Neom becomes real-world building project

26 April 2023

This package on Neom also includes:

> SITE REPORT: World’s largest piling project shifts to The Line’s marina
> INTERVIEW: Neom to fix construction
> MOVIE SET: Neom advances plans to be leading movie destination
> TUNNELS: Neom tenders Delta Junction tunnel contracts
> OXAGON: Work to start for $1.5bn Oxagon wind turbine plant


 

The launch of Neom by Saudi Arabia’s Crown Prince Mohammed bin Salman at the Future Investment Initiative (IFI) in Riyadh in October 2017 challenged the world’s imagination and marked the beginning of Saudi Arabia’s gigaprojects era.

Strategically located close to neighbouring Jordan and Egypt, the 26,500 square-kilometre project is about the size of Belgium.  With a $500bn price tag, it quickly became known as the world’s largest construction project.

In the six years that followed, there has been a steady wave of announcements detailing the individual components of Neom. Each launch has been accompanied by marketing campaigns showcasing slick computer-generated imagery (CGI) of futuristic cities that aim to change how mankind will live. 

Unless working on these projects directly, Neom has been an abstract idea for most people. That started to change in January when Neom released a progress video of construction work on Sindalah Island, which is due to open its doors in 2024. Then in March, MEED visited Neom to witness the work progressing The Line, which is now the world’s largest piling project. 

The images of construction equipment toiling on site showed that after six years of planning, Neom is here.

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar 

Awards soar 

As Neom morphs from a futuristic concept into a real-world building project, the construction industry has started to benefit from a sharp increase in contract awards, which by mid-April 2023 totalled $27bn. 

As construction activity ramps up, the data shows that Neom is no longer a single project offering tactical opportunities. It has become a strategic market in its own right. 

In 2022, there were $13.6bn of contract awards at Neom, surpassed only by Saudi Arabia, the UAE and Qatar. 

On a submarket level, the total value of contract awards exceeds the Saudi capital Riyadh, where there were $11bn of awards, and Dubai, which has traditionally been regarded as a hotbed of construction, with $9.3bn of awards in 2022. 

As tendering activity continues for major contracts, Neom’s prominence as a projects market will likely increase further. 

So far, four major components of Neom have been officially launched by Prince Mohammed. They are The Line, Trojena,
Oxagon and Sindalah Island. Meanwhile, work has also progressed on other projects that have yet to be officially launched with the full CGI treatment, such as Neom International airport and the Gulf of Aqaba.

The Line was the first to be launched in January 2021 as a 170-kilometre linear belt of hyper-connected, car-free communities. Then in July 2022, the designs of The Line’s mirrored buildings were revealed. They are 200 metres wide and 500 metres above sea level, running entirely on renewable energy. Once complete, The Line will accommodate 9 million residents.

Piling work has started for the first modules of buildings that make up The Line (click here for images of the site). Infrastructure work for The Spine, the infrastructure corridor parallel to The Line that includes the high-speed rail, is also advancing.

Floating city

The second major project launch was Oxagon industrial city in November 2021. It will be built around an integrated port and logistics hub, with its octagonal design minimising environmental impact and optimising land usage. The city will feature the world’s largest floating structure and be powered by 100 per cent clean energy. 

The first major area of construction for Oxagon is the expansion of the existing Duba port. A contract for the first phase of that project was awarded earlier this year and a second phase is being tendered.

In March 2022, Prince Mohammed announced Trojena. Located in the mountains, it has temperatures 10 degrees Celsius lower than other regional cities and offers the potential for snow-covered ski slopes.

Trojena dams face countdown to make it snow

Trojena received added impetus in October last year when it was selected to host the ninth Asian Winter Games in 2029. Trojena will have two competition clusters for the games: a snow cluster for sports, including alpine skiing, snowboarding and slalom; and an ice cluster for sports, including ice hockey, figure skating and curling. The games village will have 14 luxury hotels and be powered entirely by renewable energy.

