Masdar meets renewable’s moonshot challenge

31 January 2025

 

Register for MEED’s 14-day trial access 

Abu Dhabi Future Energy Company (Masdar) is off to a great start this year by taking on a project that addresses what UAE Minister of Industry and Advanced Technology Sultan Al-Jaber describes as the “moonshot challenge of our time”, the intermittency of renewables.

Masdar, along with state utility Emirates Water & Electricity Company (Ewec), announced the project on 14 January. The $6bn project comprises 5,200MW solar and 19 gigawatt-hour (GWh) battery energy storage system (bess) plants.  

It is designed to deliver up to 1,000MW of uninterrupted “baseload” power from a renewable source, a first in the world in terms of its scale.

“The country leadership’s will to deploy cutting-edge technology despite perceived risks, the growing experience of Masdar in developing battery energy storage projects globally, along with the decline in battery prices helped expedite the project,” Abdulaziz Alobaidli, chief operating officer of Masdar, tells MEED. “It’s a major achievement, over 15 years since the first single-site 10MW project was procured in Abu Dhabi.”

It has a lot to do with our culture to never say no to the impossible 

Alobaidli was referring to Masdar’s first 10MW solar photovoltaic (PV) plant located on the north side of Masdar City, which was connected to the Abu Dhabi electricity grid in April 2009.

The executive says the 5.2GW/19GWh project was fast-tracked thanks to the broader collaboration of the key relevant stakeholders who facilitated the overall permitting proceedings.

He also stressed that they have obtained the necessary experience by developing renewable energy projects in developed and developing countries over the past decade and a half, with their current portfolio sitting at around 32GW.

“It has a lot to do with our culture to never say no to the impossible,” explains Alobaidli.

“We solved a two-decade problem by jointly evaluating the technical and commercial feasibility of the project, doubling down on our global development experience, and the strategic relationship we have built with key solar and bess suppliers … it helped that the battery technology has reached a desired level of cost competitiveness along with improved efficiency.

“The collaborative spirit of our client, Ewec, has facilitated the development of the project and gave us confidence that we can bring it to the finish line.”

Fast-track project

Masdar announced the selection of contractors and sub-contractors for the project a few days after its launch.

It selected India’s Larsen & Toubro and Beijing-headquartered PowerChina to undertake the project’s engineering, procurement and construction (EPC) contract.

Masdar also picked Shanghai-based Jinko Solar and Beijing-headquartered JA Solar to supply solar PV modules. They will supply solar PV modules amounting to 2.6GW each, with maximum efficiency and production for 30 years.

Another Chinese firm, Fujian-based Contemporary Amperex Technology Company Limited (CATL), will supply its Tener product line for the bess plant.

The project will be structured as a classic public-private partnership (PPP), funded by equity and syndicated debt.

It is being deployed on a fast-track basis, with financial close expected by the second quarter of 2025 and commercial operations set for 2027.

Alobaidli says they are in the process of deployment and starting the mobilisation of contractors, following months of technology assessments and technical workshops.

He also says Masdar is open to considering co-investors or codevelopers in the project “if they will complement” its capability to deliver the project.  

Masdar has also engaged several banks and lenders, which have been conducting due diligence on the project, particularly on the selected battery technology.

The executive, who previously served as general manager of Masdar subsidiary, Shams Power Company, says declining battery prices provide significant opportunities for their adoption at larger scale and long-hours applications.

“This is significant for the industry, and we see demand and supply growing, including the number of suppliers in the market. Security of supply and more competitive battery price is key.”

AI connection

MEED first reported on the planned round-the-clock renewable project in October last year. At the time, sources indicated that the project was envisaged to support the state’s artificial intelligence (AI) strategy.

This was confirmed by a social media post on 14 January, when UAE President Sheikh Mohamed Bin Zayed Al-Nahyan said the project would help power advancements in AI and emerging technologies in addition to being a significant step on the UAE’s journey towards net zero.

Alobaidli says the project, which will be the first of many, “will definitely unlock opportunities for AI and other industries, which require base and round-the-clock load”.

Global expansion

While the 5GW/19GWh project is the largest single project by far to be deployed by Masdar, the experiences it gained by growing organically and through mergers and acquisitions, especially over the past decade, should help ensure it delivers the project within time and budget.

