Neom focuses on delivering first phase of The Line

14 February 2025

 

Register for MEED’s 14-day trial access 

Neom is focusing on delivering the first phase of The Line, setting a new deadline of 24 March for firms to submit their proposals to undertake the raft foundations for the modules at the Hidden Marina section of The Line.

Each module is designed so the raft works can be undertaken in three sections: North Blade, Canyon and South Blade.

Tendering for the raft works has been broken down into six lots across modules 45, 46 and 47, with lot 1 (module 46 west) and lot 2 (module 46 east) of module 46 being tendered first.

Module 46 spans an area of 311 x 200 metres, with the North Blade covering 311 x 60 metres, the South Blade 311 x 60 metres and the Canyon 311 x 80 metres.

The raft construction will include the world’s second-largest concrete pour of 43,000 cubic metres onto what is referred to as the mega core.

Lot 1 of module 46 west consists of two mega core rafts, four core rafts, four non-core rafts and the canyon raft. The estimated dimensions for the mega core raft are 101 x 60 x 7 metres, the core raft 60 x 60 x 6 metres and the non-core raft 54 x 60 x 5 metres.

The raft foundations follow the piling work for The Line. Piling work in the marina area began in 2023. Nine contractors were engaged as part of a framework agreement. Contractors were also engaged in the excavation work for the marina, which involved moving about 1 million cubic metres of earth every week, making it the world’s largest excavation project.

The marina is on the other side of The Line to the sea, meaning ships headed for the marina must pass through The Line buildings. This presents a significant engineering challenge, requiring a 165-metre-wide waterway to pass through the 500-metre-tall buildings.

While speaking at the PIF Private Sector Forum 2025 in Riyadh, Denis Hickey, chief development officer at The Line, confirmed Neom’s plans to prioritise the delivery of the project’s first phase, which will span 2.5 kilometres (km) across three modules.

He added: “The Line’s first phase will cover an area of about 21 million square metres (sq m) and will house about 200,000 people.”

In November last year, Neom announced the appointment of consultancy firms to deliver the core city planning, design and engineering for the first phase of The Line.

Austria’s Delugan Meissl Associate Architects was appointed as urban designer, leading the concept and detailed masterplan. US-based Gensler was appointed as city planning consultant, and UK-based Mott MacDonald as the city infrastructure engineer.

In a statement, Neom said that with the group’s support, it has established a design ecosystem with advanced and rigorous methodologies to deliver The Line. Starting in early 2025, a suite of architects will plan and design the neighbourhoods within phase one.

The statement added that Neom is focused on the initial phases of infrastructure and enabling works for the new city. More than 120 foundation piles are being cast into the ground each week for the first phase.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13395391/main.gif
Yasir Iqbal
Related Articles
  • Construction advances on Riyadh King Salman airport

    19 May 2026

    King Salman International Airport (KSIA) is advancing airside infrastructure works under its long-term expansion programme in Riyadh, including the delivery of a third runway and new private aviation facilities.

    Construction activity on the central runway programme is progressing across several operational zones, with works covering excavation, grading, site preparation and taxiway-enabling infrastructure to support upcoming phases.

    The third runway is intended to increase airfield capacity and cater to the airport’s future operational requirements.

    In a separate development, KSIA has completed initial landside works for the private aviation apron, marking a milestone in the rollout of its executive aviation infrastructure.

    The completed scope includes pavement markings, waterproofing systems, firefighting infrastructure chambers and final operational inspections to support readiness for the next stages.

    KSIA has also secured General Authority of Civil Aviation (GACA) approval for phase one airside works, which includes the planned connection of Taxiway Alpha to the private aviation facilities, strengthening operational integration between executive aviation assets and airfield movement areas.

    The packages form part of the wider KSIA masterplan, which covers about 57 square kilometres and supports Saudi Arabia’s objective of positioning Riyadh as a global aviation and logistics hub.

    The airport aims to accommodate up to 100 million passengers by 2030.

    Saudi Arabia plans to invest $100bn in its aviation sector. The Saudi Aviation Strategy, announced by GACA, aims to triple annual passenger traffic to 330 million travellers by 2030. It also targets air cargo growth to 4.5 million tonnes and an increase in total air connections to more than 250 destinations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16906496/main.jpeg
    Yasir Iqbal
  • Aldar launches Al-Ghadeer Gardens project

    19 May 2026

    Abu Dhabi-based real estate developer Aldar Properties has launched the Al-Ghadeer Gardens project, located on the Abu Dhabi-Dubai border.

    The new residential development will feature 437 villas and townhouses, offering two-, three- and four-bedroom homes.

    Al-Ghadeer Gardens will include more than 30,000 square metres of landscaped open space, supporting a pedestrian-friendly layout and outdoor-focused living.

    As part of its sustainability and wellbeing approach, the project is targeting Estidama Pearl 2 and Fitwel 2-star certifications.

    Earlier this month, Aldar announced its Q1 financial results, reporting a 20% year-on-year increase in net profit after tax to AED2.3bn ($626m).

    Aldar Development recorded a 14% year-on-year rise in revenue to $1.7bn, while earnings before interest, taxes, depreciation and amortisation (Ebitda) increased 23% to $599m.

