Water sector braces for likely slowdown

27 December 2024

 

Geopolitical tensions, climate change and higher-than-average population growth have exacerbated the water demand and supply gap across the Middle East and North Africa (Mena) region, home to some of the world’s most water-stressed countries.

For example, Jordan, where available water per capita is equivalent to only 12% of the absolute water scarcity level, hosts over 700,000 refugees fleeing wars and conflicts in neighbouring countries.

Most regional governments have developed and started to implement water strategies aimed at narrowing this gap. Subsidies are being phased out, environmental campaigns are being developed and digital solutions are being deployed in order to manage demand and improve efficiency.

Expanding desalination and treatment capacity, increasing treated sewage effluent (TSE) reuse, boosting reservoir capacity and building more efficient transmission and distribution networks are key levers used to improve supply.

Strong spending 

These efforts have prompted significant capital spending on more energy-efficient water production, distribution and storage facilities, typically in partnership with private investors, particularly among the more affluent states.

According to data from regional projects tracker MEED Projects, the Mena region awarded $17bn of project contracts across the water desalination, treatment, transmission and distribution, storage and district cooling subsectors in the first nine months of 2024.

This figure represents about 72% of the contracts awarded in 2023 and is slightly above the average value of annual contract awards in the preceding five years.

With only a few more packages expected to be awarded before the end of the year, 2024 looks set to be one of the best years so far in terms of water project activity, even if it fails to match the record value of contracts awarded in 2023, which reached almost $24bn.

In 2024, Saudi gigaproject developer Neom set the pace in January by awarding a $4.7bn contract to build dams at the Trojena Mountain Resort in Tabuk to Italian contractor WeBuild. 

The contract covers the construction of three dams that will form a freshwater lake for the Trojena ski resort. The main dam will have a height of 145 metres and will be 475 metres long at its crest. It will be built using 2.7 million cubic metres of roller compact concrete.

While this project does not necessarily belong to the band of solutions that aim to narrow the water supply and demand gap, the overall development is part of Saudi Arabia’s drive to boost tourism and diversify its economy away from oil.

Meanwhile, 2024 also saw the award by UAE northern emirate utility Sharjah Electricity, Water & Gas Authority of the contract to develop its first independent water project (IWP), the 400,000 cubic-metres-a-day facility in Hamriyah, to Saudi utility developer Acwa Power, the contract’s sole bidder.

In May, Saudi Arabia’s National Water Company announced that it had completed the award of 10 contracts under the first phase of its privatisation programme. Each rehabilitate, operate and transfer contract involves the retrofitting or expansion of existing sewage treatment plants and associated network, and their long-term operation and management. The facilities are expected to deliver water at the TSE level for irrigation reuse.

On the greenfield sewage treatment front, Saudi Water Partnership Company (SWPC) awarded a $400m contract to develop the Al-Haer independent sewage treatment plant (ISTP) project to a team comprising the local Miahona Company and Belgium’s Besix. The facility is the largest and first to be tendered under the third round of the water offtaker’s ISTP procurement programme.

In September, Chennai-headquartered VA Tech Wabag confirmed it had won a $317m contract to build the Ras Al-Khair seawater reverse osmosis (SWRO) facility in Saudi Arabia using an engineering, procurement and construction (EPC) model. The project client is Saudi Water Authority (SWA), formerly Saline Water Conversion Corporation.

In Oman, Nama Water Services awarded two water distribution network packages, worth a combined $600m, catering to Al-Dhahirah Governorate.

Jordan also appointed a team comprising Paris-based Meridiam, Suez and Vinci Construction Grands Projets, along with Egypt’s Orascom Construction, for the contract to develop the Aqaba-Amman water conveyance and desalination scheme. It is the country’s largest infrastructure project to date and the first phase is valued at an estimated $2bn-$3bn.

The project is crucial to addressing Jordan’s severe water shortage problem, piping desalinated water over 445 kilometres from the southern Red Sea coast to the country’s northern regions. The consortium is talking to lenders and aims to reach financial close for the project in 2025.

Slower momentum

Despite 2024 being a good year for contract awards, it fell short of the expectation built over the past few years, when the region’s largest economies began to execute their long-term water strategies.

