Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • Contractor appointed for Abu Dhabi Riviera residences

    1 July 2026

     

    Dubai-based real estate developer Mered has appointed Turkiye’s Sera Group as the main contractor for its Riviera Residences project on Al-Reem Island in Abu Dhabi.

    The development will comprise more than 400 one- to three-bedroom apartments and 11 villas.

    Lebanese engineering firm Dar Al-Handasah is the project consultant, while Switzerland’s Herzog & de Meuron is the architect.

    The enabling works are being carried out by local contractor NSCC International.

    Mered and Sera Group are also working together on the Iconic Tower project in Dubai Internet City, where the developer awarded the main contract in December 2024.

    The 67-storey tower is being built on a site covering about 6,368 square metres.

    Local firm Mirage is the project consultant, while Singapore-based Hirsch Bedner Associates is the project architect.

    Dubai-based Chawla Architectural & Consulting Engineers is the architect of record, and Omnium International is the quantity surveyor.

    The foundation works were carried out by local firm Dutch Foundations.

    Mered’s latest contract awards in the UAE market come amid heightened real estate and construction activity, with schemes worth more than $323bn at the execution or planning stages, according to UK-based analytics firm GlobalData.

    GlobalData forecasts that output from the UAE’s residential construction sector will grow by 3% in real terms in 2026-29, supported by infrastructure, energy and utilities developments, as well as residential construction projects.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17509888/main.jpg
    Yasir Iqbal
  • Aramco extends deadline for Ras Tanura refinery gas pipeline

    1 July 2026

     

    Saudi Aramco has granted contractors more time to prepare bids for a tender to replace a pipeline in the Gas Line Abqaiq–Ras Tanura (GART) transmission network.

    The GART grid transports associated gas and natural gas liquids (NGL) from the Abqaiq oil processing complex as feedstock, northwards to the Ras Tanura refinery in Saudi Arabia’s Eastern Province.

    The aim of the project is to replace the GART-22 pipeline that connects the Juaymah export terminal on the Gulf coast in the Eastern Province to the Ras Tanura refinery, to ensure reliable fuel gas supply and meet ongoing demand.

    The basic scope of work for the project is to install a new 24-inch pipeline system to replace the GART-22 line and the abandoned GART-24 line. It will cover a distance of 18 kilometres between Juaymah and the Ras Tanura terminal.

    The scope also includes the installation of associated scraper trap facilities (launcher and receiver), pressure control valves, motor-operated valves and gas detection and sampling systems.

    Aramco issued the tender for the project in May, setting an initial deadline of 30 June for contractors to submit proposals, MEED previously reported.

    The Saudi energy giant has now extended that deadline until 10 July, according to sources.

    The following contractors, among others, are understood to be bidding for the project:

    • ACE Pipeline Arabia
    • Combined Group Contracting Company
    • Gas Arabian Services Company
    • Max Streicher Saudi Arabia
    • National Basics Company
    • Saad Ali Alessa Group
    • Sicim
    • Sinopec Engineering Group Saudi
    • Tecton Engineering & Construction
    Ras Tanura refinery complex

    The Ras Tanura refinery is the oldest, and one of the largest, crude oil refineries in Saudi Arabia. The complex has a refining capacity of 550,000 barrels a day (b/d).

    The facility also has a 305,000 b/d NGL processing facility, a 960,000 b/d crude stabilisation facility, combined steam and gas turbine electrical power generation plants with a summer capacity of 145MW and a winter capacity of 158MW, and a combined 150-pound and 600-pound steam capacity of 6,217 million pounds an hour.

    It has 75 crude oil and products storage tanks with a combined capacity of 5.8 million barrels.

    The Ras Tanura refinery’s major facilities include a 325,000 b/d crude distillation unit, a 225,000 b/d gas condensate distillation unit, a 50,000 b/d hydrocracker and 107,000 b/d of catalytic reforming capacity.

    The facility is Aramco’s only refinery to contain a Visbreaker processing unit, which has a 60,000 b/d capacity.

    The Visbreaker reduces the quantity of residual oil produced in the distillation of crude oil and increases the yield of more valuable middle distillates, heating oil and diesel.

    The refinery complex also produces 17,000 b/d of asphalt, more than any other refinery in Saudi Arabia.

    Ras Tanura receives crude feedstock from the Abqaiq, Safaniya and Manifa oil field developments.

    Crude is typically transferred to Ras Tanura through a pipeline and can also be supplied by ship.

