MGS spending lifts Saudi downstream sector

15 March 2024

 

The selection of contractors by Saudi Aramco for its third expansion phase of the Master Gas System network (MGS-3) has galvanised Saudi Arabia’s midstream and downstream sectors.

Aramco has divided engineering, procurement and construction (EPC) works on the estimated $10bn MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines across various locations in the kingdom.

Aramco issued letters of intent in February to contractors for 16 EPC packages of the MGS-3 project. Some of the successful contractors have also confirmed their selection by Aramco.

The original Master Gas System (MGS) was built in the 1970s and commissioned in 1982. Since then, Aramco has been supplying natural gas to its customers across Saudi Arabia via the network, mainly channelling associated gas from Ghawar and other oil fields.

Over the past decade, amid rising gas demand from Saudi Arabia’s industrial and household sectors, Aramco has undertaken projects to increase its non-associated gas production. It launched the second expansion phase of the MGS in 2015.

Looking ahead, contractors have expressed interest in participating in the main EPC tendering process for package 16 of the MGS-3 project, which is the only EPC package not to be tendered by Aramco out of the 17 packages. The scope of work on package 16 covers the laying of a gas transport pipeline network of more than 50 kilometres in and around Jeddah.

The completion of the EPC tendering exercise – from solicitations of interest to the selection of contractors – for a scheme of the scale of MGS-3 within a year’s time underscores the commitment of Aramco, and of the Saudi government, to ensuring the steady growth of the kingdom’s gas sector.

Moreover, as Amin Nasser, president and CEO of Aramco, has said: “The recent directive from the government to maintain our maximum sustainable capacity [of oil production] at 12 million barrels a day provides increased flexibility, as well as an opportunity to focus on increasing gas production and growing our liquids-to-chemicals business.”

Liquids-to-chemicals ambition

Saudi Arabia is striving to become one of the world’s largest petrochemicals producers by the end of this decade. Its global liquids-to-chemicals programme involves expanding its portfolio of petrochemicals assets both at home and abroad.

State enterprise Aramco, along with its petrochemicals-producing subsidiary Saudi Basic Industries Corporation (Sabic), have been tasked with establishing 10-11 large mixed-feed crackers by 2030. These petrochemicals crackers, which include greenfield developments and expansions of existing facilities, will be built both in Saudi Arabia and in overseas markets.

Aramco’s global liquids-to-chemicals programme aims to convert 4 million barrels a day (b/d) of its oil production into high-value petrochemicals and chemicals feedstocks by 2030.

With a total capital expenditure by Aramco and Sabic of up to $100bn, it is the Middle East and North Africa’s largest petrochemicals spending programme ever, and will generate a significant amount of work for consultants and contractors in the run-up to 2030.

Aramco has divided its liquids-to-chemicals programme in Saudi Arabia into four main projects. It took a major step forward in September by appointing project management consultants (PMC) for the different segments of the investment scheme.

Aramco has selected US firm KBR, France’s Technip Energies, UK-based Wood Group and Australia-headquartered Worley to provide PMC services for the four projects, which include: 

  • Project East (PMC 1) – involves converting the Saudi Aramco Jubail Refinery Company (Sasref) complex in Jubail into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. The project also involves building an ethane cracker that will draw feedstock from the Sasref refinery.
  • Project West (PMC 2) – involves converting the Yanbu Aramco Sinopec Refining Company (Yasref) complex in Yanbu into an integrated refinery and petrochemicals complex through the addition of a mixed-feed cracker. Aramco and state-owned China Petroleum & Chemical Corporation (Sinopec) signed a memorandum of understanding in October for joint investment in the project, known as the Yanbu Refinery+ project.
  • Project X (PMC 3) – involves converting the Saudi Aramco Mobil Refinery Company (Samref) complex in Yanbu into an integrated refinery and petrochemicals complex by building a mixed-feed cracker. 
  • Project RTC (PMC 4) – involves establishing a crude oil-to-chemicals (COTC) complex in Ras Al Khair in the Eastern Province. Sabic is a partner in the Ras Al Khair COTC project.

Saudi Aramco is expected to start a separate tendering exercise for the provision of front-end engineering and design (feed) services on the projects in the future. Feed contracts are scheduled to be awarded in 2024, while the main EPC contracts are due for award in 2025.

Desulphurisation investments

As more sulphur recovery projects come online in Saudi Arabia, several Aramco gas treatment and processing plants in the Eastern Province and around the kingdom will discharge increased volumes of sulphur.