For example, in Saudi Arabia, the years-long restructuring of the domestic water sector took a significant turn in 2024, with Water Transmission Company (WTCO), the kingdom’s licensed desalinated water transmission operator, gaining a broader portfolio of projects. As a result, the mandate to procure upcoming water transmission pipelines has been transferred to WTCO from SWPC.

The slower pace of IWP contract awards in Saudi Arabia was somewhat offset by a slew of tenders from SWA. The authority received bids for the EPC contracts to build four SWRO facilities in 2024, although as of November it had only managed to award one.

Earlier in 2024, Saudi gigaproject developer Neom also shelved a project to develop a zero-liquid discharge (ZLD) SWRO plant.

“The year may not have been as strong as 2023, but it is still a good year,” says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting. “Some projects have been delayed or cancelled – for instance a few in Saudi Arabia – but all in all [2024 has been] a good year for the water business.”

Bryniak adds that Neom’s ZLD scheme is one of the year’s shelved projects that he would like to see revived in the future.

Beyond the GCC states, Morocco and Egypt are endeavouring to move their planned SWRO projects into the tendering phase.

In Morocco, Office National de L’Electricite et de L’Eue Potable (Onee) extended the review of its second IWP in Nador while waiting for its first IWP in Casablanca to reach financial close.

The first batch of renewable energy- powered desalination plants in Egypt has yet to reach the proposals stage despite the Sovereign Fund of Egypt having completed the bid prequalification process in 2023.

Potential contract awards

According to data from MEED Projects, an estimated $34bn-worth of water projects are in the tendering stage across the Mena region. A further $40bn-worth is in the prequalification stage and $57bn is in the design and study phases.

The $22bn Dubai Strategic Sewerage Tunnels (DSST) scheme stands out among the upcoming projects due to its scale, as well as for the chosen procurement approach.

The project aims to convert Dubai’s existing sewerage network from a pumped system to a gravity system by decommissioning the existing pump stations and providing a sustainable and reliable service that is fit for the future.

In April, Dubai Municipality launched the procurement process for the DSST project, which is to be developed as a public-private partnership (PPP).

While a dose of pessimism persists over the chosen PPP model – in part due to the project’s scale and strong civil works orientation, and Dubai’s dismal track record in procuring PPP schemes outside the utility sector – the project has managed to attract strong interest from EPC contractors, as well as from potential investors and sponsors.

Some of those that have sought to prequalify as investors, such as Begium’s Besix, Beijing-headquartered China Railway Construction Corporation and South Korea’s Samsung C&T, have previously been prequalified as EPC contractors for the DSST project, which suggests that the preferred approach of prequalifying EPCs ahead of investors could offer advantages.

In Saudi Arabia, WTCO, SWA, SWPC and Neom’s utility subsidiary Enowa are each expected to let several contracts in 2025, while Bahrain and Abu Dhabi could award one IWP contract each.  

However, a robust overall pipeline does not necessarily guarantee that 2025 will resemble the upward trajectory that the sector has seen in the past two years.

“This year could be a turning point for the water industry throughout Mena,” says Bryniak, alluding to the possibility that, come January, the foreign and climate policies of the new occupant of the White House could affect the trend of water production capacity buildout in the Mena region.

Bryniak says that if US President-elect Donald Trump follows through with his promises, then we may be in store for, among other events, lower energy prices as the US drills more oil; a dampening of world trade as the US places tariffs on imports, especially on Chinese goods and services; less focus on the environment; and, generally, a more isolationist America.

“In my view, much depends on how much oil prices fall,” he continues. 

“A significant drop in oil prices could result in cut-backs in a lot of development projects, and this, in turn, will adversely impact water demand and the overall build programme.”  

However, the impact will not be uniform across asset types and procurement models, Bryniak notes. He expects water PPP projects to continue to grow, especially if capital availability is reduced by lower oil prices, as this is one way to preserve capital for use in other areas. 

“I do not see any reason for tariffs to fall further in 2025. Tariffs, in my view, will remain roughly where they are now or increase slightly,” adds Bryniak.  

However, the executive says that EPC contracts will likely have “a higher opportunity cost”, so there might be a reduced focus on this type of procurement model.  

He concludes: “To the extent that development projects get trimmed down due to less capital being available as a result of significantly lower oil prices, then water procurers and other developers will likely scale back their projects.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13146291/main.gif
Jennifer Aguinaldo
Related Articles
  • Riyadh Expo sets November bid deadline for Souq construction

    29 October 2026

     

    Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has allowed contractors until 11 November to submit bids for a contract to deliver the Souq areas within the Expo site.

