Middle East project disputes increasing

8 November 2023

 

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.

Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.

The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.

“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.

“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”

Growing pains

Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.

“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.

“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”

HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.

While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.

Saudi resolution

In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.

“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”

Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.

In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.

One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.

Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.

A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.

The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.

“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.

“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.

“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”

Arbitration centres

Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.

He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.

The systems are maturing in Saudi Arabia and will soon reach a similar level.

“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.

But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.

According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.

This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.

Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.

A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.

“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”

With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.

As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11278295/main.jpg
Wil Crisp
Related Articles
  • Bahrain mall to install solar carport

    24 April 2024

    The Avenues-Bahrain has signed a solar power purchase agreement (PPA) with UAE-headquartered solar company Yellow Door Energy (YDE) for a 3.5MW solar carport system encompassing the mall’s entire outdoor parking facility.

    According to the shopping mall operator, YDE will build, operate and maintain the solar carport, which will comprise over 6,000 bi-facial solar panels providing shade for 1,025 parking spots while generating over 5.8 million kilowatt-hours (kWh) of clean energy in its first year.

    The Avenues-Bahrain expects construction of the solar carport to begin soon and be completed by the fourth quarter of 2024.

    The solar carport, covering an area of 23,500 square metres (sqm), will complement the mall’s four-year-old rooftop solar photovoltaic (PV) system, which has a capacity of 250KW and offsets 300 metric tonnes of carbon emissions annually.

    The Avenues-Bahrain win marks YDE’s sixth secured solar project in Bahrain, bringing its total portfolio in the country to over 30MW of awarded solar projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11709324/main.jpg
    Jennifer Aguinaldo
  • No extension for Dubai sewer tunnel prequalification

    24 April 2024

     

    Register for MEED's guest programme 

    Dubai Municipality expects interested engineering, procurement and construction (EPC) companies to submit their statements of qualifications (SOQs) by the end of April for the contracts to develop the Dubai Strategic Sewerage Tunnels (DSST) project.

    “No further extension has been granted,” a source close to the project tells MEED.

    International, regional and local EPC contractors are keen to prequalify to bid for the contracts for the $22bn DSST scheme, which Dubai Municipality is implementing on a public-private partnership (PPP) basis.

    In addition to its size, the project is gaining significant interest due to its unique procurement approach, whereby EPC contractors’ prequalification precedes developers’ prequalification.

    Dubai Municipality is undertaking the prequalification process for EPC contractors ahead of prequalifying companies that can bid for the contracts to develop and operate various packages of the project.

    According to industry sources, the floods resulting from last week’s storm that hit Dubai and other emirates have also made implementing the project more urgent. 

    The bidders for each of the PPP requests for proposals (RFPs) will be prequalified consortiums comprised of sponsors, EPC contractors and operation and management (O&M) contractors.

    MEED previously reported that the overall project will require a capital expenditure of roughly AED30bn ($8bn), while the whole life cost over the full concession terms of the entire project is estimated to reach AED80bn.

    The project aims to convert Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.

    Dubai currently has two major sewerage catchments. The first in Deira is Warsan, where the Warsan sewage treatment plant (STP) treats the flow.

    The second catchment, called Jebel Ali, is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.

    DSST-DLT packages

    Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered separately as PPP packages with concession periods lasting between 25 and 35 years.

    The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres, and the links will extend 10km. 

    The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.

    W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.

    J3, the fourth package, comprises 129km of links. Once completed, Dubai Municipality will operate them, unlike the first three packages, which are envisaged to be operated and maintained by the winning PPP contractors.  

    J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.

    J3 will be procured under a design-build-finance model with a concession period of 25-35 years.

    J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.

    MEED understands the project’s remaining two packages, the expansion and upgrade of the Jebel Ali and Warsan STPs, will be procured in a process separate from the four DSST-DLT components.

    The RFPs for the four DSST-DLT packages will likely be issued sequentially, staggered around six to 12 months apart.

    Dubai Municipality has appointed Abu Dhabi-headquartered Tribe Infrastructure Group as lead and financial adviser, UK-based Ashurst as legal adviser and the US’ Parsons as technical adviser for the DSST project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11708845/main.jpg
    Jennifer Aguinaldo
  • UAE and Oman firms sign $32bn energy deal

    24 April 2024

    Register for MEED's guest programme 

    An industrial and energy project valued at an estimated AED117bn ($31.8bn) topped the recent investment agreements reached between the UAE and Oman following Sultan Haitham Bin Tariq’s visit to the UAE capital earlier this week.

    The package encompasses renewable energy initiatives, including wind and solar projects, alongside green metals production facilities.

    The agreement’s signatories included Abu Dhabi National Energy Company (Taqa), Abu Dhabi Future Energy Company (Masdar), Emirates Global Aluminium, Emirates Steel Arkan, OQ Alternative Energy and Oman Electricity Transmission Company.

    Details of the planned projects have not yet been disclosed, although the production of green steel and green aluminium in either jurisdiction is implied.

