Acwa Power widens equity gap in power developer league

2 October 2023

 

The equity gap between Saudi utility developer Acwa Power and the other private utility developers in the GCC region has continued to widen, according to MEED’s annual GCC power developer ranking.

Acwa Power’s net capacity reached 13,340MW. This has doubled its lead to 67 per cent over France’s Engie, whose net capacity of 7,987MW has remained unchanged.

Over the past 12 months, power-purchase agreements were signed for six solar independent power producer (IPP) projects, as well as for a multi-utility public-private partnership contract and a cogeneration plant.

The seven contracts have a total combined power generation capacity of more than 8,000MW.

Acwa Power gained more than 2,900MW in net capacity over this period. This was due in large part to a 35 per cent equity share in the 2,060MW Shuaibah 2 solar power project and a 50 per cent shareholding in each of the Saad 2, Ar-Rass 2 and Kahfah solar photovoltaic (PV) projects. 

These contracts were procured by the kingdom's Public Investment Fund (PIF) through the Saudi renewable energy price discovery scheme.

Notably, the 600MW Shuaibah 1 solar IPP scheme, which was publicly tendered and awarded to an Acwa Power-led consortium under the second round of the National Renewable Energy Programme (NREP) in 2021, has been combined with the PIF’s Shuaibah 2.

Under the final scheme, which reached financial close this year, Acwa Power’s shares in Shuaibah 1 decreased from 50 per cent to 35 per cent. The shares of its partners Gulf Investment Corporation and Al-Babtain, which originally maintained 30 per cent and 20 per cent, respectively, have been bought by PIF subsidiary the Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco).

As with Engie, the net and gross capacities of Japanese firms Marubeni, Mitsui, Sumitomo and Jera also remained unchanged, with no new contract wins in the period.

Ranked 10th in the previous year’s listing, France’s EDF rose three spots this year to claim seventh place, which was previously held by Korea Electric Power Corporation (Kepco).

EDF’s rise came as a result of winning contracts for two major schemes. It was selected together with South Korea’s Korea Western Power Company (Kowepo) to develop Oman’s 500MW Manah 1 solar IPP project, and was also awarded a multi-utility contract with the UAE’s Abu Dhabi Future Energy Company (Masdar) for the Amaala development in Saudi Arabia, which includes a 250MW solar power farm.

EDF overtook Kepco despite the South Korean firm’s successful bid for the Jafurah cogeneration plant, where it maintains a 60 per cent equity. The scheme’s power generation plant has a capacity of 320MW.

Singapore’s Sembcorp and China’s Jinko Power, which comprise the team that won the Manah 2 solar IPP contract in Oman, occupy the ninth and 10th spots, respectively.

Saudi utility developer Aljomaih Energy & Water Company relinquished its 10th spot last year.

Power tariffs have scope to improve

A different view

Saudi Arabia’s renewable energy price discovery tool is becoming a potential game-changer for the competitive landscape of GCC power developers.

It allows Acwa Power to submit a proposal to match the most recent prices obtained through each round of the NREP public tendering process, which is overseen by the state-backed principal buyer, Saudi Power Procurement Company (SPPC).

Under the price discovery scheme, the PIF will only invite other developers to bid for a contract if Acwa Power fails to match prices achieved through the public tenders.

Acwa Power has so far won all five of these contracts, which have a total combined capacity of 8,110MW.

Since the PIF is tasked with procuring 70 per cent of Saudi Arabia’s 58,700MW renewable energy capacity target by 2030, the Saudi sovereign wealth vehicle is expected to procure a further 32,000MW of renewable capacity over the coming years using the price discovery scheme.

Given the scale of the PIF’s programme, and the extent to which it has expanded Acwa Power’s renewables portfolio this year, a separate league table that includes only IPPs and independent water and power producer (IWPP) projects that have been publicly tendered, or simultaneously tendered to a pool of qualified private utility developers, offers interesting insights.

Excluding the PIF contracts reveals that the ranking of the private utility developers based on their net capacity – or the capacity commensurate to a developer’s equity shareholding in each power generation asset – is unchanged. Acwa Power remains at the top, with a total equity capacity of more than 9,800MW, compared to Engie’s nearly 8,000MW.

