Acwa Power widens equity gap in power developer league

2 October 2023

 

The equity gap between Saudi utility developer Acwa Power and the other private utility developers in the GCC region has continued to widen, according to MEED’s annual GCC power developer ranking.

Acwa Power’s net capacity reached 13,340MW. This has doubled its lead to 67 per cent over France’s Engie, whose net capacity of 7,987MW has remained unchanged.

Over the past 12 months, power-purchase agreements were signed for six solar independent power producer (IPP) projects, as well as for a multi-utility public-private partnership contract and a cogeneration plant.

The seven contracts have a total combined power generation capacity of more than 8,000MW.

Acwa Power gained more than 2,900MW in net capacity over this period. This was due in large part to a 35 per cent equity share in the 2,060MW Shuaibah 2 solar power project and a 50 per cent shareholding in each of the Saad 2, Ar-Rass 2 and Kahfah solar photovoltaic (PV) projects. 

These contracts were procured by the kingdom's Public Investment Fund (PIF) through the Saudi renewable energy price discovery scheme.

Notably, the 600MW Shuaibah 1 solar IPP scheme, which was publicly tendered and awarded to an Acwa Power-led consortium under the second round of the National Renewable Energy Programme (NREP) in 2021, has been combined with the PIF’s Shuaibah 2.

Under the final scheme, which reached financial close this year, Acwa Power’s shares in Shuaibah 1 decreased from 50 per cent to 35 per cent. The shares of its partners Gulf Investment Corporation and Al-Babtain, which originally maintained 30 per cent and 20 per cent, respectively, have been bought by PIF subsidiary the Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco).

As with Engie, the net and gross capacities of Japanese firms Marubeni, Mitsui, Sumitomo and Jera also remained unchanged, with no new contract wins in the period.

Ranked 10th in the previous year’s listing, France’s EDF rose three spots this year to claim seventh place, which was previously held by Korea Electric Power Corporation (Kepco).

EDF’s rise came as a result of winning contracts for two major schemes. It was selected together with South Korea’s Korea Western Power Company (Kowepo) to develop Oman’s 500MW Manah 1 solar IPP project, and was also awarded a multi-utility contract with the UAE’s Abu Dhabi Future Energy Company (Masdar) for the Amaala development in Saudi Arabia, which includes a 250MW solar power farm.

EDF overtook Kepco despite the South Korean firm’s successful bid for the Jafurah cogeneration plant, where it maintains a 60 per cent equity. The scheme’s power generation plant has a capacity of 320MW.

Singapore’s Sembcorp and China’s Jinko Power, which comprise the team that won the Manah 2 solar IPP contract in Oman, occupy the ninth and 10th spots, respectively.

Saudi utility developer Aljomaih Energy & Water Company relinquished its 10th spot last year.

Power tariffs have scope to improve

A different view

Saudi Arabia’s renewable energy price discovery tool is becoming a potential game-changer for the competitive landscape of GCC power developers.

It allows Acwa Power to submit a proposal to match the most recent prices obtained through each round of the NREP public tendering process, which is overseen by the state-backed principal buyer, Saudi Power Procurement Company (SPPC).

Under the price discovery scheme, the PIF will only invite other developers to bid for a contract if Acwa Power fails to match prices achieved through the public tenders.

Acwa Power has so far won all five of these contracts, which have a total combined capacity of 8,110MW.

Since the PIF is tasked with procuring 70 per cent of Saudi Arabia’s 58,700MW renewable energy capacity target by 2030, the Saudi sovereign wealth vehicle is expected to procure a further 32,000MW of renewable capacity over the coming years using the price discovery scheme.

Given the scale of the PIF’s programme, and the extent to which it has expanded Acwa Power’s renewables portfolio this year, a separate league table that includes only IPPs and independent water and power producer (IWPP) projects that have been publicly tendered, or simultaneously tendered to a pool of qualified private utility developers, offers interesting insights.

Excluding the PIF contracts reveals that the ranking of the private utility developers based on their net capacity – or the capacity commensurate to a developer’s equity shareholding in each power generation asset – is unchanged. Acwa Power remains at the top, with a total equity capacity of more than 9,800MW, compared to Engie’s nearly 8,000MW.

