Middle East project disputes increasing

8 November 2023

 

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.

Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.

The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.

“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.

“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”

Growing pains

Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.

“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.

“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”

HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.

While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.

Saudi resolution

In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.

“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”

Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.

In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.

One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.

Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.

A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.

The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.

“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.

“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.

“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”

Arbitration centres

Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.

He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.

The systems are maturing in Saudi Arabia and will soon reach a similar level.

“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.

But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.

According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.

This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.

Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.

A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.

“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”

With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.

As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11278295/main.jpg
Wil Crisp
Related Articles
  • Dewa opens bids for MBR Solar Park phase seven

    3 August 2026

     

    Dubai Electricity & Water Authority (Dewa) has opened bids for the seventh phase of the Mohammed Bin Rashid Al-Maktoum Solar Park.

    According to a source, technical and financial offers were opened last month. The utility received bids on 1 July. 

    Phase seven will add 2,000MW from photovoltaic solar panels and include a 1,400MW battery energy storage system (bess) with a six-hour capacity, providing a total storage capacity of 8,400 megawatt-hours. 

    It is understood that Saudi Arabia’s Acwa, the UAE’s Etihad Water & Electricity and Abu Dhabi Future Energy Company (Masdar) are among the companies that submitted bids for the project.

    The winning bidder “is likely” to come from one of those three, a source told MEED.

    As MEED understands, the previously prequalified Electricite de France did not submit a bid for the project.

    Dewa completed the prequalification process for the latest phase of the world’s largest single-site solar park in 2025. 

    As previously reported, 47 firms submitted their responses to Dewa’s expression of interest request for the contract in March 2025. The main tender was issued last November.

    The following companies were among those prequalified to submit main contract bids on the project:

    • Acwa (Saudi Arabia) 
    • Abu Dhabi Future Energy Company (Masdar)
    • Electricite de France (EDF)
    • Etihad Water & Electricity (EtihadWE)
    • China Machinery Engineering Corporation
    • China Construction Eighth Engineering Division
    • Power China
    • Larsen & Toubro (India)
    • Shanghai Electric Group

    The transaction advisory team for the project comprises UK-headquartered Deloitte and US-based CMS and Sargent & Lundy as financial, legal and technical advisers, with Deloitte acting as lead adviser. 

    Meanwhile, construction on the 1,800MW sixth phase of the MBR Solar Park is nearing completion, with commissioning expected by the end of the third quarter.

    Dewa and Masdar reached financial close for the $1.5bn project in 2024. Once completed, the sixth phase will increase the solar park’s total production capacity to 4,660MW.

    Dewa increased its flagship solar project’s 2030 installed capacity target by 45% in 2025, from 5,000MW to 7,260MW. This comprises a total investment of AED50bn ($13.6bn).


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18031819/main.jpg
    Mark Dowdall
  • Three groups bid for $5bn Asir-Jizan highway

    3 August 2026

     

    Three groups have submitted bids for an estimated SR20bn ($5bn) contract to develop and operate the Asir-Jizan highway project on a public-private partnership (PPP) basis.

    According to sources close to the project, the consortiums that bid are:

    • Lamar Holding (local) / Shaanxi Construction Engineering (China) / Safari (local)
    • Vision Invest (local) / China Harbour Engineering Company (China)
    • Plenary (Australia) / Alayuni (local) / Limak Holding (Turkey) / Nesma & Partners (local)

    Saudi Arabia’s Roads General Authority, the National Centre for Privatisation & PPP and the Aseer Development Authority (Asda) are the government agencies managing the tender and project.

    The 136-kilometre Asir-Jizan highway will have three lanes in each direction and include six intersections, 57 bridges totalling 18km and 11 tunnels totalling 9km.

    The project is one of four planned highway schemes in the kingdom’s privatisation and public-private partnership pipeline.

    The route begins in Al-Farah in Asir and extends to the Red Sea through Jizan.

    The 30-year contract will follow a design, build, finance, operate and maintain model.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18031383/main1110.jpg
    Colin Foreman
  • Adnoc Onshore extends bid deadline for field facilities project

    3 August 2026

     

    Abu Dhabi National Oil Company’s onshore business (Adnoc Onshore) has given contractors extra time to prepare bids for a project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields, part of the Northeast Bab cluster of oil fields in Abu Dhabi.

    The project aims to enhance and sustain oil production at the Rumaitha and Shanayel fields at a rate of 45,000 barrels a day (b/d). It forms part of Adnoc Onshore’s contribution to parent company Adnoc Group’s broader objective of increasing oil production capacity to 5 million b/d by 2027 through its Accelerated Integrated Programme 5 (AiP5). Adnoc Group currently has a production capacity of 4.85 million b/d.

    Adnoc Onshore issued the main tender for the engineering, procurement and construction (EPC) works package for the Rumaitha and Shanayel on-plot and off-plot facilities project on 19 June, MEED previously reported.

    The project operator has now extended the deadline for contractors to submit technical bids to 5 August, from 2 August previously, according to sources. The prior deadline had been 30 July.