Construction contracts covering major infrastructure elements such as three major dams are at the tendering stage. Procurement activity is also starting for major buildings such as The Vault, which is a 198-metre-high, 253-metre-wide and 864-metre-long building that will serve as the gateway to Trojena.

Sindalah, Neom’s first luxury island destination, was announced in December 2022 and construction work is advancing (see main image). Once complete, the island will feature a marina, hotels and a golf course. 

Delivering these projects is a major challenge for the construction sector. Resource scarcity is a key issue for all projects in the kingdom, with construction companies already struggling to meet the demand for their services and expertise. Neom, along with its owner, the Public Investment Fund (PIF), is taking steps to address these challenges by investing in local construction firms, attracting international companies, improving payment terms and adopting alternative procurement methods. Despite these efforts, the construction sector faces sustained pressure.

New economy

Neom is much more than just a collection of construction projects. While other projects in the region offer opportunities for the construction sector and associated asset management services such as facilities management and hotel operation, the scale of Neom means it is creating a new economy.

It is an economy that not only aims to support the development of nine sectors to achieve the goals outlined in Vision 2030, but also intends to transform the way those sectors operate. 

The industrial city Oxagon will play a key role. Neom plans to create an integrated port and logistics hub that will be home to seven innovative sectors: sustainable energy, autonomous mobility, water innovation, sustainable food production, health and wellbeing, technology and digital manufacturing, and modern methods of construction. 

The Neom green fuels project is key to Oxagon’s clean energy ambitions. The integrated facility will produce hydrogen to be synthesised into carbon-free ammonia. Full construction work began on the project earlier this year after it reached financial closure. The facility is expected to be commissioned in 2026.

Neom, US-based Air Products and Acwa Power each have a 33.3 per cent stake in Neom Green Hydrogen Company, the special project vehicle implementing the project.

Aviation is another major area of investment. Neom plans to start operating its own airline, Neom Airlines, at the end of 2024 from the existing Neom Bay airport before operating from Neom International – a greenfield development inland close to Tabuk at the end of The Line.

Neom will morph from a construction project into a full-fledged economy

International airport

Plans for the international airport are advancing. US firm Aecom has been awarded a contract to provide project management consultancy services, and a series of construction and supply contracts are due to be tendered this year.

Although not confirmed, it is understood the first phase of the airport will have the capacity to handle 25 million passengers a year. A second phase could take the capacity up to 50 million a year. There is an aspiration for the airport to become the largest in the world, with a capacity of 100 million passengers a year. 

Another sector developing quickly is media. In April, Neom furthered its ambition to become the region’s leading TV and film production hub by opening more stages at its Media Village. The village now has four stages offering 12,000 sq m of production space. Six more stages are under development. Neom is also increasing its resort-style accommodation for cast and crew.

As well as gaining access to filming locations across Neom’s varied landscapes, companies using the facilities can enjoy Neom’s highly attractive production incentives, including cash rebates of over 40 per cent.

As these sectors and others advance, Neom will morph again from a construction project into a full-fledged economy. When launched in 2017, its GDP was projected to reach $100bn by 2030 – equivalent at the time to more than one-seventh of the kingdom’s GDP of $688bn. By focusing on nine high-value sectors, the Neom economy will be an affluent one. Its GDP per capita is projected to become the highest in the world.

Main image: Construction work is advancing on Sindalah Island, which is planned to open in early 2024. Credit: Neom


MEED's April 2023 special report on Saudi Arabia includes:

> GIGAPROJECTS: Saudi Arabia under project pressure
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10787833/main.gif
Colin Foreman
Related Articles
  • Lessons learnt from a power plant decommissioning

    26 February 2026

     

    Al-Kamil power plant, a 280MW, gas-fired power plant in the Sharqiya region of Oman, was recently decommissioned following nearly 20 years of operations as the country’s second independent power plant.

    The plant reached commercial operation in 2002, at which time it started to supply electricity to Nama Power & Water Procurement Company under a 15-year power purchase agreement that was later extended to the end of 2021. No further extension was granted so, in 2022, the decommissioning process was initiated.

