Manama jumpstarts utility sector

4 November 2024

 

On 21 October, Bahrain’s Electricity & Water Authority (EWA) held a market-sounding event in Manama to gauge investor interest in its two upcoming utility public-private partnership (PPP) schemes, the Sitra independent water and power project (IWPP) and the Al-Hidd independent water project (IWP).

The event did not disappoint, attracting 60 representatives from regional and international utility developers and contracting firms such as France’s Engie, Japan’s Mitsui and Saudi Arabia’s Acwa Power, among others. The EWA is expected to launch the prequalification process for both projects imminently.

The Sitra IWPP replaces the previously planned Al-Dur 3, which was in the early planning phases following the completion in 2021 of Al-Dur 2.

The planned Sitra IWPP is a combined-cycle gas turbine (CCGT) plant, which is expected to have a production capacity of about 1,200MW of electricity. The project's seawater reverse osmosis (SWRO) desalination unit will have a production capacity of 30 million imperial gallons a day (MIGD) of potable water. It is expected to reach commercial operations in 2029.

The Al-Hidd IWP is Bahrain’s first independent, standalone SWRO plant. It is expected to have a production capacity of about 60MIGD of potable water and be completed in 2028.

The imminent launch of the two projects boosts Bahrain’s lean projects pipeline, which has experienced muted growth in the aftermath of the Covid-19 pandemic and the completion of the Al-Dur 2 IWPP, which delivered 1,500MW of gas-fired generation capacity and 227,000 cubic metres a day (cm/d) of desalination capacity.

MEED understands that both the Sitra and Al-Hidd plants are being procured to cater for a combination of demand growth and some replacement capacity with more efficient and sustainable technology.

Commenting on the Al-Hidd IWP, Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting, says that it will be interesting to see what the tariff comes in at for a desalination plant of its size, and how many bids are received.

“Traditionally, Bahrain has done combined power and water plants, but given the inroads reverse osmosis (RO) technology  has made over the years, it does make sense to plan them as separate plants,” says Bryniak. “Capacity-wise, the Al-Hidd IWP can be considered a mid-size plant in the region these days, although at around 270,000 cm/d, this is a large RO plant for Bahrain.”

A different set of factors will be at play for the Sidra IWPP, however.

For one, it is likely to be the last IWPP for Bahrain, which aims to reach net-zero carbon emissions by 2060.

According to a source familiar with utility projects in the country, the EWA is planning for future capacity to be sourced from renewables despite Bahrain's space and land constraints, which have hampered the execution of at least one solar photovoltaic (PV) independent power project (IPP) in the past.

The source says that Bahrain could also consider other options to decarbonise its electricity systems, such as by developing offshore wind or importing clean energy – Bahrain, after all, has consistently secured electricity from the GCC grid – to supplement its available capacity and meet future demand.

Solar PV projects

The EWA awarded its first utility-scale solar PV IPP to a team comprising Acwa Power and Mitsui in 2019. However, the 100MW Askar solar PV was subsequently put on hold, with the utility issuing a new design-and-build tender for a similar-sized project in February this year.

China's TBEA Xinjiang Sunoasis Company is the sole bidder for the contract, offering to build the 90MW-100MW solar PV farm for BD27.6m ($73.4m).

In 2018, Bahrain's Electricity & Water Affairs Ministry awarded Deft Contractors a contract to build, own, operate and maintain grid-tied solar PV power panels with a minimum capacity of 72MW in Sakhir in the south of the country.

The power plant will be located at several premises, including­ at Bahrain International Circuit, the University of Bahrain, Bahrain International Exhibition & Convention Centre and Al-Dana Amphitheatre.

The solar panels are to be built on the rooftops, car park shades, electric vehicle (EV) charging stations and grounds of these organisations’ facilities, a measure that directly addresses the country’s space and land constraints.

The 20-year power-purchase agreement for the project was signed in August last year, at which time Electricity & Water Affairs Minister Yasser Bin Ebrahim Humaidan said that project is in line with Bahrain’s broader vision to adopt a circular carbon economy, with the aim of bringing carbon emissions to net zero by 2060.

Water and waste

Bahrain’s Works, Municipalities Affairs & Urban Planning Ministry is the other client for the island-state's power and water infrastructure-related projects.

It launched the prequalification process in 2022 for a project to develop an integrated waste PPP project, which is understood to include a waste-to energy (WTE) plant.

The WTE plant’s intended outputs are electricity, fed into the national grid through a power-purchase agreement; incinerator bottom ash and flue gas; and recyclable materials

However, no further developments on the project have been forthcoming since early 2023, when the ministry prequalified several consortiums to bid for the contract.

The construction of new power and water desalination plants in Bahrain will likely require the building of new power stations. Nine such schemes are in the planning stage, according to data from regional projects tracker MEED Projects.

