Power sector awards momentum accelerates

26 December 2024

 

The Middle East and North Africa (Mena) region’s power sector awarded over $60bn of contracts between January and early November 2024, up 47.5% compared to the value of awarded contracts in the previous full year.

This figure is more than double the average value of annual contract awards recorded between 2014 and 2023, based on data from regional projects tracker MEED Projects.

It also exceeds by 21% the total combined value of contracts awarded between 2018 and 2020, when some regional governments and utilities began pivoting to renewable energy and freezing the expansion of thermal plant capacities, in line with goals aimed at decarbonising their electricity systems.

In 2020, the Covid-19 pandemic slowed down project activity and temporarily delayed the awarding of some contracts.

The market staged a short-lived comeback in 2021, when Saudi Arabia awarded a string of contracts for solar photovoltaic (PV) independent power projects (IPPs), including a contract to develop the 600MW Shoaiba solar PV scheme, which holds the world record for the lowest unsubsidised solar PV production at $cents1.04 a kilowatt-hour.

A slight contraction occurred the following year due to a spike in raw materials and engineering, procurement and construction (EPC) costs.

Last year saw a stunning recovery, however, helped by the award of new renewable energy projects in Saudi Arabia, the UAE, Egypt and Oman, as well as by a resumption of contract awards for new gas-fired power plants, particularly in Saudi Arabia, Libya and Iraq.

Yet 2024 is set to outshine 2023 in terms of awarded contracts for thermal, renewable energy and nuclear power generation plants, as well as for power transmission and distribution (T&D) infrastructure such as substations and overhead transmission lines.

Major 2024 awards

In 2023, power generation projects accounted for an estimated 79% of total contract awards, with T&D projects accounting for the rest.

A different picture is emerging in 2024, with data in the first nine months of the year suggesting that generation contract awards are retreating to about 64% of the total. This is due to increased T&D capital spending that has so far driven a 150% increase in award value compared to full-year 2023.

This is a clear indicator of T&D capacity buildout catching up with the generation capacity expansion, especially as larger economies such as Saudi Arabia strive to set up stronger and more efficient electricity links domestically, and as the energy-rich GCC states seek to establish stronger electricity links with one another and with their neighbours, including Egypt, Iraq and Jordan.

Saudi Arabia has dominated the overall Mena power contracts landscape. Its share of 29% in 2022 soared to 61% in 2023 and 67% in the first 10-11 months of 2024.

In May, principal buyer Saudi Power Procurement Company (SPPC) signed two power-purchase agreements with Japan’s Marubeni Corporation for contracts to develop two wind IPPs under the fourth round of the National Renewable Energy Programme (NREP). The Al-Ghat and Waad Al-Shamal wind IPPs have a total combined capacity of 1,100MW. 

The contract for a third wind IPP, tendered as part of round four of the NREP, is also expected to be awarded soon.

In June, Saudi sovereign wealth vehicle the Public Investment Fund (PIF) let the fourth batch of solar PV schemes, which it is implementing bilaterally through the Price Discovery Scheme.

A team comprising Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant Saudi Aramco, will develop the three solar projects, which will have a total combined capacity of 5,500MW and will require an investment of about $3.3bn.

The Haden solar PV and Muwayh solar power plants, which will each have a capacity of 2,000MW, will be located in Saudi Arabia’s Mecca region. The third project, the 1,500MW Al-Khushaybi solar PV plant, will be located in the Qassim region. The three new solar PV facilities are expected to become operational in the first half of 2027.

In early November, SPPC also announced the winning bidders for the contracts to develop four combined-cycle gas turbine plants comprising the second batch of thermal capacity that it has tendered since 2023. The four plants, located in Riyadh and the Eastern Province, will each have a capacity of 1,800MW and will require an investment of about $2bn each.  

