The resurgence in investment in metro and intercity lines means the region is no longer an emerging market for the global rail industry. It is now an established hub with an expanding network of projects and, increasingly, the need for ongoing servicing, upgrades and new technologies.

“We are reaching a point where it is not just about building new lines. Customers are now understanding that it is not enough to just buy new trains – they also need long-term partnerships to service and maintain them efficiently,” says Martin Vaujour, Alstom’s Africa, Middle East and Central Asia region president.

Alstom, which has supplied rolling stock and systems for major schemes in the region such as the Riyadh Metro, is now seeing growing demand for both new-build contracts and service agreements. “There are still lots of new investments,” he says, “but also growing activity in signalling projects, service projects and spare parts – areas that used to be small but are now taking off. That is a [source] of satisfaction for me, because those businesses are less risky, have better margins and create long-term relationships with customers.”

The change is an important development as the region becomes a mature market with diverse opportunities for the rail industry. “There was a time when countries would just buy materials with export credit,” says Vaujour. “Now, they are supporting local capacity to service and maintain trains. The mindset is evolving, and that is a very positive sign.”

Saudi expansion

Buoyed by the opening of Riyadh Metro at the end of 2024, Saudi Arabia remains an important market. “They are happy with the success [of Riyadh Metro],” says Vaujour. “There is extension work on the existing lines, new rolling stock being discussed and a potential Line 7 project. The network is expanding, and that is a great success story.”

The next wave of growth in Saudi Arabia includes the planned Qiddiya Express high-speed line, which has recently attracted expressions of interest. 

“That project has been on our radar for some time,” says Vaujour. “It is under the umbrella of the Royal Commission for Riyadh City, which is very well organised and structured. That gives the project strength and credibility.”

The scheme is being developed as a public-private partnership, a model that Vaujour says fits Saudi Arabia’s stable economic environment. “Public-private partnerships (PPPs) take longer to put together because they are more complex to structure, but in countries like Saudi Arabia – stable and with the capacity to raise debt – why not?” he says. 

“We are fine with PPPs. We have experience from France, the UK and Spain.”

While Alstom does not invest directly, it plays a key role in structuring deals. “We are facilitators and advisers,” says Vaujour. 

“Our job is to accompany the customer, to adjust and iterate with them, and to help find the best solution. PPP is one of the tools in the box – not the simplest one, but one that works.”

The challenge in the market today is not a lack of opportunity, but deciding where to focus. 

“Our main problem is not the market; it is how to be selective,” he says. “We have more than enough opportunities to ensure a nice trajectory of growth. The difficulty is to pick our battles and fight for the right ones.”

The challenge in the market today is not a lack of opportunity, but deciding where to focus

Shifting focus

In Africa and Central Asia, Alstom has long-term locomotive and commuter train partnerships that offer years of visibility. In the Gulf, by contrast, the model remains dominated by engineering, procurement and construction-style projects. 

“It is more big projects, where civil contractors team up with us to deliver metros or airport people movers,” says Vaujour.

As regional urban transport networks become established, attention is turning to intercity and high-speed rail. “In the Gulf, the Abu Dhabi-Dubai high-speed project is probably the most advanced, while Qiddiya Express and upgrades to the Haramain line in Saudi Arabia could also accelerate momentum.”

Interest in high-speed connections between Riyadh, Doha and Kuwait is also growing, although such schemes will depend on electrification. “High-speed rail comes with electrification,” Vaujour notes. “And that means significant investment.”

In addition to new infrastructure, the rail sector is being reshaped by technology. Alstom is investing in clean traction systems, such as hydrogen and battery-powered trains, as well as in autonomous operations.

“Hydrogen and battery traction are progressing, but they are still in an early stage,” says Vaujour. “Diesel will continue to dominate freight for some time, because there is no clean technology yet that can deliver that level of power. But for passenger services, we are starting to see progress.”

Driverless trains are another major growth area. “Customers everywhere are interested, partly because it is increasingly hard to find drivers, and also because software drives more efficiently than humans. It is more energy-efficient and reduces wear and tear,” says Vaujour.

