Megaprojects will weigh on Saudi utility capacity
2 November 2023
Commentary
Jennifer Aguinaldo
Energy & technology editor
An overall projects pipeline worth nearly a trillion dollars will require Saudi Arabia to boost its power generation and water production capacity.
The kingdom expects its population to reach 50 million by 2030, about 37 per cent higher than the current population of over 36 million.
Neom's The Line alone is envisaged to have a population of 9 million by 2030.
The kingdom also aims to attract up to 150 million tourists by 2030. The plan does not state how much of this will be international or domestic tourists, although its latest figure of 93.5 million last year comprised 82 per cent domestic tourists, with international tourists accounting for the rest.
Saudi Arabia started responding to the need to accelerate the deployment of additional power generation capacity this year.
The contracts for four combined-cycle gas turbine (CCGT) independent power projects (IPPs) with a total combined capacity of 7,200MW are expected to be awarded imminently. These are the first thermal IPPs to be procured by the kingdom since 2016.
The contracts for renewable energy IPPs with a total combined capacity of 3,300MW under the fourth round of its National Renewable Energy Programme (NREP) are due for award.
The Saudi sovereign wealth fund also did its bit by awarding three major solar photovoltaic (PV) projects, which have a total combined capacity of 4,550MW, this year.
The procurement process for similarly-sized CCGT plants is expected to start early next year, along with the fifth found of NREP.
The state water offtaker, Saudi Water Partnership Company (SWPC), publishes an annual seven-year planning statement, which includes a capacity procurement plan for water desalination, treatment, reservoir and transmission projects.
This provides investors, developers and contractors with a clear view of the projects coming to the market over a specified period.
A source told MEED earlier this year that there are plans for the power offtaker, Saudi Power Procurement Company (SPPC), to issue a similar capacity planning document. However, it is unclear when the document will be made public.
There are also indications that the kingdom could update its renewable energy installed capacity target, which currently stands at 58,700MW by 2030. The kingdom's renewable energy installed capacity stands at roughly 842MW.
In parallel, the largest gigaproject, Neom, aims to be powered 100 per cent by renewable energy by 2030, with nearly every major development looking at energy-efficient alternatives for power and water supply.
No doubt Saudi Arabia is approaching a golden era in terms of power and water capacity building, not to mention a long-standing plan to introduce nuclear power to its electricity production mix as part of a plan to decarbonise its electricity sector.
The tricky part will be developing a formula that can accurately forecast medium- to long-term demand, which will require clear and reliable input in terms of expected population growth, historical demand growth, and the production capacity and retirement schedule of its existing fleets.
The expansion of electricity exchange and trade with its GCC neighbours, Egypt and Iraq, among other jurisdictions, as well as the adoption of the so-called distributed energy resources such as electric vehicles, add a further layer of complication not seen in the past to the kingdom's future capacity procurement plans.
Exclusive from Meed
-
Read the May 2026 MEED Business Review30 April 2026
-
Algeria extends bid deadline for stalled power plant30 April 2026
-
Dewa announces new record for power reliability30 April 2026
-
Riyadh tenders PMC deal for major sports arena30 April 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Read the May 2026 MEED Business Review30 April 2026
Download / Subscribe / 14-day trial access The regional war – and resulting disruption to oil and gas shipping – has triggered a major global energy security shock that is likely to recalibrate long-term decisions on how energy is produced and consumed.
The effective closure of the Strait of Hormuz is exposing the vulnerability of Middle East supply chains and pushing import-dependent countries to strengthen energy security by expanding domestic fossil fuels, speeding up nuclear projects, and investing in renewables and storage.At the same time, higher prices are encouraging producers unencumbered by reliance on the Strait to boost output.
Like the oil shocks of the 1970s, the conflict is likely to have lasting effects, reshaping energy policies and partnerships and accelerating diversification away from existing arrangements. Read more here.
The conflict is also undermining the business case for Middle East liquefied natural gas (LNG) projects, as prices rise, demand drops and confidence in the reliability of the region’s suppliers is eroded.
May’s market focus is on the UAE, where disruption from the Iran war has challenged every assumption behind the country’s non-oil model.
