Water sector braces for likely slowdown

27 December 2024

 

Geopolitical tensions, climate change and higher-than-average population growth have exacerbated the water demand and supply gap across the Middle East and North Africa (Mena) region, home to some of the world’s most water-stressed countries.

For example, Jordan, where available water per capita is equivalent to only 12% of the absolute water scarcity level, hosts over 700,000 refugees fleeing wars and conflicts in neighbouring countries.

Most regional governments have developed and started to implement water strategies aimed at narrowing this gap. Subsidies are being phased out, environmental campaigns are being developed and digital solutions are being deployed in order to manage demand and improve efficiency.

Expanding desalination and treatment capacity, increasing treated sewage effluent (TSE) reuse, boosting reservoir capacity and building more efficient transmission and distribution networks are key levers used to improve supply.

Strong spending 

These efforts have prompted significant capital spending on more energy-efficient water production, distribution and storage facilities, typically in partnership with private investors, particularly among the more affluent states.

According to data from regional projects tracker MEED Projects, the Mena region awarded $17bn of project contracts across the water desalination, treatment, transmission and distribution, storage and district cooling subsectors in the first nine months of 2024.

This figure represents about 72% of the contracts awarded in 2023 and is slightly above the average value of annual contract awards in the preceding five years.

With only a few more packages expected to be awarded before the end of the year, 2024 looks set to be one of the best years so far in terms of water project activity, even if it fails to match the record value of contracts awarded in 2023, which reached almost $24bn.

In 2024, Saudi gigaproject developer Neom set the pace in January by awarding a $4.7bn contract to build dams at the Trojena Mountain Resort in Tabuk to Italian contractor WeBuild. 

The contract covers the construction of three dams that will form a freshwater lake for the Trojena ski resort. The main dam will have a height of 145 metres and will be 475 metres long at its crest. It will be built using 2.7 million cubic metres of roller compact concrete.

While this project does not necessarily belong to the band of solutions that aim to narrow the water supply and demand gap, the overall development is part of Saudi Arabia’s drive to boost tourism and diversify its economy away from oil.

Meanwhile, 2024 also saw the award by UAE northern emirate utility Sharjah Electricity, Water & Gas Authority of the contract to develop its first independent water project (IWP), the 400,000 cubic-metres-a-day facility in Hamriyah, to Saudi utility developer Acwa Power, the contract’s sole bidder.

In May, Saudi Arabia’s National Water Company announced that it had completed the award of 10 contracts under the first phase of its privatisation programme. Each rehabilitate, operate and transfer contract involves the retrofitting or expansion of existing sewage treatment plants and associated network, and their long-term operation and management. The facilities are expected to deliver water at the TSE level for irrigation reuse.

On the greenfield sewage treatment front, Saudi Water Partnership Company (SWPC) awarded a $400m contract to develop the Al-Haer independent sewage treatment plant (ISTP) project to a team comprising the local Miahona Company and Belgium’s Besix. The facility is the largest and first to be tendered under the third round of the water offtaker’s ISTP procurement programme.

In September, Chennai-headquartered VA Tech Wabag confirmed it had won a $317m contract to build the Ras Al-Khair seawater reverse osmosis (SWRO) facility in Saudi Arabia using an engineering, procurement and construction (EPC) model. The project client is Saudi Water Authority (SWA), formerly Saline Water Conversion Corporation.

In Oman, Nama Water Services awarded two water distribution network packages, worth a combined $600m, catering to Al-Dhahirah Governorate.

Jordan also appointed a team comprising Paris-based Meridiam, Suez and Vinci Construction Grands Projets, along with Egypt’s Orascom Construction, for the contract to develop the Aqaba-Amman water conveyance and desalination scheme. It is the country’s largest infrastructure project to date and the first phase is valued at an estimated $2bn-$3bn.

The project is crucial to addressing Jordan’s severe water shortage problem, piping desalinated water over 445 kilometres from the southern Red Sea coast to the country’s northern regions. The consortium is talking to lenders and aims to reach financial close for the project in 2025.

