Water sector braces for likely slowdown

27 December 2024

 

Geopolitical tensions, climate change and higher-than-average population growth have exacerbated the water demand and supply gap across the Middle East and North Africa (Mena) region, home to some of the world’s most water-stressed countries.

For example, Jordan, where available water per capita is equivalent to only 12% of the absolute water scarcity level, hosts over 700,000 refugees fleeing wars and conflicts in neighbouring countries.

Most regional governments have developed and started to implement water strategies aimed at narrowing this gap. Subsidies are being phased out, environmental campaigns are being developed and digital solutions are being deployed in order to manage demand and improve efficiency.

Expanding desalination and treatment capacity, increasing treated sewage effluent (TSE) reuse, boosting reservoir capacity and building more efficient transmission and distribution networks are key levers used to improve supply.

Strong spending 

These efforts have prompted significant capital spending on more energy-efficient water production, distribution and storage facilities, typically in partnership with private investors, particularly among the more affluent states.

According to data from regional projects tracker MEED Projects, the Mena region awarded $17bn of project contracts across the water desalination, treatment, transmission and distribution, storage and district cooling subsectors in the first nine months of 2024.

This figure represents about 72% of the contracts awarded in 2023 and is slightly above the average value of annual contract awards in the preceding five years.

With only a few more packages expected to be awarded before the end of the year, 2024 looks set to be one of the best years so far in terms of water project activity, even if it fails to match the record value of contracts awarded in 2023, which reached almost $24bn.

In 2024, Saudi gigaproject developer Neom set the pace in January by awarding a $4.7bn contract to build dams at the Trojena Mountain Resort in Tabuk to Italian contractor WeBuild. 

The contract covers the construction of three dams that will form a freshwater lake for the Trojena ski resort. The main dam will have a height of 145 metres and will be 475 metres long at its crest. It will be built using 2.7 million cubic metres of roller compact concrete.

While this project does not necessarily belong to the band of solutions that aim to narrow the water supply and demand gap, the overall development is part of Saudi Arabia’s drive to boost tourism and diversify its economy away from oil.

Meanwhile, 2024 also saw the award by UAE northern emirate utility Sharjah Electricity, Water & Gas Authority of the contract to develop its first independent water project (IWP), the 400,000 cubic-metres-a-day facility in Hamriyah, to Saudi utility developer Acwa Power, the contract’s sole bidder.

In May, Saudi Arabia’s National Water Company announced that it had completed the award of 10 contracts under the first phase of its privatisation programme. Each rehabilitate, operate and transfer contract involves the retrofitting or expansion of existing sewage treatment plants and associated network, and their long-term operation and management. The facilities are expected to deliver water at the TSE level for irrigation reuse.

On the greenfield sewage treatment front, Saudi Water Partnership Company (SWPC) awarded a $400m contract to develop the Al-Haer independent sewage treatment plant (ISTP) project to a team comprising the local Miahona Company and Belgium’s Besix. The facility is the largest and first to be tendered under the third round of the water offtaker’s ISTP procurement programme.

In September, Chennai-headquartered VA Tech Wabag confirmed it had won a $317m contract to build the Ras Al-Khair seawater reverse osmosis (SWRO) facility in Saudi Arabia using an engineering, procurement and construction (EPC) model. The project client is Saudi Water Authority (SWA), formerly Saline Water Conversion Corporation.

In Oman, Nama Water Services awarded two water distribution network packages, worth a combined $600m, catering to Al-Dhahirah Governorate.

Jordan also appointed a team comprising Paris-based Meridiam, Suez and Vinci Construction Grands Projets, along with Egypt’s Orascom Construction, for the contract to develop the Aqaba-Amman water conveyance and desalination scheme. It is the country’s largest infrastructure project to date and the first phase is valued at an estimated $2bn-$3bn.

The project is crucial to addressing Jordan’s severe water shortage problem, piping desalinated water over 445 kilometres from the southern Red Sea coast to the country’s northern regions. The consortium is talking to lenders and aims to reach financial close for the project in 2025.

Slower momentum

Despite 2024 being a good year for contract awards, it fell short of the expectation built over the past few years, when the region’s largest economies began to execute their long-term water strategies.

For example, in Saudi Arabia, the years-long restructuring of the domestic water sector took a significant turn in 2024, with Water Transmission Company (WTCO), the kingdom’s licensed desalinated water transmission operator, gaining a broader portfolio of projects. As a result, the mandate to procure upcoming water transmission pipelines has been transferred to WTCO from SWPC.

