Morocco gas and fertiliser project activity surges

13 July 2023

Maghreb energy project activity doubles
> Morocco fertiliser project progresses towards approval
Morocco fertiliser company plans four solar plants
> Nigeria to invest $12.5bn in Morocco pipeline
> Genel in talks to develop Moroccan oil assets
> Design completed for Moroccan gas project

 


Over the past three years, Morocco has seen a surge in early-stage gas and chemical project activity that could potentially be worth multibillion dollars.

The country is taking advantage of its proximity to Europe and demand for fertilisers as well as its potential to benefit as a possible transit route for natural gas.

At the same time, it is advancing exploration and production projects for natural gas that may pay dividends over the long term.

While many of the projects are in their early stages, and some of the largest projects are highly speculative, it is likely that some will ultimately see contracts awarded over the coming years.

Nigeria pipeline

The planned $25bn Nigeria-Morocco gas pipeline is currently the biggest project in Morocco’s gas sector and is also one of the most speculative.

As the project spans 13 countries, it is complicated and will need cooperation between all of the nations involved to succeed.

Despite the challenges, there has been significant progress on the project.

In April, Nigeria’s National Petroleum Company (NNPC) said it was preparing to invest $12.5bn to secure a 50 per cent equity stake in the project.

At the time, Mallam Mele Kyari, group CEO of NNPC, said the first phase of the front-end engineering and design (feed) work had been completed, and the second phase of the feed work was under way.

Earlier this month, NNPC tendered contracts to carry out survey work for pipeline sections with a bid deadline of 20 September this year.

Morocco will host 1,672 kilometres of the pipeline. The country’s head of state, King Mohammed VI, has described it as a strategic turning point that will significantly advance the development of West Africa. The project will extend for 5,600km in total.

The 13 countries involved in the project signed a memorandum of understanding (MoU) with Morocco’s National Office of Hydrocarbons & Mines in December 2022.

Regasification

Other midstream gas projects active in Morocco include two liquefied natural gas (LNG) regasification terminals.

One of these was first announced in 2021 after Algeria shut down a gas pipeline between the two countries.

The client on this project is Morocco’s Ministry of Energy & Mining, and the terminal is due to be developed near the capital city of Rabat.

It is part of a gas-to-power project, and the entire project is estimated to have a value of $1.3bn.

Contractors have submitted bids on this project, but contracts are yet to be awarded.

The second regasification terminal has an estimated value of $200m and is due to be located in Morocco’s Mohammedia Port.

This project is also being developed by Morocco’s Ministry of Energy & Mining and was first announced in 2021.

Like the project slated to be developed near Rabat, bids have been submitted, but contracts are yet to be awarded.

Upstream

Although Morocco continues to be a net gas importer, there has been progress on upstream gas projects within the country since 2021.

In December last year, the Anchois project offshore Morocco took a step forward after London-based Chariot agreed the key principles of a gas sales deal.

Anchois hosts about 1.5 trillion cubic feet of potential gas resources and is being developed via subsea wells tied back direct to an onshore gas processing plant.

Chariot said that, together with its field partner, state-owned ONHYM, it had agreed key principles for long-term gas sales from Anchois with Morocco’s National Office of Electricity & Drinking Water (Onee).

These principles included gas sales of up to 600 million cubic metres a year on a take-or-pay basis for a minimum of 10 years, with gas to be delivered via the Maghreb-Europe gas pipeline.

Earlier this month, another London-listed oil company, Sound Energy, secured funding to execute the second development phase of the company’s Tendrara production concession in Morocco.

The company confirmed the funding arrangement in a statement and said it has “now received a conditioned offer from the arranger for a maximum financing of $237m”, subject to certain conditions being met by September 2023.

Morocco’s Attijariwafa Bank will finance the gas field’s second development phase.

Sound Energy said that the financial facility will be used for the “design, drilling, construction and operation of wells, a treatment facility and a gas pipeline to transport and sell the natural gas produced under the Tendrara production concession”.

The Tendrara gas development project has a total estimated value of $1bn.

Additionally, in December last year, the Israeli independent oil and gas company NewMed Energy struck a controversial deal to take a stake in an exploration licence offshore the disputed territory of Western Sahara.

Morocco currently controls Western Sahara, although the African Union and United Nations do not recognise Rabat’s sovereignty, while the indigenous Saharawi people are fighting for independence.

NewMed Energy signed an agreement with the Moroccan Ministry for Energy & Mining and Adarco Energy to explore and produce natural gas in the offshore Boujdour Atlantique block.

NewMed and Adarco will each have a 37.5 per cent stake in the licence partnership, while the Moroccan ministry will hold the remaining 25 per cent. The licence has been granted for eight years.

The Boujdour Atlantique block was previously operated by US oil company Kosmos Energy, which held a 55 per cent stake in the permit, while its partner UK company Capricorn – a subsidiary of Cairn Energy – had 20 per cent.

The remaining 25 per cent was in the hands of ONHYM.

Fertilisers

Morocco has seen an uptick in activity in ammonia and fertiliser projects in the wake of the Russia-Ukraine war.

In June 2022, the Moroccan phosphate giant OCP announced that its net income had more than doubled compared to the previous year, mostly attributed to the rise in fertiliser prices due to the war between Russia and Ukraine.

Morocco is among the world's top four exporters of fertiliser products, after Russia, China and Canada.

It has a large fertiliser industry, mainly due to its large phosphate reserves, one of the key minerals from which fertilisers are produced.

In January, OCP announced that it had signed supply agreements with India for 1.7 million tonnes of phosphate-based fertilisers in 2023.

Under the deals, OCP will supply India with 700,000 tonnes of a nitrogen-free fertiliser known as triple super phosphate (TSP), in addition to 1 million tonnes of diammonium phosphate (DAP).

One Moroccan fertiliser project that is seeing progress is the Khemisset potash project in the north of the country.

In April, Emmerson, the company developing the project, said it was progressing towards final approval for the project’s environmental permit.

The potash project is anticipated to have a pre-production cost of $387m. It is expected to be able to produce, on average, 810,000 tonnes of muriate of potash (MOP), with a potassium content of 60 per cent, every year over the mine’s first 19 years of production.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10999825/main.gif
Wil Crisp
Related Articles
  • Oman reveals Sohar airport and Salalah Thumrait Road plans

    21 September 2026

    Oman is planning a new passenger terminal at Sohar Airport to expand regional air connectivity and strengthen the airport’s role in the national aviation network.

    According to Said Bin Hamoud Al-Maawali, Oman’s minister of transport, communications and information technology, new routes are expected to be announced before the end of the year. Potential destinations include Dammam in Saudi Arabia, Gwadar in Pakistan, and southern Iran.

    The planned terminal and additional routes will give residents of northern Oman more travel options.

    Al-Maawali also provided an update on the long-delayed Salalah-Thumrait truck road, saying the project will be procured through a conventional tendering model rather than a public-private partnership (PPP).

    In August 2023, Oman shortlisted five of eight prequalified teams to compete for the Salalah-Thumrait truck road project, which was set to be the sultanate’s first PPP road project.

    The 67-kilometre road project is specially designed for heavy vehicles. 

    The road is a key link in Dhofar’s transport network, connecting Thumrait with Salalah and supporting movement between the interior and the governorate’s main urban and economic centre.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19794881/main.jpg
    Yasir Iqbal
  • SAR tenders design review consultancy for GCC rail link

    18 September 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia Railways (SAR) has issued a request for proposals (RFP) for a design management and review consultant to oversee engineering works on the GCC railway network, the latest step in advancing the long-delayed regional rail link.

    The RFP was issued on 9 September, with a submission deadline of 18 October.

    The tender seeks a consultant to manage, audit and verify deliverables produced by SAR's separately appointed design services consultant, rather than carry out the design itself. The tendering for the design services consultancy is currently in progress.

    Construction will be tendered separately through competitive bidding once designs are approved.

    The GCC railway will run for about 672 kilometres (km) inside Saudi Arabia, linking the kingdom's existing network to Kuwait, Qatar, the UAE and Bahrain, with four sections of about 141km, 200km, 151km and 21km, respectively.

    The line is planned as a single-track, non-electrified corridor for mixed freight and passenger traffic, with a maximum axle load of 32.4 tonnes and passing loops for bidirectional working.

    The appointed consultant will develop a design management and review plan covering governance, interdisciplinary coordination and stage-gate approvals, and will issue formal review and audit reports against SAR's requirements and international standards.

    The scope also covers stakeholder engagement, interface management and oversight of land acquisition activity tied to the design consultant's land acquisition plan.

    Key design stages are expected to take about 16 months: four months for concept design, six for preliminary design and six for issued-for-construction design, each with four weeks of contingency.

    SAR has asked bidders to mobilise a core team from day one. These must include a project director, engineering and design manager, stakeholder manager and lead document controller, all based at SAR's offices, with minimum experience thresholds ranging from three years for junior operators up to 25 years, including 15 in rail, for the project director role.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to cover about 2,186km in total.

    The route length within each member state is as follows:

    • UAE – 684km
    • Saudi Arabia – 672km
    • Oman – 306km
    • Qatar – 283km
    • Kuwait – 145km
    • Bahrain – 36km

    The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80km/h–120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19783331/main.gif
    Yasir Iqbal
  • Tender issued for Libyan gas project

    17 September 2026

    An invitation to bid has been issued for a contract to conduct environmental assessments for the project to expand the Mellitah oil and gas complex in Libya.

    The bid submission deadline is 2pm today (17 September) Libyan time.

