Manama jumpstarts utility sector
4 November 2024

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).
The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.
The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.
The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.
The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.
The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.
MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.
Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.
“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”
A different set of factors will be at play for the Sidra IWPP, however.
For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.
According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.
The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.
Solar PV projects
The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.
China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).
In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.
The power plant will be located at several premises, including at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.
The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.
The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.
Water and waste
Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.
It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.
The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials
However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.
The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.
As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.
The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.
Exclusive from Meed
-
Local firm wins contract for Kuwait power project19 November 2025
-
UKEF issues $3.5bn interest letter for Al-Maktoum airport19 November 2025
-
Riyadh gives Expo infrastructure bidders more time19 November 2025
-
NHC and Turkish firm sign $266m investment deal19 November 2025
-
Egypt announces oil discovery in Western Desert19 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Local firm wins contract for Kuwait power project19 November 2025
Local firm Alghanim International has won a contract to provide engineering services at the Subiya power and water distillation plant.
Kuwait’s Central Agency for Public Tenders approved the award following a request from the Ministry of Electricity, Water & Renewable Energy.
The contract, valued at $286m, covers engineering, supply, installation, operation and maintenance services to convert the 250MW second phase of the plant’s open-cycle gas turbines to combined-cycle gas turbines.
The upgrade is intended to increase efficiency and provide additional generation capacity during periods of high demand.
In July, MEED reported that Alghanim had submitted the lowest bid for the tender ahead of local firms Al-Daw Engineering General Trading & Contracting and Al-Zain United General Trading & Contracting.
In 2024, US-based GE Vernova completed separate upgrades of four GE Vernova 9F.03 class gas turbines at the 2GW Sabiya combined-cycle power plant. Alghanim International acted as GE’s local engineering partner for that work.
The Subiya power and water distillation plant is the largest power and water plant in Kuwait, with a power generation capacity of 7,046.7MW, accounting for 35% of the country’s installed capacity.
It has a water desalination capacity of 100 million imperial gallons a day.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15116135/main.jpg -
UKEF issues $3.5bn interest letter for Al-Maktoum airport19 November 2025
Register for MEED’s 14-day trial access
The UK’s export credit agency UK Export Finance (UKEF) has issued a $3.5bn expression of interest letter to support the participation of UK businesses in the $35bn expansion of Al-Maktoum International airport, which is also known as Dubai World Central (DWC).
Chris Bryant, UK minister for trade, handed the letter to Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai Aviation Engineering Projects (DAEP), and Paul Griffiths, CEO of Dubai Airports.
Letters of interest from UKEF, although not binding commitments, help ensure that UK exporters are given every opportunity to bid for contracts on a project. This is typically achieved by providing financial solutions in exchange for an agreed level of UK content used on the project.
Previous letter
It is not the first time UKEF has issued a letter of interest for the expansion of Al-Maktoum International airport. In 2014, it issued a $2bn letter of interest. In a statement at the time, UKEF said five prime UK-based contractors were being supported, along with UK suppliers across the supply chain.
The five prime contractors were Carillion, Kier, Balfour Beatty, Laing O’Rourke and Interserve. Of those five companies, Carillion entered liquidation in 2018 and Interserve entered administration in 2019. Balfour Beatty sold its shareholding in Dubai-based Dutco Balfour Beatty in 2017.
Although some progress was made on the project after the UKEF offer in 2014, the scheme stalled and was revived again in April 2024, when Dubai approved new designs for the airport.
Project progress
Since then, the project client, DAEP, has been awarding and tendering contracts for the first construction packages. It has awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works for the terminal building are being undertaken by Abu Dhabi-based Tristar E&C.
DAEP is also close to formally awarding a contract for the substructure works for the West Terminal and Concourse One, Concourse Two and Concourse Three.
Tendering is also ongoing for an automated people-mover (APM) system. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The airport’s construction is planned to be undertaken in three phases. Construction works on the project’s first phase are expected to be completed by 2032.
The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
Dubai has said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
This aviation package also includes:> Middle East invests in giant airports
> Broader region upgrades its airports
> Global air travel shifts easthttps://image.digitalinsightresearch.in/uploads/NewsArticle/15115788/main.jpg -
Riyadh gives Expo infrastructure bidders more time19 November 2025

Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has extended the deadline for firms to submit commercial offers for the contract to undertake the initial infrastructure works at the site to 23 November.
ERC had initially set deadlines of 26 October and 9 November for the submission of technical and commercial bids, respectively.
The tender for the project’s initial infrastructure works was issued in September, as MEED reported.
In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.
The firms invited to bid include:
- Shibh Al-Jazira Contracting (local)
- Hassan Allam Construction (Egypt)
- El-Seif Engineering Contracting (local)
- Al-Ayuni Investment & Contracting (local)
- Kolin Construction (Turkiye)
- Al-Yamama Trading & Contracting Company (local)
- Saudi Pan Kingdom (local)
- Unimac (local)
- Mapa Insaat (Turkiye)
- Yuksel Insaat (Turkiye)
- IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
- Mota-Engil / Albawani (Portugal/local)
- Almabani / FCC Construction (local/Spain)
The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:
- Lot 1 covers the main utilities corridor
- Lot 2 includes the northern cluster of the nature corridor
- Lot 3 comprises the southern cluster of the nature corridor
MEED previously reported that ERC was expected to issue the tender for some of the infrastructure packages in September.
In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.
Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.
The expo is forecast to attract more than 40 million visitors.
The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.
In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/15115697/main.jpg -
NHC and Turkish firm sign $266m investment deal19 November 2025
Register for MEED’s 14-day trial access
Saudi Arabia’s National Housing Company (NHC) has signed an investment agreement worth over SR1bn ($266m) with Turkiye’s Emlak Konut to develop new residential communities within the Mecca Gate project in Mecca.
The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.
Emlak Konut will develop 1,000 residential villas spanning over 255,000 square metres (sq m).
The latest agreement follows the NHC’s signing of deals worth over SR8.5bn ($2.2bn) for the development of two mixed-use and residential communities in Riyadh.
The first agreement, worth over SR5.2bn ($1.4bn), was signed with local developer Retal Urban Development Company.
The deal encompasses the development of 4,839 residential units in the Al-Fursan suburb of Riyadh.
The other contract, worth over SR3.3bn ($880m), was signed with a joint venture of Egypt’s Hassan Allam Holding and local developer Tilal Real Estate for a mixed-use project in the Khozam district.
The development will cover an area of over 228,000 sq m.
It will be delivered through Grova Developments, the development arm of Hassan Allam Holding.
In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.
Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers.
MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.
By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15115626/main.png -
Egypt announces oil discovery in Western Desert19 November 2025
Register for MEED’s 14-day trial access
A new gas discovery has been made in Egypt’s Western Desert region, according to a statement released by the Ministry of Petroleum & Mineral Resources.
The discovery was made by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation (EGPC) and US-headquartered Apache Corporation.
The field is expected to be brought online this week, according to the ministry.
The reserves were discovered after drilling the exploratory well ‘Gomana-1’, the ministry said.
It added that sensors confirmed the presence of gas reserves, and tests indicated that the well is expected to have a production rate of around 36 million standard cubic feet of gas a day.
Further tests are ongoing, and the initial evaluation of the well’s reserves is currently being finalised.
The ministry said that the discovery followed the introduction of new incentives designed to encourage additional gas investment within Khalda’s areas of operation.
Earlier this month, Egypt started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.
The country is currently pushing to increase domestic gas production in order to meet domestic demand and reduce its import bill.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15112551/main.png