However, their gross capacity rankings reverse when the PIF contracts are excluded. Engie leads by 4 per cent in terms of gross capacity, or the total capacity of power plants that they are developing alone or with consortium partners.

Gas revival

No new gas-fired IPP or IWPP projects have been let in the GCC since 2021, when most principal buyers and utilities began to focus on increasing their renewable energy capacity in line with their countries’ decarbonisation agendas.

With the exception of the UAE's Fujairah F3 and Saudi Aramco’s Tanajib and Jafurah cogeneration plants, solar and wind power plants have accounted for the majority of private power generation capacity that has been procured since 2020.

This is set to change in the next 12-24 months as renewed demand for combined-cycle gas turbine (CCGT) plants is driven by the need to decommission old fleets that burn liquid fuel, or to replace expiring baseload capacity.

As of September this year, gas-fired power plants account for approximately 60 per cent of the GCC region's planned power generation plants that are likely to be awarded in the next 24 months, according to MEED research. 

The bid evaluation process is under way for four gas-fired IPPs in Saudi Arabia with a total combined capacity of 7,200MW. These are the first gas-fired IPP schemes to be procured by the kingdom since 2016.

A further three IWPP schemes – Kuwait's Al-Zour North 2 & 3 and Al-Khiran 1 and Qatar’s Facility E – are in the procurement stage. These schemes have a total combined power generation capacity of 6,800MW.

Next year, SPPC is expected to begin the procurement process for two gas-fired IPPs: the PP15 in Riyadh and another in Al-Khafji. Each is expected to have power generation capacity of 3,600MW.

Abu Dhabi’s Emirates Water & Electricity Company (Ewec) is also expected to initiate the procurement process for two CCGT plants with a total combined capacity of 2,500MW before the end of 2023.

Renewable arena

The revival of gas-fired schemes will not necessarily come at the expense of renewables, however.

The region’s largest market has ramped up its issuance of solar and wind tenders over the past 12 months and is expected to sustain or even accelerate the pace of its renewables procurement.

Saudi Arabia needs to procure at least 43,000MW of renewable energy capacity through public tenders and direct negotiations over the next six years to meet its 2030 target. This equates to about 7,200MW a year – twice its current average.

Overall, the future strength of the market for private utility developers is ensured by a growing clientele in Saudi Arabia that includes Neom and its subsidiary Enowa, in addition to the utilities in the other five GCC states, and the large conglomerates and organisations that aim to build captive power plants.

A case in point is the 35,000MW of solar and wind energy projects are in the pre-development stage for Neom, which aims to be powered 100 per cent by renewable energy by 2030.

Abu Dhabi also plans to procure at least 1,500MW of solar PV capacity annually over the next 10 years, in line with its goals for decarbonising its electricity system.

Developers’ dilemma

A Dubai-based executive with one of the international developers active in the region says: “It has been a very busy year for us. If all of these plans come through in the next 12-24 months, it will be even busier.”

The executive is unsure whether all the planned gas-fired projects will materialise, however. “We have been here before, and some of these projects have experienced major delays in the past for reasons that are not even related to decarbonisation or net-zero targets.”

Given the GCC states' carbon emissions reduction targets and the recent easing of supply chain constraints, solar and wind IPPs appear to offer greater certainty for utility developers, many of which are also beholden to internal decarbonisation targets that include a reduction of their existing thermal fleets.

The contracts for five solar and three wind IPPs in the region are expected to be awarded soon.

Masdar has outpriced Acwa Power for the 1,800MW sixth phase of Dubai’s Mohammed bin Rashid al-Maktoum Solar Park project. A team of EDF and Kowepo has also submitted the lowest bid for the 1,500MW Al-Ajban solar PV IPP in Abu Dhabi.

In addition, SPPC has shortlisted bidders for two solar PV IPPs with a total combined capacity of 1,500MW under the NREP fourth round. It also expects to receive bids soon for three wind IPPs with a total combined capacity of 1,800MW.

