Morocco leads Maghreb energy transition

11 July 2023

More on Moroccos power and water sector:

Morocco seeks firms for 400MW pumped storage contract
> Morocco extends Casablanca water PPP deadline
US firm plans 2MW Morocco hydrogen project
China's Tinci plans $280m Morocco lithium-ion plant
> Xlinks to seek construction partners
> Morocco signs $6.4bn electric battery and storage deal
Morocco tenders 900MW power plant contract

 


Morocco is among the list of Maghreb countries that have seen few deals awarded in the power generation sector over the past 12 to 24 months.

The last contract awards it recorded were in April 2022 for the 333MW first phase of the Noor 2 solar photovoltaic (PV) project.

The Moroccan Agency for Sustainable Energy (Masen) and Morocco’s Energy Transition & Sustainable Development Ministry awarded six packages of this tranche to three independent power producer (IPP) developers: Voltalia Maroc, Enel Green Power Morocco and the UAE-based Amea Power.

Xlinks scheme

The country, however, could emerge from the doldrums with key projects such as the $18bn Xlinks on the horizon, enabling it to hold on to its status as the regional leader in renewable energy.

The Morocco-UK power project entails building 10,500MW solar and wind farms in Morocco’s Guelmim-Oued Noun region and sending 3,600MW a day of energy exclusively to the UK via four 3,800-kilometre high-voltage, direct current (HVDC) cables.

MEED understands the first phase of the surveys for the project is complete, with geophysical and geotechnical surveys expected to finish this year and next year.

The HVDC pipeline will pass through Spain, Portugal and France, where permitting processes are being undertaken. Financing sources could include export credit agencies, multilateral development agencies and commercial or investment banks.

Morocco aims to source up to 52 per cent of its energy – up from the current 32 per cent – from renewable sources and reduce greenhouse gas emissions by 45.5 per cent by 2030 

Earlier this year, Xlinks completed an early development funding round that included a $30.7m investment from Abu Dhabi National Energy Company (Taqa) and $6.23m from London-headquartered Octopus Energy Group.  

The UK-based startup is expected to seek interest from original equipment manufacturers and construction partners soon. This will be followed by seeking interest from financial advisers for the project.

Low-carbon molecules

Morocco aims to source up to 52 per cent of its energy – up from the current 32 per cent – from renewable sources and reduce greenhouse gas emissions by 45.5 per cent by 2030.

Thanks to the country’s strategic location and favourable legislative framework, this ambition is drawing investors focused on green hydrogen and derivatives production.

In April, a team led by China Energy International Construction Group signed a memorandum of cooperation to develop a green hydrogen project in a coastal area in southern Morocco.

The planned project involves constructing an integrated green hydrogen-based ammonia production facility. It will require a solar PV power generation plant with a capacity of 2GW and a wind power plant with a capacity of 4GW.

These plants will supply power to an electrolysis plant that can produce 320,000 tonnes of green hydrogen annually, which will then be processed to produce 1.4 million tonnes of green ammonia annually.

Energy China International Construction Group has partnered with Saudi Arabia’s Ajlan & Brothers Company and the local firm Gaia Energy Company for the project.

Amun project

It is the second high-profile green hydrogen project announced for the North African country since April 2022, when Serbia-headquartered renewables developer and investor CWP Global appointed US firm Bechtel to support developing large-scale green hydrogen and ammonia facilities in the country.

The Amun green hydrogen project, which CWP Global plans to develop in Morocco, is understood to require 15GW of renewable energy and has an estimated budget of between $18bn and $20bn.

Along with these projects – which could take several years to implement – several green hydrogen pilot projects are also under way in Morocco.

Africa-focused transitional energy group Chariot, the Mohammed VI Polytechnic University and UK-based hydrogen electrolyser developer Oort Energy are planning several small projects using a polymer electrolyte membrane electrolyser system patented by Oort.

The three parties will run initial proof of concept projects while evaluating the feasibility of implementing large-scale green hydrogen and ammonia production.

