Water sector braces for likely slowdown
27 December 2024

Geopolitical tensions, climate change and higher-than-average population growth have exacerbated the water demand and supply gap across the Middle East and North Africa (Mena) region, home to some of the world’s most water-stressed countries.
For example, Jordan, where available water per capita is equivalent to only 12% of the absolute water scarcity level, hosts over 700,000 refugees fleeing wars and conflicts in neighbouring countries.
Most regional governments have developed and started to implement water strategies aimed at narrowing this gap. Subsidies are being phased out, environmental campaigns are being developed and digital solutions are being deployed in order to manage demand and improve efficiency.
Expanding desalination and treatment capacity, increasing treated sewage effluent (TSE) reuse, boosting reservoir capacity and building more efficient transmission and distribution networks are key levers used to improve supply.
Strong spending
These efforts have prompted significant capital spending on more energy-efficient water production, distribution and storage facilities, typically in partnership with private investors, particularly among the more affluent states.
According to data from regional projects tracker MEED Projects, the Mena region awarded $17bn of project contracts across the water desalination, treatment, transmission and distribution, storage and district cooling subsectors in the first nine months of 2024.
This figure represents about 72% of the contracts awarded in 2023 and is slightly above the average value of annual contract awards in the preceding five years.
With only a few more packages expected to be awarded before the end of the year, 2024 looks set to be one of the best years so far in terms of water project activity, even if it fails to match the record value of contracts awarded in 2023, which reached almost $24bn.
In 2024, Saudi gigaproject developer Neom set the pace in January by awarding a $4.7bn contract to build dams at the Trojena Mountain Resort in Tabuk to Italian contractor WeBuild.
The contract covers the construction of three dams that will form a freshwater lake for the Trojena ski resort. The main dam will have a height of 145 metres and will be 475 metres long at its crest. It will be built using 2.7 million cubic metres of roller compact concrete.
While this project does not necessarily belong to the band of solutions that aim to narrow the water supply and demand gap, the overall development is part of Saudi Arabia’s drive to boost tourism and diversify its economy away from oil.
Meanwhile, 2024 also saw the award by UAE northern emirate utility Sharjah Electricity, Water & Gas Authority of the contract to develop its first independent water project (IWP), the 400,000 cubic-metres-a-day facility in Hamriyah, to Saudi utility developer Acwa Power, the contract’s sole bidder.
In May, Saudi Arabia’s National Water Company announced that it had completed the award of 10 contracts under the first phase of its privatisation programme. Each rehabilitate, operate and transfer contract involves the retrofitting or expansion of existing sewage treatment plants and associated network, and their long-term operation and management. The facilities are expected to deliver water at the TSE level for irrigation reuse.
On the greenfield sewage treatment front, Saudi Water Partnership Company (SWPC) awarded a $400m contract to develop the Al-Haer independent sewage treatment plant (ISTP) project to a team comprising the local Miahona Company and Belgium’s Besix. The facility is the largest and first to be tendered under the third round of the water offtaker’s ISTP procurement programme.
In September, Chennai-headquartered VA Tech Wabag confirmed it had won a $317m contract to build the Ras Al-Khair seawater reverse osmosis (SWRO) facility in Saudi Arabia using an engineering, procurement and construction (EPC) model. The project client is Saudi Water Authority (SWA), formerly Saline Water Conversion Corporation.
In Oman, Nama Water Services awarded two water distribution network packages, worth a combined $600m, catering to Al-Dhahirah Governorate.
Jordan also appointed a team comprising Paris-based Meridiam, Suez and Vinci Construction Grands Projets, along with Egypt’s Orascom Construction, for the contract to develop the Aqaba-Amman water conveyance and desalination scheme. It is the country’s largest infrastructure project to date and the first phase is valued at an estimated $2bn-$3bn.