Tenders for the NREP’s fifth round and Abu Dhabi’s fourth utility-scale solar PV farm are also expected imminently.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11143965/main.gif
Jennifer Aguinaldo
Related Articles
  • SAR tenders design review consultancy for GCC rail link

    18 September 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia Railways (SAR) has issued a request for proposals (RFP) for a design management and review consultant to oversee engineering works on the GCC railway network, the latest step in advancing the long-delayed regional rail link.

    The RFP was issued on 9 September, with a submission deadline of 18 October.

    The tender seeks a consultant to manage, audit and verify deliverables produced by SAR's separately appointed design services consultant, rather than carry out the design itself. The tendering for the design services consultancy is currently in progress.

    Construction will be tendered separately through competitive bidding once designs are approved.

    The GCC railway will run for about 672 kilometres (km) inside Saudi Arabia, linking the kingdom's existing network to Kuwait, Qatar, the UAE and Bahrain, with four sections of about 141km, 200km, 151km and 21km, respectively.

    The line is planned as a single-track, non-electrified corridor for mixed freight and passenger traffic, with a maximum axle load of 32.4 tonnes and passing loops for bidirectional working.

    The appointed consultant will develop a design management and review plan covering governance, interdisciplinary coordination and stage-gate approvals, and will issue formal review and audit reports against SAR's requirements and international standards.

    The scope also covers stakeholder engagement, interface management and oversight of land acquisition activity tied to the design consultant's land acquisition plan.

    Key design stages are expected to take about 16 months: four months for concept design, six for preliminary design and six for issued-for-construction design, each with four weeks of contingency.

    SAR has asked bidders to mobilise a core team from day one. These must include a project director, engineering and design manager, stakeholder manager and lead document controller, all based at SAR's offices, with minimum experience thresholds ranging from three years for junior operators up to 25 years, including 15 in rail, for the project director role.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to cover about 2,186km in total.

    The route length within each member state is as follows:

    • UAE – 684km
    • Saudi Arabia – 672km
    • Oman – 306km
    • Qatar – 283km
    • Kuwait – 145km
    • Bahrain – 36km

    The railway is designed for passenger trains travelling at 220 kilometres an hour (km/h) and freight trains operating at 80km/h–120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19783331/main.gif
    Yasir Iqbal
  • Tender issued for Libyan gas project

    17 September 2026

    An invitation to bid has been issued for a contract to conduct environmental assessments for the project to expand the Mellitah oil and gas complex in Libya.

    The bid submission deadline is 2pm today (17 September) Libyan time.

    The scope of the project includes provision of:

    • An environmental baseline study (EBS)
    • An environmental impact assessment (EIA)
    • An environmental management plan (EMP)

    The client is Mellitah Oil & Gas (MOG), which is a joint venture of Italy’s Eni and Libya’s National Oil Corporation (NOC).

    MOG is based in Tripoli and operates both onshore and offshore oil and gas facilities.

    The joint venture owns and operates six major oil and gas fields across the North African country.

    According to the tender documents, the company that is awarded the contract will need to prepare environmental management measures in compliance with:

    • Libyan environmental legislation
    • Ministry of Environment requirements
    • NOC environmental guidelines
    • Applicable international environmental standards and best practices

    The expansion of the Mellitah oil and gas complex is part of a project estimated to be worth $8bn.

    The wider project is known as the Mellitah Complex Expansion & CO2 Management Integrated Development Project.

    It has six main packages:

    • Onshore package
    • Offshore Structure A
    • Offshore Structure E
    • Subsea pipeline package
    • Site preparation work
    • Carbon capture and storage facility

    Security issues and political instability have been a major problem for Libya’s oil and gas sector since the country’s civil war started in 2011.

    Earlier this month, the Mellitah oil and gas complex was forced to shut down temporarily due to a protest over deteriorating public services.

    The existing onshore complex includes housing, processing units, storage facilities and export facilities.

    It also serves as the launch point for the Greenstream pipeline, which delivers Libyan gas directly to Italy.

