Masdar meets renewable’s moonshot challenge
31 January 2025

Register for MEED’s 14-day trial access
Abu Dhabi Future Energy Company (Masdar) is off to a great start this year by taking on a project that addresses what UAE Minister of Industry and Advanced Technology Sultan Al-Jaber describes as the “moonshot challenge of our time”, the intermittency of renewables.
Masdar, along with state utility Emirates Water & Electricity Company (Ewec), announced the project on 14 January. The $6bn project comprises 5,200MW solar and 19 gigawatt-hour (GWh) battery energy storage system (bess) plants.
It is designed to deliver up to 1,000MW of uninterrupted “baseload” power from a renewable source, a first in the world in terms of its scale.
“The country leadership’s will to deploy cutting-edge technology despite perceived risks, the growing experience of Masdar in developing battery energy storage projects globally, along with the decline in battery prices helped expedite the project,” Abdulaziz Alobaidli, chief operating officer of Masdar, tells MEED. “It’s a major achievement, over 15 years since the first single-site 10MW project was procured in Abu Dhabi.”
It has a lot to do with our culture to never say no to the impossible
Alobaidli was referring to Masdar’s first 10MW solar photovoltaic (PV) plant located on the north side of Masdar City, which was connected to the Abu Dhabi electricity grid in April 2009.
The executive says the 5.2GW/19GWh project was fast-tracked thanks to the broader collaboration of the key relevant stakeholders who facilitated the overall permitting proceedings.
He also stressed that they have obtained the necessary experience by developing renewable energy projects in developed and developing countries over the past decade and a half, with their current portfolio sitting at around 32GW.
“It has a lot to do with our culture to never say no to the impossible,” explains Alobaidli.
“We solved a two-decade problem by jointly evaluating the technical and commercial feasibility of the project, doubling down on our global development experience, and the strategic relationship we have built with key solar and bess suppliers … it helped that the battery technology has reached a desired level of cost competitiveness along with improved efficiency.
“The collaborative spirit of our client, Ewec, has facilitated the development of the project and gave us confidence that we can bring it to the finish line.”
Fast-track project
Masdar announced the selection of contractors and sub-contractors for the project a few days after its launch.
It selected India’s Larsen & Toubro and Beijing-headquartered PowerChina to undertake the project’s engineering, procurement and construction (EPC) contract.
Masdar also picked Shanghai-based Jinko Solar and Beijing-headquartered JA Solar to supply solar PV modules. They will supply solar PV modules amounting to 2.6GW each, with maximum efficiency and production for 30 years.
Another Chinese firm, Fujian-based Contemporary Amperex Technology Company Limited (CATL), will supply its Tener product line for the bess plant.
The project will be structured as a classic public-private partnership (PPP), funded by equity and syndicated debt.
It is being deployed on a fast-track basis, with financial close expected by the second quarter of 2025 and commercial operations set for 2027.
Alobaidli says they are in the process of deployment and starting the mobilisation of contractors, following months of technology assessments and technical workshops.
He also says Masdar is open to considering co-investors or codevelopers in the project “if they will complement” its capability to deliver the project.
Masdar has also engaged several banks and lenders, which have been conducting due diligence on the project, particularly on the selected battery technology.
The executive, who previously served as general manager of Masdar subsidiary, Shams Power Company, says declining battery prices provide significant opportunities for their adoption at larger scale and long-hours applications.
“This is significant for the industry, and we see demand and supply growing, including the number of suppliers in the market. Security of supply and more competitive battery price is key.”
AI connection
MEED first reported on the planned round-the-clock renewable project in October last year. At the time, sources indicated that the project was envisaged to support the state’s artificial intelligence (AI) strategy.
This was confirmed by a social media post on 14 January, when UAE President Sheikh Mohamed Bin Zayed Al-Nahyan said the project would help power advancements in AI and emerging technologies in addition to being a significant step on the UAE’s journey towards net zero.
Alobaidli says the project, which will be the first of many, “will definitely unlock opportunities for AI and other industries, which require base and round-the-clock load”.
Global expansion
While the 5GW/19GWh project is the largest single project by far to be deployed by Masdar, the experiences it gained by growing organically and through mergers and acquisitions, especially over the past decade, should help ensure it delivers the project within time and budget.
The project’s execution is also unlikely to hamper Masdar’s ongoing global expansion, given its goal to expand its renewable energy portfolio to 100GW by 2030.
Masdar has been expanding its global footprint as well as the type of assets it deploys or acquires, which range from onshore and offshore solar, onshore and offshore wind and, now, battery energy storage plants.
