Mena power rides high into 2024

29 December 2023

 

The Middle East and North Africa (Mena) region’s power generation and transmission sector awarded an estimated $25.3bn-worth of contracts between January and November 2023.

While this pales in comparison to the record high of $37.7bn awarded in 2015, it is up 38 per cent on the previous full year 2022, according to MEED Projects.

Year-on-year, the value of awarded power generation contracts increased by 40 per cent to reach $19bn, outperforming the transmission sub-sector growth by nine percentage points.

Saudi Arabia accounted for 60 per cent of the awarded power contracts in 2023. These include the contracts to develop four independent power projects (IPPs) that use combined-cycle gas turbines (CCGT), the first to be procured since the kingdom awarded the contract to develop the 1,500MW Al-Fadhili IPP to France’s Engie in 2016.

The Taiba 1 and 2 and Qassim 1 and 2 IPP projects each have a generation capacity of 1,800MW and require a combined investment of $7.8bn, of which roughly 80 per cent is accounted for by engineering, procurement and construction (EPC) costs.

The kingdom also awarded an EPC contract for the 1,200MW expansion of a power plant complex in Jubail during the year.

On the renewable energy front, the principal buyer, Saudi Power Procurement Company (SPPC), and the Public Investment Fund awarded some 6.7GW of solar photovoltaic (PV) IPP projects.

The uptick in awards marks a major improvement after a year of tepid renewables project activity in 2022, barring the solar and wind farm projects being developed as part of the large-scale green hydrogen and ammonia project in Neom.

The transmission and distribution sub-sector contributed to Saudi Arabia’s sterling market performance this year, delivering contracts worth over $3.5bn.

The kingdom’s electricity grid is expected to continue to be upgraded to accommodate growing renewable energy capacity and the rise in electricity demand as Vision 2030-related projects enter the execution phase.

The plan to accelerate electricity trade with its GCC neighbours and other countries in the region, such as Egypt and Iraq, is also anticipated to encourage future grid investments. 

The award of the $2bn multi-utilities package for the Amaala development project also stood out, not least due to the inclusion of a 700 megawatt-hour battery energy storage system to enable the hotels within the development to be completely off-grid.

Unlike in the previous two years, Kuwait, the UAE and Oman also tendered or awarded substantial power generation contracts in 2023.

Nama Power & Water Procurement Company awarded the contracts to develop the second and third utility-scale solar PV schemes in the sultanate, Manah 1 and 2, each with a capacity of 500MW, in the first half of the year.

In September, Dubai Electricity & Water Authority awarded the contract to develop the sixth phase of the Mohammed bin Rashid solar complex.

Looking forward

The Mena power sector is expected to maintain its momentum into 2024, if the final quarter of 2023 is anything to go by.

Saudi Arabia is likely to continue dominating power project activities, with other states such as the UAE, Oman, Morocco, Egypt, Kuwait and Qatar offering significant opportunities for developers and EPC contractors.

Saudi Arabia’s SPPC has held a market-sounding event for the four solar IPPs under the fifth round of the kingdom’s National Renewable Energy Programme (NREP), while bid evaluation is still under way for the three wind IPPs under the NREP’s round four.

The tender documents are also being prepared for two CCGT projects in Riyadh, PP15 and Al-Khafji, with each expected to have a capacity of 3.6GW.

Qatar and Kuwait are advancing the procurement process for independent water and power producer (IWPP) projects that were held back over the past few years.

Abu Dhabi has initiated the procurement process for its fourth solar PV IPP and first twin battery energy storage facilities. 

It will also almost certainly kick off the procurement process for one or two thermal power plants in the months ahead in anticipation of the need to replace expiring gas-fired capacity.

North Africa

The procurement of renewable energy plants, particularly in the North African states, led by Egypt and Morocco, is also expected to ramp up, in part due to their goals to develop green hydrogen hubs and export clean energy to Europe.

“Morocco is definitely going to be a major market from 2024 and onwards, with several IPPs in the planning and study stage,” says a senior partner with a transaction advisory firm.

Expectations also continue to thrive for many thermal projects planned in Libya and solar PV IPPs in Iraq, despite political uncertainties. 

For Iraq in particular, the external pressure to rely less on Iranian electricity imports will provide impetus to its solar and CCGT capacity programmes.

