Morocco gas and fertiliser project activity surges

13 July 2023

Maghreb energy project activity doubles
> Morocco fertiliser project progresses towards approval
Morocco fertiliser company plans four solar plants
> Nigeria to invest $12.5bn in Morocco pipeline
> Genel in talks to develop Moroccan oil assets
> Design completed for Moroccan gas project

 


Over the past three years, Morocco has seen a surge in early-stage gas and chemical project activity that could potentially be worth multibillion dollars.

The country is taking advantage of its proximity to Europe and demand for fertilisers as well as its potential to benefit as a possible transit route for natural gas.

At the same time, it is advancing exploration and production projects for natural gas that may pay dividends over the long term.

While many of the projects are in their early stages, and some of the largest projects are highly speculative, it is likely that some will ultimately see contracts awarded over the coming years.

Nigeria pipeline

The planned $25bn Nigeria-Morocco gas pipeline is currently the biggest project in Morocco’s gas sector and is also one of the most speculative.

As the project spans 13 countries, it is complicated and will need cooperation between all of the nations involved to succeed.

Despite the challenges, there has been significant progress on the project.

In April, Nigeria’s National Petroleum Company (NNPC) said it was preparing to invest $12.5bn to secure a 50 per cent equity stake in the project.

At the time, Mallam Mele Kyari, group CEO of NNPC, said the first phase of the front-end engineering and design (feed) work had been completed, and the second phase of the feed work was under way.

Earlier this month, NNPC tendered contracts to carry out survey work for pipeline sections with a bid deadline of 20 September this year.

Morocco will host 1,672 kilometres of the pipeline. The country’s head of state, King Mohammed VI, has described it as a strategic turning point that will significantly advance the development of West Africa. The project will extend for 5,600km in total.

The 13 countries involved in the project signed a memorandum of understanding (MoU) with Morocco’s National Office of Hydrocarbons & Mines in December 2022.

Regasification

Other midstream gas projects active in Morocco include two liquefied natural gas (LNG) regasification terminals.

One of these was first announced in 2021 after Algeria shut down a gas pipeline between the two countries.

The client on this project is Morocco’s Ministry of Energy & Mining, and the terminal is due to be developed near the capital city of Rabat.

It is part of a gas-to-power project, and the entire project is estimated to have a value of $1.3bn.

Contractors have submitted bids on this project, but contracts are yet to be awarded.

The second regasification terminal has an estimated value of $200m and is due to be located in Morocco’s Mohammedia Port.

This project is also being developed by Morocco’s Ministry of Energy & Mining and was first announced in 2021.

Like the project slated to be developed near Rabat, bids have been submitted, but contracts are yet to be awarded.

Upstream

Although Morocco continues to be a net gas importer, there has been progress on upstream gas projects within the country since 2021.

In December last year, the Anchois project offshore Morocco took a step forward after London-based Chariot agreed the key principles of a gas sales deal.

Anchois hosts about 1.5 trillion cubic feet of potential gas resources and is being developed via subsea wells tied back direct to an onshore gas processing plant.

Chariot said that, together with its field partner, state-owned ONHYM, it had agreed key principles for long-term gas sales from Anchois with Morocco’s National Office of Electricity & Drinking Water (Onee).

These principles included gas sales of up to 600 million cubic metres a year on a take-or-pay basis for a minimum of 10 years, with gas to be delivered via the Maghreb-Europe gas pipeline.

Earlier this month, another London-listed oil company, Sound Energy, secured funding to execute the second development phase of the company’s Tendrara production concession in Morocco.

The company confirmed the funding arrangement in a statement and said it has “now received a conditioned offer from the arranger for a maximum financing of $237m”, subject to certain conditions being met by September 2023.

Morocco’s Attijariwafa Bank will finance the gas field’s second development phase.

Sound Energy said that the financial facility will be used for the “design, drilling, construction and operation of wells, a treatment facility and a gas pipeline to transport and sell the natural gas produced under the Tendrara production concession”.

The Tendrara gas development project has a total estimated value of $1bn.

Additionally, in December last year, the Israeli independent oil and gas company NewMed Energy struck a controversial deal to take a stake in an exploration licence offshore the disputed territory of Western Sahara.