One of the pilot projects is intended to be hosted at the research and development unit at state-owned fertiliser producer OCP Group’s facilities in Jorf Lasfar.

US-headquartered Verde Hydrogen also plans to develop and commission a 2MW green hydrogen electrolyser plant project in Morocco, which it expects to complete next year.

Electric vehicle components

Recent developments also point to Morocco potentially becoming a global hotspot for the electric vehicles supply chain.

In July this year, China’s Guangzhou Tinci Materials Technology announced plans to build a lithium-ion battery materials plant in the country. The project capitalises on Morocco’s ample phosphorite ore resources.

The firm’s Singapore unit is expected to invest as much as $280m to set up a project company in the North African country to produce lithium-ion battery materials that can be exported to Europe.

In late May, the Moroccan government and Chinese-European company Gotion High-Tech also signed a preliminary agreement to establish a factory to produce electric car batteries and energy storage systems in the country.

The project is estimated to cost MD65bn ($6.3bn). The planned facility will have the potential to “create a comprehensive battery production solution” with a capacity of 100GW a year. 

Morocco’s minister-delegate in charge of investment, convergence and evaluation of public policies, Mohcine Jazouli, said the factory “will not only contribute to Morocco’s renewable energy and electric transport sector, but also solidify its reputation as an automotive industry powerhouse”.

Traditional energy

Meanwhile, along with its intense drive towards clean energy, Rabat is also making progress on traditional energy projects. The National Office of Electricity & Drinking Water (Onee) last awarded a thermal power plant deal in 2017. So it was a surprise when Onee recently tendered a five-year contract to build and operate an open-cycle 900MW thermal power plant in the country.

To be located along the M18 station point of the Maghreb-to-Europe gas pipeline, the proposed power generation plant will use dual-fuel gas turbines, with diesel fuel as a backup. Onee expects to receive bids for the contract by 5 September.

In addition, the procurement process is under way for a major seawater reverse osmosis (SWRO) desalination plant in Grand Casablanca, which has a design capacity of 548,000 cubic metres a day.

The build-operate-transfer contract is for 30 years, including a three-year construction period and 27 years of operation and management.

Making amends

To its credit, however, Morocco’s sustainable campaign has extended to other sectors that have traditionally used carbon-intensive processes and technologies.

The Washington-based International Finance Corporation (IFC) and OCP Group recently signed a €100m ($111m) green loan to build four solar plants to power OCP’s Morocco operations.

The four solar plants, with a combined capacity of 202MW, will be located in the mining towns of Benguerir and Khouribga, home to Morocco’s largest phosphate reserves.

As captive power plants, they will supply clean energy directly to OCP’s operations. The project is part of OCP’s $13bn green investment programme, which aims to increase its green fertiliser production and transition its operations to green energy by 2030.


More on Libya and Tunisia’s power and water sectors:

Libya awards $1.3bn power plant contract
Italy and Tunisia start $1bn Elmed prequalifications
Acciona and Swicorp to develop 75MW wind project
Suez signs $221m Tunisia wastewater PPP deal
Tunisia tenders 1GW of solar IPP contracts


Libya and Tunisia

Earlier this year, the state-owned General Electricity Company of Libya (Gecol) awarded a joint venture of Qatar-based construction company Urbacon for Trading & Contracting and Egypt’s ElSewedy Electric an engineering, procurement and construction contract for a 1,044MW gas-fired power plant in Libya.

The contract is valued at €1.19bn ($1.29bn). The project is expected to be completed in 26 months and comprises six gas turbines from Germany’s Siemens Energy. The emergency power plant project is located in Zliten.

The power plant is expected to help address the endemic electricity shortage in the country. However, it does little to reduce Libya’s carbon emissions. At under 10MW, the country has the lowest renewable energy installed capacity in the Middle East and North Africa (Mena) region, against a total capacity of 11,000MW as of 2021, according to International Renewable Energy Agency data.

Tunisia, where renewable sources account for at least 8 per cent of its power generation capacity, has also made minor progress over the past few months.