This edition also includes our industry report on Gulf capital markets, as well as analysis on the region’s initial public offering market.
In the latest issue, we explore why regional banks are feeling the strain despite strong buffers; consider why force majeure offers no shield against construction breaches; examine the Public Investment Fund’s 2026-30 strategy and talk to Estelle Brachlianoff, CEO of water infrastructure operator Veolia.
We hope our valued subscribers enjoy the May 2026 issue of MEED Business Review.

Must-read sections in the May 2026 issue of MEED Business Review include:
> AGENDA: War in the Middle East recalibrates global energy markets
> REGIONAL LNG: War undermines business case for Middle East LNGINDUSTRY REPORT:
Gulf capital markets
> Damage avoidance frames debt issuance
> Regional IPO market dries up amid war> INTERVIEW: Desalination holds steady amid tensions, says Veolia CEO
> LEGAL: Force majeure will not cure pre-existing construction industry breaches
> BANKS: GCC banks to feel the strain despite strong buffers
> PIF STRATEGY: Public Investment Fund approves 2026-30 strategy
> UAE MARKET FOCUS:
> COMMENT: Conflict tests UAE diversification
> GVT &: ECONOMY: UAE economy absorbs multi-sector shock
> BANKING: UAE banks ready to weather the storm
> ATTACKS: UAE counts energy infrastructure costs
> UPSTREAM: Adnoc builds long-term oil and gas production potential
> DOWNSTREAM: Adnoc Gas to rally UAE downstream project spending
> POWER: Large-scale IPPs drive UAE power market
> WATER: UAE water investment broadens beyond desalination
> CONSTRUCTION: War casts shadow over UAE construction boom
> TRANSPORT: UAE rail momentum grows as trade routes face strain
> DATABANK: UAE GDP projection corrects on conflict> MEED COMMENTS:
> War takes a rising toll on Kuwait’s oil sector
> Libya budget approval could lead to surge in oil and gas projects
> Masdar’s move abroad will not be the last
> Saudi Landbridge finds its moment in Gulf turmoil> GULF PROJECTS INDEX: Gulf index plateaus despite ceasefire
> MARCH 2026 CONTRACTS: Middle East contract awards
> ECONOMIC DATA: Data drives regional projects
> OPINION: The road to hell is paved with gold
> BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts
To see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16623768/main.gif -
Algeria extends bid deadline for stalled power plant30 April 2026
Algeria’s state-owned electricity and gas utility Sonelgaz has extended a deadline for contractors to submit expressions of interest for the construction of the 1.2GW Djelfa combined-cycle power plant.
The project is being procured through Sonelgaz’s power generation subsidiary, Societe Algerienne de l’Electricite et du Gaz – Production de l’Electricite (SPE).
In March, MEED reported that the utility was seeking contractors to complete works at the existing Djelfa plant, including the remaining construction, the supply of missing equipment and the assessment of installed equipment.
The original bid submission deadline for prequalification was 7 April. The new deadline is 5 May.
The tender is open to both local and international companies, and will be conducted in three phases: prequalification, preliminary technical assessment, and final technical and financial submission.
The retender follows earlier plans to complete the project through a Chinese consortium comprising China Energy Engineering Group Company, Northwest Electric Power Design Institute and Anhui Electric Power Construction Company.
This proposal was made after Spanish contractor Duro Felguera halted work on the project in June 2024.
According to MEED Projects, construction works had progressed to 72% at the time of the suspension.
It is understood that an agreement in principle was then reached to transfer the remaining works to the Chinese group after the Spanish firm entered a pre-bankruptcy phase in December 2024.
A company statement at the time said: “The Chinese group is committed to completing the plant construction, with commissioning scheduled to start in the ninth month following the final agreement.”
However, in October 2025, it was revealed that the attempt to transfer the project to a consortium of Chinese companies had failed, leaving the Spanish firm with an official demand to pay €413m in compensation to Sonelgaz.
This was revealed via a lengthy report containing a restructuring plan sent by Duro Felguera to creditors in Spain and the Madrid Financial Markets Authority.
