Neom becomes real-world building project

26 April 2023

This package on Neom also includes:

> SITE REPORT: World’s largest piling project shifts to The Line’s marina
> INTERVIEW: Neom to fix construction
> MOVIE SET: Neom advances plans to be leading movie destination
> TUNNELS: Neom tenders Delta Junction tunnel contracts
> OXAGON: Work to start for $1.5bn Oxagon wind turbine plant


 

The launch of Neom by Saudi Arabia’s Crown Prince Mohammed bin Salman at the Future Investment Initiative (IFI) in Riyadh in October 2017 challenged the world’s imagination and marked the beginning of Saudi Arabia’s gigaprojects era.

Strategically located close to neighbouring Jordan and Egypt, the 26,500 square-kilometre project is about the size of Belgium.  With a $500bn price tag, it quickly became known as the world’s largest construction project.

In the six years that followed, there has been a steady wave of announcements detailing the individual components of Neom. Each launch has been accompanied by marketing campaigns showcasing slick computer-generated imagery (CGI) of futuristic cities that aim to change how mankind will live. 

Unless working on these projects directly, Neom has been an abstract idea for most people. That started to change in January when Neom released a progress video of construction work on Sindalah Island, which is due to open its doors in 2024. Then in March, MEED visited Neom to witness the work progressing The Line, which is now the world’s largest piling project. 

The images of construction equipment toiling on site showed that after six years of planning, Neom is here.

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar 

Awards soar 

As Neom morphs from a futuristic concept into a real-world building project, the construction industry has started to benefit from a sharp increase in contract awards, which by mid-April 2023 totalled $27bn. 

As construction activity ramps up, the data shows that Neom is no longer a single project offering tactical opportunities. It has become a strategic market in its own right. 

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar. 

On a submarket level, the total value of contract awards exceeds the Saudi capital Riyadh, where there were $11bn of awards, and Dubai, which has traditionally been regarded as a hotbed of construction, with $9.3bn of awards in 2022. 

As tendering activity continues for major contracts, Neom’s prominence as a projects market will likely increase further. 

So far, four major components of Neom have been officially launched by Prince Mohammed. They are The Line, Trojena,
Oxagon and Sindalah Island. Meanwhile, work has also progressed on other projects that have yet to be officially launched with the full CGI treatment, such as Neom International airport and the Gulf of Aqaba.

The Line was the first to be launched in January 2021 as a 170-kilometre linear belt of hyper-connected, car-free communities. Then in July 2022, the designs of The Line’s mirrored buildings were revealed. They are 200 metres wide and 500 metres above sea level, running entirely on renewable energy. Once complete, The Line will accommodate 9 million residents.

Piling work has started for the first modules of buildings that make up The Line (click here for images of the site). Infrastructure work for The Spine, the infrastructure corridor parallel to The Line that includes the high-speed rail, is also advancing.

Floating city

The second major project launch was Oxagon industrial city in November 2021. It will be built around an integrated port and logistics hub, with its octagonal design minimising environmental impact and optimising land usage. The city will feature the world’s largest floating structure and be powered by 100 per cent clean energy. 

The first major area of construction for Oxagon is the expansion of the existing Duba port. A contract for the first phase of that project was awarded earlier this year and a second phase is being tendered.

In March 2022, Prince Mohammed announced Trojena. Located in the mountains, it has temperatures 10 degrees Celsius lower than other regional cities and offers the potential for snow-covered ski slopes.

Trojena dams face countdown to make it snow

Trojena received added impetus in October last year when it was selected to host the ninth Asian Winter Games in 2029. Trojena will have two competition clusters for the games: a snow cluster for sports, including alpine skiing, snowboarding and slalom; and an ice cluster for sports, including ice hockey, figure skating and curling. The games village will have 14 luxury hotels and be powered entirely by renewable energy.

Construction contracts covering major infrastructure elements such as three major dams are at the tendering stage. Procurement activity is also starting for major buildings such as The Vault, which is a 198-metre-high, 253-metre-wide and 864-metre-long building that will serve as the gateway to Trojena.

Sindalah, Neom’s first luxury island destination, was announced in December 2022 and construction work is advancing (see main image). Once complete, the island will feature a marina, hotels and a golf course. 

Delivering these projects is a major challenge for the construction sector. Resource scarcity is a key issue for all projects in the kingdom, with construction companies already struggling to meet the demand for their services and expertise. Neom, along with its owner, the Public Investment Fund (PIF), is taking steps to address these challenges by investing in local construction firms, attracting international companies, improving payment terms and adopting alternative procurement methods. Despite these efforts, the construction sector faces sustained pressure.

New economy

Neom is much more than just a collection of construction projects. While other projects in the region offer opportunities for the construction sector and associated asset management services such as facilities management and hotel operation, the scale of Neom means it is creating a new economy.

It is an economy that not only aims to support the development of nine sectors to achieve the goals outlined in Vision 2030, but also intends to transform the way those sectors operate. 

The industrial city Oxagon will play a key role. Neom plans to create an integrated port and logistics hub that will be home to seven innovative sectors: sustainable energy, autonomous mobility, water innovation, sustainable food production, health and wellbeing, technology and digital manufacturing, and modern methods of construction. 

The Neom green fuels project is key to Oxagon’s clean energy ambitions. The integrated facility will produce hydrogen to be synthesised into carbon-free ammonia. Full construction work began on the project earlier this year after it reached financial closure. The facility is expected to be commissioned in 2026.

Neom, US-based Air Products and Acwa Power each have a 33.3 per cent stake in Neom Green Hydrogen Company, the special project vehicle implementing the project.

Aviation is another major area of investment. Neom plans to start operating its own airline, Neom Airlines, at the end of 2024 from the existing Neom Bay airport before operating from Neom International – a greenfield development inland close to Tabuk at the end of The Line.

Neom will morph from a construction project into a full-fledged economy

International airport

Plans for the international airport are advancing. US firm Aecom has been awarded a contract to provide project management consultancy services, and a series of construction and supply contracts are due to be tendered this year.

Although not confirmed, it is understood the first phase of the airport will have the capacity to handle 25 million passengers a year. A second phase could take the capacity up to 50 million a year. There is an aspiration for the airport to become the largest in the world, with a capacity of 100 million passengers a year. 

Another sector developing quickly is media. In April, Neom furthered its ambition to become the region’s leading TV and film production hub by opening more stages at its Media Village. The village now has four stages offering 12,000 sq m of production space. Six more stages are under development. Neom is also increasing its resort-style accommodation for cast and crew.

As well as gaining access to filming locations across Neom’s varied landscapes, companies using the facilities can enjoy Neom’s highly attractive production incentives, including cash rebates of over 40 per cent.

As these sectors and others advance, Neom will morph again from a construction project into a full-fledged economy. When launched in 2017, its GDP was projected to reach $100bn by 2030 – equivalent at the time to more than one-seventh of the kingdom’s GDP of $688bn. By focusing on nine high-value sectors, the Neom economy will be an affluent one. Its GDP per capita is projected to become the highest in the world.

Main image: Construction work is advancing on Sindalah Island, which is planned to open in early 2024. Credit: Neom


MEED's April 2023 special report on Saudi Arabia includes:

> GIGAPROJECTS: Saudi Arabia under project pressure
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10787833/main.gif
Colin Foreman
Related Articles
  • SAR tenders design review consultancy for GCC rail link

    18 September 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia Railways (SAR) has issued a request for proposals (RFP) for a design management and review consultant to oversee engineering works on the GCC railway network, the latest step in advancing the long-delayed regional rail link.

    The RFP was issued on 9 September, with a submission deadline of 18 October.

    The tender seeks a consultant to manage, audit and verify deliverables produced by SAR's separately appointed design services consultant, rather than carry out the design itself. The tendering for the design services consultancy is currently in progress.

    Construction will be tendered separately through competitive bidding once designs are approved.

    The GCC railway will run for about 672 kilometres (km) inside Saudi Arabia, linking the kingdom's existing network to Kuwait, Qatar, the UAE and Bahrain, with four sections of about 141km, 200km, 151km and 21km, respectively.

    The line is planned as a single-track, non-electrified corridor for mixed freight and passenger traffic, with a maximum axle load of 32.4 tonnes and passing loops for bidirectional working.

    The appointed consultant will develop a design management and review plan covering governance, interdisciplinary coordination and stage-gate approvals, and will issue formal review and audit reports against SAR's requirements and international standards.

    The scope also covers stakeholder engagement, interface management and oversight of land acquisition activity tied to the design consultant's land acquisition plan.

    Key design stages are expected to take about 16 months: four months for concept design, six for preliminary design and six for issued-for-construction design, each with four weeks of contingency.

    SAR has asked bidders to mobilise a core team from day one. These must include a project director, engineering and design manager, stakeholder manager and lead document controller, all based at SAR's offices, with minimum experience thresholds ranging from three years for junior operators up to 25 years, including 15 in rail, for the project director role.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to cover about 2,186km in total.

    The route length within each member state is as follows:

    • UAE – 684km
    • Saudi Arabia – 672km
    • Oman – 306km
    • Qatar – 283km
    • Kuwait – 145km
    • Bahrain – 36km

    The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80km/h–120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19783331/main.gif
    Yasir Iqbal
  • Tender issued for Libyan gas project

    17 September 2026

    An invitation to bid has been issued for a contract to conduct environmental assessments for the project to expand the Mellitah oil and gas complex in Libya.

    The bid submission deadline is 2pm today (17 September) Libyan time.

    The scope of the project includes provision of:

    • An environmental baseline study (EBS)
    • An environmental impact assessment (EIA)
    • An environmental management plan (EMP)

    The client is Mellitah Oil & Gas (MOG), which is a joint venture of Italy’s Eni and Libya’s National Oil Corporation (NOC).

    MOG is based in Tripoli and operates both onshore and offshore oil and gas facilities.

    The joint venture owns and operates six major oil and gas fields across the North African country.

