Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • Dubai seeks consultants to develop drainage strategy

    18 March 2026

    Dubai Municipality has issued a request for qualifications (RFQ) for a study to develop a sustainable urban drainage systems (Suds) strategy across the emirate.

    The bid submission deadline is 9 April.

    The tender, issued through the Sewerage and Recycled Water Projects Department, covers the development of a strategy and conceptual implementation plan for Suds in Dubai.

    It follows a separate RFQ issued by the municipality in March for consultancy services to study the emirate’s sewage treatment strategy.

    The Suds project, designated TF-23-D1, aims to support the emirate’s flood protection and drainage infrastructure by promoting a more sustainable approach to stormwater management.

    The scope of work includes a review of international best practices in Suds and their applicability to Dubai. It also involves undertaking a Suds opportunity study and carrying out catchment-scale modelling and financial evaluation for a pilot study area.

    Consultants will be required to develop Suds design guidelines, specifications and standard drawings. The project also includes establishing a strategy, policy, legal and regulatory framework to support a Suds implementation roadmap.

    Dubai Municipality said the initiative represents “a significant step towards a more resilient, sustainable and forward-looking stormwater management approach for Dubai.”

    The study forms part of a broader review of Dubai’s water and wastewater infrastructure. Earlier this month, the municipality issued a separate consultancy tender (P115-D1) to assess the emirate’s sewage treatment and recycled water distribution strategy. 

    The study will focus on infrastructure requirements to support future population growth. 

    This includes identifying locations for potential future facilities such as treatment plants and pumping stations.

    The bid submission deadline is 23 March.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16027434/main.jpg
    Mark Dowdall
  • Oman awards power purchase agreements

    18 March 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued letters of award (LoA) for new power purchase agreements (PPAs) to three independent power producers (IPPs), according to regulatory filings.

    The new PPAs will extend the operating life of existing gas-fired power plants beyond the expiry of their current contracts.

    The projects have a combined capacity of about 3,500MW.

    The agreements have been awarded to Phoenix Power Company, Al-Batinah Power Company and Al-Suwadi Power Company.

    Phoenix Power Company operates the 2,000MW Sur IPP.  It is owned by a consortium of international and regional investors, including Japan’s Marubeni Corporation and Chubu Electric Power, Qatar’s Nebras Power, Qatar Electricity & Water Company and Multitech of Oman’s Bahwan Engineering Company.

    Al-Batinah Power Company and Al-Suwadi Power Company operate the 750MW Sohar 2 IPP and the 750MW Barka 3 IPP, respectively.

    According to regional projects tracker MEED Projects, Nama PWP signed the original PPA for the Barka 3 project in 2010 with a consortium led by Gaz de France (GDF) Suez under a special purpose vehicle (SPC) called Al-Suwadi Power Company.

    The shareholders comprised GDF Suez (46%), Bahwan Engineering Company (22%), Shikoku Electric Power Corporation (11%), Sojitz Corporation (11%)  and the Public Authority for Social Insurance (10%).

    In 2015, GDF Suez was rebranded as Engie following a strategic shift towards low-carbon energy and utilities.

    All three companies said the new PPAs will run for 15 years under agreed commercial terms. Acceptance of the LOAs has been requested by 18 March 2026.

    The new agreements for Sohar 2 and Barka 3 will take effect on 1 April 2028 and run until 31 March 2043. The agreement for the Sur IPP will commence on 1 April 2029 and run until 31 March 2044.

    The awards form part of Nama PWP’s 2028-29 procurement programme. The programme aims to secure firm generation capacity from existing assets whose current PPAs are due to expire during that period.

    In Oman, IPP projects are developed under a build-own-operate model. This allows plant operators to continue running assets beyond the initial PPA term, either through contract extensions or by selling power into a future electricity market.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16027001/main.jpg
    Mark Dowdall
  • DP World awards Jafza warehouse construction deal

    18 March 2026

    Dubai-based ports operator DP World has awarded a contract to build a multi-tenant warehouse development at Jebel Ali Freezone in Dubai, UAE.

    The contract was awarded to local firm Group Amana.

    The development spans 141,916 square metres (sq m) and comprises 187 units across seven blocks.

