Middle East project disputes increasing
8 November 2023

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.
Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.
The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.
“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.
“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”
Growing pains
Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.
“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.
“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”
HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.
While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.
Saudi resolution
In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.
“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”
Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.
In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.
One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.
Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.
A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.
The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.
“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.
“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.
“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”
Arbitration centres
Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.
He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.
The systems are maturing in Saudi Arabia and will soon reach a similar level.
“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.
But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.
According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.
This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.
Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.
A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.
“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”
With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.
As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.
Exclusive from Meed
-
Shell approves Egypt offshore gas project31 August 2026
-
Contractors appointed for Group 1 battery storage projects27 August 2026
-
Accor and Al-Qimmah plan 4,000 Saudi rooms27 August 2026
-
Jeddah tenders stormwater drainage contracts27 August 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Shell approves Egypt offshore gas project31 August 2026
BG Delta, a Shell subsidiary, has reached the final investment decision for phase 12a of the West Delta Deep Marine (WDDM) development project.
The project will be implemented in partnership with Malaysia’s Petronas and state-owned Egyptian General Petroleum Corporation (EGPC).
Shell, Petronas and EGPC formed a joint venture called Burullus Gas Company to operate the WDDM concession.
Phase 12a includes drilling and completing three deepwater gas wells, with production expected to begin in 2028, according to a statement from the London-headquartered company.
The wells will be tied into existing subsea infrastructure, helping accelerate development, improve capital efficiency and limit the need for additional facilities.
Dalia El-Gabry, the vice-president and chairperson of Shell Egypt, said: “This investment demonstrates our commitment to maximising the remaining potential in WDDM where the right technical and commercial conditions exist.
“By leveraging existing infrastructure and our proven development experience, we can accelerate delivery while reinforcing our partnership with the Egyptian government and joint venture partners to help meet Egypt’s energy needs.”
The new development builds on phases 10 and 11, which brought six wells online during 2024 and 2025.
Its scope also covers facility installation, tie-in operations, commissioning and connection to existing offshore infrastructure.
Egypt’s Ministry of Petroleum & Mineral Resources said in May that about $350m had been allocated to phase 12a.
In April, Egypt’s Petroleum Marine Services (PMS) was awarded a contract for offshore works for phase 12 of the WDDM field development project.
The contract awarded to PMS uses the engineering, procurement, installation and construction contract model.
Under the scope of the contract, PMS will install the required electrical, hydraulic and mechanical connections in deep waters to tie three new gas wells into production as part of phase 12.
The scope also includes the installation of three final triple tie-in spool bases to complete the connection between the wells.
During phases 10 and 11 of the WDDM project, PMS laid two offshore electrical cables at water depths reaching 660 metres, in addition to carrying out well tie-in and production connection works at depths of up to 880 metres.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19078753/main.jpg -
Contractors appointed for Group 1 battery storage projects27 August 2026

Register for MEED’s 14-day trial access
Two contractors have been appointed for engineering, procurement and construction (EPC) works on Saudi Arabia’s four Group 1 battery energy storage system (bess) projects with a combined capacity of 2,000MW, a source has confirmed to MEED.
Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), recently signed four storage service agreements for the bess projects, which will provide four hours of storage, equivalent to 8,000 megawatt-hours (MWh), and involve a total investment of more than SR4.35bn ($1.16bn).
Three projects were awarded to a consortium comprising Saudi Energy, Acwa and Al-Sharif Contracting & Commercial Development Company.
According to the source, India’s Larsen & Toubro will carry out EPC works for these three projects, comprising the Al-Muwyah and Haden bess independent storage providers (ISPs) in the Mecca region, and the Al-Kahafa bess ISP in the Hail region.
Each has a capacity of 500MW for four hours. The three projects have a combined capacity of 1,500MW and 6,000MWh.
L&T recently announced that it had secured “a major order” for bess projects in the Middle East but did not disclose the specific projects involved.
The fourth project, the Al-Khushaybi bess ISP in the Qassim region, was awarded to a consortium of France’s Engie and local firm Haji Abdullah Alireza & Co. This also has a capacity of 500MW for four hours.