    Al-Kamil power plant was one of the first privately owned power plants in Oman to be decommissioned. The entire process took significantly longer than planned – three years compared to an initial target of 12 months. This was not unexpected, however, as there were not yet any standard processes to follow. Everything was being done for the first time, and proper procedures had to be established.

    Starting decommissioning 

    The decommissioning of a power plant is a complex process and can take as much time to complete as it takes to build a plant. It involves environmental considerations, health and safety protocols, detailed surveys, de-energisation, dismantling, demolition, waste management and the segregation and storage of secondary valuables. 

    Careful planning and management are essential to ensure that decommissioning is accomplished safely, cost-effectively and in accordance with all government environmental standards.

    Consulting on the decommissioning of Al-Kamil were Dubai’s Golden Sands Marketing Consulting (GSMC), appointed in 2021, alongside Abu Dhabi’s Sustainable Water & Power Company (SWPC) and Dubai’s Tractebel Engineering Company (TEC).

    One of the first steps that GSMC undertook was to prepare a master plan covering the entire decommissioning process (see right).

    A site investigation was undertaken by GSMC and SWPC early in the process to determine the condition of the power assets and the overall site. 

    The Al-Kamil power plant was found to have been well maintained, with no major health, safety, security and environment (HSSE) issues.

    SWPC prepared the dismantling guidelines covering all plant equipment, and these were reviewed by TEC. The guidelines covered three main phases: the shut down and isolation of all assets; the de-
    energisation process; and the dismantling of the plant equipment, its removal from site and the demolition of all remaining civil works.

    GSMC designed a sales strategy for the plant equipment, taking into consideration the secondary market for power-related equipment, as well as the scrap market in Oman. A competitive procurement process was also followed in an effort to maximise sales revenues from plant equipment.

    A separate tender was issued to appoint a demolition contractor to remove the remaining civil works, and once this work was complete, a local environmental engineering company undertook a final environmental report to demonstrate that the site was properly cleared and ready for handover to the original owner, the Housing & Urban Planning Ministry.

    Final results

    The decommissioning project went well in terms of HSSE considerations, with no fatalities, no lost-time injuries and no first aid injuries over the more than 243,000 total workhours at the site. 

    There were no material environmental spills or incidents to report, and all above- and below-ground structures were demolished and safely removed from the site in accordance with local requirements. 

    The final environmental report, completed just before handover, showed that the site was effectively in the same condition as it was when originally taken over at the start of construction.

    The decommissioning was also successful from a financial perspective, as revenues from the sale of plant equipment and diesel fuel were beyond what was required to cover the costs associated with the decommissioning process. 

    Lessons learnt 

    Many lessons were learnt during the process that can benefit future power plant decommissioning efforts in the region.

    > Notify key stakeholders early: Key stakeholders are those that have a vested interest in the project, either through ownership of certain assets on site, such as grid connection assets, or via regulation, such as the environmental authority. Many of these stakeholders take time to respond, so notifying key stakeholders early in the process can ensure that unnecessary delays are avoided.

    > Prioritise HSSE: For any future decommissioning project, HSSE must be a top priority, and this should be the focus throughout the entire decommissioning process – at all levels of work and management. 

    The site manager at Al-Kamil installed a 24/7 closed-circuit television camera, which proved to be extremely effective in terms of monitoring progress and identifying potential HSSE issues before they became an incident. This simple and cost-effective practice should be replicated for all future decommissioning projects.

    > Appoint the environmental consultant early in the process: It is advisable to appoint an environmental consultant early in the process. The consultant is needed to coordinate activities with the local environmental authority and obtain a no-objection letter or certificate, complete an environmental management report and an update of the environmental impact assessment, which includes an environmental baseline.

    Ideally, these reports and environmental authority approvals should be completed well before any work is under way at the site. This information is also useful to potential bidders for the sale of equipment, or to contractors involved in the dismantling and demolition process.

