Manama jumpstarts utility sector
4 November 2024

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).
The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.
The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.
The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.
The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.
The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.
MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.
Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.
“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”
A different set of factors will be at play for the Sidra IWPP, however.
For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.
According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.
The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.
Solar PV projects
The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.
China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).
In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.
The power plant will be located at several premises, including at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.
The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.
The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.
Water and waste
Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.
It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.
The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials
However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.
The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.
As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.
The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.
Exclusive from Meed
-
-
-
-
-
Firms submit Jeddah distribution centre bids4 May 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Parsons wins role on Elon Musk-backed Dubai Loop project4 May 2026
US-based Parsons Corporation has been appointed to deliver programme management services for the Dubai Loop transportation system.
The contract was awarded by Elon Musk-backed firm The Boring Company, which signed a construction agreement with Dubai’s Roads & Transport Authority (RTA) in February.
Parsons’ scope of work includes independent design verification, stakeholder management, permitting and no-objection certificate (NOC) support, and multidisciplinary design reviews for the project’s first phase.
The first phase comprises a 6.4-kilometre route with four stations, linking the Dubai International Financial Centre (DIFC) and Dubai Mall.
Stations will be located at DIFC 2, ICD Brookfield Place, Dubai Mall Zabeel Parking and Burj Khalifa.
The first phase is expected to cost about AED565m ($154m) and to be delivered within one year after design work and other preparations are completed. Tunnelling is expected to begin in the second half of this year.
Next phase
The second phase will connect Dubai World Trade Centre and DIFC with Business Bay.
The tunnels will extend up to 22km and include 19 stations.
The total cost across both phases is expected to be around AED2bn ($545m), with completion scheduled within three years.
The pilot route is expected to serve around 13,000 passengers a day, while the full route is projected to have a capacity of about 30,000 passengers a day.
The RTA and The Boring Company signed a memorandum of understanding on the sidelines of the World Governments Summit in Dubai in February last year to explore the development of the Dubai Loop transportation system.
The Dubai Loop is expected to be similar to The Boring Company’s Las Vegas Convention Centre (LVCC) Loop project. The LVCC Loop is a 2.7km underground tunnel system that connects different convention centre halls, reducing walking time across the site to about two minutes.
The LVCC Loop has been in operation since 2021. It uses Tesla Model 3 cars to carry passengers between five stations. The Boring Company began construction in November 2019 at an estimated cost of $49m.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16672074/main.jpg -
Humain tenders infrastructure for 6GW data centre campus4 May 2026
Saudi artificial intelligence (AI) infrastructure company Humain, owned by the Public Investment Fund (PIF), has issued a tender inviting firms to develop infrastructure for its planned 6GW hyperscale AI data centre campus in Riyadh.
The project will be delivered on an early contractor involvement (ECI) basis. Under the ECI process, selected contractors are required to submit methodologies and design proposals, after which one team will be selected to deliver the construction works.
Firms have until 8 May to submit proposals.
The development will be built on a 24-square-kilometre site in the Al-Saad area in east Riyadh. It will be delivered in two phases across six plots, each with a capacity of 1GW.
The scope of infrastructure work covers:
- Construction of 380kV/132kV/33kV electrical distribution network, two substations with a capacity of 500MVA and 200MVA, bulk supply point (2,000MVA)
- Water network and fire protection systems
- Sewage treatment plant and wastewater network
- Stormwater systems
- Roads
- Underground cable and fibre optic networks
- Landscaping works
The client is being supported by Canadian engineering firm Hatch, France’s Egis and US-based firm JLL.
Humain was launched in May last year to operate and invest across the AI value chain.
Humain is building full-stack AI capabilities across four core areas: next-generation data centres, hyper-performance infrastructure and cloud platforms, and advanced AI models, including Allam.
Also in May 2025, Humain signed preliminary deals with US chipmakers AMD and Nvidia to build multibillion-dollar advanced digital infrastructure in the kingdom.
AMD said it will invest up to $10bn to deploy 500MW of AI compute capacity in Saudi Arabia over the next five years.
In October, PIF and Saudi Aramco signed a non-binding term sheet setting out key terms under which Aramco would acquire a minority stake in Humain, with PIF retaining majority ownership.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16671267/main.jpg -
Abu Dhabi selects consortium for 2.5GW Taweelah C IPP4 May 2026

