Water sector braces for likely slowdown

27 December 2024

 

Geopolitical tensions, climate change and higher-than-average population growth have exacerbated the water demand and supply gap across the Middle East and North Africa (Mena) region, home to some of the world’s most water-stressed countries.

For example, Jordan, where available water per capita is equivalent to only 12% of the absolute water scarcity level, hosts over 700,000 refugees fleeing wars and conflicts in neighbouring countries.

Most regional governments have developed and started to implement water strategies aimed at narrowing this gap. Subsidies are being phased out, environmental campaigns are being developed and digital solutions are being deployed in order to manage demand and improve efficiency.

Expanding desalination and treatment capacity, increasing treated sewage effluent (TSE) reuse, boosting reservoir capacity and building more efficient transmission and distribution networks are key levers used to improve supply.

Strong spending 

These efforts have prompted significant capital spending on more energy-efficient water production, distribution and storage facilities, typically in partnership with private investors, particularly among the more affluent states.

According to data from regional projects tracker MEED Projects, the Mena region awarded $17bn of project contracts across the water desalination, treatment, transmission and distribution, storage and district cooling subsectors in the first nine months of 2024.

This figure represents about 72% of the contracts awarded in 2023 and is slightly above the average value of annual contract awards in the preceding five years.

With only a few more packages expected to be awarded before the end of the year, 2024 looks set to be one of the best years so far in terms of water project activity, even if it fails to match the record value of contracts awarded in 2023, which reached almost $24bn.

In 2024, Saudi gigaproject developer Neom set the pace in January by awarding a $4.7bn contract to build dams at the Trojena Mountain Resort in Tabuk to Italian contractor WeBuild. 

The contract covers the construction of three dams that will form a freshwater lake for the Trojena ski resort. The main dam will have a height of 145 metres and will be 475 metres long at its crest. It will be built using 2.7 million cubic metres of roller compact concrete.

While this project does not necessarily belong to the band of solutions that aim to narrow the water supply and demand gap, the overall development is part of Saudi Arabia’s drive to boost tourism and diversify its economy away from oil.

Meanwhile, 2024 also saw the award by UAE northern emirate utility Sharjah Electricity, Water & Gas Authority of the contract to develop its first independent water project (IWP), the 400,000 cubic-metres-a-day facility in Hamriyah, to Saudi utility developer Acwa Power, the contract’s sole bidder.

In May, Saudi Arabia’s National Water Company announced that it had completed the award of 10 contracts under the first phase of its privatisation programme. Each rehabilitate, operate and transfer contract involves the retrofitting or expansion of existing sewage treatment plants and associated network, and their long-term operation and management. The facilities are expected to deliver water at the TSE level for irrigation reuse.

On the greenfield sewage treatment front, Saudi Water Partnership Company (SWPC) awarded a $400m contract to develop the Al-Haer independent sewage treatment plant (ISTP) project to a team comprising the local Miahona Company and Belgium’s Besix. The facility is the largest and first to be tendered under the third round of the water offtaker’s ISTP procurement programme.

In September, Chennai-headquartered VA Tech Wabag confirmed it had won a $317m contract to build the Ras Al-Khair seawater reverse osmosis (SWRO) facility in Saudi Arabia using an engineering, procurement and construction (EPC) model. The project client is Saudi Water Authority (SWA), formerly Saline Water Conversion Corporation.

In Oman, Nama Water Services awarded two water distribution network packages, worth a combined $600m, catering to Al-Dhahirah Governorate.

Jordan also appointed a team comprising Paris-based Meridiam, Suez and Vinci Construction Grands Projets, along with Egypt’s Orascom Construction, for the contract to develop the Aqaba-Amman water conveyance and desalination scheme. It is the country’s largest infrastructure project to date and the first phase is valued at an estimated $2bn-$3bn.

The project is crucial to addressing Jordan’s severe water shortage problem, piping desalinated water over 445 kilometres from the southern Red Sea coast to the country’s northern regions. The consortium is talking to lenders and aims to reach financial close for the project in 2025.

Slower momentum

Despite 2024 being a good year for contract awards, it fell short of the expectation built over the past few years, when the region’s largest economies began to execute their long-term water strategies.

