Neom to fix construction

25 April 2023

 

The global construction industry is in a parlous state. Construction companies typically operate with low single-digit margins if they are doing well, and one bad project could mean they join a growing list of bankruptcies. 

Developing the world’s largest project may seem like a step too far against this backdrop, but for David Heron, Neom’s director of industrialised design and construction, the scale of development at the $500bn Saudi gigaproject offers the scope and continuity required to solve the industry’s problems.

“There is a general recognition within the industry that it is broken. The challenge has been that individual companies are too small to have the required level of impact to change the industry,” says Heron. 

“Neom is a unique opportunity because of its scale, in terms of spending and the longevity of the project. It will be able to build up the evidence base that demonstrates that things can be done differently.”

Neom has grand ambitions as it sets about transforming the construction industry. “We want to achieve 30 per cent reductions in cost, speed and time, and we think we can go beyond that,” he adds.

World’s largest piling project shifts to The Line’s marina

Improving efficiency

The key to unlocking those efficiency improvements is integrating the design and the construction processes. “When we say design and construction, most people think construction, but we are constantly trying to shift the conversation back to design,” says Heron.

Before design work can start, the brief has to be clear. “The starting point is understanding what people want, and most construction projects today are too small to warrant that kind of investment.

“You need to do market research to really understand what you want, so what happens in most construction projects is that 40 per cent of the design spend goes on during the course of construction as people figure out what it is they actually wanted to build,” says Heron.

“If we understand more clearly what we are designing, we can deliver it more efficiently. We call that an end-to-end process, or industrialised design and construction, because we are industrialising both the design process and the delivery. 

“We would even love to not use the word construction because it is really much more about manufacturing and assembly. When you say construction, people think concrete blocks and mortar. We are trying to shift away from that.” 

The proposed shift requires moving construction activity off-site and rethinking how projects are delivered. “It is completely rethinking the whole process for understanding what we are trying to create, as an experience.

“The starting point for Neom is that we are the investor, so it is incumbent on us to be clearer about what we want,” he adds. 

“When we start thinking about the design process, we need to be clear. We will probably be much clearer than on many other projects about who the target population is and what the experiences are that we want to create for that population.”

Neom will build up the evidence base that demonstrates that things can be done differently
David Heron, Neom 

Manufacturing approach

Heron explains that manufacturing environments are far safer and provide higher-quality jobs with more diversity. 

Gender diversity has been easier to achieve in the manufacturing environment than on the construction site. Quality control is also easier in a manufacturing environment, as it can be monitored from both a process and product perspective. 

For a manufacturing approach to work, different processes must be adopted from the beginning of the architectural design process.

“Typically, it is the general contractor that starts to think about how the site is organised. If we are going down a prefabricated route, you start to think about it at the beginning. Logistics becomes an issue for architects because the access to the site influences the way we design buildings,” says Heron.

Innovation is essential to Neom’s vision of transforming the industry. “If we are going to transform the industry, the opportunity is absolutely massive. We are not talking about incremental innovation, we are talking about fundamentally transformative innovation, and we want that to be done here at Neom,” Heron says.

“Because of the scale of Neom, there is a massive economic return on investing in innovations that just do not exist outside of Neom,” he adds.

The benefits are not just financial. In the modern world, construction has come under pressure for its carbon emissions, and while it is developing large projects, Neom is reducing the impact on the environment. 

“Thirty-eight per cent of global carbon dioxide emissions come from building, and 40 per cent of what goes to landfill is construction and demolition waste. Something like 70 per cent of all the embodied carbon in a building is from the concrete. 

“We are building big buildings, so one of the very first things we did two years ago was to look at how we can significantly reduce emissions from concrete, and there is a whole host of levers that we are pulling,” says Heron.

“We are working closely with local industry. On the cement side, we are looking at different cement mixes, looking at using alternatives to clinker, looking at Neom-specific concrete mixes that maximise the use of locally available materials, and we have minimised the logistics. 

“We are also looking at design and challenging the engineers that are designing buildings. We see that as a massive opportunity. Everyone talks about construction, but really the opportunities lie in design.” 

https://image.digitalinsightresearch.in/uploads/NewsArticle/10786799/main.gif
Colin Foreman
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp