Muted public spending hinders global tunnelling
4 April 2025

This package also includes: Traffic drives construction underground
The pipeline of tunnel construction projects around the world as tracked by GlobalData stands at $1.3tn, encompassing projects from announcement to execution.
The total pipeline value reflects the overall values of projects that are either entirely tunnels or that have tunnels as an integral part of the work. The project pipeline includes tunnelling works across a range of sectors, including road and railway development, as well as water and sewerage.
The pipeline of tunnel construction projects around the world currently stands at $1.3tn
Subdued spending
Public spending is anticipated to remain muted globally in the short term, as governments are still trying to curtail expenditure to reduce public debt, thereby constraining investments in public infrastructure. This is affecting the demand for tunnel construction, which heavily relies on public infrastructure development. Elevated construction material prices, high interest rates and labour and skill shortages are expected to discourage new investment, further reducing demand for tunnel construction.
These challenges have already impacted project viability, leading to the withdrawal or postponement of funding for 50 projects in Australia’s $78.6bn infrastructure investment programme due to cost increases of over $21bn. The conflicts in Russia and Ukraine, the situation in Gaza and disruptions to shipping in the Red Sea are weighing on new investment levels, particularly in Eastern Europe and the Middle East and North Africa region due to increased uncertainty.
However, this decrease in new tunnel investment is not expected to be uniform globally, as China’s significant infrastructure investment drive, the US’ Infrastructure and Jobs Act and India’s various infrastructure investment programmes are driving new investment in their respective regions.

|
> Middle East and North Africa (Mena) |
> Western Europe
Western Europe has a tunnel construction project pipeline valued at $329.5bn, with Switzerland leading with $60.6bn of projects, follwed by Germany with $56.8bn. Notable projects include the Turin-Lyon tunnel and the Genoa underwater tunnel. Projects in pre-execution and execution stages total $222.8bn, with the highest-value project being Zurich’s $38.8bn CST (underground cargo) Freight Metro Tunnel.
> Northeast Asia
Northeast Asia’s tunnel construction pipeline is valued at $327.7bn, with China contributing $220.3bn, including the $42.4bn Dalian-Yantai undersea railway tunnel. Japan has projects worth $101.3bn, primarily the $65.2bn Tokyo to Nagoya Maglev Railway Line. Most projects are in later development stages, totalling $198.3bn, or 69.8% of the pipeline.
> Australasia
Australasia’s tunnel construction pipeline totals $150.1bn, with Australia holding $112.9bn, about 75% of the region’s value. The largest project is the $87bn Melbourne Suburban Rail Loop, a 90km rail loop with 13 stations. Construction on six stations began in 2022, with the entire project expected to finish by 2050, though rising costs and labour shortages may affect this.
> North America
North America’s tunnel projects are valued at $92.4bn, with $63.6bn in pre-execution and execution stages. The pipeline includes 921.8km of tunnels, primarily in the US. Railway tunnels are the largest segment at $40.7bn, with the Hudson River Rail Tunnel being the highest-value project at $16bn.
> Southeast Asia
Southeast Asia’s tunnel pipeline is valued at $91.3bn, with $55.1bn under construction. Singapore leads with $45.2bn, mainly from rail tunnel projects. The Land Transport Authority awarded a $199m contract for tunnels connecting MRT stations as part of the Cross Island Line’s second phase.
> Eastern Europe
Eastern Europe’s pipeline is valued at $56.3bn, with $46.9bn in pre-execution and execution stages. Major contributors include Turkiye, Czechia and Romania, which has the largest share at $16.3bn. The $9bn Bucharest Metro Line 5 is a key project expected to complete by 2033, with spending projected to rise in the coming years.
> South Asia
South Asia’s tunnel construction pipeline is valued at $47.9bn, with India contributing $31.9bn, primarily from road tunnels. A notable project is the $1.3bn Thane to Borivali underground tunnel. The pipeline includes 2,043.7km of developments, with spending expected to reach $1.8bn in 2024.