    The scope of the project includes provision of:

    • An environmental baseline study (EBS)
    • An environmental impact assessment (EIA)
    • An environmental management plan (EMP)

    The client is Mellitah Oil & Gas (MOG), which is a joint venture of Italy’s Eni and Libya’s National Oil Corporation (NOC).

    MOG is based in Tripoli and operates both onshore and offshore oil and gas facilities.

    The joint venture owns and operates six major oil and gas fields across the North African country.

    According to the tender documents, the company that is awarded the contract will need to prepare environmental management measures in compliance with:

    • Libyan environmental legislation
    • Ministry of Environment requirements
    • NOC environmental guidelines
    • Applicable international environmental standards and best practices

    The expansion of the Mellitah oil and gas complex is part of a project estimated to be worth $8bn.

    The wider project is known as the Mellitah Complex Expansion & CO2 Management Integrated Development Project.

    It has six main packages:

    • Onshore package
    • Offshore Structure A
    • Offshore Structure E
    • Subsea pipeline package
    • Site preparation work
    • Carbon capture and storage facility

    Security issues and political instability have been a major problem for Libya’s oil and gas sector since the country’s civil war started in 2011.

    Earlier this month, the Mellitah oil and gas complex was forced to shut down temporarily due to a protest over deteriorating public services.

    The existing onshore complex includes housing, processing units, storage facilities and export facilities.

    It also serves as the launch point for the Greenstream pipeline, which delivers Libyan gas directly to Italy.

    The planned expansion of the complex will involve:

    • Construction of a new fourth gas processing train
    • Construction of a third condensate train
    • Construction of a third natural gas liquids fractionation train
    • Construction of a fourth sulphur recovery unit train
    • Installation of a hydrogen sulphide enrichment unit
    • Installation of a sulphur recovery unit
    • Construction of other associated facilities

    The Mellitah complex is located about 100 kilometres west of Tripoli and is a key energy facility in the west of the country.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748920/main.png
    Wil Crisp
  • Nakheel awards $218m Dubai Islands buildings deal

    17 September 2026

    Register for MEED’s 14-day trial access 

    Dubai-based developer Nakheel, now part of Dubai Holding, has awarded a main construction contract worth more than AED800m ($218m) for phases one and three of Bay Grove Residences at Dubai Islands.

    The contract was awarded to the local firm Metac General Contracting Company.

    It covers the construction of 537 apartments, comprising one- to four-bedroom units, across seven residential buildings.

    Phase one includes 296 units in four buildings, while phase three comprises 241 units across three buildings.

    The works are scheduled for completion in late 2028.

    Bay Grove Residences will ultimately comprise 1,154 homes across 15 buildings. Planning is under way for the remaining 617 homes in phases two and four, with further contract awards expected.

    In August last year, Nakheel awarded a AED2.6bn ($708m) contract to Abu Dhabi-based Fibrex Contracting to build the Bay Villas project at Dubai Islands. The contract includes constructing 636 villas.

    In April this year, another AED527m ($143m) contract was awarded to local firm Al-Nasr Contracting Company to construct the primary infrastructure and utilities works on Island B at the development.

    The Dubai Islands development consists of five islands spanning 18.6 square kilometres. It features more than 59 kilometres (km) of waterfront and 20km of beaches, as well as parks, golf courses, promenades and cycling paths.

    The offshore island project gained renewed momentum in 2022, when Nakheel unveiled a new masterplan and rebranded it as Dubai Islands.

    The reclaimed islands were originally part of the Palm Deira project, which was partially completed before being put on hold in 2008.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748850/main.jpg
    Yasir Iqbal
  • Aldar and Mubadala acquire Masdar City Square

    17 September 2026

    Abu Dhabi-based sovereign wealth fund Mubadala Investment Company and local developer Aldar have completed the acquisition of Masdar City Square at Masdar City, in a transaction valued at AED918m ($250m).

    The deal was executed through their joint venture established in 2024.

    Masdar City Square comprises more than 47,000 square metres (sq m) of net leasable area across seven office buildings.

    Completed in Q1 2026, the development is 99% occupied. Tenants include Taqa, the Department of Energy, Emirates College and the Mohamed Bin Zayed University of Artificial Intelligence.

    The transaction expands the joint venture’s real estate portfolio in Masdar City, which is now valued at AED4.7bn ($1.3bn).

    Masdar City is one of the region’s leading hubs for clean energy, artificial intelligence, advanced research and sustainable urban development.

    The joint venture acquired The Link project at Masdar City for AED654m ($178m) in April.

    Comprising about 32,000 sq m of net leasable area across five buildings, The Link is fully leased to a portfolio of major tenants, including Abu Dhabi Future Energy Company (Masdar) and the Mohamed Bin Zayed University of Artificial Intelligence.

    The asset includes Grade A, Leed Platinum office space, a net-zero-energy headquarters building, a multi-use hall and residential accommodation, supporting its position as a high-performing, integrated component of Masdar City.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748241/main5814.png
    Yasir Iqbal