Middle East project disputes increasing
8 November 2023

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.
Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.
The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.
“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.
“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”
Growing pains
Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.
“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.
“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”
HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.
While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.
Saudi resolution
In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.
“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”
Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.
In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.
One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.
Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.
A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.
The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.
“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.
“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.
“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”
Arbitration centres
Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.
He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.
The systems are maturing in Saudi Arabia and will soon reach a similar level.
“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.
But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.
According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.
This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.
Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.
A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.
“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”
With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.
As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.
Exclusive from Meed
-
-
-
-
-
Aecom to supervise Dubai Loop construction11 May 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iraq enters era of resilience, reform and rising risks11 May 2026

Iraq’s projects market is at an inflection point. The country has built a sizeable and increasingly diverse projects pipeline, backed by ambitious national plans and an improving reform narrative. But according to MEED’s newly updated Iraq Projects Market report, the near-term outlook is now being tested by renewed regional volatility and persistent structural constraints at home.
Iraq is the Middle East and North Africa’s fifth-largest economy by nominal GDP, yet it remains heavily exposed to the hydrocarbons cycle. Oil and gas generate about 90% of government revenues and more than 40% of GDP, a dependency that shapes annual capital spending and the bankability of public-private partnership (PPP) deals. Earlier this year, the IMF forecast GDP growth of 3%-4%. In light of the latest regional conflict dynamics involving the US and Israel with Iran, that growth outlook is expected to soften as investor risk perceptions rise and supply chains face renewed stress.
Even so, Iraq’s projects market is not starting from a blank slate. By the end of March 2026, almost $120bn of contracts were in execution, with a further $300.4bn in the broader pipeline. The scale of that opportunity is underpinned by enduring reconstruction requirements, urgent energy-sector needs and a policy push to translate oil wealth into long-lived productive assets.
Reconstruction needs
Nearly a decade after the official end of the Islamic State conflict, Iraq’s reconstruction gap remains substantial. Estimates put the shortfall at about $88bn, reflecting the long tail of damage to housing, utilities, public buildings and transport links. Southern and central regions dominate the live pipeline, largely because they sit close to Iraq’s oil heartlands. Basra, in particular, is pivotal, anchoring major upstream activity and vital export infrastructure.
At the policy level, Iraq Vision 2030 signals a long-term ambition to diversify into tourism, agriculture, industry and digital transformation. The government’s immediate delivery vehicle is the National Development Plan (NDP) 2024-28, which commits more than $17bn a year in capital expenditure and prioritises energy, transport, housing and water infrastructure. This shift is reinforced by Iraq’s Green Growth Framework (2026), indicating that future procurement may place greater weight on efficiency, emissions reduction and climate resilience.
Macro risk
Despite policy ambition, the most immediate determinant of Iraq’s fiscal room is the oil price. A $10-a-barrel drop can reduce government revenue by an estimated $7bn-$9bn annually. Such sensitivity matters because infrastructure spending is still largely funded by the public purse. Oil price swings affect project awards, payment cycles and the government’s willingness to assume up-front capex obligations.
Iraq’s execution environment continues to be defined by bureaucratic delays, unclear land titles and opaque procurement processes. These factors can add 12-24 months to average delivery timelines. Nevertheless, there are signs of adaptation. PPP legislation is advancing, and developer-led models are gaining traction in large housing programmes. Furthermore, there is a growing reliance on international project management consultancy (PMC) firms—such as Hill International, Worley, and AtkinsRealis—to bridge capacity gaps and improve governance, cost control and scheduling.
Hydrocarbon driver
Oil and gas upstream remains the single largest driver of capital expenditure. Major developments, including the Gas Growth Integrated Project (GGIP) and Mansouriya, sit alongside a push to reduce gas flaring and expand downstream processing. The objective is to sustain export revenues while improving domestic fuel availability.
The power sector is even more urgent. Iraq faces an estimated 8-10GW generation shortfall, which keeps electricity supply at the centre of political risk. This gap is driving rapid procurement of generation capacity and grid upgrade contracts. Beyond traditional infrastructure, Iraq is also moving on digital adoption. Smart city pilots and fibre rollouts are attracting regional technology investors, while AI-enabled data centre projects are beginning to emerge.