    According to the tender documents, the company that is awarded the contract will need to prepare environmental management measures in compliance with:

    • Libyan environmental legislation
    • Ministry of Environment requirements
    • NOC environmental guidelines
    • Applicable international environmental standards and best practices

    The expansion of the Mellitah oil and gas complex is part of a project estimated to be worth $8bn.

    The wider project is known as the Mellitah Complex Expansion & CO2 Management Integrated Development Project.

    It has six main packages:

    • Onshore package
    • Offshore Structure A
    • Offshore Structure E
    • Subsea pipeline package
    • Site preparation work
    • Carbon capture and storage facility

    Security issues and political instability have been a major problem for Libya’s oil and gas sector since the country’s civil war started in 2011.

    Earlier this month, the Mellitah oil and gas complex was forced to shut down temporarily due to a protest over deteriorating public services.

    The existing onshore complex includes housing, processing units, storage facilities and export facilities.

    It also serves as the launch point for the Greenstream pipeline, which delivers Libyan gas directly to Italy.

    The planned expansion of the complex will involve:

    • Construction of a new fourth gas processing train
    • Construction of a third condensate train
    • Construction of a third natural gas liquids fractionation train
    • Construction of a fourth sulphur recovery unit train
    • Installation of a hydrogen sulphide enrichment unit
    • Installation of a sulphur recovery unit
    • Construction of other associated facilities

    The Mellitah complex is located about 100 kilometres west of Tripoli and is a key energy facility in the west of the country.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748920/main.png
    Wil Crisp
  • Nakheel awards $218m Dubai Islands buildings deal

    17 September 2026

    Register for MEED’s 14-day trial access 

    Dubai-based developer Nakheel, now part of Dubai Holding, has awarded a main construction contract worth more than AED800m ($218m) for phases one and three of Bay Grove Residences at Dubai Islands.

    The contract was awarded to the local firm Metac General Contracting Company.

    It covers the construction of 537 apartments, comprising one- to four-bedroom units, across seven residential buildings.

    Phase one includes 296 units in four buildings, while phase three comprises 241 units across three buildings.

    The works are scheduled for completion in late 2028.

    Bay Grove Residences will ultimately comprise 1,154 homes across 15 buildings. Planning is under way for the remaining 617 homes in phases two and four, with further contract awards expected.

    In August last year, Nakheel awarded a AED2.6bn ($708m) contract to Abu Dhabi-based Fibrex Contracting to build the Bay Villas project at Dubai Islands. The contract includes constructing 636 villas.

    In April this year, another AED527m ($143m) contract was awarded to local firm Al-Nasr Contracting Company to construct the primary infrastructure and utilities works on Island B at the development.

    The Dubai Islands development consists of five islands spanning 18.6 square kilometres. It features more than 59 kilometres (km) of waterfront and 20km of beaches, as well as parks, golf courses, promenades and cycling paths.

    The offshore island project gained renewed momentum in 2022, when Nakheel unveiled a new masterplan and rebranded it as Dubai Islands.

    The reclaimed islands were originally part of the Palm Deira project, which was partially completed before being put on hold in 2008.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748850/main.jpg
    Yasir Iqbal
  • Aldar and Mubadala acquire Masdar City Square

    17 September 2026

    Abu Dhabi-based sovereign wealth fund Mubadala Investment Company and local developer Aldar have completed the acquisition of Masdar City Square at Masdar City, in a transaction valued at AED918m ($250m).

    The deal was executed through their joint venture established in 2024.

    Masdar City Square comprises more than 47,000 square metres (sq m) of net leasable area across seven office buildings.

    Completed in Q1 2026, the development is 99% occupied. Tenants include Taqa, the Department of Energy, Emirates College and the Mohamed Bin Zayed University of Artificial Intelligence.

    The transaction expands the joint venture’s real estate portfolio in Masdar City, which is now valued at AED4.7bn ($1.3bn).

    Masdar City is one of the region’s leading hubs for clean energy, artificial intelligence, advanced research and sustainable urban development.

    The joint venture acquired The Link project at Masdar City for AED654m ($178m) in April.

    Comprising about 32,000 sq m of net leasable area across five buildings, The Link is fully leased to a portfolio of major tenants, including Abu Dhabi Future Energy Company (Masdar) and the Mohamed Bin Zayed University of Artificial Intelligence.

    The asset includes Grade A, Leed Platinum office space, a net-zero-energy headquarters building, a multi-use hall and residential accommodation, supporting its position as a high-performing, integrated component of Masdar City.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748241/main5814.png
    Yasir Iqbal
  • Neom tenders Oxagon highway contract

    17 September 2026

     

    Saudi Arabia’s Neom has tendered a design-and-build contract covering permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also covers one bridge and three interchanges.

    The project duration is 22 months.

    Contractors have been given until 21 September to submit their proposals.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED exclusively reported in August 2025 that contractors had submitted responses to the expressions of interest notice that Neom had issued earlier that month.

    The project is expected to support the movement of cargo vehicles from Duba Port to other parts of the country and the wider region.

    Neom tested a pilot initiative last year by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19746896/main.gif
    Yasir Iqbal