Manama jumpstarts utility sector
4 November 2024

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).
The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.
The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.
The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.
The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.
The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.
MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.
Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.
“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”
A different set of factors will be at play for the Sidra IWPP, however.
For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.
According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.
The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.
Solar PV projects
The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.
China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).
In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.
The power plant will be located at several premises, including at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.
The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.
The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.
Water and waste
Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.
It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.
The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials
However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.
The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.
As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.
The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.
Exclusive from Meed
-
Riyadh sets December deadline for Prince Mishaal Road20 November 2025
-
Riyadh advances with rail link prequalifications20 November 2025
-
Local contractor bids low for $629m Kuwait oil project20 November 2025
-
Oman’s Marafiq retenders Duqm desalination plant20 November 2025
-
Wood Group wins Iraq oil contract20 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Riyadh sets December deadline for Prince Mishaal Road20 November 2025

The Royal Commission for Riyadh City (RCRC) has allowed contractors until 3 December to submit bids for a contract to develop Prince Mishaal Bin Abdulaziz Road Axis-Taif Road in Riyadh.
The previous deadline was 19 November.
The scope of work covers general road improvement works, including street upgrades, drainage works, relocation of existing utilities, dry and wet utilities, and other associated infrastructure. RCRC is investing in improving the road network in and around the kingdom's capital.
Earlier in November, MEED reported that RCRC had begun post-tender clarifications with bidders for a contract covering upgrade works on Najm Al-Din Al-Ayoubi Road in Riyadh.
The scope of work covers general road improvement works, including upgrades to three bridges at Al-Zahabi Road, Abdulrahman Adakhel Road and Atia Al-Saady Road.
In February, RCRC announced plans to develop eight road projects in Riyadh at an estimated cost of more than SR8bn ($2bn).
The projects form part of the second group in the Riyadh Ring Roads and Main Axes development programme.
The schemes include:
- The northern part of the Prince Turki Bin Abdulaziz Al-Awwal Road development project, with a length of more than 6 kilometres (km). The scope includes the development of two main intersections, the construction of three bridges and a tunnel.
- The middle section of the Al-Thumama Road Axis development project. The scheme will cover about 10km and includes the development of five main intersections and the construction of 11 bridges and five tunnels.
- The Imam Abdullah Bin Saud Road development project, which will stretch about 9km and includes the development of four main intersections, the construction of three bridges and two tunnels.
- The Dirab Road development project, which will cover 9km and includes the development of two main intersections and the construction of nine bridges.
- The Imam Muslim Road development project, which stretches 12km and includes the development of four main intersections and the construction of four bridges. The project will serve as the future extension of the Prince Turki Bin Abdulaziz Al-Awwal Road Axis to the south.
- The road network development project surrounding King Abdullah Financial Centre, with a length of 20km. This includes the development of three main intersections and the construction of 19 bridges.
- The construction of a bridge at the intersection of King Salman Road in the east with Abu Bakr Al-Siddiq Road in the north.
- The first package of engineering modifications for crowded sites in Riyadh, encompassing improvements to alleviate traffic congestion during peak times.
In August last year, RCRC confirmed it had awarded four contracts worth SR13bn ($3.46bn) as part of the first phase of the programme to develop the city’s road network.
RCRC said the first phase will develop the axis of the main and ring roads to improve traffic movement in the city.
Other major projects by RCRC include Riyadh Metro, Riyadh Art, Sports Boulevard, King Salman International Park and the Green Riyadh project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15123861/main.jpg -
Riyadh advances with rail link prequalifications20 November 2025