The project is crucial to addressing Jordan’s severe water shortage problem, piping desalinated water over 445 kilometres from the southern Red Sea coast to the country’s northern regions. The consortium is talking to lenders and aims to reach financial close for the project in 2025.
Slower momentum
Despite 2024 being a good year for contract awards, it fell short of the expectation built over the past few years, when the region’s largest economies began to execute their long-term water strategies.
For example, in Saudi Arabia, the years-long restructuring of the domestic water sector took a significant turn in 2024, with Water Transmission Company (WTCO), the kingdom’s licensed desalinated water transmission operator, gaining a broader portfolio of projects. As a result, the mandate to procure upcoming water transmission pipelines has been transferred to WTCO from SWPC.
The slower pace of IWP contract awards in Saudi Arabia was somewhat offset by a slew of tenders from SWA. The authority received bids for the EPC contracts to build four SWRO facilities in 2024, although as of November it had only managed to award one.
Earlier in 2024, Saudi gigaproject developer Neom also shelved a project to develop a zero-liquid discharge (ZLD) SWRO plant.
“The year may not have been as strong as 2023, but it is still a good year,” says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting. “Some projects have been delayed or cancelled – for instance a few in Saudi Arabia – but all in all [2024 has been] a good year for the water business.”
Bryniak adds that Neom’s ZLD scheme is one of the year’s shelved projects that he would like to see revived in the future.
Beyond the GCC states, Morocco and Egypt are endeavouring to move their planned SWRO projects into the tendering phase.
In Morocco, Office National de L’Electricite et de L’Eue Potable (Onee) extended the review of its second IWP in Nador while waiting for its first IWP in Casablanca to reach financial close.
The first batch of renewable energy- powered desalination plants in Egypt has yet to reach the proposals stage despite the Sovereign Fund of Egypt having completed the bid prequalification process in 2023.

Potential contract awards
According to data from MEED Projects, an estimated $34bn-worth of water projects are in the tendering stage across the Mena region. A further $40bn-worth is in the prequalification stage and $57bn is in the design and study phases.
The $22bn Dubai Strategic Sewerage Tunnels (DSST) scheme stands out among the upcoming projects due to its scale, as well as for the chosen procurement approach.
The project aims to convert Dubai’s existing sewerage network from a pumped system to a gravity system by decommissioning the existing pump stations and providing a sustainable and reliable service that is fit for the future.
In April, Dubai Municipality launched the procurement process for the DSST project, which is to be developed as a public-private partnership (PPP).
While a dose of pessimism persists over the chosen PPP model – in part due to the project’s scale and strong civil works orientation, and Dubai’s dismal track record in procuring PPP schemes outside the utility sector – the project has managed to attract strong interest from EPC contractors, as well as from potential investors and sponsors.
Some of those that have sought to prequalify as investors, such as Begium’s Besix, Beijing-headquartered China Railway Construction Corporation and South Korea’s Samsung C&T, have previously been prequalified as EPC contractors for the DSST project, which suggests that the preferred approach of prequalifying EPCs ahead of investors could offer advantages.
In Saudi Arabia, WTCO, SWA, SWPC and Neom’s utility subsidiary Enowa are each expected to let several contracts in 2025, while Bahrain and Abu Dhabi could award one IWP contract each.
However, a robust overall pipeline does not necessarily guarantee that 2025 will resemble the upward trajectory that the sector has seen in the past two years.
“This year could be a turning point for the water industry throughout Mena,” says Bryniak, alluding to the possibility that, come January, the foreign and climate policies of the new occupant of the White House could affect the trend of water production capacity buildout in the Mena region.
Bryniak says that if US President-elect Donald Trump follows through with his promises, then we may be in store for, among other events, lower energy prices as the US drills more oil; a dampening of world trade as the US places tariffs on imports, especially on Chinese goods and services; less focus on the environment; and, generally, a more isolationist America.
“In my view, much depends on how much oil prices fall,” he continues.
