Middle East project disputes increasing

8 November 2023

 

The number of project disputes recorded every year in the Middle East and North Africa (Mena) is trending upwards as project activity increases and the pressure grows to execute projects on a fast-track basis.

Greater use of fast-track project models, where project execution starts before all the details of the preparatory design work are complete, can lead to a “triple whammy” of design issues that trigger disputes, according to Jad Chouman, a partner and the head of Middle East for the consultancy HKA, which specialises in risk mitigation and dispute resolution.

The three key causes of disputes related to fast-track projects are changes to the scope, design information being issued late, and incomplete designs supplied to contractors.

“In many fast-track projects, they start work before the design is 100 per cent complete,” says Chouman. “The fast-track nature of these projects is a major reason why we are seeing what we refer to as the ‘triple design whammy’.

“Owners want the projects quickly and they push the contractors to start early, and changes to the designs can cause serious problems to the projects.”

Growing pains

Due to the expanding Mena projects market, increasing project complexity and growing tendency to use fast-track project schedules, Chouman says he would not be surprised to see an upturn in the volume of project disputes every year until 2030.

“The rise in disputes related to fast-track projects is something that we’ve noticed over the past two or three years,” he says.

“The very compressed time frames for projects means that if there is disruption due to a change or a delay to an approval, the overall impact of that delay is often magnified.”

HKA also says some contractors are not fully considering the impact of the shortage of skilled labour in the region when estimating how quickly projects can be executed.

While these are all significant challenges, HKA also has reason to believe that many of the disputes could be resolved amicably.

Saudi resolution

In Saudi Arabia, Chouman says a share of future disputes could be resolved amicably because the kingdom is so focused on rapid project execution and will want to avoid projects stalling due to drawn-out legal disputes.

“In order for projects to be successful and to be completed within a reasonable time period, it is in the interest of everyone that they are resolved amicably.”

Another factor that could reduce the number of legal disputes is the increased use of more collaborative contract models.

In these contracts, the parties share the risk. The main contractor usually gets involved in the project at an earlier stage so they have a say in how the design is created.

One model increasingly used in Saudi Arabia is the early contractor involvement (ECI) model.

Under the ECI model, a single contractor is selected at an earlier stage of the design process. This may be either at the concept or detailed design stages, depending on the employer client’s preference and the level of involvement required.

A key objective of using an ECI contract and selecting a contractor early is to allow the contractor to use its knowledge and experience to influence design decisions to increase buildability or value during the process.

The contractor is appointed by the client during the first stage to perform services similar to a professional consultant.

“One of the main positive impacts that this sort of contract is likely to have is avoiding the worst kind of disputes between clients and contractors,” says Chouman.

“At the end of the day, the leadership in Saudi Arabia wants to be successful and get things done, and because of this, they are going to want to try and resolve any delays or cost overruns in a fair and amicable way.

“There is significant project momentum in Saudi Arabia and they want to maintain this positive environment.”

Arbitration centres

Dispute resolution processes have progressed significantly in several key markets in the Mena region over the past 20 years, which is having a positive impact on the projects market, according to Chouman.

He says Dubai and Abu Dhabi have developed mature arbitration processes that are competitive with international dispute resolution centres across the world.

The systems are maturing in Saudi Arabia and will soon reach a similar level.

“The development of these advanced dispute resolution centres has helped to make the UAE an attractive business hub,” says Chouman.

But while dispute resolution processes in some Mena markets parallel other world-leading hubs, the Middle East, on the whole, performs poorly in terms of project delays.

According to data collected by HKA, the average delay for projects in the Middle East is 82 per cent of the original time schedule.

This is high compared to the US, Europe, Asia and Oceania, where the average delay times are 59 per cent, 60 per cent, 63 per cent and 49 per cent.

Africa is the only continent that performs worse than the Middle East, with average project delays of 83 per cent of the original project schedule.

A key reason for the significant delays in the Middle East is the size of the projects market and complexity of the projects, says Chouman.

“It is a market with a lot of ambitious projects both in terms of size and complexity,” he says. “Additionally, the clients and contractors are also being even more optimistic with their predictions for project completion times, which is a factor.”

With the Mena region’s projects market continuing to expand rapidly, there are plenty of opportunities for contractors. However, there is also a growing scope for delays and disputes over project execution.

As the region’s biggest markets push ahead with ambitious project plans, it remains to be seen whether they have put enough thought into dispute resolution frameworks and methods to keep construction issues out of the courts.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11278295/main.jpg
Wil Crisp
Related Articles
  • Kuwait receives bids for Al-Khairan phase one IWPP

    2 June 2026

     

    Two developer consortiums have submitted bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, according to a source.

