Manama jumpstarts utility sector
4 November 2024

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).
The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.
The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.
The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.
The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.
The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.
MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.
Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.
“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”
A different set of factors will be at play for the Sidra IWPP, however.
For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.
According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.
The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.
Solar PV projects
The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.
China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).
In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.
The power plant will be located at several premises, including at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.
The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.
The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.
Water and waste
Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.
It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.
The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials
However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.
The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.
As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.
The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.
Exclusive from Meed
-
Chinese contractor wins Morocco solar plant deal10 August 2026
-
Aramco puts out fire at Jizan refinery after Houthi strike10 August 2026
-
Shamal picks Dutco for Dubai Zoo site homes10 August 2026
-
WEBINAR: Mena Oil & Gas Projects Market 2026-2710 August 2026
-
Spanish firm renews Yanbu desalination O&M contract10 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese contractor wins Morocco solar plant deal10 August 2026
China Harbour Engineering Company (CHEC), a subsidiary of China Communications Construction Company (CCCC), has won a contract to build a solar photovoltaic (PV) power plant in Fez in northern Morocco.
Known as GreenPower Morocco 4 (GPM4), the project is being developed by Moroccan company GPM Holding through its utility-scale solar subsidiary GPM Parks.
The project covers engineering design, equipment procurement and installation, construction of an operation and maintenance building, grid connection and commissioning. It also includes upgrades to the associated substation.
According to CHEC, the completed plant will supply electricity to the local grid, although it did not disclose the project’s capacity or contract value.
The project is being developed under Law 13-09, which provides Morocco’s framework for private renewable energy generation.
According to its website, GPM Holding is also developing another solar PV project called GreenPower Morocco 2 (GPM2). This follows the completion of its first solar project, the 34MW project (GPM1) commissioned in Tangier in 2024.
GPM1 was developed by Green Power Morocco, a special purpose vehicle owned by GPM Holding and UAE-based Amea Power. The $30m project covers 75 hectares and includes 91,000 PV panels. It is expected to generate about 66,149MWh a year.
The project has a 25-year power purchase agreement in place with Amendis, a subsidiary of Veolia Morocco. PowerChina was the main engineering, procurement and construction (EPC) contractor.
Chinese contractors have previously been involved in other projects in Morocco’s renewable energy sector.
Shandong Electric Power Construction Company (Sepco 3), a subsidiary of PowerChina, was part of the EPC consortium for the 200MW Noor 2 concentrated solar plants and 150MW Noor 3 concentrated solar power projects at the Noor Ouarzazate complex.
New contract awards have been limited in Morocco in 2026, although six solar PV plants are now in the execution stage under phases one and two of the 305MW Noor Atlas solar PV programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18263680/main.jpg -
Aramco puts out fire at Jizan refinery after Houthi strike10 August 2026
Saudi Aramco said it had extinguished a fire that broke out at its Jizan refinery on Saudi Arabia’s Red Sea coast after the facility was hit in drone strikes by Yemen-based Houthi rebels on 9 August.
The kingdom’s Ministry of Energy said the fire occurred at an Aramco refinery facility in Jizan and that emergency authorities had completed the necessary procedures to deal with the incident.
The energy ministry did not say what started the fire, saying only that the incident caused no injuries.
The Houthi rebels later claimed responsibility for the attack.
The province of Jizan lies close to Saudi Arabia’s border with Yemen and has repeatedly been targeted by the Houthis in attacks on the kingdom’s energy infrastructure.
The strike on the Jizan refinery was the second attack on the facility by the Houthis in as many weeks. Aramco shut the refinery on 27 July following a similar drone strike, which, according to media reports, damaged the integrated gasification combined-cycle unit and tank farm at the complex.
On a call with investors to discuss Aramco’s second-quarter results, CEO Amin Nasser said recent attacks on the company’s facilities in the world’s top oil-exporting country had caused some disruption to production, but that he was confident operations could be restored quickly. He said the attacks had had no material operational or financial impact.
Jizan refinery complex
Saudi Aramco’s sprawling Jizan refinery complex entered operations in 2021.
Aramco undertook the estimated $16bn-plus project in late 2010. The scheme consists of a refinery with an output capacity of 400,000 barrels a day (b/d), a major marine terminal and a 4GW combined-cycle power plant in Baish, in Saudi Arabia’s southwestern Jizan region.
