MGS spending lifts Saudi downstream sector
15 March 2024

The selection of contractors by Saudi Aramco for its third expansion phase of the Master Gas System network (MGS-3) has galvanised Saudi Arabia’s midstream and downstream sectors.
Aramco has divided engineering, procurement and construction (EPC) works on the estimated $10bn MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines across various locations in the kingdom.
Aramco issued letters of intent in February to contractors for 16 EPC packages of the MGS-3 project. Some of the successful contractors have also confirmed their selection by Aramco.
The original Master Gas System (MGS) was built in the 1970s and commissioned in 1982. Since then, Aramco has been supplying natural gas to its customers across Saudi Arabia via the network, mainly channelling associated gas from Ghawar and other oil fields.
Over the past decade, amid rising gas demand from Saudi Arabia’s industrial and household sectors, Aramco has undertaken projects to increase its non-associated gas production. It launched the second expansion phase of the MGS in 2015.
Looking ahead, contractors have expressed interest in participating in the main EPC tendering process for package 16 of the MGS-3 project, which is the only EPC package not to be tendered by Aramco out of the 17 packages. The scope of work on package 16 covers the laying of a gas transport pipeline network of more than 50 kilometres in and around Jeddah.
The completion of the EPC tendering exercise – from solicitations of interest to the selection of contractors – for a scheme of the scale of MGS-3 within a year’s time underscores the commitment of Aramco, and of the Saudi government, to ensuring the steady growth of the kingdom’s gas sector.
Moreover, as Amin Nasser, president and CEO of Aramco, has said: “The recent directive from the government to maintain our maximum sustainable capacity [of oil production] at 12 million barrels a day provides increased flexibility, as well as an opportunity to focus on increasing gas production and growing our liquids-to-chemicals business.”
Liquids-to-chemicals ambition
Saudi Arabia is striving to become one of the world’s largest petrochemicals producers by the end of this decade. Its global liquids-to-chemicals programme involves expanding its portfolio of petrochemicals assets both at home and abroad.
State enterprise Aramco, along with its petrochemicals-producing subsidiary Saudi Basic Industries Corporation (Sabic), have been tasked with establishing 10-11 large mixed-feed crackers by 2030. These petrochemicals crackers, which include greenfield developments and expansions of existing facilities, will be built both in Saudi Arabia and in overseas markets.
Aramco’s global liquids-to-chemicals programme aims to convert 4 million barrels a day (b/d) of its oil production into high-value petrochemicals and chemicals feedstocks by 2030.
With a total capital expenditure by Aramco and Sabic of up to $100bn, it is the Middle East and North Africa’s largest petrochemicals spending programme ever, and will generate a significant amount of work for consultants and contractors in the run-up to 2030.
Aramco has divided its liquids-to-chemicals programme in Saudi Arabia into four main projects. It took a major step forward in September by appointing project management consultants (PMC) for the different segments of the investment scheme.
Aramco has selected US firm KBR, France’s Technip Energies, UK-based Wood Group and Australia-headquartered Worley to provide PMC services for the four projects, which include:
- Project East (PMC 1) – involves converting the Saudi Aramco Jubail Refinery Company (Sasref) complex in Jubail into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. The project also involves building an ethane cracker that will draw feedstock from the Sasref refinery.
- Project West (PMC 2) – involves converting the Yanbu Aramco Sinopec Refining Company (Yasref) complex in Yanbu into an integrated refinery and petrochemicals complex through the addition of a mixed-feed cracker. Aramco and state-owned China Petroleum & Chemical Corporation (Sinopec) signed a memorandum of understanding in October for joint investment in the project, known as the Yanbu Refinery+ project.
- Project X (PMC 3) – involves converting the Saudi Aramco Mobil Refinery Company (Samref) complex in Yanbu into an integrated refinery and petrochemicals complex by building a mixed-feed cracker.
- Project RTC (PMC 4) – involves establishing a crude oil-to-chemicals (COTC) complex in Ras Al Khair in the Eastern Province. Sabic is a partner in the Ras Al Khair COTC project.
Saudi Aramco is expected to start a separate tendering exercise for the provision of front-end engineering and design (feed) services on the projects in the future. Feed contracts are scheduled to be awarded in 2024, while the main EPC contracts are due for award in 2025.
Desulphurisation investments
As more sulphur recovery projects come online in Saudi Arabia, several Aramco gas treatment and processing plants in the Eastern Province and around the kingdom will discharge increased volumes of sulphur.
Existing and planned sulphur-handling facilities in the Eastern Province may not be able to cope with the incremental volumes of sulphur generated by Aramco assets in the future.
The company has therefore planned to develop a grassroots sulphur-handling complex at Ras Al Khair port to meet this requirement. The planned complex will facilitate the receiving, formation, storage and export of molten sulphur.
To be built on a public-private partnership (PPP) basis, the proposed facility is set to come online by 2029. Aramco has gauged the interest of third-party investors in developing the project.
The Ras Al Khair project is understood to be the second such PPP scheme launched by Aramco in the desulphurisation domain. Aramco is undertaking desulphurisation initiatives in line with its environmental commitments and emissions-reduction targets.
Aramco is understood to be close to awarding the build-own-operate-transfer contract for a major project that involves modifying and upgrading sulphur recovery units at seven of its gas processing plants in the Eastern Province, by building tail gas treatment units.
Two consortiums are competing for the multibillion-dollar PPP scheme, with Aramco expected to award the main contract later this year.
Exclusive from Meed
-
Iranian missiles hit Qatari and Kuwaiti fuel tankers1 April 2026
-
-
-
Drone strikes Kuwait International airport1 April 2026
-
Saudi Arabia’s Sadara halts chemical production1 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Iranian missiles hit Qatari and Kuwaiti fuel tankers1 April 2026
Iranian missiles have struck fuel tankers in Gulf waters belonging to Qatar and Kuwait, as Tehran continues to target energy, industrial and logistical assets in GCC countries.
A fuel oil tanker chartered by QatarEnergy, named Aqua 1, was struck by missiles in Qatar’s northern territorial waters in the early hours of 1 April, the company said in a statement.
“None of the crew members on board were injured, and there is no impact on the environment as a result of this incident,” QatarEnergy said.
Earlier, on 31 March, said one of its very large crude carriers, Al-Salmi, caught fire after being hit by an Iranian missile while anchored in UAE waters just outside Dubai.
The vessel’s crew, with support from UAE authorities, extinguished the fire by 04:26 Kuwait time on 31 March, KPC said. It added that all 24 crew members were safe and that no oil spill or environmental damage occurred.
“KPC is continuing to assess the damage in coordination with relevant authorities,” the Kuwaiti state energy conglomerate said.
ALSO READ: Iran strikes Gulf aluminium assets after hits on its steel sector
https://image.digitalinsightresearch.in/uploads/NewsArticle/16217670/main4010.jpg -
One killed and one injured in drone attacks on the UAE1 April 2026
Debris falling from Iranian drones intercepted by the UAE’s air defence systems has killed one person in the emirate of Fujairah and injured another in Umm Al-Quwain in two separate incidents on 1 April.
A successful interception of a drone by UAE air defence forces resulted in debris falling on a farm in Fujairah, leading to the death of a Bangladeshi national.
The latest fatality brings the total death toll in the UAE since the start of the US-Israel-Iran war to 12. Most of the deaths have been caused by falling debris following interceptions. Among the deceased are two members of the UAE armed forces who died while performing their duties, as well as a Moroccan civilian contracted by the armed forces.
The remaining victims were of Bangladeshi, Indian, Nepali, Pakistani and Palestinian nationalities.
Hours after the Fujairah incident, authorities in Umm Al-Quwain confirmed that an Indian national was injured when debris from an intercepted drone fell in the emirate.
In a statement posted on its official social media channels, the Umm Al-Quwain government media office said the incident occurred near an industrial facility in the Umm Al-Thuoob area, after air defence systems successfully intercepted an unmanned aerial vehicle (UAV).
Meanwhile, the latest data from the UAE Ministry of Defence, released on 31 March, showed that air defence systems had engaged 36 UAVs, four cruise missiles and eight ballistic missiles in the previous 24 hours. Cumulatively, authorities said 1,977 drones, 19 cruise missiles and 433 ballistic missiles have been intercepted since the onset of the war on 28 February.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16218126/main.jpg -
Contractors submit Al-Maktoum airport superstructure bids1 April 2026

Dubai Aviation Engineering Projects (DAEP) received proposals on 31 March from contractors for three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.
MEED understands that the selected contractor will undertake superstructure works on three packages:
- West Terminal and concourse one
- Concourse two
- Concourse three
Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.
According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.
It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.
In August last year, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport.
The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
Construction progress
Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.
Construction on the project’s first phase is expected to be completed by 2032.
