Middle East project disputes increasing
8 November 2023

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.
Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.
The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.
“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.
“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”
Growing pains
Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.
“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.
“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”
HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.
While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.
Saudi resolution
In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.
“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”
Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.
In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.
One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.
Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.
A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.
The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.
“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.
“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.
“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”
Arbitration centres
Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.
He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.
The systems are maturing in Saudi Arabia and will soon reach a similar level.
“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.
But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.
According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.
This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.
Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.
A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.
“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”
With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.
As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.
Exclusive from Meed
-
-
Contractor wins Oman housing substation contract7 April 2026
-
UAE reviews $1.63bn fourth federal road project7 April 2026
-
Kingdom Holding Company signs Riyadh project deal7 April 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Adnoc builds long-term oil and gas production potential7 April 2026

Between 2023 and 2024, Abu Dhabi National Oil Company (Adnoc Group) spent an estimated $37bn on projects critical to achieving its upstream targets: increasing oil production capacity to 5 million barrels a day (b/d) by 2027 and attaining gas self-sufficiency by the end of the decade.
The state energy company spent more than $22.5bn in 2023 alone, marking the highest annual oil and gas project spending on record in the UAE. The Hail and Ghasha sour gas development – accounting for approximately $17bn – remains the single-largest contract award in the country’s hydrocarbons sector.
A slowdown in capital expenditure (capex) following two years of elevated spending is therefore in line with expectations. While engineering, procurement and construction (EPC) contract awards for upstream projects declined in 2025 and into this year, Adnoc has still committed close to $10bn over the past 15 months.
The largest award during this period came from Adnoc Offshore, which let contracts worth $7.5bn for three EPC packages under the Lower Zakum Long-Term Development Plan (LTDP-1). Spain’s Tecnicas Reunidas and Abu Dhabi-based NMDC Energy and Target Engineering Construction Company were selected last February to execute the works.
The Lower Zakum field, located 65 kilometres northwest of Abu Dhabi, is majority-owned by Adnoc Offshore (60%). Other stakeholders include an Indian consortium led by ONGC Videsh (10%), Japan’s Inpex (10%), China National Petroleum Corporation (10%), Italy’s Eni (5%) and France’s TotalEnergies (5%).
Adnoc Offshore aims to increase production capacity at Lower Zakum to 520,000 b/d by 2027 and sustain that level through 2034.
Offshore contracts in 2026
So far this year, Adnoc Offshore has awarded contracts for two key projects: the Satah Al-Razboot (Sarb) deep gas development and the expansion of the Nasr oil field.
Adnoc achieved final investment decision (FID) on the Sarb project in January and awarded the main EPC contract to US-based McDermott International. The contract is estimated to be worth around $500m, sources told MEED.
The project is expected to deliver 200 million cubic feet a day (cf/d) of gas by the end of the decade – enough to power more than 300,000 homes.
The scope includes the EPC of an offshore wellhead tower with four gas production wells, which will be connected to Das Island for processing through Adnoc Gas facilities. Works also include the installation of pipelines and intra-field connections linking the Sarb field to Das Island.
Also in January, Adnoc Offshore awarded McDermott a $942m contract for the Nasr-115 project, which will increase production capacity at the Nasr offshore field to 115,000 b/d. The field is located about 130km northwest of Abu Dhabi.
McDermott’s scope covers full EPCI services for two topside structures, a new manifold tower, a jacket, a bridge, associated pipelines, subsea cables and brownfield modifications.
Strategic projects in queue
Over the next 12-18 months, Adnoc’s upstream spending is expected to shift from meeting near-term production targets –now largely within reach – to building longer-term capacity beyond 2030.
Following $1.3bn in EPC awards in 2024 for the Upper Zakum expansion to 1.2 million b/d, Adnoc Offshore is advancing the next phase, which will increase capacity to 1.5 million b/d.
Located 84km offshore, Upper Zakum is the world’s second-largest offshore oil field. Adnoc Offshore has divided the EPC scope into three packages, with contractors submitting commercial bids for the UZ1.5MMBD project in February.
Adnoc Offshore is also progressing the Umm Shaif gas cap and surface pressure boosting project, aimed at increasing gas production by 550 million cubic feet a day (cf/d) and condensate output by 50,000 b/d. About 520 million cf/d of additional gas is expected to be fed into Adnoc’s sales gas network.
The first phase of the project has been split into three EPC packages:
- Offshore package 1: fabrication of a 30,000-tonne gas compression system
- Offshore package 2: fabrication of a 30,000-tonne gas compression system
- Onshore package: EPC of gas inlet and processing systems at Das Island
Adnoc Offshore is currently evaluating commercial bids submitted in February for these packages.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16285814/main.gif -
Contractor wins Oman housing substation contract7 April 2026
Oman’s Public Authority for Social Insurance has awarded a contract for the supply, installation, execution and maintenance of a main power substation for its affordable housing project.
