Mena power rides high into 2024

29 December 2023

 

The Middle East and North Africa (Mena) region’s power generation and transmission sector awarded an estimated $25.3bn-worth of contracts between January and November 2023.

While this pales in comparison to the record high of $37.7bn awarded in 2015, it is up 38 per cent on the previous full year 2022, according to MEED Projects.

Year-on-year, the value of awarded power generation contracts increased by 40 per cent to reach $19bn, outperforming the transmission sub-sector growth by nine percentage points.

Saudi Arabia accounted for 60 per cent of the awarded power contracts in 2023. These include the contracts to develop four independent power projects (IPPs) that use combined-cycle gas turbines (CCGT), the first to be procured since the kingdom awarded the contract to develop the 1,500MW Al-Fadhili IPP to France’s Engie in 2016.

The Taiba 1 and 2 and Qassim 1 and 2 IPP projects each have a generation capacity of 1,800MW and require a combined investment of $7.8bn, of which roughly 80 per cent is accounted for by engineering, procurement and construction (EPC) costs.

The kingdom also awarded an EPC contract for the 1,200MW expansion of a power plant complex in Jubail during the year.

On the renewable energy front, the principal buyer, Saudi Power Procurement Company (SPPC), and the Public Investment Fund awarded some 6.7GW of solar photovoltaic (PV) IPP projects.

The uptick in awards marks a major improvement after a year of tepid renewables project activity in 2022, barring the solar and wind farm projects being developed as part of the large-scale green hydrogen and ammonia project in Neom.

The transmission and distribution sub-sector contributed to Saudi Arabia’s sterling market performance this year, delivering contracts worth over $3.5bn.

The kingdom’s electricity grid is expected to continue to be upgraded to accommodate growing renewable energy capacity and the rise in electricity demand as Vision 2030-related projects enter the execution phase.

The plan to accelerate electricity trade with its GCC neighbours and other countries in the region, such as Egypt and Iraq, is also anticipated to encourage future grid investments. 

The award of the $2bn multi-utilities package for the Amaala development project also stood out, not least due to the inclusion of a 700 megawatt-hour battery energy storage system to enable the hotels within the development to be completely off-grid.

Unlike in the previous two years, Kuwait, the UAE and Oman also tendered or awarded substantial power generation contracts in 2023.

Nama Power & Water Procurement Company awarded the contracts to develop the second and third utility-scale solar PV schemes in the sultanate, Manah 1 and 2, each with a capacity of 500MW, in the first half of the year.

In September, Dubai Electricity & Water Authority awarded the contract to develop the sixth phase of the Mohammed bin Rashid solar complex.

Looking forward

The Mena power sector is expected to maintain its momentum into 2024, if the final quarter of 2023 is anything to go by.

Saudi Arabia is likely to continue dominating power project activities, with other states such as the UAE, Oman, Morocco, Egypt, Kuwait and Qatar offering significant opportunities for developers and EPC contractors.

Saudi Arabia’s SPPC has held a market-sounding event for the four solar IPPs under the fifth round of the kingdom’s National Renewable Energy Programme (NREP), while bid evaluation is still under way for the three wind IPPs under the NREP’s round four.

The tender documents are also being prepared for two CCGT projects in Riyadh, PP15 and Al-Khafji, with each expected to have a capacity of 3.6GW.

Qatar and Kuwait are advancing the procurement process for independent water and power producer (IWPP) projects that were held back over the past few years.

Abu Dhabi has initiated the procurement process for its fourth solar PV IPP and first twin battery energy storage facilities. 

It will also almost certainly kick off the procurement process for one or two thermal power plants in the months ahead in anticipation of the need to replace expiring gas-fired capacity.

North Africa

The procurement of renewable energy plants, particularly in the North African states, led by Egypt and Morocco, is also expected to ramp up, in part due to their goals to develop green hydrogen hubs and export clean energy to Europe.

“Morocco is definitely going to be a major market from 2024 and onwards, with several IPPs in the planning and study stage,” says a senior partner with a transaction advisory firm.

Expectations also continue to thrive for many thermal projects planned in Libya and solar PV IPPs in Iraq, despite political uncertainties. 

For Iraq in particular, the external pressure to rely less on Iranian electricity imports will provide impetus to its solar and CCGT capacity programmes.

The future trend for levelised costs of electricity is likely to remain mixed over the coming months

LCOE trend 

The future trend for levelised costs of electricity (LCOEs) – or the pre-agreed, long-term tariffs an offtaker pays utility developers for their plants’ electricity output – is likely to remain mixed over the coming months, according to a region-based expert.

“The LCOEs for CCGTs are likely to remain stable next year, while solar LCOEs could slightly decline, compared with those seen in 2023,” the source tells MEED.

Supply chain constraints for gas turbines remain a concern for future CCGT power plants, given what is understood to be a long lead time for delivery and the production capacity constraints in the EU plants of the leading suppliers such as Germany’s Siemens Energy and the US’ GE.