The government approved the updated designs and timelines for its largest construction project in April 2024.
In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
The statement added that the project will create housing demand for 1 million people around the airport.
In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.
Project history
The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.
An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.
Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16215664/main.jpg -
Drone strikes Kuwait International airport1 April 2026
Register for MEED’s 14-day trial access
Kuwait International airport was hit by further drone attacks on Wednesday, with strikes on fuel tanks sparking a major fire.
Kuwait’s state news agency Kuna said the attack caused significant damage to fuel tanks belonging to Kuwait Aviation Fuelling Company. No casualties were reported.
This was the second reported incident at the airport in recent days. Local media reported that the airport was attacked on 28 March by multiple drones, causing significant damage to its radar system.
The airport is currently undergoing expansion works that are expected to be completed by 2027, as MEED reported previously.
Project execution of the second terminal began in 2017, with the completion date pushed back from the original 2022 target.
The second terminal project consists of three packages.
These are:
- Package 1: Main works – $4,329m
- Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
- Package 3: Aircraft parking, runways and service buildings – $950m
Turkiye’s Limak Holding is executing the main works.
The terminal building was designed by Foster+Partners and Gulf Consult.
Spanish firm Ineco is providing the project management services for the new terminal building and the airfield.
The scope of the main package includes the new terminal building, a building for cooling and electricity supply facilities, and a building for the water supply and the future Automatic People Mover (APM) connection to the satellite building.
The terminal building will be three times the size of the original building and will have 36 boarding gates.
The building will cover more than 700,000 square metres and have five floors, one of which will be underground.
It will have the capacity, at maximum service level, for 25 million passengers a year once the first phase has been completed and up to 50 million passengers after further phases are completed.
The second package of works includes a new car park with approximately 5,000 parking spaces, connected to the new passenger terminal.
It also includes all new access roads to the airport and landscaping.
The scope of the third package comprises the main platform, new taxiways and several tunnels, including one under the platform between the terminal building and the future cargo area of the airport.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16216797/main.png -
Saudi Arabia’s Sadara halts chemical production1 April 2026
Register for MEED’s 14-day trial access
Sadara Chemical Company (Sadara), the Saudi Aramco-Dow Chemical joint venture producing petrochemicals and specialty chemicals, has announced a temporary shutdown of production, citing ongoing supply chain disruptions.
Sadara operates a sprawling chemical production complex in Jubail in Saudi Arabia’s Eastern Province, with a total output capacity of more than 3 million metric tonnes a year. Aramco and Dow established the Sadara petrochemicals complex – estimated to have cost $13bn – in 2016.
The suspension was announced in a filing on the Saudi Exchange (Tadawul) by Sadara Basic Services, which issues sukuk, or Islamic bonds, for its parent. “The shutdown was successfully completed in accordance with Sadara’s high safety standards and in a manner that safeguards operations and reduces risk,” the entity said in its filing on 31 March.
“Sadara cannot provide, at the present time, an estimate for the return to production, as this is contingent on domestic and international factors,” it said, adding the shutdown is expected to impact this year’s financial results.
The month-long war between Israel, the US and Iran has spread across the Middle East, disrupting energy supplies and threatening the global economy, as Tehran has responded to US and Israeli attacks by targeting regional energy and industrial infrastructure, as well as shipping.
ALSO READ: Sultan Al-Jaber calls Strait of Hormuz blockade “economic terrorism”
Separately, Sadara, in another Tadawul filing on 31 March, announced a net loss of SR5,793bn ($1.54bn) for the full year 2025, a further decline of about 40% compared to 2024. The company’s revenue in 2025 fell by about 15% year-on-year to $2.63bn.
The chemicals producer attributed the deepening of its losses in 2025 to a reduction in sales volumes, “which resulted from unplanned operational events and extended maintenance activities that temporarily impacted production availability”.
Sadara also pinned its augmented losses to “margin compression, and higher fixed costs associated with unplanned operational events and extended maintenance activities.
“In addition, the company experienced lower average selling prices across certain portfolio lines, which further contributed to the overall decrease in revenue,” Sadara said in the disclosure.
In addition, “the net loss for 2025 increased compared to 2024, mainly due to an accounting adjustment related to a debt modification that had a favourable impact on the prior year’s results,” the company added.
ALSO READ: Sabic registers $6.87bn net loss in 2025
https://image.digitalinsightresearch.in/uploads/NewsArticle/16215635/main2446.jpg