Morocco currently controls Western Sahara, although the African Union and United Nations do not recognise Rabat’s sovereignty, while the indigenous Saharawi people are fighting for independence.

NewMed Energy signed an agreement with the Moroccan Ministry for Energy & Mining and Adarco Energy to explore and produce natural gas in the offshore Boujdour Atlantique block.

NewMed and Adarco will each have a 37.5 per cent stake in the licence partnership, while the Moroccan ministry will hold the remaining 25 per cent. The licence has been granted for eight years.

The Boujdour Atlantique block was previously operated by US oil company Kosmos Energy, which held a 55 per cent stake in the permit, while its partner UK company Capricorn – a subsidiary of Cairn Energy – had 20 per cent.

The remaining 25 per cent was in the hands of ONHYM.

Fertilisers

Morocco has seen an uptick in activity in ammonia and fertiliser projects in the wake of the Russia-Ukraine war.

In June 2022, the Moroccan phosphate giant OCP announced that its net income had more than doubled compared to the previous year, mostly attributed to the rise in fertiliser prices due to the war between Russia and Ukraine.

Morocco is among the world's top four exporters of fertiliser products, after Russia, China and Canada.

It has a large fertiliser industry, mainly due to its large phosphate reserves, one of the key minerals from which fertilisers are produced.

In January, OCP announced that it had signed supply agreements with India for 1.7 million tonnes of phosphate-based fertilisers in 2023.

Under the deals, OCP will supply India with 700,000 tonnes of a nitrogen-free fertiliser known as triple super phosphate (TSP), in addition to 1 million tonnes of diammonium phosphate (DAP).

One Moroccan fertiliser project that is seeing progress is the Khemisset potash project in the north of the country.

In April, Emmerson, the company developing the project, said it was progressing towards final approval for the project’s environmental permit.

The potash project is anticipated to have a pre-production cost of $387m. It is expected to be able to produce, on average, 810,000 tonnes of muriate of potash (MOP), with a potassium content of 60 per cent, every year over the mine’s first 19 years of production.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10999825/main.gif
Wil Crisp
Related Articles
  • GE Vernova invests in Xlinks

    2 May 2024

    US-headquartered GE Vernova has invested $10.2m in Xlinks First, the investment company established by UK-based startup Xlinks to deliver the $18bn Morocco-UK power project.

    This investment equates to a minority shareholding in the company, which is developing a project comprising wind and solar generation as well as battery storage, with a total combined capacity of 3,600MW, to be transmitted from Morocco to the UK.

    Xlinks said the investment will “further accelerate delivery and buildout of the project”.

    GE Vernova joins at least four other investors in the project.

    Other investors include Africa Finance Corporation, which invested $14.1m in April; Abu Dhabi National Energy Company (Taqa), $30.7m; the UK’s Octopus Energy, $6.23m; and France’s Total Energies, $25.4m.

    The planned electricity generation and battery storage facilities, located in south Morocco, will be connected exclusively to the UK via 4,000-kilometre high-voltage, direct current (HVDC) cables.

    In December last year, Xlinks signed a contract with Canada-headquartered WSP to provide technical advisory services for the project.

    WSP will support Xlinks with route optimisation, power systems and interface management for the plan to construct the project.

    The Morocco-UK power project entails building 10,500MW solar and wind farms in Morocco’s Guelmim-Oued Noun region and sending 3,600MW a day of energy exclusively to the UK via four 3,800-kilometre HVDC cables.

    The HVDC network is envisaged to run from the UK’s south coast, passing France, Spain and Portugal undersea and then onshore to a planned solar and wind energy project in Morocco.

    This renewable energy-sourced electricity amounts to nearly 8% of the UK’s current requirements, equivalent to powering 7 million homes by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11734222/main5830.jpg
    Jennifer Aguinaldo
  • Awards buoy Oman’s green hydrogen strategy

    2 May 2024

    Commentary
    Jennifer Aguinaldo
    Energy & technology editor

    Oman has awarded two additional land blocks designed to develop green hydrogen projects.