“A significant drop in oil prices could result in cut-backs in a lot of development projects, and this, in turn, will adversely impact water demand and the overall build programme.”
However, the impact will not be uniform across asset types and procurement models, Bryniak notes. He expects water PPP projects to continue to grow, especially if capital availability is reduced by lower oil prices, as this is one way to preserve capital for use in other areas.
“I do not see any reason for tariffs to fall further in 2025. Tariffs, in my view, will remain roughly where they are now or increase slightly,” adds Bryniak.
However, the executive says that EPC contracts will likely have “a higher opportunity cost”, so there might be a reduced focus on this type of procurement model.
He concludes: “To the extent that development projects get trimmed down due to less capital being available as a result of significantly lower oil prices, then water procurers and other developers will likely scale back their projects.”
Exclusive from Meed
-
-
Frontrunner emerges for Bahrain’s Hidd IWP6 July 2026
-
-
-
PIF’s 2025 results back 2026-30 strategy shift3 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iraq readies tender for additional Al-Faw port piers6 July 2026
Iraq is preparing to issue a tender inviting international contractors to bid for a contract to build the remaining piers at Al-Faw Grand Port in Basra.
According to local media reports, construction work on the project's first phase is expected to be completed by the end of this year.
This will be followed by port operations, for which the client, state-owned General Company for Ports of Iraq, shortlisted three out of the initial 11 international companies that were invited to bid, as MEED reported last year.
At the time, the shortlisted companies included:
- China Merchants Port Group (China)
- Evergreen (Taiwan)
- CMA CGM (France)
- Mediterranean Shipping Company (Switzerland)
- Adani Group (India)
- International Container Terminal Services (Philippines)
- Cosco (China)
- ABM Global Shipping (UAE)
- AD Ports (UAE)
In April last year, Iraq’s Shafaq News Agency reported that the country was in talks with US-based KBR to assist in operating the Al-Faw port.
KBR was expected to provide training in port operations and management to Iraqi personnel, along with related services.
The first phase of the project is scheduled for completion by the end of this year, while the second phase is expected to be completed by 2029.
The first phase of the project cost approximately $5bn, including $2.5bn for its five main piers, which were constructed by South Korea’s Daewoo Engineering & Construction.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17562198/main.jpg -
Frontrunner emerges for Bahrain’s Hidd IWP6 July 2026

Saudi Arabia's Acwa has emerged as the frontrunner for a contract to develop and operate Bahrain’s Al-Hidd independent water project (IWP) following the disqualification of the only other bidder for the plant, a source has told MEED.
The seawater reverse osmosis (SWRO) plant is the state's first IWP project. It is expected to have a production capacity of about 60 million imperial gallons a day (MIGD), equivalent to roughly 272,000 cubic metres a day of potable water.
Acwa offered to develop the project at a levelised cost of water of BD0.276 ($0.73) a cubic metre, according to details published on Bahrain’s Tender Board on 2 July.
GS Inima (South Korea/Spain) was the only other bidder for the project.
Bids for the project had been submitted earlier this year.
The source added that Acwa's financial bid is now under evaluation and has yet to be selected as the preferred bidder. This will only be determined "subject to compliance with the [request for proposal] requirements".
Nine companies and consortiums had previously been shortlisted following the completion of the prequalification process last August.
The facility will be developed on a brownfield site and is expected to be fully operational by 2029. It will be developed using a build, own and operate (BOO) model for 20-25 years and aims to help expand Bahrain’s water infrastructure to meet projected demand based on its 2030 masterplan.
This includes doubling the state's installed power generation capacity to over 10GW by 2030, according to UK data analytics firm GlobalData.
Sitra IWPP
Bahrain's 1.2GW Sitra independent water and power plant (IWPP) project is also advancing, with two bids having been submitted for the plant in June.
The offers were made by Acwa and Abu Dhabi National Energy Company (Taqa). The technical element of the bid was opened on 18 June.