The future trend for levelised costs of electricity is likely to remain mixed over the coming months

LCOE trend 

The future trend for levelised costs of electricity (LCOEs) – or the pre-agreed, long-term tariffs an offtaker pays utility developers for their plants’ electricity output – is likely to remain mixed over the coming months, according to a region-based expert.

“The LCOEs for CCGTs are likely to remain stable next year, while solar LCOEs could slightly decline, compared with those seen in 2023,” the source tells MEED.

Supply chain constraints for gas turbines remain a concern for future CCGT power plants, given what is understood to be a long lead time for delivery and the production capacity constraints in the EU plants of the leading suppliers such as Germany’s Siemens Energy and the US’ GE.

While this opens opportunities for gas turbine manufacturers based in China, it is foreseeable that there remains a dominant preference for EU-made products across the Mena region, particularly in the GCC states.

The same expert argues, however, that the massive increase in gas turbine demand may be temporary, with demand likely to start petering off sometime after 2024, when clients and utility developers alike will have to consider the impact of these assets, whose concession agreements extend between 25 and 30 years, to their net-zero commitments.

As previously cited, Saudi Arabia will continue to dominate the region’s power sector project activities in the foreseeable future. Its ambition for renewable energy sources to account for half its capacity by 2030 and the Vision 2030-related plans to build off-grid developments such as Neom, the Red Sea and Amaala, as well as its multibillion-dollar industrialisation programme, will drive this.

According to MEED Projects data, Iran, Algeria, Kuwait, the UAE and Qatar are the other key markets for projects in the bidding stage. Morocco, Egypt, Kuwait and the UAE are the most promising markets for projects outside Saudi Arabia in the study, design or prequalification stage.

Overall, the net-zero commitments made by key states such as Saudi Arabia and the UAE, and plans to build green hydrogen valleys from Abu Dhabi to Morocco, in addition to an endemic rise in electricity demand as populations and economies grow, will likely keep the overall power sector buoyant over the coming years, barring any major events, like the Covid-19 pandemic in 2020 or the Russia-Ukraine war in 2022. 

Sustainability drives water investments

https://image.digitalinsightresearch.in/uploads/NewsArticle/11336705/main.gif
Jennifer Aguinaldo
Related Articles
  • Saudi water sector hits sharp slowdown

    8 September 2026

     

    Saudi Arabia’s water sector has recorded a sharp slowdown in contract awards this year, with $3.94bn of new contracts awarded as of early September.

    According to regional project tracker MEED Projects, this is well below the $10.7bn recorded in 2025, $13bn in 2024 and a record $15.3bn in 2023.

    The slowdown comes as several major projects remain in the procurement process, with some yet to reach financial close or contract award, while tender deadlines for other schemes have been pushed back.

    Among the largest is the estimated $2bn Riyadh-Qassim independent water transmission pipeline. The 859-kilometre project will have a transmission capacity of 685,000 cubic metres a day (cm/d). Vision Invest was selected as the preferred bidder last December; however, more than eight months later, an official developer’s agreement has not yet been signed.

    Similarly, the Arana and Hadda independent sewage treatment plant (ISTP) projects have yet to reach the financial close originally targeted for the second quarter. The two schemes will provide a combined treatment capacity of 350,000 cm/d.

    Delays extend further down the procurement pipeline. The latest developer bid deadline for the estimated $150m Riyadh East ISTP is 29 September, almost a year after the request for proposals (RFP) was issued in October 2025.

    Procurement for the main contracts for the Jubail-Buraidah and Ras Mohaisen-Baha-Mecca independent water transmission system projects could also slip into 2027, amid delivery-model changes by Water Transmission Company.

    New awards

    The market received a boost in September when Saudi Arabia’s National Water Company (NWC) announced it had signed a SR1.3bn ($347m) deal with a Saudi-Chinese consortium for package 10 of its long-term operations and maintenance programme.

    The consortium – comprising China’s Jiangsu United Water Technology and Saudi-based Armada Holding – will rehabilitate, operate and maintain nine sewage treatment plants (STPs) with a combined design capacity of more than 337,000 cm/d. Based on the latest procurement timeline, it is unclear whether the selected consortium for package 11 will be formally announced this year. Packages 12 and 14 remain under tender while package 16 is next in line, with its RFP not expected to be issued before November.