    The tender was floated on 30 July, with an initial submission deadline of 9 October.

    The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).

    The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works. 

    The precincts comprise:

    • Precinct 1 – The Icon: 41,417 sq m
    • Precinct 2 – Place & Planet: 62,306 sq m 
    • Precinct 3 – Culture of Wisdom: 67,112 sq m  
    • Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m  
    • Precinct 5 – Adaptation & Innovation: 82,358 sq m

    The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.

    The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, connecting the site’s iconic and thematic assets.

    The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.

    Site progress

    Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.

    Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to build a new metro station serving the Expo 2030 site.

    In April, ERC awarded two contracts to local firm Al-Yamama Company for the next phase of infrastructure works at the site.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.

    That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20998514/main.jpg
    Yasir Iqbal
  • Iraq oilfield water scheme to hit milestone next year

    29 October 2026

     

    China Petroleum Pipeline Engineering (CPP) expects to start laying pipeline for Iraq’s Common Seawater Supply Project (CSSP) in Basra in mid- or late next year, according to industry sources.

    The project is behind schedule, partly because importing sections of pipeline is proving challenging due to disruptions to shipping through the Strait of Hormuz.

    The project is being managed by state-owned Basra Oil Company (BOC), with Australia’s ILF acting as a project management consultant after completing the front-end engineering design (feed).

    Under current plans, the pipelines will be buried, which is expected to make them more secure than if they were installed on the surface.

    Phased development

    The client for the first phase of the CSSP is France’s TotalEnergies in partnership with QatarEnergy and BOC.

    The first phase is split into two packages currently under execution and will ultimately have the capacity to transport 5 million barrels a day (b/d) of water.

    The first package focuses on developing pipelines, and the second on developing a water treatment facility.

    CPP is executing the pipeline package contract.

    It signed a $2.5bn contract with BOC for the package in September last year.

    Also in September 2025, South Korea’s Hyundai announced that it had signed a contract worth 4.39tn won ($3.16bn) for the processing plant package.

    In September this year, MEED reported that early groundworks had started for both packages of the first phase of the CSSP.

    Phase one of the project is scheduled to start up in late 2028 or early 2029.

    Earlier this month, US-headquartered Exxon Mobil signed a memorandum of understanding related to the project’s second phase, which is expected to add 2.5 million b/d of water capacity.

    The CSSP will inject processed water into several of Iraq’s biggest oil fields. These include Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon. Water from the project will also be used in the Maysan and Dhi Qar fields.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20981033/main.jpg
    Wil Crisp
  • Dubai tenders Al-Awir sewerage and stormwater works

    29 October 2026

     

    Dubai Municipality has invited contractors to bid for a contract to build sewerage and stormwater infrastructure in New Al-Awir 1st.

    The project (DS317-C1) comprises about 95 kilometres of sewerage gravity network, excluding house connections, and about 105km of stormwater pipelines. The scope also includes house connection pipes, a stormwater pond and oil interceptors.

    According to tender documents seen by MEED, the tender was issued on 23 October, with a bid submission deadline of 12 November.

    The project comes amid wider residential and infrastructure development in Al-Awir 1. In January 2025, Dubai’s Roads & Transport Authority (RTA) announced plans to build 16.5km of internal roads in the area, including a new entrance from Emirates Road.

    In February 2025, MEED exclusively reported that the RTA had selected a local firm to undertake the road construction works.

    The Mohammed Bin Rashid Housing Establishment has also reported progress on housing projects in Al-Awir as part of a wider programme to develop residential communities across Dubai.

    The sewerage and stormwater project is relatively large compared with recent stormwater tenders, with the total cost estimated at up to AED1bn ($272m).

    The works will include approximately 69.2km of house connection pipes and 4,630 inspection chambers. The sewerage network will also include about 1,511 manholes, while the stormwater network will comprise approximately 1,247 manholes.

    Contractors will also be required to use no-dig construction methods for sections of the pipeline. The scope includes ground investigations, utility protection and traffic management.

    The bill of quantities specifies a stormwater pond with a composite volume of approximately 1.2 million cubic metres.

    Earlier this week, Dubai Municipality confirmed it had awarded contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.