    Most of Ras Tanura’s production is transferred to the Dhahran bulk plant for domestic use, while some products are exported from the nearby Ras Tanura shipping terminal.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17508681/main4014.jpg
    Indrajit Sen
  • Siemens Energy to supply turbines for Oman IPP projects

    1 July 2026

    Germany’s Siemens Energy has announced it will supply power generation technology and long-term service agreements for the 2.6GW Misfah and Duqm independent power producer (IPP) projects in Oman.

    The scope includes the supply of six F-class gas turbines, six generators and 20-year long-term service agreements for the equipment.

    The combined-cycle gas-fired plants will add almost 20% to the sultanate’s electricity generation capacity. They are expected to provide electricity to more than two million people.

    Oman’s Nama Power & Water Procurement (Nama PWP) signed power-purchase agreements (PPAs) for the development and operation of the plants in January.

    The two combined-cycle gas turbine plants are being developed by a consortium comprising Korea Western Power (Kowepo), Qatar’s Nebras Power, the UAE’s Etihad Water & Electricity (EtihadWE) and Oman’s Bhawan Infrastructure Services.

    The Misfah IPP will be led by Nebras Power and located in Wilayat Bousher in Muscat Governorate, with a planned capacity of 1,600MW.

    The Duqm IPP will be led by Kowepo and located in Wilayat Duqm in Al-Wusta Governorate, with a capacity of 800MW.

    In May, MEED exclusively reported that a consortium of China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility had been appointed as the main contractor.

    The gas turbines will have hydrogen co-firing capability, providing flexibility to increase hydrogen use over time, Siemens said in a statement.

    The turbines will be manufactured at Siemens Energy’s facility in Berlin. The generators will be produced at the company’s plant in Muelheim, Germany.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17506190/main.jpg
    Mark Dowdall
  • Qiddiya awards estimated $1bn racecourse deal

    1 July 2026

     

    Register for MEED’s 14-day trial access 

    Saudi gigaproject developer Qiddiya Investment Company (QIC) has awarded an estimated SR4.3bn ($1.1bn) contract for the construction of a racecourse at Qiddiya entertainment city, on the outskirts of Riyadh.

    The contract was awarded to Taj Dhabi, a local subsidiary of UAE-based Trojan Construction.

    The racecourse venue will cover 1.3 million square metres and accommodate 70,000 spectators.

    QIC issued the tender for the construction works in December last year, but formally announced the project only on 10 February. Contractors submitted their bids on 15 February, MEED previously reported.

    According to a statement published on QIC’s website: “The venue will include the region’s first straight-mile turf course, alongside a 2.2 kilometre (km) main turf track and a 2.4km inner dirt track.

    “A 21,000-seat grandstand will anchor the venue, with the ability to expand capacity to up to 70,000 guests through event overlays during major race days,” the statement added.

    A centrepiece of the venue will be a 110-metre central parade ring, located in the middle of the racecourse.

    The project also includes an equine hospital that will provide advanced veterinary services, including diagnostics, surgery, rehabilitation and emergency care for horses.

    The Qiddiya City horse racing venue is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, the Prince Mohammed Bin Salman Stadium, a motorsports track, a performing arts centre, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    The project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    GCC presses ahead with tourism projects


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17506035/main.jpg
    Yasir Iqbal
  • NCP seeks firms for Saudi Arabia university hospital PPP

    1 July 2026

    Saudi Arabia’s Umm Al-Qura University, in collaboration with the National Centre for Privatisation & PPP (NCP), has launched an expression of interest for the completion of the construction and operation of the Umm Al-Qura University Hospital in Mecca.

    Issued to contractors on 30 June, the notice has a submission deadline of 21 July.

    The scope includes completing the remaining construction works, as well as the subsequent operation of the hospital.

    Upon completion, the hospital will have a capacity of 391 beds.

    The project will be delivered as a public-private partnership (PPP) under a design, build, finance, operate and maintain model.

    The contract duration is 30 years.

    The project is the latest healthcare project to be procured on a PPP basis in the kingdom. In June, MEED reported that Saudi Arabia’s Ministry of Health and NCP had awarded a PPP contract for the operation and management of the Sabic Specialised Behavioural Healthcare Hospital in Riyadh.

    That contract was awarded to SEH Healthcare, a consortium comprising local firms Specialised Medical Company (SMC Healthcare) and Health Gates Complex, and Germany’s Dr Ebel Fachkliniken.

    In a filing with the Saudi Exchange (Tadawul), SMC Healthcare said the total estimated project value is about SR3.8bn ($1bn).

    In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.

    Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.

    In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17506381/main.jpg
    Yasir Iqbal