Investment targets
Foreign direct investment (FDI) remains below $3bn a year, a low figure relative to market size. The most active investors outside the oil sector include the UAE, Saudi Arabia and Kuwait. To convert interest into deals, the National Investment Commission (NIC) is pursuing streamlined licensing and investor-protection reforms. A “one-stop shop” approach has reportedly reduced registration timelines for foreign investors from months to weeks in key sectors.
Investor protection mechanisms, such as access to international arbitration, are being strengthened, though enforcement remains a concern. Iraq’s three free zones—Basra, Karbala and Nineveh—offer additional incentives including tax holidays and customs exemptions, provided they can be paired with reliable utilities and bankable arrangements.
Conflict premium
The latest escalation involving the US and Israel with Iran has increased Iraq’s security risk premium. This is inflating materials costs and disrupting supply chains near eastern border zones. Even where projects are far from conflict areas, contractors are pricing in higher contingency for logistics and insurance. Iraq must also balance deep economic ties with Iran—particularly in energy—with Western investor expectations and sanctions-related compliance.
With more than 60% of its population under 25, Iraq has a potential demographic dividend, but it also faces immediate employment pressure and a shortage of skilled technical labour. Iraq’s projects market outlook for 2026 is best described as cautiously constructive. The pipeline is deep and the need is undeniable, but delivery will hinge on whether Iraq can translate plans into predictable execution. If progress on procurement and contract enforcement continues, Iraq can sustain a broad-based market that extends beyond hydrocarbons.
Click here to learn more about MEED’s newly updated Iraq Projects Market report
https://image.digitalinsightresearch.in/uploads/NewsArticle/16782507/main.gif -
Retal to develop project in Oman’s Sultan Haitham City11 May 2026
Saudi Arabia’s Retal Urban Development Company has entered Oman with its first development agreement, signing a deal to build more than 2,000 residential units in Sultan Haitham City in Muscat.
In a statement to the Saudi Stock Exchange (Tadawul) on 11 May, the company said it had signed an agreement with Oman’s Ministry of Housing & Urban Planning to develop an integrated residential community at an estimated cost of SR3bn ($823m).
The community will be developed across zones 3, 15 and 17 within Sultan Haitham City, covering a total area of 1.3 million square metres.
The project will include villas and apartments, alongside commercial and mixed-use elements and community facilities.
Retal said the development will be delivered through an off-plan sales model and is expected to take nearly nine years to complete.
The first phase of the Sultan Haitham City project includes the development of a 5 square-kilometre city centre and six of the development’s 19 planned neighbourhoods. The first phase is set for completion by 2030.
US-based architectural firm SOM unveiled masterplan proposals for Sultan Haitham City in August 2024.
The final phase of the project is expected to be completed by 2045.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16781867/main.jpg -
Qiddiya seeks firms for light rail transit system11 May 2026

Saudi gigaproject developer Qiddiya Investment Company (QIC) has requested contractors to express interest in a contract to design and build the first phase of the light rail transit system at Qiddiya Entertainment City.
The notice was issued on 5 May, with firms given until 20 June to submit expressions of interest.
The project, also known as the Primary Urban Axis, comprises a 22-kilometre automated, driverless rail line as part of its first phase.
The contract scope includes about 16 stations – 11 elevated and five underground – along with 8km of tunnels, viaducts and other associated structures. It covers all civil, architectural, and mechanical, electrical and plumbing works.
Stations will be located at Resort Core East Village, Grand Central Station, Anime Hub Integrated Station and Primary Urban Axis 1 & 2 Hub Station.
A subsequent phase will extend the railway network by a further 11km.
QIC is accelerating plans to develop additional assets at Qiddiya City.
Separately, QIC, the Royal Commission for Riyadh City and the National Centre for Privatisation & PPP received prequalification statements from firms on 30 April for the public-private partnership (PPP) package of the Qiddiya high-speed rail project in Riyadh. This follows submission of prequalification statements for the engineering, procurement, construction and financing package on 16 April, as previously reported by MEED.