> Latin America
Latin America has a growing tunnel construction pipeline valued at $30.3bn, with $28.7bn in later development stages. The region includes 276.2km of projects, with Colombia leading at 92.1km. The highest-value project is the $9.6bn Bogota Metro, which began construction in early 2021.
> Sub-Saharan Africa
Sub-Saharan Africa’s tunnel construction pipeline is valued at $6.7bn, with 63.7% in pre-execution and execution stages. The pipeline includes 1,580km of projects, primarily in Tanzania, Ethiopia and Kenya. Spending may reach $685.4m in 2025, but investment constraints may limit new projects.
In conclusion, while the global tunnel construction industry faces challenges due to muted spending, high construction material prices and geopolitical uncertainties, significant infrastructure investment initiatives in countries like China, the US and India are expected to continue driving new investment.
Traffic drives construction underground
Exclusive from Meed
-
Engineering progresses on Ras Laffan LNG terminal berths16 September 2026
-
Design completed for Libyan oil field development16 September 2026
-
QatarEnergy selects contractors for offshore oil field expansion16 September 2026
-
Contractors prequalify for Bahrain sports stadium15 September 2026
-
Riyadh Expo signs private real estate development deal15 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Engineering progresses on Ras Laffan LNG terminal berths16 September 2026

Register for MEED’s 14-day trial access
Front-end engineering and design (feed) works are progressing on a QatarEnergy LNG project to build 13 liquefied natural gas (LNG) loading berths at the south export terminal in Qatar’s Ras Laffan Industrial City.
Ras Laffan Industrial City, which lies about 90 kilometres north of Doha, is the world's largest integrated LNG production and export complex, comprising 15 processing trains with a total capacity of 77.5 million tonnes a year (t/y). QatarEnergy began LNG operations at the facility, which houses all its processing trains and export infrastructure, in 1984.
According to sources, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, awarded the feed contract for the project to build 13 LNG berths at the south export terminal at Ras Laffan to Australia-headquartered Worley.
The contract was awarded to Worley in the second quarter of this year. Its duration is estimated to be 200,000-250,000 man hours, sources told MEED.
Ras Laffan’s LNG processing and export capabilities will increase by up to about 63% when the three phases of QatarEnergy’s estimated $40bn North Field LNG expansion project come into operation by the end of this decade. Engineering, procurement and construction (EPC) works on all three projects are progressing.
QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the engineering, procurement, construction and installation of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.
In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.
Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.
QatarEnergy took the final investment decision on the third phase, North Field West (NFW), this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting in February.
Chiyoda carried out the feed work for the NFW LNG project.
The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.
In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and liquefied petroleum gas.
With all three phases under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers in the long term.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19715235/main5946.jpg -
Design completed for Libyan oil field development16 September 2026

Register for MEED’s 14-day trial access
Design work has been completed for a project to develop Libya’s I/R oil field, according to industry sources.
The front-end engineering and design work was completed by a team in the London offices of Italy’s EniProgetti and paves the way for the main engineering, procurement and construction contract to be tendered.
One source said: “At the moment, there is no fixed date for when the invitation to bid for the main contract will be issued, but the project has a lot of momentum and is progressing towards tendering.”
The I/R oil field is located in Murzuq Basin in southwestern Libya.
In June this year, Libya's National Oil Corporation (NOC) signed a unified operating agreement for the field.
The I/R field is operated by Akakus Oil Operations, which is a joint venture of NOC in partnership with Spain’s Repsol, France’s TotalEnergies Repsol, Austria’s OMV and Norway’s Equinor.
The agreement in June was signed by NOC as well as its concession partners.
NOC said the agreement would unify operational and administrative procedures related to field management, optimise resource utilisation and support production sustainability.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19711588/main.jpg -
QatarEnergy selects contractors for offshore oil field expansion16 September 2026

Register for MEED’s 14-day trial access
QatarEnergy has selected contractors for the two main engineering, procurement and construction (EPC) packages of its estimated $4bn-$5bn Maydan Mahzam offshore oil field expansion project in Qatar.
The Qatari energy giant has selected a consortium of state-owned PetroVietnam Technical Services Corporation (PTSC) and Singapore-based Seatrium for package one of the Maydan Mahzam field expansion project, according to sources.
State-owned China Offshore Oil Engineering Company (COOEC) has secured package two of the project, sources told MEED.
Additionally, PTSC has confirmed its contract award for the first engineering, procurement, construction and installation (EPCI) package in a disclosure to the Hanoi Stock Exchange, saying its wholly owned subsidiary PTSC Mechanical & Construction had received a letter of award from QatarEnergy. The company added that “the parties will continue discussions to finalise and execute the definitive contract, which is expected to be signed in October 2026”.
In its filing, PTSC added that its scope of work covers “the provision of engineering, procurement, construction, transportation, offshore installation, hook-up, commissioning and brownfield modification services for the [Maydan Mahzam] project”.
MEED reported in late August that the consortium of PTSC and Seatrium had emerged as the frontrunner for package one of the expansion project.
At the time, US-based McDermott was ahead in the race to win package two. However, COOEC is understood to have presented "better terms to the client in the final rounds of negotiations”, sources said.
QatarEnergy issued the main tender for the Maydan Mahzam oil field expansion project in February 2025, with EPC works divided into four packages, MEED previously reported.
Contractors submitted technical bids for the project’s two main EPC packages in September 2025, sources said.
After QatarEnergy granted several extensions to the deadline for the submission of commercial bids for the two packages – initially set for 1 March – contractors submitted their prices by 21 June, MEED reported.
The following contractors, among others, are understood to have submitted bids for the two main packages of the project:
Package one:
- China Offshore Oil Engineering Company (China)
- Hanwha Ocean (South Korea)
- Hyundai Heavy Industries (South Korea)
- Larsen & Toubro Energy Hydrocarbon (India)
- PetroVietnam Technical Services Corporation (Vietnam) / Seatrium (Singapore)
- Saipem (Italy)
Package two:
- Allseas (Netherlands)
- China Offshore Oil Engineering Company (China)
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- Saipem (Italy)
The Maydan Mahzam oil field lies about 100 kilometres (km) northeast of the Qatari coastline and 28km southeast of Halul Island, located in water depths of about 40 metres. The field, together with the nearby Bul Hanine field, was discovered in the 1960s and has been in production since 1965.
QatarEnergy is undertaking the project to upgrade infrastructure at Maydan Mahzam to extend the life of this maturing asset and maintain productivity over the long term.
The scope of work for package one includes the EPC of seven new topsides, requiring the fabrication of structures weighing more than 78,000 metric tonnes in total. The main process topside will weigh 19,400 metric tonnes, while the other topsides will consist of 10-legged jackets.
The scope also includes modifications to five existing topsides, four new bridges, eight-tonne support platforms with jackets, brownfield work on Halul Island and the installation of pipelines and cables.
The scope of work for package two covers the EPCI of topsides, umbilicals and cables.
ALSO READ: Contractors submit bids for Dukhan field facilities upgrade
In addition to advancing its gas production and liquefied natural gas ambitions, QatarEnergy committed significant capital expenditure last year to increasing oil output capacity from its offshore fields.
In August 2025, QatarEnergy selected contractors for the EPC works on a project to maintain and increase production potential at the Bul Hanine offshore oil field. The EPC scope was divided into three main packages, with COOEC being awarded the first two packages and Qatari contractor Doha Petroleum Construction Company (Dopet) being selected for the third. In addition, COOEC appointed US-based KBR to provide detailed engineering services for the first and second packages.
Separately, last September, QatarEnergy awarded the main EPC contract for a project to add a fifth natural gas liquids (NGL) train at its complex in Mesaieed Industrial City. Indian contractor Larsen & Toubro Energy Hydrocarbon won the contract.
The project, estimated to be worth $2.5bn, aims to build a fifth NGL train with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.
ALSO READ: Contractors prepare bids for North Field West offshore platforms
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19688942/main3340.jpg -
Contractors prequalify for Bahrain sports stadium15 September 2026

Register for MEED’s 14-day trial access
Twenty-one local and Saudi Arabia-based contractors have been prequalified for a contract to build the first phase of the Bahrain International Sports City project in the Sakhir area.
The prequalification stage closed on 13 September.
The notice was first issued on 24 May, with an initial submission deadline of 26 July.
The prequalified firms are:
- Alfanar Projects (Saudi Arabia)
- Al-Ayuni Investment & Contracting (Saudi Arabia)
- Nesma Infrastructure & Technology (Saudi Arabia)
- Shar Construction (Saudi Arabia)
- Saudi Binladin Group (Saudi Arabia)
- Kooheji Contractors (local)
- B1 Trading & Services (local)
- Nass Contracting (local)
- RTCC / IC Ictas (Saudi Arabia / Turkiye)
- Moffareh Alharbi & Partners (Saudi Arabia)
- Al-Sharif Group Holding (Saudi Arabia)
- Cebarco (local)
- Midmac Contracting (Qatar)
- BEC Arabia (Saudi Arabia)
- Shibh Al-Jazira Contracting Company (Saudi Arabia)
- Poullaides Construction Poullaides Construction
- Isam Khairi Kabbani Partners (Saudi Arabia)
- El-Seif Engineering Contracting Company (Saudi Arabia)
- AlBawani (Saudi Arabia)
- Nesma & Partners (Saudi Arabia)
- Modern Building Leaders (Saudi Arabia)
The latest development follows US-based engineering firm Populous winning a BD5m ($13.5m) contract for the development, as MEED reported.
Populous’ scope covers pre-contract consultancy services, including finalising the masterplan and internal infrastructure, completing phase 1A design works and preparing tender documents.
The contract was first tendered in 2021, when Populous emerged as the sole bidder.
At the time, it was reported that the Sports City project would include Bahrain’s largest sports stadium and a multipurpose indoor sports arena.
The project is expected to provide renewed impetus to Bahrain’s construction and transport sector, which has struggled in recent years, with the total value of awarded contracts falling for a third consecutive year.
According to regional project tracker MEED Projects, about $400m-worth of contracts had been awarded in Bahrain by the end of October last year – less than half the $1.2bn recorded during the same period the previous year.
The sector has yet to return to pre-pandemic levels. Before 2020, Bahrain consistently awarded more than $2bn in contracts annually, peaking at nearly $4bn in 2016.
Bahrain’s construction industry is forecast to record average annual growth of 4.9% in 2026-29, supported by investments in transport infrastructure and renewable energy projects aligned with Bahrain’s Economic Vision 2030.
Vision 2030 includes the BD11.3bn ($30bn) Strategic Projects Plan, unveiled in October 2021, encompassing 22 national infrastructure projects. It also includes plans to create five new cities by 2030: Fasht Al-Jarm, Suhaila Island, Fasht Al-Azem, Bahrain Bay and Hawar Islands.
Growth over the forecast period is also expected to be driven by investments under the National Renewable Energy Action Plan, which targets a 30% reduction in carbon emissions by 2035, compared to 2015 levels, and aims to achieve net-zero emissions by 2060.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19670426/main.jpg -
Riyadh Expo signs private real estate development deal15 September 2026
Register for MEED’s 14-day trial access
Saudi Arabia's Expo 2030 Riyadh Company (ERC) has signed an agreement with Riyadh-based developer Mohammed Al-Habib Real Estate Company to develop and deliver Expo Village, the event's residential community.
The project will comprise about 2,300 apartments, housing around 5,500 residents, alongside retail and dining outlets, amenities, services and operational facilities.
The community will be connected to the Expo 2030 Riyadh site via the Expo metro station, as well as to King Khalid International airport and the city’s wider transport network.
The deal marks ERC’s first private-sector partnership deal for the site.
The latest agreement comes as ERC is gearing up to deliver several components of the site. Tendering is ongoing for the Saudi Arabia pavilion, and another tender is out for the delivery of the Souq areas within the expo site.
Site progress
Construction activity at the expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.
Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract for the construction of a new metro station catering to the Expo 2030 site.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Alyamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle (EV) charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.
That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems; and EV charging stations.
The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025, to build and operate facilities for Expo 2030.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19665616/main.jpg