A developer consortium comprising the UAE-based Abu Dhabi National Energy Company (Taqa), Japan’s Jera Company and the local Albawani Company successfully bid for the contracts to develop and operate the Rumah 2 and Nairiyah 2 IPPs. Meanwhile, Saudi Electricity Company (SEC), Riyadh-based utility developer Acwa Power and South Korea’s Korea Electric Power Corporation (Kepco) won the contracts to develop and operate the similarly configured Rumah 1 and Nairiyah 1 IPPs.

State utility SEC is also understood to have issued the limited notices to proceed for six greenfield thermal power plants with a total combined capacity of over 16,000MW.

Power generation projects for which final contracts are expected to be awarded before the end of 2024 include:

  • Hajr: 3,600MW
  • Marjan: 1,800MW
  • Riyadh PP12: 1,800MW
  • Qurayyah: 3,600MW
  • Ghazlan 1: 2,400MW
  • Ghazlan 2: 2,900MW

The $5.3bn high-voltage direct current network project connecting the central, western and southern regions of Saudi Arabia was the single largest power contract awarded in Saudi Arabia in 2024.

The UAE, meanwhile, has awarded three key power contracts this year, including for the Al-Ajban solar IPP, which was won by a team of France’s EDF and South Korea’s Korea Western Power Company (Kowepo), and for the Dhafra waste-to-energy project, which a team of Japan’s Marubeni Corporation, Japan Overseas Infrastructure Investment Corporation and Zurich-headquartered Hitachi Zosen Inova is developing.

Dubai Electricity & Water Authority (Dewa) is also understood to have awarded the contract to complete the Jebel Ali K-Station to Egypt-based Power Generation Engineering & Services Company.

2025 outlook

The Mena power projects pipeline remains robust, with over $45bn-worth of contracts under bid evaluation and another $50bn in the prequalification stage as of late 2024, according to MEED Projects.

Saudi Arabia is likely to remain dominant, particularly if SPPC and the PIF activate a plan by the Energy Ministry to procure 20,000MW of renewable energy capacity annually until it reaches its target for renewables to account for half of its energy production mix by 2030.

Morocco has the second-largest power projects pipeline thanks to several planned schemes to export clean energy and green hydrogen to Europe. Notably, the tender is under way for the country’s first two solar PV plus battery energy storage system (bess) projects, Noor Midelt 2 and 3.

Abu Dhabi also maintains a substantial renewables and gas-fired generation project pipeline. It has several upcoming IPPs with a total combined capacity of over 7,000MW, of which more than 6,000MW is in the tendering stage.

While the procurement process for Saudi Arabia’s first nuclear power plant in Duwaiheen has been delayed, the UAE has plans to procure the next phase of its nuclear power plant project in Barakah.

Green industrial development in steel and aluminium, as is being undertaken in the UAE, is a driver for ongoing clean energy capacity buildout, notes Karen Young, senior research scholar at Columbia University’s Centre on Global Energy Policy.

Egypt, Iran, Kuwait and Iraq have the next largest power projects pipelines. The key drivers in each state vary, with populous countries Egypt and Iran seeking to develop integrated green hydrogen hubs and nuclear power capacity, respectively, while Kuwait remains a promising market with extended plans to procure both conventional and renewable energy capacity to address peak demand.

There are indications that Iraq’s first utility-scale solar PV scheme – a 1GW project being developed by France’s TotalEnergies – will head into the construction stage in the coming months, along with other similar projects for which preliminary agreements were signed by Iraqi authorities in 2021-22.

Oman is actively pursuing renewable energy capacity, with the state offtaker having tendered the contracts for two wind IPPs in September 2024.

In Oman and Qatar, the main downstream companies, Petroleum Development Oman and QatarEnergy, are developing renewable energy capacity as a means of mitigating their greenhouse gas emissions, as well as to support their respective government’s net-zero targets.

In November, Bahrain started the procurement process for its fourth independent water and power project (IWPP) in Sitra, which replaced the previously planned Al-Dur IWPP 3 scheme.

Other trends

SEC affiliate National Grid Saudi Arabia has awarded EPC contracts for several bess packages to local firm Algihaz this year. In August, it tendered a contract for the construction of a further 2,500MW of energy storage capacity. 

In parallel, the procurement process is under way for the first independent bess packages in Saudi Arabia and Abu Dhabi, with other utilities expected to follow suit in procuring bess using an IPP model. Bess will boost grid flexibility and spinning reserves in the face of increased renewable energy capacity and demand.

In addition to bess and several gigawatts of solar and wind capacity, Saudi Arabia gigaproject developer Neom, which plans to be powered 100% by renewable energy by the end of the decade, is also considering a network of large-scale pumped hydropower storage plants.   

However, despite the ongoing capacity buildout across the Mena states, some end-users – particularly in fossil fuel-
scarce jurisdictions such as Morocco – continue to struggle with supply.

“I’ve been part of a research project in Morocco looking at the renewable power landscape and green economy more broadly. In that case, we do see massive buildout, but it is tailored for offtake to state-related industrials,” says Columbia University’s Young.

She adds that a telephone survey of 1,000 small and medium-sized businesses in Morocco about their perception of the accessibility and affordability of renewable energy yielded surprising results.

“They strongly suggested a lack of support, given that smaller enterprises continue to see power outages and this has in many cases caused damage to their equipment and abilities to stay open and service customers.

“The disconnect between power buildout and industrial advances in a green supply chain and how small and medium firms see power accessibility and reliability is very stark. In a Mena-wide sense, we might start to question how the delivery and transmission of power in an equitable way affects economic growth opportunities overall.”

https://image.digitalinsightresearch.in/uploads/NewsArticle/13145640/main.gif
Jennifer Aguinaldo
Related Articles
  • Adnoc Distribution signs deal to enter South Africa

    14 July 2026

    Adnoc Distribution, the fuel retailing business of Abu Dhabi National Oil Company (Adnoc Group), has entered into a definitive agreement to acquire 100% of the share capital of UK energy major Shell’s downstream unit in South Africa.

    The proposed acquisition is estimated to have an enterprise value of approximately $1bn for 100% of the share capital of Shell Downstream South Africa (SDSA), part of Shell South Africa Holdings, prior to adjustment for net debt and working capital.

    The transaction is expected to close in 2027, subject to customary regulatory conditions, other conditions precedent and closing conditions, Abu Dhabi Securities Exchange-listed Adnoc Distribution said.

    Additionally, Adnoc Distribution intends to sell a 28% stake in SDSA to a local empowerment partner and employee stock option plan following completion of the acquisition.

    Furthermore, Adnoc Distribution will enter into a long-term brand licensing agreement upon completion of the acquisition, to retain the Shell brand for retail service stations and lubricants businesses in South Africa.

    BofA Securities acted as the sole financial advisor. A&O Shearman and ENS provided legal counsel to Adnoc Distribution on the transaction.

    SDSA represents Shell’s downstream business in South Africa, including a network of 580 company- and dealer-owned mobility and convenience sites, as well as lubricants, commercial fuels, aviation and marine businesses. The brand had fuel volumes of approximately 3.5 billion litres and operated 360 convenience stores as of 2025.

    The proposed acquisition will mark a step forward in Adnoc Distribution’s international expansion, as well as in its drive to grow its fuel retail presence in Africa.

    South Africa is the fourth country where Adnoc Distribution will operate and follows its acquisition of a 50% stake in TotalEnergies Marketing Egypt in 2023 and the 2018 launch of its retail fuel stations in Saudi Arabia.

    Established in 1973, Adnoc Distribution has 1,032 service stations – 568 in the UAE, 219 in Saudi Arabia and 245 in Egypt, as of 31 March this year.

    As a non-fuel retail leader in the UAE, it operates 386 Adnoc Oasis convenience stores, 37 vehicle inspection centres and other services such as car wash and lube change, and has 400 electric vehicle charging points installed under the E2Go brand in the UAE.