    Adnoc Onshore issued the expression of interest for the Rumaitha and Shanayel on-plot and off-plot facilities project in early December, with contractors submitting their responses later that month, MEED previously reported.

    The prequalification and ongoing tendering process is understood to result from Adnoc Onshore revising its strategy for executing EPC works on an earlier, larger project covering the Northeast Bab cluster, which comprises the Al-Nouf, Rumaitha and Shanayel fields.

    MEED reported in December that Adnoc Onshore had cancelled the engineering, procurement and construction management (EPCm) phase it launched in 2024 for the Northeast Bab on-plot and off-plot facilities project in favour of executing the scheme under a conventional EPC model.

    The operator awarded a contract to state-owned China Petroleum Engineering & Construction Corporation (CPECC) to carry out EPCm services for the Northeast Bab off-plot facilities package in October 2024. However, the contract was subsequently cancelled last year.

    Separately, Adnoc Onshore received bids during the second quarter of 2025 for the EPCm tender covering the Northeast Bab on-plot facilities package, but that procurement process was also later cancelled.

    Project scope of work

    The detailed scope of work on the Rumaitha and Shanayel on-plot and off-plot facilities project is as follows:

    On-plot facilities:

    • Oil train: One new oil train with slug catcher, two-stage separation, desalting, exchangers for crude heating and stabilisation, and all associated interconnections, utilities and civil/structural works, etc.
    • Produced water treatment (PWT): New produced water treatment package to enable 100% produced water reinjection (PWRI), including chemical dosing, tanks, pumps, all associated controls and blending with aquifer water, etc.
    • Water injection system: New water injection system, including surface water injection pumps, necessary connections and controls from produced water systems, headers, chemical dosing, power and controls, etc.
    • Gas handling and export:
      • Low-pressure gas compression system
      • Medium-pressure gas compression system
      • Gas dehydration and regeneration system
      • Export gas compression system
    • Utilities and offsites: Plant air and instrument air systems, nitrogen generation system, potable water system, vapour recovery system (liquid ejector package), fuel gas import and distribution, closed and open drain systems, hot oil heater, snuffing nitrogen package, enclosed ground flare systems (high-pressure and tank flares), etc.
    • Modifications in existing systems, including, but not limited to, installation of a slug catcher at phase-I, connectivity of gas systems, water systems, existing high-pressure compressors modifications, etc
    • Electrical, instrumentation and control, and safety: Electrical systems, instrumentation and control system (ICSS, F&G system, field instrumentation, HIPPS, etc.), substation and ITR room building, fire water system, etc.
    • Overhead line (220 kV): Installation and extension of overhead lines and 220 KV GIS compound or equivalent power distribution solutions to the central processing plant and other designated areas, as necessary.

    Off-plot facilities:

    • New gas-lifted oil producers and water injectors installation with necessary piping, controls, etc. and their connections to the new or existing clusters and pipeline networks
    • New clusters with facilities such as control panels, ITR, production and test manifolds, headers, chemical injection skids, multiphase flow meters, closed drain systems, HIPPS valves, WHCPs, pig traps, ICSS/telecom extensions, etc.
    • Modifications in existing clusters, including the addition or extension of manifolds, headers, additional pipelines with pig traps, ICSS/telecom extensions, chemical injection kids, etc.
    • Gathering and injection networks: Construction of new and modified oil gathering and water injection trunklines/laterals, pigging facilities (launchers/receivers), valve stations, block valves, corrosion protection and monitoring, and all associated equipment, etc.
    • Export gas pipelines and Adnoc Gas interface: Provision for export gas pipeline and facilities from Rumaitha central processing plant to new manifold station and from NMS to Adnoc Gas, including isolation/blowdown, etc.
    • Overhead line: Installation and extension of 33kV overhead lines to clusters, etc., as required.

    The tendering exercise for the Rumaitha and Shanayel on-plot and off-plot facilities project is taking place as Adnoc Onshore continues to make progress with EPC works on another, similar project to build off-plot facilities at the Southeast cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.

    The Southeast cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.

    MEED previously reported that Adnoc Onshore had awarded EPC works on the Southeast off-plot facilities project to state-owned China Petroleum Engineering & Construction Corporation (CPECC), with the value of the contract estimated to be around $1.2bn.

    The overall scope of work on the Southeast off-plot facilities project includes tying in more than 150 wells across the area’s fields, upgrading remote and central degassing stations, laying more than 270 kilometres of flowlines, digitising wells for remote monitoring, and implementing artificial intelligence-driven telemetry technologies.

    MEED also recently reported that CPECC awarded subcontracts on the Southeast off-plot facilities project, in its capacity as the main EPC contractor.

    The off-plot facilities project is a component of the overall $2bn-$3bn South East AIP5 development, with the on-plot facilities project forming the other part of the programme.

    CPECC is also performing EPC works on the Southeast on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18022436/main2622.jpg
    Indrajit Sen
  • Lebanon seeks interest for power generation projects

    3 August 2026

    Lebanon’s Electricity Regulatory Authority (ERA) has invited the private sector to submit expressions of interest (EoIs) for several upcoming power generation projects.

