Neom becomes real-world building project

26 April 2023

This package on Neom also includes:

> SITE REPORT: World’s largest piling project shifts to The Line’s marina
> INTERVIEW: Neom to fix construction
> MOVIE SET: Neom advances plans to be leading movie destination
> TUNNELS: Neom tenders Delta Junction tunnel contracts
> OXAGON: Work to start for $1.5bn Oxagon wind turbine plant


 

The launch of Neom by Saudi Arabia’s Crown Prince Mohammed bin Salman at the Future Investment Initiative (IFI) in Riyadh in October 2017 challenged the world’s imagination and marked the beginning of Saudi Arabia’s gigaprojects era.

Strategically located close to neighbouring Jordan and Egypt, the 26,500 square-kilometre project is about the size of Belgium.  With a $500bn price tag, it quickly became known as the world’s largest construction project.

In the six years that followed, there has been a steady wave of announcements detailing the individual components of Neom. Each launch has been accompanied by marketing campaigns showcasing slick computer-generated imagery (CGI) of futuristic cities that aim to change how mankind will live. 

Unless working on these projects directly, Neom has been an abstract idea for most people. That started to change in January when Neom released a progress video of construction work on Sindalah Island, which is due to open its doors in 2024. Then in March, MEED visited Neom to witness the work progressing The Line, which is now the world’s largest piling project. 

The images of construction equipment toiling on site showed that after six years of planning, Neom is here.

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar 

Awards soar 

As Neom morphs from a futuristic concept into a real-world building project, the construction industry has started to benefit from a sharp increase in contract awards, which by mid-April 2023 totalled $27bn. 

As construction activity ramps up, the data shows that Neom is no longer a single project offering tactical opportunities. It has become a strategic market in its own right. 

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar. 

On a submarket level, the total value of contract awards exceeds the Saudi capital Riyadh, where there were $11bn of awards, and Dubai, which has traditionally been regarded as a hotbed of construction, with $9.3bn of awards in 2022. 

As tendering activity continues for major contracts, Neom’s prominence as a projects market will likely increase further. 

So far, four major components of Neom have been officially launched by Prince Mohammed. They are The Line, Trojena,
Oxagon and Sindalah Island. Meanwhile, work has also progressed on other projects that have yet to be officially launched with the full CGI treatment, such as Neom International airport and the Gulf of Aqaba.

The Line was the first to be launched in January 2021 as a 170-kilometre linear belt of hyper-connected, car-free communities. Then in July 2022, the designs of The Line’s mirrored buildings were revealed. They are 200 metres wide and 500 metres above sea level, running entirely on renewable energy. Once complete, The Line will accommodate 9 million residents.

Piling work has started for the first modules of buildings that make up The Line (click here for images of the site). Infrastructure work for The Spine, the infrastructure corridor parallel to The Line that includes the high-speed rail, is also advancing.

Floating city

The second major project launch was Oxagon industrial city in November 2021. It will be built around an integrated port and logistics hub, with its octagonal design minimising environmental impact and optimising land usage. The city will feature the world’s largest floating structure and be powered by 100 per cent clean energy. 

The first major area of construction for Oxagon is the expansion of the existing Duba port. A contract for the first phase of that project was awarded earlier this year and a second phase is being tendered.

In March 2022, Prince Mohammed announced Trojena. Located in the mountains, it has temperatures 10 degrees Celsius lower than other regional cities and offers the potential for snow-covered ski slopes.

Trojena dams face countdown to make it snow

Trojena received added impetus in October last year when it was selected to host the ninth Asian Winter Games in 2029. Trojena will have two competition clusters for the games: a snow cluster for sports, including alpine skiing, snowboarding and slalom; and an ice cluster for sports, including ice hockey, figure skating and curling. The games village will have 14 luxury hotels and be powered entirely by renewable energy.

Construction contracts covering major infrastructure elements such as three major dams are at the tendering stage. Procurement activity is also starting for major buildings such as The Vault, which is a 198-metre-high, 253-metre-wide and 864-metre-long building that will serve as the gateway to Trojena.

Sindalah, Neom’s first luxury island destination, was announced in December 2022 and construction work is advancing (see main image). Once complete, the island will feature a marina, hotels and a golf course. 