    The latest land block concessions in Dhofar were awarded to two consortiums. One comprises a team of France's EDF Group and EDF Renewables, with partners Japanese Electric Power Development Company (J-Power) and the UK-headquartered Yamna Company.

    Another team comprises UK investment firm Actis and Australian metals firm Fortescue.

    This brings the total number of land blocks awarded through the public auction process spearheaded by Hydrogen Oman (Hydrom) to four, exclusive of the four legacy initiatives signed or agreed upon already.

    *Budgets are MEED estimates if not publicly disclosed. Sources: MEED, Hydrom

    A limited gas supply and network strongly incentivises Oman to build a green hydrogen-centric downstream sector that will provide feedstock to domestic industrial plants and generate derivatives for the local and export markets.

    Stakeholders have implemented a strategy, including setting up an infrastructure company catering to these projects. The target is to generate 1 to 1.5 million tonnes a year (t/y) of green hydrogen by 2030 and 7.5 to 8.5 million t/y by 2050.

    The blueprint envisages a complete green hydrogen ecosystem, from the production of renewable energy and its distribution to electrolysis plants and hydrogen derivatives conversion plants to storage and export terminals.

    Omani ports' existing relationships with European stakeholders and growing alliances with other countries could also help seal future offtake agreements for the planned facilities.

    As things stand, the consortiums that won the land auctions and the legacy initiative partners provide much gravitas to Oman's green hydrogen programme. They comprise energy old guards such as BP and Shell that are keen to decarbonise, private companies aiming to balance their investment portfolios with clean energy investments, and offtakers or trading companies that are grappling with net-zero targets.

    Yet the most obvious question remains. Given the eye-popping foreign direct investments these complex projects entail, not all are likely to achieve a final investment decision within three years. This seems to be the window required for the projects to start production before 2030.

    But like any emerging industry, the risks can only be properly assessed and mitigated as the first projects move toward the execution phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11733331/main.gif
    Jennifer Aguinaldo
  • Operationalise loss and damage fund says Al Jaber

    2 May 2024

    Steps must be taken to ensure a fully functioning Loss and Damage Fund, following an agreement at Cop28 to operationalise the fund, according to Cop28 President Sultan Al Jaber.

    “While delivering an agreement to operationalise the Fund at Cop28 was a huge breakthrough for climate progress more needs to be done,” Al Jaber said during the first board meeting of the fund on 30 April.

    The Loss and Damage Fund, which was first proposed in the 1990s, aims to help developing countries cope with the impact of extreme global warming events such as droughts and floods.

    Al Jaber cited the need to build a fully functioning fund, which will be endorsed at Cop29 in Baku, which will be “disbursing funds soon after and a Fund that delivers lasting, positive, socio-economic impact for decades to come."

    "While it took over three decades to establish this Fund, climate change has not stood still. Every region of the world is now vulnerable…the impacts of climate change are a clear and present danger to lives and livelihoods everywhere."

    Al Jaber’s message resonates closer home given the recent storms hitting the UAE, which brought some emirates to a standstill in mid-April.

    Heavy rainfall inundated Dubai and the Northern Emirates on 16 April, causing flooding and significant property and infrastructure damages.

    A total of $792m has been pledged for loss and damage funding arrangements – of which $662m has been pledged to the Fund to date – including a $100m contribution each from the UAE and Germany and $75m from the UK.   

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11732746/main.jpg
    Jennifer Aguinaldo
  • Norwegian firm to develop Oman wave energy project

    2 May 2024

    Oman's shipping and logistics firm Asyad Group has signed an agreement with Norwegian wave energy company Havkraft to explore the development of wave energy.

    It is the first project of its kind in the sultanate and across the region.

    Havkraft is known globally for pioneering technologies that enable the production of renewable electricity from wave energy.

    According to Havkraft Middle East adviser Matt Minshall, wave power has the potential to be the “most eco-friendly and cost-effective route to net zero”.

    Oceans cover 78% of the earth’s and waves have the potential for energy with the reliability of a constantly charged battery, and have remained untouched, according to Minshall.