    NWC is the second-largest awarding entity by value in 2026, accounting for $1.09bn, or about 28% of the total. Saudi Aramco is the largest, with $2.15bn, meaning the two organisations account for more than 82% of awards so far this year.

    Aramco’s activity has been led by two major oil field developments. In June, it awarded the $1.5bn Safaniya onshore surface facilities project: package 1 to a joint venture of Tecnimont and Consolidated Contractors Company. The package includes a water treatment and injection plant supporting upstream production.

    It also awarded the second phase of its Zuluf water treatment project to a joint venture of Almar Water Solutions and AlJomaih Energy & Water. The project will add a 308,000-cm/d treatment facility at Tanajib in the Eastern Province, supplying water for injection at the offshore Zuluf oil field.

    The concentration of awards in industrial projects this year has been notable. Against the slowdown in municipal water infrastructure procurement, much of the value awarded so far has been linked to the water requirements of oil and gas and mining developments.

    The third-largest award is the $350m Taif Ar Rjum water pipeline project, being developed by Saudi Arabian Mining Company (Maaden) in Mecca. The project will support the Ar Rjum gold mining and processing facility and is being developed under a build-own-operate-transfer model. 

    By project type, treatment projects make up the largest share of awards, at $2.85bn or about 72% of the total. Transmission projects account for $980m and cooling projects for a further $110m, while no major desalination or water storage contracts have been awarded so far this year.

    Project pipeline

    The slowdown in awards appears to reflect the timing of projects moving through procurement rather than a fundamental weakening in demand for water infrastructure.

    Saudi Arabia continues to face rising demand for desalination, wastewater treatment and water transmission as population growth and industrial expansion drive demand for water.

    Sharakat, formerly Saudi Water Partnership Company, set out the next phase of the kingdom’s water investment programme in its latest seven-year statement, published in March.

    The plan points to a significant expansion in desalination capacity. Capacity from Sharakat-procured projects is expected to increase from about 3.88 million cm/d in 2025 to roughly 7.18 million cm/d by 2031.

    The increase will be supported by seven new independent water plants (IWPs) with a combined capacity of about 2.8 million cm/d, in addition to projects already operating, under construction or in procurement.

    However, several of the planned projects have yet to move into active procurement, while others have seen their expected timelines pushed back.

    Among the schemes affected are the Ras Al-Khair, Tabuk, Shuqaiq and Jizan IWPs, which have all progressed through prequalification, but have seen changes to their expected procurement schedules.

    The largest is phase two of the Ras Al-Khair IWP, a 600,000-cm/d reverse osmosis desalination plant that has been in development for more than a decade.

    The revised schedule indicates that the $400m Al-Shuqaiq 4 IWP is expected to be the first of the seven new plants to reach commercial operation. Its main contract had been expected to be tendered later this year, but it is now understood that the first RFP will not be issued until early 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19466739/main.gif
    Mark Dowdall
  • Kuwait grants loan for GCC grid extension study

    8 September 2026

    The Kuwait Fund for Arab Economic Development has signed a KD200,000 ($647,000) grant agreement with the GCC Interconnection Authority (GCCIA) to finance a feasibility study on extending the Gulf power grid to electricity networks outside the GCC.

    The agreement was signed on 3 September by Ahmed Bin Ali Al-Ibrahim, CEO of the GCCIA, and Kuwait Fund acting director general Rashid Al-Bader.

    The study will assess opportunities to expand the GCC power interconnection system to neighbouring countries. It will examine their electricity requirements and the technical and economic feasibility of connecting their national grids to the Gulf network.

    The Kuwait Fund did not identify the countries or potential interconnection routes. However, it is understood that the study will identify potential phases for future expansion, determine priority projects and assess the most appropriate interconnection options based on technical and economic criteria.

    It will cover the proposed project’s main components, costs, implementation arrangements and expected timeframe. The study will also assess the potential economic and social benefits for GCC member states and connected countries, as well as how the GCC network would operate alongside neighbouring national grids.

    A preliminary assessment of the project’s potential environmental and social impacts will also be carried out, together with proposed mitigation measures.

    The Kuwait Fund has previously provided three loans worth a combined KD78m ($252m) to GCCIA to support expansion of the GCC power interconnection system and its connection to southern Iraq’s electricity grid.

