Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • Lowest bidder emerges for Kuwait Airport Terminal 2 operations

    19 October 2026

     

    Ireland’s DAA International has emerged as the lowest bidder for the contract to operate, manage and maintain the new passenger Terminal 2 (T2) at Kuwait International airport, submitting an offer of KD419m ($1.35bn).

    Official price-opening records released by Kuwait’s Central Agency for Public Tenders on behalf of the Directorate General of Civil Aviation show three international airport operators submitted commercial bids for the tender.

    DAA International’s proposal undercut its nearest rival by about 45%. Turkiye’s TAV Airports Holding submitted the second-lowest offer at KD764.15m ($2.46bn), while South Korea’s Incheon International Airport Corporation bid KD959.48m ($3.1bn).

    All three proposals were marked as approved in the tender committee’s price disclosure.

    The contract entails the operation, management and improvement of training, maintenance and development services across Terminal 2 and its associated aircraft parking aprons.

    The remit also includes corporate management of centralised operation and maintenance across the broader Kuwait International airport model, centralising operational procedures, systems integration and service delivery across the aviation hub.

    Technical documents indicate the winning operator will oversee facility management, terminal operational readiness, passenger processing systems, apron operations and staff development programmes before and after the complex’s commercial launch.

    MEED reported in June 2023 that six airport operators had initially been invited to bid for the Terminal 2 operating concession.

    Terminal 2 is the centrepiece of Kuwait International airport’s multibillion-dollar expansion, aimed at boosting total handling capacity to 25 million passengers a year.

    Turkish contractor Limak Insaat is executing the main terminal building under an estimated $4.34bn contract awarded in 2016.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20747061/main.png
    Yasir Iqbal
  • Dubai tenders Al-Maktoum-Dubai South drainage scheme

    19 October 2026

    Dubai Municipality has invited contractors to submit bids by 5 November for the construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South

    The project, designated TF-06-C2, involves approximately 20 kilometres of pipelines with diameters ranging from 400mm to 3,000mm. The works will use deep trenchless construction and conventional open-cut methods. 

    The scheme is one of four projects, for which a project management consultancy (PMC) tender was issued earlier this month.

    The tender for TF-06-S1 Supervision of Stormwater Drainage System Projects – Package 4 was issued on 6 October.

    The consultancy covers the following projects:

    • TF-06-C1: Construction of a stormwater pond connecting Al-Maktoum Airport and Dubai South
    • TF-06-C2: Construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
    • TF-07-C1: Construction of a stormwater drainage system on Sheikh Zayed Bin Hamdan Road connecting developers
    • TF-24-C1: Connecting developers’ areas to the stormwater networks in Dubailand 

    The projects are part of Dubai Municipality’s wider Tasreef programme, intended to increase Dubai’s rainwater drainage capacity by 700% by 2033 and provide capacity for the emirate’s needs for the next 100 years.

    Investment in the UAE water sector has been dominated by stormwater drainage and network resilience schemes this year, as Dubai Municipality advances procurement under its AED30bn ($8.1bn) Tasreef programme.

    TF-07-C1

    As previously reported, contractors are preparing to submit bids on 22 October for the main construction contract for TF-07-C1.

    The project covers more than 100 million square metres between Sheikh Mohammed Bin Zayed Road and Emirates Road, and from Expo Road to Dubailand.

    It will provide stormwater infrastructure and service connections for more than 20 private developers and Al-Yalayis 5, as well as supporting major roads in the Jebel Ali area. The construction scope includes a major gravity drainage system with pipeline diameters of up to 3,000mm.

    TF-24-C1

    Bids for TF-24-C1 were submitted on 1 October, with Nael Construction & Contracting, Al-Nasr Contracting Company and Al-Kharafi & Sons understood to be among the bidders. 

    The project will connect developers’ areas in Dubailand to the stormwater network. It includes 18km of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.

    As MEED understands, the main contract tender for TF-06-C1 has yet to be released.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20746611/main.jpg
    Mark Dowdall
  • Contractor wins $44m Morocco rail stations deal

    19 October 2026

    Morocco’s national railway operator, Office National des Chemins de Fer (ONCF), has awarded a MD437.6m ($44.5m) contract to local firm Jet Contractors to build five railway stations along the Benguerir-Marrakech corridor.

    The project forms part of the wider Kenitra-Marrakech high-speed rail development programme.

    Jet Contractors will build one high-speed rail station and four regional express rail stations.

    These include two stations in Benguerir, and one each at Sidi Bou Othmane, Sidi Ghanem and Marrakech Stadium.

    The scope of work includes construction and fit-out of the stations and associated infrastructure, including concrete structures, platforms, ancillary facilities, passageways, circulation areas and connection zones within the stations.