As of November, bids are under evaluation for a contract to build two water distribution stations, one in Al-Hunayniyah and the other in South Saar. The bidders for the estimated $100m contract include the local Mohammed Abdulmohsin Al-Kharafi & Sons, Ahmed Mansoor Al-Aali and Panorama Contracting, as well as the UAE-based Tecton Engineering.

The scope covers the construction of two ground storage tanks, each with a capacity of 10 million gallons; two pump stations; and elevated storage reservoirs, in addition to the distributions stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12832025/main.jpg
Jennifer Aguinaldo
Related Articles
  • UAE firm acquires majority stake in African power producer

    31 August 2026

    Abu Dhabi-based ePointZero has announced a deal to acquire a 90% stake in pan-African independent power producer Azura Power Holdings.

    The transaction will give the subsidiary of UAE investment group 2PointZero control of 752MW of operating power generation capacity across Nigeria, Senegal and Mozambique.

    The company will acquire the respective stakes held by existing shareholders Actis and Africa50 through an acquisition vehicle established with Amaya Capital, an Africa-focused investment firm based in London.

    Amaya Capital founded Azuro Power in 2010 and will retain a 10% minority stake in the company, which also has a development pipeline of more than 1.5GW of planned power projects.

    The pipeline includes expansions at existing sites, as well as new gas and renewable energy projects and battery energy storage systems.

    Azuro Power’s operating portfolio comprises the 461MW Azura-Edo power plant in Nigeria, the 116MW Tobene power plant in Senegal and the 175MW Central Termica de Ressano Garcia plant in Mozambique. The company’s operating assets generate around 10% of each country’s grid baseload power, the statement said.

    The company’s projects have received financing and support from development finance institutions including the World Bank, British International Investment, German Investment & Development Company, the US International Development Finance Corporation, the Dutch entrepreneurial development bank, the International Finance Corporation, the Multilateral Investment Guarantee Agency and France’s Proparco.

    The deal, subject to regulatory approvals and other customary closing conditions, marks ePointZero’s entry into African power generation and follows the acquisition of a 20% stake in Egypt’s Elsewedy Electric in 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19171095/main.jpg
    Mark Dowdall
  • Contract award nears for Saudi Landbridge Riyadh section

    31 August 2026

     

    Saudi Arabia Railways (SAR) is preparing to award the main construction contract for the design-and-build of the Riyadh Rail Link, a new north-to-south railway line across the capital.

    MEED understands that the commercial proposals were opened two weeks ago, with a decision expected imminently.

    SAR began the post-tender clarifications with bidders in July, as MEED reported.

    The bidders include:

    • China Civil Engineering Construction Corporation / Al-Ayuni Investment & Contracting (China/local)
    • Nesma & Partners / China Harbour Engineering Company (local/China)
    • Al-Rashid Trading & Contracting / IC Ictas Construction / Saipem (local/Turkiye/Spain)
    • Saudi Binladin Group (local)

    In June, MEED exclusively reported that contractors submitted their commercial proposals on the 30th of that month.

    The scope includes a 35-kilometre double-track line connecting SAR’s North-South Railway to the Eastern Railway network.

    Issued on 29 January, the tender also covers the procurement, construction and installation of associated infrastructure, including viaducts, civil works, utility diversions/installations, signalling systems and other related works.

    Once delivered, the Riyadh Rail Link is expected to become a key component of the Saudi Landbridge railway.

    In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and that the project would instead be delivered in several phases under a different procurement model.

    Negotiations have been under way between Saudi Arabia and China-backed investors interested in developing the scheme through a public-private partnership (PPP). Al-Malik put the project cost at about SR100bn ($26.6bn).

    Overall, it comprises more than 1,500km of new track. A core element is a 900km railway between Riyadh and Jeddah, providing the capital with direct freight access to King Abdullah Port on the Red Sea.

    Other key elements include upgrading the existing Riyadh-Dammam line, a bypass around the capital known as the Riyadh Link, and a connection between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. First announced in 2004, it was put on hold in 2010 before being revived a year later. Rights-of-way issues, route alignment and the high cost have been among the main stumbling blocks.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19161887/main.gif
    Yasir Iqbal
  • Prequalification begins for Dammam suburb boulevard PPP

    31 August 2026

    Saudi Arabia’s Ministry of Municipalities & Housing, in collaboration with Ashraq Development Company and the National Centre for Privatisation & PPP, has issued a request for qualification (RFQ) notice for the development of the King Fahd suburb boulevard project in Dammam.

    The notice was issued on 27 August, with a submission deadline of 22 October.

    The public-private partnership (PPP) project will be delivered using a design, build, finance, operate, maintain and transfer model, with a 43-year contract term.

    The project is located in Al-Bayda Governorate and features a 4 kilometre (km) mixed-use zone along a central boulevard, forming part of a larger 7.3km corridor.

    The project will be developed in two phases and span about 1 million square metres.