    Bids were received by the Kuwait Authority for Partnership Projects (Kapp) on 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The bidders include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The Al-Khairan IWPP is being procured by Kapp in partnership with the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate in the tender.

    Ernst & Young, BNP Paribas, AtkinsRealis and Addleshaw Goddard are financial advisers on the project. Chadbourne & Parke is acting as legal adviser.

    The winning bidder will sign a set of public-private partnership agreements covering financing, design, construction, operation and transfer of the project. The energy conversion and water-purchase agreement is expected to cover a 25-year supply period.

    Future phases

    The Al-Khairan IWPP project is expected to run on low-sulphur fuel oil as the primary fuel and to accommodate crude oil, gas oil and natural gas as backup fuels. Future phases will further expand capacity.

    It is understood that the estimated $750m second phase of the Al-Khairan IWPP project will add a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant.

    The project, first mooted over a decade ago, remains in the early development stages, with no plans currently to advance to procurement in 2026, a source said.

    According to the source, the immediate focus is on advancing plans for the 3,600MW Nuwaiseeb power and water desalination IWPP project.

    The Nuwaiseeb IWPP plant will have a desalination capacity of 75 million imperial gallons a day.

    Kapp plans to release a transaction advisory tender for the project by the end of the year.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072685/main.jpg
    Mark Dowdall
  • Doosan confirms Saudi Jafurah 2 cogen contract

    2 June 2026

    South Korea’s Doosan Enerbility has confirmed it has signed an engineering, procurement and construction (EPC) contract worth about $556m for the second phase of the Jafurah combined heat and power (CHP) plant in Saudi Arabia.

    The project is being developed by Korea Electric Power Corporation (Kepco) in partnership with Saudi Aramco.

    Doosan said the contract covers design, equipment supply, installation, construction and commissioning of the facility.

    The Jafurah CHP phase 2 project will be built near the Jafurah gas field, about 400 kilometres east of Riyadh. Once operational, it will generate 330MW of electricity and produce 465 tonnes of steam an hour for the nearby gas field.

    According to the firm, the project’s main steam turbine will be supplied by Doosan Skoda Power, a subsidiary of Doosan Enerbility.

    WSP is acting as the project management consultant for the project, which is scheduled for completion in 2029.

    The Jafurah gas development is part of Aramco’s $3.2bn unconventional resources programme, which aims to develop shale gas in three areas. Jafurah lies southeast of Ghawar, the world’s largest conventional oil field.

    The programme is part of Riyadh’s plans under Vision 20230 to ensure the kingdom remains self-sufficient in gas supply amid rising demand from the residential and industrial power sectors.

    Jafurah phase one

    In February 2025, MEED exclusively reported that talks were under way to expand the capacity of the $500m Jafurah cogeneration independent steam and power plant (ISPP).

    Construction works were completed on the facility last November.

    At the time of its procurement, the plant’s first phase was to have a power capacity of 270-320MW, and a low-pressure (LP) steam demand of 77-166 thousand pounds an hour (klb/hr) and high-pressure (HP) steam demand of 29-126 klb/hour by 2023.

    The LP and HP steam demand will increase to 283-373 klb/hr and 66-321 klb/hr by 2027, respectively.

    The oil giant issued the letter of award to Kepco for the contract to develop the Jafurah ISPP scheme in July 2022.

    Kepco subsequently awarded South Korea’s Doosan Heavy Industries & Construction the project’s EPC contract.

    US/India-based Synergy Consulting provided financial advisory services to Kepco on its bid.

    Sumitomo Mitsui Banking Corporation (SMBC) served as the client’s financial adviser for the project. Germany’s Fichtner Consulting Engineers is technical consultant, while the UK’s Wood Group is project management consultant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17072199/main.jpg
    Mark Dowdall
  • Al-Mabanee submits lowest bids for Kuwait infrastructure

    2 June 2026

    Kuwait’s Public Authority for Housing Welfare (PAHW) has opened commercial bids for two major infrastructure and public buildings packages at South Al-Mutlaa Residential City.

    Local firm Al-Mabanee United Company has emerged as the lowest bidder for both contracts, submitting combined offers worth KD44m. Both packages entail the construction, completion and maintenance of services, infrastructure works and public buildings for different district centres within the city.

    The first contract covers the infrastructure and public buildings for the N3 District Centre. PAHW received proposals from eight bidders, with Al-Mabanee United Company submitting the lowest price at KD20.9m. The second-lowest offer was submitted by The Contractor General Trading & Contracting Company at KD22.4m, followed by Golden Engineering Group for General Trading & Contracting at KD22.7m, though Golden Engineering Group was flagged for not providing a bid bond.