The project’s execution is also unlikely to hamper Masdar’s ongoing global expansion, given its goal to expand its renewable energy portfolio to 100GW by 2030.

Masdar has been expanding its global footprint as well as the type of assets it deploys or acquires, which range from onshore and offshore solar, onshore and offshore wind and, now, battery energy storage plants.

It has been bidding for new projects close to home, such as in Saudi Arabia and Oman, as well as in developing countries or acquiring stakes in projects across nearly every region of the world, from the Philippines, Malaysia and Indonesia in Southeast Asia, to Africa, more mature markets in Europe such as Greece and Spain, and the Americas.

“We are not just running after capacity. We look at profitability and the impact of these acquisitions on our earnings and P&L,” explains Alobaidli. “More importantly, we focus on the impact of these projects on the local communities.”

Alobaidli stresses that Masdar is focusing on prudent risk-reward factors as it expands its operations to avoid overexposure and ensure every deal is robust and backed by objective risk analysis.

“We are backed by three very strong institutions,” he points out, referring to Abu Dhabi National Oil Company, Abu Dhabi National Energy Company (Taqa) and sovereign wealth fund Mubadala. “So every investment opportunity is thoroughly assessed to ensure it meets our growth objectives and stakeholders’ expectations.”


READ MEED’s YEARBOOK 2025

MEED’s 16th highly prized flagship Yearbook publication is available to read, offering subscribers analysis on the outlook for the Mena region’s major markets.

Published on 31 December 2024 and distributed to senior decision-makers in the region and around the world, the MEED Yearbook 2025 includes:

> GIGAPROJECTS INDEX: Gigaproject spending finds a level
https://image.digitalinsightresearch.in/uploads/NewsArticle/13347001/main.jpg
Jennifer Aguinaldo
Related Articles
  • Saudi water sector hits sharp slowdown

    8 September 2026

     

    Saudi Arabia’s water sector has recorded a sharp slowdown in contract awards this year, with $3.94bn of new contracts awarded as of early September.

    According to regional project tracker MEED Projects, this is well below the $10.7bn recorded in 2025, $13bn in 2024 and a record $15.3bn in 2023.

    The slowdown comes as several major projects remain in the procurement process, with some yet to reach financial close or contract award, while tender deadlines for other schemes have been pushed back.

    Among the largest is the estimated $2bn Riyadh-Qassim independent water transmission pipeline. The 859-kilometre project will have a transmission capacity of 685,000 cubic metres a day (cm/d). Vision Invest was selected as the preferred bidder last December; however, more than eight months later, an official developer’s agreement has not yet been signed.

    Similarly, the Arana and Hadda independent sewage treatment plant (ISTP) projects have yet to reach the financial close originally targeted for the second quarter. The two schemes will provide a combined treatment capacity of 350,000 cm/d.

    Delays extend further down the procurement pipeline. The latest developer bid deadline for the estimated $150m Riyadh East ISTP is 29 September, almost a year after the request for proposals (RFP) was issued in October 2025.

    Procurement for the main contracts for the Jubail-Buraidah and Ras Mohaisen-Baha-Mecca independent water transmission system projects could also slip into 2027, amid delivery-model changes by Water Transmission Company.

    New awards

    The market received a boost in September when Saudi Arabia’s National Water Company (NWC) announced it had signed a SR1.3bn ($347m) deal with a Saudi-Chinese consortium for package 10 of its long-term operations and maintenance programme.

    The consortium – comprising China’s Jiangsu United Water Technology and Saudi-based Armada Holding – will rehabilitate, operate and maintain nine sewage treatment plants (STPs) with a combined design capacity of more than 337,000 cm/d. Based on the latest procurement timeline, it is unclear whether the selected consortium for package 11 will be formally announced this year. Packages 12 and 14 remain under tender while package 16 is next in line, with its RFP not expected to be issued before November.

    NWC is the second-largest awarding entity by value in 2026, accounting for $1.09bn, or about 28% of the total. Saudi Aramco is the largest, with $2.15bn, meaning the two organisations account for more than 82% of awards so far this year.

