Neom to tender hydropower contract

29 October 2024

 

Register for MEED's 14-day trial access 

Neom's utility subsidiary Enowa is expected to issue the request for proposals (RFP) for a contract to develop and operate the first phase of a pumped hydropower storage (PHS) network catering to Saudi Arabia's Neom gigaproject before the end of the year.

The planned first phase of Neom’s PHS project, known as Nestor, will have an installed capacity of 2,200MW and a storage capacity of 23.1 gigawatt-hours, or about 11 hours, according to industry sources.

Enowa received statements of qualifications from international and local developers and investors on 30 June.

However, it has yet to release the prequalification evaluation results. 

"As far as we know, the RFP is set to be issued some time in December this year," a source familiar with the project tells MEED. 

The Nestor project will be developed using a build-own-operate-transfer model that is expected to cover 40 years, excluding the construction period.

The expected capital expenditure for the project is $2.7bn.

Enowa received expressions of interest in bidding for the project from developers and contractors in January this year.

PHS network

The overall infrastructure will involve developing four PHS stations in Neom. The planned schemes will form the backbone of an energy storage infrastructure at the SR1.5tn ($500bn) development. 

The other three planned PHS projects will be located in Al-Qimmah, Nima and Beach Mountain, and will have capacities of about 3,000MW, 1,000MW and 3,000MW, respectively.

UK-based HSBC and US-based White & Case are advising the client on the scheme.

The PHS independent power project will complement Neom’s planned multi-gigawatt renewable energy infrastructure, in line with its vision of being 100% powered by renewable energy by 2030.

A PHS facility typically comprises two water reservoirs at different elevations that can generate power when water passes through a turbine and moves down or is discharged from the upper reservoir to the lower reservoir.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12812234/main.jpg
Jennifer Aguinaldo
Related Articles
  • IHC deepens India links with $11.5bn aluminium venture

    3 July 2026

    Abu Dhabi’s International Holding Company (IHC) has struck its third major partnership with India’s Adani Group in a year, signing an agreement to co-develop an $11.5bn greenfield aluminium complex in the eastern Indian state of Odisha.

    Under a memorandum of understanding signed with the Odisha state government on 2 July, Adani Enterprises (AEL) and International Resources Holding (IRH), the natural resources investment platform IHC operates through its 2PointZero subsidiary, will form a 50:50 joint venture to build an integrated alumina and aluminium complex. The project comprises a 4-million-tonne-a-year (t/y) alumina refinery, a 2 million t/y aluminium smelter, a 4,000MW captive power plant and a 1 million t/y downstream manufacturing park.

    The deal marks Odisha’s largest foreign direct investment proposal to date and what the partners describe as India’s largest single foreign investment in the metallurgy sector. It is expected to create about 53,500 jobs, split between roughly 35,000 during construction and 18,500 in ongoing mining, refining, smelting and manufacturing operations once the complex is running.

    The tie-up extends a fast-growing relationship between IHC and Adani that began with a renewable energy joint venture between IHC subsidiary ePointZero and Adani Green Energy earlier this year. For IHC, which has built a $233bn portfolio spanning more than 1,300 subsidiaries across technology, infrastructure, financial services and consumer sectors, the Odisha project deepens a strategy of using IRH as a vehicle to secure positions across the minerals value chain underpinning the energy transition, moving beyond passive investment into direct industrial development.

    Odisha holds some of India’s largest bauxite reserves and is already a significant alumina and aluminium producer. State officials cast the project as central to plans to position the region as a global manufacturing hub, tying it to the state’s Samruddha Odisha 2036 development programme and the national Viksit Bharat 2047 agenda.

    The project will proceed in two phases. Following the MoU signing, AEL and IRH said they would move to land acquisition, statutory approvals and infrastructure planning alongside the Odisha government.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17539363/main.png
    Colin Foreman
  • Contractor wins Qiddiya Speed Park package deal

    3 July 2026

     

    Riyadh-based contractor El-Seif Engineering Contracting has won a contract to build the Exclusive Viewing Lounge (EVL) project in Qiddiya Entertainment City.

    Saudi gigaproject developer Qiddiya Investment Company (QIC) awarded the contract.

    The EVL comprises a four-storey structure designed for race-day viewing and guest hospitality. It will include dedicated spectator viewing areas, indoor lounge spaces, guest amenities and back-of-house service areas to support operations.

    Local firm Ammico Contracting carried out the project’s enabling works.

    The EVL is part of the Speed Park project at Qiddiya, which El-Seif Engineering Contracting and UAE-based Alec are jointly executing, as previously reported by MEED. The wider scope includes the construction of buildings around the racetrack.

    The racetrack is being delivered by local United Maintenance & Contracting Company (Unimac). In February 2024, MEED exclusively reported that QIC had awarded an estimated SR1.8bn ($480m) contract for the racetrack and associated infrastructure at Qiddiya’s Speed Park.

    The contract scope includes the track build and all infrastructure works, including electrical networks, storm drainage systems, water and sewer networks, landscaping, and associated underground and above-ground structures, along with related civil works.

    The Speed Park is being built around a Federation Internationale de l’Automobile (FIA) Grade 1 racetrack as part of the resort core in Qiddiya Entertainment City. Once complete, the circuit will be capable of hosting Formula 1 Grand Prix and motorcycling MotoGP races. 