Slower momentum

Despite 2024 being a good year for contract awards, it fell short of the expectation built over the past few years, when the region’s largest economies began to execute their long-term water strategies.

For example, in Saudi Arabia, the years-long restructuring of the domestic water sector took a significant turn in 2024, with Water Transmission Company (WTCO), the kingdom’s licensed desalinated water transmission operator, gaining a broader portfolio of projects. As a result, the mandate to procure upcoming water transmission pipelines has been transferred to WTCO from SWPC.

The slower pace of IWP contract awards in Saudi Arabia was somewhat offset by a slew of tenders from SWA. The authority received bids for the EPC contracts to build four SWRO facilities in 2024, although as of November it had only managed to award one.

Earlier in 2024, Saudi gigaproject developer Neom also shelved a project to develop a zero-liquid discharge (ZLD) SWRO plant.

“The year may not have been as strong as 2023, but it is still a good year,” says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting. “Some projects have been delayed or cancelled – for instance a few in Saudi Arabia – but all in all [2024 has been] a good year for the water business.”

Bryniak adds that Neom’s ZLD scheme is one of the year’s shelved projects that he would like to see revived in the future.

Beyond the GCC states, Morocco and Egypt are endeavouring to move their planned SWRO projects into the tendering phase.

In Morocco, Office National de L’Electricite et de L’Eue Potable (Onee) extended the review of its second IWP in Nador while waiting for its first IWP in Casablanca to reach financial close.

The first batch of renewable energy- powered desalination plants in Egypt has yet to reach the proposals stage despite the Sovereign Fund of Egypt having completed the bid prequalification process in 2023.

Potential contract awards

According to data from MEED Projects, an estimated $34bn-worth of water projects are in the tendering stage across the Mena region. A further $40bn-worth is in the prequalification stage and $57bn is in the design and study phases.

The $22bn Dubai Strategic Sewerage Tunnels (DSST) scheme stands out among the upcoming projects due to its scale, as well as for the chosen procurement approach.

The project aims to convert Dubai’s existing sewerage network from a pumped system to a gravity system by decommissioning the existing pump stations and providing a sustainable and reliable service that is fit for the future.

In April, Dubai Municipality launched the procurement process for the DSST project, which is to be developed as a public-private partnership (PPP).

While a dose of pessimism persists over the chosen PPP model – in part due to the project’s scale and strong civil works orientation, and Dubai’s dismal track record in procuring PPP schemes outside the utility sector – the project has managed to attract strong interest from EPC contractors, as well as from potential investors and sponsors.

Some of those that have sought to prequalify as investors, such as Begium’s Besix, Beijing-headquartered China Railway Construction Corporation and South Korea’s Samsung C&T, have previously been prequalified as EPC contractors for the DSST project, which suggests that the preferred approach of prequalifying EPCs ahead of investors could offer advantages.

In Saudi Arabia, WTCO, SWA, SWPC and Neom’s utility subsidiary Enowa are each expected to let several contracts in 2025, while Bahrain and Abu Dhabi could award one IWP contract each.  

However, a robust overall pipeline does not necessarily guarantee that 2025 will resemble the upward trajectory that the sector has seen in the past two years.

“This year could be a turning point for the water industry throughout Mena,” says Bryniak, alluding to the possibility that, come January, the foreign and climate policies of the new occupant of the White House could affect the trend of water production capacity buildout in the Mena region.

Bryniak says that if US President-elect Donald Trump follows through with his promises, then we may be in store for, among other events, lower energy prices as the US drills more oil; a dampening of world trade as the US places tariffs on imports, especially on Chinese goods and services; less focus on the environment; and, generally, a more isolationist America.

“In my view, much depends on how much oil prices fall,” he continues. 

“A significant drop in oil prices could result in cut-backs in a lot of development projects, and this, in turn, will adversely impact water demand and the overall build programme.”  

However, the impact will not be uniform across asset types and procurement models, Bryniak notes. He expects water PPP projects to continue to grow, especially if capital availability is reduced by lower oil prices, as this is one way to preserve capital for use in other areas. 

