Manama jumpstarts utility sector
4 November 2024

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).
The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.
The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.
The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.
The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.
The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.
MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.
Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.
“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”
A different set of factors will be at play for the Sidra IWPP, however.
For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.
According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.
The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.
Solar PV projects
The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.
China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).
In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.
The power plant will be located at several premises, including at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.
The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.
The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.
Water and waste
Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.
It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.
The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials
However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.
The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.
As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.
The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg