Morocco leads Maghreb energy transition
11 July 2023
More on Morocco’s power and water sector:
> Morocco seeks firms for 400MW pumped storage contract
> Morocco extends Casablanca water PPP deadline
> US firm plans 2MW Morocco hydrogen project
> China's Tinci plans $280m Morocco lithium-ion plant
> Xlinks to seek construction partners
> Morocco signs $6.4bn electric battery and storage deal
> Morocco tenders 900MW power plant contract

Morocco is among the list of Maghreb countries that have seen few deals awarded in the power generation sector over the past 12 to 24 months.
The last contract awards it recorded were in April 2022 for the 333MW first phase of the Noor 2 solar photovoltaic (PV) project.
The Moroccan Agency for Sustainable Energy (Masen) and Morocco’s Energy Transition & Sustainable Development Ministry awarded six packages of this tranche to three independent power producer (IPP) developers: Voltalia Maroc, Enel Green Power Morocco and the UAE-based Amea Power.
Xlinks scheme
The country, however, could emerge from the doldrums with key projects such as the $18bn Xlinks on the horizon, enabling it to hold on to its status as the regional leader in renewable energy.
The Morocco-UK power project entails building 10,500MW solar and wind farms in Morocco’s Guelmim-Oued Noun region and sending 3,600MW a day of energy exclusively to the UK via four 3,800-kilometre high-voltage, direct current (HVDC) cables.
MEED understands the first phase of the surveys for the project is complete, with geophysical and geotechnical surveys expected to finish this year and next year.
The HVDC pipeline will pass through Spain, Portugal and France, where permitting processes are being undertaken. Financing sources could include export credit agencies, multilateral development agencies and commercial or investment banks.
Morocco aims to source up to 52 per cent of its energy – up from the current 32 per cent – from renewable sources and reduce greenhouse gas emissions by 45.5 per cent by 2030
Earlier this year, Xlinks completed an early development funding round that included a $30.7m investment from Abu Dhabi National Energy Company (Taqa) and $6.23m from London-headquartered Octopus Energy Group.
The UK-based startup is expected to seek interest from original equipment manufacturers and construction partners soon. This will be followed by seeking interest from financial advisers for the project.
Low-carbon molecules
Morocco aims to source up to 52 per cent of its energy – up from the current 32 per cent – from renewable sources and reduce greenhouse gas emissions by 45.5 per cent by 2030.
Thanks to the country’s strategic location and favourable legislative framework, this ambition is drawing investors focused on green hydrogen and derivatives production.
In April, a team led by China Energy International Construction Group signed a memorandum of cooperation to develop a green hydrogen project in a coastal area in southern Morocco.
The planned project involves constructing an integrated green hydrogen-based ammonia production facility. It will require a solar PV power generation plant with a capacity of 2GW and a wind power plant with a capacity of 4GW.
These plants will supply power to an electrolysis plant that can produce 320,000 tonnes of green hydrogen annually, which will then be processed to produce 1.4 million tonnes of green ammonia annually.
Energy China International Construction Group has partnered with Saudi Arabia’s Ajlan & Brothers Company and the local firm Gaia Energy Company for the project.
Amun project
It is the second high-profile green hydrogen project announced for the North African country since April 2022, when Serbia-headquartered renewables developer and investor CWP Global appointed US firm Bechtel to support developing large-scale green hydrogen and ammonia facilities in the country.
The Amun green hydrogen project, which CWP Global plans to develop in Morocco, is understood to require 15GW of renewable energy and has an estimated budget of between $18bn and $20bn.
Along with these projects – which could take several years to implement – several green hydrogen pilot projects are also under way in Morocco.
Africa-focused transitional energy group Chariot, the Mohammed VI Polytechnic University and UK-based hydrogen electrolyser developer Oort Energy are planning several small projects using a polymer electrolyte membrane electrolyser system patented by Oort.
The three parties will run initial proof of concept projects while evaluating the feasibility of implementing large-scale green hydrogen and ammonia production.
One of the pilot projects is intended to be hosted at the research and development unit at state-owned fertiliser producer OCP Group’s facilities in Jorf Lasfar.
US-headquartered Verde Hydrogen also plans to develop and commission a 2MW green hydrogen electrolyser plant project in Morocco, which it expects to complete next year.
Electric vehicle components
Recent developments also point to Morocco potentially becoming a global hotspot for the electric vehicles supply chain.