“I do not see any reason for tariffs to fall further in 2025. Tariffs, in my view, will remain roughly where they are now or increase slightly,” adds Bryniak.  

However, the executive says that EPC contracts will likely have “a higher opportunity cost”, so there might be a reduced focus on this type of procurement model.  

He concludes: “To the extent that development projects get trimmed down due to less capital being available as a result of significantly lower oil prices, then water procurers and other developers will likely scale back their projects.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13146291/main.gif
Jennifer Aguinaldo
Related Articles
  • Oman’s Barka 5 IWP solar plant begins full operations

    1 May 2026

    Spain’s GS Inima has begun permanent operations at the solar photovoltaic (PV) plant serving the Barka 5 independent water project (IWP) in Oman.

    The solar facility is the third of its kind in Oman to power a large-scale desalination facility through a self-supply model.

    In a statement, GS Inima said it will provide up to 50% of the desalination plant’s electricity needs during daytime operations, improving efficiency and reducing reliance on external power sources.

    The PV plant has an installed capacity of 6.5MWp. It is designed to optimise energy consumption at the adjacent reverse osmosis desalination facility.

    The project was developed by GS Inima in collaboration with local firm Nafath Renewable Energy as the engineering, procurement and construction (EPC) contractor. China-based OCA Global provided owner’s engineering services.

    The Barka 5 IWP has a desalination capacity of approximately 100,000 cubic metres a day.

    GS Inima won the contract to develop the Barka 5 IWP project in November 2020. As previously reported, financial close was reached in 2022, and construction of the facility was completed in 2024.  

    The self-supply solar PV plant is equipped with 10,504 bifacial modules supplied by China’s Jinko Solar. These are mounted on fixed structures provided by Mibet Energy.

    Power is managed through 18 Sungrow inverters with a total capacity of 320kWac each, while electricity is fed into the desalination plant through an 11kV connection.

    The integration of solar power supports the efficiency of the Barka 5 facility, which has an energy consumption rate of 2.7kWh per cubic metre. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16645971/main.jpg
    Mark Dowdall
  • Qiddiya receives high-speed rail PPP prequalifications

    1 May 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Royal Commission for Riyadh City, in collaboration with Qiddiya Investment Company (QIC) and the National Centre for Privatisation & PPP, received prequalification statements from firms on 30 April for the public-private partnership (PPP) package of the Qiddiya high-speed rail project in Riyadh.

    This follows the submission of prequalification statements for the engineering, procurement, construction and financing (EPCF) package on 16 April, as reported by MEED.

    The prequalification notice was issued on 19 January, and a project briefing session was held on 23 February at Qiddiya Entertainment City.

    The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at speeds of up to 250 kilometres an hour, reaching Qiddiya in 30 minutes.

    The line is expected to be developed in two phases. The first phase will connect Qiddiya with KAFD and King Khalid International airport.

    The second phase will start from a development known as the North Pole and travel to the New Murabba development, King Salman Park, central Riyadh and Industrial City in the south of the city.

    In November last year, MEED reported that more than 145 local and international companies had expressed interest in developing the project, including 68 contracting companies, 23 design and project management consultants, 16 investment firms, 12 rail operators, 10 rolling stock providers and 16 other services firms.

    In November 2023, MEED reported that French consultant Egis had been appointed as the technical adviser for the project. UK-based consultancy Ernst & Young is acting as the transaction adviser, and Ashurst is the legal adviser.

    Qiddiya is one of Saudi Arabia’s five official gigaprojects and covers a total area of 376 square kilometres (sq km), with 223 sq km of developed land. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16641057/main.gif
    Yasir Iqbal
  • Bid deadline extensions hint at tighter project market

    1 May 2026

    Commentary
    Mark Dowdall
    Power & water editor

    There has been a steady run of bid deadline extensions across major power and water projects in recent weeks.

    The latest is the Al-Dibdibah and Al-Shagaya solar independent power producer (IPP) plant in Kuwait, where the submission date has been moved again to 31 May, following an earlier shift from February to the end of April. Similarly, bidding for the first phase of the Al-Khairan IWPP has also been extended.

