Neom becomes real-world building project

26 April 2023

This package on Neom also includes:

> SITE REPORT: World’s largest piling project shifts to The Line’s marina
> INTERVIEW: Neom to fix construction
> MOVIE SET: Neom advances plans to be leading movie destination
> TUNNELS: Neom tenders Delta Junction tunnel contracts
> OXAGON: Work to start for $1.5bn Oxagon wind turbine plant


 

The launch of Neom by Saudi Arabia’s Crown Prince Mohammed bin Salman at the Future Investment Initiative (IFI) in Riyadh in October 2017 challenged the world’s imagination and marked the beginning of Saudi Arabia’s gigaprojects era.

Strategically located close to neighbouring Jordan and Egypt, the 26,500 square-kilometre project is about the size of Belgium.  With a $500bn price tag, it quickly became known as the world’s largest construction project.

In the six years that followed, there has been a steady wave of announcements detailing the individual components of Neom. Each launch has been accompanied by marketing campaigns showcasing slick computer-generated imagery (CGI) of futuristic cities that aim to change how mankind will live. 

Unless working on these projects directly, Neom has been an abstract idea for most people. That started to change in January when Neom released a progress video of construction work on Sindalah Island, which is due to open its doors in 2024. Then in March, MEED visited Neom to witness the work progressing The Line, which is now the world’s largest piling project. 

The images of construction equipment toiling on site showed that after six years of planning, Neom is here.

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar 

Awards soar 

As Neom morphs from a futuristic concept into a real-world building project, the construction industry has started to benefit from a sharp increase in contract awards, which by mid-April 2023 totalled $27bn. 

As construction activity ramps up, the data shows that Neom is no longer a single project offering tactical opportunities. It has become a strategic market in its own right. 

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar. 

On a submarket level, the total value of contract awards exceeds the Saudi capital Riyadh, where there were $11bn of awards, and Dubai, which has traditionally been regarded as a hotbed of construction, with $9.3bn of awards in 2022. 

As tendering activity continues for major contracts, Neom’s prominence as a projects market will likely increase further. 

So far, four major components of Neom have been officially launched by Prince Mohammed. They are The Line, Trojena,
Oxagon and Sindalah Island. Meanwhile, work has also progressed on other projects that have yet to be officially launched with the full CGI treatment, such as Neom International airport and the Gulf of Aqaba.

The Line was the first to be launched in January 2021 as a 170-kilometre linear belt of hyper-connected, car-free communities. Then in July 2022, the designs of The Line’s mirrored buildings were revealed. They are 200 metres wide and 500 metres above sea level, running entirely on renewable energy. Once complete, The Line will accommodate 9 million residents.

Piling work has started for the first modules of buildings that make up The Line (click here for images of the site). Infrastructure work for The Spine, the infrastructure corridor parallel to The Line that includes the high-speed rail, is also advancing.

Floating city

The second major project launch was Oxagon industrial city in November 2021. It will be built around an integrated port and logistics hub, with its octagonal design minimising environmental impact and optimising land usage. The city will feature the world’s largest floating structure and be powered by 100 per cent clean energy. 

The first major area of construction for Oxagon is the expansion of the existing Duba port. A contract for the first phase of that project was awarded earlier this year and a second phase is being tendered.

In March 2022, Prince Mohammed announced Trojena. Located in the mountains, it has temperatures 10 degrees Celsius lower than other regional cities and offers the potential for snow-covered ski slopes.

Trojena dams face countdown to make it snow

Trojena received added impetus in October last year when it was selected to host the ninth Asian Winter Games in 2029. Trojena will have two competition clusters for the games: a snow cluster for sports, including alpine skiing, snowboarding and slalom; and an ice cluster for sports, including ice hockey, figure skating and curling. The games village will have 14 luxury hotels and be powered entirely by renewable energy.

Construction contracts covering major infrastructure elements such as three major dams are at the tendering stage. Procurement activity is also starting for major buildings such as The Vault, which is a 198-metre-high, 253-metre-wide and 864-metre-long building that will serve as the gateway to Trojena.

Sindalah, Neom’s first luxury island destination, was announced in December 2022 and construction work is advancing (see main image). Once complete, the island will feature a marina, hotels and a golf course. 

Delivering these projects is a major challenge for the construction sector. Resource scarcity is a key issue for all projects in the kingdom, with construction companies already struggling to meet the demand for their services and expertise. Neom, along with its owner, the Public Investment Fund (PIF), is taking steps to address these challenges by investing in local construction firms, attracting international companies, improving payment terms and adopting alternative procurement methods. Despite these efforts, the construction sector faces sustained pressure.

New economy

Neom is much more than just a collection of construction projects. While other projects in the region offer opportunities for the construction sector and associated asset management services such as facilities management and hotel operation, the scale of Neom means it is creating a new economy.

It is an economy that not only aims to support the development of nine sectors to achieve the goals outlined in Vision 2030, but also intends to transform the way those sectors operate. 

The industrial city Oxagon will play a key role. Neom plans to create an integrated port and logistics hub that will be home to seven innovative sectors: sustainable energy, autonomous mobility, water innovation, sustainable food production, health and wellbeing, technology and digital manufacturing, and modern methods of construction. 

The Neom green fuels project is key to Oxagon’s clean energy ambitions. The integrated facility will produce hydrogen to be synthesised into carbon-free ammonia. Full construction work began on the project earlier this year after it reached financial closure. The facility is expected to be commissioned in 2026.

Neom, US-based Air Products and Acwa Power each have a 33.3 per cent stake in Neom Green Hydrogen Company, the special project vehicle implementing the project.

Aviation is another major area of investment. Neom plans to start operating its own airline, Neom Airlines, at the end of 2024 from the existing Neom Bay airport before operating from Neom International – a greenfield development inland close to Tabuk at the end of The Line.

Neom will morph from a construction project into a full-fledged economy

International airport

Plans for the international airport are advancing. US firm Aecom has been awarded a contract to provide project management consultancy services, and a series of construction and supply contracts are due to be tendered this year.

Although not confirmed, it is understood the first phase of the airport will have the capacity to handle 25 million passengers a year. A second phase could take the capacity up to 50 million a year. There is an aspiration for the airport to become the largest in the world, with a capacity of 100 million passengers a year. 

Another sector developing quickly is media. In April, Neom furthered its ambition to become the region’s leading TV and film production hub by opening more stages at its Media Village. The village now has four stages offering 12,000 sq m of production space. Six more stages are under development. Neom is also increasing its resort-style accommodation for cast and crew.

As well as gaining access to filming locations across Neom’s varied landscapes, companies using the facilities can enjoy Neom’s highly attractive production incentives, including cash rebates of over 40 per cent.

As these sectors and others advance, Neom will morph again from a construction project into a full-fledged economy. When launched in 2017, its GDP was projected to reach $100bn by 2030 – equivalent at the time to more than one-seventh of the kingdom’s GDP of $688bn. By focusing on nine high-value sectors, the Neom economy will be an affluent one. Its GDP per capita is projected to become the highest in the world.

Main image: Construction work is advancing on Sindalah Island, which is planned to open in early 2024. Credit: Neom


MEED's April 2023 special report on Saudi Arabia includes:

> GIGAPROJECTS: Saudi Arabia under project pressure
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10787833/main.gif
Colin Foreman
Related Articles
  • Saudi Arabia approves new procurement law

    17 August 2026

    Saudi Arabia’s Council of Ministers has approved a new Government Tenders and Procurement Law (GTPL), introducing changes to public procurement procedures and government contracting.

    The Ministry of Finance announced the approval on 5 August.

    The new law aims to strengthen governance and transparency, improve procurement planning and implementation, and promote fairness and equal opportunities in government contracting.

    The changes give government entities greater flexibility in procurement while introducing new provisions that could affect contractors and suppliers, including contract variations, outstanding payments and procurement procedures.

    Contract flexibility

    According to a Ministry of Finance summary of the key amendments, one of the main changes allows government entities to increase existing contract items by up to 20% of the contract value. Contractor approval is required for increases exceeding 10%, while the total increase from adding new items or increasing existing items cannot exceed 20% of the contract value.

    The amendments also introduce measures addressing outstanding payments to contractors. A government entity cannot make a new award when it has outstanding amounts owed to contractors for works or procurement and the required procedures have not been taken, after notification from the Ministry of Finance.

    Exceptions apply where non-payment relates to ministry procedures or where the government entity has taken the required action on a claim but does not have sufficient budget allocations.

    Single committee

    Under the new law, the committees responsible for opening and examining bids will be merged into a single committee.