    The companies signed the agreements on 22 April in the presence of Sheikh Theyab Bin Mohamed Bin Zayed Al Nahyan, chairman of the Office of Development and Martyrs’ Families Affairs at the Presidential Court, and Sheikh Hamed Bin Zayed Al Nahyan, managing director of Abu Dhabi Investment Authority.

    Along with other technology and infrastructure-related partnerships and projects, an agreement for the UAE-Oman rail connectivity project, valued at AED11bn, was also signed.

    Photo: WAM


    MEED’s latest special report on Oman includes: 

    > COMMENT: Muscat needs to stimulate growth
    > GOVERNMENT & ECONOMY: Muscat performs tricky budget balancing act

    > BANKING: Oman banks look to projects for growth
    > OIL & GAS: Oman diversifies hydrocarbons value chain
    > POWER & WATER: Oman expands grid connectivity
    > HYDROGEN: Oman seeks early hydrogen success

    > CONSTRUCTION: Oman construction is back on track

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11706425/main5922.jpg
    Jennifer Aguinaldo
  • Abu Dhabi and Oman launch $180m tech fund

    24 April 2024

    Abu Dhabi-based investment and holding company, ADQ, and Oman Investment Authority (OIA) have launched a $180m technology focused vehicle called Jasoor Fund.

    Jasoor Fund aims to bolster Oman’s digital economy as well as the wider Middle East and North Africa (Mena) region by supporting high-growth technology companies in sectors such as finance, education, health care, clean energy, food, agriculture and logistics.

    OIA is represented by Ithca Group, formerly known as Oman Information and Communication Technologies Group, in the fund.

    According to ADQ, the fund’s core focus will be on innovative technology companies established in the sultanate, in addition to technology startups in other countries in the region.

    It will undertake investments in high-growth technology companies at various stages of development that have established business models.

    Mohamed Hassan Alsuwaidi, ADQ managing director and chief executive, said the launch of Jasoor Fund “reinforces our commitment to make investments that unlock the potential of key sectors of the economy, while creating lasting value for stakeholders”.

    Jasoor Fund is part of broader framework agreement signed between both parties in 2022, when they identified investment opportunities worth over $8bn across key sectors of Oman’s economy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11707308/main.jpg
    Jennifer Aguinaldo
  • Contractors win Oman-Etihad Rail packages

    23 April 2024

    Register for MEED's guest programme 

    Oman-Etihad Rail Company (OERC) has announced that it has awarded contracts for three civil works packages for the railway project linking Oman and the UAE, which is now officially called Hafeet Rail.

    The estimated AED5.5bn ($1.5bn) design-and-build contract was awarded to a consortium of Abu Dhabi-based National Projects Construction (NPC), National Infrastructure Construction Company (NICC), Tristar Engineering & Construction and Oman’s Galfar Engineering & Contracting.

    NPC is the infrastructure development arm of the Abu Dhabi-based Trojan Construction Group, which is a subsidiary of local investment firm Alpha Dhabi.

    According to sources close to the project, the clients are expected to appoint an engineering design firm for the project imminently.

    NICC is the project management consultant for the Hafeet Rail scheme.

    OERC also awarded a separate contract for the rolling stock systems and integration contracts to German firm Siemens and Egyptian contractor Hassan Allam Construction.

    Several high-ranking officials from both sides attended the agreement signing ceremony.

    They included Sheikh Hamed Bin Zayed Al Nahyan, managing director of Abu Dhabi Investment Authority; Suhail Bin Mohammed Al Mazrouei, minister of energy and infrastructure; Abdul Salam Bin Mohammed Al Murshidi, chairman of the Omani Investment Authority; Qais Bin Mohammed Al Yousef, minister of commerce, industry and investment promotion; and Ahmed Bin Hilal Al Busaidi, Oman’s ambassador to the UAE.

    In January, MEED reported that OERC had received bids for three civil works packages for the railway project linking the two countries.

    According to regional projects tracker MEED Projects, the firms submitted their bids on 4 December for packages A and B. The bid for package C was submitted on 11 December.

    OERC qualified companies that could bid for the three civil works packages for the railway project in August last year.

    Network development

    Oman-Etihad Rail Company was established in September 2022 to implement the railway network between the two countries.

    The project subsequently received a push after Oman-Etihad Rail Company inked a strategic agreement with Abu Dhabi-based Mubadala Investment Company to support its development.

    The UAE-Oman Rail Network is set to improve the two countries’ competitiveness in global trade and help establish their positions as logistics hubs that serve as gateways to regional markets.

    The scheme supports both countries’ sustainable development goals by improving their transport and infrastructure sectors.

    The line’s increased efficiency compared to other modes of transport is expected to reduce the overall cost of supply chains. The network will also provide trade and investment opportunities for the private sector and new job opportunities.

    Passenger trains will run up to 200 kilometres (km) an hour on the line, reducing the journey time between Sohar and Abu Dhabi to 100 minutes and between Sohar and Al Ain to 47 minutes.

    Freight trains will reach a top speed of 120km/hour.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11706161/main.gif
    Yasir Iqbal