In July this year, China’s Guangzhou Tinci Materials Technology announced plans to build a lithium-ion battery materials plant in the country. The project capitalises on Morocco’s ample phosphorite ore resources.
The firm’s Singapore unit is expected to invest as much as $280m to set up a project company in the North African country to produce lithium-ion battery materials that can be exported to Europe.
In late May, the Moroccan government and Chinese-European company Gotion High-Tech also signed a preliminary agreement to establish a factory to produce electric car batteries and energy storage systems in the country.
The project is estimated to cost MD65bn ($6.3bn). The planned facility will have the potential to “create a comprehensive battery production solution” with a capacity of 100GW a year.
Morocco’s minister-delegate in charge of investment, convergence and evaluation of public policies, Mohcine Jazouli, said the factory “will not only contribute to Morocco’s renewable energy and electric transport sector, but also solidify its reputation as an automotive industry powerhouse”.
Traditional energy
Meanwhile, along with its intense drive towards clean energy, Rabat is also making progress on traditional energy projects. The National Office of Electricity & Drinking Water (Onee) last awarded a thermal power plant deal in 2017. So it was a surprise when Onee recently tendered a five-year contract to build and operate an open-cycle 900MW thermal power plant in the country.
To be located along the M18 station point of the Maghreb-to-Europe gas pipeline, the proposed power generation plant will use dual-fuel gas turbines, with diesel fuel as a backup. Onee expects to receive bids for the contract by 5 September.
In addition, the procurement process is under way for a major seawater reverse osmosis (SWRO) desalination plant in Grand Casablanca, which has a design capacity of 548,000 cubic metres a day.
The build-operate-transfer contract is for 30 years, including a three-year construction period and 27 years of operation and management.
Making amends
To its credit, however, Morocco’s sustainable campaign has extended to other sectors that have traditionally used carbon-intensive processes and technologies.
The Washington-based International Finance Corporation (IFC) and OCP Group recently signed a €100m ($111m) green loan to build four solar plants to power OCP’s Morocco operations.
The four solar plants, with a combined capacity of 202MW, will be located in the mining towns of Benguerir and Khouribga, home to Morocco’s largest phosphate reserves.
As captive power plants, they will supply clean energy directly to OCP’s operations. The project is part of OCP’s $13bn green investment programme, which aims to increase its green fertiliser production and transition its operations to green energy by 2030.
More on Libya and Tunisia’s power and water sectors:
> Libya awards $1.3bn power plant contract
> Italy and Tunisia start $1bn Elmed prequalifications
> Acciona and Swicorp to develop 75MW wind project
> Suez signs $221m Tunisia wastewater PPP deal
> Tunisia tenders 1GW of solar IPP contracts
Libya and Tunisia
Earlier this year, the state-owned General Electricity Company of Libya (Gecol) awarded a joint venture of Qatar-based construction company Urbacon for Trading & Contracting and Egypt’s ElSewedy Electric an engineering, procurement and construction contract for a 1,044MW gas-fired power plant in Libya.
The contract is valued at €1.19bn ($1.29bn). The project is expected to be completed in 26 months and comprises six gas turbines from Germany’s Siemens Energy. The emergency power plant project is located in Zliten.
The power plant is expected to help address the endemic electricity shortage in the country. However, it does little to reduce Libya’s carbon emissions. At under 10MW, the country has the lowest renewable energy installed capacity in the Middle East and North Africa (Mena) region, against a total capacity of 11,000MW as of 2021, according to International Renewable Energy Agency data.
Tunisia, where renewable sources account for at least 8 per cent of its power generation capacity, has also made minor progress over the past few months.
A team of Spain’s Acciona and Saudi investment group Swicorp have partnered to develop a 75MW wind farm in Chenini in Tunisia’s Tataouine governorate.
The Spanish-Saudi team is understood to have agreed to the technical and financial terms of the project, as well as the land lease for installing 14 wind turbines in Djebel Dahar, located 80 kilometres from Djerba.
Each wind turbine will have a capacity of 6MW. The project will require an estimated investment of TD500m ($164m).
Tunisia’s wind potential is estimated at 8,000MW, according to its wind atlas and a study published in 2021 by the German international cooperation agency Giz.
In January this year, the African Development Bank Group approved a $27m and €10m ($10.67m) loan package to co-finance the construction of a 100MW solar power plant in Kairouan, Tunisia.
The approval covers $10m and another €10m from the bank, and a $17m concessional financing from the Sustainable Energy Fund for Africa, a special multi-donor fund managed by the bank.