A team of Spain’s Acciona and Saudi investment group Swicorp have partnered to develop a 75MW wind farm in Chenini in Tunisia’s Tataouine governorate.

The Spanish-Saudi team is understood to have agreed to the technical and financial terms of the project, as well as the land lease for installing 14 wind turbines in Djebel Dahar, located 80 kilometres from Djerba.

Each wind turbine will have a capacity of 6MW. The project will require an estimated investment of TD500m ($164m).

Tunisia’s wind potential is estimated at 8,000MW, according to its wind atlas and a study published in 2021 by the German international cooperation agency Giz.

In January this year, the African Development Bank Group approved a $27m and €10m ($10.67m) loan package to co-finance the construction of a 100MW solar power plant in Kairouan, Tunisia.

The approval covers $10m and another €10m from the bank, and a $17m concessional financing from the Sustainable Energy Fund for Africa, a special multi-donor fund managed by the bank.

Additional financing will come from the IFC, the World Bank Group and the Clean Technology Fund (CTF).

The 100MW Kairouan project was part of the first round of solar schemes under Tunisia’s concession regime, launched through an international tender by the Ministry of Industry, SMEs & Cooperatives in 2018.

A consortium formed by Dubai-headquartered Amea Power and TBEA Xinjiang New Energy Company won the contract to develop the scheme in December 2019.

The project is located in El-Metbassta, in the Kairouan North region, about 150km south of the capital, Tunis.


More on Algeria’s power and water sectors:

Sonatrach seeks solar PV consultants
Cosider tenders desalination contract
Sonelgaz tenders 2GW solar schemes
Wetico wins Algeria water desalination contracts


Algeria

Despite a highly tentative approach to adopting low-carbon energy, there are some promising projects in Algeria.

In March, state-owned utility Sonelgaz invited companies to bid for the contract to build 15 solar plants in the country with a combined capacity of 2,000MW.

The solar projects will be built in 11 locations across the North African state.

The locations and capacities of the proposed solar power plants include:

  • Bechar (Abadla): 80MW
  • Bechar (Kenadsa): 120MW
  • Msila (Batmete): 220MW
  • Bordj Bou Arreridj (Ras al-Oued): 80MW
  • Batna (Merouana): 80MW
  • Laghouat: 200MW
  • Ghardaia (Guerrara): 80MW
  • Tiaret (Frenda): 80MW
  • El-Oued (Nakhla): 200MW
  • El-Oued (Taleb Larbi): 80MW
  • Touggort: 130MW
  • Mghaier: 220MW
  • Biskra (Leghrous): 200MW
  • Biskra (Tolga): 80MW
  • Biskra (Khenguet Sidi Nadji): 150MW

In December 2022, Algeria’s Energy Transition & Renewable Energies Ministry (Shaems) also launched a tender to deploy 1,000MW of solar capacity. However, the status of the tender is unclear as of mid-2023.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10991889/main4537.jpg
Jennifer Aguinaldo
Related Articles
  • Local firm bids lowest for Kuwait substation deal

    22 December 2025

    The local Al-Ahleia Switchgear Company has submitted the lowest price of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare (PAHW).

    The bid was marginally lower than the two other offers of KD35.1m and KD35.5m submitted respectively by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.

    PAHW is expected to take about three months to evaluate the prices before selecting the successful contractor.

    The project is one of several transmission and distribution projects either out to bid or recently awarded by Kuwait’s main affordable housing client.

    This year alone, it has awarded two contracts worth more than $100m for cable works at its 1Z, 2Z, 3Z and 4Z 400kV substations at Al-Istiqlal City, and two deals totalling just under $280m for the construction of seven 132/11kV substations in the same township.

    Most recently, it has tendered two contracts to build seven 132/11kV main substations at its affordable housing project, west of Kuwait City. The bid deadline for the two deals covering the MS-01 through to MS-08 substations is 8 January.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305745/main.gif
    Edward James
  • Saudi-Dutch JV awards ‘supercentre’ metals reclamation project

    22 December 2025

    The local Advanced Circular Materials Company (ACMC), a joint venture of the Netherlands-based Shell & AMG Recycling BV (SARBV) and local firm United Company for Industry (UCI), has awarded the engineering, procurement and construction (EPC) contract for the first phase of its $500m-plus metals reclamation complex in Jubail.