    Al-Khonaini General Trading & Contracting Company, operating as Inshat Al-Khonaini, ranked fourth with a bid of KD22.7m, followed closely by Kuwait Industrial Centre Company at KD22.8m. Combined Group Contracting Company submitted a bid of KD23.8m, Al-Dar Engineering & Construction Company bid KD25.7m, and China’s Sichuan Road & Bridge Group Corporation submitted the highest active proposal at KD29m. 

    The second contract is for identical infrastructure and public building works at the N1 District Centre. Al-Mabanee United Company submitted the lowest bid of KD22.8m. Its closest competitor was The Contractor General Trading & Contracting Company, which submitted an offer of KD23.9m.

    Al-Khonaini General Trading & Contracting Company came in third with a bid of KD24.2m, followed by Kuwait Industrial Centre Company at KD24.4m and Golden Engineering Group for General Trading & Contracting at KD24.4m. Combined Group Contracting Company placed a bid of KD26m, Al-Dar Engineering & Construction Company bid KD26.5m, and United Construction Company, known as Al-Inshat Al-Muttahida, submitted an offer of KD 30.9m. Al-Ghanim International General Trading & Contracting filed the highest bid at KD344m and was also noted for lacking a bid bond.

    South Mutlaa Residential City is a large-scale planned development designed to accommodate around 400,000 residents in a modern, fully serviced urban environment. Once completed, it will offer contemporary housing alongside extensive logistical services and a wide range of public and commercial areas, including hospitals, schools and other social services.

    The project also includes major infrastructure works such as approximately 150 kilometres of roads and related structures, lighting and other public works, as well as integrated systems for water distribution, rainwater collection and sewage. In addition, it will provide the civil infrastructure needed for electricity distribution, telecommunications networks and traffic control to support a well-connected, functional city.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071938/main.gif
    Colin Foreman
  • Local developer secures finance for three Riyadh projects

    2 June 2026

    Qimam Noshoz for Real Estate Development Company, a subsidiary of Saudi Arabia’s Banan Real Estate Company, has signed a sharia-compliant credit facility agreement worth SR84m ($22.4m) with Riyad Bank to fund three commercial, hospitality and sports developments in the kingdom.

    The financing agreement is split into two distinct tranches to align with the projects’ development timelines. The first tranche consists of SR49m with a maturity duration of seven years, while the remaining SR35m has been secured for an eight-year term.

    Qimam Noshoz will utilise the capital to fund construction works for the Al-Rahmaniyah Gem and Al-Wadi District Gem projects. Both of these projects are already leased to the fitness operator Armah Sports Company. The other project is an independent hotel located within the Al-Wadi District.

    The Al-Wadi development is designed as an integrated commercial complex spanning approximately 7,818.5 square metres of land, with a built-up area of about 975 square metres. It includes a men’s gym, a women’s gym and a hotel building.

    The Al-Rahmaniyah project is an integrated commercial development combining fitness facilities with retail. The asset features men’s and women’s gyms operating alongside an independent commercial zone.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17071628/main.jpg
    Colin Foreman
  • SLB wins $385m contract for Kuwait oil research centre

    2 June 2026

    Schlumberger Oilfield Eastern, a unit of the US-headquartered oilfield services company SLB, has been awarded a KD118m ($385m) contract to develop an oil and gas research centre in Kuwait.

    The contract was awarded by the state-owned upstream operator Kuwait Oil Company (KOC), according to a report by Kuwait’s Al-Rai newspaper.

    The Ahmadi Innovation Valley (AIV) project is planned as an advanced research and innovation hub equipped with specialised facilities and technical teams focused on applied research for Kuwait’s oil and gas sector.

    The contract was awarded after the Higher Purchase Committee (HPC) of Kuwait’s national oil and gas company Kuwait Petroleum Corporation (KPC) determined the bid to be compliant with the project’s technical and commercial requirements.

    In February 2025, KOC signed memorandums of understanding (MoUs) with five international oilfield service companies to support the development of the AIV initiative.

    These companies were:

    • SLB (US)
    • Baker Hughes (US)
    • Weatherford (US)
    • Halliburton (US)
    • National Energy Services Reunited (US)

    Under the preliminary agreements, each of the five companies agreed to establish a world-class research and development centre at the project site, focused on helping KOC meet challenges in the upstream sector.

    KOC’s CEO Ahmad Jaber Al-Eidan had said in February 2025 that the project will enable Kuwait to keep pace with global transformations while investing in advanced technologies to ensure the sector’s sustainability and achieve operational excellence.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17063475/main.gif
    Wil Crisp