Delivering these projects is a major challenge for the construction sector. Resource scarcity is a key issue for all projects in the kingdom, with construction companies already struggling to meet the demand for their services and expertise. Neom, along with its owner, the Public Investment Fund (PIF), is taking steps to address these challenges by investing in local construction firms, attracting international companies, improving payment terms and adopting alternative procurement methods. Despite these efforts, the construction sector faces sustained pressure.

New economy

Neom is much more than just a collection of construction projects. While other projects in the region offer opportunities for the construction sector and associated asset management services such as facilities management and hotel operation, the scale of Neom means it is creating a new economy.

It is an economy that not only aims to support the development of nine sectors to achieve the goals outlined in Vision 2030, but also intends to transform the way those sectors operate. 

The industrial city Oxagon will play a key role. Neom plans to create an integrated port and logistics hub that will be home to seven innovative sectors: sustainable energy, autonomous mobility, water innovation, sustainable food production, health and wellbeing, technology and digital manufacturing, and modern methods of construction. 

The Neom green fuels project is key to Oxagon’s clean energy ambitions. The integrated facility will produce hydrogen to be synthesised into carbon-free ammonia. Full construction work began on the project earlier this year after it reached financial closure. The facility is expected to be commissioned in 2026.

Neom, US-based Air Products and Acwa Power each have a 33.3 per cent stake in Neom Green Hydrogen Company, the special project vehicle implementing the project.

Aviation is another major area of investment. Neom plans to start operating its own airline, Neom Airlines, at the end of 2024 from the existing Neom Bay airport before operating from Neom International – a greenfield development inland close to Tabuk at the end of The Line.

Neom will morph from a construction project into a full-fledged economy

International airport

Plans for the international airport are advancing. US firm Aecom has been awarded a contract to provide project management consultancy services, and a series of construction and supply contracts are due to be tendered this year.

Although not confirmed, it is understood the first phase of the airport will have the capacity to handle 25 million passengers a year. A second phase could take the capacity up to 50 million a year. There is an aspiration for the airport to become the largest in the world, with a capacity of 100 million passengers a year. 

Another sector developing quickly is media. In April, Neom furthered its ambition to become the region’s leading TV and film production hub by opening more stages at its Media Village. The village now has four stages offering 12,000 sq m of production space. Six more stages are under development. Neom is also increasing its resort-style accommodation for cast and crew.

As well as gaining access to filming locations across Neom’s varied landscapes, companies using the facilities can enjoy Neom’s highly attractive production incentives, including cash rebates of over 40 per cent.

As these sectors and others advance, Neom will morph again from a construction project into a full-fledged economy. When launched in 2017, its GDP was projected to reach $100bn by 2030 – equivalent at the time to more than one-seventh of the kingdom’s GDP of $688bn. By focusing on nine high-value sectors, the Neom economy will be an affluent one. Its GDP per capita is projected to become the highest in the world.

Main image: Construction work is advancing on Sindalah Island, which is planned to open in early 2024. Credit: Neom


MEED's April 2023 special report on Saudi Arabia includes:

> GIGAPROJECTS: Saudi Arabia under project pressure
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10787833/main.gif
Colin Foreman
Related Articles
  • Tabreed finishes the year on a high

    17 December 2025

     

    Tabreed is consolidating its position as a leading regional district cooling provider following a series of major transactions and new concessions that will reshape its portfolio in the UAE and beyond.

    In 2025, the company completed the AED3.87bn ($1bn) acquisition of PAL Cooling Holding (PCH) in consortium with CVC DIF, and finalised the long-term district cooling concession for Palm Jebel Ali in Dubai as part of a joint venture (JV) with Dubai Holding Investments.

    The PCH deal will eventually add about 600,000 refrigeration tons (RT) of capacity across eight long-term concessions in Abu Dhabi, raising Tabreed’s total connected capacity by 13% to 1.55 million RT. The AED1.5bn Palm Jebel Ali JV will ultimately deliver a further 250,000RT.

    Speaking to MEED, Tabreed CEO Khalid Al-Marzooqi outlined how the company is integrating the newly acquired brownfield assets, developing greenfield projects and advancing a new generation of sustainable cooling solutions, including geothermal energy for data centres.