China’s Sepco 3 has been appointed as the EPC contractor for this project, a source said.
The agreements cover the first group of ISP bess projects being procured by SPPC under a build, own and operate model. The projects are supervised by the Energy Ministry.
The projects form part of Saudi Arabia’s efforts to achieve an electricity generation mix comprising approximately 50% renewable energy by 2030.
As previously reported, the Group 2 programme comprises six ISP projects with a total capacity of 3GW, equivalent to 12,000MWh based on a four-hour storage duration.
Developers recently submitted a first round of clarification requests to SPPC as they prepare their bids in advance of an October deadline.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19052381/main.jpg -
Accor and Al-Qimmah plan 4,000 Saudi rooms27 August 2026
France’s hotel operator Accor has expanded its partnership with local firm Al-Qimmah Hospitality, a subsidiary of Saudi Arabia’s BinDawood Investment Company, to develop more than 4,000 hotel rooms in the kingdom.
The plan focuses on building a portfolio in Mecca and Medina.
The expanded agreement was announced in Paris during the French-Saudi Investment Roundtable. It follows a master development agreement signed in 2025. The partnership now covers five hotels in Jeddah, Mecca and Medina across the premium, midscale and economy segments.
One planned development is an 850-room Novotel in Mecca, due to open in 2030. The agreement also covers the Mercure Makkah Shesha, ibis Styles Makkah Mesfalah, Movenpick Madinah and Swissotel Jeddah properties.
The partnership will also support job creation and Saudi workforce development through Tamayyaz by Accor, the group’s national talent programme run with the Saudi Ministry of Tourism. The programme aims to develop and hire more than 3,000 Saudi nationals by 2030.
Accor has operated in Saudi Arabia for more than three decades and runs 48 hotels with more than 21,600 rooms nationwide. Its pipeline includes a further 47 properties comprising more than 11,400 rooms.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19051854/main.jpg -
Jeddah tenders stormwater drainage contracts27 August 2026
Jeddah Municipality has invited contractors to bid for a contract covering the construction of a rainwater drainage network for the Prince Fawaz neighbourhood.
The project aims to collect and convey rainwater away from residential streets and low-lying areas. It is valued at $60m and intended to reduce flooding risks during heavy rainfall.
The scope includes manholes, stormwater catch basins and connections to existing manholes as well as the restoration of road surfaces.
The bid submission deadline is 12 October.
The municipality is also progressing with a second stormwater drainage project for the first package of Zone (BC), Old Zahraa in Jeddah Governorate, with bids due on 2 September. The project is valued at about $30m.
The two projects are part of the municipality’s wider drainage programme, which includes the flagship King Abdullah Road-Falasteen Road tunnel project.
MEED previously reported that Saudi contractor Thrustboring Construction Company had been selected for phases one and two of the project, each valued at about $175m, covering the construction of large-diameter stormwater drainage tunnels.
It is understood that an official agreement has yet to be signed.
In June, MEED reported that local contractor Alkhorayef Water & Power Technologies (AWPT) had signed two contracts with Jeddah Municipality to operate and maintain stormwater and surface water drainage networks across the city.
The contracts have a combined value of SR202.06m ($53.9m), and each will run for five years.
The first contract, valued at SR108.46m ($28.9m), covers the operation and cleaning of stormwater and surface water networks in the South and Al-Malisa sub-municipalities.
The second contract, worth SR93.59m ($25m), covers similar services for the Airport Sub-Municipality.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19039514/main.jpg -
OQ seeks revised prices for NGL project from preferred contractors26 August 2026

Omani state energy conglomerate OQ Group has sought revised commercial proposals from a set of preferred bidders for its planned project to build a major natural gas liquids (NGL) facility in the sultanate.
The planned NGL facility at Saih Nihayda in central Oman will extract condensates and transport them to Duqm on the sultanate’s Arabian Sea coast for fractionation and export, OQ Group said.
OQ Group intends to deliver the project using a front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) competition model. Under this model, the project operator selects contractors to carry out the feed work. The operator then awards the EPC contract to the contractor with the most competitive feed proposal, while compensating the other participants for their work.