The contract was awarded to Kuwait-based Al-Ahleia Switchgear Company.
The project comprises a 400/132/11kV main substation for the Affordable Housing Project, known locally as Al-Masaken Al-Muyassara.
The tender was announced last November, with the bid envelopes opened on 16 December 2025.
Al-Ahleia Switchgear submitted another bid in March for a contract to build three 132/11kV main transformer stations for Kuwait’s Public Authority for Housing Welfare (PAHW).
As reported by MEED, the company’s price of KD10.5m ($34.1m) was the lowest of two offers for the engineering, procurement and construction (EPC) contract.
Separately, in December, Al-Ahleia Switchgear submitted the lowest bid of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s PAHW.
The bid was marginally lower than the two other offers submitted by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16285335/main5555.jpg -
UAE reviews $1.63bn fourth federal road project7 April 2026
UAE authorities on 6 April unveiled details of the AED6bn ($1.63bn) fourth federal corridor scheme, a major highway programme aimed at boosting inter-emirate connectivity, increasing road capacity and easing congestion.
The project comprises a 68-kilometre corridor with 10 major interchanges, four flyovers and six to eight lanes in each direction.
Officials provided technical updates on the corridor, including revised connection points and coordination with local authorities to finalise route alignments in line with broader development plans.
Suhail Mohamed Al-Mazrouei, minister of energy and infrastructure, said the programme underscores the central role of infrastructure in the UAE’s development agenda and competitiveness. He was speaking while chairing the first meeting of the UAE Infrastructure and Housing Council this year.
The council also reviewed progress on federal infrastructure initiatives aimed at improving transport efficiency and strengthening coordination between federal and local authorities.
Al-Mazrouei said the next phase will focus on accelerating the delivery of high-impact projects to enhance transport system performance and support the shift towards smart and sustainable mobility in line with population growth and urban expansion.
The council also assessed progress on linking Ajman to the third and fourth federal corridors, which is expected to provide alternative routes, improve traffic flow and further enhance mobility between the emirates.
On public transport, the council reviewed a study on transport links between Dubai, Sharjah and Ajman to address rising commuting demand.
The proposed plan includes 10 priority routes incorporating bus rapid transit and dedicated lanes, with connections to key hubs such as the Dubai Metro and city centres.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16285296/main.jpg -
Kingdom Holding Company signs Riyadh project deal7 April 2026
Saudi Arabia’s Kingdom Holding Company has signed an agreement with Sumou Real Estate Company under which Sumou will manage the development, marketing and sale of a 3-million-square-metre land plot in Riyadh.
The scheme is expected to generate about SR4bn ($1bn) in total sales.
In a Tadawul disclosure, Kingdom Holding Company said its subsidiaries, Kingdom Real Estate Development Company and Trade Centre Company, have appointed Sumou as the exclusive development manager for the site.
The project is scheduled to be implemented over 36 months, starting once the masterplans are approved by the relevant authorities.
In a separate stock exchange statement, Sumou said it will be paid 6.5% of total infrastructure development costs and 2.5% of project sales, in addition to the brokerage commission paid by buyers.
Kingdom Holding Company said the agreement aligns with its long-term strategy for its Riyadh landbank, which originally totalled around 20 million sq m and is being developed in phases.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16284668/main.jpg -
Saudi Arabia’s Jubail industrial city hit by missile debris7 April 2026
Explosions were reported in Saudi Arabia’s Jubail industrial city on 7 April. Saudi authorities said the country’s air defence systems intercepted seven ballistic missiles targeting the Eastern Province, with debris landing near energy facilities, primarily in Jubail.
Jubail is one of the world’s largest petrochemical production hubs, with an annual output of about 60 million tonnes, accounting for an estimated 6% to 8% of global supply.
The incident places renewed focus on the kingdom’s flagship petrochemical cluster, where majority state-owned Saudi Basic Industries Corporation (Sabic) is a key investor.
Jubail also hosts major downstream oil, gas and petrochemical assets operated by Saudi Aramco, US-based Dow and France’s TotalEnergies, underscoring the industrial zone’s international significance.
Saudi officials said damage assessments are ongoing.
The developments follow an Israeli strike on 6 April targeting a major petrochemical complex in Iran’s southern Asaluyeh region, described as the country’s largest industrial hub.
Separately, authorities closed the King Fahd Causeway – the main bridge linking Saudi Arabia and Bahrain – early on 7 April as a precaution amid heightened security concerns.
The King Fahd Causeway Authority said in a post on X that vehicle movement had been “suspended as a precautionary measure” due to Iranian attacks targeting Saudi Arabia’s Eastern Province.
The 25-kilometre bridge is Bahrain’s only road link to the Arabian Peninsula.
US President Donald Trump has issued an ultimatum for Iran to reopen the Strait of Hormuz and threatened to bomb Iranian power plants and bridges if Tehran does not comply by 8pm EDT on 7 April.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16283711/main2424.jpg