The slower pace of IWP contract awards in Saudi Arabia was somewhat offset by a slew of tenders from SWA. The authority received bids for the EPC contracts to build four SWRO facilities in 2024, although as of November it had only managed to award one.

Earlier in 2024, Saudi gigaproject developer Neom also shelved a project to develop a zero-liquid discharge (ZLD) SWRO plant.

“The year may not have been as strong as 2023, but it is still a good year,” says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting. “Some projects have been delayed or cancelled – for instance a few in Saudi Arabia – but all in all [2024 has been] a good year for the water business.”

Bryniak adds that Neom’s ZLD scheme is one of the year’s shelved projects that he would like to see revived in the future.

Beyond the GCC states, Morocco and Egypt are endeavouring to move their planned SWRO projects into the tendering phase.

In Morocco, Office National de L’Electricite et de L’Eue Potable (Onee) extended the review of its second IWP in Nador while waiting for its first IWP in Casablanca to reach financial close.

The first batch of renewable energy- powered desalination plants in Egypt has yet to reach the proposals stage despite the Sovereign Fund of Egypt having completed the bid prequalification process in 2023.

Potential contract awards

According to data from MEED Projects, an estimated $34bn-worth of water projects are in the tendering stage across the Mena region. A further $40bn-worth is in the prequalification stage and $57bn is in the design and study phases.

The $22bn Dubai Strategic Sewerage Tunnels (DSST) scheme stands out among the upcoming projects due to its scale, as well as for the chosen procurement approach.

The project aims to convert Dubai’s existing sewerage network from a pumped system to a gravity system by decommissioning the existing pump stations and providing a sustainable and reliable service that is fit for the future.

In April, Dubai Municipality launched the procurement process for the DSST project, which is to be developed as a public-private partnership (PPP).

While a dose of pessimism persists over the chosen PPP model – in part due to the project’s scale and strong civil works orientation, and Dubai’s dismal track record in procuring PPP schemes outside the utility sector – the project has managed to attract strong interest from EPC contractors, as well as from potential investors and sponsors.

Some of those that have sought to prequalify as investors, such as Begium’s Besix, Beijing-headquartered China Railway Construction Corporation and South Korea’s Samsung C&T, have previously been prequalified as EPC contractors for the DSST project, which suggests that the preferred approach of prequalifying EPCs ahead of investors could offer advantages.

In Saudi Arabia, WTCO, SWA, SWPC and Neom’s utility subsidiary Enowa are each expected to let several contracts in 2025, while Bahrain and Abu Dhabi could award one IWP contract each.  

However, a robust overall pipeline does not necessarily guarantee that 2025 will resemble the upward trajectory that the sector has seen in the past two years.

“This year could be a turning point for the water industry throughout Mena,” says Bryniak, alluding to the possibility that, come January, the foreign and climate policies of the new occupant of the White House could affect the trend of water production capacity buildout in the Mena region.

Bryniak says that if US President-elect Donald Trump follows through with his promises, then we may be in store for, among other events, lower energy prices as the US drills more oil; a dampening of world trade as the US places tariffs on imports, especially on Chinese goods and services; less focus on the environment; and, generally, a more isolationist America.

“In my view, much depends on how much oil prices fall,” he continues. 

“A significant drop in oil prices could result in cut-backs in a lot of development projects, and this, in turn, will adversely impact water demand and the overall build programme.”  

However, the impact will not be uniform across asset types and procurement models, Bryniak notes. He expects water PPP projects to continue to grow, especially if capital availability is reduced by lower oil prices, as this is one way to preserve capital for use in other areas. 

“I do not see any reason for tariffs to fall further in 2025. Tariffs, in my view, will remain roughly where they are now or increase slightly,” adds Bryniak.  

However, the executive says that EPC contracts will likely have “a higher opportunity cost”, so there might be a reduced focus on this type of procurement model.  

He concludes: “To the extent that development projects get trimmed down due to less capital being available as a result of significantly lower oil prices, then water procurers and other developers will likely scale back their projects.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13146291/main.gif
Jennifer Aguinaldo
Related Articles
  • Qatar’s new $8bn investment spices up global LNG race

    13 March 2026

     

    In the midst of the conflict between Iran and the US and Israel, which has spilled over into the GCC region, QatarEnergy has temporarily halted production of liquefied natural gas (LNG) in the country and declared force majeure on LNG shipments after its energy assets came under attack.