    The maximum value for direct procurement will rise from SR100,000 ($26,700) to SR1m ($267,000) while government entities will be required to explain and document their use of direct procurement.

    Direct procurement will also be permitted in cases involving research, development and innovation and certain contracts with professional practitioners.

    The amendments reduce the minimum standstill period following a procurement award from five working days to three working days. Government entities will also be able to negotiate where the best bid exceeds the estimated cost plus the permitted contingency.

    Localisation

    The new framework includes provisions covering industrial localisation and knowledge transfer. The Ministry of Finance said it will issue rules for contracting for these purposes in cooperation with the Local Content and Government Procurement Authority.

    A new regulation will also cover research, development and innovation, including tendering and contracting provisions for these activities.

    Other changes involve contractors’ exposure to penalties. The maximum delay penalty on contracts, excluding supply contracts, will fall from 20% to 15% of contract value. The maximum penalty for non-performance in continuous-performance contracts will also fall from 20% to 15%.

    The value of purchases exempt from providing a final guarantee will rise from SR100,000 ($26,700) to SR300,000 ($80,000). Additional exemptions will apply to contracts with professional practitioners and emergency or urgent cases.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18805103/main.jpg
    Mark Dowdall
  • GCC reviews first phase of water interconnection study

    17 August 2026

    The GCC General Secretariat has completed the first phase of a study examining the feasibility of developing water interconnection projects between GCC member states.

    A two-day workshop reviewing the study’s findings concluded on 12 August at the headquarters of the GCC Interconnection Authority (GCCIA) in Dammam, Saudi Arabia.

    The GCC General Secretariat organised the workshop in cooperation with GCCIA, with representatives from relevant authorities and experts in water, infrastructure and water security taking part.

    Participants reviewed the first phase findings, including an assessment of existing water supply infrastructure and the actual water needs of GCC member states. They also discussed the technical requirements and data needed to complete the study.

    The study is intended to identify practical options and feasible solutions for developing a regional water interconnection network. This includes establishing an implementation roadmap.

    The initiative aims to improve the GCC states’ ability to respond to emergencies and crises and support continuity of water supplies.

    First meeting

    The workshop followed a virtual meeting on 22 July between the GCC General Secretariat and Saudi Arabia’s water authorities as part of the study.

    That meeting, which also involved consultancy Artelia, reviewed the study’s methodology and implementation stages. These include assessing existing water systems across GCC states, their resilience and emergency readiness, and developing technical options for bilateral water interconnection projects.

    In Saudi Arabia, the study is focused primarily on the Eastern Province and Riyadh. It is assessing water production and desalination facilities, transmission pipelines, strategic reservoirs, pumping stations and existing and planned projects.

    The study is also examining potential bilateral connections between Saudi Arabia and Bahrain, Kuwait and Qatar, as well as the possibility of a connection with the UAE.

    The 22 July meeting also discussed potential connection points and routes, water flow directions and the possibility of designing interconnection pipelines to operate in both directions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18802726/main.jpg
    Mark Dowdall
  • Neom’s next phase is crucial to green hydrogen pipeline

    17 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The completion of construction at Neom Green Hydrogen comes at an important point for Saudi Arabia’s wider hydrogen ambitions.

    The project has already shown that a large green hydrogen scheme can secure financing by reaching financial close in 2023 with long-term offtake from Air Products.

    With the facility now moving into commissioning ahead of a targeted commercial operations date next year, Neom could soon give lenders and developers real evidence on the performance, costs and risks of a large-scale green hydrogen project.

    That could be important for projects still moving through development. Acwa’s Yanbu Green Hydrogen Hub, for example, is targeting commercial operations in 2030.

    The project has brought in Germany’s EnBW as a co-developer and minority investor and Japan’s Itochu as a co-developer, investor and offtaker. Acwa is targeting production of 2.5 million tonnes a year of green ammonia from the hub.

    Saudi Arabia is also putting more of the framework around the industry in place. In July, the government granted Acwa exclusive rights to export green hydrogen produced in the kingdom along with its derivatives, including green ammonia, methanol and fuels.

    However, partnerships and policy support alone will not remove the commercial questions facing projects. Yanbu still needs to progress through development and secure the financing needed to move into construction.

    Neom’s financing structure and 30-year offtake may be specific to the project, but its operating performance should give future developers and lenders a clearer reference point for assessing production, reliability and costs.

