Monthly briefing: 20 key developments in the region

25 October 2022

By MEED staff


Opec and its allies cut oil output

Saipem wins $4.5bn North Field offshore gas contract

Qatar to inaugurate 800MW solar farm

Lebanon and Israel agree maritime border deal

Aramco launches SME stimulator programme

Region to be third-largest hydrogen source by 2050

Egypt ready to supply natural gas to Lebanon

> Riyadh makes debt announcements

Neom hydrogen project expected to close by year-end

Abu Dhabi transfers ownership of Etihad Airways to ADQ

Mipco secures $4bn to refinance Abu Dhabi plant


OIL OUTPUT CUTS

Opec+ to slash production from November to keep prices high

The Opec+ alliance of oil producers has decided to reduce oil production by 2 million barrels a day (b/d) from November to further shore up crude prices, which have fluctuated amid fears that a global recession could curb oil demand. 

The decision, which was led by Saudi Arabia and Russia, was taken at a meeting of the group in Austria on 5 October. 

The move represents a major reversal in production policy for Opec+, which slashed output by a record 10 million b/d in early 2020 when demand plummeted as a result of the Covid-19 pandemic. Since then, the group has gradually unwound those cuts. Read more

 Tight oil market increases unease for stakeholders



The 33rd Opec and non-Opec ministerial meeting on 5 October. Credit: Opec



US FALLOUT

Saudi Arabia and UAE condemn US warning of ‘consequences’

Saudi Arabia and the UAE have rejected as baseless accusations that the Opec+ decision to reduce oil production from November was politically motivated against the US.

Riyadh has insisted decisions by Opec and its allies were taken “purely on economic considerations”, and said its economic advice had been to resist calls to delay the production cut. 

The UAE issued a statement calling upon the US to refrain from “politicisation” of the Opec+ decision. US President Joe Biden had previously warned that there would be “consequences” for Saudi Arabia and the Opec+ members for their decision to cut oil output.


EGYPT

World leaders to gather for meeting on climate change

Leaders from almost 200 countries will meet in Sharm el-Sheikh, Egypt, on 6-18 November for the UN’s 27th Conference of the Parties (Cop 27) climate change summit. 

Egypt’s International Cooperation Minister, Rania al-Mashat, has previously said that the focus of Cop 27 should be moving from “pledges to implementation”. The conference aims to deliver action on issues critical to tackling the climate emergency, from reducing greenhouse gas emissions, building resilience and adapting to the impacts of climate change, to delivering on the commitments to finance climate action in developing countries.


STEEL

Region could lead global steel decarbonisation efforts

As the global steel industry considers switching to direct reduced iron (DRI) production, the Middle East and North Africa (Mena) region is primed to start producing carbon-neutral steel, according to a report by the Institute for Energy Economics & Financial Analysis. 

“The Mena region can lead the world if it shifts promptly to renewables and applies green hydrogen in its steel sector,” says Soroush Basirat, the author of the report. 

“The region’s steel sector is dominated by direct reduced iron-electric arc furnace technology, which releases lower emissions than the … coal-fuelled blast furnace and basic oxygen furnace process used in 71 per cent of global crude steel production in 2021.” 

The Mena region produced just 3 per cent of global crude steel last  year, but accounted for nearly 46 per cent of the world’s DRI production. 

Basirat adds: “Mena has an established supply of DR-grade iron ore and its iron ore pelletising plants are among the world’s largest.”


SAUDI ARABIA

Riyadh announces government spending increase in 2022-24

Saudi Arabia has announced increases in government spending in 2022-24 of more than 18 per cent, which is close to SR175bn ($47bn) or 4 to 4.5 per cent of GDP. 

The rise in spending targets points to smaller fiscal surpluses in the coming years, according to Moody’s Investors Service. 

Increased spending could contribute to reducing the kingdom’s economic reliance on hydrocarbons, provided the spending is successfully deployed to advance government-sponsored diversification projects.