Existing and planned sulphur-handling facilities in the Eastern Province may not be able to cope with the incremental volumes of sulphur generated by Aramco assets in the future.

The company has therefore planned to develop a grassroots sulphur-handling complex at Ras Al Khair port to meet this requirement. The planned complex will facilitate the receiving, formation, storage and export of molten sulphur.

To be built on a public-private partnership (PPP) basis, the proposed facility is set to come online by 2029. Aramco has gauged the interest of third-party investors in developing the project.

The Ras Al Khair project is understood to be the second such PPP scheme launched by Aramco in the desulphurisation domain. Aramco is undertaking desulphurisation initiatives in line with its environmental commitments and emissions-reduction targets.

Aramco is understood to be close to awarding the build-own-operate-transfer contract for a major project that involves modifying and upgrading sulphur recovery units at seven of its gas processing plants in the Eastern Province, by building tail gas treatment units.

Two consortiums are competing for the multibillion-dollar PPP scheme, with Aramco expected to award the main contract later this year.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11595902/main49193808.jpg
Indrajit Sen
Related Articles
  • WEBINAR: End-of-Year Mena Market Review

    13 November 2026

    Webinar: The big questions shaping the Gulf market. You decide what gets debated.
    Tuesday 24 November 2026  | 11:00 AM GST  |  Register now


    What makes this session particularly interesting is that the audience gets to decide the agenda. Registrants can vote for the topics they’d like Ed and Colin to debate, with the most popular questions forming the final shortlist for the live session.

    Topics in the ballot:

    • Is the Gulf trying to build too much, too quickly?
    • Saudi Arabia or the UAE: where would you place your next big bet?
    • Are gigaprojects the best use of public money?
    • Who is really responsible when projects go wrong?
    • Should the lowest-price tender become a thing of the past?
    • Can private capital take over from the government in financing infrastructure and diversification?
    • Is the Gulf’s AI and data centre boom a smart bet or the next overbuilding risk?
    • Should the Gulf double down on hydrocarbons to fund diversification?
    • Is localisation strengthening the economy or making delivery harder?
    • Are Gulf countries building complementary economies or competing for the same customers?

    The session will also feature live audience polling and Q&A, giving attendees an opportunity to share their views.

    Hosted by: 

    Edward James, head of content and analysis at MEED

    A well-known and respected thought leader in Mena affairs, Edward James has been with MEED for more than 19 years, working as a researcher, consultant and content director. Today, he heads up all content and research produced by the MEED group. His specific areas of expertise are construction, hydrocarbons, power and water, and the petrochemicals market. He is considered one of the world’s foremost experts on the Mena projects market. He is a regular guest commentator on Middle East issues for news channels such as the BBC, CNN and ABC News and is a regular speaker at events in the region. 


    Colin Foreman, editor of MEED 

    Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21380319/main.gif
    MEED Editorial
  • PDO awards contract for Al-Ghubar oil field project

    12 November 2026

     

    Register for MEED’s 14-day trial access 

    Petroleum Development Oman (PDO) has awarded the main contract for a project to build a facility to handle additional oil production from the Al-Ghubar field in the sultanate.

    The Al-Ghubar field is located in the Ghaba Salt Basin at Qarn Alam, within majority state-owned PDO’s Block 6 concession area.

    The Al-Ghubar gas-oil gravity drainage (GOGD) facility will be designed as a sour (hydrogen sulphide) facility and is expected to handle a maximum oil production rate of 1,800 standard cubic metres a day (cm/d), a total water flow rate of up to 10,421 standard cm/d and gas lift of up to 256,934 standard cm/d. Production from the planned Al-Ghubar GOGD facility will be exported to PDO’s main oil line.

    China-based Jereh Group has won the contract for the Al-Ghubar GOGD facility project, sources told MEED.

    A project kick-off meeting between PDO and Jereh has also recently taken place, the sources said.

    MEED previously reported that Jereh had emerged as the lowest bidder for the project.

    The following contractors, among others, are understood to have been bidding for the Al-Ghubar GOGD facility project:

    • Engineering for the Petroleum & Process Industries (Egypt) / Petrojet (Egypt)
    • GS Engineering & Construction (South Korea)
    • Jereh (China)
    • Larsen & Toubro Energy Hydrocarbon (India)

    PDO floated the tender for the Al-Ghubar GOGD facility project in March, setting an initial bid submission deadline of 4 May, MEED previously reported.

    PDO later extended the deadlines for the submission of technical and commercial bids to 26 July and 7 August, respectively. Contractors submitted technical proposals by the revised deadline, according to sources.