It has been bidding for new projects close to home, such as in Saudi Arabia and Oman, as well as in developing countries or acquiring stakes in projects across nearly every region of the world, from the Philippines, Malaysia and Indonesia in Southeast Asia, to Africa, more mature markets in Europe such as Greece and Spain, and the Americas.
“We are not just running after capacity. We look at profitability and the impact of these acquisitions on our earnings and P&L,” explains Alobaidli. “More importantly, we focus on the impact of these projects on the local communities.”
Alobaidli stresses that Masdar is focusing on prudent risk-reward factors as it expands its operations to avoid overexposure and ensure every deal is robust and backed by objective risk analysis.
“We are backed by three very strong institutions,” he points out, referring to Abu Dhabi National Oil Company, Abu Dhabi National Energy Company (Taqa) and sovereign wealth fund Mubadala. “So every investment opportunity is thoroughly assessed to ensure it meets our growth objectives and stakeholders’ expectations.”
READ MEED’s YEARBOOK 2025
MEED’s 16th highly prized flagship Yearbook publication is available to read, offering subscribers analysis on the outlook for the Mena region’s major markets.
Published on 31 December 2024 and distributed to senior decision-makers in the region and around the world, the MEED Yearbook 2025 includes:
|
> PROJECTS: Another bumper year for Mena projects
> GIGAPROJECTS INDEX: Gigaproject spending finds a level
> INFRASTRUCTURE: Dubai focuses on infrastructure
> US POLITICS: Donald Trump’s win presages shake-up of global politics
> REGIONAL ALLIANCES: Middle East’s evolving alliances continue to shift
> DOWNSTREAM: Regional downstream sector prepares for consolidation
> CONSTRUCTION: Bigger is better for construction
> TRANSPORT: Transport projects driven by key trends
> PROJECTS: Gulf projects index continues ascension
> CONTRACTS: Mena projects market set to break records in 2024
|
Exclusive from Meed
-
Adnoc Onshore selects contractors for well tie-ins project27 October 2026
-
Ashghal tenders Al-Udeid air base access road works27 October 2026
-
Saudi Arabia gauges interest for Al-Ula wastewater expansion27 October 2026
-
Qatari firm wins $147m Syria road deal27 October 2026
-
Adnoc showcases $16.3bn local manufacturing potential27 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Adnoc Onshore selects contractors for well tie-ins project27 October 2026

Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.
Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields.
The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.
According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.
Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.
Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.
The project budget is estimated at $1.2bn.
Bidders for the contract are understood to have included:
- Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
- Jereh (China)
- Kalpataru Projects International (India)
- Matrix Construction (UAE)
- Robt Stone Middle East (UAE)
- Target Engineering Construction Company (UAE)
The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.
Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.
ALSO READ:
https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg -
Ashghal tenders Al-Udeid air base access road works27 October 2026

Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.
The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road.
The tender was issued on 22 October, with a submission deadline of 22 November.
The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.
Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.
The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.
The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.
The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.
Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.
The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.
Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.
Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.
For joint-venture bids, the lead partner must hold the required classification grade.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg -
Saudi Arabia gauges interest for Al-Ula wastewater expansion27 October 2026

Saudi Arabia’s Royal Commission for Al-Ula (RCU) is conducting market sounding for the first phase of the Mughayra wastewater treatment plant (WWTP) expansion before formally starting its tendering process, according to industry sources.
The project is valued at SR400m ($107m) and is intended to increase the Mughayra plant’s wastewater treatment capacity to 62,000 cubic metres a day.
RCU is gauging interest from potential contractors and has not yet issued a prequalification questionnaire, a source said.
The scheme forms part of Saudi Arabia’s broader investment drive to develop its cultural and tourism offering across Al-Ula.
The commission launched its Journey Through Time Masterplan in April 2021, with implementation scheduled in three phases through 2035. The masterplan covers infrastructure development, water management and irrigation, alongside the regeneration of a 9-kilometre cultural oasis.
French engineering firm Artelia previously noted in its 2025 annual corporate report that it is involved in the design phase of the Mughayra WWTP.
RCU is also developing strategic potable-water storage infrastructure in Al-Ula, including a design-and-build project covering a 50,000-cubic-metre reservoir at Hub 06 and a 15,000-cubic-metre reservoir at Hub 08.
Local contractor Bin Omairah previously confirmed that it is serving as the engineering, procurement and construction contractor for the storage facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20950333/main.jpg -
Qatari firm wins $147m Syria road deal27 October 2026
Qatari contractor Al-Mohannadi for Roads, Trading & Contracting has signed a $147m contract with Syria’s General Directorate of Roads to rehabilitate and expand a 215-kilometre (km) highway corridor connecting to the Iraqi border.
