Water sector braces for likely slowdown

27 December 2024

 

Geopolitical tensions, climate change and higher-than-average population growth have exacerbated the water demand and supply gap across the Middle East and North Africa (Mena) region, home to some of the world’s most water-stressed countries.

For example, Jordan, where available water per capita is equivalent to only 12% of the absolute water scarcity level, hosts over 700,000 refugees fleeing wars and conflicts in neighbouring countries.

Most regional governments have developed and started to implement water strategies aimed at narrowing this gap. Subsidies are being phased out, environmental campaigns are being developed and digital solutions are being deployed in order to manage demand and improve efficiency.

Expanding desalination and treatment capacity, increasing treated sewage effluent (TSE) reuse, boosting reservoir capacity and building more efficient transmission and distribution networks are key levers used to improve supply.

Strong spending 

These efforts have prompted significant capital spending on more energy-efficient water production, distribution and storage facilities, typically in partnership with private investors, particularly among the more affluent states.

According to data from regional projects tracker MEED Projects, the Mena region awarded $17bn of project contracts across the water desalination, treatment, transmission and distribution, storage and district cooling subsectors in the first nine months of 2024.

This figure represents about 72% of the contracts awarded in 2023 and is slightly above the average value of annual contract awards in the preceding five years.

With only a few more packages expected to be awarded before the end of the year, 2024 looks set to be one of the best years so far in terms of water project activity, even if it fails to match the record value of contracts awarded in 2023, which reached almost $24bn.

In 2024, Saudi gigaproject developer Neom set the pace in January by awarding a $4.7bn contract to build dams at the Trojena Mountain Resort in Tabuk to Italian contractor WeBuild. 

The contract covers the construction of three dams that will form a freshwater lake for the Trojena ski resort. The main dam will have a height of 145 metres and will be 475 metres long at its crest. It will be built using 2.7 million cubic metres of roller compact concrete.

While this project does not necessarily belong to the band of solutions that aim to narrow the water supply and demand gap, the overall development is part of Saudi Arabia’s drive to boost tourism and diversify its economy away from oil.

Meanwhile, 2024 also saw the award by UAE northern emirate utility Sharjah Electricity, Water & Gas Authority of the contract to develop its first independent water project (IWP), the 400,000 cubic-metres-a-day facility in Hamriyah, to Saudi utility developer Acwa Power, the contract’s sole bidder.

In May, Saudi Arabia’s National Water Company announced that it had completed the award of 10 contracts under the first phase of its privatisation programme. Each rehabilitate, operate and transfer contract involves the retrofitting or expansion of existing sewage treatment plants and associated network, and their long-term operation and management. The facilities are expected to deliver water at the TSE level for irrigation reuse.

On the greenfield sewage treatment front, Saudi Water Partnership Company (SWPC) awarded a $400m contract to develop the Al-Haer independent sewage treatment plant (ISTP) project to a team comprising the local Miahona Company and Belgium’s Besix. The facility is the largest and first to be tendered under the third round of the water offtaker’s ISTP procurement programme.

In September, Chennai-headquartered VA Tech Wabag confirmed it had won a $317m contract to build the Ras Al-Khair seawater reverse osmosis (SWRO) facility in Saudi Arabia using an engineering, procurement and construction (EPC) model. The project client is Saudi Water Authority (SWA), formerly Saline Water Conversion Corporation.

In Oman, Nama Water Services awarded two water distribution network packages, worth a combined $600m, catering to Al-Dhahirah Governorate.

Jordan also appointed a team comprising Paris-based Meridiam, Suez and Vinci Construction Grands Projets, along with Egypt’s Orascom Construction, for the contract to develop the Aqaba-Amman water conveyance and desalination scheme. It is the country’s largest infrastructure project to date and the first phase is valued at an estimated $2bn-$3bn.

The project is crucial to addressing Jordan’s severe water shortage problem, piping desalinated water over 445 kilometres from the southern Red Sea coast to the country’s northern regions. The consortium is talking to lenders and aims to reach financial close for the project in 2025.

Slower momentum

Despite 2024 being a good year for contract awards, it fell short of the expectation built over the past few years, when the region’s largest economies began to execute their long-term water strategies.

For example, in Saudi Arabia, the years-long restructuring of the domestic water sector took a significant turn in 2024, with Water Transmission Company (WTCO), the kingdom’s licensed desalinated water transmission operator, gaining a broader portfolio of projects. As a result, the mandate to procure upcoming water transmission pipelines has been transferred to WTCO from SWPC.

The slower pace of IWP contract awards in Saudi Arabia was somewhat offset by a slew of tenders from SWA. The authority received bids for the EPC contracts to build four SWRO facilities in 2024, although as of November it had only managed to award one.

Earlier in 2024, Saudi gigaproject developer Neom also shelved a project to develop a zero-liquid discharge (ZLD) SWRO plant.

“The year may not have been as strong as 2023, but it is still a good year,” says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting. “Some projects have been delayed or cancelled – for instance a few in Saudi Arabia – but all in all [2024 has been] a good year for the water business.”

Bryniak adds that Neom’s ZLD scheme is one of the year’s shelved projects that he would like to see revived in the future.

Beyond the GCC states, Morocco and Egypt are endeavouring to move their planned SWRO projects into the tendering phase.

In Morocco, Office National de L’Electricite et de L’Eue Potable (Onee) extended the review of its second IWP in Nador while waiting for its first IWP in Casablanca to reach financial close.