    > Submit an environmental management plan for approval: It is unlikely that any environmental authority will provide a no-objection letter or certificate without reviewing the environmental plan. It is therefore necessary to complete the plan early, prior to informing the environmental authority. This can minimise potential delays in starting the decommissioning process. 

    As a general practice, an environmental consultant should be brought on board early in the process, ideally once the overall master plan is approved by the company.

    > Establish a proactive steering committee: This was done at Al-Kamil and proved to be effective when it came to overseeing project progress and dealing with issues as they arose. Certain members of the steering committee visited the site regularly and undertook spot HSSE inspections.

    At Al-Kamil, the overall decommissioning was relatively straightforward as the plant was in a remote area. However, decommissioning a power plant in a busier location, or when part of the power plant remains in operation, is more challenging. Under these circumstances, a steering committee is vital. 

    > Set realistic delivery and completion timelines: Decommissioning a power plant is a complex process. The initial timeline to complete the process for Al-Kamil was one year, which was the best estimate at the time as there were no benchmarks or references in Oman. However, the actual completion time turned out to be three years – longer than the approximately 2.5 years it took to build the plant, from the start of construction in early 2001 to full commercial operation in July 2003.

    Realistic delivery dates should be set for contractors, suppliers and others involved in the decommissioning process. This is likely to result in better pricing, as bidders tend to factor in higher contingencies with shorter or fast-track delivery dates. More realistic delivery dates also help management to allocate staff resources and manage the decommissioning budget. 

    Finally, realistic delivery dates help to manage owner and shareholder expectations regarding project completion.

    Given the experience with Al-Kamil, a reasonable decommissioning timeline for a power plant is probably close to the actual construction timeline for the plant involved.

    > Allow time to maximise revenues from the sale of assets: The market value for Al-Kamil’s power assets was estimated at a value significantly higher than the prevailing scrap value. This was based in part on the value of similar gas turbine units, after adjusting for age, usage and other factors that affect the net market value. However, the company realised a much lower value, even after retendering the equipment sales in an effort to get a better price.

    It appears that prices close to the market rate are only achievable if there is time to find a suitable buyer. This can take many months or even years – typically a longer time than the owners of power plants wish to take. 

    Moreover, as renewables continue to penetrate the market, there is less worldwide demand for used gas turbine units. Prevailing market supply and demand conditions also have a bearing on the sale price for secondary equipment, and this factor needs to be considered.

    If time is of the essence, then power plant owners need to accept the fact that the expected revenues will likely be on the low side, although still higher than the scrap value of the assets. 


    Main image: Picture 1: Al-Kamil power plant as constructed; Picture 2: Post decommissioning 


    https://image.digitalinsightresearch.in/uploads/NewsArticle/15780944/main.gif
  • Abu Dhabi’s Enersol charts acquisitions path

    26 February 2026

     

    With about half of its $1.5bn seed capital still available to deploy, Abu Dhabi- based oil and gas drilling services firm Enersol is firmly on a growth trajectory driven by acquisitions. Since its establishment in November 2023 as a 51:49 joint venture of Adnoc Drilling – a subsidiary of Abu Dhabi National Oil Company (Adnoc Group) – and holding company Alpha Dhabi, Enersol has pursued inorganic growth as its core expansion strategy.

    Having completed four key acquisitions to date, Enersol is now targeting opportunities that will not only expand its portfolio but also enhance the value of its offerings to customers, says the company’s CEO, Dean Watson.

    “The unifying theme that we want to focus on is around the production side of what we call the well lifecycle. Why is that important? For investors it is super important because that’s where we get to the opex [operating expenditure] side, moving away from capex [capital expenditure], achieving completions and recurring revenues. So, with the potential target acquisitions, that’s where we’re focused on,” Watson explains.

    “We think that they [future acquisitions] are going to unify and anchor our current portfolio,” he tells MEED in an interview.

    “We have a lot of dry powder to spend. We have identified targets that we want to go after. We are pursuing a few targets,” Watson says, without revealing details. “With the targets we are after, we want to make sure that they’ve got a presence here in the UAE and Mena. We’re also looking for a global footprint.”

    Completed acquisitions 

    Enersol became the majority shareholder in US oil and gas drilling firm Gordon Technologies in 2024, acquiring a 67.2% stake through two transactions with a combined value of $387m. 

    Louisiana-based Gordon Technologies provides measurement while drilling (MWD) technology. MWD technology captures critical data near the drill bit and transmits it to the surface in real time without interrupting normal drilling operations.

    “Gordon Technologies are number one in North America, by a long way, in terms of market share percentage. It’s quite amazing how big that difference is in terms of how much they dominate [in] North America,” Watson says about the rationale behind Enersol acquiring the majority stake.

    Enersol then initiated a $58m transaction in July 2024 to acquire a 51% majority stake in UAE-based oil and gas services provider NTS Amega from Alpha Dhabi.

    “NTS Amega is a manufacturing business with a rental component,” Watson explains. “It manufactures a product and rents out a portion of it.  What excites us about NTS Amega is its potential to serve as our manufacturing backbone, helping to strengthen and promote our in-country value, as it is based and originated in the UAE.”

    In August of the same year, Enersol started a transaction to fully acquire US-headquartered EV Holdings Limited, paying $45m to UK-based private equity firm Dunedin for 100% of the company’s shares.

    EV Holdings has a significant technology portfolio, with more than 100 pieces of intellectual property, primarily patents. It is a highly technical company that generates vast amounts of data, Watson explains.

    Aligned with Enersol’s focus on technology leadership, EV is the number one provider of downhole camera technology in oil field services. It therefore meets what Watson calls “the key investment criteria we are looking for”.

    In November 2024, Enersol entered into a $223m deal to acquire a 95% equity stake in US-based Deep Well Services (DWS). 

    The acquisition, which was completed in the first quarter of 2025, gives Enersol access to DWS’s hydraulic completion units, complemented by its data analytics software, BoreSite, as well as accredited training programmes designed to enhance operational safety and efficiency.

    We have a lot of dry powder to spend. We have identified targets that we want to go after. We are pursuing a few targets
    Dean Watson, Enersol

    Securing contracts

    Enersol is seeking to leverage the suite of capabilities and technologies it has acquired to secure oil field services contracts in the UAE and the wider regional market, Watson says.

    “We’re very excited about being part of the Adnoc ecosystem. Gordon Technologies, through Turnwell, has just completed its first batch of wells and is currently working on the Turnwell project,” the Enersol CEO says, adding: “Gordon is the MWD provider on that project.”

    Adnoc Drilling signed a term sheet in 2024 to enter into a partnership with the Middle East arm of US oil field services provider SLB and US firm Patterson-UTI International Holdings to form a new company called Turnwell Industries.

    In May of that year, Adnoc Drilling was awarded a major contract, worth about $1.7bn, by its parent Adnoc Group, to provide drilling and associated services for the recovery of unconventional oil and gas resources. Work on this contract is being executed by Turnwell. The broad scope of work on the contract covers drilling and appraisal of 144 unconventional oil and gas wells.

    Separately, DWS won its first contract from Malaysia’s state energy company Petronas last November for deploying its hydraulic completion units and BoreSite systems to support a 12-well unconventional programme in Abu Dhabi.

    Watson is optimistic about Enersol securing additional work in Abu Dhabi from Adnoc Drilling. Beyond its home market, the company is “in active discussions and negotiations with our Saudi joint-venture partner on a major scope of work with Saudi Aramco,” he says.

    Enersol’s growing portfolio and its push to secure contracts across the region also place the company in competition with established oil field services majors. On that subject, Watson concludes: “I believe our offering is unique and does not necessarily compete directly with companies such as SLB or Weatherford. 

    “We will identify a niche that fits between the major players and deliver parallel value through our differentiated offering.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15780622/main.gif
    Indrajit Sen
  • Dubai plans EPC tender for Warsan sewage treatment plant

    25 February 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Municipality is preparing to tender the main construction package for the Warsan sewage treatment plant (STP) by the end of the year, according to sources close to the project.