Register for MEED’s 14-day trial access
A consortium of Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore) has been selected to develop the Taweelah C independent power producer (IPP) project in Abu Dhabi.
The consortium will sign a power purchase agreement (PPA) in mid-May, a source told MEED.
The combined-cycle gas turbine (CCGT) plant will have a capacity of 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.
It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction (EPC) contractor.
Last September, MEED reported that state offtaker Emirates Water & Electricity Company (Ewec) had received three bids for the facility.
The bidders included:
- Al-Jomaih Energy & Water Company / Sembcorp Industries
- Sumitomo Corporation (Japan) / Korea Overseas Infrastructure & Urban Development Corporation / Korean Midland Power
- Korea Western Power Company / Etihad Water & Electricity (UAE) / Kyuden International (Japan)
At the time, Mohamed Al-Marzooqi, chief asset development and management officer at Ewec, said the bids would make Taweelah C “one of the lowest tariff CCGT projects in the region”.
The carbon-capture-ready facility had been scheduled to begin commercial operations in the fourth quarter of 2028.
This was based on the initial timeline for a PPA to be signed in the fourth quarter of 2025.
Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.
Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared to 2019.
Ewec is also expanding its low-carbon water desalination capacity, with the Taweelah reverse osmosis (RO) plant already operating as the world’s largest RO facility and additional projects, such as the Mirfa 2 RO and Shuweihat 4 RO, under way.
By 2030, it expects 95% of Abu Dhabi’s installed water capacity to come from RO technology.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16670622/main0858.jpg -
Dubai launches Blue Line metro tunnelling works4 May 2026
Dubai has announced the launch of tunnelling works for the Dubai Metro Blue Line extension project.
In a post on X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President, Prime Minister and Ruler of Dubai, announced the start of operations of the tunnel boring machine (TBM), which the Roads & Transport Authority (RTA) has named ‘Al-Wugeisha’.
The TBM is 163 metres long, weighs more than 2,000 tonnes and will operate around the clock. The post added that its average excavation rate ranges from 13 to 17 metres a day.
The Blue Line will connect the existing Red and Green lines. It will be 30 kilometres (km) long, with 15.5km underground and 14.5km above ground.
The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.
In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project to a consortium comprising Turkiye’s Limak Holding and Mapa Group, along with the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).
The consortium is responsible for all civil works, electromechanical works, rolling stock and rail systems. After completing the project, it will assist with maintenance and operations for an initial three-year period.
According to an official statement, the Blue Line will have a capacity of 46,000 passengers an hour in both directions.
The project is scheduled for completion in September 2029.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16670584/main.jpeg -
Firms submit Jeddah distribution centre bids4 May 2026

Contractors submitted bids on 26 April for an estimated SR140m ($37m) contract to build a distribution centre in Jeddah.
Saudi Logistics Services Company (SAL) launched the tender on 11 March, as previously reported by MEED. The project will cover an area of about 37,000 square metres. Egyptian firm Cosmos-E Engineers & Consultants has been appointed as the project consultant.
This tender follows the start of construction by Egyptian contractor Rowad Modern Engineering, a subsidiary of Elsewedy Electric Group, on the expansion of SAL’s facilities at King Khalid International airport in Riyadh. The scope of work includes rehabilitating and upgrading existing infrastructure, as well as constructing new supporting facilities and services.
SAL also launched the tendering process in September last year for its SR4.2bn ($1bn) logistics zone in northern Riyadh, MEED previously reported. UAE-based Global Engineering Consultants is the consultant for that development.
The logistics hub aims to meet demand for customised warehouses near King Khalid International airport and the Riyadh Metro. The project aligns with Vision 2030 and the National Transport & Logistics Strategy, which aims to strengthen the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16670338/main.gif
.gif)
