Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • Contractors submit revised bids for Dukhan field facilities upgrade

    6 October 2026

     

    Contractors have submitted revised proposals to QatarEnergy for a key tender to upgrade facilities at the Dukhan oil field in Qatar, about 80 kilometres west of Doha.

    Following the submission of the initial round of bids for the project on 9 August, QatarEnergy requested revised proposals from contractors, which they submitted by 27 September, sources told MEED.

    The following local contractors, among others, are understood to be bidding for the DPFU Phase 1B (Part 2) tender, according to information obtained by MEED Projects:

    • Doha Petroleum Construction Company (Dopet)
    • Galfar Al-Misnad Engineering & Contracting
    • Qatar Engineering & Construction Company (Q-con)

    QatarEnergy originally stipulated a bond validity of 150 days (until 23 December) and a bid validity of 120 days (until 23 November) for the project.

    The engineering, procurement, installation and commissioning scope covers upgrades to 56 oil manifolds, 108 gas-lift manifold slots, chemical injection systems and key pumping facilities, along with associated piping, instrumentation, control, electrical and civil works.

    The scope includes the demolition of obsolete equipment, degassing station enhancements, and full testing and handover. It also encompasses additional capacity enhancement works under Part 3, mainly the installation of new oil export and produced-water transfer pumps, along with supporting facility modifications.

    The project involves complex interfaces and shutdown-critical activities, requiring expertise in live-plant integration.

    QatarEnergy issued the tender for the DPFU Phase 1B (Part 2) project on 8 June and initially set a bid submission deadline of 26 July, later extending it to 9 August.

    Dukhan, Qatar’s first and only onshore oil field, was discovered in 1938, with oil production starting in 1939-40. The country currently produces about 1.8 million barrels a day (b/d) of crude, with the Dukhan field accounting for about 350,000 b/d.

    The Dukhan oil field covers about 80km by 8km and consists of four reservoirs: Khatiyah, Fahahil, Jaleha and Diyab. The first three are oil reservoirs. The more recently developed Diyab reservoir contains non-associated gas and is estimated to hold around 2 billion barrels of crude oil reserves. Diyab lies on Dukhan’s southern flank.

    ALSO READ: QatarEnergy selects contractors for offshore oil field expansion
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20306273/main5440.jpg
    Indrajit Sen
  • Dubai issues PMC tender for four stormwater projects

    6 October 2026

     

    Dubai Municipality has invited consultants to bid for a contract to provide construction supervision services for four stormwater projects.

    The bid submission deadline is 29 October.

    All four projects are part of the municipality’s Tasreef programme, intended to increase Dubai’s rainwater drainage capacity by 700% by 2033 and provide capacity for the emirate’s needs for the next 100 years.

    The tender for TF-06-S1 Supervision of Stormwater Drainage System Projects – Package 4 was issued on 6 October.

    The consultancy covers the following projects:

    • TF-06-C1: Construction of a stormwater pond connecting Al-Maktoum Airport and Dubai South
    • TF-06-C2: Construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
    • TF-07-C1: Construction of a stormwater drainage system on Sheikh Zayed Bin Hamdan Road connecting developers
    • TF-24-C1: Connecting developers’ areas to the stormwater networks in Dubailand 

    In documents seen by MEED, the municipality said it will require a dedicated supervision team for each project.

    The consultancy will cover construction supervision, including the deployment of resident engineers, civil engineers, inspectors, quantity surveyors, land surveyors and planning engineers. Mechanical engineers will also be required, along with health and safety personnel and NOC engineers, depending on the project. 

    TF-07-C1 is the same strategic stormwater drainage project that Dubai Municipality recently tendered for construction, with contractors preparing to submit bids on 22 October.

    The project covers more than 100 million square metres between Sheikh Mohammed Bin Zayed Road and Emirates Road, and from Expo Road to Dubailand.

    It will provide stormwater infrastructure and service connections for more than 20 private developers and Al-Yalayis 5, as well as supporting major roads in the Jebel Ali area. The construction scope includes a major gravity drainage system with pipeline diameters of up to 3,000mm.

    TF-24-C1 is one of three water infrastructure tenders issued by the municipality in August, as reported by MEED. The project will connect developers’ areas in Dubailand to the stormwater network. It includes 18 kilometres (km) of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.

    Bidding for the engineering, procurement and construction contract was recently extended to 1 October, with Nael Construction & Contracting and Al-Nasr Contracting Company among those expected to make an offer for the project.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20305174/main.jpg
    Mark Dowdall
  • Aramco nears contract award for Jafurah fifth expansion phase

    6 October 2026

     

    Saudi Aramco is believed to be close to awarding the main contract for a major project representing the fifth expansion phase of the Jafurah unconventional gas development programme in Saudi Arabia.

    The main scope of work for the fifth expansion phase of Jafurah involves the engineering, procurement and construction (EPC) of three gas compression plants at the gas basin in the kingdom’s Eastern Province. Each plant will be capable of processing up to 200 million cubic feet a day (cf/d).

