Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • Saudi Aramco profits decline by 22%

    5 August 2025

    Saudi Aramco has announced a net income of $22.67bn for the second quarter of 2025, a 22% decline compared to the same period last year. The Saudi energy giant attributed the 10th consecutive quarterly drop in profit to a low oil price environment, as well as global economic and geopolitical headwinds.

    Global crude benchmark Brent crude has been on a largely downward trajectory since a 2025 high of $82.03 in January. Brent was trading around $68.5 a barrel as of 1pm GST on 5 August.

    For the first half of the year, Aramco registered a profit of $48.68bn, a year-on-year decline of 13.6%.

    “Aramco’s resilience was proven once again in the first half of 2025 with robust profitability, consistent shareholder distributions and disciplined capital allocation. Despite geopolitical headwinds, we continued to supply energy with exceptional reliability to our customers, both domestically and around the world,” Amin Nasser, Aramco’s president and CEO, said in his remarks about the financial results.

    “Market fundamentals remain strong and we anticipate oil demand in the second half of 2025 to be more than 2 million barrels per day higher than the first half. Our long-term strategy is consistent with our belief that hydrocarbons will continue to play a vital role in global energy and chemicals markets, and we are ready to play our part in meeting customer demand over the short and the long term,” Nasser commented.  

    Despite the drop in net income, Aramco’s board declared a base dividend of $21.1bn and a performance-linked dividend of $200m for the second quarter of 2025, to be paid in the third quarter of the year.

    Aramco had said in March it expected to declare total dividends of $85.4bn in 2025, down sharply from last year's payout of over $124bn, which was based on 2023 and 2024 earnings. The performance-linked payout, which last year totalled $43.1bn, was slashed roughly 98% as free cash flow dried up.

    Meanwhile, the state enterprise’s free cash flow stood at $15.2bn in the second quarter of this year, and $34.4bn in the first half.

    The company’s gearing ratio was recorded at 6.5% as at the end of the second quarter, compared to 5.3% at the end of the first quarter.

    Separately, Aramco said its first US dollar-denominated sukuk, or Islamic bond, issuance for 2025, from which it raised $5bn in three separate tranches of five, 10 and 30-year maturities, “highlights investor confidence in Aramco’s strong financial position, resilience and long-term strategy".

    Capital expenditure

    Aramco’s capital expenditure (capex) in the second quarter of 2025 stood at $12.3bn, a marginal year-on-year increase of 1.46%. For the first half of the year, the firm registered capex of $24.85bn, an increase of 9.5% compared to the same period of last year.

    The company had earlier announced a capital investment guidance in the range of $52bn to $58bn for 2025, excluding around $4bn of project financing.

    “We continue to invest in various initiatives, such as new energies and digital innovation with a focus on AI – aiming to leverage our scale, low cost, and technological advancements for long-term success,” Nasser stated.

    On the operational side, Aramco affirmed it maintained supply reliability of 100% in the first half of 2025, reflecting a “strong track record of consistency and stability".

    ALSO READ: Aramco offshore contract awards set to rebound

    The company also said it made progress with the Berri, Marjan and Zuluf crude oil increment projects, while work on the Jafurah unconventional gas development programme is “on track".

    In addition, Aramco said it commissioned the first phase of the Dammam onshore field development project. The company had earlier expected to bring the project onstream last year, with an initial output of 25,000 barrels a day (b/d), ramping up to 50,000 b/d by 2027.

    On the other hand, Aramco also highlighted the introduction of premium fuel lines in Chile and Pakistan during the first half of the year.

    The energy giant also signed power purchase agreements to develop new renewable projects during the period, “capitalising on the kingdom’s advantaged solar and wind resources".

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14406412/main.png
    Indrajit Sen
  • Contractors prepare bids for Safaniya offshore field expansion

    5 August 2025

    Contractors within Saudi Aramco’s pool of offshore engineering, procurement, construction and installation (EPCI) service providers are preparing bids for three tenders that represent the next infrastructure expansion phase at the Safaniya offshore oil field development in Saudi Arabia.

    The tenders are numbers 154, 155 and 156 on Aramco’s Contract Release and Purchase Order (CRPO) system. The Saudi energy giant issued these CRPOs to its offshore LTA contractors in February, and set an initial bid submission deadline of 31 July, MEED previously reported.

    Aramco has now extended the bid submission deadline for CRPOs 154, 155 and 156 to 28 August, sources told MEED.