    It also covers architectural finishing works; testing and commissioning of electrical networks; and all mechanical, electrical and plumbing services.

    The contractor will also provide all safety, security and protection systems, including alarms, fire detection and firefighting systems, and surveillance systems.

    Morocco awarded multiple civil works contracts in 2024 to international and local firms to build its Kenitra-Marrakech high-speed railway line.

    The rail project is part of a $37bn strategy to connect more of Morocco’s cities, ports and airports by rail. It will stretch 375 kilometres from Kenitra on the northwest coast to Marrakech in the south.

    The project is divided into seven lots, each measuring 36km to 64km. The rail link will pass through cities including Rabat, Sale and Casablanca.

    The link will extend the Al-Boraq high-speed rail line between Tangier, Rabat and Casablanca. The line began operating in 2018 and was Africa’s first high-speed railway system.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20745963/main.jpg
    Yasir Iqbal
  • Firms submit Dubai multibillion-dollar road scheme interest

    19 October 2026

     

    Register for MEED’s 14-day trial access 

    Contractors submitted expressions of interest on 10 October for a design-and-build contract for a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.

    Dubai’s Roads & Transport Authority (RTA) held an online meeting after the submissions to prepare for the prequalification phase of tendering, expected to start in a few weeks.

    The scope covers about 30 kilometres (km) of works.

    These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.

    The RTA floated the expression of interest notice to contractors in early September.

    The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.

    Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.

    The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through traffic while existing at-grade lanes served local access.

    The plans ultimately became standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.

    The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.

    Planning for growth

    Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20745908/main.jpg
    Yasir Iqbal
  • Libya seeks offshore contractors for $8bn gas project

    19 October 2026

    Libya’s Mellitah Oil & Gas Company (MOG) has invited companies to prequalify for a major offshore package as part of its Mellitah Complex Expansion & CO2 Management Integrated Development Project, which is estimated to be worth about $8bn.

    The package is estimated at around $3bn and focuses on developing offshore pipelines and subsea systems for the “E” Offshore Installation Project and CO2 project.

    The deadline to submit prequalification documents is 5 November. The contract will use the engineering, procurement, installation and commissioning (EPIC) model.

    MOG is a joint venture of Libya’s National Oil Corporation and Italian oil and gas company Eni.

    This is not the first time MOG has invited submissions for the offshore pipelines and subsea systems package. The company originally launched a prequalification process for the EPIC contract in 2021, but the project experienced delays and the process was eventually cancelled. The prequalification process was restarted nearly three years later, but it was also ultimately abandoned.

    Complex expansion

    As part of the Mellitah Complex Expansion & CO2 Management Integrated Development Project, two offshore structures – Structure A and Structure E – will be developed in Libya’s offshore block NC 41.

    Structure A is in the central-western part of the area, about 80 kilometres (km) from the Libyan coast, with a water depth of 95-105 metres.

    Structure E is located in the central-eastern part of the area, about 130km from the Libyan coast, in a water depth of 205-235 metres.

    The scope of the wider project includes:

    • A new wellhead platform installed in 96 metres of water as part of the development of Structure A
    • A new production platform installed in about 220 metres of water depth as part of the development of Structure E
    • Modification of the existing Sabratha platform
    • Sealines and subsea systems for structures A and E
    • Upgrading the existing onshore Mellitah complex
    Project contract awards

    In June 2024, MOG awarded an offshore engineering, procurement and construction (EPC) contract worth €1.2bn ($1.28bn), which was part of the Mellitah Complex Expansion & CO2 Management Integrated Development Project.

    The contract was awarded to a consortium of three Italian companies: Rosetti Marino, Kerry Project Logistics and Gruppo Antonini.

    In a statement, Rosetti Marino said its share of the project contract was worth €400m ($428m), comprising 33% of the total contract value.

    Rosetti Marino said its scope of work includes EPC and load-out activities to deliver the topside of the approximately 6,000-tonne gas production wellhead platform, named WHP-A, to be installed off the coast of Libya.

    Project setbacks

    During 2023 and 2024, several setbacks affected the Mellitah Complex Expansion & CO2 Management Integrated Development Project.

    In November 2023, MOG restarted the prequalification process for an upstream offshore package worth an estimated $700m.

    The project scope involves modifications to the offshore Sabratha platform at the Bahr Essalam field.

    Less than two months later, MOG restarted prequalification for a second package as part of the integrated development project.

    The scope of the second package covers key sealine and subsea systems.

    No reason was given for restarting the prequalification process for two of the project’s packages.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20738707/main.jpg
    Wil Crisp