Morocco gas and fertiliser project activity surges

13 July 2023

> Maghreb energy project activity doubles
> Morocco fertiliser project progresses towards approval
> Morocco fertiliser company plans four solar plants
> Nigeria to invest $12.5bn in Morocco pipeline
> Genel in talks to develop Moroccan oil assets
> Design completed for Moroccan gas project

 


Over the past three years, Morocco has seen a surge in early-stage gas and chemical project activity that could potentially be worth multibillion dollars.

The country is taking advantage of its proximity to Europe and demand for fertilisers as well as its potential to benefit as a possible transit route for natural gas.

At the same time, it is advancing exploration and production projects for natural gas that may pay dividends over the long term.

While many of the projects are in their early stages, and some of the largest projects are highly speculative, it is likely that some will ultimately see contracts awarded over the coming years.

Nigeria pipeline

The planned $25bn Nigeria-Morocco gas pipeline is currently the biggest project in Morocco’s gas sector and is also one of the most speculative.

As the project spans 13 countries, it is complicated and will need cooperation between all of the nations involved to succeed.

Despite the challenges, there has been significant progress on the project.

In April, Nigeria’s National Petroleum Company (NNPC) said it was preparing to invest $12.5bn to secure a 50 per cent equity stake in the project.

At the time, Mallam Mele Kyari, group CEO of NNPC, said the first phase of the front-end engineering and design (feed) work had been completed, and the second phase of the feed work was under way.

Earlier this month, NNPC tendered contracts to carry out survey work for pipeline sections with a bid deadline of 20 September this year.

Morocco will host 1,672 kilometres of the pipeline. The country’s head of state, King Mohammed VI, has described it as a strategic turning point that will significantly advance the development of West Africa. The project will extend for 5,600km in total.

The 13 countries involved in the project signed a memorandum of understanding (MoU) with Morocco’s National Office of Hydrocarbons & Mines in December 2022.

Regasification

Other midstream gas projects active in Morocco include two liquefied natural gas (LNG) regasification terminals.

One of these was first announced in 2021 after Algeria shut down a gas pipeline between the two countries.

The client on this project is Morocco’s Ministry of Energy & Mining, and the terminal is due to be developed near the capital city of Rabat.

It is part of a gas-to-power project, and the entire project is estimated to have a value of $1.3bn.

Contractors have submitted bids on this project, but contracts are yet to be awarded.

The second regasification terminal has an estimated value of $200m and is due to be located in Morocco’s Mohammedia Port.

This project is also being developed by Morocco’s Ministry of Energy & Mining and was first announced in 2021.

Like the project slated to be developed near Rabat, bids have been submitted, but contracts are yet to be awarded.

Upstream

Although Morocco continues to be a net gas importer, there has been progress on upstream gas projects within the country since 2021.

In December last year, the Anchois project offshore Morocco took a step forward after London-based Chariot agreed the key principles of a gas sales deal.

Anchois hosts about 1.5 trillion cubic feet of potential gas resources and is being developed via subsea wells tied back direct to an onshore gas processing plant.

Chariot said that, together with its field partner, state-owned ONHYM, it had agreed key principles for long-term gas sales from Anchois with Morocco’s National Office of Electricity & Drinking Water (Onee).

These principles included gas sales of up to 600 million cubic metres a year on a take-or-pay basis for a minimum of 10 years, with gas to be delivered via the Maghreb-Europe gas pipeline.

Earlier this month, another London-listed oil company, Sound Energy, secured funding to execute the second development phase of the company’s Tendrara production concession in Morocco.

The company confirmed the funding arrangement in a statement and said it has “now received a conditioned offer from the arranger for a maximum financing of $237m”, subject to certain conditions being met by September 2023.

Morocco’s Attijariwafa Bank will finance the gas field’s second development phase.

Sound Energy said that the financial facility will be used for the “design, drilling, construction and operation of wells, a treatment facility and a gas pipeline to transport and sell the natural gas produced under the Tendrara production concession”.

The Tendrara gas development project has a total estimated value of $1bn.

Additionally, in December last year, the Israeli independent oil and gas company NewMed Energy struck a controversial deal to take a stake in an exploration licence offshore the disputed territory of Western Sahara.

Morocco currently controls Western Sahara, although the African Union and United Nations do not recognise Rabat’s sovereignty, while the indigenous Saharawi people are fighting for independence.

NewMed Energy signed an agreement with the Moroccan Ministry for Energy & Mining and Adarco Energy to explore and produce natural gas in the offshore Boujdour Atlantique block.