    The brief scope of EPCI work on the three tenders are as follows:

    CRPO 154:

    EPCI of a water injection tie-in platform; two production deck modules (PDMs)/wellhead platforms; associated pipelines; hook-ups; and subsea valve skids

    CRPO 155:

    EPCI of four PDMs; intra-field and main trunklines to shore; and jackets

    CRPO 156:

    EPCI of a 48-inch trunkline covering a distance of 62 kilometres from the Safaniya offshore oilfield to the onshore processing facility; plus hook-ups and associated structures.

    Aramco intends to award the EPCI contracts for CRPOs 154, 155 and 156 in January next year, as per sources.

    The oil major's LTA pool of offshore service providers comprises the following entities:

    • Saipem (Italy)
    • McDermott International (US)
    • Larsen & Toubro Energy Hydrocarbon (LTEH, India) / Subsea7 (UK)
    • NMDC Energy (UAE)
    • Lamprell (UAE/Saudi Arabia)
    • China Offshore Oil Engineering Company 
    • Dynamic Industries (US)
    • Sapura Energy (Malaysia)
    • TechnipFMC (France) / MMHE (Malaysia)
    • Hyundai Heavy Industries (South Korea)

    Aramco renewed its LTAs in April with the following contractors, whose contracts had either lapsed or were close to expiry:

    • Saipem
    • McDermott International
    • Larsen & Toubro Energy Hydrocarbon / Subsea7
    • NMDC Energy
    • Lamprell
    • China Offshore Oil Engineering Company
    Awards rebound

    Concerns had grown in Saudi Arabia’s offshore market as EPCI contract awards stalled earlier this year.

    Aramco spent a record $5bn on offshore EPCI contracts in 2024 and was expected to exceed that in 2025. However, it awarded no CRPOs in the first half of the year, fuelling concern among contractors and suppliers.

    In July, Aramco eased speculation by selecting contractors for five CRPOs – numbers 150, 157, 158, 159 and 160 – worth over $3bn. These involve EPCI work and infrastructure upgrades at the Abu Safah, Berri, Manifa, Marjan and Zuluf offshore fields.

    Furthermore, frontrunners have emerged for four more CRPOs that are part of a large-scale project to expand infrastructure at the Zuluf offshore field development. The tenders are CRPOs 145, 146, 147 and 148, and their combined value is estimated to be almost $6bn.

    Although official contracts for these CRPOs have yet to be issued, Aramco is expected to formally award the jobs to the contractors it has selected from its LTA pool within the third quarter.

    When these contract awards take place, Aramco will have almost doubled its capex on offshore projects this year compared to 2024, marking yet another year of robust upstream project spending.

    Furthermore, it is understood there are at least seven more CRPOs – including 154, 155 and 156 – that LTA contractors are preparing bids for.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14405455/main2233.jpg
    Indrajit Sen
  • Tendering begins for Riyadh Expo 2030 infrastructure

    5 August 2025

     

    Saudi Arabia’s Expo 2030 Riyadh Company (ERC), tasked with delivering the Expo 2030 Riyadh venue, received interest from contractors on 24 July for initial infrastructure works at the project, located in the north of Riyadh.

    MEED understands the expression of interest (EoI) notice was issued on 17 July.

    The infrastructure works covering the construction of main utilities and civil works will be tendered in three packages:

    • Lot 1 covers the main utilities corridor
    • Lot 2 includes the northern cluster of the nature corridor
    • Lot 3 comprises the southern cluster of the nature corridor

    The client is also expected to ask firms to prequalify for the contracts in August.

    The tendering for the infrastructure package follows ERC receiving bids from firms on 6 July for a contract to build the site offices required for initial construction works at the project.

    In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within the Saudi capital.

    Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.

    The expo is forecast to attract more than 40 million visitors.

    In June, the Public Investment Fund (PIF), Saudi Arabia's sovereign wealth vehicle,  launched ERC as a wholly-owned subsidiary to build and operate facilities for Expo 2030.

    In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”


    MEED’s April 2025 report on Saudi Arabia includes:

    > GOVERNMENT: Riyadh takes the diplomatic initiative
    > ECONOMY: Saudi Arabia’s non-oil economy forges onward
    > BANKING:
     Saudi banks work to keep pace with credit expansion
    > UPSTREAM: Saudi oil and gas spending to surpass 2024 level
    > DOWNSTREAM: Aramco’s recalibrated chemical goals reflect realism
    > POWER: Saudi power sector enters busiest year
    > WATER: Saudi water contracts set another annual record
    > CONSTRUCTION: Reprioritisation underpins Saudi construction
    > TRANSPORT: Riyadh pushes ahead with infrastructure development
    > DATABANK: Saudi Arabia’s growth trend heads up

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14405209/main.jpg
  • Riyadh announces Prince Faisal bin Bandar road project

    5 August 2025

    Riyadh Municipality has announced the Prince Faisal bin Bandar Road development project, which spans 15.5 kilometres (km) in the north of Riyadh.