As the Middle East’s networks expand, upgrading existing infrastructure is becoming as important as building new lines. Signalling systems are central to this evolution. “You cannot just create new lines every year – it is too expensive,” says Vaujour. “Signalling allows you to double train frequency. It is what makes networks more efficient.”

The evolution reflects a wider transformation of the region’s rail sector. “The Middle East has become an established rail hub,” says Vaujour. “It is no longer just about building – it is about operating, maintaining and evolving.” 

https://image.digitalinsightresearch.in/uploads/NewsArticle/15131845/main.gif
Colin Foreman
Related Articles
  • Oman’s growth forecast points upwards

    24 December 2025

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15306449/main.gif
    MEED Editorial
  • December 2025: Data drives regional projects

    23 December 2025

    Click here to download the PDF

    Includes: Top inward FDI locations by project volume | Brent spot price | Construction output


    MEED’s January 2026 report on Oman includes:

    > COMMENT: Oman steadies growth with strategic restraint
    > ECONOMY: Oman pursues diversification amid regional concerns
    > BANKING: Oman banks feel impact of stronger economy
    > OIL & GAS: LNG goals galvanise Oman’s oil and gas sector

    > POWER & WATER: Oman prepares for a wave of IPP awards
    > CONSTRUCTION: Momentum builds in construction sector

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15306140/main.gif
    MEED Editorial
  • Local firm bids lowest for Kuwait substation deal

    22 December 2025

    The local Al-Ahleia Switchgear Company has submitted the lowest price of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare (PAHW).

    The bid was marginally lower than the two other offers of KD35.1m and KD35.5m submitted respectively by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.

    PAHW is expected to take about three months to evaluate the prices before selecting the successful contractor.

    The project is one of several transmission and distribution projects either out to bid or recently awarded by Kuwait’s main affordable housing client.

    This year alone, it has awarded two contracts worth more than $100m for cable works at its 1Z, 2Z, 3Z and 4Z 400kV substations at Al-Istiqlal City, and two deals totalling just under $280m for the construction of seven 132/11kV substations in the same township.

    Most recently, it has tendered two contracts to build seven 132/11kV main substations at its affordable housing project, west of Kuwait City. The bid deadline for the two deals covering the MS-01 through to MS-08 substations is 8 January.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305745/main.gif
    Edward James
  • Saudi-Dutch JV awards ‘supercentre’ metals reclamation project

    22 December 2025

    The local Advanced Circular Materials Company (ACMC), a joint venture of the Netherlands-based Shell & AMG Recycling BV (SARBV) and local firm United Company for Industry (UCI), has awarded the engineering, procurement and construction (EPC) contract for the first phase of its $500m-plus metals reclamation complex in Jubail.

    The contract, estimated to be worth in excess of $200m, was won by China TianChen Engineering Corporation (TCC), a subsidiary of China National Chemical Engineering Company (CNCEC), following the issue of the tender in July 2024.

    Under the terms of the deal, TCC will process gasification ash generated at Saudi Aramco’s Jizan refining complex on the Red Sea coast to produce battery-grade vanadium oxide and vanadium electrolyte for vanadium redox flow batteries. AMG will provide the licensed technology required for the production process.

    The works are the first of four planned phases at the catalyst and gasification ash recycling ‘Supercentre’, which is located at the PlasChem Park in Jubail Industrial City 2 alongside the Sadara integrated refining and petrochemical complex.

    Phase 2 will expand the facility to process spent catalysts from heavy oil upgrading facilities to produce ferrovanadium for the steel industry and/or additional battery-grade vanadium oxide.

    Phase 3 involves installing a manufacturing facility for residue-upgrading catalysts.

    In the fourth phase, a vanadium electrolyte production plant will be developed.

    The developers expect a total reduction of 3.6 million metric tonnes of carbon dioxide emissions a year when the four phases of the project are commissioned.

    SARBV first announced its intention to build a metal reclamation and catalyst manufacturing facility in Saudi Arabia in November 2019. The kingdom’s Ministry of Investment, then known as the Saudi Arabian General Investment Authority (Sagia), supported the project.