For example, in Saudi Arabia, the years-long restructuring of the domestic water sector took a significant turn in 2024, with Water Transmission Company (WTCO), the kingdom’s licensed desalinated water transmission operator, gaining a broader portfolio of projects. As a result, the mandate to procure upcoming water transmission pipelines has been transferred to WTCO from SWPC.

The slower pace of IWP contract awards in Saudi Arabia was somewhat offset by a slew of tenders from SWA. The authority received bids for the EPC contracts to build four SWRO facilities in 2024, although as of November it had only managed to award one.

Earlier in 2024, Saudi gigaproject developer Neom also shelved a project to develop a zero-liquid discharge (ZLD) SWRO plant.

“The year may not have been as strong as 2023, but it is still a good year,” says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting. “Some projects have been delayed or cancelled – for instance a few in Saudi Arabia – but all in all [2024 has been] a good year for the water business.”

Bryniak adds that Neom’s ZLD scheme is one of the year’s shelved projects that he would like to see revived in the future.

Beyond the GCC states, Morocco and Egypt are endeavouring to move their planned SWRO projects into the tendering phase.

In Morocco, Office National de L’Electricite et de L’Eue Potable (Onee) extended the review of its second IWP in Nador while waiting for its first IWP in Casablanca to reach financial close.

The first batch of renewable energy- powered desalination plants in Egypt has yet to reach the proposals stage despite the Sovereign Fund of Egypt having completed the bid prequalification process in 2023.

Potential contract awards

According to data from MEED Projects, an estimated $34bn-worth of water projects are in the tendering stage across the Mena region. A further $40bn-worth is in the prequalification stage and $57bn is in the design and study phases.

The $22bn Dubai Strategic Sewerage Tunnels (DSST) scheme stands out among the upcoming projects due to its scale, as well as for the chosen procurement approach.

The project aims to convert Dubai’s existing sewerage network from a pumped system to a gravity system by decommissioning the existing pump stations and providing a sustainable and reliable service that is fit for the future.

In April, Dubai Municipality launched the procurement process for the DSST project, which is to be developed as a public-private partnership (PPP).

While a dose of pessimism persists over the chosen PPP model – in part due to the project’s scale and strong civil works orientation, and Dubai’s dismal track record in procuring PPP schemes outside the utility sector – the project has managed to attract strong interest from EPC contractors, as well as from potential investors and sponsors.

Some of those that have sought to prequalify as investors, such as Begium’s Besix, Beijing-headquartered China Railway Construction Corporation and South Korea’s Samsung C&T, have previously been prequalified as EPC contractors for the DSST project, which suggests that the preferred approach of prequalifying EPCs ahead of investors could offer advantages.

In Saudi Arabia, WTCO, SWA, SWPC and Neom’s utility subsidiary Enowa are each expected to let several contracts in 2025, while Bahrain and Abu Dhabi could award one IWP contract each.  

However, a robust overall pipeline does not necessarily guarantee that 2025 will resemble the upward trajectory that the sector has seen in the past two years.

“This year could be a turning point for the water industry throughout Mena,” says Bryniak, alluding to the possibility that, come January, the foreign and climate policies of the new occupant of the White House could affect the trend of water production capacity buildout in the Mena region.

Bryniak says that if US President-elect Donald Trump follows through with his promises, then we may be in store for, among other events, lower energy prices as the US drills more oil; a dampening of world trade as the US places tariffs on imports, especially on Chinese goods and services; less focus on the environment; and, generally, a more isolationist America.

“In my view, much depends on how much oil prices fall,” he continues. 

“A significant drop in oil prices could result in cut-backs in a lot of development projects, and this, in turn, will adversely impact water demand and the overall build programme.”  

However, the impact will not be uniform across asset types and procurement models, Bryniak notes. He expects water PPP projects to continue to grow, especially if capital availability is reduced by lower oil prices, as this is one way to preserve capital for use in other areas. 

“I do not see any reason for tariffs to fall further in 2025. Tariffs, in my view, will remain roughly where they are now or increase slightly,” adds Bryniak.  

However, the executive says that EPC contracts will likely have “a higher opportunity cost”, so there might be a reduced focus on this type of procurement model.  