However, their gross capacity rankings reverse when the PIF contracts are excluded. Engie leads by 4 per cent in terms of gross capacity, or the total capacity of power plants that they are developing alone or with consortium partners.

Gas revival

No new gas-fired IPP or IWPP projects have been let in the GCC since 2021, when most principal buyers and utilities began to focus on increasing their renewable energy capacity in line with their countries’ decarbonisation agendas.

With the exception of the UAE's Fujairah F3 and Saudi Aramco’s Tanajib and Jafurah cogeneration plants, solar and wind power plants have accounted for the majority of private power generation capacity that has been procured since 2020.

This is set to change in the next 12-24 months as renewed demand for combined-cycle gas turbine (CCGT) plants is driven by the need to decommission old fleets that burn liquid fuel, or to replace expiring baseload capacity.

As of September this year, gas-fired power plants account for approximately 60 per cent of the GCC region's planned power generation plants that are likely to be awarded in the next 24 months, according to MEED research. 

The bid evaluation process is under way for four gas-fired IPPs in Saudi Arabia with a total combined capacity of 7,200MW. These are the first gas-fired IPP schemes to be procured by the kingdom since 2016.

A further three IWPP schemes – Kuwait's Al-Zour North 2 & 3 and Al-Khiran 1 and Qatar’s Facility E – are in the procurement stage. These schemes have a total combined power generation capacity of 6,800MW.

Next year, SPPC is expected to begin the procurement process for two gas-fired IPPs: the PP15 in Riyadh and another in Al-Khafji. Each is expected to have power generation capacity of 3,600MW.

Abu Dhabi’s Emirates Water & Electricity Company (Ewec) is also expected to initiate the procurement process for two CCGT plants with a total combined capacity of 2,500MW before the end of 2023.

Renewable arena

The revival of gas-fired schemes will not necessarily come at the expense of renewables, however.

The region’s largest market has ramped up its issuance of solar and wind tenders over the past 12 months and is expected to sustain or even accelerate the pace of its renewables procurement.

Saudi Arabia needs to procure at least 43,000MW of renewable energy capacity through public tenders and direct negotiations over the next six years to meet its 2030 target. This equates to about 7,200MW a year – twice its current average.

Overall, the future strength of the market for private utility developers is ensured by a growing clientele in Saudi Arabia that includes Neom and its subsidiary Enowa, in addition to the utilities in the other five GCC states, and the large conglomerates and organisations that aim to build captive power plants.

A case in point is the 35,000MW of solar and wind energy projects are in the pre-development stage for Neom, which aims to be powered 100 per cent by renewable energy by 2030.

Abu Dhabi also plans to procure at least 1,500MW of solar PV capacity annually over the next 10 years, in line with its goals for decarbonising its electricity system.

Developers’ dilemma

A Dubai-based executive with one of the international developers active in the region says: “It has been a very busy year for us. If all of these plans come through in the next 12-24 months, it will be even busier.”

The executive is unsure whether all the planned gas-fired projects will materialise, however. “We have been here before, and some of these projects have experienced major delays in the past for reasons that are not even related to decarbonisation or net-zero targets.”

Given the GCC states' carbon emissions reduction targets and the recent easing of supply chain constraints, solar and wind IPPs appear to offer greater certainty for utility developers, many of which are also beholden to internal decarbonisation targets that include a reduction of their existing thermal fleets.

The contracts for five solar and three wind IPPs in the region are expected to be awarded soon.

Masdar has outpriced Acwa Power for the 1,800MW sixth phase of Dubai’s Mohammed bin Rashid al-Maktoum Solar Park project. A team of EDF and Kowepo has also submitted the lowest bid for the 1,500MW Al-Ajban solar PV IPP in Abu Dhabi.

In addition, SPPC has shortlisted bidders for two solar PV IPPs with a total combined capacity of 1,500MW under the NREP fourth round. It also expects to receive bids soon for three wind IPPs with a total combined capacity of 1,800MW.

Tenders for the NREP’s fifth round and Abu Dhabi’s fourth utility-scale solar PV farm are also expected imminently.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11143965/main.gif
Jennifer Aguinaldo
Related Articles
  • Dubai evaluates Tasreef drainage bids

    24 November 2026

     

    Up to eight stormwater and drainage projects under the next phase of Dubai Municipality’s AED30bn ($8.2bn) Tasreef programme have moved into the bid evaluation stage in recent weeks as procurement activity continues to drive the wider water infrastructure sector.