    According to a statement: “The private sector partner will be responsible for developing and operating the boulevard, which includes leisure and recreational facilities, public parks, entertainment venues, retail outlets, office spaces, hospitality zones, pedestrian walkways and road networks.”

    The project is the latest addition to the growing number of PPP projects in the kingdom. 

    In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.

    Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.

    In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19160560/main.jpg
    Yasir Iqbal
  • Contractors submit bids for Kuwait power transmission works

    31 August 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has received bids for two tenders covering power transmission works at the South Saad Al-Abdullah residential development.

    The first tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the third phase of the development. 

    According to sources, five contractors submitted bids on 26 August. The local Sayed Hamid Behbehani & Sons made the lowest offer of $104.2m.

    The bids include:

    • Sayed Hamid Behbehani & Sons: $104.2m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.5m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    The second PAHW tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the fourth phase of the project. 

    According to sources, five contractors also submitted bids on 26 August, with A-Ahleia Switchgear making the lowest offer of $103.3m.

    The bids include:

    • Al-Ahleia Switchgear: $103.3m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.7m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118.3m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    Both projects were initially tendered in May. As reported by MEED, PAHW previously issued addendums for both substation tenders, revising the qualification requirements for bidders.

    According to the revised requirements, contractors must be approved by Kuwait’s Ministry of Electricity, Water & Renewable Energy and have experience supplying and installing at least 10 132kV substations in Kuwait.

    The addendums also introduced requirements related to transformer and gas-insulated switchgear manufacturing approvals, as well as operational performance records for installed equipment.

    Sabah Al-Ahmad residential city

    Meanwhile, bids remain under evaluation for two 132kV underground cable tenders for the South Sabah Al-Ahmad residential development, tendered by PAHW in May.

    The first cable tender covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts in the project’s fourth phase. 

    MEED previously reported that Egytech Cables, a subsidiary of Egypt’s Elsewedy Electric, was the lowest bidder with an offer of $42.37m.

    The second cable tender covers the supply, extension and maintenance of 132kV underground cables linked to substations serving the N5, N6, N8 and N10 districts in the project’s third phase. 

    Egytech Cables submitted the lowest offer of $39.95m. TBEA Shandong Luneng Taishan Cable submitted a bid of $41.89m, along with Riyadh Cables ($42.05m) and The Contractor General Trading & Contracting ($44.97m).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19151780/main.jpg
    Mark Dowdall
  • Eni plans to drill 230 oil and gas wells in Egypt

    31 August 2026

    Italy’s Eni is planning to drill 230 new oil and gas wells in Egypt, according to a statement from the country’s Ministry of Petroleum & Mineral Resources.

    Eni’s chief executive, Claudio Descalzi, discussed his plans for exploration and development in Egypt on 25 August during a meeting with Egypt’s Prime Minister Mostafa Madbouly and the Minister of Petroleum and Mineral Resources Karim Badawi.

    During the meeting, Descalzi said that the company has plans to drill 30 exploration wells in addition to 200 development wells.

    Descalzi said his company plans to intensify its exploration and development programmes, especially in the Mediterranean and Western Sahara regions, to increase production of natural gas and crude oil.

    He said that his company plans to use the latest seismic imaging and artificial intelligence technologies as a key part of its exploration and development plans.

    In a separate statement, Eni also said that it is working with UK-headquartered BP and state-owned Egyptian General Petroleum Corporation (EGPC) to reach a final investment decision (FID) for a project to develop the major gas discovery of Denise West in Egypt’s Temsah concession.

    Eni made the discovery in February and says it holds about 2 trillion cubic feet of gas and 130,000 barrels of condensate.

    It is targeting first gas in less than two years and expects to reach FID “in the next few months”, according to its statement.

    Eni’s total investments in Egypt have reached a value of $8.5bn, according to the statement from Egypt’s Ministry of Petroleum & Mineral Resources.

    During the meeting on 25 August, Descalzi also stressed the importance of linking Cyprus’ Cronos gas field to Egyptian export infrastructure.

    In July, Eni reached the FID to develop the Cronos project in deep waters offshore Cyprus, targeting the first Cypriot gas to market in 2028.

    Production is expected to reach a plateau of 500 million standard cubic feet a day.

    In October last year, Egypt and Cyprus signed provisional agreements to connect Cyprus’ Cronos gas field to Egypt’s gas infrastructure.

    The agreements were signed by parties including Egypt’s Ministry of Petroleum and Mineral Resources, Eni, and the French oil and gas company TotalEnergies.

    Connecting the Cronos field to Egypt is expected to involve the tendering of a major subsea pipeline project.

    This will allow gas to be transported and processed in existing Zohr facilities in Egypt, then transferred and liquefied at the Damietta LNG plant for export as LNG to international markets, primarily Europe.

    At the meeting on 25 August, Descalzi said the planned project to connect the Cronos field to Egypt will be considered a model for regional cooperation in the gas sector and will enhance Egypt’s status as a regional gas hub.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19079059/main.jpg
    Wil Crisp