    Tabreed’s recent milestones span both greenfield and brownfield investments, each requiring a different approach, says Al-Marzooqi. 

    Greenfield projects, such as Palm Jebel Ali, remain Tabreed’s preferred route for new capacity, he adds. “The beauty of a greenfield is that you can optimise it the way you want. You build it as you want.” 

    For new plants, Tabreed designs the civil structure to accommodate long-term capacity, while phasing in mechanical equipment in line with demand. By contrast, the acquisition of PCH is a large-scale brownfield integration, bringing in a portfolio of existing and future plants and networks, mainly on Abu Dhabi’s main island and Reem Island.

    The immediate focus is on integration and driving network synergies. “That’s the beauty of district cooling. If you achieve the synergies, the benefits literally double up and triple up as well,” Al-Marzooqi says.

    By interconnecting plants, Tabreed can avoid building for peak capacity at each individual site and instead leverage shared spare capacity across the network.

    Growth strategy

    Acquiring a competitor in Abu Dhabi is part of a strategy to sustain growth in a sector where many contracts follow build-own-operate-transfer or similarly time-bound models.

    Organic growth via new concessions and inorganic growth via acquisitions are both seen as key to maintaining and expanding the asset base.

    Tabreed’s portfolio remains weighted towards the UAE, with the home market accounting for the bulk of its business. 

    Beyond the UAE, Tabreed has built a regional presence, with a partially owned business in Saudi Arabia, where it sees significant growth potential as district cooling is integrated into gigaprojects and major urban developments; a wholly owned operation in Bahrain; and a majority stake in Tabreed Oman, a market that Al-Marzooqi says is expanding well.

    Despite the energy and lifecycle cost benefits of district cooling, Al-Marzooqi says tariff subsidies on conventional, building-level cooling are a barrier to adoption in parts of the UAE.

    “The killer for us is subsidy,” he says, explaining that artificially low tariffs for individual customers make it harder for district cooling to compete on price in Abu Dhabi compared to Dubai.

    He says that policy support and regulatory mandates are needed, particularly as existing buildings approach the end of life for their standalone cooling systems. At that point, compulsory connection to district cooling could lock in significant energy savings and emissions reductions at city scale.

    Raising Abu Dhabi’s district cooling penetration from about 15% towards Dubai’s estimated 30% remains a key concern and strategic objective.

    In Abu Dhabi, Tabreed has developed … the Middle East’s first geothermal-powered district cooling plant

    Geothermal breakthrough

    Alongside portfolio growth, Tabreed is investing in new technologies to decarbonise cooling, with a focus on large campuses, major developments and, increasingly, data centres.

    At Masdar City in Abu Dhabi, Tabreed has developed what Al-Marzooqi describes as the Middle East’s first geothermal-powered district cooling plant. 

    “We have started off by building the region’s first geothermal plant, to prove the concept of using geothermal energy to provide cooling,” he says. 

    The pilot plant is already achieving efficiency levels in the range of 0.5-0.6 kilowatts per ton (kW/ton) of cooling, better than Tabreed’s typical district cooling benchmark of about 0.85kW/ton. Conventional, standalone cooling systems generally consume about twice as much energy per ton.

    “This is proof that if you really want to pursue a sustainable cooling solution for data centres in this area, this is the one,” he says.

    Data centres are emerging as a priority growth segment for Tabreed. The facilities have high, continuous cooling loads and increasingly stringent decarbonisation requirements, making them a natural fit with both district cooling and geothermal systems.

    Al-Marzooqi says geothermal cooling is a “godsend solution” for data centres, combining 24/7 availability with the potential for near-zero operational emissions.

    For hyperscale and colocation data centre operators facing mounting pressure to reduce their carbon footprint, geothermal district cooling could offer a differentiated, long-term solution in the Gulf region, particularly where grid power is still largely fossil-fuel based.

    Tabreed’s technology agenda is not limited to low-carbon generation. The utility is in the second phase of connecting its plants to a centralised digital control centre, enabling remote operation and optimisation.