    The Speed Park is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, the Prince Mohammed Bin Salman Stadium, a horse race venue, a performing arts centre, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    The project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17538940/main.jpg
    Yasir Iqbal
  • Local contractor wins DIFC tower contract

    3 July 2026

    Dubai-based contractor Al-Basti & Muktha has been awarded a contract to build the DIFC Heights Tower mixed-use development.

    The state-backed Dubai International Financial Centre (DIFC) awarded the contract.

    The project comprises a 43-storey building with 366 residential units, office space, and retail and food-and-beverage outlets. Construction is expected to commence shortly, with completion slated for 2029.

    Enabling works are under way and are being undertaken by Germany’s Bauer.

    Lebanese engineering firm Dar Al-Handasah is the lead and supervision consultant, while UAE-based Time is the project manager. Canadian engineering firm AtkinsRealis is the architect and concept designer, and local firm Omnium is the cost consultant.

    In a statement, DIFC said the project is being developed on the final remaining plot within its original land bank in the Gate District.

    Earlier this year, Dubai announced a AED100bn ($27bn) expansion of DIFC through the creation of the DIFC Zabeel District. A statement from the Government of Dubai Media Office said the new district will add more than 7 million square feet (sq ft), bringing total gross floor area to 17.7 million sq ft.

    The Zabeel District is expected to more than double DIFC’s capacity to more than 42,000 businesses, support a workforce exceeding 125,000, and allocate more than 1 million sq ft for future technologies and artificial intelligence. Planned in six phases, the expansion is scheduled to open to the public in 2030, with the masterplan due for completion in 2040.

    A bridge will link the DIFC Zabeel District to the existing DIFC Gate District.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17538278/main.jpg
    Yasir Iqbal
  • Iraq and Turkiye discuss oil pipeline deal

    3 July 2026

    Turkiye’s Energy Minister Alparslan Bayraktar has met with senior Iraqi oil and foreign ministry ‌officials to discuss energy cooperation, including on the Iraq-Turkiye Pipeline (ITP) that runs from Kirkuk to Ceyhan, according to a statement.

    In a post on social media, Bayraktar said that Turkiye aims to work closely with the new Iraqi government on more effective use of existing energy infrastructure.

    The decades-old agreement, which governs crude oil exports through the ⁠pipeline, is due to expire on 27 ​July.

    Baghdad and Ankara are still ​discussing a new draft agreement.

    Turkiye is ​also seeking ​to support ⁠existing infrastructure with new connections, Bayraktar said.

    Baghdad last month asked ​Ankara to extend the pipeline agreement ​for ⁠at least a year to allow time for more talks, but Ankara said ⁠it ​does not want an extension ​under current conditions.

    If the existing pipeline deal expires without Turkiye agreeing to an extension, it would be a major blow to Iraq, which has recently seen a large drop in crude exports due to disruption to shipping through the Strait of Hormuz.

    At the moment, in addition to transporting oil from northern Iraq, the ITP is also transporting crude from southern Iraq, which is brought to the north by truck and then injected into the pipeline network.

    At the end of March, Amer Khalil, the director-general of Iraq’s state-run North Oil Company, said that Iraq was exporting 200,000 barrels a day through the ITP.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17538073/main.jpg
    Wil Crisp
  • Oman begins procurement for truck road PPP

    2 July 2026

     

    Oman’s Ministry of Transport, Communications & Information Technology (MTCIT) has tendered a contract for the sultanate’s second public-private partnership (PPP) road scheme.

    The project spans 66 kilometres between Al-Buraimi and Al-Dhahirah governorates, starting at the Al-Khatm border crossing in Mahdah and ending at the Al-Fath area in Dhank.

    Under the scheme, the winning bidder will design, build, finance and transfer the project, which is specially designed for heavy vehicles.

    MTCIT issued the tender on 30 June. The deadline to purchase tender documents is 11 August, and the clarification period will run from 11 to 18 August.

    The bid submission deadline is 30 January 2027.

    In August 2023, Oman shortlisted five of the eight prequalified teams to compete for the Salalah-Thumrait truck road (STTR) project, the sultanate’s first PPP road project.

    The project failed to materialise beyond that point.

    In January, MEED reported that Oman is planning to establish a new commercial railway line to transport essential supplies between Salalah and Thumrait – an initiative understood to have preceded the STTR project. The railway is planned to be implemented as a PPP.

    The scheme comprises the construction of a railway line approximately 150-170km long. Two main stations are planned: Salalah Station, near the port and food storage facilities, and Thumrait Station, which will serve as a distribution hub for the surrounding areas.

    Trains are expected to be equipped with refrigerated and dry containers. The scheme aims to reduce transport costs between the two areas by 20%-30%, and Oman plans to pitch the project to major food companies to secure long-term transport contracts.

    The proposed project timeline is:

    • 2025: Conduct economic, technical and environmental feasibility studies
    • 2026: Launch the project for investment on a PPP basis
    • 2027-30: Construction of the railway line
    • 2031: Trial operations
    • 2032: Full commercial operations

    The project is touted as a key initiative under Oman Vision 2040, which aims to transform the sultanate into a global logistics hub.