    The projects cover major stormwater drainage networks, pumping stations, storage tanks and sewerage infrastructure. They include schemes serving Dubai South, Abu Hail, the area surrounding Dubai International airport, Dubailand and Al-Awir.

    According to regional project tracker MEED Projects, the eight tenders have an estimated combined value of at least $800m. The tenders cover the following projects:

    • DS-316-C1: Drainage networks serving Hind 4
    • TF-24-C1: Connections to the stormwater network in Dubailand
    • TF-25-C1: Stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman
    • TF-07-C1: Strategic stormwater drainage network between Sheikh Mohammed bin Zayed Road and Emirates Road
    • TF-21-C1: Stormwater system upgrade and rehabilitation in Abu Hail
    • TF-30-C1: Stormwater storage tanks serving the Dubai International airport area
    • TF-06-C2: Stormwater drainage system connecting Al-Maktoum International airport and Dubai South
    • DS317-C1: Sewerage and stormwater infrastructure in New Al-Awir 1st

    According to sources, local firms Nael Construction & Contracting, Al-Nasr Contracting and Arifco Building Contracting are among those that submitted bids for the Dubailand stormwater network project (TF-24-C1) in October. The bidders for this tender do not include the local DeTech Contracting, which won the estimated $350m engineering, procurement and construction contract for a package on Al-Wasl Road (TF-15-C1), earlier this year.

    On 29 October, DeTech, Mohammed Abdulmohsin Al-Kharafi & Sons and Green Oasis General Contracting Company were among those that submitted bids for TF-07-C1, sources told MEED.

    It is undersood that both DeTech and Kharafi also submitted offers on 12 November for a contract to upgrade and rehabilitate the stormwater system in Abu Hail (TF-21-C1). The Abu Hail project comprises a stormwater pumping station with a total discharge capacity of 26 cubic metres a second. The wider project involves a major stormwater gravity drainage network, including large-diameter pipelines, and is estimated to cost up to $163m.

    Meanwhile, the the municipality is preparing to receive bids for a further scheme (TF-06-C1) on 26 November, involving the construction of a stormwater pond connecting Al-Maktoum airport and Dubai South. Al-Nasr Contracting and Green Oasis are among those preparing to bid, sources said.

    In October, the municipality confirmed it had awarded four contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.

    The projects will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. The works include constructing and extending main stormwater drainage lines with diameters of up to 3 metres.

    The Tasreef programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21756439/main.jpg
    Mark Dowdall
  • Muscat financial centre opens for business

    24 November 2026

    The International Financial Centre of Oman (IFC Oman) has opened its headquarters at Al-Mouj Business Park in Muscat and registered its first 13 companies.

    Sayyid Theyazin bin Haitham Al-Said, Oman's Deputy Prime Minister for Economic Affairs and chairman of IFC Oman, opened the headquarters on 23 November. The ceremony also marked the official start of company registration, which allows local and international businesses to set up within the centre's jurisdiction.

    The first 13 companies received their certificates of incorporation at the event. The centre was set up by Royal Decree No. 8/2026 in January, so the move from setting up a legal framework to taking in businesses has taken 10 months.

    Registration follows royal decrees that put in place IFC Oman's operating law, regulatory law and courts law. Five core regulations sit alongside them and cover operations, companies, partnerships, foundations and interpretation. Together they set the rules for setting up and running a business in the centre, including corporate governance, regulatory obligations and dispute resolution.

    Businesses can apply through a new digital registry platform. A separate regulatory framework for financial services is still being drafted, and licensing for those activities is expected to start in early 2027.

    Finance Minister Sultan bin Salim Al-Habsi, who is vice-chairman of IFC Oman, said the decision by 13 companies to join from the start "reflects the strength of the business and investment environment the centre offers".

    "We will maintain this momentum as we complete the regulatory framework ahead of the start of financial services licensing early next year," he said.

    Sayyid Theyazin said the framework "lays the foundation for a stable and competitive business environment" and will strengthen Oman's appeal to international investors and financial institutions.

    He also chaired a board meeting. It reviewed progress on finishing the centre's legal, regulatory and operational infrastructure and set priorities for attracting companies and investment.