    Aramco’s activity has been led by two major oil field developments. In June, it awarded the $1.5bn Safaniya onshore surface facilities project: package 1 to a joint venture of Tecnimont and Consolidated Contractors Company. The package includes a water treatment and injection plant supporting upstream production.

    It also awarded the second phase of its Zuluf water treatment project to a joint venture of Almar Water Solutions and AlJomaih Energy & Water. The project will add a 308,000-cm/d treatment facility at Tanajib in the Eastern Province, supplying water for injection at the offshore Zuluf oil field.

    The concentration of awards in industrial projects this year has been notable. Against the slowdown in municipal water infrastructure procurement, much of the value awarded so far has been linked to the water requirements of oil and gas and mining developments.

    The third-largest award is the $350m Taif Ar Rjum water pipeline project, being developed by Saudi Arabian Mining Company (Maaden) in Mecca. The project will support the Ar Rjum gold mining and processing facility and is being developed under a build-own-operate-transfer model. 

    By project type, treatment projects make up the largest share of awards, at $2.85bn or about 72% of the total. Transmission projects account for $980m and cooling projects for a further $110m, while no major desalination or water storage contracts have been awarded so far this year.

    Project pipeline

    The slowdown in awards appears to reflect the timing of projects moving through procurement rather than a fundamental weakening in demand for water infrastructure.

    Saudi Arabia continues to face rising demand for desalination, wastewater treatment and water transmission as population growth and industrial expansion drive demand for water.

    Sharakat, formerly Saudi Water Partnership Company, set out the next phase of the kingdom’s water investment programme in its latest seven-year statement, published in March.

    The plan points to a significant expansion in desalination capacity. Capacity from Sharakat-procured projects is expected to increase from about 3.88 million cm/d in 2025 to roughly 7.18 million cm/d by 2031.

    The increase will be supported by seven new independent water plants (IWPs) with a combined capacity of about 2.8 million cm/d, in addition to projects already operating, under construction or in procurement.

    However, several of the planned projects have yet to move into active procurement, while others have seen their expected timelines pushed back.

    Among the schemes affected are the Ras Al-Khair, Tabuk, Shuqaiq and Jizan IWPs, which have all progressed through prequalification, but have seen changes to their expected procurement schedules.

    The largest is phase two of the Ras Al-Khair IWP, a 600,000-cm/d reverse osmosis desalination plant that has been in development for more than a decade.

    The revised schedule indicates that the $400m Al-Shuqaiq 4 IWP is expected to be the first of the seven new plants to reach commercial operation. Its main contract had been expected to be tendered later this year, but it is now understood that the first RFP will not be issued until early 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19466739/main.gif
    Mark Dowdall
  • Kuwait grants loan for GCC grid extension study

    8 September 2026

    The Kuwait Fund for Arab Economic Development has signed a KD200,000 ($647,000) grant agreement with the GCC Interconnection Authority (GCCIA) to finance a feasibility study on extending the Gulf power grid to electricity networks outside the GCC.

    The agreement was signed on 3 September by Ahmed Bin Ali Al-Ibrahim, CEO of the GCCIA, and Kuwait Fund acting director general Rashid Al-Bader.

    The study will assess opportunities to expand the GCC power interconnection system to neighbouring countries. It will examine their electricity requirements and the technical and economic feasibility of connecting their national grids to the Gulf network.

    The Kuwait Fund did not identify the countries or potential interconnection routes. However, it is understood that the study will identify potential phases for future expansion, determine priority projects and assess the most appropriate interconnection options based on technical and economic criteria.

    It will cover the proposed project’s main components, costs, implementation arrangements and expected timeframe. The study will also assess the potential economic and social benefits for GCC member states and connected countries, as well as how the GCC network would operate alongside neighbouring national grids.

    A preliminary assessment of the project’s potential environmental and social impacts will also be carried out, together with proposed mitigation measures.

    The Kuwait Fund has previously provided three loans worth a combined KD78m ($252m) to GCCIA to support expansion of the GCC power interconnection system and its connection to southern Iraq’s electricity grid.

    In August 2025, the fund announced two loans worth KD70m ($224m) for the expansion of the Gulf Power Interconnection Project. The financing included support for the Al-Wafra 400kV substation and infrastructure connecting Kuwait’s grid with Iraq. 