    In Bahrain, bidding for the 1.2GW Sitra IWPP has been pushed back by another month to 17 May, having already been under main contract tender since last August.

    Meanwhile, in Dubai, contractors have been given additional time to submit bids for both the Jebel Ali sewage treatment plant expansion and a dams rehabilitation project in Hatta.

    Individually, these shifts are not unusual, and extensions are a routine part of the procurement cycle, especially with large, capital-intensive schemes.

    However, amid regional tensions and increasingly complex risk profiles, stakeholders are having to weigh up how much they can absorb, whether that is performance guarantees, financing exposure or delivery risk.

    For contractors and developers, this could mean looking more closely at supply chains, insurance costs and the potential for disruption. Lenders, too, are likely taking a more measured view on long-term exposure.

    This caution can show up in the bid process. More internal approvals, more conservative pricing, and in some cases, perhaps a hesitation to commit altogether.

    At the same time, strong pipelines across the GCC mean contractors are not short of work. Firms can afford to be selective, focusing on projects where risk and return are better aligned.

    Clients, in turn, face a choice. Push ahead with more limited competition or extend and try to draw in stronger participation. Most appear to be opting for the latter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16640998/main.jpg
    Mark Dowdall
  • Saudi Arabia launches $2bn Jawharat Al-Arous project

    1 May 2026

    Saudi Arabia has launched Jawharat Al-Arous, an SR8bn ($2bn) private-sector-led residential development in north Jeddah.

    The scheme covers 107 million square metres and comprises 18 residential neighbourhoods planned to accommodate more than 700,000 residents. It will provide more than 80,000 residential and commercial plots.

    The masterplan also includes 41 government-backed infrastructure and service zones to support large-scale urban expansion.

    The project was unveiled by Mecca Region Governor Khalid Al-Faisal and will be overseen by Saud Bin Mishaal Bin Abdulaziz.

    According to a recent report by real estate firm Cavendish Maxwell, Jeddah’s residential stock stood at about 1.09 million units at the end of 2025, following the completion of around 4,000 units that year.

    An expanding pipeline of about 18,000 units in 2026 and 22,000 units in 2027 is expected to bring total stock to around 1.14 million units by 2027, gradually adding supply without destabilising market equilibrium.

    GlobalData expects the Saudi construction industry to grow by 3.6% in real terms in 2026, supported by increased foreign direct investment (FDI) and investment in the housing and manufacturing sectors.

    The residential construction sector is forecast to grow by 3.8% in real terms in 2026 and to record an average annual growth rate of 4.7% between 2027 and 2030, supported by Saudi Vision 2030’s goal of increasing homeownership from 65.4% in 2024 to 70% by 2030, including through the delivery of 600,000 homes by 2030.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16640863/main.png
    Yasir Iqbal
  • Damage to US bases in region expected to cost more than $15bn

    1 May 2026

    The $25bn estimate a Pentagon official gave US lawmakers on 29 April did not include the cost of repairing damage to US bases in the Middle East, and the real cost of the war is likely to be between $40bn and $50bn, according to CNN.

    That would put the cost of repairing bases and replacing destroyed assets at between $15bn and $25bn.

    Jules Hurst III, the Pentagon official serving as the agency’s comptroller, told the House Armed Services Committee that “most” of the $25bn he cited had been spent on munitions. Defence Secretary Pete Hegseth declined to say whether the figure included repairs to damaged US bases.

    Iranian strikes across the Gulf in the early days of the war significantly damaged at least nine US military sites in 48 hours, hitting facilities in Bahrain, Kuwait, Iraq, the UAE and Qatar.

    Six US servicemembers were killed in an attack on a command post in Kuwait, and 20 more were injured.

    Three sources told CNN that the figure provided to the House Armed Services Committee did not include the cost of rebuilding US military installations and replacing destroyed assets.

    One source said the true cost would likely be between $40bn and $50bn.

    US contractors such as KBR and Fluor, as well as local firms, are likely to be among the leading contenders for contracts to repair and rebuild US bases in the region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16638663/main.gif
    Wil Crisp