    The projects are part of Dubai’s AED30bn Tasreef programme and will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. 

    The overall programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20977734/main.jpg
    Mark Dowdall
  • Contractors bid for QatarEnergy’s North Field West topsides

    28 October 2026

     

    QatarEnergy has received technical bids from contractors for a key tender covering the engineering, procurement, construction and installation (EPCI) of large platforms for the North Field gas field in Qatari waters.

    Contractors submitted their technical bids by the 26 October deadline, according to sources.

    Commercial bids are currently due on 10 November.

    The following contractors, among others, are understood to be bidding for the North Field West (NFW) production deck modules (PDMs) tender:

    • China Offshore Oil Engineering Company (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem (Italy)

    The core scope comprises the EPCI of four PDMs and associated structures. The modules will increase gas production from North Field reservoirs and supply additional gas feedstock to the NFW liquefied natural gas (LNG) development.

    Issued earlier this year, the tender forms part of the wider NFW project, the third and final phase of QatarEnergy’s North Field LNG expansion programme.

    The technical-bid deadline has been extended several times, from 30 August to 15 September, 28 September, 12 October and 19 October. Commercial bids were previously due on 25 October, as MEED reported.

    Before issuing the PDMs tender, QatarEnergy awarded US firm McDermott an EPCI contract for four offshore jackets to support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.

    North Field LNG expansion

    QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three projects are progressing.

    QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.

    QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.

    In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.

    Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.

    QatarEnergy took the final investment decision on NFW earlier this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting in February.

    Chiyoda carried out the front-end engineering and design work for the NFW LNG project.

    The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.

    In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and liquefied petroleum gas.

    With all three phases under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers in the long term.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20973187/main.jpg
    Indrajit Sen
  • US military approaches contractors for Qatar air base project

    28 October 2026

     

    The US Army Corps of Engineers (USACE) has begun market engagement for an anticipated contract to design and build a Space Campus at Al-Udeid Air Base in Qatar.

    USACE’s Southwestern Division, Middle East District, has issued a sources-sought notice to identify contractors capable of delivering an integrated design-and-construction (IDaC) contract.

    The successful contractor will provide pre-construction services and build secure facilities that comply with Intelligence Community Directive 705 (ICD 705) standards.

    Interested firms must submit capability statements by 30 October.

    The construction market engagement follows USACE’s procurement of architect-engineer services for the development. The authority intends to award a single-award, task-order contract covering planning, design, site investigations and construction-phase support. The contract will have a five-year base period, with a two-year option, and a capacity of up to $100m.

    USACE expects to award the design contract in April 2028, alongside an IDaC construction contract following completion of the planning activities.

    The Space Campus is being developed to meet an operational requirement of the US Air Force and forms part of the Al-Udeid Air Base 2040 Strategic Master Plan.

    It will include a secure administrative headquarters, coalition operations centre, secure warehouse, conference centre, storage facilities, access-control and guardhouse complex, antenna yards, shelters and multiple unit buildings.

    The scope also includes secure perimeter fencing, intrusion-detection and closed-circuit television systems, roads, parking, site preparation, utility networks, substations, generators, chilled-water systems, fuelling facilities, and secure and unclassified communications networks.

    The project will require hardened and potentially underground structures. Contractors are expected to demonstrate expertise in managing saline groundwater, dewatering, underground waterproofing and Qatar’s geotechnical conditions.

    The latest procurement activity comes as Qatar’s Public Works Authority, Ashghal, tenders a contract for roads and associated infrastructure serving Al-Udeid Air Base.

    The project in Zone 95 of Al-Wakra Municipality includes a dual-lane carriageway, three roundabouts, electrical substations, drainage, lighting, intelligent transport systems and utility works.

    The road will link Al-Majd Road to the east with Street 203 in Zone 95 to the west.

    According to GlobalData’s Qatar Defence Market 2026-2031 report, Qatar allocated an estimated $17bn to defence in 2026, representing a compound annual growth rate (CAGR) of 2.5% between 2022 and 2026.

    The defence budget is projected to grow at a CAGR of 3.8% over the 2027-31 forecast period, reaching an estimated $20.8bn in 2031.

    Defence diplomacy is also a key factor in military procurement, with Doha strengthening bilateral ties through acquisitions from the US, France and Turkiye.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20971169/main.jpg
    Yasir Iqbal