Saudi Arabia Railways (SAR) is expected to begin the second stage of the prequalification process for a contract covering the construction of a new railway line, known as the Riyadh Rail Link, which will run from the north to the south of Riyadh.
MEED understands that the consortiums need to propose self-funded financing arrangements for the project as part of the new round of prequalifications.
Contractors submitted their initial prequalification documents earlier this month.
The scope of work includes constructing a 35-kilometre-long double-track railway line connecting SAR’s North-South Railway to the Eastern Railway network.
The contract also covers the procurement, construction and installation of associated infrastructure such as viaducts, civil works, utility installations, signalling systems and other related works.
The project is expected to form a key component of the Saudi Landbridge railway.
The Saudi Landbridge is an estimated $7bn project comprising more than 1,500km of new track. Its core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.
Other key sections include upgrades to the existing Riyadh-Dammam line and a link between King Abdullah Port and Yanbu.
The start of tendering activity for the Riyadh Rail Link project makes the construction of the Saudi Landbridge more likely.
The project is one of the kingdom’s most anticipated infrastructure programmes. Plans to develop it were first announced in 2004, but the project was put on hold in 2010 before being revived a year later.
Key stumbling blocks were rights-of-way issues, route alignment and its high cost.
In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.
If it proceeds, the Landbridge will be one of the largest railway projects ever undertaken in the Middle East – and among the biggest globally.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15123411/main.jpg -
Local contractor bids low for $629m Kuwait oil project20 November 2025
Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid on a contract to develop oil and gas facilities at the Sabriya and Bahra oil fields.
The scope of the project is focused on developing a water separation facility next to Gathering Centre 23 (GC-23) and GC-24.
It also includes developing an injection facility at GC-31.
The full list of bidders for the project is:
- Mechanical Engineering & Contracting Company (MECC) – KD193m ($629m)
- Spetco – KD229m
- Alghanim International – KD239m
The tender was issued on 15 December 2024, with an initial bid submission deadline of 16 March 2025.
The bid deadline was extended more than 10 times before prices were submitted.
The client on the project is state-owned upstream operator Kuwait Oil Company (KOC).
The scope of the project includes:
- Installation of a high-integrity pressure protection system
- Installation of chemical injection systems
- Installation of effluent water transfer pumps
- Installation of a low-pressure (LP) gas pipeline from the new LP gas knockout drum (KOD) to existing LP separator gas crude accumulator (inside GC-23 & 24)
- Installation of interconnecting piping, instrumentation, electrical and civil works
- Installation of a new oil recovery system with pumps, flowmeter and analyser
- Installation of the substation and its equipment/systems
- Installation of tie-ins for process and utilities from/to existing GC-30 to new injection facility
- Installation of sludge collection, treatment and disposal system
- Associated facilities
Kuwait is trying to boost project activity in its upstream sector.
The country’s national oil company, Kuwait Petroleum Corporation, aims to increase oil production capacity to 4 million barrels a day (b/d) by 2035.
In August, Kuwait announced that it was producing 3.2 million b/d.
Earlier this month, KOC said it was planning to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15120909/main.png -
Oman’s Marafiq retenders Duqm desalination plant20 November 2025
Register for MEED’s 14-day trial access
Oman-based Central Utilities Company (Marafiq) has reissued the main contract tender for its planned seawater reverse osmosis (RO) desalination plant in Duqm.
The revised submission deadline is 25 November.
The project has an estimated budget of $100m and will supply industrial water and support wastewater services in the Duqm Special Economic Zone.
The scheme involves building a seawater RO plant, an intake system, pre-treatment facilities, pumping stations, metering stations, pipelines and associated infrastructure.
Marafiq is developing the project in its capacity as the authorised utilities provider for the Duqm Special Economic Zone.
The company intends to develop a plant with a capacity of 45 million litres a day to serve industrial customers, including a planned hot-briquetted iron (HBI) facility proposed by an international steel manufacturer at Duqm Port.
Spain’s Cobra Group and Oman’s Global Chemicals & Maintenance System were previously prequalified to bid for the engineering, procurement and construction contract.
The main contract was initially tendered in December 2024, with the bid submission deadline in February.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15116821/main.jpg -
Wood Group wins Iraq oil contract20 November 2025
Register for MEED’s 14-day trial access
Aberdeen-based Wood Group has won a contract to deliver project management and engineering services for PetroChina at the West Qurna-1 oil field in southern Iraq, according to a statement from the company.
Under the terms of the contract, Wood will manage engineering, procurement and construction (EPC) projects at the field.
Located approximately 50 kilometres northwest of Basra, West Qurna-1 holds more than 20 billion barrels of recoverable reserves.
Ellis Renforth, Wood’s president of operations for the Europe, Africa and Middle East region, said: “This contract award deepens our decade-long partnership at West Qurna-1 and reflects the continued trust placed in Wood to deliver complex energy solutions in Iraq.
“We’re proud to combine our global expertise with a strong local workforce to help support Iraq’s energy ambitions.”
The contract will be delivered by nearly 200 Wood employees based in Iraq and the UAE, the company said.
On 17 November, in a vote, 88% of Wood Group’s shareholders backed the company’s takeover by Dubai-based Sidara.
The vote came after months of delay, while Wood struggled to agree its accounts with its auditor.
The company’s accounts were eventually published on 30 October, showing a pre-tax loss of more than £2bn and evidence that the auditor was still not satisfied with the figures going back several years.
Wood Group accepted a $292m conditional takeover bid from Sidara in August.
As of February, Wood Group employed 35,000 people across about 60 countries, many in consulting and engineering roles.
In the Middle East, the company has project contracts in Iraq, Kuwait, Oman, Qatar, Saudi Arabia and the UAE, where it has opened its third office in Sharjah.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15122155/main.png