Gas-fired power plants
Located in Djelfa province, the project remains a key part of Algeria’s power generation expansion plans.
Sonelgaz has been seeking contractors to build a separate 1.2GW combined-cycle gas-fired power plant in Aldrar since last April.
The most recent deadline extension was 29 April.
According to recent reports, Algeria has also begun construction of a power generation plant in El-Aouinet, with a total installed capacity of 1,406MW.
The combined-cycle gas turbine plant is being developed in partnership with China National Electric Engineering Company.
Gas-fired combined-cycle plants continue to account for the majority of Algeria’s electricity generation capacity. Data from MEED Projects indicates that more than 5,000MW of oil- and gas-fired power capacity is currently in the execution phase.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16623787/main.jpg -
Dewa announces new record for power reliability30 April 2026
Dubai Electricity & Water Authority (Dewa) has announced that it set a new world record for the lowest electricity customer minutes lost (CML), at 0.82 minutes a year in 2025.
The figure is equivalent to about 49 seconds of annual outage per customer. It improves on the utility’s previous record of 0.94 minutes in 2024, a reduction of around 13%.
Dewa said it has reduced CML in Dubai from 6.88 minutes a year in 2012 to 0.82 minutes in 2025, significantly lower than the average of about 15 minutes recorded by leading electricity utilities in the European Union.
The smart grid is a central component of Dewa’s strategy to improve reliability and efficiency. The programme is being implemented with total investments of AED7bn up to 2035.
One of the key initiatives of the programme is the Automatic Smart Grid Restoration System, which enables remote, round-the-clock control and monitoring.
Dewa currently has tenders out for several power and water infrastructure projects in the emirate. These include at least four Glass Reinforced Epoxy (GRE) water transmission pipeline projects.
According to regional projects tracker MEED Projects, Dewa awarded $1.1bn-worth of new power and water contracts in 2025. Contract awards had previously reached $2.6bn in 2024, and $4bn in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16623721/main.jpg -
Riyadh tenders PMC deal for major sports arena30 April 2026

Saudi Arabia’s Sports Boulevard Foundation has tendered a contract inviting firms to bid for project management consultancy (PMC) services for the Global Sports Tower in the Athletics District of the Sports Boulevard development in Riyadh.
The tender was issued on 8 April, with a bid submission deadline of 10 May.
The 130-metre-tall Global Sports Tower will cover an area of 84,000 square metres and will include more than 30 sports facilities. The tower will feature the world’s tallest indoor climbing wall at 98 metres and a 250-metre running track.
Earlier this week, MEED reported that the Sports Boulevard Foundation is preparing to award the main construction contract for the Global Sports Tower. MEED understands that bid evaluation has reached an advanced stage and the contract is likely to be awarded by the end of May.
MEED reported in May last year that design work on the tower had been completed. Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud approved the designs in 2024.
The Sports Boulevard development runs across Riyadh from east to west and, once complete, is set to be the world’s longest park spanning more than 135 kilometres.
The development will be spread across several districts, including Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco, as well as Sands Sports Park.
The large-scale project aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.
Sports Boulevard, which will feature 4.4 million sq m of public realm and landmark buildings, will also be home to the Centre for Cinematic Arts and a 2,000-seat amphitheatre.
The development will provide more than 2.3 million sq m of mixed-use commercial, residential, and retail assets, along with sports facilities around the park, known as Linear Park.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16622287/main.jpeg -
Contractors submit Saudi Arabia phosphate rail track bids30 April 2026

Saudi Arabian Railways (SAR) received bids from contractors on 27 April for a multibillion-riyal tender to double the tracks on the existing phosphate transport railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the kingdom’s Eastern Province.
The tender – covering the second section of the track-doubling works and spanning more than 150 kilometres (km) – was issued on 9 February.
This follows SAR receiving bids on 1 February for the project’s first phase, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.
The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track. It also includes support for signalling and telecommunications systems.
The tender notice was issued in late November.
Switzerland-based engineering firm ARX is the project consultant.
MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line. Other packages anticipated to be tendered shortly include the depot and systems packages.
In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.
Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.
Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.
State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16622526/main.jpg
.gif)