    In August 2025, the fund announced two loans worth KD70m ($224m) for the expansion of the Gulf Power Interconnection Project. The financing included support for the Al-Wafra 400kV substation and infrastructure connecting Kuwait’s grid with Iraq. 

    The Al-Wafra substation facilitates electricity exchanges and enables Kuwait to access surplus power available through the GCC interconnection system.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461053/main.jpg
    Mark Dowdall
  • Chinese firm to set up $300m anode facility in the UAE

    8 September 2026

    Beijing-headquartered Sunstone Development has signed a memorandum of understanding (MoU) with the UAE Ministry of Investment to develop an anode production facility in the UAE, with an estimated investment of about $300m.

    The MoU follows Sunstone’s December 2025 joint-venture agreement with Emirates Global Aluminium (EGA) to build the project.

    Upon completion, the plant is expected to replace most of EGA’s current anode imports and support the UAE’s ambition to become one of a limited number of global anode-exporting countries, aligning with the Make It In The Emirates initiative and Operation 300bn.

    The ministry said the agreement reflects its role in helping strategic investors navigate the UAE’s investment ecosystem and convert commitments into long-term operations, in line with the National Investment Strategy 2031.

    By localising a key stage in the aluminium value chain, the facility will reduce reliance on imported anodes, enhance the competitiveness of the UAE aluminium sector and support wider economic diversification.

    The Ministry of Investment and Sunstone will establish a joint working group, chaired by the ministry, to oversee project delivery.

    The project is expected to create skilled employment opportunities for UAE nationals and residents, while strengthening domestic manufacturing capacity and industrial capabilities.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461120/main.jpg
    Yasir Iqbal
  • Riyadh tenders Expo 2030 Souq areas package

    8 September 2026

     

    Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has tendered a contract to deliver the Souq areas within the Expo site.

    The tender was floated on 30 July, with a submission deadline of 9 October.

    The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).

    The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works. 

    The precincts comprise:

    • Precinct 1 – The Icon: 41,417 sq m
    • Precinct 2 – Place & Planet: 62,306 sq m 
    • Precinct 3 – Culture of Wisdom: 67,112 sq m  
    • Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m  
    • Precinct 5 – Adaptation & Innovation: 82,358 sq m

    The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.

    The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, providing a central connection between the site’s iconic and thematic assets.

    The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.

    Site progress

    Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.

    Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City (RCRC) awarded a design-and-build contract for the construction of a new metro station catering to the Expo 2030 site.

    In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Alyamama Company.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.

    That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19457171/main.jpg
    Yasir Iqbal
  • Powering the next chapter with nuclear energy

    8 September 2026

    Commentary
    Colin Foreman
    Editor

    Nuclear energy is increasingly being viewed as essential around the world. It offers a non-CO2-emitting, steady baseload at a time when governments have made net-zero commitments. 

    In the Gulf, the UAE has spent the past 15 years building the Middle East’s first commercial nuclear plant, now supplying about a quarter of the country’s electricity. What is new is the breadth of ambition beyond Abu Dhabi. The civil nuclear cooperation deal signed between Saudi Arabia and the US in July is the most significant step in the kingdom’s nuclear programme for several years, and it lands as the region moves decisively towards atomic power.

    The logic is clear. Electricity demand from industry, desalination and digital infrastructure is climbing, and governments want reliable low-carbon supply to meet it. Saudi Arabia is targeting up to 17GW of nuclear capacity by 2040. Its first plant at Khor Duwaiheen, comprising two 1.4GW reactors, represents only about a sixth of that goal, which points to a programme rather than a one-off.

    What is new is the breadth of ambition beyond Abu Dhabi

    The opportunity extends well beyond reactors. The UAE’s nuclear programme shows the scale of the economic impact. More than 2,000 local firms secured contracts worth over $6.7bn supporting construction, operations and maintenance. 

    Saudi Arabia’s ambitions reach further still, into small modular reactors, domestic uranium and elements of the fuel cycle. At the same time, Bahrain is studying a modular plant to power its industrial base, and Egypt’s 4.8GW El-Dabaa project is already under construction, with first generation expected in 2028.

    For contractors, engineers and financiers, this is the beginning of a projects market that will unfold over decades. The reactor awards will grab the headlines, but the supporting ecosystem, from regulation and fuel supply to workforce development, is where much of the value lies.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461185/main.gif
    Colin Foreman