The Line to Neom City Station through Neom Bay Mansions, Neom Bay airport and on to Oxagon.

  1. NEOM Oxagon Port

Crown Prince Mohammed bin Salman launched Oxagon in late 2021. It includes onshore elements as well as floating structures offshore. Construction works on the 48 square-kilometre, eight-sided industrial city have already started.

In January, Neom awarded a contract to deliver the first phase of the port expansion. A team of Boskalis, Besix and the local Modern Building Leaders (MBL) was awarded that estimated SR3bn ($800m) contract in mid-January.

It was followed by another $1bn contract award in October to Belgium’s Deme with Greece’s Archirodon to complete phase two of the Duba port expansion at Oxagon industrial city.

The scope of the Duba port expansion package includes excavation and dredging, revetments for channel widening, demolition, container terminal quay expansion and earthworks, in addition to the development of a flexible quay, a roll-on/roll-off (RoRo) berth and quay walls to a marine services berth and a coast guard facility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11209234/main.jpg
Yasir Iqbal
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal