L&T wins massive QatarEnergy LNG gas project package

26 March 2025

 

Register for MEED’s 14-day trial access 

India’s Larsen & Toubro (L&T) has announced that QatarEnergy LNG has officially awarded its subsidiary, Larsen & Toubro Energy Hydrocarbon (LTEH), the main contract for the COMP4 package of the second phase of its North Field Production Sustainability (NFPS) project.

L&T described the contract as “ultra-mega”, a term it uses to denote values exceeding INR150bn ($1.75bn), adding that it is the single-largest contract it has ever won.

MEED recently reported that QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, had selected LTEH – through a letter of intent – for the engineering, procurement, construction and installation (EPCI) works on the NFPS COMP4 package, which is estimated to be valued between $4bn and $5bn.

L&T, in its statement on 26 March, said that the scope of work encompasses the engineering, procurement, fabrication, installation and commissioning of two offshore compression complexes, each comprising large offshore platforms with compression and power generation facilities, living quarters, flare platforms, interconnected bridges and other associated structures, to be located approximately 80 kilometres off the northeast coast of Qatar. 

Sources previously told MEED that the objective of the combined 4A and 4B package (COMP4), which is the fourth package of the second phase of the NFPS project, is the EPCI of two large gas compression systems that will be known as CP8S and CP4N, each weighing 25,000-35,000 tonnes. The contract scope also includes compression platforms, flare gas platforms and other associated structures.

The other contractors that bid for the package are understood to include Italian contractor Saipem and US-based McDermott International.

North Field Production Sustainability

QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme requires the state enterprise to pump large volumes of gas from the North Field offshore reserve to feed the three phases of the estimated $40bn-plus programme.

QatarEnergy has already invested billions of dollars in engineering, procurement and construction works on the two phases of the NFPS project, which aims to maintain steady gas feedstock for the North Field LNG expansion phases.

The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.

Saipem has secured work worth a total of $8.5bn on the second NFPS phase.

QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities. The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.

The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.

Following that, Saipem won combined packages COMP3A and COMP3B of the NFPS project’s second phase in September last year.

The scope of work on the combined packages encompasses the EPCI for six platforms, approximately 100km of corrosion-resistant alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

Separately, QatarEnergy LNG awarded McDermott the contract for the NFPS second phase package known as EPCI 1, or COMP1, in July 2023. The scope of work on the estimated $1bn-plus contract is to install a subsea gas pipeline network at the North Field gas development.

NFPS first phase

Saipem is also executing the EPCI works on the entire first phase of the NFPS project, which consists of two main packages.

Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.

QatarEnergy LNG, formerly Qatargas, awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.

Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.

The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.

In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.

QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.

Saipem’s scope of work on the package, which is known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.

Saipem performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.

ALSO READ: QatarEnergy LNG prepares to receive decarbonisation bids

https://image.digitalinsightresearch.in/uploads/NewsArticle/13560925/main5742.jpg
Indrajit Sen
Related Articles
  • Adnoc-Covestro deal decision due in May

    2 April 2025

    EU antitrust regulators are expected to decide by 12 May whether to clear or extend the review of Abu Dhabi National Oil Company's (Adnoc) €15.9bn ($17.1bn) takeover of German chemicals producer Covestro.

    The 27-country EU competition enforcer can either clear the deal with or without conditions, or open a four-month investigation after its preliminary review, a Reuters report said, citing a filing on the European Commission's website.

    It was reported in October last year that Adnoc International, the overseas business arm of Adnoc Group, had signed an investment agreement Covestro in which it made a takeover offer of €14.7bn.

    Adnoc International said at the time that it will launch a voluntary public takeover of €62 ($69) a share, which implies an equity value for Covestro of about €11.7bn and represents a premium of about 54% to Covestro’s closing price on 19 June, the day before the first media coverage regarding a potential transaction.

    Leverkusen-headquartered Covestro’s supervisory and management boards supported the takeover offer.

    In addition, Adnoc International will subscribe to a 10% non-preemptive capital increase of €1.17bn in Covestro at the closing of the transaction.

    The offer will be subject to a minimum acceptance level of 50% plus one share and customary closing conditions, including merger control, foreign investment control and EU foreign subsidies clearances, the companies said.

    The agreement between Adnoc International and Covestro, which runs until the end of 2028, contains several obligations on the part of the Abu Dhabi energy producer, including maintaining Covestro’s existing business activities, corporate governance and organisational business structure.

    Adnoc approached Covestro about a potential takeover in September 2023, but initial advances were rejected, leading the Abu Dhabi state enterprise to raise the value of its offer.

    Adnoc’s initial approaches included a takeover price of €55 and then €57 a share, Bloomberg News reported at the time.

    Covestro’s expertise lies in chemicals recycling, which is key for the future of the energy industry and a target area for Adnoc.

    Russia's invasion of Ukraine in 2022 slashed deliveries of natural gas to Germany, resulting in a crisis that gripped the German chemicals industry, which accounts for about 5% of the country’s GDP.

    Precedent

    In September, the European Commission approved the takeover of the telecommunications assets of Czech investment group PPF by UAE telecoms group e&.