    The company is also a marketer and distributor of fuels to commercial, industrial and government customers throughout the UAE.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17664769/main4804.jpg
    Indrajit Sen
  • Expo 2030 Riyadh construction gathers pace

    14 July 2026

     

    Construction activity at the Expo 2030 Riyadh site is accelerating, with Expo Riyadh 2030 Company (ERC) moving to award its first major vertical contracts and advancing infrastructure works across a programme that will eventually require between 50,000 and 70,000 workers at peak.

    Saudi Arabia’s first World Expo runs from 1 October 2030 to 31 March 2031. Riyadh was awarded the hosting rights in November 2023, winning the vote in the first round, and the event is projected to attract more than 40 million visits over its six months. Beyond the event itself, the project carries significant economic weight: ERC, wholly owned by the Public Investment Fund (PIF), expects the construction phase and legacy development to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs, with the live event contributing a further $5.6bn.

    The masterplan covers 6 million square metres to the north of Riyadh, adjacent to the future King Salman International airport. After the event closes, ERC plans to transform the site into a global village combining retail, food and beverage and an international residential community – meaning every asset being built now is being designed with its post-Expo purpose in mind.

    Infrastructure works under way

    The earliest works on site – bulk earthworks including cut, fill and levelling – have been completed by local contractor Binyah, with millions of cubic metres of material moved to bring the site to design level.

    The programme has now moved into utility infrastructure, which has been split into two packages. Nesma is constructing the primary utility networks – the main corridor running around the site carrying high-voltage power lines, water mains, sewerage and communications – while Al-Yamama is delivering the secondary networks that bring services into the central event area, with construction expected to commence this month.

    Power has been a priority. ERC has worked with the Saudi electricity sector since 2025 to develop the site’s demand profile, and an agreement for permanent supply has been signed. Design and procurement of the main substation and primary power infrastructure are under way, with a contract award expected within weeks and full permanent power – at a capacity of 400MW – targeted approximately 18 months ahead of the event.

    An initial 25MW supply to power site operations and support testing and commissioning is already installed and ready to be energised.

    On water, ERC is finalising an agreement with the Royal Commission for Riyadh City (RCRC), the Saudi Water Authority and the National Water Company, with an announcement expected in Q3 and construction targeted to start in 2027.

    Transport and connectivity

    With more than 42 million visits anticipated over the six-month event, transport connectivity is treated as central to the project’s success. ERC is working with RCRC on a mobility plan that covers several modes. Two road enhancement projects around the airport and along King Salman Road are expected to be announced shortly, increasing capacity on the main arteries approaching the site.

    A dedicated Expo metro station on Riyadh Metro Line 4 – which connects the airport to the city centre – will be built within the site boundary, forming the first stop from the airport towards Riyadh, and providing a direct link for international arrivals.

    A park-and-ride programme using dedicated bus lanes will serve domestic visitors parking at locations across the city.

    A hotel within the fenced Expo site is also nearing contract, with a design agreement close to signature. ERC says the intention is to give guests staying on site “the full experience from early morning when the gates open until late at night when the gates close” – an offer it expects will prove particularly popular with international visitors.

    Pavilions and vertical assets

    The Expo's masterplan is organised around five districts, each echoing one of the event’s sub-themes under its overarching theme of Foresight for Tomorrow: planet, people, technology, collaboration and culture. ERC is responsible for delivering a signature pavilion in each district, plus an iconic structure in the Global Collaboration district and a convention centre intended to serve both the event and Riyadh’s long-term conference market.

    The Kingdom of Saudi Arabia (KSA) Pavilion, one of the centrepieces of the event, is also under ERC’s delivery responsibility. Design work is progressing across all these assets with engineering firms taking concepts through to schematic and detailed design.

    For international participating countries, this edition of the Expo marks a significant departure from previous editions. Rather than grouping lower-income countries into shared halls, all participants will have their own national pavilion.

    “In this edition, we are following the ‘one nation, one pavilion’ model, whereby each country has its own pavilion, and we have a dedicated budget to help up to 100 eligible countries deliver those pavilions,” says Murad Al-Sayed, ERC’s chief delivery officer.

    Contracting strategy

    The contracting approach for vertical assets is being calibrated to the complexity of each building. Less complex assets will be procured on a design-and-build basis.

    For the most complex – the KSA Pavilion and the iconic structure – ERC is using a two-stage model, separating enabling works and substructure from the main contract. This allows construction to begin on site while the main package is finalised and brings contractors into the design process earlier.

    “We are adopting different contracting strategies depending on the asset – its size, complexity and anticipated construction duration,” Al-Sayed says.

    For the KSA Pavilion, enabling and substructure works are already in the market, with an award targeted in Q3, allowing construction to start before the main contract – for which nine tier-one contractors, local and international, have been invited to bid – is awarded towards the end of the year. Packages for the remaining signature pavilions are expected to follow later this year and into 2026.

    On commercial terms, ERC is favouring lump-sum contracts where design maturity allows, with provisional sum or remeasurement provisions used where elements remain in development. A final public realm package, covering site-wide finishing works, remains under design and is expected to be tendered in 2026, sequenced deliberately to be installed last and once only ahead of the event.

    Bidding appetite from the market has been strong. ERC says all tenders issued to date have attracted healthy numbers of qualified bids, reflecting a contracting market that has eased over the past 18 months as several gigaprojects elsewhere in the kingdom have reached completion or had their timelines revised.

    Programme and supply chain

    ERC is targeting completion of major construction by the end of 2029, leaving six to nine months for finishing, snagging and operational testing. To ease the build programme for international participants, ERC is making plots available up to 36 months before the event – around nine to 12 months longer than the industry norm – giving countries more schedule float to complete their pavilions.

    On the supply chain, ERC is leaning heavily on local manufacturers for current infrastructure work, covering piping, cabling, electrical equipment and bulk materials. As construction moves above ground and international participants begin work on their pavilions from 2027 onwards, ERC will make its database of prequalified local contractors, suppliers and consultants available to them through a dedicated one-stop shop – a registration exercise already under way and expected to remain open until the event itself.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17664502/main.gif
    Colin Foreman
  • Masdar reaches financial close on world-first 24/7 solar project

    14 July 2026

    Abu Dhabi Future Energy Company (Masdar) has reached financial close on the world's first gigascale round-the-clock renewable energy project, securing a $5.1bn financing package from a consortium of 13 international and local banks.

    The project, being developed in Abu Dhabi with state offtaker Emirates Water & Electricity Company (Ewec), represents a total capital investment of $6.1bn, with Masdar providing $1bn of equity. It integrates a 5.2GW solar photovoltaic (PV) plant with a 19 gigawatt-hour battery energy storage system, which Masdar says is the largest of its kind in the world.

    The 13 lenders providing the financing are Abu Dhabi Commercial Bank, Abu Dhabi Islamic Bank, France's BNP Paribas, Bank of China, France's Credit Agricole Corporate & Investment Bank, Dubai Islamic Bank, First Abu Dhabi Bank, UK-based HSBC, Germany's KfW Ipex-Bank, France's Natixis, Japan's Sumitomo Mitsui Banking Corporation, UK-based Standard Chartered Bank and France's Societe Generale.

    The independent power project is designed to deliver 1GW of baseload power around the clock, addressing the challenge of solar intermittency by pairing large-scale generation with battery storage. It is intended to serve large energy users requiring 24/7 clean electricity, including data centre operators and technology firms driving artificial intelligence deployment in the region.

    Ewec will act as offtaker under a long-term power purchase agreement, while private offtakers such as data centres will access electricity through back-to-back arrangements.