    These comprise warehouses, light industrial units, a retail shop, a mosque and other associated infrastructure.

    The new contract builds on their existing partnership to deliver the logistics park at Jeddah Islamic Port in Saudi Arabia.

    In February last year, MEED exclusively reported that Dubai’s DP World and the Saudi Ports Authority (Mawani) had awarded a SR347m ($92m) design-and-build contract to Group Amana for the project.

    The scope of the contract covers construction work on the buildings under package two of the project’s first phase.

    Earlier this week, MEED reported that DP World has kept its 2026 capital expenditure budget at nearly $3bn, focusing on two domestic assets and four overseas projects.

    The company said in a statement that the priority developments include Jebel Ali and Drydocks World in Dubai.

    Earlier this month, the group announced record financial results for 2025, with revenue up 22% to $24.4bn and adjusted earnings before interest, taxes, depreciation and amortisation (Ebitda) up 18% to $6.4bn, delivering a 26.3% margin.

    DP World said this performance was driven by strong momentum across its ports and terminals and logistics business.

    The group’s gross throughput rose 5.8% to 93.4 million 20-foot equivalent units.

    Profit for the year increased 32.2% to $1.96bn, and operating cash flow grew 14% to $6.3bn.

    Return on capital employed increased to 9.9% in 2025, up from 8.9% in 2024, reflecting stronger earnings despite ongoing geopolitical and trade uncertainty.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16026660/main.png
    Yasir Iqbal
  • Egyptian firm starts building Sal’s Riyadh logistics centre

    18 March 2026

    Egyptian contractor Rowad Modern Engineering, a subsidiary of the Elsewedy Electric Group, has begun construction on the expansion of Saudi Logistics Services Company (Sal) facilities at King Khalid International airport in Riyadh.

    The scope of work includes the rehabilitation and upgrade of existing infrastructure, as well as the construction of new supporting facilities and services.

    Sal started the tendering process for its SR4.2bn ($1bn) logistics zone in the north of Riyadh in September last year, as MEED reported.

    UAE-based Global Engineering Consultants is the project consultant.

    The logistics hub aims to meet the demand for customised warehouses located near King Khalid International airport and the Riyadh Metro.

    The project is in line with Vision 2030 and the National Transport & Logistics Strategy, which aims to support the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.

    Sal and Sela signed an agreement to develop the project in March last year.

    This was followed by another lease agreement for the project, which will span about 1.57 million square metres. 

    According to an official statement: “The lease will extend for 30 years, which is further extendable to an additional 15 years upon agreement of both parties.”

    GlobalData expects the kingdom’s construction industry to record an annual average growth rate of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure projects, as well as the $850bn-plus gigaprojects programme.

    Growth will also be supported by government investments in rail, dams, industrial and road infrastructure projects. 

    The industrial sector is estimated to grow by 3.3% in 2025-28, supported by investments in the development of manufacturing, logistics, chemicals and pharmaceuticals plants.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16026154/main.gif
    Yasir Iqbal
  • Jabal Omar plans next phase of its Mecca development

    18 March 2026

    Saudi Arabian developer Jabal Omar Development Company is carrying out planning for phase seven of its Jabal Omar master development in Mecca, according to a fourth-quarter 2025 financial presentation.

    The company said phase seven will be a mixed-use scheme comprising hotels, retail and residential components, but did not disclose a breakdown of the project elements.

    Jabal Omar plans to use a development partnership model for the phase to minimise capital expenditure.

    Separately, the developer said it is targeting the delivery of 1,346 hotel keys and more than 20,000 square metres of gross leasing area in phase four by 2027.

    Rotana Jabal Omar Makkah, comprising 655 keys, is due to be fully operational in the first quarter of 2026, after 450 keys began operating in the final week of December 2025.

    The 1,141-key Sofitel is scheduled to become operational in the fourth quarter of 2026, while the 20,000 square metres of gross leasable area is expected to be ready in 2027.

    Jabal Omar estimates its 2026 capital expenditure at SR1.1bn ($293m), with spending expected to fall once the phase four hotels are completed.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16026145/main.png
    Yasir Iqbal