    The EoI covers up to five grid-connected solar photovoltaic projects with a combined installed capacity of 350MWp. The projects are also expected to include battery energy storage systems (bess) with a combined capacity of 1,000MWh. 

    The regulator is also seeking proposals for distributed dual-fired thermal power plants with net capacities ranging from 20MW to 100MW. The plants are expected to operate on natural gas as the primary fuel and heavy fuel oil as a backup fuel. 

    The submission deadline is 31 August. 

    Regulatory progress

    The EoI follows the establishment of Lebanon’s Electricity Regulatory Authority earlier this year, more than two decades after it was envisaged under Law No. 462/2002 but not implemented due to political delays. The electricity sector had previously been overseen by the Ministry of Energy & Water and state utility Electricite du Liban.

    Lebanon’s electricity sector continues to face insufficient generation capacity, fuel supply constraints, ageing generation assets and limited grid flexibility. These challenges have led to prolonged electricity shortages and increased reliance on private diesel generation and distributed solar systems, prompting the government to seek additional private investment in new generation capacity. 

    IPP model

    According to the EoI document, the projects are expected to be structured as independent power producer (IPP) schemes. Any future contractual arrangements, including power-purchase agreements, will be determined by the competent public authority under the applicable legal framework. 

    The ERA said the EoI is open to private investors, IPP operators, engineering, procurement and construction contractors, equipment suppliers and consortiums. It is intended to assess market interest, identify potential generation projects and evaluate the technical and financial capabilities of prospective developers. 

    Respondents are required to provide information on their technical and financial capabilities, proposed project locations, grid connection plans and relevant project experience. 

    For solar projects, developers are required to provide details including module and inverter technology, annual generation estimates and battery storage specifications where applicable. Thermal project submissions must include information on technology type, efficiency, fuel strategy, emissions performance and readiness for future natural gas operation. 

    The EoI states that developers will be responsible for land acquisition or leasing, permitting, financing, design, construction, grid interconnection, commissioning, and long-term operation and maintenance of the projects. 


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18018733/main.jpg
    Mark Dowdall
  • Saudi economy swings to 4.8% contraction

    3 August 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s economy contracted 4.8% year-on-year in the second quarter of 2026, as a sharp fall in oil activities outweighed continued growth in the non-oil economy, according to flash estimates from the General Authority for Statistics (Gastat).

    The contraction was driven by a 24.7% year-on-year drop in oil activities, which cut 5.4 percentage points from the headline figure. Non-oil activities grew 0.6% and government activities rose 0.9%, contributing 0.4 and 0.1 percentage points respectively. Net taxes on products added a further 0.1 percentage points.

    On a seasonally adjusted basis, real GDP fell 4.9% from the first quarter, with oil activities down 21.5% quarter-on-quarter. Non-oil activities eased 0.5% over the same period, while government activities rose 0.2%.

    The second-quarter figures mark a reversal from the first quarter, when the economy grew 3% year-on-year. In the first quarter, both oil and non-oil activities expanded by 2.9% and government activities rose 1.5%, with growth recorded across all major sectors. Oil activities have since swung from that modest expansion to a steep contraction, while non-oil growth has slowed from 2.9% to 0.6%.

    The divergence between the oil and non-oil economy has widened as a result. While crude output fell steeply in the second quarter, the broader non-oil sector, the focus of the kingdom’s economic diversification programme, continued to expand, albeit at a slower pace than in the opening months of the year.

    Public finances

    The contraction came in a quarter when higher oil revenue improved the public finances. The budget deficit narrowed to SR34.29bn in the second quarter, down from SR125.71bn in the first, as oil revenue rose 22% year-on-year to SR185.13bn, according to the Finance Ministry’s quarterly budget performance report. Total revenue reached SR338.78bn, up 12% on the same period of 2025, while non-oil revenue increased 3% to SR153.66bn.

    Total spending rose 11% year-on-year to SR373.07bn. The sharpest increases were in grants, up 199% to SR1.24bn, subsidies, up 73% to SR13.27bn, and financing expenses, up 41% to SR16.81bn. Capital spending rose 16% to SR46.23bn.

    For the first half, the deficit totalled SR160bn, financed entirely through borrowing with no drawdown on government reserves. Revenue for the six months rose 6% year-on-year to SR599.76bn, while spending increased 15% to SR759.76bn. Actual first-half spending reached 58% of the full-year budget of SR1.312tn. Health and social development recorded the highest sectoral outlay at SR170.61bn, followed by the military at SR124.57bn and education at SR109.73bn.

    Public debt reached SR1.684tn by the end of the first half, up from an opening balance of SR1.519tn. Domestic debt stood at SR1.060tn and external debt at SR624.9bn. The government reserve closing balance was SR399.07bn.

    The kingdom has continued to tap the domestic debt market. The National Debt Management Centre closed its July 2026 issuance under the Saudi Arabian Government riyal-denominated sukuk programme at SR5.35bn, divided into five tranches. The largest, at SR3.83bn, matures in 2031, with further tranches of SR515m maturing in 2033, SR204m in 2036, SR300m in 2039 and SR500m in 2041.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18015899/main.gif
    Colin Foreman