    The scheme is linked to the deep sewerage tunnels infrastructure programme being implemented by the municipality’s sewerage and recycled water projects department.

    As MEED understands, the Warsan STP had previously been expected to be procured as a public-private partnership (PPP) scheme.

    However, sources confirmed that the main construction package will now be procured as an engineering, procurement and construction (EPC) contract.

    The project involves the construction of a sewage treatment plant with a capacity of about 175,000 cubic metres a day (cm/d), including treatment units, sludge handling systems and associated infrastructure.

    The plant, estimated to cost about $326m, will be developed at the existing Warsan complex, where the municipality is also progressing separate expansion and rehabilitation packages.

    These include Warsan STP Phase 1 (DS-355/1), which involves sewerage and stormwater network upgrades, and Stage 2 of the Al-Warsan sewage treatment plant (DS-203/2), comprising new treatment units

    Kuwait-headquartered Mohammed Abdulmohsin Al-Kharafi & Sons is the main EPC contractor for both projects.

    Separately, the municipality is also progressing the expansion and upgrade of the first and second phases of the Jebel Ali STP.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cm/d.

    Earlier this month, contractors were invited to prequalify for the contract.

    The bid submission deadline is 2 April.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15765751/main.jpg
    Mark Dowdall
  • Aramco firm and Arcapita sign logistics facility deal

    25 February 2026

    Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, has signed an agreement with Bahrain‑headquartered Arcapita Group Holdings to deliver a 1.4-million-square-metre (sq m) built-to-suit logistics complex at King Salman Energy Park (Spark).

    The project will feature a 43,000 sq m temperature-controlled, Grade A warehouse, more than 3,000 sq m of office and staff amenities, 5,300 sq m dedicated to chemical storage, and an open yard spanning about 1.2 million sq m.

    Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.

    It will also be developed in line with internationally recognised sustainability standards, featuring solar (photovoltaic) readiness, EV charging infrastructure and a target of LEED Gold certification.

    The development is aimed at supporting the next stage of Saudi Arabia’s logistics and supply chain expansion.

    Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.

    According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.

    Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy (NTLS) under Saudi Vision 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15765085/main.gif
    Yasir Iqbal
  • Algeria gives bidders more time for 1.2GW plant

    25 February 2026

    Algeria’s state-owned electricity and gas utility Sonelgaz has extended the bid submission deadline for a contract to build a 1,200MW combined-cycle gas-fired power plant in Adrar.

    The project is being procured through Sonelgaz’s power generation subsidiary, Societe Algerienne de l’Electricite et du Gaz – Production de l’Electricite (SPE).

    The new bid submission deadline is 29 April. The main contract was first tendered in April last year, and the deadline has been extended several times since.

    The latest deadline was 26 February.

    The tender is open to local and international companies with experience in delivering large-scale power generation projects and with sufficient technical and financial capacity.

    Algeria’s wider power sector has experienced periods of limited contract activity in recent years. Between 2018 and 2022, virtually no new solar or wind farm contracts were awarded, according to available data from the regional projects tracker MEED Projects.

    In 2023, Sonelgaz Energie Renouvelables, a subsidiary of Algeria’s state-owned utility, awarded 14 of the 15 solar photovoltaic (PV) packages it tendered that year.

    At the time, MEED reported that the 15 packages had a total combined capacity of 2,000MW, requiring at least AD172bn ($1.2bn) of investment.

    However, publicly available data suggests that progress has been slow with several schemes yet to reach full construction or commercial stages.

    Gas-fired combined-cycle plants continue to account for the majority of Algeria’s electricity generation capacity. Data from MEED Projects indicates that more than 5,000MW of oil- and gas-fired power capacity is currently under construction.

    Despite this, new contract awards in 2025 came from three solar schemes.

    This included the construction of a 154MW solar PV plant in Bechar, for which China Power was appointed main contractor in August.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15765079/main.jpg
    Mark Dowdall