    The contract, estimated to be worth in excess of $200m, was won by China TianChen Engineering Corporation (TCC), a subsidiary of China National Chemical Engineering Company (CNCEC), following the issue of the tender in July 2024.

    Under the terms of the deal, TCC will process gasification ash generated at Saudi Aramco’s Jizan refining complex on the Red Sea coast to produce battery-grade vanadium oxide and vanadium electrolyte for vanadium redox flow batteries. AMG will provide the licensed technology required for the production process.

    The works are the first of four planned phases at the catalyst and gasification ash recycling ‘Supercentre’, which is located at the PlasChem Park in Jubail Industrial City 2 alongside the Sadara integrated refining and petrochemical complex.

    Phase 2 will expand the facility to process spent catalysts from heavy oil upgrading facilities to produce ferrovanadium for the steel industry and/or additional battery-grade vanadium oxide.

    Phase 3 involves installing a manufacturing facility for residue-upgrading catalysts.

    In the fourth phase, a vanadium electrolyte production plant will be developed.

    The developers expect a total reduction of 3.6 million metric tonnes of carbon dioxide emissions a year when the four phases of the project are commissioned.

    SARBV first announced its intention to build a metal reclamation and catalyst manufacturing facility in Saudi Arabia in November 2019. The kingdom’s Ministry of Investment, then known as the Saudi Arabian General Investment Authority (Sagia), supported the project.

    In July 2022, SARBV and UCI signed the agreement to formalise their joint venture and build the proposed facility.

    The project has received support from Saudi Aramco’s Namaat industrial investment programme. Aramco, at the time, also signed an agreement with the joint venture to offtake vanadium-bearing gasification ash from its Jizan refining complex.

    Photo credit: SARBV

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305326/main.gif
    Edward James
  • QatarEnergy LNG awards $4bn gas project package

    22 December 2025

    QatarEnergy LNG, a subsidiary of state-owned QatarEnergy, has awarded the main engineering, procurement, construction and installation (EPCI) contract for a major package for the second phase of its North Field Production Sustainability (NFPS) project.

    A consortium comprising the Italian contractor Saipem and state-owned China Offshore Oil Engineering Company (COOEC) has secured the EPCI contract for the COMP5 package. The contract value is $4bn, with Saipem declaring its share to be worth $3.1bn.

    Milan-headquartered Saipem said the contract will run for about five years. The scope of work comprises engineering, procurement, fabrication and installation of two compression complexes, each including a compression platform, a living quarters platform, a flare platform supporting the gas combustion system, and the related interconnecting bridges. Each complex will have a total weight of about 68,000 tonnes.

    Offshore installation operations will be carried out by Saipem’s De He construction vessel in 2029 and 2030.

    MEED previously reported that the following contractors submitted bids for the NFPS phase two COMP5 package:

    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem/China Offshore Oil Engineering Company (Italy/China)

    QatarEnergy LNG, formerly Qatargas, is said to have issued the tender for the NFPS phase two COMP5 package in the first quarter of the year.

    Contractors submitted technical bids for the COMP5 package in late June, while commercial bids were submitted by 8 October, as per sources.

    Based upon initial evaluation of bids by QatarEnergy LNG, L&TEH has emerged as the lowest bidder for the COMP5 package, followed by McDermott, with the consortium of Saipem and COOEC in third place, MEED reported in late October.

    In the weeks following that, the project operator is said to have engaged all bidders for a final round of negotiations, during which the consortium of Saipem and COOEC is believed to have “clinched the deal”, according to sources.

    The detailed scope of work on the COMP5 package covers the EPCI work on the following:

    • Two gas compression platforms, each weighing 30,000-35,000 tonnes, plus jacket
    • Two living quarters platforms, plus jacket
    • Two gas flare platforms, plus jacket
    • Brownfield modification work at two complexes
    NFPS scheme

    QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme requires the state enterprise to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the estimated $40bn-plus programme.