MEED reported in June that OQ Group was seeking revised prices from contractors it had selected earlier this year to participate in the feed-to-EPC competition. Contractors submitted their revised bids by 6 July.
According to sources, OQ Group entered into negotiations with bidders in the weeks after receiving the revised commercial bids. The client is then said to have approached only the following three contractors for their final commercial offers on the NGL project:
- Saipem (Italy)
- Tecnicas Reunidas (Spain)
- Tecnimont (Italy)
MEED previously reported that the contractors who had submitted their original proposals to OQ for the feed-to-EPC competition on 20 May were:
- Hyundai Engineering & Construction (South Korea) / KBR (US)
- JGC Corporation (Japan)
- Petrofac (UK)
- Saipem (Italy)
- Technip Energies (France)
- Tecnicas Reunidas (Spain)
- Tecnimont (Italy)
OQ issued the main tender for the feed-to-EPC competition in March, setting an initial deadline of 8 April for contractors to submit proposals, which it later extended to 6 May and then again to 20 May.
MEED previously reported that the state enterprise had started the prequalification process for the feed-to-EPC contest for the planned NGL project in November last year, with contractors submitting responses by 15 December.
In addition to the contractors understood to have submitted proposals for the feed-to-EPC competition, OQ also invited the following firms to participate, although they are understood to have pulled out of the contest later:
- Chiyoda (Japan) / CTCI (Taiwan)
- GS Engineering & Construction (South Korea)
- Kent (UAE)
- Samsung E&A (South Korea) / Larsen & Toubro Energy Hydrocarbon (India) / Wood (UAE).
Project scope of work
The scope of work on the project covers the development, verification and integration of feed deliverables for the following facilities and systems:
NGL extraction facility – Saih Nihayda:
- Verification and updating of the existing feed to enable dual-mode operation (ethane recovery and ethane rejection)
- Identification and implementation of required process, equipment, utilities and control system modifications
NGL pipeline – Saih Nihayda to Duqm:
- Feed for a new NGL transmission pipeline stretching approximately 230 kilometres, including routing, hydraulics, stations, pigging facilities, metering, corrosion protection, leak detection and safety systems
Fractionation unit at Duqm:
- Feed for a new fractionation facility to process ethane and propane plus NGL and recover propane, butane, condensate, and the provision for future ethane recovery
- Design accommodating licensed or open-art technology and future tie-in to a planned petrochemicals project in Duqm
Product pipelines, storage and export facilities at Duqm jetty:
- Feed for product pipelines, cryogenic and atmospheric storage tanks, vapour recovery systems, marine loading arms and export facilities
- Integration with existing port and refinery infrastructure, where feasible
Supporting systems and studies:
- Utilities, offsites, flare systems, safety and environmental studies, cost estimates (class 2+10%), project schedules, constructability assessments and EPC tender documentation
Gulf NGL projects
Gulf national oil companies have been allocating significant capital expenditure to the construction or expansion of NGL production facilities.
In September last year, QatarEnergy awarded the main EPC contract for its project to add a fifth NGL train at its fractionation complex in Qatar’s Mesaieed Industrial City. The aim of the project, which is estimated to be worth $2.5bn, is to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.
The main EPC contract for the QatarEnergy NGL-5 project was won by a consortium of India’s Larsen & Toubro Energy Hydrocarbons Onshore and Greece-headquartered Consolidated Contractors Group.
Separately, MEED reported in March that the gas processing business of Abu Dhabi National Oil Company (Adnoc Gas) had selected the main contractor for a project to install a fifth NGL fractionation train at its Ruwais gas processing facility in Abu Dhabi.
The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day, or about 8 million tonnes a year. The Ruwais NGL Train 5 project represents the second phase of Adnoc Gas’ Rich Gas Development programme, and its budget is estimated to be about $4bn, Peter Van Driel, Adnoc Gas’ chief financial officer, confirmed in February.
ALSO READ: PDO floats tender for major flare gas monetisation scheme
https://image.digitalinsightresearch.in/uploads/NewsArticle/19011913/main.jpg