Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • Oman begins procurement for truck road PPP

    2 July 2026

     

    Oman’s Ministry of Transport, Communications & Information Technology (MTCIT) has tendered a contract for the sultanate’s second public-private partnership (PPP) road scheme.

    The project spans 66 kilometres between Al-Buraimi and Al-Dhahirah governorates, starting at the Al-Khatm border crossing in Mahdah and ending at the Al-Fath area in Dhank.

    Under the scheme, the winning bidder will design, build, finance and transfer the project, which is specially designed for heavy vehicles.

    MTCIT issued the tender on 30 June. The deadline to purchase tender documents is 11 August, and the clarification period will run from 11 to 18 August.

    The bid submission deadline is 30 January 2027.

    In August 2023, Oman shortlisted five of the eight prequalified teams to compete for the Salalah-Thumrait truck road (STTR) project, the sultanate’s first PPP road project.

    The project failed to materialise beyond that point.

    In January, MEED reported that Oman is planning to establish a new commercial railway line to transport essential supplies between Salalah and Thumrait – an initiative understood to have preceded the STTR project. The railway is planned to be implemented as a PPP.

    The scheme comprises the construction of a railway line approximately 150-170km long. Two main stations are planned: Salalah Station, near the port and food storage facilities, and Thumrait Station, which will serve as a distribution hub for the surrounding areas.

    Trains are expected to be equipped with refrigerated and dry containers. The scheme aims to reduce transport costs between the two areas by 20%-30%, and Oman plans to pitch the project to major food companies to secure long-term transport contracts.

    The proposed project timeline is:

    • 2025: Conduct economic, technical and environmental feasibility studies
    • 2026: Launch the project for investment on a PPP basis
    • 2027-30: Construction of the railway line
    • 2031: Trial operations
    • 2032: Full commercial operations

    The project is touted as a key initiative under Oman Vision 2040, which aims to transform the sultanate into a global logistics hub.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17525698/main.jpg
    Yasir Iqbal
  • Acwa signs Mauritania gas IPP agreements

    2 July 2026

    Saudi Arabia’s Acwa has announced it has signed the public-private partnership (PPP) and power-purchase agreements for the 230MW N’diago combined-cycle gas turbine (CCGT) power plant in Nouakchott, Mauritania.

    The agreements cover the development, financing, construction and operation of the project. They were signed in Nouakchott in the presence of senior officials from the Mauritanian government and Acwa chairman Mohammad Abunayyan.

    The project is Mauritania’s first large-scale gas-fired independent power project (IPP). It is also expected to be the country’s first major gas-fired power plant procured through a PPP structure.

    The CCGT plant will provide 230MW of baseload generation capacity. It will use Mauritania’s domestic natural gas resources to supply the national grid.

    Separately, Mauritanian Electricity Company (Somelec) has been advancing procurement for the construction of a 50MW solar power and battery energy storage system IPP project. It issued an expression of interest request in May.  

    Mauritania currently has several wind and solar power projects in the early study stages, according to regional project tracker MEED Projects.

    There are also plans to build a 1,200MW wind power plant near Port Etienne in the Bay Province of Nouadhibou, for which China Energy Engineering was appointed as the main contractor in 2024. 

    Meanwhile, Acwa’s portfolio comprises 111 assets that are operational, under construction or in advanced development. These represent investments of SR468.9bn ($125bn).

    According to the company, it has a power generation capacity of 98GW, including 52.3GW of renewable energy, and manages 9.7 million cubic metres a day of desalinated water globally.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17525605/main.jpg
    Mark Dowdall
  • Saudi water sector awaits next catalyst

    2 July 2026

    Commentary
    Mark Dowdall
    Power & water editor

    Saudi Arabia’s water sector is entering a critical period as developers and investors wait for the next signal that the kingdom’s project pipeline is moving forward.

    Seven months have passed since preferred bidders were announced for the Arana and Hadda independent sewage treatment plant (ISTP) projects, which together will provide 350,000 cubic metres a day (cm/d) of treatment capacity. The projects had been expected to reach financial close in the second quarter of this year, but have yet to do so.

    In parallel, Saudi Arabia’s Vision Invest was selected as preferred bidder last December for the estimated $2bn Riyadh-Qassim independent water transmission pipeline (IWTP) project. It was reported at the time that the company had submitted a levelised tariff of SR2.627 ($0.70) a cubic metre, almost 20% below the next nearest bid. The project, which will comprise an 859-kilometre pipeline with transmission capacity of 685,000 cm/d, had been tipped to reach financial close this quarter.