    IFC Oman aims to connect the national economy more closely to international capital and to support growth in financial and professional services, in line with the Oman Vision 2040 economic diversification programme.

    The centre goes up against established regional financial hubs, including Dubai International Financial Centre, Abu Dhabi Global Market and Qatar Financial Centre.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21756636/main5305.gif
    Colin Foreman
  • Mecca university tenders water infrastructure projects

    24 November 2026

    Mecca-based Umm Al-Qura University has issued two tenders for wastewater and water storage infrastructure at its student campus in the Al-Abidiyah district.

    The first tender covers the second phase of the university’s main water storage scheme. The project involves building seven tanks with a combined capacity of 14,700 cubic metres.

    The scope includes three ground-level tanks with a total capacity of 7,500 cubic metres and four elevated tanks with a combined capacity of 7,200 cubic metres.

    It also includes a 2.1-kilometre backup water supply pipeline with a diameter of 400 millimetres, as well as pumping stations, inlet and outlet pipework, valves and water control systems.

    The second tender covers the construction of a wastewater treatment plant with a capacity of 4,000 cubic metres a day at the university’s student campus. The contract duration is listed as two years.

    The projects will expand the campus’s water infrastructure, adding storage capacity and wastewater treatment facilities to support its operational requirements.

    Both tenders were issued in November. Bids for the water storage tanks and wastewater plant are due by 14 December and 13 December, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21752745/main.jpg
    Mark Dowdall
  • Oman’s OQT formalises Pakistan fuel supply agreement

    24 November 2026

    Oman's state-owned commodity trader OQT has signed a petroleum products supply agreement with Pakistan State Oil (PSO), the South Asian country's national oil marketing company.

    The deal was signed on 8 October and formally marked at a ceremony in Muscat on 22 November. It was made under the Oman-Pakistan intergovernmental framework and gives OQT a structured arrangement for supplying petroleum products to PSO.

    The two companies have yet to disclose the agreement's value, volumes or duration.

    The agreement builds on an existing trading relationship. OQT says it has supplied more than 1 million tonnes of gasoline to PSO in 2026.

    OQT also supplies Pakistan's liquefied petroleum gas (LPG) market, selling to both state-owned and private buyers. The company expects its LPG deliveries to Pakistan to pass 120,000 tonnes by the end of the year.

    "This agreement gives us a stronger framework to build on that relationship, combining OQT's international trading capabilities with PSO's position in the Pakistani market," said OQT chief executive Wail Al-Jamali.

    PSO chief executive Jawwad Ahmed Cheema said the partnership is now "formal, government-backed and built for the long term under the Oman-Pakistan Intergovernmental Agreement".

    "For PSO, this is about more than supply. It is about ensuring that Pakistan has the fuel it needs, when it needs it, on terms that protect our national interest," he said.

    Oman's Energy & Minerals Minister Salim Al-Aufi and Pakistan's Petroleum Minister Ali Pervaiz Malik attended the ceremony, along with Mulham Al-Jarf, deputy president of investment at the Oman Investment Authority, which owns OQT.

    The companies said the agreement will support reliable supply at a time of continued volatility in regional energy markets. They will now focus on implementation and deliveries, and will continue talks on wider petroleum and energy cooperation.

    OQT trades crude oil, refined products, petrochemicals, LPG, liquefied natural gas, fertilisers and carbon-related products, and is expanding into metals. It has offices in Muscat, Dubai, London, Rotterdam, Singapore, Houston and Shanghai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21750539/main1214.jpeg
    Colin Foreman
  • Contractors bid for Aramco-backed logistics hub

    24 November 2026

     

    Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, received proposals from contractors on 15 November for a contract to expand the logistics complex at King Salman Energy Park (Spark) in Saudi Arabia’s Eastern Province.

    The logistics hub will add over 124,000 square metres (sq m) at Spark.

    Al-Khobar-based engineering firm House of Consulting Office is the project consultant.

    The tender for the expansion works comes after Asmo awarded an estimated SR820m ($218m) contract to build the logistics complex’s first phase in May this year.

    The overall project will feature a 43,000 sq m, temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.

    Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings in February to deliver the project at Spark.

    Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.

    It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.

    The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.

    Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.

    According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.

    Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21747071/main.gif
    Yasir Iqbal