    While Neom will not make the next projects bankable on its own, if it stays on track and performs as expected, it could give lenders a stronger basis for assessing projects that follow. In the long-run, this could be one of its most important contributions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18800285/main.jpg
    Mark Dowdall
  • Five bid for King Salman Bay construction work

    17 August 2026

     

    Five teams have submitted bids for the contract covering the marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.

    MEED understands that the bids were submitted on 31 July.

    The bidders include:

    • Deme / Archirodon (Belgium/Netherlands)
    • ⁠Van Oord (Netherlands)
    • ⁠Abdulmohsen Altamimi / NMDC Group (local/UAE)
    • ⁠Urbacon / Negida Contracting  (Qatar/Egypt )
    • ⁠Modern Building Leaders / China Harbour (local/China)

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.

    King Salman Bay is expected to be a waterfront development that aims to reshape the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.

    Saudi gigaproject developer Red Sea Global (RSG) is developing the project.

    The latest development follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a materials recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18800910/main.jpg
    Yasir Iqbal
  • PDO allows more time for Al-Ghubar field project prices

    17 August 2026

     

    Petroleum Development Oman (PDO) has allowed contractors additional time to prepare commercial bids for a project to build a new facility to handle additional oil production from the Al-Ghubar field in the sultanate.

    The Al-Ghubar field is located in the Ghaba Salt Basin at Qarn Alam, within majority state-owned PDO’s Block 6 concession area.

    The Al-Ghubar gas-oil gravity drainage (GOGD) facility will be designed as a sour (hydrogen sulphide) facility and is expected to handle maximum oil production of 1,800 standard cubic metres a day (cm/d), a maximum total water flow rate of 10,421 standard cm/d, and maximum gas lift of 256,934 standard cm/d. Production from the planned Al-Ghubar GOGD facility will be exported to PDO’s main oil line.

    Following receipt of the technical bids for the project in July, PDO granted contractors additional time – until 16 August – to submit commercial bids for the project, MEED recently reported.

    The project operator has now extended the deadline for submitting commercial bids to 1 September, sources told MEED.

    PDO floated the tender for the Al-Ghubar GOGD facility project in March, setting an initial bid submission deadline of 4 May, MEED previously reported.

    PDO later extended the deadlines for submission of technical and commercial bids to 26 July and 7 August, respectively. Contractors submitted technical proposals by the revised deadline, according to sources.

    The following contractors, among others, are understood to be bidding for the project:

    • Archirodon (Greece)
    • Engineering for the Petroleum & Process Industries (Egypt) / Petrojet (Egypt)
    • Jereh (China)
    • Kent (UAE)
    • Larsen & Toubro Energy Hydrocarbon (India)

    The scope of work on the Al-Ghubar GOGD facility project covers the engineering, procurement and construction (EPC) of the following:

    • On-plot scope consists of:
      • Production separator  
      • Test separator  
      • Concentric wash tank
      • Wet oil pump
      • Water bath heater
      • Surge tank
      • Gas injection/gas lift compressor (centrifugal)
      • Utilities (Instrument Air compressors, chemical injection skids, drain system, vent system) 
      • Suction scrubber
      • Air coolers
      • Discharge scrubbers
      • Condensate flash drum
      • Atmospheric pressure knock-out drum 
      • Flare system
      • Gas heater
      • Water disposal pump
      • Oil shipping pump
      • New 132kV substation and plant substation (housing 6.6kV & 415-Volt switchboard)
      • New control room
         
    • Off-plot scope consists of:
      • Off-plot pipeline network (bulk header, test header, gathering infrastructure/ gathering line header, instrument air header, water disposal header)
      • Two remote manifold stations 
      • Tie-in connection to main oil line
      • Tie-in to gas network pipeline

    PDO previously intended to tender the Al-Ghubar GOGD project under its framework structure with selected EPC contractors, but eventually tendered it separately.

    PDO is the operator of the Block 6 hydrocarbons concession in Oman, which is the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields, with PDO producing a total of approximately 680,000 barrels a day (b/d) of oil and condensates from those fields.

    The Omani government holds a 60% stake in PDO through Energy Development Oman (EDO). The other shareholders are UK-based Shell (34%), France’s TotalEnergies (4%) and Thailand’s state-owned PTTEP (2%).

    ALSO READ: PDO floats tender for major flare gas monetisation scheme
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18799485/main.jpg
    Indrajit Sen