The first batch of renewable energy- powered desalination plants in Egypt has yet to reach the proposals stage despite the Sovereign Fund of Egypt having completed the bid prequalification process in 2023.

Potential contract awards

According to data from MEED Projects, an estimated $34bn-worth of water projects are in the tendering stage across the Mena region. A further $40bn-worth is in the prequalification stage and $57bn is in the design and study phases.

The $22bn Dubai Strategic Sewerage Tunnels (DSST) scheme stands out among the upcoming projects due to its scale, as well as for the chosen procurement approach.

The project aims to convert Dubai’s existing sewerage network from a pumped system to a gravity system by decommissioning the existing pump stations and providing a sustainable and reliable service that is fit for the future.

In April, Dubai Municipality launched the procurement process for the DSST project, which is to be developed as a public-private partnership (PPP).

While a dose of pessimism persists over the chosen PPP model – in part due to the project’s scale and strong civil works orientation, and Dubai’s dismal track record in procuring PPP schemes outside the utility sector – the project has managed to attract strong interest from EPC contractors, as well as from potential investors and sponsors.

Some of those that have sought to prequalify as investors, such as Begium’s Besix, Beijing-headquartered China Railway Construction Corporation and South Korea’s Samsung C&T, have previously been prequalified as EPC contractors for the DSST project, which suggests that the preferred approach of prequalifying EPCs ahead of investors could offer advantages.

In Saudi Arabia, WTCO, SWA, SWPC and Neom’s utility subsidiary Enowa are each expected to let several contracts in 2025, while Bahrain and Abu Dhabi could award one IWP contract each.  

However, a robust overall pipeline does not necessarily guarantee that 2025 will resemble the upward trajectory that the sector has seen in the past two years.

“This year could be a turning point for the water industry throughout Mena,” says Bryniak, alluding to the possibility that, come January, the foreign and climate policies of the new occupant of the White House could affect the trend of water production capacity buildout in the Mena region.

Bryniak says that if US President-elect Donald Trump follows through with his promises, then we may be in store for, among other events, lower energy prices as the US drills more oil; a dampening of world trade as the US places tariffs on imports, especially on Chinese goods and services; less focus on the environment; and, generally, a more isolationist America.

“In my view, much depends on how much oil prices fall,” he continues. 

“A significant drop in oil prices could result in cut-backs in a lot of development projects, and this, in turn, will adversely impact water demand and the overall build programme.”  

However, the impact will not be uniform across asset types and procurement models, Bryniak notes. He expects water PPP projects to continue to grow, especially if capital availability is reduced by lower oil prices, as this is one way to preserve capital for use in other areas. 

“I do not see any reason for tariffs to fall further in 2025. Tariffs, in my view, will remain roughly where they are now or increase slightly,” adds Bryniak.  

However, the executive says that EPC contracts will likely have “a higher opportunity cost”, so there might be a reduced focus on this type of procurement model.  

He concludes: “To the extent that development projects get trimmed down due to less capital being available as a result of significantly lower oil prices, then water procurers and other developers will likely scale back their projects.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13146291/main.gif
Jennifer Aguinaldo
Related Articles
  • Qiddiya plans $7bn theme park hub near Paris

    25 August 2026

    Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.

    The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.

    The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.

    One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.

    The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.

    Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.

    The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.

    It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png
    Colin Foreman
  • Masdar shelves Abu Dhabi green hydrogen project

    25 August 2026

     

    Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.

    After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.

    However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.

    Contractors that submitted bids for the Masdar green hydrogen project included:

    • Envision (China)
    • Larsen & Toubro (India)
    • PowerChina (China)
    • Samsung E&A (South Korea)
    • Sinopec (China)

    Masdar did not respond to MEED’s request for comment on the information.

    In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.

    Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.

    Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.

    Contractors submitted bids by the end of the year, according to sources.

    The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.

    The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.

    It also included tie-ins to pre-defined interface points, including (but not limited to):

    • a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
    • a water supply connection to a nearby Taqa Distribution network

    Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.

    Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.

    The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.

    This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.

    “Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg
    Indrajit Sen
  • Oman invites bids for Musandam renewables study

    25 August 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.

    The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.

    The consultant will be required to determine which technologies are technically and economically justified for the governorate.

    The bid submission deadline is 24 September.

    The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.

    Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.

    Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.

    The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity. 

    Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.

    The bid submissions deadline is 10 September.

    The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.

    Bidding for this tender closes on 26 August.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg
    Mark Dowdall
  • US launches sanctions campaign against Iran

    25 August 2026

    The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.

    The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.

    The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.

    The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.

    Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.

    Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.

    Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.

    Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.

    The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg
    Colin Foreman
  • Kuwait tenders $3.3bn gas processing facility

    25 August 2026

     

    State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.

    The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.

    The tender was issued on 23 August.

    The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    In February, MEED reported that at least seven companies had shown interest in participating in the tender.

    Contractors that sent representatives to previous meetings to discuss the project include:

    • Samsung E&A (South Korea)
    • Larsen & Toubro (India)
    • Tecnicas Reunidas (Spain)
    • Saipem (Italy)
    • Hyundai Engineering & Construction (South Korea)
    • Hyundai Engineering Company (South Korea)
    • JGC (Japan)

    The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.

    Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.

    It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.

    Iran disputes ownership of the field, referring to it as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.

    The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.

    Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.

    KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.

    US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.

    A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.

    Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.

    MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.

    Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png
    Wil Crisp