    The long-term goal is for the majority of plants to be unmanned, with operations centrally monitored and controlled. This integrated view of the network will enable the application of artificial intelligence and advanced analytics to fine-tune performance, optimise energy use and predict maintenance requirements. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15266676/main.gif
    Colin Foreman
  • Kuwait Oil Company seeks higher project budgets

    17 December 2025

     

    Contractors in Kuwait expect to have answers by the end of the year on whether budgets for several key upstream projects in the oil and gas sector will be increased, according to industry sources.

    State-owned upstream operator Kuwait Oil Company (KOC) is seeking approvals for at least three upstream projects, for which bids came in significantly over budget.

    The first project, with a low bid of $2.47bn, involves the development of two facilities: Separation Gathering Centre 1 (SGC-1) and Water Injection Plant 1 (WIP-1).

    The second project, with a low bid of $2.48bn, focuses on developing SGC‑3 and WIP‑3.

    The third project, which involves developing effluent water disposal plants for injector wells, had a low bid of $1.3bn.

    For KOC to increase the budgets for all three projects, approvals will be required from Kuwait Petroleum Corporation (KPC) and the country’s Ministry of Finance.

    Already cancelled

    One Kuwaiti oil project tender that received bids significantly above budget has already been cancelled.

    On 7 October, MEED reported that the tender for the SGC-2 oil project – focused on the installation of a separation gathering centre – was cancelled by Kuwait’s Central Agency for Public Tenders.

    Earlier this year, UK-based Petrofac had submitted a bid more than double the project’s proposed budget.

    Petrofac’s bid was KD422.45m ($1.37bn), while the provisional budget stood at KD207m ($670.2m).

    This contract is expected to be retendered, but there is significant uncertainty about when a new invitation to bid will be issued and how the scope may change.

    Earlier in December, MEED reported that KOC was discussing whether to retender the contract using a different contract model.

    Initially, the project was tendered using the engineering, procurement and construction (EPC) contract model.

    Discussions are ongoing on whether it will be relaunched under a build-own-operate (BOO) contract model.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15263996/main.png
    Wil Crisp
  • Morocco awards $185m Guercif-Nador road contracts

    17 December 2025

     

    Morocco’s Ministry of Equipment, Transport, Logistics & Water has awarded three contracts totalling MD1.7bn ($185m) for building three lots of the 40-kilometre (km) section two of the Guercif to Nador highway between Saka and Driouch.

    The contracts were awarded to local firms.

    Casablanca-based Groupe Mojazine won a $64m contract for lot one, which covers the construction of 14km of highway.

    The other two contracts covering construction works on lots two and three were awarded to the local firm Bioui Travaux.

    The contract value for lot two is over $56m and covers the 12km highway section. The lot three contract is worth about $69m and covers 40km of highway construction.

    The 104km Guercif to Nador highway is being implemented in three sections. Prequalification for section two from Saka to Driouch was completed in June, as MEED reported.

    The estimated $700m project, partly funded by the African Development Bank, is part of the kingdom’s plans to upgrade its public infrastructure in preparation for co-hosting the 2030 Fifa World Cup alongside Portugal and Spain. The programme includes the expansion of over 1,000km of highways.

    In May, Societe Nationale des Autoroutes du Maroc awarded MD5bn ($540m) of contracts for nine packages covering construction works on the Rabat-Casablanca continental expressway.

    Morocco’s construction and infrastructure sector is gearing up for billions of dollars in projects as the North African nation continues to award contracts for building infrastructure for the 2030 Fifa World Cup.

    Morocco has made a strong head start in ensuring that the necessary infrastructure is ready for the tournament.

    According to data from regional project tracker MEED Projects, 2024 was the best year in the past decade for construction and transport contract awards in Morocco, with contracts worth over $3.6bn signed with local construction firms and international companies from South Korea, China, France and Spain.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15266606/main.jpg
    Yasir Iqbal
  • Egypt plans $5.7bn oil and gas exploration campaign

    17 December 2025

    Egypt plans to drill 480 exploratory wells, with total investment estimated at $5.7bn, over the next five years, according to Karim Badawi, the country’s minister of petroleum and mineral resources.

    Speaking at a conference in Cairo, Badawi said that Egypt’s oil and gas sector was stabilising after a period of decline.