Additional financing will come from the IFC, the World Bank Group and the Clean Technology Fund (CTF).
The 100MW Kairouan project was part of the first round of solar schemes under Tunisia’s concession regime, launched through an international tender by the Ministry of Industry, SMEs & Cooperatives in 2018.
A consortium formed by Dubai-headquartered Amea Power and TBEA Xinjiang New Energy Company won the contract to develop the scheme in December 2019.
The project is located in El-Metbassta, in the Kairouan North region, about 150km south of the capital, Tunis.
More on Algeria’s power and water sectors:
> Sonatrach seeks solar PV consultants
> Cosider tenders desalination contract
> Sonelgaz tenders 2GW solar schemes
> Wetico wins Algeria water desalination contracts
Algeria
Despite a highly tentative approach to adopting low-carbon energy, there are some promising projects in Algeria.
In March, state-owned utility Sonelgaz invited companies to bid for the contract to build 15 solar plants in the country with a combined capacity of 2,000MW.
The solar projects will be built in 11 locations across the North African state.
The locations and capacities of the proposed solar power plants include:
- Bechar (Abadla): 80MW
- Bechar (Kenadsa): 120MW
- Msila (Batmete): 220MW
- Bordj Bou Arreridj (Ras al-Oued): 80MW
- Batna (Merouana): 80MW
- Laghouat: 200MW
- Ghardaia (Guerrara): 80MW
- Tiaret (Frenda): 80MW
- El-Oued (Nakhla): 200MW
- El-Oued (Taleb Larbi): 80MW
- Touggort: 130MW
- Mghaier: 220MW
- Biskra (Leghrous): 200MW
- Biskra (Tolga): 80MW
- Biskra (Khenguet Sidi Nadji): 150MW
In December 2022, Algeria’s Energy Transition & Renewable Energies Ministry (Shaems) also launched a tender to deploy 1,000MW of solar capacity. However, the status of the tender is unclear as of mid-2023.
Exclusive from Meed
-
Firms prepare bids for NWC sewage treatment package 144 September 2026
-
Egyptian contractor wins Abu Dhabi Ramhan Island deal4 September 2026
-
Dubai sets deadline for Jebel Ali waste-to-energy PPP4 September 2026
-
Egypt to invest $4.5bn in refinery upgrades4 September 2026
-
North Field West platform bidders get extra time4 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms prepare bids for NWC sewage treatment package 144 September 2026

At least three contractors are preparing to make offers for package 14 of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, according to sources.
Known as Eastern A Cluster (LTOM14), the package was tendered by the state-owned National Water Company (NWC) in April, with a bid submission deadline of 30 September.
The contract covers the upgrade of six existing sewage treatment plants (STPs), with a capacity expansion of 30,000 cubic metres a day (cm/d) at the Al-Jarodia STP.
This will increase total treatment capacity from about 263,000 cm/d to approximately 293,000 cm/d, with an estimated cost of $180m.
According to sources, the firms preparing to submit bids include:
- Alkhorayef Water & Power Technologies (Saudi Arabia)
- Civil Works Company (Saudi Arabia)
- Miahona (Saudi Arabia)
The latest phase follows the formal signing of a $347m contract between NWC and a Saudi-Chinese consortium for Northern Cluster Sewage Treatment Plants Package 10 (LTOM10) on 2 September.
The same consortium led by United Water (China) is not planning to bid for LTOM14 and is expected to formally sign a contract for LTOM11 in the coming months, a source said.
In April, MEED exclusively reported that the group had won the contract for package 11, which will have a combined capacity of about 440,000 cm/d.
It is also understood that Beijing Enterprises, a bidder for North Western B Cluster (LTOM12), is not preparing to bid for package 14.
In the meantime, the contract for LTOM12 is moving towards award, with bids currently under evaluation.
The contract covers the construction and upgrade of seven STPs with a combined capacity of about 162,000 cm/d. As previously reported, NWC opened financial bids for the project in April.
Future phases
In total, the LTOM programme comprises 19 packages split into two phases. In May 2024, NWC announced it had awarded $2.5bn-worth of contracts in the first phase. Phase two of the programme includes 10 packages covering 117 treatment plants.
In April, MEED exclusively reported that NWC had held several discussions regarding changes in scope details and potential expansions to upcoming projects. This involved “grouping some upcoming projects”.
The request for proposals for LTOM13 was subsequently put on hold and it is now understood that this tender has likely been merged with other packages in the programme.