    The Al-Wafra substation facilitates electricity exchanges and enables Kuwait to access surplus power available through the GCC interconnection system.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461053/main.jpg
    Mark Dowdall
  • Chinese firm to set up $300m anode facility in the UAE

    8 September 2026

    Beijing-headquartered Sunstone Development has signed a memorandum of understanding (MoU) with the UAE Ministry of Investment to develop an anode production facility in the UAE, with an estimated investment of about $300m.

    The MoU follows Sunstone’s December 2025 joint-venture agreement with Emirates Global Aluminium (EGA) to build the project.

    Upon completion, the plant is expected to replace most of EGA’s current anode imports and support the UAE’s ambition to become one of a limited number of global anode-exporting countries, aligning with the Make It In The Emirates initiative and Operation 300bn.

    The ministry said the agreement reflects its role in helping strategic investors navigate the UAE’s investment ecosystem and convert commitments into long-term operations, in line with the National Investment Strategy 2031.

    By localising a key stage in the aluminium value chain, the facility will reduce reliance on imported anodes, enhance the competitiveness of the UAE aluminium sector and support wider economic diversification.

    The Ministry of Investment and Sunstone will establish a joint working group, chaired by the ministry, to oversee project delivery.

    The project is expected to create skilled employment opportunities for UAE nationals and residents, while strengthening domestic manufacturing capacity and industrial capabilities.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461120/main.jpg
    Yasir Iqbal
  • Riyadh tenders Expo 2030 Souq areas package

    8 September 2026

     

    Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has tendered a contract to deliver the Souq areas within the Expo site.

    The tender was floated on 30 July, with a submission deadline of 9 October.

    The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).

    The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works. 

    The precincts comprise:

    • Precinct 1 – The Icon: 41,417 sq m
    • Precinct 2 – Place & Planet: 62,306 sq m 
    • Precinct 3 – Culture of Wisdom: 67,112 sq m  
    • Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m  
    • Precinct 5 – Adaptation & Innovation: 82,358 sq m

    The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.

    The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, providing a central connection between the site’s iconic and thematic assets.

    The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.

    Site progress

    Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.

    Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City (RCRC) awarded a design-and-build contract for the construction of a new metro station catering to the Expo 2030 site.

    In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Alyamama Company.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.

    That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19457171/main.jpg
    Yasir Iqbal
  • Powering the next chapter with nuclear energy

    8 September 2026

    Commentary
    Colin Foreman
    Editor

    Nuclear energy is increasingly being viewed as essential around the world. It offers a non-CO2-emitting, steady baseload at a time when governments have made net-zero commitments. 

    In the Gulf, the UAE has spent the past 15 years building the Middle East’s first commercial nuclear plant, now supplying about a quarter of the country’s electricity. What is new is the breadth of ambition beyond Abu Dhabi. The civil nuclear cooperation deal signed between Saudi Arabia and the US in July is the most significant step in the kingdom’s nuclear programme for several years, and it lands as the region moves decisively towards atomic power.

    The logic is clear. Electricity demand from industry, desalination and digital infrastructure is climbing, and governments want reliable low-carbon supply to meet it. Saudi Arabia is targeting up to 17GW of nuclear capacity by 2040. Its first plant at Khor Duwaiheen, comprising two 1.4GW reactors, represents only about a sixth of that goal, which points to a programme rather than a one-off.

    What is new is the breadth of ambition beyond Abu Dhabi

    The opportunity extends well beyond reactors. The UAE’s nuclear programme shows the scale of the economic impact. More than 2,000 local firms secured contracts worth over $6.7bn supporting construction, operations and maintenance. 

    Saudi Arabia’s ambitions reach further still, into small modular reactors, domestic uranium and elements of the fuel cycle. At the same time, Bahrain is studying a modular plant to power its industrial base, and Egypt’s 4.8GW El-Dabaa project is already under construction, with first generation expected in 2028.

    For contractors, engineers and financiers, this is the beginning of a projects market that will unfold over decades. The reactor awards will grab the headlines, but the supporting ecosystem, from regulation and fuel supply to workforce development, is where much of the value lies.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19461185/main.gif
    Colin Foreman