Neom to award Gayal wind farm in Q2
12 February 2024

Register for MEED's guest programme
Enowa, a fully owned subsidiary of Neom, will likely award the engineering, procurement and construction (EPC) contract tender in the second quarter of this year to build the Gayal wind farm on a turnkey basis in Saudi Arabia’s Tabuk province.
Bid submission was initially expected on 29 January. However, the date has been extended to 3 March.
The project site is approximately 35 kilometres northwest of the former town of Gayal.
The project will have an estimated plot area of 164 square kilometres and is expected to have a capacity of 1,200MW.
The project duration is 31 months from the start date of construction.
The scope of work for the EPC contractors includes the design, supply and installation of wind turbine generators and foundations, three 380kV substations and control systems, meteorological towers, site roads, hard stands, crane pads and associated infrastructure.
According to MEED’s sister site Power Technology, the top four onshore wind power plants in development in Saudi Arabia are:
- Neom green hydrogen wind project: 1,370MW
- Yanbu wind IPP: 700MW
- Al Ghat wind IPP: 600MW
- Waad Al Shamal wind IPP: 500MW
MEED previously reported that Enowa is expected to seek developers’ interest in bidding for the first-phase packages of its renewable energy programme by early 2024.
The first-phase projects are expected to have a capacity of up to 3,000MW.
According to a source close to the project, discussions are ongoing regarding the total number of packages for the first-phase projects, which will include both wind and solar photovoltaic (PV) schemes.
MEED has reported that up to 55,000MW of renewable energy projects are being planned by Neom, which expects to be powered 100% by renewable energy by 2030.
Neom is understood to have appointed SMBC Advisory Services as financial adviser for the first phase of its renewable energy procurement programme.
It will work with Boston Consulting Group, the project’s strategy adviser.
In addition to hosting greenfield residential and tourism hubs, the $500bn Neom gigaproject in northwest Saudi Arabia will also host industrial facilities such as the $8.5bn green hydrogen-based ammonia production complex and water desalination plants.
100 per cent renewable
Before 2030, Neom will source power from the country’s electricity grid to complement energy generated from the first renewable plants catering to the development.
“We aim to start with roughly 50% renewables on day one,” Thorsten Schwarz, grid technology and projects executive director at Neom, told the Middle East & Africa Energy Week organised by Germany’s Siemens Energy in June 2022.
“We are looking at energy deliveries between 2024 and 2025. In the first few years, we will be working with all potential energy sources including … importing from the surrounding environment for energy including from Saudi Electricity Company,” the executive added.
In March last year, Germany’s ILF Consulting Engineers announced that it had been appointed as the consultant for the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined total capacity of 30GW.
MEED later confirmed that the schemes are “related to a major project in northwestern Saudi Arabia”.
The same month, MEED reported that Spanish consulting and engineering firm Typsa would undertake the preliminary studies for three utility-scale solar plants being developed to supply power to Neom.
The solar projects will be located in Hasma, Sharifa and Airport West, according to the company’s newsletter.
The proposed power plant will cover an area of 10,000 hectares and has a total combined capacity of approximately 5,000MW.
Typsa indicated that the client is Enowa, Neom’s energy, water and hydrogen subsidiary.
Earlier this month, Enowa appointed France-headquartered Assystem to conduct pre-development studies for seven planned solar PV parks in the Tabuk and Duba regions in Saudi Arabia.
The sites earmarked to host the solar PV parks stretch across 420 square kilometres, with 65% of land use yielding 20GW in energy generating capacity.
Exclusive from Meed
-
Dubai seeks consultants to develop drainage strategy18 March 2026
-
Oman awards power purchase agreements18 March 2026
-
DP World awards Jafza warehouse construction deal18 March 2026
-
-
Jabal Omar plans next phase of its Mecca development18 March 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai seeks consultants to develop drainage strategy18 March 2026
Dubai Municipality has issued a request for qualifications (RFQ) for a study to develop a sustainable urban drainage systems (Suds) strategy across the emirate.