    Indian contractor Larsen & Toubro Energy Hydrocarbon (L&TEH) is the favourite to win the main EPC contract, according to sources.

    “Negotiations between Aramco and L&T have reached an advanced stage and the [Indian] contractor is now in pole position to clinch the deal,” one source told MEED.

    MEED previously reported that China Petroleum Engineering & Construction Company (CPECC) was in a favourable position to secure the main EPC contract for the Jafurah fifth expansion phase, based on Aramco’s initial evaluation of proposals. The situation remained subject to change as Aramco negotiated with the project’s other bidders, MEED reported in August.

    Aramco set 19 July as the final deadline for proposals, and contractors submitted their bids by that date, MEED previously reported.

    ALSO READ: Aramco receives interest for major gas processing plant

    The Saudi energy giant is understood to have issued the main EPC tender for the project in the first quarter of this year.

    Aramco issued a solicitation of interest for the Jafurah fifth expansion phase in mid-November, with contractors submitting responses by 30 November, MEED previously reported.

    UK-headquartered Wood Group has carried out the front-end engineering and design for the project.

    The Jafurah basin is the largest liquid-rich shale gas play in the Middle East, spanning about 17,000 square kilometres. The reserve is estimated to contain 229 trillion cubic feet of gas and 75 billion stock-tank barrels of condensate.

    Aramco recently brought the greenfield Jafurah gas processing plant online, with a production capacity of 450 million cf/d, marking the commissioning of the first phase of its $100bn capital expenditure programme to produce gas from the unconventional resource base.

    The company previously stated that it expected to start gas production at Jafurah in 2025, with the intention of progressively ramping up to 2 billion cf/d of sales gas, 420 million cf/d of ethane and 630,000 barrels a day (b/d) of high-value liquids by 2030.

    Aramco has said that its unconventional gas programme, at peak production, is expected to generate electricity equivalent to displacing 500,000 b/d of oil.

    Jafurah gas development phases

    Alongside nearing an EPC contract award decision for the fifth expansion phase at Jafurah, MEED also recently reported that Aramco had completed the solicitation of interest process with contractors for the unconventional gas programme’s sixth phase.

    The main scope of work on the Jafurah sixth expansion phase is similar to the fifth phase, and involves the EPC of three gas compression plants at the giant gas reserve, each with an output capacity of 200 million cf/d.

    Aramco also kicked off EPC works on the Jafurah fourth expansion phase in the second quarter of the year.

    MEED reported in April that Aramco had selected Mumbai-headquartered L&TEH as the main contractor for the fourth phase, which sources estimate could be valued at about $1.5bn.

    The main scope of work on Jafurah’s fourth expansion phase involves the EPC of two gas compression trains at the gas basin. Each plant will be able to process up to 200 million cf/d.

    EPC work on the third phase of the Jafurah unconventional gas development programme is also advancing.

    In July 2024, Aramco issued a non-binding letter of intent to a consortium of Tecnicas Reunidas and Sinopec Group for the EPC contract for phase three. The contract is estimated at $2.24bn.

    The objective of the third expansion phase is similar to that of the fourth phase. The main scope of work involves the EPC of three gas compression plants, each with a capacity of 200 million cf/d.

    The third phase’s scope of work also includes building a 230kV substation to power the new gas compression plants, and installing other utilities units, piping systems and safety equipment.

    The selection of contractors for the third expansion phase came within weeks of Aramco officially awarding EPC contracts for the second phase, which aims to raise the field’s processing potential to up to 2 billion cf/d of raw gas.

    Aramco awarded 16 contracts, worth a combined total of about $12.4bn, for the second expansion phase on 30 June 2024.

    The EPC scope of work for that project involves the construction of gas compression facilities and associated pipelines, and the expansion of the Jafurah gas plant, including the construction of gas processing trains, utilities, sulphur and export facilities, Aramco said in a statement.

    The main EPC packages of the Jafurah second expansion phase project, their estimated values and the selected contractors are:

    • Package 1 – gas processing plant and main process units – $2.9bn: Larsen & Toubro Energy Hydrocarbon (India)
    • Package 2 – utilities and offsites – $2.4bn: Hyundai Engineering (South Korea)
    • Package 3 – gas compression units – $1bn: Larsen & Toubro Energy Hydrocarbon
    • Riyas natural gas liquids (NGL) package 1 – NGL fractionation trains – $1bn: Tecnicas Reunidas / Refining & Chemical Engineering Group (part of China’s Sinopec Group)
    • Riyas NGL package 2 – utilities, storage and export facilities – $2.2bn: Tecnicas Reunidas/Refining & Chemical Engineering Group
    • Riyas NGL package 6 – site preparation works – $107m: Mofarreh Alharbi & Partners (Saudi Arabia)
    • Riyas NGL package 9 – temporary construction facilities – $80m: Mofarreh Alharbi & Partners

    Aramco kickstarted EPC works on the first phase of the programme in November 2021 by awarding $10bn-worth of subsurface and EPC contracts.