    UAE revenue backlog rose to $17bn at the end of March from $16.6bn at the end of December, with an average duration of 29 months.

    The group attributed its performance to revenue from its development backlog and steady income from its investment properties.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16906154/main.jpg
    Yasir Iqbal
  • Iraq trucks oil from the south to Kurdish pipeline

    19 May 2026

     

    Iraq is trucking crude from Basra to the north of the country to be exported via the Iraq-Turkiye Pipeline (ITP), according to industry sources.

    The oil is being loaded into trucks at fields in Basra before being driven to the north, where it is injected into the pipeline network at Khurmala Dome, in the northern section of the Kirkuk field.

    Once it has entered the network at Khurmala Dome, it is transported to the main ITP export pipeline and eventually to the port of Ceyhan in Turkiye, where it can be loaded onto ships.

    The volumes of crude being transported using trucks have surged in Iraq since the US and Israel attacked Iran on 28 February, starting a regional conflict that has disrupted shipping through the Strait of Hormuz.

    One source said: “Most of the crude that is being trucked out of Iraqi oil fields at the moment is going to Syria, but some is being trucked to the north where it is being funnelled through the pipeline.”

    Even with the additional volumes being trucked from the south, Iraq is struggling to boost exports using the ITP.

    At the end of March, Amer Khalil, the director-general of Iraq’s state-run North Oil Company, said that Iraq was exporting 200,000 barrels a day (b/d) through the ITP.

    At the time, he said that the pipeline, which runs from Kirkuk in Iraqi Kurdistan to the port of Ceyhan in Turkiye, was expected to start transporting 300,000 b/d “in the near future”.

    As of early May, the pipeline was still exporting about 200,000 b/d, despite having a nameplate capacity of 1.4 million b/d.

    One of the factors said to be stopping increased volumes from being shipped through the pipeline is that several key oil fields in northern Iraq evacuated staff and stopped production after the US and Israel started their war with Iran.

    Another factor is that Iraq has not invested in domestic pipeline infrastructure to pipe production from Basra to Kurdistan, where it could be exported via the Kurdish ITP route.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16902345/main1824.jpg
    Wil Crisp
  • Kuwaiti oil services company secures credit facility

    19 May 2026

    The Kuwaiti drilling and oilfield services provider Action Energy Company (AEC) has secured a new credit facility and renewed and expanded an existing facility in order to support the company’s rig fleet expansion.

    The new facility and the expansion were obtained from two Kuwaiti banks and had a combined value of KD40.9m ($132.8m).

    In its statement, AEC said that the facilities support the financing and deployment of new rigs linked to contract awards previously announced with the state-owned upstream operator Kuwait Oil Company (KOC).

    The company added: “They further reinforce AEC’s financing structure and strengthen its ability to execute its contracted fleet expansion plan through 2026 and beyond, while maintaining a disciplined approach to capital allocation.”

    The new credit facility was obtained from Kuwait International Bank (KIB).

    It is worth KD7.3m ($23.7m) and will finance two new 750-horsepower (HP) rigs.

    The renewal and expansion of the existing facility is worth KD33.6m ($109.1m) and was obtained from Commercial Bank of Kuwait (CBK) to finance four new 1,500 HP rigs and one 1,000 HP rig, in addition to the renewal of the existing facilities.

    AEC announced its financial and operational performance for the first quarter earlier this month.

    The company reported a net profit of KD2.2m ($7.1m).

    The company’s revenue grew by 69.2% year-on-year, primarily driven by the expansion of the operating rig fleet from 13 rigs in the first quarter of 2025 to 20 rigs in the first quarter of 2026, including the full-quarter contribution of 10 new rigs deployed during 2025.

    The company is benefitting from a substantial multi-year contracted backlog with KOC.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16902234/main.jpg
    Wil Crisp
  • Emirates awards $5bn engineering complex deal

    18 May 2026

    Register for MEED’s 14-day trial access 

    Emirates Airline has awarded a AED19bn ($5bn) contract to build one of the world's largest engineering complexes in Dubai South.

    The contract was awarded to Beijing-headquartered China Railway Construction Corporation (CRCC).

    CRCC is being supported by French firm Artelia, as the project consultant.

    The complex will cover over 1 million square metres (sq m).

    It will comprise 77,000 sq m of dedicated workshop space for maintenance and repairs, 380,000 sq m of storage and logistics capacity, a 50,000 sq m administrative building for Emirates Engineering and 15,000 sq m of training facilities.

    It will be the world's only complex with a capacity to service 28 wide-body aircraft simultaneously.

    The airline officially broke ground on the project on 18 May. 

    The groundbreaking ceremony was attended by Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and CEO of Emirates Group; Tim Clark, president of Emirates Airline; Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai South; and Dai Hegen, chairman of CRCC.

    The facility will enable large-scale retrofits, cabin redesigns and structural modifications to be performed in-house, thereby reducing turnaround times.

    The engineering complex is scheduled for completion in 2030 and will be located at Al-Maktoum International airport.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16895218/main.jpg
    Yasir Iqbal