The Sitra IWPP is a combined-cycle gas turbine plant and is expected to have a production capacity of about 1,200MW of electricity. The project’s SWRO desalination facility will have a production capacity of 30 MIGD of potable water.
The plant is Bahrain’s fourth IWPP, replacing the previously planned Al-Dur 3. The Sitra IWPP is expected to be fully operational by the second quarter of 2029.
The Bahraini Electricity & Water Authority’s transaction advisory team for the two BOO projects comprises KPMG Fakhro as the financial consultant and Trowers & Hamlins as the legal consultant.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17562089/main.jpg -
Chinese contractor completes 70% of Iraq oil project6 July 2026

The project to develop new crude oil processing facilities at Iraq’s Rumaila field is 70% complete, according to industry sources.
The project scope for the planned plant in Mishrif Qurainat includes developing two new oil trains, each with a capacity of 120,000 barrels a day (b/d).
When it was originally announced, the planned plant in Mishrif Qurainat was the first new crude oil processing facility project at the oil field in 10 years.
In the fourth quarter of 2022, China Petroleum Engineering & Construction Corporation signed a contract for the design, procurement, construction and testing of the crude oil processing facilities.
The contract was valued at about $386m, and construction was expected to take three years to complete.
Since 2022, the project has seen significant delays and the date for completion is currently uncertain, according to industry sources, as bringing the new crude processing facility online is no longer a priority for the client.
One source said: “Work is continuing on this project at a slow pace because the client is not prioritising commissioning the oil trains.
“The companies that form the joint venture, which operates the Rumaila field, are dealing with a range of other issues right now as a result of the regional war and disruption to shipping through the Strait of Hormuz.”
Rumaila is operated by Rumaila Operating Organisation (ROO).
ROO is a joint venture formed by state-owned Basra Oil Company; Iraq’s State Oil Marketing Organisation (Somo); and Basra Energy Company, a joint venture owned by UK-based oil company BP and PetroChina.
PetroChina is the listed arm of state-owned China National Petroleum Corporation.
Oil exports from Iraq have dropped steeply since the US and Israel attacked Iran on 28 February, leading to a regional conflict.
The conflict has caused significant disruption to Iraq’s oil exports via the Strait of Hormuz.
This has had a knock-on impact for production in the country, where output from many major oil fields has had to stop or has been significantly lowered.
One source said: “At the moment, Basra Oil Company is prioritising restoring production, where it is possible, from assets that have seen reductions in output.
“They are using a lot of resources just to keep existing facilities online and restarting facilities that have stopped due to the crisis.
“Commissioning a brand new project, like the Mishrif Qurainat facilities, is unlikely to be a priority until Iraq’s oil sector returns to a situation that is more like business as usual prior to the conflict with Iran.”
Rumaila is the second-largest producing field in the world, and it is estimated to have about 17 billion barrels of recoverable oil remaining.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17561830/main.jpg -
Riyadh awards Thumama Road eastern section contract6 July 2026

Register for MEED’s 14-day trial access
The Royal Commission for Riyadh City (RCRC) has awarded a contract for the eastern section of the Thumamah Road development project in Riyadh.
Yuksel Saudi, the local subsidiary of Turkish construction firm Yuksel Holding, won the contract.
The mobilisation works are expected to begin by mid-July and the project is expected to be completed by 2028.
The project covers about 8 kilometres (km) and includes three bridges and three tunnels. It is designed to handle up to 200,000 vehicles a day.
The RCRC is investing in upgrading the road networks in the capital. Earlier in July, it awarded another contract to local firm Sapac for the Jeddah Road development project.
Covering 29km, the scheme includes 14 bridges and five lanes.
Designed to handle up to 353,000 vehicles a day, the road is expected to be completed by 2028, with mobilisation works already under way.
The projects form part of the third package of the RCRC’s Riyadh Main and Ring Road Axes Development Programme, which was announced in January.