The project covers the rehabilitation and dualisation of a 170km section linking the Al-Busairi junction to the Al-Tanf border crossing, alongside the construction of a 45km link between the Al-Sabaa Biyar junction and Al-Busairi. Work is scheduled for completion within 900 days.
The agreement was signed in Damascus by Moaz Najjar, director-general of the General Directorate of Roads, and Abdullah Adnan Al-Zattam, chief executive of Al-Mohannadi, in the presence of Syrian Transport Minister Yarob Badr and Finance Minister Mohammad Yusr Barnieh.
The upgrade is intended to restore and expand one of Syria’s primary overland arteries to Iraq, which has suffered significant deterioration and capacity bottlenecks following years of conflict. The Al-Tanf corridor represents the most direct overland link between Damascus, central Syrian industrial centres and Baghdad.
The project is designed to accommodate heavier commercial freight vehicles and reduce transit times between the two countries.
The investment also forms part of broader efforts to re-establish Syria’s role as a regional transit corridor connecting Mediterranean ports with landlocked trade routes into Iraq and the wider region.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20950332/main.gif -
Adnoc showcases $16.3bn local manufacturing potential27 October 2026
Abu Dhabi National Oil Company (Adnoc Group) has identified more than AED60bn ($16.3bn) in local manufacturing opportunities through 2030.
The Abu Dhabi energy company also announced changes to its procurement, supplier registration and In-Country Value (ICV) localisation frameworks.
The measures were announced at the second Make it with Adnoc Forum, held in Abu Dhabi on October 25. They are intended to give manufacturers, suppliers and investors greater visibility of future demand and a faster, clearer route to compete for Adnoc contracts, the company said.
The more than 200 manufacturing opportunities cover products required for Adnoc’s projects and operations, including:
- Rotating equipment and power
- Electrical, control and automation systems
- Drilling and completion equipment
- Chemicals and catalysts
- Piping, fabrication and heavy equipment
- Spare parts and advanced manufacturing
Many of the identified products are currently imported, Adnoc said. “Manufacturing them in the UAE shortens lead times, reduces exposure to global supply disruptions and strengthens the resilience of Adnoc’s operations,” it said in its statement.
Adnoc, the UAE Ministry of Industry & Advanced Technology and the Abu Dhabi Investment Office (Adio) will work together to connect manufacturers with these opportunities. The collaboration will combine visibility of Adnoc’s demand, access to the national industrial database and financing through the National Industrial Resilience Fund, the company said.
Adnoc also signed two memorandums of understanding on the sidelines of the forum with Adio and Kezad Group.
ICV scheme expansion
Adnoc announced the expansion of its Local+ programme, part of its ICV framework, to more than 100 UAE manufacturers, compared with 70 at its launch in May. The programme gives UAE-made products priority in Adnoc projects by requiring engineering, procurement and construction (EPC) contractors bidding for new tenders to source relevant products from manufacturers approved under the programme.
Separately, Adnoc announced a redesign of its supplier registration and prequalification process. The company is targeting a reduction of up to 80% in the time required for suppliers to complete the process and become eligible to compete for Adnoc opportunities.
The new model halves the number of required documents and removes prequalification requirements for 60% of service categories.
A single window brings together registration, qualification and compliance, with requirements tailored to the nature of the work and its level of risk. Artificial intelligence will support document verification and the reuse of existing data, reducing repetitive submissions and administrative processing.
ALSO READ:
Adnoc steps up crude oil capacity expansion
Adnoc funnels billions into boosting gas processing
“Adnoc’s enhanced ICV model will more closely connect procurement decisions with commercial value and suppliers’ contribution to the UAE economy. Under the new model, commercial and ICV offers will be integrated into a single evaluation model,” the company said.
“The previous bid-matching approach will be retired, encouraging suppliers to submit their most competitive commercial and ICV offers from the outset. Requirements will be proportionate to contract size and scope.
“The model also enhances the administration of ICV-related retention payments. Where retention applies, automated calculation and release processes through the Adnoc Supplier Hub will improve transparency, reduce manual follow-up and support suppliers’ cash flow as obligations are met.”
Alongside the ICV and registration enhancements, Adnoc outlined a new commercial approach built around four strategic shifts: agile, competitive, strategic and forward-looking.
“The approach will advance simpler procurement and faster decision-making, contracting models aligned with project and market dynamics, targeted commercial negotiations and earlier visibility of Adnoc’s future demand.”
Since its launch in 2018, Adnoc’s ICV programme has directed more than AED307bn ($83.6bn) into the UAE economy, the company said. By the end of 2025, it had also supported the localisation of more than 130 products, the development of 95 UAE factories, and employment opportunities for more than 27,500 Emiratis at participating private sector companies.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20948385/main5518.jpg