Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • Trump confirms UAE currency swap talks

    22 April 2026

    Register for MEED’s 14-day trial access 

    US President Donald Trump has confirmed that Washington is considering a currency swap agreement with the UAE.

    During an interview with US broadcaster CNBC, Trump acknowledged that the arrangement is being considered. “It is [under consideration], but it’s been a good country. It’s been a good ally of ours,” Trump stated, noting that the request stems from a liquidity challenge rather than a solvency issue.

    Addressing the scale of the conflict’s impact on the federation, he added, “UAE got hit with 1,400 missiles. Now, fortunately, they had the Patriots, and they had a great defence … but they did get hit hard. They were hit the hardest of the group, actually.”

    The president also emphasised the strength of the bilateral economic relationship and his personal regard for the country’s leadership. “They’re really led by incredible people,” Trump told CNBC. “A year ago, I went there and I got them to invest $1tn in the United States. So, yeah, if I could help them, I would.”

    An early report by the Wall Street Journal said that high-level talks were initiated by UAE Central Bank governor Khaled Mohamed Balama, who recently met with Treasury secretary Scott Bessent and Federal Reserve officials in Washington.

    The UAE’s move is viewed as a precautionary effort to protect the dirham’s peg to the dollar and maintain its position as a global financial hub. The conflict has already inflicted significant damage on Emirati oil-and-gas infrastructure and disrupted tanker traffic through the Strait of Hormuz, which has historically been the primary source of the nation’s dollar revenues.

    While swap lines are traditionally managed by the Federal Reserve and reserved for major economies with deep ties to US markets, the Trump administration may look to the Treasury Department for a solution. Trump referenced a recent $20bn swap for Argentina facilitated by Secretary Bessent through the Exchange Stabilisation Fund as a potential model for the UAE.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16512000/main.jpg
    Colin Foreman
  • Egyptian and Chinese firms sign green hydrogen deal

    22 April 2026

    A group of Egyptian companies and China’s UEG have signed a preliminary agreement to explore developing a Mediterranean green hydrogen hub in the port city of Alexandria.

    The memorandum of understanding was signed by:

    • Abu Qir Fertilisers & Chemicals Company (Egypt)
    • AlexFert (Egypt)
    • Orascom Construction (Egypt)
    • UEG Green Hydrogen Development Holding (China)

    In a joint statement, the companies said: “The collaboration marks a significant step toward advancing Egypt’s position as a regional leader in green hydrogen and sustainable energy solutions.

    “The proposed project aims to develop a large-scale green hydrogen production facility powered by renewable energy, with integration into existing ammonia production infrastructure.”

    Under the terms of the deal, UEG and Orascom Construction will lead feasibility studies for 500MW of renewable energy generation and 480 tonnes a day (t/d) of green hydrogen production.

    Abu Qir and AlexFert will evaluate the integration of green hydrogen into ammonia production processes and support access to local resources and infrastructure.

    The renewable energy will be a mix of wind and solar, according to the statement.

    Hany Dahy, the chairman of Abu Qir Fertilisers & Chemicals Company, said: “This partnership reflects Abu Qir’s commitment to leading the transition toward low-carbon ammonia production, leveraging our existing assets while integrating green hydrogen solutions.”

    Joe Williams, the chief executive of the Green Hydrogen Organisation, said: “The announcement of this project comes at a crucial time, as geopolitical tensions in the Middle East highlight the importance of diversifying energy and fuel supply chains.

    “Developing integrated green ammonia and fertiliser production in Alexandria supports local industrial value, and strengthens long-term energy and food security.

    “As green ammonia production scales in Egypt, it can also be used as a clean shipping fuel given Egypt’s strategic maritime location.”

    The preliminary agreement establishes a framework for cooperation while the parties conduct technical, commercial and regulatory assessments.

    Subject to the outcomes, the partners intend to negotiate definitive agreements for the project’s development, according to their statement.

    Abu Qir Fertilisers established North Abu Qir for Agricultural Nutrients in May 2023 to develop a major Egyptian fertiliser project designed to produce 2,400 t/d of ammonium nitrate.

    Located next to Abu Qir Fertilisers in Alexandria, on a site formerly occupied by the Rakta paper manufacturing facility, the project is a joint venture with a capital investment of £E10bn ($190m), of which Abu Qir Fertilisers holds a 45% stake.

    The state-owned companies Egyptian General Petroleum Corporation and Egyptian Petrochemicals Holding Company hold stakes of 45% and 10%, respectively.

    The project focuses on the production of ammonia and nitric acid.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16498782/main.jpg
    Wil Crisp
  • Populous wins Bahrain Sports City contract

    21 April 2026

     

    US-based engineering firm Populous has won a BD5m ($13.5m) contract for the Sports City development at Sakhir in Bahrain.

    The contract was awarded by Bahrain’s Ministry of Works, Municipalities Affairs & Urban Planning.

    The scope covers pre-contract consultancy services, including finalising the masterplan and internal infrastructure, completing phase 1A design works and preparing tender documents.

    Populous is a specialist sports venue designer that formerly operated as part of HOK Group.

    The contract was first tendered in 2021, when Populous emerged as the sole bidder.