While this opens opportunities for gas turbine manufacturers based in China, it is foreseeable that there remains a dominant preference for EU-made products across the Mena region, particularly in the GCC states.

The same expert argues, however, that the massive increase in gas turbine demand may be temporary, with demand likely to start petering off sometime after 2024, when clients and utility developers alike will have to consider the impact of these assets, whose concession agreements extend between 25 and 30 years, to their net-zero commitments.

As previously cited, Saudi Arabia will continue to dominate the region’s power sector project activities in the foreseeable future. Its ambition for renewable energy sources to account for half its capacity by 2030 and the Vision 2030-related plans to build off-grid developments such as Neom, the Red Sea and Amaala, as well as its multibillion-dollar industrialisation programme, will drive this.

According to MEED Projects data, Iran, Algeria, Kuwait, the UAE and Qatar are the other key markets for projects in the bidding stage. Morocco, Egypt, Kuwait and the UAE are the most promising markets for projects outside Saudi Arabia in the study, design or prequalification stage.

Overall, the net-zero commitments made by key states such as Saudi Arabia and the UAE, and plans to build green hydrogen valleys from Abu Dhabi to Morocco, in addition to an endemic rise in electricity demand as populations and economies grow, will likely keep the overall power sector buoyant over the coming years, barring any major events, like the Covid-19 pandemic in 2020 or the Russia-Ukraine war in 2022. 

Sustainability drives water investments

https://image.digitalinsightresearch.in/uploads/NewsArticle/11336705/main.gif
Jennifer Aguinaldo
Related Articles
  • Eni completes $1bn Libya gas project

    20 October 2026

    Register for MEED’s 14-day trial access 

    Libya’s Mellitah Oil & Gas Company, a joint venture of Libya’s National Oil Corporation (NOC) and Italian oil and gas company Eni, has achieved mechanical completion on its Bouri gas utilisation project (GUP).

    In a statement, Eni said that start-up procedures are currently under way, enabling the recovery of associated gas produced from the Bouri field, which is located in Libya’s western offshore area.

    The main contract for the project, worth $1bn, was awarded to Italy’s Saipem in August 2023.

    The project involved the construction and installation of the new Bouri gas recovery module and related tie-in infrastructure that enables the recovery and treatment of gas that was previously flared.

    In its statement, Eni said that the project “represents one of the most significant emissions reduction initiatives in Libya’s energy sector”.

    It also said that it would contribute to improving the environmental performance of the country’s production system by reducing greenhouse gas emissions by approximately 1.5 million tonnes of carbon dioxide a year.

    The recovered gas will be supplied to the domestic market, adding about 700 million cubic metres a year and helping meet demand from the power generation sector.

    The project will also support additional gas volumes available for export to Europe through the GreenStream pipeline.

    Eni said: “The start-up of the Bouri GUP confirms the joint commitment of Eni and NOC to the development of Libya’s energy sector through initiatives that combine production growth, operational efficiency and environmental stewardship.

    “The project is part of a broader strategy aimed at enhancing the value of the country’s gas resources while reducing the emissions intensity of upstream activities.”

    Other key projects currently under way in Libya include the A&E Structures Project, which is focused on bringing new offshore gas resources onstream for both the domestic market and exports, as well as initiatives aimed at upgrading and optimising gas production and transportation infrastructures.

    Eni has been present in Libya since 1959, and the company’s equity production in the country in 2025 amounted to approximately 162,000 barrels of oil equivalent a day.

    The Bouri offshore field is part of Libya’s Block NC-41, located 120 kilometres north of the Libyan coast in the Mediterranean Sea.

    It was first discovered in 1976 at a depth of 8,700 feet. It is estimated to contain 4.5 billion barrels in proven recoverable crude oil reserves and 3.5 trillion cubic feet of associated natural gas, with an annual production potential of 6 billion cubic metres.

    The first development phase, costing nearly $2bn, was completed in 1990.

    This was immediately followed by a second development phase, which entailed drilling 55 new wells and constructing three additional platforms. Production began from the oil platforms DP4 and DP3 in August 1998.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20770288/main3529.jpg
    Wil Crisp
  • Diriyah Company tenders East Wadi bridge

    20 October 2026

     

    Saudi Arabia’s Diriyah Company has invited contractors to bid on the construction of the DG II East Wadi Bridge, a key crossing within Riyadh’s Diriyah master development.  

    The bridge will provide an arterial road connection linking the Diriyah Gate Phase 2 (DG II) Infrastructure Package 1 and Package 2 zones.  

    The project scope involves the construction of a 100-metre clear-span, 44-metre-wide, single-span post-tensioned concrete bridge structure with integrated abutments and four architectural towers.  

    The contract also encompasses approach slabs, access roads, pavements, associated earthworks, architectural finishes and cladding, mechanical, electrical and plumbing installations, utility interfaces, bridge parapets, vehicle restraint systems, waterproofing, testing and commissioning, and associated temporary works.  