    When the fog of war clears, however, and the Strait of Hormuz reopens to oil and gas flows, the global economy will look to QatarEnergy to swiftly restore regular LNG cargoes in order to bring gas prices down from record highs.

    Beyond that short-term role, the recent $8bn investment the Qatari giant has committed to building two new LNG processing trains will also cement its position as a reliable long-term supplier, while further intensifying the race among global LNG producers to carve out larger market shares in an increasingly gas-hungry world.

    North Field West – a game changer

    The state-owned company has progressed from the front-end engineering and design (feed) phase to the engineering, procurement and construction (EPC) stage of its North Field West LNG project at pace.

    It awarded the main EPC contract for the scheme – covering two LNG processing trains with a total capacity of 16 million tonnes a year (t/y) – to a joint venture comprising France’s Technip Energies, Greece/Lebanon-based Consolidated Contractors Company (CCC) and Gulf Asia Contracting on 25 February.

    The contract, estimated to be worth $8bn, was awarded just a month after Japan-based Chiyoda Corporation won the project’s feed contract.

    Such a short interval between the feed and EPC phases for a project as large as North Field West LNG would typically be considered improbable. Industry sources suggest QatarEnergy may have been in discussions with Chiyoda and the Technip Energies-CCC consortium for at least a year regarding the feed and EPC contracts, respectively – particularly given the two-year gap between the project’s announcement in February 2024 and the start of the EPC phase.

    Chiyoda, Technip Energies and CCC are also involved in the first two phases of QatarEnergy’s $40bn North Field LNG expansion project. A consortium of Chiyoda and Technip Energies is executing EPC works on the North Field East project, which involves the construction of four LNG trains with a combined capacity of 32 million t/y, following the award of a $13bn contract in February 2021. Meanwhile, a Technip Energies-CCC consortium is carrying out EPC works on two 7.8 million t/y LNG trains as part of the North Field South project, having secured a $10bn contract in May 2023.

    More significant, however, is the speed with which QatarEnergy is advancing its strategic objective of reaching a total LNG production capacity of 142 million t/y by the end of the decade, from 77.5 million t/y at present.

    With all three phases of the North Field LNG expansion programme now under EPC execution – and North Field East scheduled for commissioning later this year – QatarEnergy appears firmly on track to become one of the world’s largest LNG suppliers over the long term, reinforcing Qatar’s economic future in the process.

    US domination

    While QatarEnergy is on course to increase its LNG production capacity by 83% by 2030 through the overall North Field LNG expansion programme, it is still some way behind the US, which is set to account for over half of the total global LNG liquefaction projects by 2030.

    There are 40 new-build and expansion LNG liquefaction projects planned or under way in the US, according to UK analytics firm GlobalData. Among these, two projects stand out.

    The first is the Rio Grande LNG production project, being developed by NextDecade in Texas, on the US Gulf of Mexico coast. Up to 10 processing trains are planned for the complex, the first three of which are in the EPC phase.

    NextDecade achieved the final investment decision on the fourth and fifth trains at the facility, estimated to cost $6.7bn each, in September and October last year. The company has awarded EPC contracts to build all five trains at the Rio Grande facility to US-based Bechtel.

    On the investments front, the overseas-focused energy investment vehicle of Abu Dhabi National Oil Company (Adnoc), XRG, acquired an indirect 11.7% stake in the first phase of the project from Global Infrastructure Partners (GIP), part of US asset manager BlackRock, in September last year. In February 2026, XRG entered into another transaction with GIP to raise its overall participation in the Rio Grande LNG project by acquiring additional 7.6% equity interests in trains four and five of the scheme.

    Additionally, as part of that transaction, another Adnoc Group subsidiary, Adnoc Trading, entered into a 20-year offtake agreement with NextDecade last year to purchase 1.9 million t/y of LNG from Rio Grande train four, on a free-on-board basis at a Henry Hub-indexed price. France’s TotalEnergies and Saudi Aramco are the other LNG offtakers for train four.

    Separately, the Commonwealth LNG facility in the US state of Louisiana has also received backing from Abu Dhabi. Expected to start operations in 2030, the facility is designed to produce up to 9.5 million metric t/y of LNG.