The bid submission deadline is 9 April.
The tender, issued through the Sewerage and Recycled Water Projects Department, covers the development of a strategy and conceptual implementation plan for Suds in Dubai.
It follows a separate RFQ issued by the municipality in March for consultancy services to study the emirate’s sewage treatment strategy.
The Suds project, designated TF-23-D1, aims to support the emirate’s flood protection and drainage infrastructure by promoting a more sustainable approach to stormwater management.
The scope of work includes a review of international best practices in Suds and their applicability to Dubai. It also involves undertaking a Suds opportunity study and carrying out catchment-scale modelling and financial evaluation for a pilot study area.
Consultants will be required to develop Suds design guidelines, specifications and standard drawings. The project also includes establishing a strategy, policy, legal and regulatory framework to support a Suds implementation roadmap.
Dubai Municipality said the initiative represents “a significant step towards a more resilient, sustainable and forward-looking stormwater management approach for Dubai.”
The study forms part of a broader review of Dubai’s water and wastewater infrastructure. Earlier this month, the municipality issued a separate consultancy tender (P115-D1) to assess the emirate’s sewage treatment and recycled water distribution strategy.
The study will focus on infrastructure requirements to support future population growth.
This includes identifying locations for potential future facilities such as treatment plants and pumping stations.
The bid submission deadline is 23 March.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16027434/main.jpg -
Oman awards power purchase agreements18 March 2026
Oman’s Nama Power & Water Procurement Company (PWP) has issued letters of award (LoA) for new power purchase agreements (PPAs) to three independent power producers (IPPs), according to regulatory filings.
The new PPAs will extend the operating life of existing gas-fired power plants beyond the expiry of their current contracts.
The projects have a combined capacity of about 3,500MW.
The agreements have been awarded to Phoenix Power Company, Al-Batinah Power Company and Al-Suwadi Power Company.
Phoenix Power Company operates the 2,000MW Sur IPP. It is owned by a consortium of international and regional investors, including Japan’s Marubeni Corporation and Chubu Electric Power, Qatar’s Nebras Power, Qatar Electricity & Water Company and Multitech of Oman’s Bahwan Engineering Company.
Al-Batinah Power Company and Al-Suwadi Power Company operate the 750MW Sohar 2 IPP and the 750MW Barka 3 IPP, respectively.
According to regional projects tracker MEED Projects, Nama PWP signed the original PPA for the Barka 3 project in 2010 with a consortium led by Gaz de France (GDF) Suez under a special purpose vehicle (SPC) called Al-Suwadi Power Company.
The shareholders comprised GDF Suez (46%), Bahwan Engineering Company (22%), Shikoku Electric Power Corporation (11%), Sojitz Corporation (11%) and the Public Authority for Social Insurance (10%).
In 2015, GDF Suez was rebranded as Engie following a strategic shift towards low-carbon energy and utilities.
All three companies said the new PPAs will run for 15 years under agreed commercial terms. Acceptance of the LOAs has been requested by 18 March 2026.
The new agreements for Sohar 2 and Barka 3 will take effect on 1 April 2028 and run until 31 March 2043. The agreement for the Sur IPP will commence on 1 April 2029 and run until 31 March 2044.
The awards form part of Nama PWP’s 2028-29 procurement programme. The programme aims to secure firm generation capacity from existing assets whose current PPAs are due to expire during that period.
In Oman, IPP projects are developed under a build-own-operate model. This allows plant operators to continue running assets beyond the initial PPA term, either through contract extensions or by selling power into a future electricity market.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16027001/main.jpg -
DP World awards Jafza warehouse construction deal18 March 2026
Dubai-based ports operator DP World has awarded a contract to build a multi-tenant warehouse development at Jebel Ali Freezone in Dubai, UAE.
The contract was awarded to local firm Group Amana.
The development spans 141,916 square metres (sq m) and comprises 187 units across seven blocks.