    The client will supply the detailed engineering design, and the selected contractor will develop the construction methodology.

    Diriyah Company issued the prequalification tender on 14 September, with submissions due by 10 December.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20769223/main.png
    Yasir Iqbal
  • Kuwait selects firms for power works at housing projects

    20 October 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has appointed contractors for works covering the supply and installation of 132kV underground cables at South Sabah Al-Ahmad Residential City.

    The contracts relate to engineering, procurement and construction (EPC) packages for works for 28 main 132/11kV substations across four phases.

    According to sources, Egypt’s Elsewedy Cables has won contracts for phases 1 and 3, while China’s TBEA Shandong Luneng Taishan Cable Company has won contracts for phases 2 and 4 of the development.

    In April, MEED reported that PAHW had received at least five bids for each of the first two packages, with Elsewedy and TBEA offering $44m and $40.5m, respectively.

    The first contract (phase 1) covers seven substations in zones N9, N7 and N5. The second contract (phase 2) covers seven substations in zones N10 and N5.

    PAHW issued two further 132kV underground cable tenders for the South Sabah Al-Ahmad residential development at the end of May, as reported by MEED.

    This included a contract (phase 3) covering the supply, extension and maintenance of 132kV underground cables linked to seven substations serving the N5, N6, N8 and N10 districts. Egytech Cables, a subsidiary of Elsewedy, submitted an offer of $39.95m, the lowest of four bids.

    The other contract (phase 4) covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts. 

    MEED reported in July that TBEA had submitted an offer of $44.06m for the contract.

    South Saad Al-Abdullah 

    Separately, PAHW has appointed contractors for power transmission works at the South Saad Al-Abdullah residential development.

    The local firm Sayed Hamid Behbehani & Sons has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the development’s third phase. 

    Another local firm, Al-Ahleia Switchgear, has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the project’s fourth phase. 

    As reported in August, the contractors submitted bids of $104.2m and $103.3m, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20761431/main.jpg
    Mark Dowdall
  • Taqa moves forward with Mirfa-Liwa scheme

    20 October 2026

     

    Taqa Transmission and Taqa Distribution are advancing a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, sources told MEED.

    The project, originally estimated to cost $775m, has been in procurement for several years. According to sources, a request for proposals has been issued, with bids due on 5 January 2027.

    The initial submission deadline was 11 November, before it was extended.

    The project was previously tendered in December 2024, with contractors submitting bids for transmission and distribution packages in January 2025.  As of August, the bids were still under evaluation. It is unclear whether the latest tender represents a revised procurement process for the same scheme.

    The project comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in the western region.

    According to details seen by MEED, the latest scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, about 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.

    The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.

    The earlier procurement was structured as an engineering, procurement and construction scheme, divided between transmission and distribution works.

    As MEED understands, the latest tender is being pursued under a design, build and operate model, which extends the contractor’s responsibilities to operating the infrastructure after construction.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20758109/main2934.jpg
    Mark Dowdall
  • Contractors prepare prices for Adnoc Onshore field facilities project

    20 October 2026

     

    Contractors are preparing commercial bids for Adnoc Onshore’s project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields in Abu Dhabi’s North East Bab oil field cluster.

    The project will enhance and sustain crude output at Rumaitha and Shanayel at 45,000 barrels a day (b/d), supporting Adnoc’s Accelerated Integrated Programme 5 (AiP5) drive to lift capacity to 5 million b/d by 2027.

    Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on 19 June. Contractors submitted technical bids by 5 August, sources told MEED.

    The on-plot works include adding a crude processing train, produced water treatment and reinjection systems, surface water pumps, and multi-stage gas compression and dehydration units. Works also include utilities, safety and control systems, modifications to existing Phase 1 units and 220kV power infrastructure.

    The off-plot scope includes installing and tying in new gas-lifted producer and water-injection wells, as well as building and expanding wellhead clusters. Contractors will also lay crude-gathering, water-injection and gas-export pipelines connecting to the Adnoc Gas network and extend 33kV overhead power lines across the fields.

    The tender follows Adnoc Onshore’s shift in strategy for the wider North East Bab development – comprising the Al-Nouf, Rumaitha and Shanayel fields – after scrapping an earlier engineering, procurement and construction management (EPCm) approach. MEED reported in December that the operator had cancelled an off-plot EPCm contract awarded to China Petroleum Engineering & Construction Corporation (CPECC) in October 2024. Adnoc later cancelled a separate on-plot EPCm tender that it received bids for in the second quarter of 2025.

    In addition to the North East cluster, Adnoc Onshore continues to make progress on EPC works for another similar project to build off-plot facilities at the South East cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.

    The South East cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.

    MEED previously reported that Adnoc Onshore awarded CPECC the EPC works for the South East off-plot facilities project, with the contract value estimated at around $1.2bn.

    CPECC is also performing EPC works on the South East on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.

    ALSO READ: Adnoc Onshore seeks bids for Bu Hasa field EOR project

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20757699/main.jpeg
    Indrajit Sen