    After receiving the technical bids for the project in July, PDO granted contractors until 16 August to submit commercial bids. It eventually extended the deadline to 1 September, with contractors submitting commercial proposals by that date, as MEED reported.

    The scope of work on the Al-Ghubar GOGD project covers the engineering, procurement and construction (EPC) of the following:

    • On-plot scope, consisting of:
      • Production separator  
      • Test separator  
      • Concentric wash tank
      • Wet oil pump
      • Water bath heater
      • Surge tank
      • Gas injection/gas lift compressor (centrifugal)
      • Utilities (instrument air compressors, chemical injection skids, drain system, vent system) 
      • Suction scrubber
      • Air coolers
      • Discharge scrubbers
      • Condensate flash drum
      • Atmospheric pressure knock-out drum 
      • Flare system
      • Gas heater
      • Water disposal pump
      • Oil shipping pump
      • 132kV substation and plant substation (housing 6.6kV and 415-Volt switchboard)
      • Control room
         
    • Off-plot scope consisting of:
      • Off-plot pipeline network (bulk header, test header, gathering infrastructure/ gathering line header, instrument air header, water disposal header)
      • Two remote manifold stations 
      • Tie-in connection to main oil line
      • Tie-in to gas network pipeline

    PDO previously intended to tender the Al-Ghubar GOGD project under its framework structure with selected EPC contractors, but ultimately tendered it separately.

    PDO is the operator of Oman’s Block 6 hydrocarbons concession, the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields. PDO produces approximately 680,000 barrels a day of oil and condensates from the fields.

    The Omani government holds a 60% stake in PDO through Energy Development Oman. The other shareholders are UK-based Shell (34%), France’s TotalEnergies (4%) and Thailand’s state-owned PTTEP (2%).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21345337/main2647.jpg
    Indrajit Sen
  • Laing O’Rourke joins the international exit list

    12 November 2026

    Commentary
    Colin Foreman
    Editor

    Register for MEED’s 14-day trial access 

    Laing O’Rourke’s decision to seek a buyer for its Middle East business marks the end of an era for UAE construction.

    In the early 2000s, the contractor was among the leading names in the market. Its work at Dubai International airport, the Atlantis hotel on the Palm Jumeirah and the ski slope at Mall of the Emirates made it arguably the UAE’s most prominent contractor during the pre-global financial crisis construction boom.

    Its activities were not limited to Dubai. A partnering agreement with Aldar for Al-Raha Beach then made it the most active contractor in Abu Dhabi almost overnight.

    The global financial crisis changed its fortunes. The Aldar Laing O’Rourke joint venture ended. Unsettled by payment problems and wider stress in the industry, the company took a more cautious approach to clients and projects in the region. One executive at the time told MEED: “You might see lots of tower cranes, but none of them are doing work that we would want to do.”

    The contractor’s appetite partially returned in the late 2010s, when it won Al-Wasl Plaza at the Expo 2020 site in Dubai. It also became a leading player in the growing data centre market, delivering facilities for repeat clients, including Khazna and Equinix.

    Data centres have since been its focus. These are significant projects, but they lack the public profile of the airport, Atlantis and Al-Wasl Plaza. As its profile faded, the company sold its UAE joinery arm to Dubai-based Arco Turnkey Solutions in 2025.

    Laing O’Rourke now looks set to follow other international contractors that have, for various reasons, left the region, including Murray & Roberts, Balfour Beatty, Multiplex, Carillion and Bam. With a record £17.2bn order book anchored by UK and Australian infrastructure, the group’s priorities clearly lie elsewhere.

    Whoever buys the business will inherit strong data centre credentials. For much of the market, however, Laing O’Rourke will be remembered for the landmark projects that defined the UAE’s boom years.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21344577/main.jpg
    Colin Foreman
  • Poland’s Orlen terminates QatarEnergy LNG supply deal

    11 November 2026

    Register for MEED’s 14-day trial access 

    Poland’s Orlen has announced it has terminated one of two long-term contracts for the supply of liquefied natural gas (LNG) by QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy. The termination follows an ongoing force majeure event “resulting in an inability to meet contractual delivery obligations”.

    The agreement covered the supply of 1 million tonnes a year (t/y) of LNG, equivalent to approximately 15.3 terawatt-hours, with pricing linked to crude oil quotations. The estimated value of the agreement for 2026 is approximately €570m ($634.9m), Orlen said in a statement on 10 November.

    The terminated agreement was originally signed by Polskie Gornictwo Naftowe i Gazownictwo and QatarEnergy on 29 June 2009. Deliveries under the agreement commenced in 2016 and were due to remain in force until 2034, the Polish energy company said.