The other schemes include:
- Taif Road development project: The project stretches 15km and includes four bridges, each with four lanes. It also features two tunnels. It will have a capacity of up to 200,000 vehicles a day and will enhance connectivity between Riyadh’s southern and western districts and the city centre.
- Thumamah Road development project: The eastern section of the project will cover 8km and include three bridges and three tunnels, linking the northern and eastern parts of Riyadh. The project will have a daily capacity of up to 200,000 vehicles.
- King Abdulaziz Road development project: The northern section of the project stretches 4.7km and will include four bridges, four lanes and one tunnel, with a capacity of up to 450,000 vehicles a day.
- Othman Bin Affan Road development project: The northern section will cover 4.3km and include seven bridges and other related upgrades to enhance traffic flow in northern Riyadh. The project will have a daily capacity of up to 500,000 vehicles.
- Second phase of engineering enhancements for congested areas: This project targets eight locations in the city’s road network, where advanced engineering solutions will be applied to reduce congestion and improve intersection performance, increasing traffic capacity by 40%-60%.
The contract for the Thumamah Road development project is the latest of several high-profile deals awarded by the RCRC recently. In May, it awarded an estimated SR5bn ($1.3bn) contract to construct the Sheikh Jaber Al-Sabah Road project in Riyadh.
That contract went to a joint venture of Riyadh-based Al-Rashid Trading & Contracting Company and Turkiye’s IC Ictas.
Stretching 12km, the project runs from Khurais Road to Al-Thumama Road and is a key component of the Second Eastern Ring Road scheme.
Works include five interchanges: Prince Bandar, King Abdullah, Imam Abdullah, Dammam Road and Al-Thumama.
In 2021, Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud said the population of Riyadh would double to 15-20 million people by 2030.
He directed government entities to work closely with the RCRC to prepare the city’s development strategy.
As well as several road development projects in the capital, the RCRC’s major projects include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park and Green Riyadh.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17561818/main.jpg -
PIF’s 2025 results back 2026-30 strategy shift3 July 2026
Saudi Arabia’s Public Investment Fund (PIF) has published its audited consolidated financial statements for the year ended 31 December 2025, the first full set of annual results to follow the board’s approval of the fund’s 2026-30 strategy.
The results show a sharp improvement in profitability last year even as leverage rose and volatility in its listed equity holdings widened. The performance helps explain the strategic shift towards capital discipline and focus on private sector partnerships set out in April.
In April, PIF’s board, chaired by Crown Prince Mohammed Bin Salman Al-Saud, approved a new five-year strategy structured around three portfolios, the Vision Portfolio, the Strategic Portfolio and the Financial Portfolio, and organised around six domestic ecosystems: tourism, travel and entertainment; urban development and liveability; advanced manufacturing and innovation; industrials and logistics; clean energy, water and renewables infrastructure; and Neom as a standalone ecosystem.
Project reprioritisation
The strategy followed a period of reprioritisation across PIF’s gigaproject portfolio and set out a renewed emphasis on private capital, with PIF stating it would “further enable the role of the private sector as an effective partner for sustainable economic development”.
PIF’s consolidated profit for 2025 rose to SR65.2bn ($17.4bn) in 2025, up 152% from SR25.8bn in 2024. The increase was driven by operating profit more than doubling, to SR78bn from SR34.7bn, as revenue growth outpaced cost of revenue and general and administrative expenses moderated relative to the prior year. Profit attributable to the owner of the fund rose to SR46.4bn, up from just SR1bn in 2024, a swing that accounts for most of the year-on-year improvement.
Total revenue, comprising SR312bn of operating revenue and SR137.9bn of income from investment activities, rose 8.8% to SR449.9bn. Core operating revenue alone was up 9.9%, from SR284bn in 2024.