    He said that his ministry was targeting an increase in gas production for the first time in four years.

    The government is also aiming for self-sufficiency in crude oil production within five years, he said.

    Egypt is aiming to boost crude production by introducing investment incentive packages and utilising new production technologies.

    Badawi highlighted specific capital commitments from international partners to develop oil and gas resources over the next five years. These included Italian company Eni’s commitment to invest $8bn, as well as London-headquartered BP’s plan to invest $5bn.

    He also highlighted Arcius Energy’s plan to invest $3.7bn. Arcius Energy is a joint venture of BP and Adnoc’s XRG.

    The $5.7bn exploration programme includes 101 wells scheduled for drilling in 2026.

    Badawi said that seismic survey operations would expand to cover 100,000 square kilometres in the Western Desert and 95,000 square kilometres in the Eastern Mediterranean using Ocean Bottom Node (OBN) technology.

    Renewable energy strategy

    Addressing the national energy strategy, Badawi said the government aims to increase the share of renewable energy in electricity generation to 42% by 2030.

    He said this would enable natural gas to be redirected to value-added industries, such as petrochemicals and fertilisers, to boost exports.

    On the transition to green energy, the minister cited plans to reduce reliance on traditional fuels and open investment in sustainable aviation fuel (SAF), green ammonia and bioethanol.

    Efficiency measures in the sector have already reduced carbon emissions by 1.4 million tonnes, he said.

    Recently, Egypt announced a $200m deal with Qatar to produce aviation fuel from used cooking oil.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15264077/main0508.jpg
    Wil Crisp
  • Saudi Arabia to award Abha airport expansion by March

    17 December 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Civil Aviation Holding Company (Matarat) and the National Centre for Privatisation & PPP (NCP) are expected to award the contract to develop and operate a new passenger terminal building and related facilities at Abha International airport by March next year.

    The announcement was made by Abdulaziz Al-Duailej, president of the General Authority of Civil Aviation (Gaca), at the Supply Chain and Logistics Conference 2025 in Riyadh on Tuesday.

    The companies prequalified to bid for the contract are:

    • GMR Airports (India)
    • Mada TAV: Mada International Holding (local) / TAV Airports Holding
    • Touwalk Alliance: Skilled Engineers Contracting (local) / Limak Insaat (Turkiye) / Incheon International Airport Corporation (South Korea) / Dar Al-Handasah Consultants (Shair & Partners, Lebanon) /  Obermeyer Middle East (Germany/Abu Dhabi)
    • VI Asyad DAA: Vision International Investment Company (local) / Asyad Holding (local) / DAA International (Ireland)

    Located in Asir Province, the first phase of the Abha International airport public-private partnership (PPP) project will expand the terminal area from 10,500 square metres (sq m) to 65,000 sq m.

    In early March this year, the clients held one-on-one meetings with prospective bidders in Riyadh, as reported by MEED.

    The contract scope includes a new rapid-exit taxiway on the existing runway, a new apron to serve the new terminal, access roads to the new terminal building and a new car park area.

    Additionally, the scope includes support facilities, such as an electrical substation expansion and a new sewage treatment plant. 

    Construction is scheduled for completion in 2028.

    The project will be developed under a build-transfer-operate (BTO) model and involves designing, financing, constructing and operating a greenfield terminal.

    This will be the kingdom’s third airport PPP project, following the Hajj terminal at Jeddah’s King Abdulaziz International airport and the $1.2bn Prince Mohammed Bin Abdulaziz International airport in Medina.

    Higher capacity

    According to Matarat, Abha airport’s capacity will increase to accommodate over 13 million passengers annually—a 10-fold rise from its current 1.5 million capacity.

    Once completed, the airport will handle more than 90,000 flights a year, up from 30,000.

    The new terminal is also expected to feature 20 gates and 41 check-in counters, including seven new self-service check-in kiosks.

    The BTO contract duration is 30 years.

    The existing terminal, which served 4.4 million passengers in 2019, will be closed once the new terminal becomes operational.

    Matarat’s transaction advisory team for the project comprises UK-headquartered Deloitte as financial adviser, ALG as technical adviser and London-based Ashurst as legal adviser.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15264715/main.jpg
    Yasir Iqbal