    India's Larsen & Toubro and Beijing-headquartered PowerChina are handling engineering, procurement and construction works, with PwC Middle East advising Ewec on financial structuring. China's CATL will supply the battery storage system, while Jinko Solar and JA Solar will each provide 2.6GW of PV modules.

    Masdar broke ground on the project in October 2025, and it is expected to be operational in 2027. The scheme will avoid 5.7 million tonnes of carbon dioxide emissions a year and provide enough clean energy to power nearly half a million homes.

    The developer has a diversified portfolio of more than 65GW and has set a target of reaching 100GW of renewable energy capacity by 2030.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17664609/main.jpg
    Colin Foreman
  • Jordan tenders IPP8 power project

    14 July 2026

    Jordan’s National Electric Power Company (Nepco) has issued a tender for a contract to develop the 700MW combined-cycle gas turbine (CCGT) power project known as independent power project 8 (IPP8).

    Companies understood to have prequalified include France’s EDF, Saudi Arabia’s Acwa and Egypt’s Orascom Construction. Bids are due in July, although the market expects the closing date may be extended.

    MEED reported in November last year that Nepco had invited developers to submit prequalification documents for IPP8. The project will be developed on a build, own and operate (BOO) basis and will supply power to the national grid under a 25-year agreement.

    Natural gas will serve as the primary fuel, with light distillate as backup. The facility will be connected to Nepco’s 132kV/400kV transmission infrastructure, which will be built separately.

    In April, MEED reported that Nepco had signed an agreement to establish a natural gas supply point for the 700MW IPP7. The agreement was signed with Fajr Jordanian-Egyptian for Natural Gas Transmission and Supply to support fuel provision for the CCGT plant.

    The plant will be developed in partnership with Etihad Development Company, a subsidiary of the UAE’s Etihad Water & Electricity (EtihadWE), following recent approval by the Ministry of Energy & Mineral Resources.

    The IPP7 plant is expected to meet about 10% of Jordan’s electricity demand once operational. It is also intended to enhance the reliability and efficiency of the national power system.

    The project is scheduled to become operational between 2027 and 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17662814/main.jpg
    Colin Foreman
  • Indian firm wins Oman’s Al-Dhahirah economic zone deal

    14 July 2026

    Oman Shapoorji Company, the local branch of India's Shapoorji Pallonji, has won an estimated $67m contract to construct an administrative and commercial buildings complex within the Economic Zone at Al-Dhahirah (Ezad).

    The scope of work includes the construction of an administration building, a commercial centre, a hotel and a health centre.

    The scope also covers the construction of roads, sewers and water, irrigation and landscaping works.

    Oman’s Public Authority for Special Economic Zones & Free Zones (Opaz) tendered the contract.

    In July last year, MEED reported that Opaz had signed seven agreements and memorandums of understanding (MoUs) for the first phase of development of Ezad.

    The zone is located in Al-Dhahirah Governorate in northwestern Oman, on the sultanate’s borders with Saudi Arabia and the UAE. Oman’s Finance Ministry and the Saudi Fund for Development signed an MoU in February 2023 to jointly invest $320m in developing Ezad.

    Among the agreements was a contract awarded by Opaz for the construction of main roads and the surface water drainage system at Ezad, valued at $58m. A consortium of Omani and Saudi contractors won the contract, which had a duration of 24 months.

    Opaz awarded two further contracts for engineering consultancy work to Oman-based Al-Watanyiah United Engineering and Saudi Arabia’s Dar Al-Riyadh. As part of their contracts, both firms were to prepare architectural, structural and infrastructure designs for projects in Ezad; provide technical advice; perform feasibility studies; and assist with approvals.

    Opaz intends to develop 20 square kilometres (sq km) of the total land area allocated to Ezad as part of the first phase of development, with 7.5 sq km of that earmarked for fast-track development.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17661726/main.gif
    Yasir Iqbal