    Sovereign wealth fund Emirates Investment Authority holds a 60% stake in e&. The commission's review concluded that the “subsidies received by e& did not lead to actual or potential negative effects on competition in the acquisition process”.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13602719/main.jpg
    Jennifer Aguinaldo
  • Edgnex acquires Nordic data centre developer

    2 April 2025

    Register for MEED’s 14-day trial access 

    Edgnex, a subsidiary of Dubai-based property developer Damac, has acquired Helsinki-headquartered data centre-focused real estate developer Hyperco as part of its European expansion strategy.

    Damac announced the acquisition on 31 March.

    Hyperco operates data centres in Finland and Sweden, "leveraging the region’s renewable energy sources, mature digital ecosystem and high connectivity", local media reports said.

    Hyperco's three co-founders and existing team will continue to lead operations through the next phase of growth, according to a statement by the company.

    Hussain Sajwani, founder of Damac Group, said his firm plans to "build a significant future capacity in the Nordics and establish a strong foothold in the market".

    Edgnex’s recent European activities include a €150m ($161.9m) joint venture in Greece with Public Power Corporation to develop a 12.5MW facility, expandable to 25MW, and a €400m commitment to build a 40MW data centre in Madrid, Spain.

    In January, Sajwani pledged $20bn to develop data centres in the US.

    Sajwani and then US President-Elect Donald Trump announced the plan on 7 January in Florida, a day after the US Congress certified Trump as the winner of the 2024 presidential election.

    The project’s initial phase covers establishing data centres in Texas, Arizona, Oklahoma, Louisiana, Ohio, Illinois, Michigan and Indiana.

    It was previously reported that the Dubai-based property developer plans to develop $1bn-worth of data centres in countries in Europe, Asia, Africa, the Middle East and the Commonwealth of Independent States.

    Edgnex is constructing two data centre facilities in Dammam and Riyadh in Saudi Arabia that will deliver 55MW in 2025. There are also plans for a data centre in Amman, Jordan, and another in Turkiye in partnership with Vodafone.

    In May, Damac announced its entry into the Indonesian market with plans to build a 15MW data centre in Jakarta. The first construction phase for the facility is scheduled to be completed in the fourth quarter of 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13602668/main1456.jpg
    Jennifer Aguinaldo
  • Developers prepare Saudi round six solar IPP bids

    2 April 2025

     

    Register for MEED’s 14-day trial access 

    Prequalified developers are forming teams to bid for the contracts to develop solar farms under the sixth round of Saudi Arabia's National Renewable Energy Programme (NREP).

    MEED understands that bids are due for the four solar photovoltaic (PV) independent power projects (IPPs) by 1 June.

    The four solar IPPs have a combined capacity of 3,000MW.

    A 1,400MW solar PV IPP will be located in Najran, while the smallest – the 400MW Al-Sufun solar IPP – will be in Hail.

    The 600MW Samtah and 600MW Al-Darb solar IPPs will be located in Jizan, a region that has been placed under security-related travel alerts by some countries and international firms.

    Most of the prequalified bidders participated in site visits, which Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), conducted in late January.

    SPPC prequalified 16 companies that can bid as managing and technical members for the solar PV contracts. These are:

    • Abu Dhabi Future Energy Company (Masdar, UAE) 
    • Alfanar Company (local)
    • EDF Renewables (France)
    • Kahrabel (Engie, France)
    • FAS Energy (local)
    • Jinko Power (Hong Kong)
    • Korea Electric Power Corporation (Kepco, South Korea)
    • Marubeni Corporation (Japan)
    • Nesma Renewable Energy (local)
    • SPIC Hunaghe Hydropower Development (China)
    • Sumitomo Corporation (Japan)
    • TotalEnergies Renewables (France)
    • AlJomaih Energy & Water (local)
    • Sembcorp Utilities (Singapore)
    • AlGihaz Holding Company (local)
    • Korea Western Power Company (Kowepo, South Korea)

    The following five companies have been prequalified to bid as managing partners:

    • Jera Nex (Japan)
    • Power Construction Corporation of China (PowerChina)
    • China Power Engineering Consulting Group International Engineering (China)
    • Posco International (South Korea)
    • Saudi Electricity Company (SEC, local)

    Round six of the NREP will have a total combined capacity of 4,500MW, including the 1,500MW Dawadmi wind farm, for which a separate set of bidders has been prequalified.

    SPPC issued the prequalification request for round six of the NREP in September last year and received statements of qualifications from interested developers and developer consortiums the following month.

    SPPC is responsible for the pre-development, tendering and subsequent offtaking of the energy from the projects.

    US/India-based Synergy Consulting is the client's financial adviser for the NREP sixth-round tender. Germany’s Fichtner Consulting and US-headquartered CMS are the technical and legal consultants, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13602412/main0154.jpg
    Jennifer Aguinaldo
  • Mitsubishi Power confirms Rumah 1 and Nairiyah 1 deal

    2 April 2025

    Register for MEED’s 14-day trial access 

    Mitsubishi Power, part of Japan’s Mitsubishi Heavy Industries, has confirmed it has received two orders to supply six M501JAC gas turbines for the Rumah 1 and Al-Nairiyah 1 power generation projects in Saudi Arabia.