The Jizan refinery covers an area of 12 square kilometres. The complex processes Arabian Heavy and Arabian Medium crude grades to produce 80 million b/d of gasoline, 250 million b/d of diesel and more than 1 million tonnes a year of petrochemical products such as benzene and paraxylene.
A multiple-pier marine terminal supports the supply of crude oil from oil fields located mainly in the kingdom’s Eastern Province to the refinery, as well as the export of surplus refined products to overseas markets. The terminal has been designed to accommodate very large crude carriers.
A 4,000MW combined-cycle power plant uses approximately 90,000 b/d of vacuum residue from the refinery to generate electricity, hydrogen and water for the refinery, while conveying excess power to the national grid.
The hydrocracker unit comprises two parallel trains with a combined capacity of 54,500 b/d. The diesel hydrotreater plant comprises two trains, each with a capacity of 87,500 b/d.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18262347/main.jpg -
Shamal picks Dutco for Dubai Zoo site homes10 August 2026
Dubai-based Shamal Holding has awarded local contractor Dutco Construction the main construction works contract for a low-rise residential project on the site of the former Dubai Zoo in Jumeirah 1.
The project will comprise 90 low-rise homes and is designed as a residential leasing community that will remain under Shamal’s ownership, with all homes offered for premium leasing.
The development will retain mature trees from the former zoo and is planned around shared courtyards, landscaped open spaces and a central park. Residents will have access to a clubhouse, wellness area, children’s play area, family pool, lounge and gym.
The architect is DXB Lab. The local H&H is the development manager for the project.
Dutco has previously worked with Shamal on infrastructure elements of the Dubai Harbour and Dubai Harbour Marinas developments.
Shamal’s wider real estate portfolio includes the Naia Island, Dubai Harbour and Nad Al-Sheba Gardens developments. The company also holds hospitality and leisure assets, including partnerships with Jumeirah, Hilton and Baccarat, and operates attractions such as Skydive Dubai and Deep Dive Dubai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18262386/main.png -
WEBINAR: Mena Oil & Gas Projects Market 2026-2710 August 2026
Webinar: Mena Oil & Gas Projects Market 2026-27
Thursday 27 August 2026 | 11:00 AM GST | Register now
Agenda:
- Summary of the Mena oil, gas and petrochemicals projects market
- Overview of major megaprojects, including project programmes
- Analysis of active contracts and spending to date
- Review of top contracts by work already awarded
- Long-term capital expenditure outlays and forecasts
- Key contracts expected to be tendered and awarded over the next 18 months
- Leading clients, contractors and market participants
- Spending by segment: oil, gas and petrochemicals (upstream, downstream, onshore and offshore)
- Audience Q&A
Hosted by: Indrajit Sen, MEED’s oil & gas editor
https://image.digitalinsightresearch.in/uploads/NewsArticle/18260597/main.gif -
Spanish firm renews Yanbu desalination O&M contract10 August 2026
Spain’s Aqualia has announced it has renewed a contract to operate and maintain three floating desalination plants in Yanbu on Saudi Arabia’s Red Sea coast.
The contract was awarded by the National Shipping Company of Saudi Arabia (Bahri) and will run until 14 September 2028, with an option to extend for a further two years.
The three reverse osmosis (RO) plants are mounted on barges and have a combined production capacity of 150,000 cubic metres a day (cm/d). Each plant has a capacity of 50,000 cm/d.
The three plants were originally deployed at Al-Shuqaiq and are designed to be relocated along Saudi Arabia’s coastline according to water demand. The barges are currently located at Yanbu.
The $255m floating desalination project was commissioned for the Saudi Water Authority in 2022, with Bahri as the developer and UAE-based Metitio as the main contractor.
Bahri is publicly listed on the Saudi Exchange but has significant government ownership, with the Public Investment Fund (PIF) holding 22.5% and Saudi Aramco Development Company owning 20% of the company.
Aqualia is providing operation and maintenance services in Saudi Arabia through its joint venture Haji Abdullah Alireza Integrated Services Company (Haaisco), in which it holds a 51% stake.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18259350/main.jpg