These comprise warehouses, light industrial units, a retail shop, a mosque and other associated infrastructure.
The new contract builds on their existing partnership to deliver the logistics park at Jeddah Islamic Port in Saudi Arabia.
In February last year, MEED exclusively reported that Dubai’s DP World and the Saudi Ports Authority (Mawani) had awarded a SR347m ($92m) design-and-build contract to Group Amana for the project.
The scope of the contract covers construction work on the buildings under package two of the project’s first phase.
Earlier this week, MEED reported that DP World has kept its 2026 capital expenditure budget at nearly $3bn, focusing on two domestic assets and four overseas projects.
The company said in a statement that the priority developments include Jebel Ali and Drydocks World in Dubai.
Earlier this month, the group announced record financial results for 2025, with revenue up 22% to $24.4bn and adjusted earnings before interest, taxes, depreciation and amortisation (Ebitda) up 18% to $6.4bn, delivering a 26.3% margin.
DP World said this performance was driven by strong momentum across its ports and terminals and logistics business.
The group’s gross throughput rose 5.8% to 93.4 million 20-foot equivalent units.
Profit for the year increased 32.2% to $1.96bn, and operating cash flow grew 14% to $6.3bn.
Return on capital employed increased to 9.9% in 2025, up from 8.9% in 2024, reflecting stronger earnings despite ongoing geopolitical and trade uncertainty.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16026660/main.png -
Egyptian firm starts building Sal’s Riyadh logistics centre18 March 2026
Egyptian contractor Rowad Modern Engineering, a subsidiary of the Elsewedy Electric Group, has begun construction on the expansion of Saudi Logistics Services Company (Sal) facilities at King Khalid International airport in Riyadh.
The scope of work includes the rehabilitation and upgrade of existing infrastructure, as well as the construction of new supporting facilities and services.
Sal started the tendering process for its SR4.2bn ($1bn) logistics zone in the north of Riyadh in September last year, as MEED reported.
UAE-based Global Engineering Consultants is the project consultant.
The logistics hub aims to meet the demand for customised warehouses located near King Khalid International airport and the Riyadh Metro.
The project is in line with Vision 2030 and the National Transport & Logistics Strategy, which aims to support the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.
Sal and Sela signed an agreement to develop the project in March last year.
This was followed by another lease agreement for the project, which will span about 1.57 million square metres.
According to an official statement: “The lease will extend for 30 years, which is further extendable to an additional 15 years upon agreement of both parties.”
GlobalData expects the kingdom’s construction industry to record an annual average growth rate of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure projects, as well as the $850bn-plus gigaprojects programme.
Growth will also be supported by government investments in rail, dams, industrial and road infrastructure projects.
The industrial sector is estimated to grow by 3.3% in 2025-28, supported by investments in the development of manufacturing, logistics, chemicals and pharmaceuticals plants.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16026154/main.gif -
Jabal Omar plans next phase of its Mecca development18 March 2026
Saudi Arabian developer Jabal Omar Development Company is carrying out planning for phase seven of its Jabal Omar master development in Mecca, according to a fourth-quarter 2025 financial presentation.
The company said phase seven will be a mixed-use scheme comprising hotels, retail and residential components, but did not disclose a breakdown of the project elements.
Jabal Omar plans to use a development partnership model for the phase to minimise capital expenditure.
Separately, the developer said it is targeting the delivery of 1,346 hotel keys and more than 20,000 square metres of gross leasing area in phase four by 2027.
Rotana Jabal Omar Makkah, comprising 655 keys, is due to be fully operational in the first quarter of 2026, after 450 keys began operating in the final week of December 2025.
The 1,141-key Sofitel is scheduled to become operational in the fourth quarter of 2026, while the 20,000 square metres of gross leasable area is expected to be ready in 2027.
Jabal Omar estimates its 2026 capital expenditure at SR1.1bn ($293m), with spending expected to fall once the phase four hotels are completed.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16026145/main.png