    Rumah 1 is located in the Central Region in Riyadh and is part of the previously planned Riyadh Power Plant 15. Nairiyah 1 is located in the Eastern Region.

    The scope includes the supply of generators and auxiliary equipment, Mitsubishi Power said in a statement.

    MEED exclusively reported that the Japanese original equipment manufacturer had been selected to supply its gas turbines for the independent power project (IPP) in November last year.

    A consortium comprising the local Saudi Electricity Company (SEC) and Acwa Power and South Korea’s Korea Electric Power Corporation (Kepco) won the contract to develop the Rumah 1 and Al-Nairiyah 1 IPP the same month.

    The power plants will deliver a combined 3.6GW, accounting for nearly 2.5% of the national grid’s capacity.

    The M501JAC turbines will be assembled at Mitsubishi Power Saudi Arabia’s Dammam factory.

    The 17,730 square-metre facility also provides services for gas turbine components.

    According to Mitsubishi Power, the plant features "a majority of Saudi employees, in line with the firm’s Saudi National programme".

    China’s Sepco 3 and South Korea's Doosan Enerbility will undertake the engineering, procurement and construction (EPC) contract for the projects, as MEED reported.

    The SEC, Acwa Power and Kepco team offered a levelised electricity cost (LCOE) of $cents 4.5859 a kilowatt-hour ($c/kWh) for Rumah 1 and 4.6114 $c/kWh for Al-Nairiyah 1.

    Acwa Power said that the two IPPs will require a combined investment of approximately SR15bn ($4bn). The IPPs are expected to reach commercial operations in Q2 2028. 

    Saudi Power Procurement Company (SPPC) received bids for the contracts for four thermal IPPs – the other two being the similarly configured Rumah 2 and Al-Nairiyah 2 – in August last year.

    The four power generation facilities will be developed using a build, own and operate model over 25 years. 

    SPPC’s transaction advisory team for the Rumah 1 and 2 and Al-Nairiyah 1 and 2 IPP projects comprises US/India-based Synergy Consulting, Germany’s Fichtner and US-headquartered Baker McKenzie. 

    Photo credit: Mitsubishi Power (for illustrative purposes only)

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13599792/main4910.jpg
    Jennifer Aguinaldo
  • Iraq approves two major energy project contracts

    2 April 2025

    Register for MEED’s 14-day trial access 

    Iraq’s Council of Ministers has approved two major energy contracts that form part of the $10bn Gas Growth Integrated Project (GGIP), according to a statement from the prime minister’s office.

    French oil and gas company TotalEnergies and its partners are developing the GGIP.

    TotalEnergies is the main operator of the GGIP. Basra Oil Company (30%) and QatarEnergy (25%) are the other stakeholders.

    One of the two awarded contracts is focused on the development of the Ratawi gas field and the other is focused on the Common Seawater Supply Project (CSSP), which will transport seawater to oil fields for injection to increase production.

    The statement said that Iraq's Council of Ministers had approved the award of tender CSSP-ITT-06 from state-owned Basra Oil Company to China Petroleum Pipeline Engineering Corporation (CPP).

    The contract awarded to CPP is for the pipeline package, which involves the construction of a seawater pipeline.

    MEED reported that CPP was a frontrunner to win the pipeline package in May last year.

    CPP is a subsidiary of China National Petroleum Corporation and the primary builder of pipelines in its home country.

    The pipeline package is one of two major packages in the CSSP. The other major package focuses on developing a water processing facility.

    The pipeline contract awarded to CPP will be executed over 54 months, including 42 months for engineering, procurement and construction and 12 months for operation, maintenance and training.

    The second contract that has been approved is for a planned gas processing plant at the Ratawi gas processing complex project.

    The Ratawi field is also sometimes called the Artawi field.

    This contract has been awarded by Iraq’s state-owned South Gas Company to China Petroleum Engineering & Construction Corporation (CPECC).

    In January, MEED revealed that CPECC had emerged as the frontrunner to win the contract, which is estimated to be worth about $1.7bn.

    When commissioned, the planned facility is expected to process 300 million cubic feet a day of gas. Its capacity is expected to double when a second expansion phase becomes operational in the future.

    The Ratawi gas processing facility project aims to improve Iraq’s electricity supply by capturing gas that would have otherwise been flared at several oil fields, including:

    • Luhais
    • Majnoon
    • Ratawi
    • West Qurna 2
    • Tuba

    Large gas volumes are flared from these oil fields, causing significant environmental damage. Collecting and processing flared gas will generate increased hydrocarbons revenues and reduce ecological damage.

    The gas tapped and processed from the oil fields will then be used to supply power plants, helping to reduce Iraq’s power import bill.

    As well as supplying Iraq’s national gas network to generate electricity, the Ratawi gas processing complex will increase the production of gas products, including liquefied petroleum gas (LPG) and condensates.

    US-based consultant KBR has performed the front-end engineering and design work on the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13587414/main3428.jpg
    Wil Crisp