According to a source, Eastern B Cluster (LTOM15) has also been cancelled and has likely been merged. LTOM15 had comprised two STPs with a total capacity of 152,000 cm/d.
The next contract to be tendered will be Central Cluster (LTOM16), potentially in November, a source added.
Under the original scope, LTOM16 covers the construction of 14 STPs with a total capacity of 153,000 cm/d.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19358188/main.jpg -
Egyptian contractor wins Abu Dhabi Ramhan Island deal4 September 2026
Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.
The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.
Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.
The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.
The development comprises two residential towers offering 187 residential units.
The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.
The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.
Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.
The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.
Mohamed Alabbar launched the Ramhan Island development in May 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg -
Dubai sets deadline for Jebel Ali waste-to-energy PPP4 September 2026

Register for MEED’s 14-day trial access
Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.
The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.
The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.
The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.
Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.
It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.
That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.
The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.
Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.
In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.
Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.
The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation.
The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg -
Egypt to invest $4.5bn in refinery upgrades4 September 2026
Egypt is planning to invest $4.5bn in refinery upgrades, according to the country’s Minister of Petroleum and Mineral Resources, Karim Badawi.
Egyptian refineries are operating at 80% of capacity compared with 66% two years ago, according to Badawi, who wants further increases in utilisation of existing facilities.
“We aim to invest around $4.5bn to develop existing refineries and build new units to reduce imports and achieve self-sufficiency in refined products,” he said in a statement.
In May, Egypt said that it had increased its fuel import budget by almost 40% for the 2026-27 fiscal year amid higher global prices driven by the Iran war, which started when the US and Israel launched an attack on Iran on 28 February.
Brent crude prices are up about a third since the conflict started, trading at more than $90 a barrel for most of this month so far.
Badawi said a decline in Egypt’s oil and gas production between 2021 and 2024 occurred because foreign companies were reluctant to invest in the country’s energy sector due to unpaid government debts.
He said: “We have settled all the debt, which reached $6.1bn in June 2024. As a result, hydrocarbon exploration and production activity grew by nearly 20% this year.
“We are now moving in the right direction to increase oil and gas output gradually.”
Despite the ongoing push to develop projects in the country’s oil and gas sector, several key projects have seen significant delays in recent years.
These include a $2bn hydrocracking complex package that forms part of the wider Assiut oil refinery upgrade project.
Earlier this month, MEED revealed that mechanical completion of the hydrocracking package is now unlikely to be reached until early next year due to complications in the final stages of construction.
The hydrocracking complex package has experienced extensive delays over several years.
In April this year, Badawi called for work to accelerate on the Assiut oil refinery upgrade project, saying it is important for reducing the country’s spending on imported refined products.
At the time, the oil ministry said the project was 88% complete, with trial operations planned by the end of the year.
Assiut Oil Refining Company (ASORC), a subsidiary of state-owned Egyptian General Petroleum Corporation, is the project operator.
France’s Technip Energies is the main contractor, performing engineering, procurement and construction work on the Assiut hydrocracking complex under a $2bn contract awarded by ASORC in February 2020.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19353521/main.jpg -
North Field West platform bidders get extra time4 September 2026

QatarEnergy has granted contractors additional time to prepare bids for a key tender for the engineering, procurement, construction and installation (EPCI) of large platforms for the giant North Field gas field in Qatari waters.
The tender, issued earlier this year, forms part of the wider North Field West (NFW) project, the third and last phase of the state enterprise’s North Field liquefied natural gas (LNG) expansion programme.
The core scope comprises the EPCI of four production deck modules (PDMs) and associated structures. The new PDMs will increase gas production from North Field reservoirs and provide additional gas feedstock for the NFW LNG development.
QatarEnergy has set 15 September as the deadline for technical bid submissions, while commercial bids are due on 10 November, according to sources.
The previous deadlines for submission of technical and commercial bids were 30 August and 25 October, respectively, MEED previously reported.
The following contractors, among others, are understood to be bidding:
- China Offshore Oil Engineering Company (China)
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- Saipem (Italy)
Before issuing the PDM tender, QatarEnergy awarded McDermott a contract for the EPCI of four offshore jackets that will also support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.
North Field LNG expansion
QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three giant projects are progressing.
QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.
QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.
In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.
Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.
QatarEnergy took the final investment decision on NFW this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting (GAC) in February.
Chiyoda carried out the front-end engineering and design (feed) work for the NFW LNG project.
The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.
In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and LPG.
With all three phases now under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers over the long term.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19352006/main.jpg