    Commonwealth LNG is a project of US-based alternative asset manager Kimmeridge Energy Management Company and Abu Dhabi’s sovereign wealth fund Mubadala Investment Company through their joint venture Caturus.

    Caturus was formed in August 2025 when Kimmeridge announced a rebranding that saw Commonwealth LNG and Kimmeridge’s upstream operations combined under a new integrated platform. At the same time, Mubadala acquired a 24.1% equity stake in Caturus, providing financial backing for the new entity to proceed with the Commonwealth LNG project.

    Also in August, Caturus awarded Technip Energies the contract for EPC works on the Commonwealth LNG project. The French contractor had previously performed the project’s feed work.

    Moreover, Aramco subsidiary Aramco Trading signed a 20-year agreement to buy 1 million metric t/y of LNG from the Commonwealth LNG facility in February, increasing offtake deals secured by Caturus to cover 8 million metric t/y of the project’s total planned output capacity.

    Positive outlook

    The growth in LNG production capacity in the US, as well as in wider North America, is driven by several factors, including abundant natural gas reserves, the shale gas revolution and advancements in hydraulic fracturing and horizontal drilling.

    While it might be a challenge for QatarEnergy to compete with US players in combined liquefaction capacity, its strength and success will lie in clinching long-term offtake deals with customers in Asia, where the bulk of global LNG demand growth is expected.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15954252/main3511.jpg
    Indrajit Sen
  • Bahrain opens bids for first solar IPP project

    13 March 2026

    Two companies have made offers for a contract to develop Bahrain’s first solar photovoltaic (PV) independent power project (IPP).

    Bahrain’s Electricity & Water Authority (EWA) opened bids for the Bilaj Al-Jazayer solar IPP project on 12 March.

    The bidders include Saudi Arabia’s Acwa, formerly Acwa Power, and UAE-headquartered Yellow Door Energy.

    The 150 MWac Bilaj Al-Jazayer solar IPP project will be Bahrain’s first grid-connected solar PV power plant developed under a public-private partnership (PPP) framework on a build-own-operate basis. It will be delivered as a long-term concession and is intended to come online by 2027.

    The proposed site covers more than 1 square kilometre, with the private sector responsible for end-to-end development, including financing, design, construction and operation.

    Last August, EWA held a market consultation event during which it outlined plans for the country’s first solar PV IPP. The main contract was then tendered in October.

    EWA said Yellow Door Energy’s proposal was “accepted with conditions”, but did not disclose further details.

    The local KPMG Fakhro is the financial consultant, the US’ WSP Parsons Brinckerhoff is the technical consultant, and the UK’s Trowers & Hamlins is the legal consultant.

    Bahrain’s clean energy targets, as set by its national plans, include 20% renewables by 2035, and net-zero emissions by 2060.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968088/main.jpg
    Mark Dowdall
  • DP World sees Red Sea port volumes rising as Hormuz shuts

    13 March 2026

    Register for MEED’s 14-day trial access 

    Dubai-based ports operator DP World is preparing for higher throughput at its Red Sea terminals as the Iran conflict approaches its second week, CEO Yuvraj Narayan said on Thursday.

    With the Strait of Hormuz effectively closed and tanker attacks escalating, shipping movements into Gulf ports have fallen.

    The disruption began after US and Israeli strikes on Iran, rattling energy and freight markets and cutting access through what is widely seen as the world’s most critical oil corridor.

    Since most major Gulf ports rely on the narrow Strait of Hormuz, the shutdown is weighing on regional trade flows.

    Narayan said Jebel Ali, DP World’s main hub in Dubai, has not suffered any infrastructure damage and is operating normally, but inbound vessel arrivals are down. Some cargo is still moving through terminals on the eastern side of the strait, he added.

    Ports in the UAE that sit outside Hormuz have limited headroom to absorb the shortfall. Khorfakkan can handle about 5 million 20-foot equivalent units (TEUs) and Fujairah under 1 million TEUs, which Narayan indicated would not be enough to offset lost volume from Jebel Ali or Abu Dhabi’s Khalifa Port.

    Jebel Ali alone processed 15.6 million TEUs last year, out of DP World’s 56.1 million TEUs globally.

    DP World is rolling out rerouting options and other operational measures to keep supply chains moving. Narayan said the company’s Red Sea assets, such as Jeddah in Saudi Arabia and Sokhna in Egypt, are likely to see increased traffic, though he did not quantify the additional volumes or specify cargo types.

    He cautioned that logistical and security risks remain elevated.

    Earlier this week, DP World announced record financial results for 2025, with revenue up 22% to $24.4bn and adjusted earnings before interest, taxes, depreciation and amortisation (Ebitda) up 18% to $6.4bn, delivering a 26.3% margin, as MEED reported.

    DP World said that this performance was driven by strong momentum across its ports and terminals and logistics business.

    The group’s gross throughput rose 5.8% to 93.4 million TEUs.

    Profit for the year increased 32.2% to $1.96bn, and operating cash flow grew 14% to $6.3bn.

    Return on capital employed increased to 9.9% in 2025, up from 8.9% in 2024, reflecting stronger earnings despite ongoing geopolitical and trade uncertainty.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968045/main.jpg
    Yasir Iqbal
  • Frontrunner emerges for Saudi sewage treatment project

    13 March 2026

     

    A consortium led by China’s Jiangsu United Water Technology has emerged as the frontrunner for a contract to build and upgrade two sewage treatment plants in Saudi Arabia, according to sources.

    The contract covers the North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11), part of the next phase of National Water Company’s (NWC) long-term operations and maintenance (LTOM) sewage treatment programme.

    The consortium comprising United Water, Prosus Energy (UAE) and Armada Holding (Saudi Arabia) offered “the lowest tariff” for the project, sources told MEED.

    It is understood that Turkey’s Kuzu has made the next-lowest bid.

    The development, estimated to cost about $211m, will have a combined capacity of about 440,000 cubic metres a day (cm/d).

    In February, MEED exclusively reported that six bidders were competing for the contract.

    The other companies that have submitted proposals include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • VA Tech Wabag (India)
    • Aguas de Valencia (Spain)

    LTOM11, also known as the North Western A Cluster, forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    The scheme is being procured on an engineering, procurement and construction (EPC) basis with a long-term operations component.

    The main contract was tendered last year, with an award initially expected by the end of 2025.

    It is now understood that NWC is preparing to offer the main contract in the second quarter.

    As previously reported, Saudi Arabia’s NWC is also evaluating five bids for package 12 of its long-term operations and maintenance (LTOM12) sewage treatment programme.

    Known as the North Western B Cluster, LTOM12 forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    In January, the same United Water-led consortium won the main contract for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).

    That project includes the rehabilitation and operation of nine sewage treatment plants located across the Hail, Qassim, Al-Jouf and Northern Borders provinces

    NWC is also preparing to tender a contract for the construction of 10 sewage treatment plants as part of package 14 of the programme.

    The final details of the Eastern A Cluster (LTOM14) package are being finalised, with a tender likely to be issued in March or April, sources told MEED.


    READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

    Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

    Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968035/main.jpg
    Mark Dowdall
  • Medina tenders Sikkah Al-Hadid PPP project

    13 March 2026

    Saudi entities including Al-Madinah Regional Municipality, in collaboration with the Ministry of Municipalities & Housing and the National Centre for Privatisation & PPP (NCP), have floated a request for proposal (RFP) notice for the development of the Sikkah Al-Hadid project.

    The project will be procured through build-own-operate-transfer contracts with a 50-year duration, using a public-private partnership (PPP) model.

    The deadline for bid submission is 23 June.

    The project will be located to the west of Medina on an 84,657-square-metre (sq m) site. 

    It includes a four-storey medical centre with a capacity of up to 200 beds and a shopping mall offering retail, food and beverage, and other entertainment facilities.

    In January last year, NCP asked firms to express their interest and prequalify for a contract to develop two mixed-use developments in Medina, which included the Sikkah Al-Hadid project and the Dhul Hulaifah project.

    The Dhul Hulaifah project will be built on a 30,112 sq m site located six kilometres from the Prophet’s Mosque. 

    The development will consist of a four-star hotel integrated with retail and healthcare facilities.

    MEED previously reported that Saudi Arabia had announced a P&PPP pipeline comprising 200 projects across 16 sectors.

    This pipeline aims to attract local and international investors and ensure their readiness to participate in the schemes tendered to the market.

    The initiative comes as the kingdom strives to increase the attractiveness of its economy and raise the private sector’s contribution to GDP.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15968021/main.jpg
    Yasir Iqbal