    The Norwegian startup reached a breakthrough in 2013 when it successfully developed the Havkraft Wave Energy Converter (H-Wec), which is suited for "all types of wave climates globally."

    Since then, the company has launched several solutions, including the deployment of a floating power-plant powered entirely by wave energy.

    Havkraft envisages a supersystem – a combination of solar, wind and wave power – to achieve a more resilient and sustainable energy mix while reducing dependence on expensive storage.

    Photo: Asyad

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11732539/main.jpeg
    Jennifer Aguinaldo
  • Saudi Arabia foregoes April nuclear deadline

    2 May 2024

     

    Register for MEED's guest programme 

    The 30 April bid deadline for nuclear technology providers to submit bids for a contract to build Saudi Arabia’s Duwaiheen nuclear power plant project has passed without any clear indication of a new tender closing date, according to two sources familiar with the project.

    “The understanding is that the tendering process requires a level of [political] stability in the region. This seems like an automatic postponement for the project tendering process,” one of the sources said.

    Companies that have been invited and are expected to bid for the contract include:

    • China National Nuclear Corporation (CNNC, China)
    • Korea Electric Power Corporation (Kepco, South Korea)
    • Rosatom (Russia) 
    • EDF Group (France)

    The project is in the so-called bid invitation specification stage, and there are no direct negotiations between the client and the potential bidders at this stage, MEED reported in July 2023.

    Saudi Arabia plans to build a large-scale nuclear power plant facility as part of its energy diversification agenda. 

    However, the ongoing conflict between Israel, Gaza and other neighbouring countries appears to be a major contributing factor in the extended procurement timeline of the Duwaiheen nuclear plant project.

    In October, an industry source said the ongoing conflict in Gaza is not likely to help advance negotiations between the countries with a key stake in the project.

    It is understood that Riyadh is using its nuclear power plant project, along with its plan to enrich uranium sources as part of its industrial strategy, as a bargaining chip with the US government. The White House is pushing for the normalisation of relations between Israel and Saudi Arabia and opposed to uranium enrichment.

    A month before the latest conflict between Israel and Hamas started, it was reported that senior Palestinian officials were in Riyadh for talks with senior Saudi and US officials.

    According to a BBC report in September 2023, the Palestinians were negotiating for hundreds of millions of dollars and more control of land in the occupied West Bank in the event of a three-way deal between Israel, Saudi Arabia and the US.

    On 14 October, Saudi Arabia suspended the talks on potentially normalising ties with Israel, which it never officially recognised as an independent state.

    Consultants

    Duwaiheen Nuclear Energy Company received three bids for the project management consultancy package for the nuclear plant project last year.

    MEED understands the following companies submitted proposals for the contract:

    • Atkins (UK/Canada)
    • Worley (Australia)
    • Assystems (France)

    Two of the three bidders have had previous engagements with the Saudi nuclear energy project. 

    2.8GW project

    The Duwaiheen nuclear power plant is expected to be procured using a traditional design-and-build model. 

    In September 2016, MEED reported that Saudi Arabia was carrying out technical and economic feasibility studies for the first reactors, and was also looking at possible locations for the kingdom’s first nuclear project, a 2.8GW facility.

    A site at Khor Duwaiheen, on the coast near the UAE and Qatari borders, was subsequently chosen for the first project.

    In March 2022, Saudi Arabia announced the establishment of a holding company – understood to be the Duwaiheen Nuclear Energy Company – to develop nuclear power projects in the country to produce electricity, desalinate seawater and support thermal energy applications.


    MEED's April 2024 special report on Saudi Arabia includes:

    > GVT & ECONOMY: Saudi Arabia seeks diversification amid regional tensions
    > BANKING: Saudi lenders gear up for corporate growth
    > UPSTREAM: Aramco spending drawdown to jolt oil projects
    > DOWNSTREAM: Master Gas System spending stimulates Saudi downstream sector

    > POWER: Riyadh to sustain power spending
    > WATER: Growth inevitable for the Saudi water sector
    > CONSTRUCTION: Saudi gigaprojects propel construction sector
    > TRANSPORT: Saudi Arabia’s transport sector offers prospects

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11729932/main3634.jpg
    Jennifer Aguinaldo