    At the time, it was reported that Sports City would include Bahrain’s largest sports stadium and a multi-purpose indoor sports arena.

    The project is expected to provide renewed impetus to Bahrain’s construction and transport sector, which has struggled in recent years, with the total value of awarded contracts falling for a third consecutive year.

    According to regional project tracker MEED Projects, about $400m-worth of contracts had been awarded in Bahrain by the end of October last year – less than half the $1.2bn recorded during the same period the previous year.

    The sector has yet to return to pre-pandemic levels. Before 2020, Bahrain consistently awarded more than $2bn in contracts annually, peaking at nearly $4bn in 2016.

    Bahrain’s construction industry is forecast to record average annual growth of 4.9% in 2026-29, supported by investments in transport infrastructure and renewable energy projects aligned with Bahrain’s Economic Vision 2030.

    Vision 2030 includes the BD11.3bn ($30bn) Strategic Projects Plan, unveiled in October 2021, encompassing 22 national infrastructure projects. It also includes plans to create five new cities by 2030: Fasht Al-Jarm, Suhaila Island, Fasht Al-Azem, Bahrain Bay and the Hawar Islands.

    Growth over the forecast period is also expected to be driven by investments under the National Renewable Energy Action Plan, which targets a 30% reduction in carbon emissions by 2035, compared to 2015 levels, and aims to achieve net-zero emissions by 2060.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16487784/main.jpg
    Yasir Iqbal
  • Entries now open for MEED Projects Awards 2026

    21 April 2026

    Enter the awards

    The MEED Projects Awards in association with Mashreq 2026 have officially opened for entries, inviting companies, developers, contractors and project teams to submit their projects for the region’s most prestigious construction awards.

    For over 15 years, the MEED Projects Awards have celebrated the Middle East and North Africa’s most ambitious and transformative projects, recognising technical excellence, innovation, sustainability and delivery impact. Past editions have highlighted landmark developments that set new benchmarks for the region’s built environment, including internationally recognised projects such as Burj Khalifa and Louvre Abu Dhabi.

    “The MEED Projects Awards are the gold standard for recognising outstanding achievements in construction across Mena, showcasing the region’s technical and design excellence while bringing the industry together to celebrate and connect over the very best projects of the year,” said Ed James, head of content and research at MEED.

    “As a long-standing partner of the MEED Projects Awards, Mashreq is proud to support a programme that is recognised for its independence, credibility and industry impact. These awards celebrate projects that set benchmarks for excellence and contribute meaningfully to the region’s development,” said Arun Mathur, executive vice-president and global head of contracting finance at Mashreq.

    Winners are chosen through a rigorous, independent judging process, led by a panel of more than 50 senior industry experts representing developers, contractors, engineers and project specialists. The awards celebrate projects across a wide range of sectors, including Building, Transport, Energy, Water, Healthcare, Education, Hospitality, Culture, Industrial, Power, Small Projects and Developments.

    Being shortlisted or winning a MEED Projects Award places a project among the region’s elite, offering regional recognition, global exposure and industry credibility.

    Submissions are now open, with full category details and entry guidelines available on the official entry platform.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16487756/main.gif
    MEED Editorial
  • Work advances on Saudi Maaden mine renewables project

    21 April 2026

     

    Local contractor Arabian Qudra Company is advancing construction works on an integrated solar photovoltaic (PV) and battery energy storage system (bess) project at the Al-Baitha bauxite mine in Saudi Arabia.

    The off-grid facility will integrate an 8MWp solar PV array with a 30MWh bess, allowing the mine to operate almost entirely on renewable energy.

    Emerge, a joint venture of Masdar and EDF Power Solutions, is developing the project, including managing financing, design, procurement, construction, operation and maintenance.

    Last August, MEED reported that Maaden Bauxite & Alumina Company (MBAC), a subsidiary of Saudi Arabian Mining Company (Maaden), had signed a 30-year power purchase agreement with Emerge to supply its Al-Baitha bauxite mine with renewable energy.

    Arabian Qudra Company was subsequently appointed as the engineering, procurement and construction (EPC) contractor, with works beginning at the start of 2026.

    The firm is a subsidiary of Abunayyan Holding Company, a privately owned Saudi industrial group.

    The project is expected to generate around 17,300MWh of electricity annually and provide a continuous 24/7 power supply. It will reduce carbon dioxide emissions by approximately 13,800 tonnes a year.

    According to projects tracker MEED Projects, construction is expected to be completed in early 2028.

    Maaden Solar 1

    Maaden is also in the early stages of developing Maaden Solar 1, potentially the world’s largest solar process heat plant. 

    MEED previously reported that US-based GlassPoint had partnered with Saudi Arabia’s Ministry of Investment as a first step towards construction of the planned $1.5bn project.

    In 2025, Spain-headquartered Cox Energy signed a collaboration agreement with the client to participate in the project. The client had been expected to invest approximately $31.1m in the first phase of the project.

    Once complete, Maaden Solar 1 will be a 1,500 megawatt-thermal (MWth) facility. A timeline for the project remains unclear, with construction not expected to begin until at least 2027.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16487404/main.jpg
    Mark Dowdall