Saudi Arabia’s finances and ambition align


IRAQ

Prime minister-designate vows to act against corruption

Iraq’s prime minister-designate Mohammed Shia al-Sudani has pledged to take action against corruption after authorities announced that ID3.7tn ($2.5bn) had been embezzled from the General Tax Authority’s trust account held by a branch of Rafidain Bank. 

The Iraqi Integrity Commission has said it is opening an investigation into the theft 

On 13 October, Iraq’s parliament elected Abdul Latif Rashid as the country’s new president. He then tasked Al-Sudani with forming a new government to end a year of political gridlock. 

Al-Sudani faces a challenge in the coming weeks as he attempts to appoint a new cabinet of ministers. Members of the Iraqi political bloc led by Shiite cleric Moqtada al-Sadr have said that they will not join the new government.


YEMEN

Houthi rebels attack oil terminal in southern Yemen

Iran-backed Houthi rebels have claimed responsibility for an attack on a cargo ship at an oil terminal in the south of the country on 21 October. The group said the attack by explosives-laden drones was meant to prevent pro-government forces from using the Al-Dhabba terminal for oil exports. 

The incident occurred in Ash-Shihr in the Hadramawt governorate, and targeted the Marshall Islands-flagged tanker Nissos Kea. The Greek owners of the tanker said it was undamaged. 

The internationally recognised government of Yemen said that its forces had intercepted armed drones launched against the Al-Dhabba oil terminal. 

UN special envoy for Yemen, Hans Grundberg, called the attack a “deeply worrying military escalation”. The Yemeni government sent a letter to the UN Security Council regarding the “threat to disrupt international maritime navigation and target ships and oil infrastructures”. 

The attack was the first military action announced by the Houthis since a truce between Yemen’s warring sides expired on 2 October.


LEBANON-ISRAEL

Lebanon and Israel reach maritime border deal

Lebanon and Israel have forged a deal to end a long-running maritime border dispute in the gas-rich Mediterranean Sea. Lebanon’s deputy speaker Elias Bou Saab said that an agreement had been reached that satisfies both sides. 

It is hoped that the new deal will resolve the two countries’ dispute over a swathe of territory in the Mediterranean Sea in an area where Lebanon aims to explore for natural gas, and near waters where Israel has already found commercially viable quantities of hydrocarbons. Read more


GCC

Region faces green hydrogen production challenges

GCC governments including Oman, Saudi Arabia and the UAE are developing zero-carbon green hydrogen and low-carbon blue hydrogen schemes. However, achieving large-scale production, especially of green hydrogen, will be challenging in the coming years, according to Moody’s Investors Service. 

While both green and blue hydrogen will play a role in reducing the global carbon footprint, only green hydrogen has the potential to reduce the reliance of GCC countries on hydrocarbons, but this will take several years, Moody’s says. 

In the short to medium term, GCC countries’ access to cheap domestic natural gas, their carbon capture and storage expertise, and the limited availability of infrastructure make blue hydrogen production a more viable option than the more expensive and challenging production of green hydrogen.

Region to be third-largest hydrogen source by 2050


https://image.digitalinsightresearch.in/uploads/NewsArticle/10112593/main.gif
MEED Editorial
Related Articles
  • Local firm bids lowest for Kuwait substation deal

    22 December 2025

    The local Al-Ahleia Switchgear Company has submitted the lowest price of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare (PAHW).

    The bid was marginally lower than the two other offers of KD35.1m and KD35.5m submitted respectively by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.

    PAHW is expected to take about three months to evaluate the prices before selecting the successful contractor.

    The project is one of several transmission and distribution projects either out to bid or recently awarded by Kuwait’s main affordable housing client.

    This year alone, it has awarded two contracts worth more than $100m for cable works at its 1Z, 2Z, 3Z and 4Z 400kV substations at Al-Istiqlal City, and two deals totalling just under $280m for the construction of seven 132/11kV substations in the same township.