He concludes: “To the extent that development projects get trimmed down due to less capital being available as a result of significantly lower oil prices, then water procurers and other developers will likely scale back their projects.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13146291/main.gif
Jennifer Aguinaldo
Related Articles
  • Bidders get more time for Jebel Ali sewage EPC contract

    29 April 2026

     

    Dubai Municipality has extended the deadline for contractors to submit bids for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.

    Contractors now have until June to submit offers, a source told MEED. Bidding had been expected to close on 30 April.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d), with the expansion estimated to cost $300m.

    The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.

    Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.

    The main element of the expansion involves modifications to the secondary treatment process at Jebel Ali STP phase two.

    UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.

    Future expansion

    It is understood that the project is part of long-term plans to treat about 1.05 million cm/d once all future phases are completed.

    According to sources, this includes a Jebel Ali-based build-operate-transfer (BOT) project to be developed under a public-private partnership (PPP) model.

    It is understood that the prequalification process for this will begin in the coming months.

    In February, MEED exclusively revealed that the municipality is preparing to tender the main construction package for the Warsan STP by the end of the year.

    As MEED understands, the Warsan STP had previously been planned as a PPP project.

    The main package will now be procured as an engineering, procurement and construction contract, a source said.

    The project involves the construction of a sewage treatment plant with a capacity of about 175,000 cm/d, including treatment units, sludge handling systems and associated infrastructure.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16608027/main.jpg
    Mark Dowdall
  • UAE’s departure from Opec marks a tectonic shift

    29 April 2026

    Commentary
    Indrajit Sen
    Oil & gas editor

    Register for MEED’s 14-day trial access 

    The UAE’s decision to leave Opec and the Opec+ grouping marks a significant turning point in global oil markets and highlights shifting geopolitical dynamics and evolving supply expectations.

    The UAE announced it will leave the producer alliance effective 1 May, ending nearly six decades of membership. The move reflects a broader strategic shift, as the country seeks greater flexibility over its production policy amid rising capacity and changing market conditions.

    For oil markets, this is about more than one country wanting to pump more oil. Abu Dhabi National Oil Company (Adnoc) has spent billions of dollars over the years to raise crude production capacity to 5 million barrels a day.

    Opec+ quotas had increasingly looked as though they were stifling Abu Dhabi’s growing desire to maximise revenues by tapping into its expanded spare capacity. Leaving the Opec+ coalition gives Abu Dhabi more room to monetise those investments.

    The timing also matters. It comes against a backdrop of regional security concerns, tensions around Iran and the Strait of Hormuz, and a sense that consumers are once again being squeezed by high energy costs and depleted strategic reserves. 

    The immediate dip in the price of global benchmark Brent crude following the announcement of the UAE’s decision on 28 April showed the market’s first instinct: more UAE barrels could mean more supply and lower prices. However, the price rebound on 29 April, with Brent trading around $111 a barrel, also tells the other half of the story: extra capacity does not instantly become risk-free supply when regional bottlenecks and security threats remain front and centre.

    For Opec+, this is a blow to unity and to Saudi Arabia’s ability to marshal producer discipline. It does not mean that a price war will start tomorrow, but it raises the risk of other member states choosing to abandon the alliance’s cooperation mechanism and pursue a higher market share. In trading terms, this adds a new volatility premium: more potential supply, less cartel discipline and a Gulf energy landscape that looks significantly less predictable.

    The announcement comes at a time of heightened uncertainty in global energy markets, with geopolitical tensions, supply chain constraints and demand recovery trends all contributing to price volatility. The UAE’s exit is expected to reshape market expectations around supply flexibility and producer coordination.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16608006/main.gif
    Indrajit Sen
  • Kuwait Oil Company prepares to sign flowline contract

    29 April 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) is preparing to sign a contract worth KD174.2m ($565m) with Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco), according to industry sources.

    The contract is focused on developing flowlines and associated works in North Kuwait.

    One source said: “The contract is expected to be signed soon and everything associated with the contract award process is moving very smoothly.”

    Heisco announced in a stock exchange statement earlier this month that it had received a formal contract award letter for the project.

