Middle East project disputes increasing
8 November 2023

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.
Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.
The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.
“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.
“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”
Growing pains
Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.
“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.
“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”
HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.
While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.
Saudi resolution
In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.
“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”
Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.
In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.
One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.
Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.
A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.
The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.
“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.
“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.
“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”
Arbitration centres
Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.
He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.
The systems are maturing in Saudi Arabia and will soon reach a similar level.
“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.
But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.
According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.
This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.
Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.
A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.
“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”
With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.
As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.
Exclusive from Meed
-
What actually slows a gigaproject down9 September 2026
-
Jordan tenders advisory for wastewater treatment plant9 September 2026
-
Medina’s KEC signs real estate project development deal9 September 2026
-
Morocco signs agreement for synthetic fuel complex9 September 2026
-
Iraq solar package on track to come online in December9 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
What actually slows a gigaproject down9 September 2026

Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.
“None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.
For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.
“The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.
The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.
“Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”
Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.
Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.
Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.
“The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”
Integration needs to be well understood
“Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.
Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.
Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.
“The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”
That shared view, he argues, will be what the next phase of Gulf delivery is judged on.
Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.
“This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.
From reporting progress to managing risk before it lands
Digital tools have a role here, Caldwell says, but not as a headline in themselves.
Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.
“The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."
None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”
Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.
With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.
“The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.
What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.
“The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif -
Jordan tenders advisory for wastewater treatment plant9 September 2026
The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.
The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).
The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.
The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.
The submission deadline is 21 September.
The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.
The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.
The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.
WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.
The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.
The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg -
Medina’s KEC signs real estate project development deal9 September 2026
Medina’s Knowledge Economic City (KEC) has signed an agreement with Riyadh-based Kaden Investment Company to develop a mixed-use project in Medina.
The project will have an estimated gross floor area of about 230,000 square metres (sq m).
According to a statement filed by KEC with the Saudi Exchange (Tadawul), the project – called Multaqa Al-Madinah 2 – will be built on a 92,000 sq m plot located directly north of the first phase of the Multaqa Al-Madinah development.
It is expected to include about 1,527 residential units across three residential zones, along with commercial and office space totalling about 31,108 sq m of net leasable area.
It will also feature parking, recreational and service facilities, landscaping and other supporting infrastructure.
KEC and Kaden intend to deliver the project through a closed-ended real estate investment fund regulated by Saudi Arabia’s Capital Market Authority.
Under the proposed structure, KEC will contribute the land as an in-kind contribution and hold 75% of the fund units, while Kaden will contribute cash and hold the remaining 25%.
Kaden will also serve as the development manager.
KEC said the land has been initially valued at about SR692.3m ($184.6m), while the total equity required for the project is estimated at around SR833m.
Once final agreements are signed, KEC expects to receive SR67.7m in cash and fund units valued at approximately SR624.6m.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19492407/main.png -
Morocco signs agreement for synthetic fuel complex9 September 2026
Switzerland-based Synhelion has signed an agreement with the Government of Morocco with the aim of developing a large-scale commercial synthetic fuel plant in the country’s southern Tan-Tan province.
The memorandum of understanding (MoU) relates to a facility with the capacity to produce 100,000 tonnes a year of fuel, according to a statement released by the company.
Synhelion has secured land for the project site and established a subsidiary in Morocco to develop the fuel complex.
Gianluca Ambrosetti, one of Synhelion’s co-chief executives, said: “Morocco’s exceptional renewable energy resources and its clear industrial strategy make it an ideal location for scaling our synthetic fuel technology.
“With the MoU signed, the land reservation secured and our branch in place, we are moving from evaluation to execution and toward our first commercial-scale plant in the region.”
Synhelion specialises in producing hydrocarbon fuels using renewable energy. Its products include synthetic jet fuel, gasoline and diesel.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19489903/main.jpg -
Iraq solar package on track to come online in December9 September 2026

The 1,000MW solar photovoltaic project in Artawi – also called Ratawi – in southern Iraq is on track for its second phase to come online on 8 December, according to industry sources.
This phase has a capacity of 250MW and will bring the project’s total online capacity to 500MW.
The first phase of the project, also with a capacity of 250MW, came online in March this year.
The third and fourth phases, each with a capacity of 250MW, are expected to be brought online next year.
The solar project is part of the broader Gas Growth Integrated Project (GGIP), which has an estimated total value of $27bn and a first phase worth an estimated $10bn.
The solar project’s ownership differs from the headline GGIP ownership structure, with its ownership equally divided between France’s TotalEnergies and QatarEnergy.
The wider GGIP consortium includes TotalEnergies, Iraq’s Basra Oil Company and QatarEnergy, which hold stakes of 45%, 30% and 25%, respectively.
China Energy Engineering Corporation is part of a consortium that is executing the main engineering, procurement and construction contract for the project.
It announced that the first 250MW of capacity had been connected to the grid on 4 March this year.
The consortium also includes China Energy Engineering Group Tianjin Electric Power Construction Company and Chengdu-headquartered Southwest Electric Power Design Institute Company.
The project scope includes:
- Construction of a substation
- Installation of a 132kV booster station
- Installation of solar panels
- Installation of transformers
- Laying of transmission lines
- Construction of related infrastructure
In February 2025, Basra Investment Commission director Alaa Abdul Hussein said the solar plant had an estimated total value of $820m.
The GGIP programme is focused on developing four major projects in Iraq:
- The Common Seawater Supply Project (CSSP)
- The Ratawi gas processing complex
- The 1GW solar power project for Iraq’s electricity ministry
- A field development project at Ratawi, known as the Associated Gas Upstream Project (AGUP)
All four of these projects are currently under execution, though there have been some delays related to the regional war that started when the US and Israel attacked Iran on 28 February.
The conflict has caused significant disruption to shipping through the Strait of Hormuz, which Iraq uses to export crude oil and import equipment and materials for projects.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19489818/main.jpg