    QatarEnergy has already invested billions of dollars in engineering, procurement and construction works on the two phases of the NFPS project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.

    The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.

    Saipem has been the most successful contractor on the second NFPS phase, securing work worth a total of $8.5bn.

    QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities. The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.

    The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.

    Following that, Saipem won combined packages COMP3A and COMP3B of the NFPS project’s second phase in September last year.

    The scope of work on the combined packages encompasses the EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

    Separately, QatarEnergy LNG awarded McDermott the contract for the NFPS second phase package known as EPCI 1, or COMP1, in July 2023. The scope of work on the estimated $1bn-plus contract is to install a subsea gas pipeline network at the North Field gas development.

    In March this year, India’s Larsen & Toubro Energy Hydrocarbon (LTEH) won the main contract for the combined 4A and 4B package, which is the fourth package of the second phase of the NFPS project and is estimated to be valued at $4bn-$5bn.

    The main scope of work on the package is the EPCI of two large gas compression systems that will be known as CP8S and CP4N, each weighing 25,000-35,000 tonnes. The contract scope also includes compression platforms, flare gas platforms and other associated structures.

    LTHE sub-contracted detailed engineering and design works on the combined 4A and 4B package to French contractor Technip Energies.

    NFPS first phase

    Saipem is also executing the EPCI works on the entire first phase of the NFPS project, which consists of two main packages.

    Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.

    QatarEnergy LNG awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.

    Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.

    The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.

    In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.

    QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.

    Saipem’s scope of work on the package, which is known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.

    Saipem performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305330/main2239.jpg
    Indrajit Sen
  • Managing risk in the GCC construction market

    19 December 2025

     

    The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.

    Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.

    MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.

    The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.

    Systemic risk

    The regional market is characterised by several systemic issues that amplify risks for contractors. 

    The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.

    Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.

    Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:

    > Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.

    > Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.

    > Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.


    Supply-chain erosion

    The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly. 

    Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.

    The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.

    Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.

    The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is. 

    A 10-point checklist for contractors in 2026

    1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract.

    2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement.

    3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing.

    4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects.

    5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement.

    6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues.

    7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client.

    8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively.

    9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit.

    10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need.  Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site.

    MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:

    Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com

    Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com

    Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com

    Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com

    IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com

    White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15289183/main.gif
    Colin Foreman
  • Contractor wins $1.3bn Hudayriyat Island villas deal

    19 December 2025

     

    UK-headquartered construction firm Innovo Group has won a AED5bn ($1.3bn) contract to build two residential developments, Nawayef East and Nawayef West, on Hudayriyat Island.

    Abu Dhabi-based developer Modon Properties awarded the contract.

    The scope of the contract includes the construction of 735 three- to eight-bedroom villas.

    The Hudayriyat Island masterplan was unveiled in 2023. The integrated development comprises residential communities and other leisure and mixed-use facilities.

    The masterplan features 53.5 kilometres (km) of coastline, including 16km of beaches.

    Some of the major destinations on Hudayriyat Island include the Velodrome Abu Dhabi, Surf Abu Dhabi, a wide range of sports, commerce and leisure amenities, the largest park in Abu Dhabi and a 220km-long network of cycle tracks.

    Project developments

    In November 2023, Modon appointed local contractor Trojan General Contracting as the main contractor for the sports hotel, as MEED reported.

    Modon also awarded the local National Marine Dredging Company an $803m enabling works contract in April 2023. 

    Abu Dhabi-based Hilalco completed the construction of mountain bike trails on the island earlier in 2023.

    In November 2022, Chinese contractor China Harbour Engineering Company was awarded the main contract for dredging and reclamation works at Hudayriyat Island.

    In 2019, Modon appointed the local Wade Adams to undertake the initial landscaping and infrastructure works on the island.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15289204/main.jpg
    Yasir Iqbal