    The project will comprise six lanes, four service lanes, three intersections and 6,800 parking spaces. 

    It will also have pedestrian and bicycle paths, landscaping and drainage and an irrigation network.

    According to an official statement published on the Saudi Press Agency, the project will start from its intersection with King Salman bin Abdulaziz Road in the south to the Saudi Aramco oil pipeline in the north.

    The project is expected to alleviate traffic congestion to the north of the capital. Riyadh is significantly investing in developing the road infrastructure in and around the city to expand traffic capacity. 

    In February, Saudi Arabia’s Royal Commission for Riyadh City (RCRC) announced plans to develop eight road projects in Riyadh at an estimated cost of more than SR8bn ($2bn).

    The projects form part of the second group in the Riyadh Ring Roads and Main Axes development programme.

    The schemes include:

    1. The northern part of the Prince Turki Bin Abdulaziz Al-Awwal Road Development Project, with a length of more than 6 kilometres (km). The scope includes the development of two main intersections, the construction of three bridges and a tunnel.

    2. The middle section of the Al-Thumama Road Axis Development Project. The scheme will cover about 10km and include the development of five main intersections and the construction of 11 bridges and five tunnels.

    3. Imam Abdullah Bin Saud Road Development Project, which will stretch about 9km and include the development of four main intersections, the construction of three bridges and two tunnels.

    4. Dirab Road Development Project will cover 9km and includes the development of two main intersections and the construction of nine bridges.

    5. Imam Muslim Road Development Project, which stretches 12km and includes the development of four main intersections and the construction of four bridges. The project will serve as the future extension of Prince Turki Bin Abdulaziz Al-Awwal Road Axis to the south.

    6. The road network development project surrounding King Abdullah Financial Centre, with a length of 20km. This includes the development of three main intersections and the construction of 19 bridges.

    7. The construction of a bridge at the intersection of King Salman Road in the east with Abu Bakr Al-Siddiq Road in the north.

    8. The first package of engineering modifications for crowded sites in Riyadh, the scope of which includes improving traffic congestion during peak times.

    In August last year, the RCRC confirmed that it had awarded four contracts worth SR13bn as part of the first phase of the programme to develop the city’s road network.

    The RCRC said the programme’s first phase will develop the axis of the main and ring roads to improve traffic movement in the city.

    The RCRC’s major projects include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park and the Green Riyadh project.


    MEED’s April 2025 report on Saudi Arabia includes:

    > GOVERNMENT: Riyadh takes the diplomatic initiative
    > ECONOMY: Saudi Arabia’s non-oil economy forges onward
    > BANKING:
     Saudi banks work to keep pace with credit expansion
    > UPSTREAM: Saudi oil and gas spending to surpass 2024 level
    > DOWNSTREAM: Aramco’s recalibrated chemical goals reflect realism
    > POWER: Saudi power sector enters busiest year
    > WATER: Saudi water contracts set another annual record
    > CONSTRUCTION: Reprioritisation underpins Saudi construction
    > TRANSPORT: Riyadh pushes ahead with infrastructure development
    > DATABANK: Saudi Arabia’s growth trend heads up

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14405155/main.jpg
    Yasir Iqbal
  • Acwa Power picks contractors for Yanbu Green Hydrogen Project

    5 August 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia's Acwa Power has awarded a consortium of Spain's Tecnicas Reunidas and China's Sinopec Guangzhou Engineering a convertible front-end engineering design (feed) contract for its Yanbu Green Hydrogen Project.

    The feed contract, which is set to last for 10 months, will focus on the design of a facility capable of producing 400,000 tonnes a year of green hydrogen. This hydrogen will subsequently be converted into green ammonia through multiple ammonia synthesis loops.

    Following the completion of the feed phase, the joint venture will submit an engineering, procurement, and construction (EPC) proposal for the multibillion-dollar facility, which is expected to commence commercial operations by 2030.

    Tecnicas Reunidas has been involved in the project since its pre-feed stages, while Sinopec Guangzhou Engineering's participation continues from a memorandum of understanding signed with Acwa Power in 2024.

    Located in Yanbu Industrial City, the Yanbu Green Hydrogen Project aims to harness 5 GW each of wind and solar power, along with a 400km transmission line and up to 4.4GW of electrolysers. The green hydrogen produced will be converted into 2.5 million tonnes of green ammonia for export to international markets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14405003/main.jpg
    Colin Foreman