Middle East project disputes increasing

8 November 2023

 

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.

Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.

The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.

“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.

“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”

Growing pains

Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.

“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.

“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”

HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.

While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.

Saudi resolution

In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.

“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”

Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.

In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.

One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.

Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.

A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.

The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.

“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.

“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.

“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”

Arbitration centres

Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.

He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.

The systems are maturing in Saudi Arabia and will soon reach a similar level.

“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.

But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.

According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.

This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.

Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.

A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.

“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”

With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.

As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11278295/main.jpg
Wil Crisp
Related Articles
  • Firms prepare Hudayriat East PPP tunnels advisory bids

    25 June 2026

     

    Abu Dhabi’s Modon Infrastructure, formerly Gridora, has tendered a contract for technical advisory services for the construction of two underwater tunnels connecting the eastern side of Hudayriat Island with mainland Abu Dhabi.

    Consultants have until 26 June to submit their proposals.

    The project includes the construction of a 4.8-kilometre (km) highway, with four lanes in each direction, connecting Hudayriat Island to Mussafah 8th Street.

    The project will be delivered on a public-private partnership (PPP) basis in coordination with the Abu Dhabi Department of Municipalities and Transport and the Abu Dhabi Investment Office.

    The contract term is expected to be 25 years.

    The latest infrastructure development in Abu Dhabi follows Modon Infrastructure’s invitation in May for firms to register for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will also be developed on a PPP basis.

    Modon Infrastructure will act as the lead developer, holding the majority equity stake in the project company. It will award the engineering, procurement and construction contract, as well as the operations and maintenance services and advisory appointments.

    The second phase of the MIPP involves the construction of about 11km of highways, including a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.

    The project includes several major structures, such as the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange with cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. The project will be completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17410214/main.jpg
    Yasir Iqbal
  • Algeria tenders upstream oil project contract

    25 June 2026

    Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.

    The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.

    Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.

    It also says the project aims to improve production yields and quality.

    The contract includes both initial and detailed studies as well as the supply of all equipment and materials.

    It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.

    The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg
    Wil Crisp
  • Red Sea Global tenders King Salman Bay construction work

    25 June 2026

     

    Saudi gigaproject developer Red Sea Global (RSG) has tendered a contract inviting firms to undertake marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.

    The bid submission deadline is 31 July.

    King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.

    The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.

    According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.

    “The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.

    The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17430045/main.jpg
    Yasir Iqbal
  • MECC submits lowest bid on three Kuwaiti oil and gas contracts

    25 June 2026

     

    Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).

    The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds

    Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD65,760,000 ($212m)
    • Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
    • Amco Engineering & Construction: KD73,446,100 ($237m)
    • Combined Group Contracting Company: KD76,186,000 ($246m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)

    Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD30,760,000 ($99m)
    • Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
    • Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
    • Industrial Company for Electrical Projects: KD36,375,520 ($118m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
    • Combined Group Contracting Company: KD37,790,000 ($122m)

    Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD35,760,000 ($116m)
    • Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
    • Amco Engineering & Construction: KD39,736,800 ($128m)
    • Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
    • Industrial Company for Electrical Projects: KD43,238,265 ($140m)
    • Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
    • Combined Group Contracting Company: KD43,650,000 ($141m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)

    Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.

    A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.

    Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg
    Wil Crisp
  • Chinese firm wins $265m Saudi hospital contract

    24 June 2026

    Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.

    Construction is expected to take three years from the start date.

    Prince Mohammed Bin Fahd University awarded the contract.

    Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.

    The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.

    Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.

    The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.

    Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.

    China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.

    China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.

    GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg
    Yasir Iqbal