The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at up to 250 kilometres per hour, reaching Qiddiya in 30 minutes.
Contractors are also preparing bids for a 13 May deadline for a contract covering new infrastructure works at Qiddiya Entertainment City. The scope includes two infrastructure development packages for District 0, including the construction of four event park-and-ride facilities.
QIC’s other major projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.
QIC officially opened the Six Flags theme park to the public in December last year.
The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16779176/main.jpg -
RCRC awards $1bn Sheikh Jaber Al-Sabah Road contract11 May 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s Royal Commission for Riyadh City (RCRC) has awarded an estimated SR5bn ($1.3bn) contract for the construction of the Sheikh Jaber Al-Sabah Road project in Riyadh.
The contract was awarded to the joint venture of Riyadh-based Al-Rashid Trading & Contracting Company (RTCC) and Turkiye’s IC Ictas.
The project stretches 12 kilometres (km) from Khurais Road to Al-Thumama Road in Riyadh.
The Sheikh Jaber Al-Sabah Road project is a key component of the Second Eastern Ring Road scheme.
The project includes the construction of five interchanges: Prince Bandar interchange, King Abdullah interchange, Imam Abdullah interchange, Dammam Road interchange and Al-Thumama interchange.
The latest contract marks another significant project award to the RTCC-IC Ictas joint venture by RCRC.
In June 2024, RCRC awarded an estimated SR4bn ($1bn) design-and-build contract to upgrade the Wadi Laban cable bridge in Riyadh to the joint venture of RTCC and IC Ictas.
The project aims to ease traffic congestion around the Western Ring Road in the area extending from Ibn-Hazm Road to Jeddah Road. The contract also covers the construction of an intersection at Jeddah Road.
The construction of the bridge originally began in August 1993 and was completed in 1997.
The existing bridge is 763 metres long and 35 metres wide, with two 14-metre-wide carriageways.
In 2021, Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud said the population of Riyadh would double to 15-20 million people by 2030.
He directed government entities to work closely with the RCRC to prepare the city’s development strategy.
The RCRC’s major projects include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park, Green Riyadh and several road development projects in the capital.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16775717/main.jpg -
Aecom to supervise Dubai Loop construction11 May 2026

Register for MEED’s 14-day trial access
US-based Aecom has been selected for a contract to undertake design review and construction supervision services for the Dubai Loop transportation system.
The contract was tendered by Dubai’s Roads & Transport Authority (RTA), which signed a construction agreement with Elon Musk-backed firm The Boring Company.
The first phase comprises a 6.4-kilometre route with four stations, linking the Dubai International Financial Centre (DIFC) and Dubai Mall.
Stations will be located at DIFC 2, ICD Brookfield Place, Dubai Mall Zabeel Parking and Burj Khalifa.
The first phase is expected to cost about AED565m ($154m) and be delivered within one year of design work and other preparations being completed. Tunnelling is expected to begin in the second half of this year.
The latest update follows the appointment of Parsons Corporation to deliver programme management services for the Dubai Loop transportation system.
Next phase
The second phase will connect the Dubai World Trade Centre and DIFC with Business Bay.
The tunnels will extend up to 22km and include 19 stations.
The total cost across both phases is expected to be around AED2bn ($545m), with completion scheduled within three years.
The pilot route is expected to serve around 13,000 passengers a day, while the full route is projected to have a capacity of about 30,000 passengers a day.
The RTA and The Boring Company signed a memorandum of understanding on the sidelines of the World Governments Summit in Dubai in February last year to explore the development of the Dubai Loop transportation system.
The Dubai Loop is expected to be similar to The Boring Company’s Las Vegas Convention Centre (LVCC) Loop project. The LVCC Loop is a 2.7km underground tunnel system that connects different convention centre halls, reducing walking time across the site to about two minutes.
The LVCC Loop has been in operation since 2021. It uses Tesla Model 3 cars to carry passengers between five stations. The Boring Company began construction in November 2019 at an estimated cost of $49m.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/16775632/main.jpg