    Most recently, it has tendered two contracts to build seven 132/11kV main substations at its affordable housing project, west of Kuwait City. The bid deadline for the two deals covering the MS-01 through to MS-08 substations is 8 January.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305745/main.gif
    Edward James
  • Saudi-Dutch JV awards ‘supercentre’ metals reclamation project

    22 December 2025

    The local Advanced Circular Materials Company (ACMC), a joint venture of the Netherlands-based Shell & AMG Recycling BV (SARBV) and local firm United Company for Industry (UCI), has awarded the engineering, procurement and construction (EPC) contract for the first phase of its $500m-plus metals reclamation complex in Jubail.

    The contract, estimated to be worth in excess of $200m, was won by China TianChen Engineering Corporation (TCC), a subsidiary of China National Chemical Engineering Company (CNCEC), following the issue of the tender in July 2024.

    Under the terms of the deal, TCC will process gasification ash generated at Saudi Aramco’s Jizan refining complex on the Red Sea coast to produce battery-grade vanadium oxide and vanadium electrolyte for vanadium redox flow batteries. AMG will provide the licensed technology required for the production process.

    The works are the first of four planned phases at the catalyst and gasification ash recycling ‘Supercentre’, which is located at the PlasChem Park in Jubail Industrial City 2 alongside the Sadara integrated refining and petrochemical complex.

    Phase 2 will expand the facility to process spent catalysts from heavy oil upgrading facilities to produce ferrovanadium for the steel industry and/or additional battery-grade vanadium oxide.

    Phase 3 involves installing a manufacturing facility for residue-upgrading catalysts.

    In the fourth phase, a vanadium electrolyte production plant will be developed.

    The developers expect a total reduction of 3.6 million metric tonnes of carbon dioxide emissions a year when the four phases of the project are commissioned.

    SARBV first announced its intention to build a metal reclamation and catalyst manufacturing facility in Saudi Arabia in November 2019. The kingdom’s Ministry of Investment, then known as the Saudi Arabian General Investment Authority (Sagia), supported the project.

    In July 2022, SARBV and UCI signed the agreement to formalise their joint venture and build the proposed facility.

    The project has received support from Saudi Aramco’s Namaat industrial investment programme. Aramco, at the time, also signed an agreement with the joint venture to offtake vanadium-bearing gasification ash from its Jizan refining complex.

    Photo credit: SARBV

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305326/main.gif
    Edward James
  • QatarEnergy LNG awards $4bn gas project package

    22 December 2025

    QatarEnergy LNG, a subsidiary of state-owned QatarEnergy, has awarded the main engineering, procurement, construction and installation (EPCI) contract for a major package for the second phase of its North Field Production Sustainability (NFPS) project.

    A consortium comprising the Italian contractor Saipem and state-owned China Offshore Oil Engineering Company (COOEC) has secured the EPCI contract for the COMP5 package. The contract value is $4bn, with Saipem declaring its share to be worth $3.1bn.

    Milan-headquartered Saipem said the contract will run for about five years. The scope of work comprises engineering, procurement, fabrication and installation of two compression complexes, each including a compression platform, a living quarters platform, a flare platform supporting the gas combustion system, and the related interconnecting bridges. Each complex will have a total weight of about 68,000 tonnes.

    Offshore installation operations will be carried out by Saipem’s De He construction vessel in 2029 and 2030.

    MEED previously reported that the following contractors submitted bids for the NFPS phase two COMP5 package:

    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem/China Offshore Oil Engineering Company (Italy/China)

    QatarEnergy LNG, formerly Qatargas, is said to have issued the tender for the NFPS phase two COMP5 package in the first quarter of the year.

    Contractors submitted technical bids for the COMP5 package in late June, while commercial bids were submitted by 8 October, as per sources.

    Based upon initial evaluation of bids by QatarEnergy LNG, L&TEH has emerged as the lowest bidder for the COMP5 package, followed by McDermott, with the consortium of Saipem and COOEC in third place, MEED reported in late October.

    In the weeks following that, the project operator is said to have engaged all bidders for a final round of negotiations, during which the consortium of Saipem and COOEC is believed to have “clinched the deal”, according to sources.

    The detailed scope of work on the COMP5 package covers the EPCI work on the following:

    • Two gas compression platforms, each weighing 30,000-35,000 tonnes, plus jacket
    • Two living quarters platforms, plus jacket
    • Two gas flare platforms, plus jacket
    • Brownfield modification work at two complexes
    NFPS scheme

    QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme requires the state enterprise to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the estimated $40bn-plus programme.

    QatarEnergy has already invested billions of dollars in engineering, procurement and construction works on the two phases of the NFPS project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.

    The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.

    Saipem has been the most successful contractor on the second NFPS phase, securing work worth a total of $8.5bn.

    QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities. The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.

    The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.

    Following that, Saipem won combined packages COMP3A and COMP3B of the NFPS project’s second phase in September last year.

    The scope of work on the combined packages encompasses the EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

    Separately, QatarEnergy LNG awarded McDermott the contract for the NFPS second phase package known as EPCI 1, or COMP1, in July 2023. The scope of work on the estimated $1bn-plus contract is to install a subsea gas pipeline network at the North Field gas development.

    In March this year, India’s Larsen & Toubro Energy Hydrocarbon (LTEH) won the main contract for the combined 4A and 4B package, which is the fourth package of the second phase of the NFPS project and is estimated to be valued at $4bn-$5bn.

    The main scope of work on the package is the EPCI of two large gas compression systems that will be known as CP8S and CP4N, each weighing 25,000-35,000 tonnes. The contract scope also includes compression platforms, flare gas platforms and other associated structures.

    LTHE sub-contracted detailed engineering and design works on the combined 4A and 4B package to French contractor Technip Energies.

    NFPS first phase

    Saipem is also executing the EPCI works on the entire first phase of the NFPS project, which consists of two main packages.

    Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.

    QatarEnergy LNG awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.

    Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.

    The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.

    In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.

    QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.

    Saipem’s scope of work on the package, which is known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.

    Saipem performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305330/main2239.jpg
    Indrajit Sen
  • Managing risk in the GCC construction market

    19 December 2025

     

    The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.

    Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.

    MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.

    The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.

    Systemic risk

    The regional market is characterised by several systemic issues that amplify risks for contractors. 

    The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.

    Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.

    Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:

    > Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.

    > Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.

    > Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.


    Supply-chain erosion

    The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly. 

    Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.

    The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.

    Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.

    The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is. 

    A 10-point checklist for contractors in 2026

    1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract.

    2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement.

    3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing.

    4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects.

    5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement.

    6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues.

    7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client.

    8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively.

    9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit.

    10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need.  Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site.

    MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:

    Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com

    Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com

    Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com

    Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com

    IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com

    White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15289183/main.gif
    Colin Foreman
  • Contractor wins $1.3bn Hudayriyat Island villas deal

    19 December 2025

     

    UK-headquartered construction firm Innovo Group has won a AED5bn ($1.3bn) contract to build two residential developments, Nawayef East and Nawayef West, on Hudayriyat Island.

    Abu Dhabi-based developer Modon Properties awarded the contract.

    The scope of the contract includes the construction of 735 three- to eight-bedroom villas.

    The Hudayriyat Island masterplan was unveiled in 2023. The integrated development comprises residential communities and other leisure and mixed-use facilities.

    The masterplan features 53.5 kilometres (km) of coastline, including 16km of beaches.

    Some of the major destinations on Hudayriyat Island include the Velodrome Abu Dhabi, Surf Abu Dhabi, a wide range of sports, commerce and leisure amenities, the largest park in Abu Dhabi and a 220km-long network of cycle tracks.

    Project developments

    In November 2023, Modon appointed local contractor Trojan General Contracting as the main contractor for the sports hotel, as MEED reported.

    Modon also awarded the local National Marine Dredging Company an $803m enabling works contract in April 2023. 

    Abu Dhabi-based Hilalco completed the construction of mountain bike trails on the island earlier in 2023.

    In November 2022, Chinese contractor China Harbour Engineering Company was awarded the main contract for dredging and reclamation works at Hudayriyat Island.

    In 2019, Modon appointed the local Wade Adams to undertake the initial landscaping and infrastructure works on the island.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15289204/main.jpg
    Yasir Iqbal