NewMed and Adarco will each have a 37.5 per cent stake in the licence partnership, while the Moroccan ministry will hold the remaining 25 per cent. The licence has been granted for eight years.

The Boujdour Atlantique block was previously operated by US oil company Kosmos Energy, which held a 55 per cent stake in the permit, while its partner UK company Capricorn – a subsidiary of Cairn Energy – had 20 per cent.

The remaining 25 per cent was in the hands of ONHYM.

Fertilisers

Morocco has seen an uptick in activity in ammonia and fertiliser projects in the wake of the Russia-Ukraine war.

In June 2022, the Moroccan phosphate giant OCP announced that its net income had more than doubled compared to the previous year, mostly attributed to the rise in fertiliser prices due to the war between Russia and Ukraine.

Morocco is among the world's top four exporters of fertiliser products, after Russia, China and Canada.

It has a large fertiliser industry, mainly due to its large phosphate reserves, one of the key minerals from which fertilisers are produced.

In January, OCP announced that it had signed supply agreements with India for 1.7 million tonnes of phosphate-based fertilisers in 2023.

Under the deals, OCP will supply India with 700,000 tonnes of a nitrogen-free fertiliser known as triple super phosphate (TSP), in addition to 1 million tonnes of diammonium phosphate (DAP).

One Moroccan fertiliser project that is seeing progress is the Khemisset potash project in the north of the country.

In April, Emmerson, the company developing the project, said it was progressing towards final approval for the project’s environmental permit.

The potash project is anticipated to have a pre-production cost of $387m. It is expected to be able to produce, on average, 810,000 tonnes of muriate of potash (MOP), with a potassium content of 60 per cent, every year over the mine’s first 19 years of production.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10999825/main.gif
Wil Crisp
Related Articles
  • Adnoc Onshore selects contractors for well tie-ins project

    27 October 2026

     

    Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.

    Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields. 

    The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.

    Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.

    Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.

    The project budget is estimated at $1.2bn.

    Bidders for the contract are understood to have included:

    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Jereh (China)
    • Kalpataru Projects International (India)
    • Matrix Construction (UAE)
    • Robt Stone Middle East (UAE)
    • Target Engineering Construction Company (UAE)

    The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg
    Indrajit Sen
  • Ashghal tenders Al-Udeid air base access road works

    27 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.

    The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road. 

    The tender was issued on 22 October, with a submission deadline of 22 November.

    The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.

    Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.

    The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.

    The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.

    The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.

    Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.

    The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.

    Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.

    Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.

    For joint-venture bids, the lead partner must hold the required classification grade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg
    Yasir Iqbal
  • Saudi Arabia gauges interest for Al-Ula wastewater expansion

    27 October 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) is conducting market sounding for the first phase of the Mughayra wastewater treatment plant (WWTP) expansion before formally starting its tendering process, according to industry sources.

    The project is valued at SR400m ($107m) and is intended to increase the Mughayra plant’s wastewater treatment capacity to 62,000 cubic metres a day.

    RCU is gauging interest from potential contractors and has not yet issued a prequalification questionnaire, a source said.

    The scheme forms part of Saudi Arabia’s broader investment drive to develop its cultural and tourism offering across Al-Ula.

    The commission launched its Journey Through Time Masterplan in April 2021, with implementation scheduled in three phases through 2035. The masterplan covers infrastructure development, water management and irrigation, alongside the regeneration of a 9-kilometre cultural oasis.

    French engineering firm Artelia previously noted in its 2025 annual corporate report that it is involved in the design phase of the Mughayra WWTP.

    RCU is also developing strategic potable-water storage infrastructure in Al-Ula, including a design-and-build project covering a 50,000-cubic-metre reservoir at Hub 06 and a 15,000-cubic-metre reservoir at Hub 08.

    Local contractor Bin Omairah previously confirmed that it is serving as the engineering, procurement and construction contractor for the storage facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950333/main.jpg
    Mark Dowdall
  • Qatari firm wins $147m Syria road deal

    27 October 2026

    Qatari contractor Al-Mohannadi for Roads, Trading & Contracting has signed a $147m contract with Syria’s General Directorate of Roads to rehabilitate and expand a 215-kilometre (km) highway corridor connecting to the Iraqi border.

    The project covers the rehabilitation and dualisation of a 170km section linking the Al-Busairi junction to the Al-Tanf border crossing, alongside the construction of a 45km link between the Al-Sabaa Biyar junction and Al-Busairi. Work is scheduled for completion within 900 days.