    In July 2022, SARBV and UCI signed the agreement to formalise their joint venture and build the proposed facility.

    The project has received support from Saudi Aramco’s Namaat industrial investment programme. Aramco, at the time, also signed an agreement with the joint venture to offtake vanadium-bearing gasification ash from its Jizan refining complex.

    Photo credit: SARBV

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305326/main.gif
    Edward James
  • QatarEnergy LNG awards $4bn gas project package

    22 December 2025

    QatarEnergy LNG, a subsidiary of state-owned QatarEnergy, has awarded the main engineering, procurement, construction and installation (EPCI) contract for a major package for the second phase of its North Field Production Sustainability (NFPS) project.

    A consortium comprising the Italian contractor Saipem and state-owned China Offshore Oil Engineering Company (COOEC) has secured the EPCI contract for the COMP5 package. The contract value is $4bn, with Saipem declaring its share to be worth $3.1bn.

    Milan-headquartered Saipem said the contract will run for about five years. The scope of work comprises engineering, procurement, fabrication and installation of two compression complexes, each including a compression platform, a living quarters platform, a flare platform supporting the gas combustion system, and the related interconnecting bridges. Each complex will have a total weight of about 68,000 tonnes.

    Offshore installation operations will be carried out by Saipem’s De He construction vessel in 2029 and 2030.

    MEED previously reported that the following contractors submitted bids for the NFPS phase two COMP5 package:

    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem/China Offshore Oil Engineering Company (Italy/China)

    QatarEnergy LNG, formerly Qatargas, is said to have issued the tender for the NFPS phase two COMP5 package in the first quarter of the year.

    Contractors submitted technical bids for the COMP5 package in late June, while commercial bids were submitted by 8 October, as per sources.

    Based upon initial evaluation of bids by QatarEnergy LNG, L&TEH has emerged as the lowest bidder for the COMP5 package, followed by McDermott, with the consortium of Saipem and COOEC in third place, MEED reported in late October.

    In the weeks following that, the project operator is said to have engaged all bidders for a final round of negotiations, during which the consortium of Saipem and COOEC is believed to have “clinched the deal”, according to sources.

    The detailed scope of work on the COMP5 package covers the EPCI work on the following:

    • Two gas compression platforms, each weighing 30,000-35,000 tonnes, plus jacket
    • Two living quarters platforms, plus jacket
    • Two gas flare platforms, plus jacket
    • Brownfield modification work at two complexes
    NFPS scheme

    QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme requires the state enterprise to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the estimated $40bn-plus programme.

    QatarEnergy has already invested billions of dollars in engineering, procurement and construction works on the two phases of the NFPS project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.

    The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.

    Saipem has been the most successful contractor on the second NFPS phase, securing work worth a total of $8.5bn.

    QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities. The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.

    The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.

    Following that, Saipem won combined packages COMP3A and COMP3B of the NFPS project’s second phase in September last year.

    The scope of work on the combined packages encompasses the EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

    Separately, QatarEnergy LNG awarded McDermott the contract for the NFPS second phase package known as EPCI 1, or COMP1, in July 2023. The scope of work on the estimated $1bn-plus contract is to install a subsea gas pipeline network at the North Field gas development.

    In March this year, India’s Larsen & Toubro Energy Hydrocarbon (LTEH) won the main contract for the combined 4A and 4B package, which is the fourth package of the second phase of the NFPS project and is estimated to be valued at $4bn-$5bn.

    The main scope of work on the package is the EPCI of two large gas compression systems that will be known as CP8S and CP4N, each weighing 25,000-35,000 tonnes. The contract scope also includes compression platforms, flare gas platforms and other associated structures.

    LTHE sub-contracted detailed engineering and design works on the combined 4A and 4B package to French contractor Technip Energies.

    NFPS first phase

    Saipem is also executing the EPCI works on the entire first phase of the NFPS project, which consists of two main packages.

    Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.

    QatarEnergy LNG awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.

    Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.

    The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.

    In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.

    QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.

    Saipem’s scope of work on the package, which is known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.

    Saipem performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15305330/main2239.jpg
    Indrajit Sen