    The planned expansion of the complex will involve:

    • Construction of a new fourth gas processing train
    • Construction of a third condensate train
    • Construction of a third natural gas liquids fractionation train
    • Construction of a fourth sulphur recovery unit train
    • Installation of a hydrogen sulphide enrichment unit
    • Installation of a sulphur recovery unit
    • Construction of other associated facilities

    The Mellitah complex is located about 100 kilometres west of Tripoli and is a key energy facility in the west of the country.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748920/main.png
    Wil Crisp
  • Nakheel awards $218m Dubai Islands buildings deal

    17 September 2026

    Register for MEED’s 14-day trial access 

    Dubai-based developer Nakheel, now part of Dubai Holding, has awarded a main construction contract worth more than AED800m ($218m) for phases one and three of Bay Grove Residences at Dubai Islands.

    The contract was awarded to the local firm Metac General Contracting Company.

    It covers the construction of 537 apartments, comprising one- to four-bedroom units, across seven residential buildings.

    Phase one includes 296 units in four buildings, while phase three comprises 241 units across three buildings.

    The works are scheduled for completion in late 2028.

    Bay Grove Residences will ultimately comprise 1,154 homes across 15 buildings. Planning is under way for the remaining 617 homes in phases two and four, with further contract awards expected.

    In August last year, Nakheel awarded a AED2.6bn ($708m) contract to Abu Dhabi-based Fibrex Contracting to build the Bay Villas project at Dubai Islands. The contract includes constructing 636 villas.

    In April this year, another AED527m ($143m) contract was awarded to local firm Al-Nasr Contracting Company to construct the primary infrastructure and utilities works on Island B at the development.

    The Dubai Islands development consists of five islands spanning 18.6 square kilometres. It features more than 59 kilometres (km) of waterfront and 20km of beaches, as well as parks, golf courses, promenades and cycling paths.

    The offshore island project gained renewed momentum in 2022, when Nakheel unveiled a new masterplan and rebranded it as Dubai Islands.

    The reclaimed islands were originally part of the Palm Deira project, which was partially completed before being put on hold in 2008.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748850/main.jpg
    Yasir Iqbal
  • Aldar and Mubadala acquire Masdar City Square

    17 September 2026

    Abu Dhabi-based sovereign wealth fund Mubadala Investment Company and local developer Aldar have completed the acquisition of Masdar City Square at Masdar City, in a transaction valued at AED918m ($250m).

    The deal was executed through their joint venture established in 2024.

    Masdar City Square comprises more than 47,000 square metres (sq m) of net leasable area across seven office buildings.

    Completed in Q1 2026, the development is 99% occupied. Tenants include Taqa, the Department of Energy, Emirates College and the Mohamed Bin Zayed University of Artificial Intelligence.

    The transaction expands the joint venture’s real estate portfolio in Masdar City, which is now valued at AED4.7bn ($1.3bn).

    Masdar City is one of the region’s leading hubs for clean energy, artificial intelligence, advanced research and sustainable urban development.

    The joint venture acquired The Link project at Masdar City for AED654m ($178m) in April.

    Comprising about 32,000 sq m of net leasable area across five buildings, The Link is fully leased to a portfolio of major tenants, including Abu Dhabi Future Energy Company (Masdar) and the Mohamed Bin Zayed University of Artificial Intelligence.

    The asset includes Grade A, Leed Platinum office space, a net-zero-energy headquarters building, a multi-use hall and residential accommodation, supporting its position as a high-performing, integrated component of Masdar City.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19748241/main5814.png
    Yasir Iqbal
  • Neom tenders Oxagon highway contract

    17 September 2026

     

    Saudi Arabia’s Neom has tendered a design-and-build contract covering permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also covers one bridge and three interchanges.

    The project duration is 22 months.

    Contractors have been given until 21 September to submit their proposals.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED exclusively reported in August 2025 that contractors had submitted responses to the expressions of interest notice that Neom had issued earlier that month.

    The project is expected to support the movement of cargo vehicles from Duba Port to other parts of the country and the wider region.

    Neom tested a pilot initiative last year by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19746896/main.gif
    Yasir Iqbal