    The agreement was signed in Damascus by Moaz Najjar, director-general of the General Directorate of Roads, and Abdullah Adnan Al-Zattam, chief executive of Al-Mohannadi, in the presence of Syrian Transport Minister Yarob Badr and Finance Minister Mohammad Yusr Barnieh.

    The upgrade is intended to restore and expand one of Syria’s primary overland arteries to Iraq, which has suffered significant deterioration and capacity bottlenecks following years of conflict. The Al-Tanf corridor represents the most direct overland link between Damascus, central Syrian industrial centres and Baghdad.

    The project is designed to accommodate heavier commercial freight vehicles and reduce transit times between the two countries.

    The investment also forms part of broader efforts to re-establish Syria’s role as a regional transit corridor connecting Mediterranean ports with landlocked trade routes into Iraq and the wider region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950332/main.gif
    Yasir Iqbal
  • Adnoc showcases $16.3bn local manufacturing potential

    27 October 2026

    Abu Dhabi National Oil Company (Adnoc Group) has identified more than AED60bn ($16.3bn) in local manufacturing opportunities through 2030.

    The Abu Dhabi energy company also announced changes to its procurement, supplier registration and In-Country Value (ICV) localisation frameworks.

    The measures were announced at the second Make it with Adnoc Forum, held in Abu Dhabi on October 25. They are intended to give manufacturers, suppliers and investors greater visibility of future demand and a faster, clearer route to compete for Adnoc contracts, the company said.

    The more than 200 manufacturing opportunities cover products required for Adnoc’s projects and operations, including:

    • Rotating equipment and power
    • Electrical, control and automation systems
    • Drilling and completion equipment
    • Chemicals and catalysts
    • Piping, fabrication and heavy equipment
    • Spare parts and advanced manufacturing

    Many of the identified products are currently imported, Adnoc said. “Manufacturing them in the UAE shortens lead times, reduces exposure to global supply disruptions and strengthens the resilience of Adnoc’s operations,” it said in its statement.

    Adnoc, the UAE Ministry of Industry & Advanced Technology and the Abu Dhabi Investment Office (Adio) will work together to connect manufacturers with these opportunities. The collaboration will combine visibility of Adnoc’s demand, access to the national industrial database and financing through the National Industrial Resilience Fund, the company said.

    Adnoc also signed two memorandums of understanding on the sidelines of the forum with Adio and Kezad Group.

    ICV scheme expansion

    Adnoc announced the expansion of its Local+ programme, part of its ICV framework, to more than 100 UAE manufacturers, compared with 70 at its launch in May. The programme gives UAE-made products priority in Adnoc projects by requiring engineering, procurement and construction (EPC) contractors bidding for new tenders to source relevant products from manufacturers approved under the programme.

    Separately, Adnoc announced a redesign of its supplier registration and prequalification process. The company is targeting a reduction of up to 80% in the time required for suppliers to complete the process and become eligible to compete for Adnoc opportunities.

    The new model halves the number of required documents and removes prequalification requirements for 60% of service categories.

    A single window brings together registration, qualification and compliance, with requirements tailored to the nature of the work and its level of risk. Artificial intelligence will support document verification and the reuse of existing data, reducing repetitive submissions and administrative processing.

    ALSO READ:
    Adnoc steps up crude oil capacity expansion
    Adnoc funnels billions into boosting gas processing

    “Adnoc’s enhanced ICV model will more closely connect procurement decisions with commercial value and suppliers’ contribution to the UAE economy. Under the new model, commercial and ICV offers will be integrated into a single evaluation model,” the company said.

    “The previous bid-matching approach will be retired, encouraging suppliers to submit their most competitive commercial and ICV offers from the outset. Requirements will be proportionate to contract size and scope.

    “The model also enhances the administration of ICV-related retention payments. Where retention applies, automated calculation and release processes through the Adnoc Supplier Hub will improve transparency, reduce manual follow-up and support suppliers’ cash flow as obligations are met.”

    Alongside the ICV and registration enhancements, Adnoc outlined a new commercial approach built around four strategic shifts: agile, competitive, strategic and forward-looking.

    “The approach will advance simpler procurement and faster decision-making, contracting models aligned with project and market dynamics, targeted commercial negotiations and earlier visibility of Adnoc’s future demand.”

    Since its launch in 2018, Adnoc’s ICV programme has directed more than AED307bn ($83.6bn) into the UAE economy, the company said. By the end of 2025, it had also supported the localisation of more than 130 products, the development of 95 UAE factories, and employment opportunities for more than 27,500 Emiratis at participating private sector companies.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20948385/main5518.jpg
    Indrajit Sen