    In February 2020, Aramco received a capital expenditure grant of $110bn from the Saudi government for the long-term phased development of the Jafurah unconventional gas resource base.

    The Jafurah programme is central to Aramco’s goal of increasing gas production capacity. The target has recently been raised to 80%, with 2021 as the baseline, up from 60%, to meet rising domestic and global demand. The company expects life-cycle investment in Jafurah to exceed $100bn.

    Aramco completed an $11bn lease-and-leaseback deal in late October 2025 for gas processing facilities at the Jafurah unconventional gas reserve with a consortium led by funds managed by Global Infrastructure Partners (GIP), part of US asset manager BlackRock.

    Under the transaction, a newly formed subsidiary, Jafurah Midstream Gas Company (JMGC), will lease development and usage rights to the Jafurah field gas processing plant and the Riyas natural gas liquids fractionation facility.

    After 20 years, JMGC will lease the assets back to Aramco. JMGC will collect a tariff payable by Aramco in exchange for granting Aramco the exclusive right to receive, process and treat raw gas from the Jafurah resource base.

    Aramco will hold a 51% majority stake in JMGC, while the GIP-led consortium will hold the remaining 49%. Investors participating in the GIP-led consortium include Hassana Investment Company, the Arab Energy Fund and Aberdeen Investcorp Infrastructure Partners, as well as other institutional investors from North and Southeast Asia and the Middle East.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20299556/main3638.jpg
    Indrajit Sen
  • Joint venture wins Riyadh data centre construction deal

    6 October 2026

     

    Register for MEED’s 14-day trial access 

    Egyptian contractor Hassan Allam Construction and India’s Sterling & Wilson have won an estimated SR750m ($200m) contract to build the first phase of a data centre project in Riyadh.

    The first phase will have an IT load capacity of 16.2MW, with overall capacity reaching 50MW in the second phase.

    The scope includes civil, architectural, and mechanical, electrical and plumbing (MEP) works, infrastructure works and other associated works.

    Upon completion of both phases, the facility will comprise one 5MW standard-density hall and four high-density halls, each rated at 11.2MW.

    Saudi Arabian artificial intelligence (AI) firm Humain and Center3 – the digital infrastructure subsidiary of local telecom company STC Group – are jointly developing the project.

    The first phase is scheduled to take 16 months.

    In December last year, Center3 and Humain partnered to develop and operate AI-focused data centres across Saudi Arabia, with a planned capacity of up to 1GW.

    The partners said the first phase will deliver up to 250MW of capacity, designed for high-density AI workloads and large-scale model training.

    The venture combines Center3’s data centre operations and regional connectivity with Humain’s full-stack AI capabilities, with the latter responsible for aligning facility design with advanced compute requirements and future architectures.

    The companies said the programme will deliver purpose-built facilities engineered for high power density, low latency and resilient operations, to support large language models and other mission-critical AI applications.

    They added that the initial schemes will serve as a template for subsequent rollouts as capacity scales towards the 1GW target.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20298893/main.jpg
    Yasir Iqbal
  • Chevron signs Egypt oil and gas exploration deal

    6 October 2026

    State-owned Egyptian Natural Gas Holding Company (Egas) and US-headquartered Chevron have signed an agreement related to oil and gas exploration in Egypt’s offshore Lotus concession.

    Under the agreement, Chevron will invest at least $88m in exploration activities within the concession, according to a statement from Egypt’s Ministry of Petroleum & Mineral Resources.

    Chevron has agreed to drill two deepwater exploration wells and to reprocess 3D seismic data for the concession.

    Egypt’s Ministry of Petroleum & Mineral Resources said the agreement was part of the ministry’s “efforts to expand exploration activities and unlock new areas for petroleum investments”.

    It also said that the deal reflected Chevron’s “commitment to pumping new investments into exploration activities in Egypt”.

    In August, Egypt’s Minister of Petroleum and Mineral Resources, Karim Badawi, presented the ministry’s five-year production strategy, which aims to double Egypt’s oil and condensate output while strengthening the country’s position as a regional hub for petroleum product trading and gas liquefaction.

    Egypt has been working towards this goal by forging a range of new deals with international oil companies.

    Chevron has offshore exploration and development rights for several Egyptian concessions, including Nargis, North El-Dabaa, North West Atoll, North Simian and North Cleopatra, where it partners with Shell.

    In April, Egypt’s cabinet approved a draft version of the Lotus concession agreement between Egas and Chevron during a meeting chaired by Prime Minister Mostafa Madbouly.


    READ THE OCTOBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Industry and logistics drive development at Neom; Saudi Arabia’s investment priorities realign amid conflict; MEED’s 2026 power developer ranking.

    Distributed to senior decision-makers in the region and around the world, the October 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/20298172/main.jpeg
    Wil Crisp