    The uncertainty extends beyond projects awaiting financial close. The developer tender bid deadline was recently pushed back again for the $150m Riyadh East ISTP. Meanwhile, Saudi Arabia’s Water Transmission Company (WTCO) is understood to be reviewing the delivery model for the Jubail-Buraidah and Ras Mohaisen-Baha-Mecca independent water transmission system (IWTS) projects.

    According to sources familiar with the plans, WTCO is considering establishing a special purpose vehicle that would take equity stakes in both schemes. This could further delay procurement for a project that has already seen multiple deadline extensions. Sharakat’s next wave of independent water projects (IWPs) is also in the pipeline. The first of these is not expected to be tendered until early 2027.

    According to regional project tracker MEED Projects, Saudi Arabia’s water infrastructure sector recorded $3.14bn-worth of awards in the first half of this year, substantially lower than the $7.58bn recorded during the same period in 2025.

    While activity has slowed, the longer-term outlook remains unchanged. Population growth and industrial expansion continue to drive demand for desalination, wastewater treatment and water transmission infrastructure. In the meantime, key stakeholders are looking for the next clear signal that the project pipeline is regaining momentum.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17510220/main.jpg
    Mark Dowdall
  • Contractor wins Jeddah road expansion deal in Riyadh

    2 July 2026

     

    The Royal Commission for Riyadh City (RCRC) has awarded a contract for the Jeddah Road Development Project in Riyadh.

    Local construction firm Saudi Pan Kingdom (Sapac) won the contract.

    Spanning 29 kilometres, the scheme includes 14 bridges and five lanes.

    Designed to handle up to 353,000 vehicles a day, the road is expected to be completed by 2028, with mobilisation works already under way.

    The project forms part of the third package of the RCRC’s Riyadh Main and Ring Road Axes Development Programme, which was announced in January.

    The other schemes include:

    > Taif Road Development Project: The project stretches 15km and includes four bridges, each with four lanes. It also features two tunnels. It will have a capacity of up to 200,000 vehicles a day and will enhance connectivity between Riyadh’s southern and western districts and the city centre.

    Thumamah Road Development Project: The eastern section of the project will span 8km and include three bridges and three tunnels, linking the northern and eastern parts of Riyadh. The project will have a daily capacity of up to 200,000 vehicles.

    King Abdulaziz Road Development Project: The northern section of the project stretches 4.7km and will include four bridges, four lanes and one tunnel, with a capacity of up to 450,000 vehicles per day.

    Othman Bin Affan Road Development Project: The northern section will span 4.3km and include seven bridges and other related upgrades to enhance traffic flow across northern Riyadh. The project will have a daily capacity of up to 500,000 vehicles.

    Second phase of engineering enhancements for congested areas: This project targets eight locations across the city’s road network, where advanced engineering solutions will be applied to reduce congestion and improve intersection performance, increasing traffic capacity by 40% to 60%.

    The contract for the Jeddah Road Development Project is the latest of several high-profile deals awarded by the RCRC recently. In May, it awarded an estimated SR5bn ($1.3bn) contract to construct the Sheikh Jaber Al-Sabah Road project in Riyadh.

    That contract went to a joint venture of Riyadh-based Al-Rashid Trading & Contracting Company (RTCC) and Turkiye’s IC Ictas.

    Stretching 12km, the project runs from Khurais Road to Al-Thumama Road and is a key component of the Second Eastern Ring Road scheme.

    Works include five interchanges: Prince Bandar, King Abdullah, Imam Abdullah, Dammam Road and Al-Thumama.

    In 2021, Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud said the population of Riyadh would double to 15-20 million people by 2030. 

    He directed government entities to work closely with the RCRC to prepare the city’s development strategy.

    The RCRC’s major projects include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park, Green Riyadh and several road development projects in the capital.


    READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Stress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.

    Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17523376/main.jpg
    Yasir Iqbal
  • Dubai announces First Al-Khail road development project

    2 July 2026

    Register for MEED’s 14-day trial access 

    Dubai’s Executive Council has announced the First Al-Khail Street Development project, which will run parallel to Sheikh Zayed Road.

    The scheme comprises a 15-kilometre elevated carriageway with three lanes in each direction.

    According to a Dubai Media Office statement, “The project will provide access to areas including Al-Barsha, Al-Quoz, Business Bay and Meydan.”

    “It is expected to serve more than 2.6 million people and reduce travel time on Sheikh Zayed Road by 51% during peak hours,” the statement added.

    Designed to accommodate more than 9,000 vehicles an hour, construction is expected to begin in the third quarter of 2027, with completion targeted for 2030.

    The development forms part of a wider AED18bn ($5bn) programme covering initiatives related to culture, trade, infrastructure, Emiratisation, finance, investment, urban planning and the city’s population census.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17523587/main.jpg
    Yasir Iqbal