Segment mix
The segment breakdown shows where that growth came from, and it lines up closely with the six ecosystems named in the 2026-30 strategy. Banking and financial services remained the largest single revenue line at SR85.3bn, followed by telecommunications at SR76.8bn ($20.5bn), which was down slightly on 2024. Mining revenue rose 19.3% to SR38.8bn, consistent with the strategy’s focus on industrials and logistics, while revenue from electronic gaming and related services held broadly flat at SR15.6bn, an area PIF governor Yasir Al-Rumayyan specifically cited as a sector for strategic investment alongside artificial intelligence and renewable energy. Agricultural and livestock revenue nearly tripled, to SR7.6bn from SR2.5bn, and revenue from events operations rose to SR7.6bn from SR6bn, both pointing to the diversification into domestic ecosystems the strategy describes. Real estate operations revenue and revenue from advanced electronics and aerospace both declined slightly year-on-year.
Total assets grew 5.1% to SR4.54tn from SR4.32tn, continuing the expansion PIF has reported since 2015, when the strategy document put assets under management at $150bn, against more than $900bn today. The two figures are not directly comparable, since the IFRS consolidated balance sheet captures the full assets of consolidated subsidiaries such as the fund’s banking, telecommunications and mining operations, while PIF’s publicly cited assets-under-management figure uses a different valuation methodology, but both point to the same order of scale.
Total equity, by contrast, fell 2% to SR2.63tn ($701bn) from SR2.68tn, despite the sharp rise in reported profit. The gap is explained by other comprehensive income, which swung to a loss of SR113.3bn for the year, driven primarily by a SR112.8bn fair-value loss on equity instruments measured at fair value through other comprehensive income. In other words, unrealised mark-to-market losses on part of PIF’s listed equity portfolio outweighed the operating profit improvement, leaving total comprehensive income attributable to the owner of the fund at a loss of SR64.7bn for the year, though this was narrower than the SR154.4bn loss recorded in 2024.
Total liabilities rose 16.7%, to SR1.91tn from SR1.64tn, driven mainly by loans and borrowings, which climbed 27.2% to SR725.3bn from SR570.4bn. Property, plant and equipment grew 6.3%, to SR429.6bn, reflecting continued capital spending across PIF’s real estate and gigaproject portfolio, including the stadium, hospitality and urban development programmes.
Strategy context
The scale of PIF’s investment activity in the run-up to 2025 is set out in the April strategy announcement rather than the financial statements themselves. Between 2021 and 2025, PIF says it invested more than $199bn in new projects in Saudi Arabia, contributed $243bn to real non-oil GDP and spent more than $157bn with the local private sector, alongside growing assets under management six-fold and delivering an annualised total shareholder return of more than 7% since 2017. Read against the 2025 results, the rise in mining, gaming, agricultural and events revenue is an early indication that this domestic ecosystem investment is beginning to show up in operating performance, even as the wider balance sheet shows the cost of that expansion in higher borrowing and greater sensitivity to listed equity markets.
The results reinforce a theme demonstrated by PIF’s ongoing award of construction contracts for Expo 2030, the 2034 Fifa World Cup and other gigaprojects in the kingdom. Growth is increasingly funded through a combination of retained earnings, debt and, with the new strategy, private co-investment, rather than balance-sheet expansion alone. The explicit retention of Neom as a named ecosystem in the 2026-30 strategy, despite the cancellation of several Trojena contracts and the loss of the Asian Winter Games over the past year, suggests PIF intends to continue funding the project, but within a more disciplined framework most likely centred on industrial development around the Port of Neom, which is also known as Oxagon.
The 2025 results and the 2026-30 strategy point to a fund entering a new phase: profit generation has improved markedly, but leverage has grown and comprehensive income remains exposed to swings in listed markets, both factors consistent with a strategy that emphasises capital efficiency, institutional excellence and a larger role for private capital rather than a further scaling-up of gigaproject spending on PIF’s own balance sheet.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17540500/main.gif