    The agreement will remain in force for a further 60 days following the notice of termination, Orlen said in its statement.

    Orlen continues to honour its second agreement with QatarEnergy, which covers deliveries of up to 1 million t/y of LNG until 2034, under a pricing formula linked to gas price quotations.

    “The decision to terminate the agreement does not affect the security of gas supplies. Gas production from the company’s own fields, together with its long-term gas supply agreements, ensures full coverage of Orlen Group’s gas requirements,” the company concluded.

    It is not clear whether Orlen’s termination of one of its long-term LNG supply agreements with QatarEnergy is related to the Qatari energy giant declaring force majeure on two instances in March this year, when its energy infrastructure was hit in Iranian drone and missile attacks.

    Force majeure episodes

    On 4 March, QatarEnergy issued force majeure to customers that were affected by its decision to stop production and shipments of LNG and associated products after military attacks on the company’s operating facilities in Ras Laffan Industrial City and Mesaieed Industrial City in Qatar on 2 March.

    Later that month, Qatar said Iranian missiles had caused extensive damage at Ras Laffan Industrial City on 18 March, with Saad Sherida Al-Kaabi, QatarEnergy’s CEO and Minister of State for Energy Affairs, saying that the Iranian strikes had knocked out about 17% of its LNG export capacity, causing an estimated $20bn in lost annual revenue.

    At least two of Qatar’s 14 LNG trains and one of its two gas-to-liquids facilities were damaged in the Iranian strikes, Al-Kaabi told news agency Reuters at the time. 

    Repairing damaged assets will sideline 12.8 million t/y of LNG for three to five years, threatening supplies to European and Asian nations, including China and India, according to Al-Kaabi.

    As a result, QatarEnergy said it would have to declare force majeure on long-term contracts for up to five years for LNG supplies bound for Italy, Belgium, South Korea and China. Poland was not specifically mentioned at the time.

    “These are long-term contracts that we have to declare force majeure. We already declared, but that was a shorter term. Now it is whatever the period is,” Al-Kaabi said in March.

    QatarEnergy currently has a nameplate LNG production capacity of 77.5 million t/y, with all its processing trains and export infrastructure located in Ras Laffan Industrial City, which lies about 90 kilometres to the north of Doha and is home to the largest LNG production and export facility in the world. 

    QatarEnergy’s LNG production capacity is on course to rise to 142 million t/y when the three phases of its $40bn North Field LNG expansion programme are commissioned by the end of the decade. Engineering, procurement and construction works on its North Field East, North Field South and North Field West projects are progressing, with the first phase expected to be operational by the end of this year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21333808/main2615.jpg
    Indrajit Sen
  • Riyadh shifts bid deadline for King Salman Stadium works

    11 November 2026

     

    Saudi Arabia’s Sports Ministry has set a deadline of 1 December for a contract covering early works at the King Salman International Stadium in Riyadh.

    The tender scope encompasses enabling works, site preparation and initial construction activities. The tender was issued on 11 October, carrying an initial submission deadline of 19 November. Contractors previously submitted prequalification statements for the main design-and-build contract in February.

    Designed by US-based architectural firm Populous, the stadium will cover approximately 660,000 square metres (sq m), seat 92,000 spectators and stand adjacent to King Abdulaziz Park. Facilities will feature a 150-seat royal suite, 120 hospitality suites, 300 VIP seats and 2,200 dignitary seats.

    The broader masterplan encompasses more than 360,000 sq m of ancillary facilities, featuring two training fields, fan zones, a closed sports hall, an Olympic-sized swimming pool, an athletics track, and outdoor courts for volleyball, basketball and padel.

    Scheduled for completion by 2029, the venue will serve as the home base for the Saudi national football team and host the opening match and final of the 2034 Fifa World Cup.

    Saudi stadium plans

    In August 2024, MEED reported that Saudi Arabia plans to build 11 new stadiums and refurbish four existing venues for the 2034 tournament. Eight venues will be located in Riyadh, four in Jeddah, and one each in Al-Khobar, Abha and Neom.

    An additional 10 cities will host team base camps: Al-Baha, Jazan, Taif, Medina, AlUla, Umluj, Tabuk, Hail, Al-Ahsa and Buraidah. Across the kingdom, organisers plan to deploy 134 training sites, comprising 61 existing facilities and 73 new builds.

    Saudi Arabia was officially selected to host the 2034 Fifa World Cup during an online convention of member associations at the Fifa Congress on 11 December 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21325461/main.jpg
    Yasir Iqbal