    While progress on the project is moving smoothly for now, the project may be impacted by fallout from the US and Israel’s war with Iran in the future.

    The project requires a large volume of pipelines to be transported into Kuwait, which would normally be shipped through the Strait of Hormuz.

    Heisco was the fourth-lowest bidder for the contract.

    Also this month, Heisco submitted the lowest bid for a project to upgrade part of the Mina Abdullah refinery’s export infrastructure.

    It submitted a bid of KD11,919,652 ($38.6m) for the project to implement renovation works on the artificial island that forms part of the port at the refinery.

    The only other bidder was Kuwait’s International Marine Construction Company (IMCC), which submitted a bid of KD12,480,113 ($40.4m).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16599814/main.png
    Wil Crisp
  • Algerian-Indian team makes oil and gas discovery in Libya

    29 April 2026

    A consortium of state-owned companies from India and Algeria has made an oil and gas discovery in Libya’s Ghadames basin.

    The consortium comprises Algeria’s Sonatrach International Petroleum Exploration & Production (Sipex), Oil India and Indian Oil Corporation.

    The discovery was made in the Area 95/96 block, which is located near Libya’s border with Algeria.

    In a statement, India’s Ministry of Petroleum & Natural Gas said that the well was completed to a final depth of 8,440 feet and achieved production of 13 million cubic feet of gas a day and 327 barrels of condensate a day during testing.

    The hydrocarbons were extracted from the Awynat Wanin and Awyn Kaza formations.

    The ministry added: “The discovery reflects the growing global footprints of Indian energy companies, importance of strategic international alliances, and our commitment to strengthening national energy security through overseas assets acquisition by national oil companies.”

    The consortium won the exploration and production rights for the block, which covers an area of nearly 7,000 square kilometres, during Libya’s fourth oil and gas licensing round in December 2007.

    Stakeholders are expecting a surge in oil and gas project activity in Libya after the country’s rival legislative bodies recently approved a unified state budget for the first time in more than 13 years.

    The Central Bank of Libya confirmed on 11 April that both chambers had endorsed the budget, saying that it was a key step towards restoring financial stability after prolonged division.

    The budget is valued at LD190bn ($29.95bn), and LD12bn ($1.9bn) has been allocated to the NOC.

    An additional LD40bn ($6.3bn) has been allocated for “development projects”.

    Libya has stated that a joint committee has been formed to help prioritise development projects, and the projects have been listed in the budget.

    The development comes at a time when Libya’s oil and gas sector could be positioned to make windfall revenues as oil and gas prices remain high due to fallout from the US and Israel’s war with Iran.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16599813/main.png
    Wil Crisp
  • UAE and Saudi firms plan data centre projects in Saudi Arabia

    29 April 2026

    Register for MEED’s 14-day trial access 

    UAE-based firm Taranis Capital has signed a memorandum of understanding agreement with Saudi Arabia’s Emaar Executive Company to build several data centre facilities in the kingdom.

    According to a statement, the firms plan to develop, construct and operate a portfolio of data centre facilities, each with a capacity of 40-50MW.

    Emaar Executive Company will provide engineering, procurement and construction (EPC) capabilities, alongside its design and operations expertise.

    Saudi Arabia and the UAE are leading the market expansion of data centres through hyperscale campuses, sovereign cloud initiatives and edge data centre deployments.

    Data centres have become foundational infrastructure across the region, underpinning national digital economies and enabling cloud computing, artificial intelligence (AI) workloads, smart cities, e-government platforms, fintech and cybersecurity resilience.

    Governments and enterprises are accelerating investment as data localisation requirements and power-intensive AI applications drive sustained demand for capacity.

    Data centre development is closely aligned with national strategies such as Saudi Arabia’s Vision 2030, the UAE’s digital economy and AI roadmaps, and wider smart city programmes across the GCC.

    These agendas are translating into long-term demand for high-capacity, energy-efficient and resilient data centre infrastructure. 

    Priorities include hyperscale and colocation facilities to support cloud service providers; edge data centres to reduce latency and enable 5G and IoT use cases; energy-efficient designs using advanced cooling, modular construction and renewables; and strategic partnerships between global hyperscalers, local developers and utilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16595179/main.jpg
    Yasir Iqbal